SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT

Similar documents
North Shore of Long Island, Feasibility Study

Town of Duck, North Carolina

Building Coastal Resiliency at Plymouth Long Beach

New Jersey Coastal Zone Overview. The New Jersey Beach Profile Network (NJBPN) 3 Dimensional Assessments. Quantifying Shoreline Migration

Saco River Maintenance Dredge PROJECT PLAN AND TIMELINE JUNE 15, 2017

Figure79. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 155

Inlet Management Study for Pass-A-Grille and Bunces Pass, Pinellas County, Florida

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby

4/20/17. #32 - Coastal Erosion Case Histories - Lake Michigan

OECS Regional Engineering Workshop September 29 October 3, 2014

ST. LUCIE COUNTY, FLORIDA

UPPER BEACH REPLENISHMENT PROJECT RELATED

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION

United States Department of the Interior

FINDING OF NO SIGNIFICANT IMPACT

US Beach Nourishment Experience:

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION AND FUNCTIONAL DESIGN OF COASTAL STRUCTURES

ST. JOSEPH PENINSULA, GULF COUNTY, FLORIDA Beach Re-Nourishment and Environmental Enhancement Project RECOMMENDATIONS

FINAL ENVIRONMENTAL IMPACT STATEMENT ON BROWARD COUNTY SHORE PROTECTION PROJECT SEGMENTS II AND III BROWARD COUNTY, FLORIDA

Town of Duck, North Carolina

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

CHAPTER 281 INFLUENCE OF NEARSHORE HARDBOTTOM ON REGIONAL SEDIMENT TRANSPORT

The 2017 Panama City Beaches Beach Interim Renourishment Project. Answers to Common Questions

Tanya M. Beck. Kelly Legault. Research Physical Scientist Coastal & Hydraulics Lab, ERDC Vicksburg, MS

Beach Renourishment in Jacksonville

RE: Hurricane Matthew Beach Damage Assessment and Recommendations [CSE 2416]

KEYNOTE PRESENTATION FSBPA olsen

Protecting our Beaches

Mouth of the Columbia River Jetties Three-Phase Construction Plan

23- Year Sand Volume Changes at Site 132, 15th Street, Brigantine

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

Absecon Island Shore Protection The planning behind the project

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

DRAFT. October 17, 2014 File No Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA.

Chronic coastal erosion is a statewide problem

Assateague Island National Seashore North End Restoration Project Timeline

SELECTION OF THE PREFERRED MANAGEMENT OPTION FOR STOCKTON BEACH APPLICATION OF 2D COASTAL PROCESSES MODELLING

New Jersey Beach Profile Network Atlantic County Profile Site Locations

VENICE LOCAL COASTAL PROGRAM UPDATE: COASTAL HAZARDS WELCOME

ADAPTATION TO SEA LEVEL RISE AND COASTAL IMPACTS

North Half Moon Bay Shoreline Improvement Project, Pillar Point Harbor, CA Coastal Engineering Appendix

MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP)

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

CORPS FACTS. Harbor Dredging U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG

Impact of Hurricane Matthew on the Atlantic Coast of Florida

Nome Harbor Page 2 of 12

ATLANTIC COUNTY 2006 to 2008

SPECIAL SPRING 2018 STORM REPORT ON THE CONDITION OF THE MUNICIPAL BEACHES FOR THE BOROUGH OF STONE HARBOR, CAPE MAY COUNTY, NEW JERSEY

CHAPTER 8 ASSESSMENT OF COASTAL VULNERABILITY INDEX

FEMA Region V. Great Lakes Coastal Flood Study. Pilot Study Webinar. Berrien County, Michigan. February 26, 2014

County of Santa Barbara Permit Option Analysis Goleta Beach JULY 13, 2017

DELAWARE S VULNERABLE COASTAL AREAS. DELAWARE INLAND BAYS and DELAWARE BAY RECONNAISSANCE STUDY

Beach Restoration in Okaloosa and Walton Counties. FSBPA Technology Conference Clearwater, FL

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California

Guidelines for Providing Access to Public Transportation Stations APPENDIX C TRANSIT STATION ACCESS PLANNING TOOL INSTRUCTIONS

Climate Change Impacts to KSC Launch Complex

Louisiana CPRA SJB Group, Baton Rouge Coastal Engineering Consultants U.S. Army Corps of Engineers Federal and State PDT Members

Building Beaches with Navigation Sand, Just Don t Forget the Dunes!!

4/20/17. #31 - Coastal Erosion. Coastal Erosion - Overview

HARBOR INFRASTRUCTURE INVENTORIES Marquette Harbor, Michigan

Salt Ponds Shore Zone Modeling for Breakwater Placement: Summary Report

Redondo Beach Boat Launch Ramp Facility

April 7, Prepared for: The Caribbean Disaster Emergency Response Agency Prepared by: CEAC Solutions Co. Ltd.

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE 8-FOOT CHANNEL OF THE FEDERAL NAVIGATION PROJECT IN KENNEBUNK RIVER KENNEBUNK & KENNEBUNKPORT, ME

Figure 262. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 279

Beach profile surveys and morphological change, Otago Harbour entrance to Karitane May 2014 to June 2015

Notes to Benefit-Cost Analysis

Recycling of Surplus Sand to Extend the Time Between Beach Fill Episodes

Chapter 4 EM THE COASTAL ENGINEERING MANUAL (Part I) 1 August 2008 (Change 2) Table of Contents. Page. I-4-1. Background...

Trusted Partners Delivering Value, Today and Tomorrow BUILDING STRONG

Sussex County, DE Preliminary Study Overview

PUBLIC EXHIBITION OF COASTAL ZONE MANAGEMENT PLAN FOR COLLAROY-NARRABEEN BEACH AND FISHERMANS BEACH

Trends in Shoreline Change and Hazard Impacts: Hot Spots and Management Challenges. Greg Berman CAPE COASTAL CONFERENCE.

APPENDIX D-2. Sea Level Rise Technical Memo

LOCAL COASTAL PROGRAM UPDATE

Bay County, MI Coastal Hazard Analysis Flood Risk Review Meeting. May 14, 2018

Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA

David Revell, PhD And others. CSBPA Coastal Conditions 2018 Bodega Bay, CA

Future Global Trade Trends - Risks & Opportunities. Pulse of the Ports: Peak Season Forecast March 21, 2013

PNWA Conference Update

U.S. Army Engineer Institute for Water Resources

A REVIEW OF THE CONDITION OF THE MUNICIPAL BEACHES AS A RESULT OF HURRICANE SANDY IN THE BOROUGH OF STONE HARBOR, CAPE MAY COUNTY, NEW JERSEY

Performance of Upham Beach T-Groin Project and Its Impact to the Downdrift Beach

Nearshore Dredged Material Placement Pilot Study at Noyo Harbor, CA

Beach Nourishment Impact on Beach Safety and Surfing in the North Reach of Brevard County, Florida

Llandudno Beach Management Plan and Options Appraisal

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

The History of Coastal Flood Hazard Assessments in the Great Lakes

Southwest Washington Littoral Drift Restoration Project: Design, Construction, and Monitoring

SURGE SUPPRESSION ACHIEVED BY DIFFERENT COASTAL SPINE (IKE DIKE) ALIGNMENTS. Bruce A. Ebersole, Thomas W. Richardson and Robert W.

Modeling Sediment Transport Along the Upper Texas Coast

Appendix F: Public Access Plan

July 14, The Beaches Conference Greg Berman (WHOI Sea Grant & Cape Cod Cooperative Extension)

Leaning Into Adaptation

CORPS ON THE COAST. North Carolina Coastal Conference Coastal Infrastructure Raleigh, NC April 14, Jim Medlock Chief, Programs Management Branch

Sport Fishing Expenditures and Economic Impacts on Public Lands in Oregon

City of Del Mar Local Coastal Plan (LCP) Amendment for Sea Level Rise and Coastal Flooding

Water Resources Report RKLD Annual Meeting July 30, 2016

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update

Coastal Inundation. An Overview for TCDC

Transcription:

SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT Department of the Army New England District, Corps of Engineers 696 Virginia Road Concord, MA 01742-2751 October 2012

Introduction The purpose of this analysis is to identify and evaluate alternatives for halting further beach erosion losses and associated damage caused by an existing Corps jetty in the Camp Ellis section of Saco, Maine. The report includes a description of the study area and a quantitative assessment of benefits and costs for each alternative. Benefits are derived from reduction of property losses due to future shoreline retreat in the without-project condition. The without-project condition for this study is defined as the condition as it currently exists with the original Corps jetty in place. An In-Progress Review (IPR) Conference was convened in March 2010 to discuss the scope of work for the decision document and the process requirements for planning and review policies. The IPR Conference Planning Guidance Memorandum, dated 15 September 2010, clarified guidance for the study and stated that Per the vertical team conference call on 29 March and IPR on 30 March 2010, it was determined that the project justification (recommended alternative) for this study will be based upon the least costly, technically feasible, and environmentally acceptable alternative. This analysis is performed per the Camp Ellis Implementation Guidance issued 28 June 2010, the IPR Conference Planning Guidance Memorandum dated 15 September 2010, and US Army Corps of Engineers (Corps) guidance outlined in ER 1105-2-100 Appendix F, Section 111, River and Harbor Act of 1968, as amended - Shore Damage Prevention or Mitigation Caused by Federal Navigation Projects (22 April 2000). Future shoreline retreat is estimated under three Sea Level Rise (SLR) scenarios as defined in Corps Engineering Circular (EC) 1165-2-211 (01 July 2009). The without-project condition is evaluated for each of the three SLR scenarios. Benefits and costs are converted to average annual equivalent terms using the Fiscal Year 2013 Federal interest rate for water resources projects of 3 3/4 percent (3.75%) and a period of analysis of 50 years. Economic Setting The city of Saco is located in York County, Maine on the southwestern coastline. US Census data for 2000 (latest year available), show a population of 16,822 with approximately 8,200 housing units. Five-year estimates between 2005 and 2009 show a labor force of 10,250, of which 338 or 3.3% are unemployed. The largest employment sectors were in service industries for education, health care and social assistance which had 25.8 % of employment, followed by 12.6% in retail trade and 10.9% in manufacturing. Median household income for 2009 was $54,175. F-1

Study Area Camp Ellis Beach is located in Saco, Maine, about 16 miles south of Portland, Maine. The Saco River Federal Navigation Project consists of an 8-foot deep channel, 100 to 200 feet wide. The channel is protected to the south by a 4,800-foot long jetty and to the north by a 6,600-foot long jetty. The north jetty at the mouth of the Saco River separates the river from Camp Ellis Beach to the north. Camp Ellis Beach lies adjacent to the north jetty and extends 2,500 feet north to Ferry Beach. The project was authorized and constructed by the Corps in several increments between 1828 and 1968. During the last modification in 1968, the shoreward end of the north jetty was adjusted to reduce the maintenance dredging frequency in the river channel. The beach north of the jetty has experienced severe erosion over the past several decades with losses of property, roadways, and public and private infrastructure. The study area is defined as the stretch of shoreline in Camp Ellis extending 2500 feet from the northern jetty and extending inland from the shore for a distance delineated by the three SLR scenarios. The study area is divided into two reaches. Reach 1 has experienced the most severe and damaging erosion at current historic rates of 3 feet per year. The area stretches from the jetty to 1500 feet north of the jetty and includes the shoreline areas of Bay, Beach, Pearl, Eastern, North, Main and Riverside Avenues, Island View Street, Fore Street and Lower Beach Road. Reach 2 is the area from 1500 to 2500 feet north of the jetty and has experienced erosion at a slower historic rate of approximately 2 feet per year. Reach 2 includes the shoreline areas of Sunset, Sunrise, Beacon, Fairhaven and Eagle Avenues. Without Project Condition Sea Level Rise The without project condition is an estimate of losses likely to happen in the study area if no federal mitigation project is constructed and erosion is allowed to continue unabated. Current Corps guidance outlined in EC 1165-2-211 (1 July 2009) further requires the without-project analysis to consider a range of future sea level rise (SLR) at the project area. The range consists of a low rate based on historic change at the project area, and an intermediate and high rate based on curves for local mean sea level change published by the National Resource Council. As SLR increases, the rate of erosion will increase causing the amount of property losses and damages to increase. The withoutproject condition will be evaluated for each of the three SLR scenarios. The three rates of SLR and subsequent erosion rates determined by coastal engineering are presented below in Table 1. The historic rate of SLR exists as a component of the current erosion rates. The rise in water surface elevation of only 0.3 feet over the 50-year project life contributes erosion of 0.56 feet per year already included in the historic erosion rates. Over the 50-year life of the project, the historic erosion rate will cause a shoreline retreat F-2

of approximately 150 feet (50 years x 3 feet/yr) in Area 1 and 100 feet (50 years x 2 feet/yr) in Area 2. Additional erosion of 2.24 feet per year is estimated to occur in the intermediate SLR scenario based on an addition of 1.5 feet of vertical rise in the water surface elevation over the 50 year project life. Shoreline in the intermediate SLR scenario will move inland an additional 112 feet beyond the historic shore retreat line. For the high SLR scenario, additional erosion of 3.54 feet per year is estimated to occur based on an addition of 2.2 feet of vertical rise in the water surface elevation over the 50 year project life. Shoreline retreat in the Intermediate SLR scenario will move inland an additional 177 feet from the historic shore retreat line. A map indicating the shoreline retreat for each SLR scenario is available as Attachment 1 at the end of this appendix. For a more detailed analysis of sea level change and associated risk and uncertainty, please see Appendix C - Coastal Engineering. Table 1 Rate of Sea Level Rise and Erosion at Camp Ellis Beach HISTORIC INTERMED. HIGH SLR Vertical feet per 50 yrs 0.3 1.5 2.2 Additional Erosion - feet/yr 0.56 2.24 3.54 Shoreline Retreat - feet per 50 yrs 28 112 177 Area 1 Erosion Rate - feet/yr 3 5.24 6.54 Distance of Shoreline Retreat - feet 150 262 327 Area 2 Erosion Rate - feet/yr 2 4.24 5.54 Distance of Shoreline Retreat - feet 100 212 277 Value of Property Values for the land and structures in the study area were obtained from the most current tax assessments available from the City of Saco, dated July 31, 2010. The assessed values were used as the basis of valuing the land and properties projected to be lost to erosion. According to the city assessor, the assessed values represent 100 percent of current market value. Current Corps guidance (ER 1105-2-100 3-4) requires shorefront land to be valued as near shore land for economic evaluation purposes. An analysis was done comparing the average square foot value of land on shoreline lots to the average square foot value of land two and three lots back from the shoreline. On average it was found that the land of near shore lots was valued at approximately two-thirds of the land of the shore line lots. For this analysis, the market value of shore line lots was multiplied by 0.67 to reflect near shore, not shore line, land values. F-3

Projected Property Losses Historic Sea Level Rise Based on historic erosion rates, future losses of land and structures in the without-project condition were predicted for the historic SLR scenario. Using Computer Aided Design (CAD) and Geographic Information Systems (GIS) technologies, the project area was overlaid on a current City of Saco Assessor s Map, the existing shoreline and the 50-year retreat line were drawn in. The shore retreat distance was sectioned into 10-year bands and properties to be lost to erosion were identified and grouped within 10 year intervals. As displayed in Table 2 below, a total of 62 lots with 59 structures are projected to be lost over the next 50 years, with a current market value total of $20,774,500. Table 2 Market Value of Projected Property Losses Erosion Rates based on Historic SLR TIME INTERVAL NUMBER OF LOTS LOST MARKET VALUE OF LAND NUMBER OF STRUCTURES LOST MARKET VALUE OF STRUCTURES TOTAL LOSSES (ROUNDED) YEARS 1-10 28 $ 7,003,000 25 $ 3,122,900 $ 10,125,900 YEARS 11-20 7 1,304,700 7 1,549,500 2,854,200 YEARS 21-30 13 2,220,600 13 1,404,300 3,624,900 YEARS 31-40 10 2,170,300 10 997,900 3,168,200 YEARS 41-50 4 695,500 4 305,800 1,001,300 TOTAL 62 $ 13,394,100 59 $ 7,380,400 $ 20,774,500 Projected Property Losses Intermediate Sea Level Rise For the intermediate SLR scenario, the inland distance of the shore retreat line was increased by 112 Ft beyond the historic retreat line on the CAD map. The new retreat line showed 24 additional lots and 22 additional structures affected by accelerated erosion rates over the 50-year project life. The accelerated erosion rates were used to place each structure in the correct 10-year interval of erosion. Total market value of all losses in the intermediate SLR scenario amounts to $28,862,300 as presented in table 3 below. Table 3 Market Value of Projected Property Losses Erosion Rates based on Intermediate SLR TIME INTERVAL NUMBER OF LOTS LOST MARKET VALUE OF LAND NUMBER OF STRUCTURES LOST MARKET VALUE OF STRUCTURES TOTAL LOSSES (ROUNDED) YEARS 1-10 29 $ 7,298,100 27 $ 3,258,400 $10,556,500 YEARS 11-20 23 4,244,300 23 3,287,100 7,531,400 YEARS 21-30 10 1,851,600 9 834,900 2,686,500 YEARS 31-40 9 1,964,600 9 1,523,200 3,487,800 YEARS 41-50 15 2,625,500 13 1,974,600 4,600,100 TOTAL 86 $ 17,984,100 81 $ 10,878,200 $28,862,300 F-4

Projected Property Losses High Sea Level Rise For the high SLR scenario, the inland distance of the shore retreat line was increased by 177 Ft beyond the historic retreat line on the CAD map. In comparison to the intermediate SLR scenario, the new retreat line showed15 additional lots and 13 additional structures affected by accelerated erosion rates over the 50-year project life. Total market value of losses in the high SLR scenario amounts to $33,774,800 as presented in Table 4 below. Table 4 Market Value of Projected Property Losses Erosion Rates based on High SLR TIME INTERVAL NUMBER OF LOTS LOST MARKET VALUE OF LAND NUMBER OF STRUCTURES LOST MARKET VALUE OF STRUCTURES TOTAL LOSSES (ROUNDED) YEARS 1-10 38 $ 9,031,900 36 $ 5,387,000 $14,418,900 YEARS 11-20 21 3,903,000 21 1,744,000 5,647,000 YEARS 21-30 3 459,100 2 249,400 708,500 YEARS 31-40 11 2,301,900 10 1,592,800 3,894,700 YEARS 41-50 28 5,460,300 25 3,645,400 9,105,700 TOTAL 101 $ 21,156,200 94 $ 12,618,600 $33,774,800 Calculation of Benefits Prevention of Property Losses In order to compare project costs and benefits on an equivalent annual basis, projected losses for each 10-year period are converted to present value equivalents using the midpoint of each 10-year interval. Annual equivalent values are calculated using the capital recovery factor for 50 years at 3.75% percent. Annualized property losses for each SLR scenario are presented in Tables 5 through 7 below. Table 5 Annualized Value of Projected Property Losses Historic SLR Scenario TIME INTERVAL MIDPOINT YEAR MARKET VALUE OF PROPERTY PRESENT VALUE FACTOR CAPITAL RECOVERY FACTOR ANNUALIZED VALUE (Rounded) YEARS 1-10 5 $ 10,125,900 0.83188 0.04457 $ 375,500 YEARS 11-20 15 2,854,200 0.57568 0.04457 73,200 YEARS 21-30 25 3,624,900 0.39838 0.04457 64,400 YEARS 31-40 35 3,168,200 0.27569 0.04457 38,900 YEARS 41-50 45 1,001,300 0.19078 0.04457 8,500 TOTAL $ 20,774,500 $ 560,500 F-5

Table 6 Annualized Value of Projected Property Losses Intermediate SLR Scenario TIME INTERVAL MIDPOINT YEAR MARKET VALUE OF PROPERTY PRESENT VALUE FACTOR CAPITAL RECOVERY FACTOR ANNUALIZED VALUE (Rounded) YEARS 1-10 5 $ 10,556,500 0.83188 0.04457 $ 391,400 YEARS 11-20 15 7,531,400 0.57568 0.04457 193,300 YEARS 21-30 25 2,686,500 0.39838 0.04457 47,700 YEARS 31-40 35 3,487,800 0.27569 0.04457 42,900 YEARS 41-50 45 4,600,100 0.19078 0.04457 39,100 TOTAL $ 28,862,300 $ 714,400 Table 7 Annualized Value of Projected Property Losses High SLR Scenario TIME INTERVAL MIDPOINT YEAR MARKET VALUE OF PROPERTY PRESENT VALUE FACTOR CAPITAL RECOVERY FACTOR ANNUALIZED VALUE (Rounded) YEARS 1-10 5 $ 14,418,900 0.83188 0.04457 $ 534,700 YEARS 11-20 15 5,647,000 0.57568 0.04457 144,900 YEARS 21-30 25 708,500 0.39838 0.04457 12,600 YEARS 31-40 35 3,894,700 0.27569 0.04457 47,900 YEARS 41-50 45 9,105,700 0.19078 0.04457 77,400 TOTAL $ 33,774,800 $ 817,500 Prevention of Maintenance and Emergency Services The superintendent of Saco Public Works provided a detailed list of costs incurred between 1972 and 2010 for road repair, beach restoration, clean-up, and additional public works services for damages in the Camp Ellis area caused by the erosion problem. Costs were updated to 2011 values using the Construction Cost Index and Implicit Price Deflator. During this 38-year time period, there were 21 separate events costing more than $2.632 M (2011 dollars) for an average emergency repair cost of $125,300 per event. In some years there were several events and in other years there were no major storm events; yielding an average of 0.55 major storm events per year. On an annual basis, prevention of costs for beach restoration and infrastructure related emergency repairs were estimated at $69,300 under current conditions. Average annual repair costs for the intermediate and high SLR scenarios were estimated by applying EPA suggested percentage increases. Historic costs were increased by 36 % to derive intermediate costs caused by a 1.5 foot increase in SLR. Costs for the high SLR scenario were derived from increasing historic costs by 46% corresponding to a 2.2 foot increase in SLR. Annualized costs for the three SLR scenarios are presented below in Table 8. F-6

Table 8 Annualized Cost of Emergency Repairs HISTORIC INTERMED. HIGH Major Road Repairs $1,107,800 $1,506,600 $2,199,600 Seawall and Dune Repairs $211,000 $287,000 $419,000 General Emergency Repairs $1,313,000 $ 1,785,700 $2,607,100 Total Repairs $2,631,800 $3,579,300 $5,225,700 Number of Events 21 21 21 Average Cost per Event $125,324 $ 170,443 $48,843 Number of Events per Year 0.55 0.55 0.55 Average Annual Emergency Cost $ 69,258 $ 94,192 $ 137,518 Calculation of Costs Alternatives The recommended alternative for Camp Ellis will be based upon the least costly, technically feasible, and environmentally acceptable plan. Economic justification through a positive cost-benefit ratio is not required. The alternatives being considered for the Camp Ellis project are as follows: Beach nourishment only 750 feet spur jetty attached to existing north jetty plus beach nourishment (Alternative 6) 500 feet spur jetty with two nearshore segmented breakwaters plus beach nourishment (Alternative 25a ) Buy-out Plan Calculations for cost development and details of each alternative are contained in the main report and engineering appendices. Annualized first costs for comparison of alternatives are presented below. Project first costs include engineering and design costs, costs for preparation of plans and specifications, supervision and administration costs,, and real estate costs. Costs are projected over the 50-year period of analysis for each alternative under each of the three SLR scenarios. Beach Nourishment Only The Beach Nourishment Only alternative consists of placing sand fill along Camp Ellis Beach. Beach nourishment reduces shoreline erosion by providing sacrificial fill that erodes during storm events. The initial nourishment for the design beach profile consists of approximately 712,000 cubic yards of material placed along approximately 3,250 feet of shoreline with the southern end of the project located at the northern jetty. The changes in F-7

costs vary according to the volumes necessary for each subsequent fill required to maintain the design beach profile. The initial first cost for establishing the design beach profile is $14.437 M. Table 9 below presents the costs annualized for a 7-month construction period with re-nourishment every 10 years over the 50-year life of the project. Table 9 Annualized Cost of Beach Nourishment for SLR Scenarios Annualized Cost Calculation Historic Intermediate High Project First Cost $14,437,000 $14,437,000 $14,437,000 Interest During Construction $136,054 $136,054 $136,054 Total Investment Cost $14,573,054 $14,573,054 $14,573,054 Capital Recovery Factor (CRF) 0.04457 0.04457 0.04457 Average Annual Cost $649,600 $649,600 $649,600 Annual Re-nourishment Cost $817,300 $948,800 $1,025,900 Annual O&M Costs $15,000 $15,000 $15,000 Total Annual Cost of Beach Nourishment $1,481,900 $1,613,400 $1,690,500 Alternative 6 Spur Jetty and Beach Nourishment Alternative 6 consists of a 750-feet spur jetty located approximately 1,500 feet from the shoreline and attached to the existing northern jetty. This alternative also includes the placement of 365,000 cubic yards of beach fill along Camp Ellis Beach to stabilize the shoreline. The initial first cost for constructing the jetty is $23.835 M. Table 10 below presents the costs annualized for a 19-month construction period. Due to wave energy reductions provided by the spur jetty, the beach re-nourishment interval was increased to every 11.6 years over the 50-year life of the project. Table 10 Annualized Cost of Alt 6 Spur Jetty for SLR Scenarios Annualized Cost Calculation Historic Intermediate High Project First Cost $23,835,000 $23,835,000 $23,835,000 Interest During Construction $682,380 $682,380 $682,380 Total Investment Cost $24,517,380 $24,517,380 $24,517,380 Capital Recovery Factor (CRF) 0.04457 0.04457 0.04457 Average Annual Cost $1,092,800 $1,092,800 $1,092,800 Annual Re-nourishment Cost $202,800 $313,400 $377,500 Annual O&M Costs $30,000 $30,000 $30,000 Total Annual Cost of Alternatives $1,325,600 $1,436,200 $1,500,300 Alternative 25A Spur Jetty with Two Breakwaters and Beach Nourishment This alternative consists of a 500-ft. spur jetty located approximately 875 feet from shore, with two detached breakwater segments. This alternative also includes the placement of 328,000 cubic yards of beach fill along Camp Ellis Beach to stabilize the shoreline. The initial first cost for construction is $29.685 M. Table 11 below presents the costs F-8

annualized for a 19-month construction period. As the spur jetty and breakwaters reduce wave energy reaching the beach, re-nourishment intervals are extended to every 19 years over the 50-year life of the project. Table 11 Annualized Cost of Alt 25-A Spur Jetty with Breakwaters for SLR Scenarios Annualized Cost Calculation Historic Intermediate High Project First Cost $29,685,000 $29,685,000 $29,685,000 Interest During Construction $849,862 $849,862 $849,862 Total Investment Cost $30,534,862 $30,534,862 $30,534,862 Capital Recovery Factor (CRF) 0.04457 0.04457 0.04457 Average Annual Cost $1,361,100 $1,361,100 $1,361,100 Annual Re-nourishment Cost $103,100 $175,500 $218,300 Annual O&M Costs $45,000 $45,000 $45,000 Total Annual Cost of Alternatives $1,509,200 $1,581,600 $1,624,400 Real Estate Buy-Out Alternative This plan consists of the purchase of all property that will be subject to erosion over the next 50 years. Under this option, all improvements will be removed and the land returned to a natural state after the purchase. The total cost of the buy-out option and the total number of properties purchased under each SLR scenario are listed in Table 12 below. Table 12 Annualized Cost of Buy-Out Alternative Annualized Cost Calculation Historic Intermediate High Real Estate Acquisition Cost $38,220,000 $51,485,000 $59,480,000 Ownerships Acquired 62 86 101 Capital Recovery Factor (CRF) 0.04457 0.04457 0.04457 Average Annual Cost $1,703,600 $2,294,900 $2,651,300 Summary Table 13 below provides a comparison of all annualized costs for each alternative over the three SLR scenarios. Table 13 Comparison of all Annualized Costs Historic Intermediate High Beach Nourishment Only $1,481,900 $1,613,400 $1,690,500 Spur Jetty $1,325,600 $1,436,200 $1,500,300 Spur Jetty with Breakwaters $1,509,200 $1,581,600 $1,624,400 Real Estate Acquisition $1,703,600 $2,294,900 $2,651,300 F-9

Attachment 1 Camp Ellis Beach Projected Shoreline Retreat for Historic, Intermediate and High SLR over the 50-year project life F-10