Charmborough Bells Risk Assessment and Method Statement

Similar documents
Staff Contractors. Public. Staff Contractors

Assembly Instructions. -Cantilever Boat Lifts

Thank you for purchasing a Porta-Dock product! *Please read and follow these instructions step by step*

Deans, Directors, Heads of Schools and Departments and Research Institute Directors and Managers

Assembly Instructions

Shoreline Cantilever Lift 2500lb Capacity Models: (108" inside width) - Part # (120" inside width) - Part #

QUALITY ALUMINUM BOAT LIFTS, INC. INSTRUCTIONS. Dominator Lake Lift

Ladies Shopper Bike Assembly Manual 28C03

Safety Risk Assessment Working at Height: Mobile Tower Scaffold

Safe Use of Access Equipment

Wellhead Mast. Installation and Operation Guide. Nanometrics Inc. Kanata, Ontario Canada

2,500/4,000 LB Easy Riser Vertical Cable Feighner Lift

VL SHEAVES/CABLE UPGRADE KIT INSTRUCTIONS

Safety System Installation Guide for ARE Wind Poles

FIX ROAD & FIX STRAP cargo securing systems Operating Instruction Manual

InstallatIon and owner s InstrUCtIons

Assembly Instructions

DE8410 FIVB Official Beach Volleyball Net

1. Product Name. 2. Product Code. 3. Colour. 4. Brief Description. 5. Contents. Itinerant Frame. Likely to be as shown

Specialists Window Cleaning Induction

The purpose of this training is to give field technicians awareness training and guidelines on potential hazards they may encounter in the field.

American Flagpole & Flag Co. 1(800)

Parts List. 7. Handlebars 8. Grips 9. Handlebar Stem 10. Front Brake 11. Front Wheel 12. Crank 13. Chain

SAFE WORK PROCEDURE. Location of Equipment Written By: Approved By: Date Created Last Revision

HYDRAULIC MOBILE LIFTING TABLE

Installation and Training Manual

Cable Replacement Instructions for R-Series Roust-A-Bout 100/150/250

Duo/Trio Office Bike Owner s Manual

Boat Boat Loader Fitting Instructions

CABLE REPAIR PROCEDURE 2100 Series, 2000 Series & Eventer

400/488 Rotating Davit Installation Instructions

User s Manual. Model SWTC800. CAUTION: Adult Assembly Required

VL 2K LIFT D-L WINCH INSTRUCTIONS (Applies to P/Ns , , , , , )

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.

contents introduction

HOME ASSEMBLY INSTRUCTIONS

Assembly Instructions And User Guide

INDEX. Specifications 1. Important Safety Precautions 2. Operating Instructions 3, 4. Optional Extras (Meal Tray & Footrest) 5.

MO Tech Challenge Info- Conference 2019

Fall Protection Refresher Orientation. Fall Protection Refresher Orientation 1

Deluxe Gourd Racks I D E G A. Parts List. Shown above are parts for the two-level, Deluxe Gourd Rack (DGR 12V)with 12 arms for vertically hung gourds.

Backboard and Rim Owners Manual

75 Ton SD Shop Press Operating Instructions

7130 Lancer Rear Drive Magnetic Commercial Indoor Cycling Bike

Instructions for assembly and use ZAP telescopic platform ladder Z600

Pre-control risk estimate. Likelihood Risk

Installation, Operating, Inspection and Maintenance Instructions Ladder Climber s Safety System. Warning

Troyer s Gourd Rack 8 unit F R H O P

TRAILMATE METEOR ASSEMBLY MANUAL

OPERATION MANUAL DMI 16-LIGHT LIGHT TOWER ALSO AVAILABLE ONLINE AT DMI-LT.COM

Chapter 2 Rigging. Cutting Wire Rope. Anchoring Wire Rope to Drum. Winding Wire Rope Onto Drum

Tripod Setup Guide (M-TPx)

Operator s Manual Series 2400 Material Lift

Instruction Sheet. CP2000: 2000 lb Cable Puller IMPORTANT RECEIVING INSTRUCTIONS SAFETY ISSUES

Trike-Bike Assembly Manual

RATCHET RELEASE SHACKLE

USER MANUAL. you pedal, something amazing happens

CHAPTER 10 FALL PROTECTION

Thank you for purchasing the Hollander II Bike from Made.com

First Team Sports, Inc. Stellar Recreational Volleyball System

-- SGP (NOVA TEAM SQUARE)

Rhino-Rack 570, 580. Important Information

IMPORTANT: RECEIVING INSTRUCTIONS:

PF30 Inspection & Maintenance Manual

WIRE ROPE PULLING MACHINE

8MAY15 US RACK, Inc Falcon Drive, Madera, CA

CAUTION - PUT SAFETY FIRST

10.2. Basketball Single Post System

Order No Projection Backboard

C - SERIES. Height Adjustable Portable Goal Supports. Installation & Owner s Instructions C1000 C2000. Made in the USA

HEALTH & SAFETY ARRANGEMENTS FOR MANAGEMENT OF WORK AT HEIGHT

INSTALLATION INSTRUCTIONS. Parts List. Tools Required. Before You Begin. Installation. Customer Information BICYCLE ATTACHMENT JUL.

Parts: Included in the parts box: Inner Rear Tire Tray. Inner Front Tire Tray. Trail Doc Clamp. Pivot Assembly. Trail Doc Post.

USER MANUAL. Beach volleyball posts BEACH CHAMP ID:

TENNESSEE COMMISSION ON FIRE FIGHTING

MAGNETIC INDOOR CYCLING BIKE

Trilogy Theory of Operation

No ' Long No ' Long

Fiber Cable Puller with Tuf-Lugger lite

Final Assembly Instructions Bikes with Quill Stems

ASSEMBLY MANUAL HOBIE CATSY

Thank you for purchasing a WIKE BOX BIKE!

2000 lb manual winch

RISK ASSESSMENT FOR Philips Smart Touch Installation 03/04/2012

Operator s Manual. 2010, 2015, 2020, 2025 Material Lifts

USER MANUAL. you pedal, something amazing happens

BANKSMAN / SLINGER. 1. What is the smallest size diameter of synthetic rope allowed for use as a hand held tagline?

Safe Work Method Statement

PHOENIX, ARIZONA USA

Operator s Manual. Series 2100 Contractor Lifts

ES-701 INSTRUCTIONS FOR USE

HELMETS SAVE LIVES!!! ALWAYS WEAR A PROPERLY FITTED HELMET WHEN YOU RIDE YOUR SCOOTER. DO NOT RIDE AT NIGHT. AVOID RIDING IN WET CONDITIONS.

GENERAL MAINTENANCE & SAFETY GUIDANCE

Final Assembly Instructions Bikes with Threaded Headsets

Manual winch MANISTOR 100 and 200

Trampoline & Enclosure Assembly Instructions

User Instruction Manual For Davit Rescue System

BRONZE BUSHING REPLACEMENT PROCEDURE DN345 & NL450C

Square Diagonal Tripod Japanese Square Filipino Diagonal Round Shear Ladder

SERIES 2 RAMP OWNER S MANUAL TOOLS REQUIRED: BEFORE YOU BEGIN... Read and understand these instructions before beginning a ramp setup.

Transcription:

Charmborough Bells Risk Assessment & Method Statement Charmborough Bells Risk Assessment and Method Statement Introduction This risk assessment and method statement has been prepared to outline the procedures adopted in assembling, using and dismantling the Charmborough Ring. It also considers the key health and safety risks and the control measures designed to minimise these risks. The Charmborough ring is a small ring of tower bells hung in their own steel structure. See photographs. A video of the assembly process can also be viewed here The Charmborough ring is checked for defects prior to assembly and on dismantling, and any defects rectified. The trailer is also serviced periodically by GT Towing. Pre-planning The Charmborough Ring is hired for use at public events for about 12 to 15 days per year. Each hirer is responsible for providing the details of the proposed location to the booking coordinator and highlighting any site specific risks in advance. We check proposed access using google streetview and if necessary a site inspection is undertaken by one of the experienced supervisors before the booking is confirmed. On arrival, the supervisor will double check the site and ensure that it is safe to drive the vehicle and trailer on to the site, how close this is to the place where the ring will be erected, and whether the trailer can be left at this location whilst the event takes place. Where the trailer cannot reach the place of erection, and act as a safe working platform, we check the route between the trailer and place of erection, and ensure that openings are wide enough, and there are no surfaces that are easily damaged. We have timbers that are used as load spreaders at the base of the ring, which also protect surfaces. Transport The mobile belfry is transported in a dismantled state on a four-wheeled trailer which measures approximately 4m long, 2.1m wide and 2m high with a laden weight of about 1 ton. Prior to towing there will be a safety check of the trailer and towing vehicle, using the checklist provided (appendix 2). This method statement and risk assessment considers the issues once the trailer has reached the site. Supervision The belfry is assembled and dismantled under the supervision of an experienced erector. The ring is erected in two stages the first taking about three quarters of an hour. For the first stage, a team of five able bodied adults will assist with carrying the components and the assembly and dismantling process generally. No person will need to lift a weight greater than about 25kg.

Charmborough Bells Risk Assessment & Method Statement The second stage involves hoisting the bells into position using an electric hoist and involves working at height. Only one assistant is required at this stage, and it is preferable that other people are not present underneath the ring. This stage will about half an hour. Safety Prior to erection the supervisor will give a toolbox talk and safety briefing to the assembly team. Personal protective equipment (PPE) in the form of five pairs of stout gloves and hard hats are stored in the toolbox on the trailer. The team should also wear appropriate footwear. Members of the public will be kept out of the site whilst assembly and dismantling takes place. The area needed measures 8m x 5m. Assembly Two 225 x 50mm x 2400mm lengths of timber will be used as load spreaders on the surface. If the surface is not entirely level, additional timber packers will be used to bring the two lengths of timber level. The steel framework will be unloaded from the trailer, carried to the site, and bolted together in accordance with the erection sequence (see appendix 1). The largest items are the portal legs and each weighs approximately 70kg and needs to be carried by three people. Fully assembled, each portal contains three components and weighs a total of about 200kg. Where there is limited space, one set of portal legs can be assembled upside down, before being raised. Each portal is raised manually from horizontal to vertical by the five person team, and diagonal braces fixed to restrain the structure. This completes the first half of the erection sequence. Working from the ladders, the upper parts of the frame and uprights for the tubular lifting gantry are then bolted on, and two timber duck boards are put into position either side of bells 5 and 6, for the supervisor to stand on to complete assembly of the hoist and then hoist the bells. The bells are then carefully lowered from the trailer down two of the 225 x 50mm x 2400mm lengths of timber. This is a five person operation, with care being taken to ensure that the castors remain on the boards, and no-one is in front of the bells aas they are lowered. Each pair of bells will then be wheeled to the site and then lifted into position using the electric scaffold hoist provided. Power will be taken from portable generator, or permanent mains supply. Care will taken to ensure that electric cables do not become snagged. The hoist has a lifting capacity of 250kgs. Each pair of bells weighs a maximum of about 200kg. The hoisting operation is undertaken by the supervisor who stands on the platforms at bell level. A blue tarpaulin cover may then be fitted over the top of the belfry and a second translucent cover around the sides at high level, if wet and outdoors. Once the ring has been assembled all bolts are then checked for tightness, the ring can be used. Dismantling Dismantling us undertaken as the reverse of this process. As the components are dismantled and stored on the trailer, their condition is checked, using the checklist provided (Appendix 3). Any defects are rectified before the next use.

Charmborough Bells Risk Assessment & Method Statement Assembly takes about one and a half hours; dismantling takes about one and a quarter hours, depending on how far the trailer is away. Feedback We encourage feedback from each event, so that we can continuously improve our procedures.

Charmborough Bells Risk Assessment & Method Statement Risk assessment Risk Party responsible for managing risk Risk management action After risk management Action period/deadline Likelihood of risk Impact Delivery to site and return to depot afterwards Supervisor The ring will be transported to site on the trailer. This will be checked before towing. Safety of erection team Supervisor Prior to erection the supervisor will give a toolbox talk and safety briefing to the assembly team. The team are also encouraged to view the video beforehand. Personal protective equipment (PPE) in the form of five pairs of stout gloves and hard hats are stored in the toolbox on the trailer. The team should also wear appropriate footwear. Manual handling Supervisor To be covered in toolbox talk. All beams are to be lifted by at least two people. The legs will be erected by five people. As they are assembled on the ground, and prior to lowering afterwards, the legs will be resting on timber packers, to help avoid fingers becoming trapped. Falling objects Supervisor As components are handed up or taken down from high level there is a risk of falling objects. No work is to be carried out at low level during this stage and assistants to wear hard hats.

Charmborough Bells Risk Assessment & Method Statement Risk of slips, trips and falls Supervisor Those carrying the steel beams and lowering the bells off the trailer need to check the path and ensure that there are no trip hazards. Risk of slips, trips and falls Supervisor Falling from the ring during stage 2 of the erection sequence is a risk. Care will be taken and only one person will be working at high level at one time, and people keep well away.. Catching fingers Supervisor There is a risk of fingers becoming caught in between beams as they are assembled and in the pulley on the hoist during operation. Stout gloves must be worn and hands kept clear of the pulley during hoisting. Electric shock Supervisor The electrical equipment will be checked visually before use. Care will be taken with the routing of electric cables to ensure that they do not become snagged or damaged during the lifting operation. Ringing of the bells Supervisor The bells will only be rung under the supervision of a competent bellringer. The bells are sufficiently light for there to be very little risk of any damage to people misusing them. A video of the bells being rung can be viewed here.

Appendix 1 Erection Sequence 1. If the surface on which the ring is being erected is likely to be damaged, lay the four 6mm sheets of plywood and join with gaffer tape. The sheets have an outline of the ring on them, so enabling the ring to be assembled square. On soft ground the 225x 50mm 2400mm long timbers may be used underneath each floor angle to spread the load. 2. The portal frames are numbered I and II, and are marked as such. Lay out the first top beam on the ground. Ensure that there is timber packing underneath, to make lifting easier later. 3. Lay the two legs out on the ground and offer each leg up to the top beam. Each leg is lettered A, B, C or D, to correspond with the letters on the relevant ends of the top beam. Ensure that the sides labelled inner are facing up. Fit three long M12 bolts to the upper side of each joint and leave finger tight. 4. Repeat the operation for the other portal frame 5. Connect the two floor angles to the legs as shown, using the larger M16 nuts, bolts and washers. The bottom flange goes underneath the leg. 6. Attach the four cross braces with long M12 bolts. The cranked end is attached to the floor angle and goes on the outside flange. 7. Five people are needed to lift each portal frame member into position. It becomes easier the nearer to the vertical it gets. One person will then fit the two diagonal braces, with long M12 bolts. 8. Once the two portals have been lifted, ensure that the structure is square. Move if necessary.

Appendix 1 9. If it is possible, move the trailer underneath the erected portals to act as a safe working platform. Otherwise work from the extension ladder provided. 10. Fit the two side cross members with short M12 bolts. The connecters for the gantry poles are on the outside. The cross members are numbered with the appropriate bells 1/2; etc and these must correspond with the same numbers on the top flanges of the portal beams. 11. Fit the middle cross member. Ensure the bell numbers correspond with the same numbers on the top flanges of the portal beams. 12. Fit in position with short M12 bolts. 13. Lay the two wide timber platforms between the side and middle cross member. They go either side of bells 5 and 6. Ensure that they are square. Also check that rest of structure is square 14. Fix the remaining long M12 bolts on the inside joints between portal legs and top beam. 15. Insert the four gantry poles. Tighten each one with an allen key. Do not over tighten. 16. Fit the two gantry transoms. Each has a 90 o coupler on the end. Tighten the allen screws. 17. Pass up the electric hoist and runners to those working at high level. Thread the hoist on to the pole and loosely fit the 2 nd set of runners. Offer up to the gantry cross members. Ensure that this runs smoothly and then tighten the allen screw on the 2 nd set of runners. 18. If the hoist is lowered without any load, the cable on the drum can become slack and snag, and can damage the cable. Always use the counterweight provided. 19. The bells are normally transported with the ropes taken round the wheel and the tail end looped around the clapper. The bells are at about 45 o to the horizontal. Unattach the ropes from the clappers before lifting. 20. Position the bellframe containing bells 1 and 2 on the trailer under the space for 5 & 6 and so that the gantry can travel across to their final position, without moving the electric hoist on the gantry. er the hoist and attach the frame. Hoist through the larger opening. Move across into position and lower. Put one 6mm bolt in each corner and fit nut from underneath. 21. Repeat this operation for bells 3 & 4. 22. The narrow platform fits between these two frames. 23. Repeat the operation for bells 5 & 6, which can be lifted straight to their final position. 24. Unattach the power supply and wrap the cables and operator out of the way so that they are not damaged by the bells. 25. If it is likely to rain, attach the tent roof. The frame is rectangular, so make sure it is the right way round. 26. If desired, attach the translucent sides of the tent. This wraps round the belfry. Otherwise attach the Charmborough Ring banners with cable ties. 27. The bells are now ready for ringing.

Appendix 1 Plan showing space needed for assembly 2400mm 270mm 1480mm 2490mm 90mm* 4030mm Overall height 4240mm (excluding timber packing/floor protection) Area on plan 4030mm x 2050mm. * If angles bolted on outside, this increases to 4210mm x 2050mm Important: These are overall dimensions of the structure and do not include working space needed for assembly. 90mm* The Charmborough Ring Overall Dimensions Revision 2 Roger Booth 13 th July 2008

Appendix 2 Towing Checklist Yes No Is lock fitted? Is safety chain attached? Is load secure? Is load spread evenly? Is cover secured? Is correct number plate fixed to trailer? Are indicator lights working? Are brake lights working Are side lights working Are tyres properly inflated and in good condition? Comments

Appendix 3 Dismantling Checklist Yes No Are bells and wheels secure on their headstocks? Are contents of toolbox correct (tools & nuts and bolts)? Is electric hoist satisfactory? Is petrol generator satisfactory? Are electric cables, plugs and sockets satisfactory? Is there fuel and oil for generator Is plywood and timber protection satisfactory? Is trailer satisfactory? Are bell ropes satisfactory? Comments/repairs needed