Coastal Engineering Technical Note

Similar documents
APPENDIX D-2. Sea Level Rise Technical Memo

USE OF SEGMENTED OFFSHORE BREAKWATERS FOR BEACH EROSION CONTROL

Technical Note AN EMPIRICAL. METHOD FOR DESIGN OF BREAKWATERS AS SHORE PROTECTION STRUCTURES

Chapter 4 EM THE COASTAL ENGINEERING MANUAL (Part I) 1 August 2008 (Change 2) Table of Contents. Page. I-4-1. Background...

Shoreline Response to an Offshore Wave Screen, Blairgowrie Safe Boat Harbour, Victoria, Australia

Comparisons of Physical and Numerical Model Wave Predictions with Prototype Data at Morro Bay Harbor Entrance, California

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby

Juneau Douglas Harbor

EXPERIMENTAL RESEARCH ON COEFFICIENT OF WAVE TRANSMISSION THROUGH IMMERSED VERTICAL BARRIER OF OPEN-TYPE BREAKWATER

Cline s Point Marina Ship Wave Analysis

Figure 4, Photo mosaic taken on February 14 about an hour before sunset near low tide.

Inner-Bank Erosion Processes and Solutions at Coastal Inlets

SHORE PROTECTION AND HABITAT CREATION AT SHAMROCK ISLAND, TEXAS ABSTRACT

Appendix E Cat Island Borrow Area Analysis

page - Laboratory Exercise #5 Shoreline Processes

The development of the historical harbour of Paphos, Cyprus H.J. van Wijhe*, M. Meletiou^ Division, P.O. Box 152, 8300 AD Emmeloord, The Netherlands

Examples of Carter Corrected DBDB-V Applied to Acoustic Propagation Modeling

OCEAN WAVES NAME. I. Introduction

Redondo Beach Boat Launch Ramp Facility

CORPS FACTS. Harbor Dredging U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG

Nearshore Dredged Material Placement Pilot Study at Noyo Harbor, CA

Proceedings, 2001National Conference on Beach Preservation Technology, pp COASTAL INLET BANK EROSION. William C.

Tedious Creek Small Craft Harbor: CGWAVE Model Comparisons Between Existing and Authorized Breakwater Configurations

City of Port Aransas Shoreline Analysis and Improvements

1-44. SITKA HARBOR, ALASKA (Western Channel, Crescent Bay Basin, Channel Rock Breakwaters) (CWIS NOS , 16840, 10322, 55030, 13787)

Nome Harbor Page 2 of 12

Chapter 10 Lecture Outline. The Restless Oceans

BRRAKING WAVE FORCES ON WALLS

CROSS-SHORE SEDIMENT PROCESSES

Coastal Hazards Study

WOODFIBRE LNG VESSEL WAKE ASSESSMENT

Chapter 22, Section 1 - Ocean Currents. Section Objectives

Ketchikan Harbors Thomas Basin and Bar Point Harbor

Oceans and Coasts. Chapter 18

Mouth of the Columbia River Jetties Three-Phase Construction Plan

STUDY ON TSUNAMI PROPAGATION INTO RIVERS

INTRODUCTION TO COASTAL ENGINEERING

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

Chapter 10 Waves. wave energy NOT the water particles moves across the surface of the sea. wave form moves and with it, energy is transmitted

Designing a Harbor Entrance to Defeat Swell Wave Agitation. FAX (506) ; 2

WAVE PRESSURE DISTRIBUTION ON PERMEABLE VERTICAL WALLS

OECS Regional Engineering Workshop September 29 October 3, 2014

Lecture Outlines PowerPoint. Chapter 15 Earth Science, 12e Tarbuck/Lutgens

1-22. KETCHIKAN, ALASKA (Thomas and Bar Point Basins) (CWIS NOS & 87071) Condition of Improvement 30 September 2007

INVESTIGATION OF WAVE AGITATION INSIDE THE NEW FISHERY PORT (CASE STUDY: NEW MRZOUKA FISHERY PORT, LIBYA)

Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College

Ocean Waves. Capillary. Gravity. Wind generated. Tides Tsunamis Seiches

Imagine that you can see a side view of a wave as it approaches a beach. Describe how the wave changes as the wave approaches the beach.

SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT

ABSTRACT. KEY WORDS: Navigation safety; numerical modeling; waves; current; sediment transport; channel infilling; morphology change.

Wave Transmission Testing of the Martin Ecosystems BioHaven Floating Breakwater

International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN:

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

OECS Regional Engineering Workshop September 29 October 3, 2014

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 1, No 4, 2010

Cordova Harbor Page 2 of 9

CALCASIEU SALINITY STRUCTURES. HYDRODYNAMIC MODELING (To Support Design of Salinity Barriers)

Technical Brief - Wave Uprush Analysis Island Harbour Club, Gananoque, Ontario

Nearshore Placed Mound Physical Model Experiment

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

COFFS HARBOUR SEDIMENT MODELLING AND INVESTIGATION

Utilizing Vessel Based Mobile LiDAR & Bathymetry Survey Techniques for Survey of Four Southern California Breakwaters

Chapter. The Dynamic Ocean

Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No , )

Juneau Aurora Harbor

PHYSICAL AND NUMERICAL MODELLING OF WAVE FIELD IN FRONT OF THE CONTAINER TERMINAL PEAR - PORT OF RIJEKA (ADRIATIC SEA)

Steven A. Hughes. Ph.D., P.E. David R. Basco. Ph.D., P.E.

MAR 110 LECTURE #15 Wave Hazards

Photo by: Darryl Hatheway, 2011

PROPAGATION OF LONG-PERIOD WAVES INTO AN ESTUARY THROUGH A NARROW INLET

New Orleans Municipal Yacht Harbor

Earth Science Chapter 16 Section 3 Review

DESIGN OPTIMIZATION FOR A PASSIVE MESH SCREEN WAVE ABSORBER FOR THE CCOB

Undertow - Zonation of Flow in Broken Wave Bores

TechnicalNotes. Application Criteria for the Automated Real-Time Tidal Elevation System (ARTI ES)

Coastal & Marine Environment. Chapter. Wave Transformation. Mazen Abualtayef Assistant Prof., IUG, Palestine

Bob Battalio, PE Chief Engineer, ESA September 8, 2016

Oceans - Laboratory 12

SEA LEVEL RISE IMPACT ASSESSMENT AND MITIGATION ALTERNATIVES DEVELOPMENT FOR BALBOA ISLANDS, CITY OF NEWPORT BEACH, CALIFORNIA

Figure 1 Example feature overview.

Monitoring Completed Navigation Projects, Lessons Learned IV

SURFACE CURRENTS AND TIDES

Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA

Undertow - Zonation of Flow in Broken Wave Bores

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

WATERWAYS AND HARBORS DIVISION Proceedings of the American Society of Civil Engineers. EQUILIBRIUM FLOW AREAS OF INLETS ON SANDY COASTS a

OCN 201 Tides. Tsunamis, Tides and other long waves

S E SKELLY ENGINEERING

PREDICTION OF ERODED VERSUS ACCRETED BEACHES

Waves. G. Cowles. General Physical Oceanography MAR 555. School for Marine Sciences and Technology Umass-Dartmouth

Wave Transmission at Detached Breakwaters for Shoreline Response Modeling

DUXBURY WAVE MODELING STUDY

DRAFT. October 17, 2014 File No Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA.

Eelgrass and Macroalgae Presence/Absence Preliminary Surveys BHP Proposed Grays Harbor Potash Export Facility A Task 400

Taranaki Tsunami Inundation Analysis. Prepared for Taranaki Civil Defence Emergency Management Group. Final Version

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION AND FUNCTIONAL DESIGN OF COASTAL STRUCTURES

( max)o Wind Waves 10 Short Swell (large wave steepness) 25 Long Swell (small wave steepness) 75

Coastal Harbors and Waterways, NC (Shallow Draft Navigation) (O&M)

U.S. Army Engineer Institute for Water Resources

Transcription:

Coastal Engineering Technical Note BAFFLED BREAKWATER FOR LIMITED FETCH SITES CETN III-45.(12/91) PURPOSE: To describe the Spud Point Marina breakwater, an innovative baffledtype breakwater designed to permit marina flushing while reducing short-period wave penetration. BACKGROUND: Spud Point Marina breakwater is located in the northwestern part of Bodega Harbor, an enclosed bay on the California coast, about 60 miles north of San Francisco (Figure 1). Bodega Harbor is protected from the open Pacific Ocean by a rocky headland and peninsula, Bodega Head. A sandy peninsula across the southern part of Bodega Harbor, Doran Beach, separates it from the area of the open coast known as Bodega Bay. Access to the various marina facilities inside Bodega Harbor is provided through a jettied entrance and dredged navigational channels. Bodega Harbor is relatively shallow; the deepest parts are the dredged channels and turning basins (nominal project depth of -12 ft mean lower low water (mllw)). Spud Point Marina is operated by Sonoma County. The breakwater and access channel are maintained by the Corps of Engineers in addition to the entrance jetties and other dredged channels and basins shown in Figure 1. The breakwater is a concrete pile-supported baffled structure consisting of prestressed concrete vertical piles and a cast-in-place concrete cap beam, with prestressed concrete baffle panels between the vertical support piles under the cap beam. Angled prestressed concrete batter piles along the marina side of the structure are embedded into the cap beam to form bents, giving increased lateral support. The top of the cap beam is located at an elevation of +8 ft mllw datum. The baffle panels extend from the bottom of the cap beam down to -1 ft mllw. Since the breakwater is open between support piles below the baffle panels, the structure allows a varying degree of circulation through the marina, depending on the stage of the tide. Figure 2 is an oblique aerial photo of the marina and breakwater looking in an easterly direction. Spud Point is the promontory and sand flat on the right (south) side of the breakwater; the main Federal channel and narrower access channel also are visible. Figure 3 shows the middle part of the breakwater at a relatively low tide from a viewpoint on the hillside west of the marina. The batter piles and openings below the baffle panels can be seen, as well as handrails and a fishing platform for public use. US Army Engineer Waterways Experiment Station, Coastal Engineering Research Center 3909 Halls Ferry Road, Vicksburg, Mississippi 39180-6199

38'18 123'04' I N MN V 123'02' A Entrance Jetties 0 1000 2000 feet Figure 1. Site location map. BODEGA Figure 4 is a scaled site plan of the breakwater and vicinity. State Plane coordinates are shown. Dredged channels are indicated by dashed lines. The zero elevation mllw contour is shown as a solid line enclosing tidal flat zones indicated by hatching. Selected recent soundings referenced to mllw are shown to point out the large depth difference between the channel and the adjacent flat fronting the breakwater, where depths range from -5 to -1 ft mllw. North of the marina, depths are generally slightly greater than those in front of the breakwater. Preliminary design of the breakwater was done by Moffatt & Nichol, Engineers, Long Beach, California, under contract to the US Army Engineer District (USAED), San Francisco (SPN). The breakwater was subsequently built by Sonoma County. Final design and construction supervision were also by Moffatt & Nichol. Because the as-built breakwater meets the criteria of the authorized Federal Project, maintenance responsiblity has since been assumed by SPN. BAY

BAFFLED CONCRETE I7 SHEET PILE,B BREAKWATER Figure 4. Detail map of marina and breakwater. BREAKWATER DESIGN: The tidal range between mllw and mean higher high water (mhhw) is 4.1 ft at the north end of Bodega Harbor. The mhhw, 4.1 ft, and the highest estimated tide (het), 6.5 ft, were critical to design of the breakwater cap elevation. No explicit consideration of current effects on the structure, such as scour potential or wave/current interaction, was included in the breakwater design. Qualitative information indicated that pre-existing currents were generally north-to-south at the proposed breakwater location. The structure's effects on currents and, consequently, on flushing and water quality in the marina were an important consideration in the decision to use a permeable baffled structure. Design wave characteristics were determined using forecasting procedures found in the Coastal Engineering Research Center's (CERC's) Shore Protection Manual (SPM 1977). Pacific Ocean waves do not penetrate as far as Spud Point, so only locally-generated waves needed to be considered. Boat wakes within the marina were expected to be negligible, since speeds are restricted to 5 mph in such areas. A wind rose for seven years of record at the U.S. Coast Guard (USCG) station at Doran Point was available. Winds from northwesterly to southerly directions were considered unimportant for wave generation, due to sheltering of the site by Bodega Head peninsula, and lack of long fetches in those directions. From a review of the wind rose versus fetch orientation, fetch length, and water depths, two critical fetches were selected for calculation of wave forecasts (see Figure 5). The SPM shallow-water forecasting curves were used assuming a stillwater level (swl) of 4.1 ft (the mhhw elevation for northern Bodega Harbor). Wave characteristics under het conditions were not forecast. 4

Breakwater BODECA BAY CETN III-45 (12/91) Figure 5. Critical wave generation fetches for Spud Point site. It was determined that no breakwater would be needed for the north side of the marina. The wave forecast for the southeasterly fetch resulted in significant wave height and period, H, and T,, of 1.5 ft and 2.5 set, respectively, giving a design wave height, H, of 2.5 ft. The SPM recommends use of HI, the height of the average of highest 1 percent of all waves (= 1.67 H,) r as the design wave height for rigid structures. Selection of the Spud Point site and recommended breakwater design involved many other considerations, including costs over a 50-year design life span and environmental impact. Configuration and maintenance of dredged channels and dredged material disposal options played an important part in selection of the recommended plan. Bottom sediments and bathymetry were considered with respect to dredging of the marina and access channels, and foundation conditions for the breakwater. The Corps' General Design Memorandum (GDM) (USAED, San Francisco 1981) describes alternative plans and covers the selection process in detail. 5

The concrete structure includes baffle panels, vertical and batter support piles, and a continuous cap beam. In the most seaward part of the breakwater, every vertical pile forms a bent with a tilted batter pile on the marina side. For the rest of the breakwater, bents alternate with vertical intermediate piles. Baffle panels were designed as simple beams, supported by the vertical piles. Their design considered bending stresses due to wave loads and panel dead load. The batter piles were designed for axial load due to wave loads and bending stresses due to dead load. The vertical bent piles were designed for axial load due to dead and wave loads and bending stress due to wave loads. The intermediate piles are similar to the vertical bent piles. The cast-in-place cap was designed as a continous beam for vertical loads supported by the bents and intermediate piles, and for horizontal loads supported by the bents alone. The GDM states that wave forces were calculated in accordance with EM 1110-2-2904, "Design of Breakwaters and Jetties" (US Army Corps of Engineers 1986), as applicable to non-breaking, breaking, and broken waves. Breaking conditions were determined on the basis that the average ratio of the depth of water in which a wave breaks to the wave height at the point of breaking is approximately 1.3. Wave forces were calculated by the Sainflou method for non-breaking waves, and by Minikin's method for breaking waves, both of which are presented in EM 1110-2-2904. The crest height of the breakwater (top of cap elevation) was arrived at using methods detailed in EM 1110-2-2904 for the case of non-breaking waves forming a standing wave (clapotis) due to reflection off the wall. The design wave height, 2.5 ft, was used along with a swl (= mhhw elevation) of 4.1 ft plus a wind setup of 0.4 ft in an equation which EM 1110-2-2904 refers to as the modified Sainflou method or the Miche-Rundgren method. The method gives the superelevation (above the swl) of the mean level of the clapotis. The crest of the clapotis was calculated to occur at about +7.7 ft mllw, determined as this mean level plus the design wave height. The cap elevation was consequently set at +8.0 ft mllw. For the het swl of +6.5 ft mllw, the calculated clapotis crest elevation was +10.2 ft, an overtopping condition. Since het conditions were considered an infrequent occurrence, and the distance between the breakwater and the nearest berths was considered likely to be sufficient to result in dissipation of overtopped waves, the +8.0 ft cap elevation was considered to be adequate. As previously described, the baffled breakwater uses baffle panels which extend only part of the way from the cap to the harbor bottom. Lowering the panel bottom elevation decreases the wave transmission, but also decreases the flushing potential of the marina. The design approach was to find the highest panel bottom elevation possible, given the allowable wave transmission criteria. The GDM states that normal criteria for acceptable maximum wave heights in berthing areas limit maximum wave heights to 1.5 ft. Since there is no published Corps design guidance for this type of breakwater, results presented by Wiegel (1960, 1964) in his landmark book, Oceanographical Engineering, were used. Wiegel developed a nomograph from a first-order transmission expression based on wave power for the case of an infinitely thin, rigid barrier extending from above the water surface to some distance below the water surface. The theoretical approach assumes monochromatic waves over a flat bottom and does not consider the effects of supporting piles. A detailed description of the theoretical development and laboratory tests performed for comparison with the theory's predictions are given in an earlier journal article (Wiegel 1960). Figure 6 shows the version of Wiegel's nomograph given in the US Navy's Coastal Protection Design Manual (US Navy 1982). The nomograph relates the transmission coefficient, Kt, (ratio of transmitted wave height to incident wave height) to the ratio of the baffle panel penetration depth to the stillwater depth, h/d,, for a range of relative depths. The relative depth is the local ratio of depth to wavelength, d/l, 6

TRANSMISSION COEFFICIENT, Kt (AFTER WIEGEL, 1960 CETN III-45 (12/91) Figure 6. Nomograph for wave transmission of baffled structure. occurring at the structure. For example, one might compute the deepwater wavelength, L,, using the design wave period, then compute an equivalent deepwater relative depth, d,/l,, (using the stillwater depth at the structure) then find local relative depth, d/l, using Table C-l of the SPM (which relates d/l and d/l,). Given a design swl, mudline elevation on the structure, and incident wave height, the nomograph can be used to determine the required baffle bottom elevation corresponding to a transmitted wave height criterion. The GDM states that with the bottom of baffle panels set at -1.0 ft mllw, the transmitted wave heights would be about 1 ft under design conditions for the mhhw and het swls (K, of about 0.4 in Figure 6), and lower than 1 ft for lower tidal stages. Although not stated in the GDM, apparently the mudline elevation on the structure was assumed for transmission calculations to be at about -7 ft mllw, which was also assumed in the final design by Moffatt & Nichol.

POST-CONSTRUCTION MONITORING OF BREAKWATER PERFORMANCE: A field monitoring study of the Spud Point Marina breakwater was conducted by CERC in conjunction with SPN as part of the Monitoring Completed Coastal Projects (MCCP) program (Lott 1991). A field study of wave transmission was conducted using boat wakes and pressure sensors to measure the generated waves. USCG lifeboats from the Doran Point station were provided for generation of wakes. Soundings of potential scour zones and a side-scan sonar survey were made. Circulation through the breakwater and marina was measured, and the breakwater was examined for structural integrity. Flushing performance appeared to be satisfactory. No evidence of scour or structural displacement was found. At higher tide stages during the boat wake experiment, some generated waves were able to penetrate the marina, but these same large wakes were producing unacceptable boat motions in other marinas on the opposite side of Bodega Harbor, forcing a pause in the experiment to wait for lower tides later in the day. The transmitted wave heights were too small to be quantified from the pressure records, and were well below design criteria. Later, at the lower tide stages, generated waves were highly dissipated as they crossed the shallow region fronting the breakwater. Although the wave attenuation was not quantified by the boat wake experiment, the difficulty experienced in producing transmitted waves is evidence that the breakwater is providing significant wave attenuation. The marina operator reports that the breakwater performance has been very satisfactory, and that only the largest tenant boat (65-ft-long) produces a wake large enough to penetrate the breakwater and cause rolling of the docked boats. Figure 7 is convincing evidence of the breakwater's wind wave attenuation performance under severe conditions. Even with overtopping, water inside the marina remains calm. Although the transmitted wave heights were small during the experiment, the significant rolling of some of the boats due to the largest wakes suggests that parameters other than wave heiqht may be of interest for wake or wave transmission criteria. It is unknown whether wind waves of similar height would have caused the rolling. Boats were docked so that they were broadside to the breakwater. The baffled type of breakwater may reduce vertical water particle motions and surface disturbances, yet allow appreciable horizontal motion to pass through the breakwater in the lower part of the water column. This emphasizes that for some protected breakwaters, protection against wakes may govern the design more than protection against wind waves. SUMMARY: Based on the experimental, anecdotal, and photographic evidence, the Spud Point Marina baffled breakwater appears to be performing acceptably and Wiegel's nomograph seems suitable for its design. Designers of breakwaters in low-energy environments where flushing performance is critical should consider a baffled structure. Since the relative contribution of site-specific conditions (particularly the shallow flats fronting the breakwater) to successful performance of the Spud Point breakwater is unknown, care should be taken when extending the use of the nomograph and the baffled structure beyond preliminary conceptual studies. Physical model testing may be needed to more confidently predict wind wave and boat wake attenuation where costs or risks are high, until a more comprehensive evaluation of the theory and performance of baffled breakwaters has been completed.

POINT-OF-CONTACT: For further information contact Jonathan W. Lott at (601) 634-4268 (FTS 542-4268). REFERENCES: Lott, J. W. 1991. "Spud Point Marina Breakwater, Bodega Bay, Sonoma County, California," Miscellaneous Paper CERC-91-5, US Army Engineer Waterways Experiment Station, Coastal Engineering Research Center, Vicksburg, MS. Shore Protection Manual. 1977. 3rd Ed., 3 vols., US Army Engineer Waterways Experiment Station, Coastal Engineering Research Center, US Government Printing Office, Washington, D.C. US Army Engineer District, San Francisco. 1981 (Sep). "General Design and Environmental Impact Statement for Navigation Improvements, Bodega Bay, Sonoma County, California," Design Memorandum No. 1, San Francisco, CA. US Army, Office of the Chief of Engineers. 1986 (Aug). "Design of Breakwaters and Jetties," Engineer Manual No. 1110-2-2904, Washington, DC. US Navy, Naval Facilities Engineering Command. 1982 (Apr). "Coastal Protection," Design Manual 26.2, Alexandria, VA. Wiegel, R. L. 1964. Oceanographical Engineering, Prentice-Hall, Inc., Englewood Cliffs, NJ.. 1960 (Mar). "Transmission of Waves Past a Rigid Vertical Thin Barrier," Journal of the Waterways and Harbors Division, American Society of Civil Engineers, Vol 86, No. WW 1, pp l-12. 10