Navarre Beach & Dune Restoration Project Status Report to be regularly updated June 17, 2016 Report

Similar documents
The 2017 Panama City Beaches Beach Interim Renourishment Project. Answers to Common Questions

2018 Beach Preservation Project Information

Dare County Nourishment Project Town of Duck

RE: Hurricane Matthew Beach Damage Assessment and Recommendations [CSE 2416]

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update

ATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY. Contract #2 Construction Scope. April 18th-19th 2018

Effectiveness of Beach Nourishment in Response to Sea Level Rise

Shoalwater Bay Shorline Erosion Dredging

Protecting our Beaches

Beach Restoration in Okaloosa and Walton Counties. FSBPA Technology Conference Clearwater, FL

Delaware Chapter Surfrider Foundation - Indian River Inlet Monitoring

UPPER BEACH REPLENISHMENT PROJECT RELATED

Long Term Success and Future Approach of the Captiva and Sanibel Islands Beach Renourishment Program

Follets Island Nearshore Beach Nourishment Project

Figure79. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 155

Beach Nourishment Impact on Beach Safety and Surfing in the North Reach of Brevard County, Florida

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby

ST. LUCIE COUNTY, FLORIDA

ATLANTIC COUNTY 2006 to 2008

2014 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

Beach Renourishment in Jacksonville

FINDING OF NO SIGNIFICANT IMPACT

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

Assateague Island National Seashore North End Restoration Project Timeline

FINAL REPORT FOR 2013 ON THE CONDITION OF THE MUNICIPAL OCEANFRONT BEACHES THE BOROUGH OF AVALON, CAPE MAY COUNTY, NEW JERSEY

PLAQUEMINES PARISH BARRIER ISLAND RESTORATION & SUSTAINABILITY. MVD/Gulf Coast Regional Dredging Meeting November 5, 2013

23- Year Sand Volume Changes at Site 132, 15th Street, Brigantine

Town of Duck, North Carolina

ST. JOSEPH PENINSULA, GULF COUNTY, FLORIDA Beach Re-Nourishment and Environmental Enhancement Project RECOMMENDATIONS

Town of Duck, North Carolina

SPECIAL SPRING 2018 STORM REPORT ON THE CONDITION OF THE MUNICIPAL BEACHES FOR THE BOROUGH OF STONE HARBOR, CAPE MAY COUNTY, NEW JERSEY

North Shore of Long Island, Feasibility Study

2013 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

FINAL ENVIRONMENTAL IMPACT STATEMENT ON BROWARD COUNTY SHORE PROTECTION PROJECT SEGMENTS II AND III BROWARD COUNTY, FLORIDA

Chapter 11. Beach Fill and Soft Engineering Structures

New Jersey Beach Profile Network Atlantic County Profile Site Locations

Figure 262. Location map for the 10 NJBPN profile sites in Atlantic County, NJ 279

Regular Workshop October 20, 2014 Agenda Item: Dr. Albert E. Browder, PE; Olsen Associates, Inc.

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers

A REVIEW OF THE CONDITION OF THE MUNICIPAL BEACHES AS A RESULT OF HURRICANE SANDY IN THE BOROUGH OF STONE HARBOR, CAPE MAY COUNTY, NEW JERSEY

Figure 38. Locations of the 28 NJBPN profile stations in Ocean County, NJ.

Planning Considerations for Nearshore Placement of Mixed Dredged Sediments

New Jersey Coastal Zone Overview. The New Jersey Beach Profile Network (NJBPN) 3 Dimensional Assessments. Quantifying Shoreline Migration

Florida Seagrass Integrated Mapping and Monitoring Program

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

Figure 106. Locations of the 28 NJBPN profile stations in Ocean County, NJ.

FINAL REPORT FOR 2013 ON THE CONDITION OF THE MUNICIPAL BEACHES IN THE TOWNSHIP OF UPPER, CAPE MAY COUNTY, NEW JERSEY

MILE POINT TRAINING WALL JACKSONVILLE, FL. Geotextile Tube Installation

Cat Island Chain Restoration

MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP)

Living Beaches: Integrating The Ecological Function Of Beaches Into Coastal Engineering Projects and Beach Management

BEACH FILL CONSTRUCTION USING SEABED REHANDLING AREAS. Kevin R. Bodge, Ph.D., P.E. 1

County of Santa Barbara Permit Option Analysis Goleta Beach JULY 13, 2017

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION

Nome Harbor Page 2 of 12

Shoreline Studies Program, Department of Physical Sciences, VIMS

AD-A II~lllII I I 7

Reading Material. Inshore oceanography, Anikouchine and Sternberg The World Ocean, Prentice-Hall

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

Trusted Partners Delivering Value, Today and Tomorrow BUILDING STRONG

Maltester Channel Dredging. Shoreline Marina Committee. November 18, 2008

Beach, dune and development in the Borough of Mantoloking as of January Prepared for The Borough of Mantoloking: April 2, 2008

Absecon Island Shore Protection The planning behind the project

Changes in Beach Profile and Grain Size after Beach Renourishment

An Update of Coastal Erosion in Puerto Rico

Broad Beach Sand & Dune Habitat Restoration Project. Revetment Owners Meeting July 12, 2017

Performance of Upham Beach T-Groin Project and Its Impact to the Downdrift Beach

US Beach Nourishment Experience:

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

Blakely Island, N Thatcher Bay. Restoration Recommendation: Rank Score (total score)

CHAPTER 281 INFLUENCE OF NEARSHORE HARDBOTTOM ON REGIONAL SEDIMENT TRANSPORT

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

2015 ANNUAL REPORT - TO THE CITY OF NORTH WILDWOOD ON THE CONDITION OF THE CITY BEACHES

Texas passes, longshore transport, hurricanes, beach erosion and sea level

Recycling of Surplus Sand to Extend the Time Between Beach Fill Episodes

For more information or permission to reprint slides, please contact Donna Milligan at 1

La Quinta Channel Extension Port of Corpus Christi Ingleside, Texas. Mark Coyle

OCEAN COUNTY 2006 to 2008

CLAM PASS RESTORATION AND MANAGEMENT PLAN BATHYMETRIC MONITORING REPORT NO. 7 Including Interior Bay Dredge Cuts and Tidal Data

KEYNOTE PRESENTATION FSBPA olsen

Australian Coastal Councils Conference

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

Appendix E Cat Island Borrow Area Analysis

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION AND FUNCTIONAL DESIGN OF COASTAL STRUCTURES

Table 4. Volumetric Change Rates Pre-Project and Post-Project for the Town of Duck

2013 FEDERAL STORM RESPONSE

Beach Dune Performance Assessment of. New Jersey Beach Profile Network (NJBPN) Sites at. Long Beach Island, New Jersey. After Hurricane Sandy

Marine Ecosystems. Aquatic Ecosystems Section 2

APPLICATION OF SHORE PROTECTION SCHEMES IN HORNB^K Mads Peder J0rgensen ' Peer Skaarup 2 Karsten Mangor 3 J0rgen Juhl 4

ARTIFICIAL REEF CONSTRUCTION: AN ENGINEERED APPROACH. Timothy K. Blankenship, P.E. R. Harvey Sasso, P.E.

JAP Additional Information Sheet

Inlet Management Study for Pass-A-Grille and Bunces Pass, Pinellas County, Florida

FINAL REPORT FOR 2009 ON THE CONDITION OF THE MUNICIPAL OCEANFRONT BEACHES IN THE BOROUGH OF AVALON, CAPE MAY COUNTY, NEW JERSEY

Update from Port Metro Vancouver Deltaport Third Berth Project Community Liaison Group. Meeting Date: August 28, Construction Update

Figure 1. Schematic illustration of the major environments on Mustang Island.

Impact of Dredging the Lower Narrow River on Circulation and Flushing

Habitat Development: Habitat Boulders Lawson Pier Foreshore Enhancement

Climate Change Impacts to KSC Launch Complex

VIMS CCRM Coastal Management Decision Tools. Decision Tree for Undefended Shorelines and Those with Failed Structures

FINAL REPORT FOR 2011 ON THE CONDITION OF THE MUNICIPAL BEACHES IN THE CITY OF BRIGANTINE BEACH, ATLANTIC COUNTY, NEW JERSEY

Transcription:

Navarre Beach & Dune Restoration Project Status Report to be regularly updated June 17, 2016 Report Work Completed (June 11 to June 17) Weeks Marine Inc. (Contractor): o continued filling Segment 4 including restoration of dunes, o continued using Beach Access 12 to stage equipment, o removed the subline located in front of the Beach Colony, o began tilling the beach along the eastern ¾ of the project, o continued turtle relocation trawling operations, relocating a total of 209 turtles as of June 16, 2016 to a location outside of the borrow area, and o placed approximately 210,000 cubic yards (cy) of sand, (equivalent to approximately 11,700 18 cubic yard dump trucks), bringing the total to over 1.2 million cy placed since April 29. Coastal Tech G.E.C., Inc. (Engineer): o continued daily shorebird and seabird surveys including the monitoring of nests outside the construction zone, o continued with pre-fill and post-fill surveys at 100 ft intervals, o continued with field compliance observations of the Contractor and sediment compliance checks, and o continued to contact property owners whose dune overwalks may be impacted by fill placement. Work Planned (June 18 to June 24) The Contractor will: o finish filling Segment 4, likely completing beach fill and grading on Saturday June 18, o continue turtle relocation trawling while dredging, o begin to break down and move pipe out of the project area beginning on Sunday June 19, o remove the floating hose assembly from subline 2 on Sunday June 19 and remove subline 2 from the beach by Wednesday June 22, and o load trucks with equipment and transit to Pensacola Beach. The Engineer will: o continue to monitor for shorebird and seabird nesting and breeding activity, and o continue field compliance observations of the Contractor as dredging completes and demobilization begins. For live video of existing beach - see: http://www.navarrebeachlife.com/live-hd-1080-zoom-cam/ For expected schedule of beach fill placement along a specific segment of beach, see the map below. For an aerial video of the construction process - see http://www.coastaltechcorp.com/video Page 1 of 7

Beach Fill Plan - Expected Schedule Page 2 of 7

Project Facts: On December 10, 2015, the Santa Rosa County Board of County Commissioners awarded a construction contract to Weeks Marine Inc. About 1.3 million cubic yards of sand will be placed from immediately east of the Gulf Islands National Seashore to the eastern limits of the Navarre Beach Marine Park. The Project construction will: o make use of the same offshore borrow area used for the initial 2006 restoration project, o place sand that looks slightly gray when first placed, but will lighten to near white as the sand dries and is exposed to the sun as occurred in 2006, o restore the dune crest to a width of 30 feet with native dune plants, o increase the width of the beach berm by 100 to 200 feet, and o occur 24 hours per day at 7 days per week until completed. The Contractor: o estimates about 50 days of dredging and sand placement with completion by mid-june, o is using the east portion of the Pier parking lot (see Figure below) and will be using the other beach access point as the project progresses to stage land-based equipment, o will use two Trailing Suction Hopper Dredges the R.N. Weeks and the B.E. Lindholm to excavate sand from the offshore borrow area, haul the material to a pump-out station and the submerged pipeline near the beach, connect to the pipeline and begin hydraulic placement of the material onto the beach with extension of the pipeline along the beach as construction progresses. o will generally place sand from East to West along the beach averaging about 500 feet per daythe Contractor will specifically place fill in the following sequence: Segment 1 (COMPLETE) started at the landward end of Pipeline Corridor 1 then moved from West to East to the eastern limits of Segment 1 and the eastern limits of fill; Segment 2 (COMPLETE) - beginning at the landward end of Pipeline Corridor 1 then moving from East to West to the western limits of Segment 2; Segment 3 (COMPLETE) starting at the landward end of Pipeline Corridor 2 then moving from West to East to the eastern limits of Segment 3; and Segment 4 - beginning at the landward end of Pipeline Corridor 2 then moving from East to West to the western limits of Segment 4 and the western limits of fill. Following completion of sand placement in Navarre Beach, the Contractor has also indicated his intent to use the same two dredges to construct the Pensacola Beach project. As required by the permits, seabird and shorebird monitoring began on March 31, 2016 and turtle monitoring began on May 1, 2016 coinciding with the start of Marine Turtle Nesting Season. Turtle trawlers are operating in the borrow area and have relocated 154 turtles as of June 1, 2016. Per the Technical Specifications, permits, and customary construction practices: o At any time during construction, up to a 1,000-foot long area of beach (around the pipeline discharge) will not be open to the public. For security, this area will be marked and fenced. Beaches east and west of the pipeline discharge will be open to the public. Sand ramps will be placed over the pipeline to allow beachgoers access to the Gulf. o Dredging operations will produce turbidity (cloudiness) in the water. Turbidity levels will be closely monitored and if levels get too high, construction will be temporarily suspended and modified to meet permitted levels. The proposed Local Funding Plan includes federal funding from the Federal Emergency Management Agency and state funding from the Florida Department of Environmental Protection. The balance of project funding will come from local sources, including the Santa Rosa County Tourist Development Council, Santa Rosa County, and a municipal services benefit unit (MSBU) by Navarre Beach Leaseholders. The County has fronted the MSBU share of costs to be subsequently repaid to the County via the MSBU. The Santa Rosa County Commission is expected to consider the proposed Local Funding Plan and MSBU for adoption in August 2016. Page 3 of 7

For Questions, please contact: Name Title Affiliation Phone Number Email Address Andrew Condon Michael Walther Roger Blaylock Engineer-of-Record Construction Engineer-of-Record Design County Engineer Frequently Asked Questions: Coastal Tech G.E.C., Inc. (321) 751-1135 acondon@coastaltechcorp.com Coastal Tech G.E.C., Inc. (772) 559-2493 mwalther@coastaltechcorp.com Santa Rosa County (850) 981-7100 RogerB@santarosa.fl.gov 1. What is the approximate number of dump trucks in comparison of each dredge's delivery of sand and for the total project? Answer: Each dredge load delivers about 140 dump truck loads (assuming an 18 cubic yard dump truck). The entire project volume is estimated at 1.3 million cubic yards which equates to approximately 72,200 dump truck loads (assuming an 18 cubic yard dump truck). 2. How many approximate sand trip deliveries for each dredge in a 24 hour period to the beach? Answer: Each dredge has been completing 6 to 8 round trips within a 24 hour period. 3. What is the approximate time for each dredge to complete a cycle collecting sand from the borrow area, returning to the beach, distributing the sand onto the beach, and returning back to the borrow area? Answer: The approximate cycle time for a dredge to fill its hopper at the borrow area, transit to the beach, discharge onto the beach, and then return to the borrow area has been 3 to 4 hours. 4. Will vegetation be added to the areas where sand is added to the berm? Answer: Vegetation will be added to the dune (not the beach berm) where the dune is being reconstructed. 5. Is it safe to assume the 24/7 work schedule will create a less than desirable sleeping environment in beachfront residences? Answer: The Contractor is to use the minimum lighting that is necessary and complies with OSHA standards. Nighttime work may be loud enough to be disruptive when directly in front of a property. As the Contractor is expected to move equipment along the beach to construct about 500 feet of beach each day, noise disruption in front of a particular property is expected to be limited to one night. Sleeping with closed windows should substantially diminish any noise during the night. 6. How far in advance of beach closing at my property will I be able to know exactly when it will happen? Answer: The fact sheet will be updated weekly so everyone is aware of what work is expected in the next week. You should have at least a week s notice. 7. How will the construction be sequenced and what is the general process, both for the dredges and for the shore equipment? Answer: As described in the Project Facts, the Contractor will generally place sand in four segments from East to West along the beach; the Contractor will specifically place fill in the following sequence: Segment 1 (COMPLETE) started at the landward end of Pipeline Corridor 1 then moved from West to East to the eastern limits of Segment 1 and the eastern limits of fill; Segment 2 (COMPLETE) - beginning at the landward end of Pipeline Corridor 1 then moving from East to West to the western limits of Segment 2; Page 4 of 7

Segment 3 (COMPLETE) starting at the landward end of Pipeline Corridor 2 then moving from West to East to the eastern limits of Segment 3; and Segment 4 - beginning at the landward end of Pipeline Corridor 2 then moving from East to West to the western limits of Segment 4 and the western limits of fill. The two dredges work in an alternating sequence on the same pipeline. While one dredge is unloading fill at the shoreline, the other dredges material from the borrow area 4 miles away. They then switch, providing a quick succession for unloading material onto the beach. As the material is pumped onto the beach, the Contractor will add shore pipe (40-foot lengths of pipe) to extend the pipe discharge point along the beach to fill each segment as described above. 8. Will the Pier parking lot remain open? Answer: Now that Segments 1 and 2 are completed, the pier parking lot is back open. 9. Why was the nearshore water east of the pier pink on May 4 th? Answer: Per the Contractor, the pink water was the result of a velocity test to calibrate their equipment on the dredge. The test used a non-toxic pink dye which was inserted into the pipeline at the dredge. Then, the amount of time for the dye to reach the beach was measured. Per the Contractor, the test was completed in accordance with industry standards and will not likely be needed again during this project. 10. Who is Harriet the turtle? Answer: Harriet was named by workers at the Gulfarium after she was brought there for rehabilitation. She was captured by turtle trawlers on May 9 and found by the endangered species observer to be lethargic, emaciated, and had much of her body covered in algae and barnacles. She was brought to the Gulfarium s Sea Turtle C.A.R.E. Program in Fort Walton Beach for rehabilitation. Allen McDowell, curator of fish and invertebrates reports she is doing well and responding to treatment. She started eating on her own, which is a big milestone for her recovery. Turtle trawling is a common practice associated with hopper dredging operations, such as the Navarre Beach renourishment. Turtle trawling is conducted by dragging nets within the dredging area only. Any captured sea turtles are relocated further offshore to keep them away from potential harm. Harriet when found by turtle trawler Harriet swimming at the Gulfarium Page 5 of 7

11. It appeared that sand was lost due to Tropical Storm Colin and the shape of the beach changed. What happened? Answer: With the elevated water level and flooded beach associated with the passage of Tropical Storm Colin, it appeared that much sand had been lost from the beach, but most, if not all of the placed sand remains as appears evident now with more normal water levels. The sand was placed in a construction template that is expected to shift and equilibrate into a more natural beach profile over time. The equilibration happens rapidly at first then slowly evolves over time. Based on monitoring of the 2006 Project within the first year the Mean High Water Line (Shoreline) migrated landward about 20 feet on average. During the monitoring period of 2006 to 2014 the Mean High Water Line migrated 55 feet on average throughout the project. The same monitoring data indicate that within the nearshore system (out to 18 feet water depth) only about 1.2% of the placed sand had been lost since 2006. This indicates that while the sand shifts and moves, nearly all of it remains in the system and provides upland protection and associated storm damage reduction. As part of the permit required monitoring, surveys will be performed after construction is completed to document the constructed beach and assess any actual losses. 12. How do they bring the sand to the shore? Answer: The Contractor has been using two hopper dredges to remove sand from the offshore borrow area and transport the sand to a nearshore pump-out station from where the sand is pumped through a pipeline to the beach. 13. Why are there no signs posted? Answer: A project sign is posted by the Navarre Beach Pier. 14. Are they taking sand away from the shore? Answer: No, the Contractor is placing sand to extend the beach. 15. Is it making the water shallower? Answer: Immediately following construction the nearshore water will likely be shallower. Over time, as the constructed template adjusts to wave conditions and equilibrates to the natural profile, water depths will be similar to how they were before construction. 16. Where is the best spot to get the most shells? Answer: Some shells are deposited within the beach fill, but it appears the best spot for shelling is along the water s edge where the shells are flushed out by the wave action and most easily collected. 17. When will they be finished? Answer: The current estimate is for the Contractor to complete dredging operations around June 20 th and to completely demobilize all dredging equipment prior to July 4. Dune planting will be done in mid-july. 18. Are they still on schedule due to the storms? Answer: Yes, they are mostly on schedule in spite of some weather delays; dredging is still expected to be completed by mid-june. The Contractor generally operates 24/7 rain or shine, but even moderate waves can impeded dredging operations. TS Colin led to a brief delay due to wave heights that made it unsafe to operate the dredges, but only a few weather delays have been encountered since construction began. 19. How deep is it where they are dredging? Page 6 of 7

Answer: Natural water depths in the borrow area average 70 feet. The Contractor is permitted to dredge to depth of about 78 feet. 20. Is this hurting the environment? Answer: There are temporary adverse impacts upon the environment during construction associated with equipment operations and turbidity. Environmental impacts to shorebirds, marine turtles and turbidity are closely monitored particularly during construction. Trawlers almost continuously sweep the borrow area to capture and relocate turtles from the borrow area to avoid adverse impacts to turtles by the hopper dredges. Turtle and shorebird monitors check conditions along the beach each morning to ensure no birds or turtle nests are endangered by construction operations. Turbidity is monitored near the beach and in the borrow area to ensure that levels remain within State water quality standards. When completed, the restored beach will provide enhanced habitat for shorebird and turtle nesting. 21. Is it possible they could finish sooner than mid-june? Answer: June 20 th is the current target date for completion of dredging operations. 22. How often does Navarre Beach do this process? Answer: The initial restoration of Navarre Beach occurred in 2006. This 2016 Project is the first beach nourishment since 2006. It is likely depending on weather conditions that the next nourishment event may become warranted in 8 to 10 years. 23. Why are the seagulls flocking towards the pipes as the water is gushing from it? Is it because they are feeding off small fish? Answer: The discharge pipe pushes out a slurry of dredged material (mostly sand) and water. Within the slurry is a small amount of marine invertebrates that the birds feed on. 24. When will the rebuilt dune be planted? Answer: The rebuilt dune will be planted with native vegetation by Aquatic Plants of Florida beginning on or around July 11. Page 7 of 7