ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND TMACOG TRANSPORTATION SUMMIT MARCH 16, 2018 Mike Gramza, District Two, Capital Programs Administrator John R. Kasich, Governor Jerry Wray, ODOT Director Patrick McColley, ODOT Deputy Director
I-75 RECONSTRUCTION NORTHWEST OHIO Proj. Sale Date Compl. Date Cost A Dec 2014 Oct 2017 $70,000,000 B Nov 2014 Oct 2018 $134,210,000 C May 2014 Oct 2016 $33,500,000 D May 2018 Spring 2022 $150,000,000 E Feb 2019 Fall 2022 $185,000,000 F May 2014 Aug 2017 $71,500,000 G April 2014 Nov 2016 $74,200,000 H April 2014 Aug 2016 $57,200,000 I Feb 2014 June 2017 $72,800,000 J Feb 2017 Aug 2020 $114,117,000 Total $962,527,000 2
RECAP 2017 MAJOR CONSTRUCTION PROJECTS 3
I-75 WIDENING: SR582 TO I-475 Cost: $71.5M Completion: spring 2018 Contractor: ES Wagner Designer: ODOT, TetraTech, DGL, Baker 4
I-75 WIDENING: SR582 TO I-475 5
I-75 WIDENING: SR582 TO I-475 6
SR 25 OVER I-475 PERRYSBURG Cost: $8.8M Completion: spring 2018 Contractor: ES Wagner Designer: DGL 7
SR 25 OVER I-475 PERRYSBURG 8
ANTHONY WAYNE BRIDGE PAINTING Cost: $12.6M Completion: spring 2018 Contractor: UCL Inc. Designer: Arcadis 9
PHASE 2: BRIDGE PAINTING 10
PHASE 2: BRIDGE PAINTING 11
HEN-109 MAUMEE RIVER BRIDGE Cost: $12M Bridge Opened: June 9, 2017 Contractor: Miller Bros. Designer: EL Robinson 12
HEN-109 MAUMEE RIVER BRIDGE 13
HEN-109 MAUMEE RIVER BRIDGE 14
I-75 LAGRANGE TO I-280 Cost: $70M Completion: fall 2017 Contractor: Kokosing Designer: HDR 15
I-75 LAGRANGE TO I-280 16
I-75 LAGRANGE TO I-280 17
CURRENT MAJOR CONSTRUCTION PROJECTS 18
HAN-75 FINDLAY WIDENING Cost: $113M Completion: fall 2020 Contractor: Beaver Designer: WSP 19
HAN-75 FINDLAY WIDENING 20
HAN-75 FINDLAY WIDENING New fly over ramp (SB I-75 to US68) opens mid summer US68 to SB I-75 closes mid summer NB US224 Ramps will close late spring/early summer for reconstruction NB SR12 ramps will close this summer for reconstruction 21
LUC-75/475 Cost: $134M Completion: October 31, 2018 Contractor: Kokosing Designer: B&N, Mannik, TetraTech 22
LUC-75/475 23
LUC-75/475 24
LUC-75/475 Status of major work items 3 spans of Berdan SB deck to be poured-estimated to open to traffic by July 2018 New SB I-75 to WB I-475 ramp to be complete by Aug 2018 New EB I-475 to NB I-75 will be complete in Sept 2018 Berdan and Haverhill, Phillips and Manhattan, Willys parkway roundabouts to be completed yet 25
LUC-75/475 2018 MOT impacts Phillips to SB I-75 closed All Jeep Parkway ramps except the NB I-75 exit are closed Berdan & Haverhill closed 60 days (May-July) Haverhill closed 60 days (July-Sept) Manhattan & Phillips closed 60 days (June-Aug) Traffic shifts to move into final configuration 26
WATERVILLE BRIDGE Cost: $13.4M Completion: September 30, 2020 Contractor: Miller Bros Const. Designer: Mannik & Smith 27
WATERVILLE BRIDGE 28
WATERVILLE BRIDGE 29
WATERVILLE BRIDGE 2018 MOT impacts 45 day closure of SR64 and SR65 to construct the roundabout Scheduled for summer 2018 when school is out between June 1 and Aug. 15 (dates TBD) 30
WATERVILLE BRIDGE 31
WATERVILLE BRIDGE 32
PORT CLINTON LIFT BRIDGE Cost: $13M Completion: May 24, 2018 Contractor: Ruhlin/Perram Designer: Hardesty and Hanover End River closure: April 1, 2018 End Road closure: May 24, 2018 33
PORT CLINTON LIFT BRIDGE 34
PORT CLINTON LIFT BRIDGE 35
LUC-75 INDIANA AVE Cost: $5M Completion: May 31, 2019 Contractor: Kokosing Designer: WSP 36
LUC-75 INDIANA AVE 2018 MOT impacts Washington St. ramp from SB I-75 is reduced to one lane Indiana Ave. will close around Aug 1, 2018 37
TRANSPORTATION SUMMIT 2018 Chris Matta Deputy Chief Engineer Ohio Turnpike and Infrastructure Commission Friday, March 16, 2018
3 rd Lane Construction 1996 2002 Service Plaza Reconstruction 1998 2000, 03, 10, 11 E ZPass 2009 Pavement Replacement 2011 2041
$250,000,000 $225,000,000 $200,000,000 $175,000,000 $150,000,000 $125,000,000 $100,000,000 $75,000,000 $50,000,000 $25,000,000 $0
Bridge Painting Program Project No. 40 18 01 MP 21.4 Williams County MP 24.7, 36.3, 37.1, 38.3, 39.3 Fulton County OZEU Paint System Bridge Painting Program Project No. 40 18 02 MP 94.7, 97.6, 98.1, 100.2, 104.3 Sandusky County MP 106.1, 107.5 Erie County OZEU Paint System Bridge Rehabilitation Program Project No. 43 18 02 MP 59.0 Lucas County MP 84.4 Sandusky County Bridge Replacement / Deck Replacement
Mainline Pavement Reconstruction Project No. 39 18 01 Milepost 149.2 154.1 Lorain & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Construction: April 2018 November 2020 Mainline Pavement Resurfacing Project No. 59 18 01 Milepost 127.2 136.2 Erie & Lorain Counties Resurfacing of all 3 East & Westbound lanes Construction: April 2018 October 2018 Mainline Pavement Reconstruction Project No. 39 18 02 Milepost 169.7 176.3 Summit & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Interchange 173 Repairs and Reconstruction Construction: April 2018 November 2020 *All 2018 Mainline Pavement Reconstruction will take place in the Eastbound direction.
2019 & Beyond Toll Collection System Modifications
Legal & Policy 241 Miles 160 Miles of 3 Lanes 8 Long Combination Vehicle Lots (28.4 Total Acres) 7 Sets of Service Plazas (1,412 Commercial Parking Spaces) 241 Miles of Fiber 6 Pavement Markings 55 Emergency Pull Off Areas
15 Roadside Units
This Tech will Immediately Improve Our Efficiency Provide a Significant Opportunity for Savings of Labor and Materials
Thank You Follow us on @OhioTurnpike TRANSPORTATION www.ohioturnpike.org SUMMIT 2018
2018 MAJOR CONSTRUCTION PROJECTS 53
LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD Cost: $9.5M Bid Opening: March 2018 Completion: Fall 2019 Designer: Mannik & Smith 54
LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 55
LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 56
LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 2018 MOT impacts AWT will be down to 1 lane inbound and 2 lanes outbound for entire 2018 season (starting about May 1) 57
LUC-75 SOUTH AVE. TO DORR ST. Cost: $150M Bid Opening: May 2018 Completion: summer 2022 Designer: WSP 58
LUC-75 SOUTH AVE. TO DORR ST. 2018 MOT impacts Dorr St. Bridge closes for 300 days (late summer/early fall) Weiler Ave closes for storm sewer Installation for approx. 2 weeks (late summer) SR-25 Ramp C (SB I-75 to Outbound AW Trail) closes for 2 Weeks for Storm Sewer installation (summer) 59
PHASE 3: LIGHTING AND DEHUMIDIFICATION Cost: $13M Bid Opening: June 2018 Completion: summer 2020 Designer: Arcadis 60
DEHUMIDIFICATION 61
PHASE 3: LIGHTING AND DEHUMIDIFICATION 62
DEHUMIDIFICATION EXTERIOR WRAP 63
DEHUMIDIFICATION BUILDING RENDERING 64
DECORATIVE LIGHTING Tower Cable Deck Edge 65
TOP OF TOWER Historic housing to remain Replace internal HPS lamps with custom LED light source 66
EXISTING LIGHTING SYSTEM 67
LED LIGHTING 68
WOOSTER STREET INTERCHANGE AT I-75 69
WOOSTER STREET INTERCHANGE AT I-75 70
2018 ODOT AWARDED PROJECTS 2018 (9-1-17 to 8-31-18 ODOT Awarded Projects) 50 ODOT LET Projects for a total of $251M 71
Anthony Wayne Trail Gateway Erie Street to I 75 Cost: $4.5 m Roadway Construction completed 2017
Anthony Wayne Trail Gateway Erie Street to I 75
Anthony Wayne Trail Gateway Erie Street to I 75 Streetscape/Landscape elements complete Fall 2018
Bancroft Street Westwood to Parkside east end road diet 3 lanes & bike lanes completed 2017 Westwood to Perth Perth to Parkside
Bancroft Street Secor to Westwood west end 5 lanes, median islands at UT & bike lanes construction 2018 Secor to Campus UT Area University HIlls- to Westood
Overland Industrial Park Connector Phillips to Willys Parkway Redevelop connecting corridor reconstruct Berdan & Jeep Parkway 5 roundabouts, bike path complete Fall 2018 A NEW CORRIDOR TO SUPPORT REDEVELOPMENT
North and South Expressway Drives Lagrange to Stickney Finish Polish Village interchange roads & bike path $3.2 m. Fall 2018
AWT Reconstruction Plan Downtown to Maumee Phase 1 South to CBD, reconstruct with committed projects by 2022 Phase 2 Glendale to South, resurface 2018 Phase 3 Detroit to Glendale, reconstruct/narrow, partially programmed 2021 2022
Front/Millard from I 280 to Tiffin Avenue (related to new Cliffs Furnace) $5.7 m. Toledo Port Partnership Begin Fall 2018 complete 2019
Downtown Toledo Resurfacing/Utility Improvements Toledo Waterways Initiative CSO elimination and Monroe/Summit/Erie/Michigan Resurface
Overland Trail (OV) and Chessie Circle (CC) UT to Bowman Park and Stickney (Bike) 2018 OV Project 1 S. Cove to Jeep Parkway OV Project 2 Bancroft to Monroe cc Project 3 Connector Bancroft to Chessie Corridor 2021 CC North Paved Path Bowman Park to Bancroft (UT)
Major 2019 Committed Projects Detroit Avenue Byrne to Copland, full reconstruct, roundabout at Byrne, bike lanes $3.5 m. Complete Fall 2019 South Avenue Reynolds to Byrne, full reconstruct, roundabout at Wenz, bike lanes $5.3 m. Complete Fall 2019 Monroe Street Talmadge to Secor, reconstruct/realign mall entrances/resurface $3.2 m. Complete Fall 2019 Heatherdowns/Perrysburg Holland/Garden Road intersection, reconstruct $3.6 m. Complete Fall 2019
Cherry St Transit Hub Goodwill Building
Downtown Toledo Bike Share 18 Stations near hubs of activity within a 2 mile radius downtown 100 bikes / 150 rack-capacity Smart Bike Technology Launch as early as July 31, 2018
UPCOMING MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING SECURED 86
WOO/LUC-75 GLENWOOD TO SOUTH Cost: $185M Bid Opening: Feb 2019 Completion: fall 2022 Designer: AECOM 87
LUC-475 WIDENING SR2 TO US20 88
TRAC 89
TRAC ADDITIONS TIER 1 90
I-475 DORR ST. INTERCHANGE Cost: $41M Bid Opening: spring 2020 Completion: summer 2021 Designer: TetraTech, Mannik,DGL 91
DORR ST AND MCCORD ROUNDABOUT 92
FUTURE MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING NOT SECURED 93
LUC-20A INTERCHANGE & I-475 WIDENING Cost: $28M US 20A $64M I-475 Bid Opening: unknown Completion: Bid opening + 2 Designer: Arcadis 94
LUC-20A INTERCHANGE 95
WHERE IS ODOT HEADING IN THE FUTURE? 96
The Future of Smart Mobility will continuously Drive Ohio s preparation and leadership for the future of transportation technology Governor Kasich signs the Executive Order establishing DriveOhio as the statewide center for smart mobility Executive Director Jim Barna
WORKING GROUPS/FOCUS AREAS Data Analytics and Security Infrastructure Telecommunications/Right-of-Way Vehicle Deployment Budget/Partnerships Communications Policy/Regulatory Education & Workforce Development
SMART MOBILITY IN OHIO: HAPPENING NOW
INITIATIVES o US 33 Smart Mobility Corridor o Interstate 90 Lake Effect Corridor o Interstate 670 Smart lane o Interstate 80 - Ohio Turnpike o Connected Marysville o Smart Columbus
REAL-TIME TRAFFIC MANAGEMENT o Planning and Asset Management o Predictive Traffic Analytics o Hard Shoulder Running o Traffic Re-routing o Emergency Response o Wrong-way Warning/Avoidance o Adverse Weather/Road Conditions o Enhanced Traveler Information o Just-in-time Delivery/Commuter Commercial Truck Parking Availability o Work Zone Identification