Charlottesville Bike-Ped Steering Committee Meeting Notes 2/26/2015 Master Plan Update

Similar documents
City of Charlottesville Bicycle and Pedestrian Master Plan Update

TOWN OF PARADISE VALLEY

MASTER BICYCLE AND PEDESTRIAN PLAN

Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan. January 18, 2011

Arlington s Master Transportation Plan

GIS Based Non-Motorized Transportation Planning APA Ohio Statewide Planning Conference. GIS Assisted Non-Motorized Transportation Planning

GIS Based Data Collection / Network Planning On a City Scale. Healthy Communities Active Transportation Workshop, Cleveland, Ohio May 10, 2011

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN

CHAPTER 3: Vision Statement and Goals

Plant City Bicycle and Pedestrian Master Plan. Project Update March 2, 2017

Agency Advisory Group Meeting #3 and Walk Audit Anchorage Non-Motorized Plan

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses

EXECUTIVE SUMMARY. Vision

Urbana Pedestrian Master Plan

Roosevelt Estates Neighborhood Improvements

What Is a Complete Street?

Borough of Danville, PA Traffic Calming Program Guidelines

Public Information Centre

Moraga Pedestrian and Bicycle Master Plan Update and Wayfinding Plan. Citizens Advisory Committee Meeting July 21, 2015

Bicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution

Orinda Bicycle, Trails and Walkways Master Plan

City of Birmingham Draft Multi-modal Transportation Plan

CITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE FOR BROAD STREET BICYCLE BOULEVARD PROJECT

Castro Valley Municipal Advisory Council March 19, 2018

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

The Wiggle Route in Context

CTDOT Pedestrian and Bicycle Safety Initiatives

About the Studio. Edward J. Bloustein School of Planning and Public Policy - Rutgers University

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

BIKE PLAN CONTENTS GATEWAY

Pedestrian and Bicycle Improvements in Balboa Park Station Area

Off-road Trails. Guidance

Bicycle and Pedestrian Chapter TPP Update Overview. TAB September 20, 2017

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue

CITY MANUALS AND STANDARDS REVIEW

Hennepin County Bicycle and Pedestrian Planning

WALKNBIKE DRAFT PLAN NASHVILLE, TENNESSEE EXECUTIVE SUMMARY NASHVILLE, TENNESSEE

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

Citywide Sidewalk and Crosswalk Programs

Use this guide to learn more about walkability and how you can make your community safer to walk

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Bicycle Master Plan Goals, Strategies, and Policies

» Draft Recommendations» Discussion» Next Steps. Plan for Walking and Biking

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PROJECT OVERVIEW. 20th Avenue Project Limits (Lincoln Way to Wawona St)

Physical Implications of Complete Streets Policies

Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment

This page intentionally left blank.

Who is Toole Design Group?

Long Island Rail Road Expansion Project Floral Park to Hicksville

Hennepin County Pedestrian Plan Public Comment Report

Table of Contents Introduction. 2 Purpose of the Plan...2 The Benefits of Walking and Bicycling...3 Vision and Goals of the Plan...

Plant City Walk-Bike Plan

WELCOME Public Information Centre

This page intentionally left blank.

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Safe Streets. City of Lake Forest Park. March 21, 2017

University of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description

MASTER BICYCLE AND PEDESTRIAN PLAN

City of Jacksonville Mobility Fee Update

CHAPTER. Implementation

TRAFFIC CALMING POLICY & PROCEDURES

Appendix C 3. Bicycle / Pedestrian Planning

Watertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017

Dec 2, Dear Tri Ong, Sam Woods, and Scott Kubly,

Vision. Goals and Objectives. Walking

City of Ann Arbor Pedestrian Safety & Access Task Force

Chapter 2. Bellingham Bicycle Master Plan Chapter 2: Policies and Actions

Public Transportation and Bicycle & Pedestrian Stakeholder Webinar. April 11, :30 PM

Ulster County Non-motorized Transportation Plan

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

New Castle County Bicycle Plan. Heather Dunigan ext

Lynchburg District Update

Edenbrook Hill Drive Traffic Calming Study

City of Wilsonville 5 th Street to Kinsman Road Extension Project

Multimodal Connectivity: Walking & Wheeling to Transit

MONTGOMERY COUNTY COUNCIL MEMORANDUM

City of Novi Non-Motorized Master Plan 2011 Executive Summary

Austin Avenue Bridges Project. Public Meeting Summary

Bobbie Walthall. Hi Bobby, please include these comments in tonight s CC packet. Thanks for your consideration, Phil Collison Lawrence Resident

TRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO

Montclair s Complete Streets Experience

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

TOWN OF WILLIAMSTON, SC BICYCLE AND PEDESTRIAN MASTER PLAN TOWN OF WILLIAMSTON, SC BICYCLE AND PEDESTRIAN MASTER PLAN

TRANSPORTATION STUDY REPORT DRAFT - APRIL 2015 A BLUEPRINT FOR HOW WE CAN GET AROUND GREATER SUDBURY, FROM NOW UNTIL 2031

Complete Streets. Designing Streets for Everyone. Sarnia

North Avenue Corridor Study

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

REGULAR MEETING of the San Mateo County Bicycle and Pedestrian Advisory Committee (SMCBPAC) Thursday, October 20, 2016

Improving the Process: How Statewide Organizations Are Winning Federal Dollars for Bicycle and Pedestrian Projects

122 Avenue: 107 Street to Fort Road

Ann Arbor Downtown Street Plan

Complete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner

RiNo Railroad Crossing Connectivity Analysis. Stakeholder Workshop June 29, 2017

Walking & Bicycling Questionnaire for Candidates

Steps to Conducting a Complete Streets Assessment

PEDALING FORWARD. A Glance at the SFMTA s Bike Program for SFMTA.COM

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

Safety & Convenience for All Users, in All Modes. Barbara McCann NCSL December 3, 2013

Transcription:

Charlottesville Bike-Ped Steering Committee Meeting Notes 2/26/2015 Master Plan Update Streets that Work meeting in December Progress since September SC meeting o Policy o Ped highlights o Bike planning o Prioritization o Public meeting Plan timeline o Policy document updates o Pedestrian prioritization and policies o Updated bicycle network, bicycle vision network o Upcoming Draft plan (mid-april) Public meeting (May 6, 2015) Plan approval POLICY ASSESSMENT Several existing policy strengths identified Additional funding opportunities exist for bike-ped improvement projects o The City already spends above average on bike-ped projects o Look to San Luis Obispo for inspiration Room for improvement of bike parking standards City can improve on the current sidewalks policy needs better standards for the construction of new sidewalks What are Charlottesville s Program Strengths? o Bike-ped Coordinator and Trails Planner added to City staff o Complete Streets initiative o Above average bike-walking percentage o Silver bike/gold walk friendly status o Multiple open street events o SRTS participation Still room for growth and several program opportunities exist for improvement Can review the full policy assessment online and give opinion on which are most needed; Which will resonate most with the public? Meeting Discussion: 1/4 mile radius is too small for Charlottesville Bicycle Vision map o Distinguish Transportation trails from recreational trails

o Recommend lighting on transportation trails Clearing sidewalks and bike lanes after the snow o Commercial areas, businesses could be responsible for bike lane in front of their business o Marketing neighbor to neighbor snow removal Be Neighborly o Guides for snow clearing to ensure that piled up snow does not block curb ramps at intersections and push buttons o Access to Neighborhood Development Services snow plow volunteers list o Adopt a bike lane o Policy that requires snow removal/street cleaning from separated bicycle lanes o Policy that requires bike lanes be cleared/cleaned when streets are cleared/cleaned o Get allowable and acceptable bike lane design in the BAR guide Street crossings o It would be helpful for the city to provide a list of criteria that explains the level of pedestrian facilities for an intersection i.e. when does an intersection receive a push button, crosswalk, etc. o Some automatic pedestrian signals actually slow down the flow of traffic because they go off even when pedestrians are not there and cause cars to idle Woonerfs/Shared Space streets o Is there a VA law restricting woonerf style streets? A quick review shows that there is no statewide ban on woonerf Woonerfs are not a single traffic calming intervention, but a combination of several interventions in a single area (e.g. alternate on street parking, inconsistent curbs, curb extensions, etc.). They are ideally set up in urban areas when motor vehicles should not be traveling faster than walking speeds. PEDESTRIAN HIGHLIGHTS The ADA transition plan is a great document to build upon Engineers should investigate driveway curb cut standards Assess sidewalk disruption during construction (sidewalk closure policy) Proposed Sidewalk Project Ranking Criteria o Point value assigned based on: Context/connectivity Proximity to facilities/attractors Street traffic Land use (GLUP) designation Related projects Field analysis by staff Proposed sidewalk criteria has 25 factors, yet to be tested o How to incorporate deficient sidewalks in this criteria o Current sidewalk priority list is full of requests, build out in 5 years Maybe adopt a similar system for crosswalks (VDOT guidelines)? Pedestrian Network Analysis o Good connectivity in the downtown/central Charlottesville area

o Not so good on residential streets around the periphery o Prioritized streets--emmet, Avon, Roosevelt Brown, W. Main (this may not be all streets mentioned ) There were several pedestrian hotspots identified on map BIKE PLANNING Bike Facilities Map How do we get people excited about the content and implementation of this map? Meeting Attendee Discussion: Maps and wayfinding facilities would need to be available to guide people when on their bikes Topography was not included in level of stress assessment however it was considered by recommendations we established o Individual changes Grove/Hazel are flatter than Gillespie/Poplar The meeting opinion is that some of the routes on the map do not reflect which routes community members actually use o Changes for vision map Old Lynchburg Road is hole in south city transportation network Old Lynchburg road was removed from previous recommendations maps because of safety concerns Monte Vista is narrow, hilly and will not be used by bicyclists Overall opinion is that the map design is good! (head nods from all) Would be useful to explain the bicycle network to others Map shows bike network on the rail beds is this OK? o It probably won't happen, but having it on the plan is important (some are more feasible might be good to designate this on the map realistic vs. unrealistic) Maybe add dashed lines that show bike routes that are probable and those that aren't might make it easier to sell this plan to people Or two diff maps one pie-in-the-sky (general), one more realistic (implementation focused) BIKE NETWORK PRIORITIZATION Active Transportation Priority Tool o Four prioritization factors they identified (with Toole s weighting) Connectivity 40% Demonstrated need 30% Public support 15% Implementation effort 15% Weighting prioritization efforts o Include more variables Proximity to schools as a variable for public support Projects on SRTS streets will be needed to help sell the program Take a poll of residents to determine public support Additional variables will be difficult to add without additional data Add potential SRTS streets to help determine

BREAK OUT SESSION Need to do a test run with two different sets of numbers to better understand how the tool works Tooles numbers and 35-35-20-10 Recommended factor weighting o Connectivity 35, Demonstrated need 35, Public support 20, implementation 10 o Also run prioritization all factors equal and for TDG recommended weighting Are weights negative? o Weighting isn t negative however variables can be scaled so that certain projects will be prioritized at a lower level, e.g. an overly expensive project will receive less priority that a moderately priced project Demand map o Rename high demand areas for what they are proximity to commercial, schools, parks, etc. NEXT STEPS AND TIMELINE Project prioritization feb-mar Implementation/funding feb-mar Plan writing and revisions feb-april Public Meeting preparations and outreach o Public meeting expected May 6, 2015 o Need to present bike/ped plan to NB associations (city and SC members) o The city and steering committee should approach neighborhood committees in advance of the plan release to gain support o Discussion of the plan should take place at multiple events o Advocacy for the plan similar to how plan decorators organize develop alliances for the plan Public meeting (final draft roll out) May 6th City Space 5-7:30PM Final report/plan approval may FINAL THOUGHTS Should we present this plan to the neighborhood associations before the official public meeting to get supporters for this plan? Any guidance from Toole on how to combat the negative/car centric viewpoint of many community members? Additional information to include in the prioritization or discussion of bike facilities o Heat map from UBike (Jake)? o Strava? map data? Strava data is a very limited data set because of the general characteristics of strava users (competitive cyclists) Failure to make allies with neighborhoods and merchants NEED TO WORK ON THIS advice from Toole on this?

Set aside money in project budget for education and encouragement There is a meeting to discuss West Main Street and its resistance on March 17 o AP has since noted that the meeting is March 23 o A first prioritization will need to be run by then