Somerville Community Path Feasibility Study

Similar documents
section 4 Existing Conditions, Issues, and Options

RiNo Railroad Crossing Connectivity Analysis. Stakeholder Workshop June 29, 2017

TRANSPORTATION COMMISSION Agenda Staff Report

Golden s Plan. For the Highway 6 & 93 Corridor

PEDESTRIAN ACTION PLAN

Accommodating Pedestrians in the Work Zone

June 11, RE: Comments on the ENF for The Boston Garden project, MEPA # Dear Mr. Sullivan:

5. RUNNINGWAY GUIDELINES

ADA on Construction. Guidance for Section C Plan Preparers

DRAFT. A fifth objective, other considerations, has been added to capture considerations not captured by the four primary objectives.

Executive Summary Route 30 Corridor Master Plan

Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering. Minnesota Department of Transportation (the Department)

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses

Welcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study

3.9 Recreational Trails and Natural Areas

Construction Specifications Manual

Stakeholders Advisory Working Groups (SAWGs) Bridge and Bike / Pedestrian SAWG (#15)

Chapter 5 Future Transportation

Appendix C. Bicycle Route Signage

Duwamish Way-finding and CTR Report

Route 47 (North Main Street) Reconstruction

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY

Central Jersey Transportation Forum. March 2007

State Highway 16 Kuna-Mora Road to Ada/Gem County Line

NEWMARKET UPHAM S CORNER

State Highway 16/McDermott Road Kuna-Mora Road to Ada/Gem County Line

State Highway 16 Kuna-Mora Road to Ada/Gem County Line

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Environmental Assessment Findings & Recommendations. Public Hearing November 13, 2014

Off-Road Facilities Part 1: Shared Use Path Design

Alewife Bicycle and Pedestrian Access Study

City of Wilsonville 5 th Street to Kinsman Road Extension Project

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives

PEDESTRIAN FENCE TABLE OF CONTENTS CHAPTER 30

DRAFT. Table of Contents. Background

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

Moving Cambridge. City of Cambridge Transportation Master Plan Public Consultation Centre. March 7, :00 8:00 PM.

ADA TRANSITION PLAN 2013

Bicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1)

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

Fitting Light Rail through Well-established Communities

CURBSIDE ACTIVITY DESIGN

1. What is the Doran Street and Broadway/Brazil Grade Separation Project (Project)?

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

South King County High-Capacity Transit Corridor Study

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway

STUDY PROCESS & SCHEDULE

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Memorandum. Exhibit 60 SSDP To: Jenny Bailey, Senior Planner. From: Bill Schultheiss, P.E. (WA. P.E. #46108) Date: June 20, 2017

Pattullo Bridge Replacement Project Community Connections Phase 2 Consultation. Appendix 3: Open House Display Boards

TRANSBAY JOINT POWERS AUTHORITY

700 Multi-Modal Considerations

8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN

Thoreau Path Master Plan Final Draft. prepared for: The Boston Redevelopment Authority West End Community November 2007

Johnwoods Street Closure Summary Response

I-90 ALLSTON INTERCHANGE A MULTIMODAL TRANSPORTATION PROJECT MEPA CONSULTATION MEETING NOVEMBER 20, 2014 BRIGHTON HIGH SCHOOL

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia

YELLOWHEAD TRAIL / 149 STREET INTERCHANGE

Carbondale to Murphysboro Bike Route JACKSON COUNTY

PennDOT ICE Policy An Introduction

CHAPTER 1 INTRODUCTION

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018

SOLANA BEACH BICYCLE TRANSPORTATION PLAN SECOND ADDENDUM

Improvements Infrastructure Gap Assessment and Improvements Street Striping

Draft. Lecompton. Table of Contents. Background

Figure 1: East West Connector Alignment Alternatives Concept Drawing

FALL 2014 WORKSHOPS TAKEAWAYS

Roadway Design Manual

McGrath Boulevard Project Development Public Meeting #2 May 28 th, 2015 East Somerville Community School

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

Chapter 3 DESIGN SPECIFICATIONS

DESIGN MEMORANDUM WITH DESIGN EXCEPTIONS SP SP

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

WELCOME TO OPEN HOUSE # 1 June 14, 2017

TABLE OF CONTENTS. Executive Summary

EXHIBIT B-1 PROJECT DESCRIPTION. Phase 1 of the Preferred Alternative

Route 29 Solutions Projects

C C C

FY 2006 TRANSPORTATION CAPITAL PROGRAM

Comments EXECUTIVE SUMMARY

Design Criteria. Design Criteria

Blair/Williamson Intersection Expressed Needs

APPENDIX A. GIS ANALYSIS FOR THE MRT

RZC Appendix 8A Marymoor Subarea Street Requirements

Phone: Fax: Project Reference No. (to be filled out by MassHighway):

Active Transportation Rail to River Corridor. Community Meeting - Segment A

Owl Canyon Corridor Project Overview and Summary

Welcome! Fore River Bridge Reconstruction Project Quincy & Weymouth Project File No Public Information Meeting May 18, 2017

This page intentionally left blank.

Creating the Future Bruce B Downs Blvd

Modal Interrelationships: A bicycle lane is proposed between Harrington Ave and Swanns Station Rd.

Charles River Pathways

We support several of Regional Municipality of Durham Transportation Master Plan Directions such as

Maywood Town Hall Meeting. May 4, 2016

Transcription:

Somerville Community Path Feasibility Study Prepared for: City of Somerville, Massachusetts Strategic Planning and Community Development July 14, 2006 Prepared by: VOLLMER

Table of Contents Section 1.0 Study Summary...1-1 1.1 Overview of the Green Line Extension Project...1-1 1.2 Alternatives...1-2 1.3 Study Conclusions & Recommendations...1-2 Section 2.0 Study Introduction...2-1 2.1 Study Understanding...2-1 2.2 Study Location...2-1 2.3 Major Crossings...2-1 2.4 Pathway Segments...2-2 Section 3.0 Previous Reports and Studies...3-1 3.1 Somerville Community Path Feasibility Study...3-1 3.2 North Point Somerville Planning Study...3-2 3.3 North Point Development Proposal...3-2 3.4 Somerville Community Path: Cedar to Central...3-2 3.5 Inner Belt Park Access Alternatives Study...3-3 3.6 Green Line Extension: Beyond Lechmere - Northwest Corridor Study...3-4 3.7 Cross Street Bridge...3-4 Section 4.0 Existing Conditions, Issues, and Options...4-1 4.1 School Street...4-1 4.2 School Street to Medford Street - Segment 1...4-2 4.3 Medford Street...4-3 4.4 Medford Street to Walnut Street - Segment 2...4-4 4.5 Walnut Street...4-5 4.6 Walnut Street to McGrath Highway - Segment 3...4-6 4.7 McGrath Highway...4-7 4.8 McGrath Highway to Cross Street - Segment 4...4-8 4.9 Cross Street...4-9 4.10 Cross Street to Washington Street - Segment 5...4-10 4.11 Washington Street...4-11 4.12 Washington Street to Fitchburg Line - Segment 6...4-12 4.13 Fitchburg Line...4-13 4.14 Fitchburg Line to Cambridge Line - Segment 7...4-14 Section 5.0 Alternatives Analysis...5-1 5.1 Approach to Alternatives...5-1 5.2 Description of Alternatives...5-1 i

5.3 Alternatives Analysis...5-2 Section 6.0 Recommended Plan...6-1 6.1 Path Alignment...6-1 6.2 Construction Feasibility...6-7 6.3 Shared Benefits...6-7 6.4 Shared Costs...6-8 6.5 Green Line Stations...6-8 6.6 Community Access Points...6-8 6.7 Future Connections...6-8 Appendices Appendix A - Cost Estimates Appendix B - Typical Light Rail Station Appendix C - Typical Fencing Styles Appendix D - Articles Related to Green Line Extension ii

section 1 Study Summary

1.0 Study Summary This project examines the feasibility of constructing a proposed section of the Somerville Community Path along the Southern New Hampshire Main Line. This corridor currently serves active rail traffic that includes the MBTA Lowell Commuter Rail and Guilford freight operations. This study focuses on an extension of the existing Community Path running along the ROW from School Street to the Somerville/Cambridge line. Ultimately, this path is envisioned extending north from School Street to Central Street where the path departs the active ROW and connects with sections of the path that are either built or in the final stages of design. A future section of the proposed trail from School Street to Central Street is not included in this study (due to study funding limits) but is assumed to be along the western edge of the corridor at the top of the embankment. In the past, MBTA policy has been unfavorable to the construction of trails within or directly adjacent to active rail corridors (so called "rails-with-trails"). Recently however, the MBTA has shown a greater willingness to consider path construction where clear separation of pedestrian and rail is demonstrated. A relevant example is the proposed Cedar Street to Central Street segment of the Somerville Community Path, where grade separation of the path from the active right-of-way within the right-of-way is moving forward. While the initial premise was to construct the entire Community Path (form School Street to the Cambridge line) upon the right-of-way embankment, further analysis has shown that this is not entirely feasible. Therefore, in certain locations, the concepts consider alignments within portions of the active rail corridor. Where sections of the proposed path are conceptually shown to push within the active rail bed area, the final design should anticipate that the path would be elevated a minimum of 3'-4' in height above the track grade and should be provided with secure fencing or railing acceptable to the MBTA. This grade separation is intended to improve the safety of pedestrians as well as the quality and character of the path, without interference to rail operations. This study builds on the 2001 report, prepared by Rizzo Associates, that recommended an entirely off-road path using embankments along the corridor and relocation of an existing freight track. 1.1 Overview of the Green Line Extension Project The Green Line extension is one of several mitigation projects proposed by the State as part of the Big Dig environmental process. In 2004, the MBTA hired a planning team to study the feasibility of extending the Green Line from Cambridge into Somerville and Medford (See Appendix B for typical sections). This study indicates that this extension provides a number of benefits for the costs. Subsequently, in May of 2005, the State announced their intent to move forward with the project. This study finds that the Green Line extension Project provides a number of advantages that should facilitate development of the Community Path, and that the path provides benefits to the extension project as well. 1-1

1.2 Alternatives In light of MBTA policies related to trails near active Right-of-ways and the future Green Line, this study focused on three alternatives: Alternative 1: A trail utilizing embankments and inactive rail sections beyond Washington Street that avoids the development of any elaborate structures. Alternative 2: A trail utilizing embankments and inactive rail sections beyond Washington Street including a structure to bridge the gap between Cross Street and Washington Street. Alternative 3: A trail utilizing embankments and some portions of the active ROW after McGrath Highway (as proposed by Rizzo Associates). Based on an examination of the constraints, construction issues, estimated costs, and pending projects, the third alternative was further advanced and is provided in this study as the Recommended Plan. The proposed Green Line Project is moving forward and is slated to be built to the western side of the rail corridor. The westerly side is also the preferred location of the Community Path. Construction of the path adjacent to the light rail service is preferred over location next to the heavy rail operations. Extension of the Green Line will require relocation/removal of the freight track from Lowell Street to Washington Street. The onus of relocating the freight track is removed from the community path project. 1.3 Study Conclusions & Recommendations The Recommended Plan is provided in Chapter 6 of this study. Based on input from the City, advocate groups, and the MBTA; a number of conclusions can be drawn from this study. These include the following: According to the MBTA study, the bridges at Medford Street and School Street are substandard in width (to accommodate the Green Line) and will need to be rebuilt. Reconstruction of the Medford Street Bridge provides opportunity to run the path beneath Medford Street, thereby improving path alignment and avoiding crossing Medford Street where the vertical crest of the bridge makes sight lines poor. MBTA stations are under consideration at City Hall/Gilman Square and at Washington Street. These stations are slated for important points of arrival and destination that compliment the path. The rail bridge over the Fitchburg Line (former Red Bridge) has been removed. Installation of a new pedestrian structure will need to consider the MBTA's plan to elevate the Fitchburg Line to alleviate flooding issues. Further consideration of a possible Union Square extension of the Green Line will also need to be considered. Location of a new Light Rail storage yard is being considered at the Yard 8 location. 1-2

The rail yard operations south of the Fitchburg Line will be replaced by the North Point development. The North Point Development includes plans for a path that extends to the Charles River. The new Lechmere Station is an elevated station with tail tracks leading north out of the station. Extending this elevated structure north over the Fitchburg Line would allow the potential for the path to cross (west to east) under the Green Line to the North Point connection. This structure would also allow the development of a new connection into the Southern Inner Belt district, something recently explored by the City of Somerville. Construction of the path in conjunction with the Green Line improves construction access to the corridor and thereby feasibility of path construction. Creation of the path in conjunction with the Green Line extension provides greater access to the proposed MBTA stations. Location of the MBTA station at City Hall/Gilman Square may require relocation of the electrical sub-station. Final location should be based on costs of relocation and the need for maintenance access. The path is viewed as a means of both maintenance and emergency access to both the electrical sub-station as well as the MBTA station. The highest and best use of the embankment at Chester Street is for ramped connections to/from the McGrath Highway and Cross Street. Location of the Washington Street station (as shown on the Recommended Plan) on the south side of the bridge provides greater room for the station with fewer impacts to adjacent residences. This location also provides potential access to buses from Joy Street. This location will require some property taking. Location of the path along the westerly edge of Yard 8 should consider the active freight track as well as potential staging of Green Line cars. A path connection from the north side of Washington Street (behind Cataldo Ambulance) allows pedestrian access via the path to the proposed MBTA station, thereby alleviating the need to cross Washington Street at-grade. 1-3