Chapter 4 Route Window C3 Hyde Park and Park Lane shafts. Transport for London

Similar documents
72 Crossrail Amendment of Provisions

Chapter 17 Principal findings and conclusions Central route section

Roads and public rights of way

SLOUGH Stage 3 Road Safety Audit of A4 London Road, M4 J5 to Sutton Lane

Design and Installation of Low Level Cycle Signals

CHECKLIST 2: PRELIMINARY DESIGN STAGE AUDIT

Commonwealth Heads of Government Meeting: London 2018

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

Appendix A Type of Traffic Calming Measures Engineering Solutions

Have your say on the transformation of Oxford Street West

MUTCD Part 6G: Type of Temporary Traffic Control Zone Activities

Traffic Sensitive Streets. Guidance Notes. GeoPlace Streets Team. Traffic Sensitive Streets. Guidance Note Page 1 of 7.

Amendments to Essex Highway Maintenance Strategy Maintenance Policy and Standards April 2008

4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL

Frascati Road and Temple Hill Route Improvements. Outline Design Report to Accompany Public consultation

4. Guided Bus Explained

SCHEME DESIGN AND ENGINEERING

Appendix 12 Parking on footways and verges

Traffic Calming Regulations

M6 J7 Rushall Canal: Essential Repair Work Briefing

Appendix FRANCE Annecy Tunnel Courier

(HIGHWAY GEOMETRIC DESIGN -1)

IMPROVEMENT OPTIONS REPORT - WONERSH VILLAGE. for WONERSH PARISH COUNCIL. March V3.0 stilwell-ltd.co.uk

1 VicRoads Access Management Policies May 2006 Ver VicRoads Access Management Policies May 2006 Version 1.02

A27 East of Lewes improvement scheme Have your say

The existing site constraints which may be encountered for the A428 scheme proposals are divided into sections as follows.

TS 109 DURHAM ROAD QTC PHASE 4 PROJECT PROPOSAL. Page 1

Chelmsford City Growth Package

North West Non-Technical Summary of the Transport Assessment September 2011

M6 Junction 10 Public Consultation

APPENDIX E: Transportation Technical Report

Chapter 7 - Rural Roads

Oxford Street West. 21 December

Hospital Link Project Project Update September 2017

AT403.1 Ancient monument Note 3 amended P500 Basic triangle New size 1800mm added

Guide to the Cycle Enfield Public Consultation on Enfield Town. Produced by the Save Our Enfield Town Campaign Group

Essential Standard No. 16. Streetworks - Short duration static works carried out from a vehicle

Our Approach to Managing Level Crossing Safety Our Policy

MILTON ROAD ~ MITCHAM'S CORNER PARAMICS MODEL INITIAL OPTION TESTING

EXECUTIVE SUMMARY Callan Park accommodates travel from a wide range of transport modes, including walking, cycling, bus and light rail.

Drawing 5269/GA01: A2/A28 Coast bound off-slip - Wincheap Scheme

Design Workshops Summary of all Feedback January 2017

7.3 Traffic and Transport Impacts 15/10/2014

A52. Nottingham Junctions. Construction at Nottingham Road and Cropwell Road junctions commencing early January 2017

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY

3 TRAFFIC CONTROL SIGNAL TIMING AND SYNCHRONIZATION

CROSSRAIL INFORMATION PAPER A4 VENTILATION AND INTERVENTION SHAFTS

Improving the A1 in Northumberland Public consultation. November December North of Ellingham

Collision Site Investigation - Bodenham By-Pass Background

Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering. Minnesota Department of Transportation (the Department)

How do we design for pedestrians? Case study: transforming the Walworth Road

The Wincheap Society

PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT

Ministry of Education Flat Bush School Notice of Requirement. Integrated Transportation Assessment Report. February 2016

MILTON ROAD LLF PROJECT UPDATE

Pedestrians safety. ROAD SAFETY SEMINAR PIARC/AGEPAR/GRSP Lome, Togo October 2006 Lise Fournier, Canada-Qu

Frequently asked questions (FAQ) about a borough-wide 20 mph speed limit

Nottingham Cycle City Frequently Asked Questions

Tonight is for you. Learn everything you can. Share all your ideas.

Giles Run Connector Road

A5.1 Permitted activities

5 Highways and Transport Assessment

PROPOSED RESIDENTIAL SUBDIVISION

The Consultation has now ended.

Cabinet Member for Highways & Streetscene. Highway Infrastructure Manager

NORTH TURNAROUND. Recommended Design: Expand the existing transit terminal

Hospital Link Project Project Update November 2017

1 This technical note considers the issues associated with the use of tidal flow bus lanes on key public transport corridors in Cambridge.

Traffic calming regulations (Scotland)

Progress update on the Sustainable Movement Corridor scheme Guildford Borough Council, June 2016

I3.0 DESIGN GUIDANCE. PART THREE: Design Guidance

6.0 PEDESTRIAN AND BICYCLE FACILITIES 6.1 INTRODUCTION 6.2 BICYCLE DEMAND AND SUITABILITY Bicycle Demand

Potential Bicycle Facility on Bayou Street Mobile, Alabama

ROAD SIGNS IN THE CZECH REPUBLIC.

Welcome. Knutsford to Bowdon Improvement. Start of works exhibition November An executive agency of the Department for Transport

CITY OF VANCOUVER ADMINISTRATIVE REPORT

TRAVEL GUIDE /1 2017/18

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm

Intersection Safety 6/7/2015 INTERSECTIONS. Five basic elements should be considered in intersection design. Intersection Safety (continued)

1.5 On this basis it is fundamental that the Transport Strategy for the site focuses on the following key criteria,

Frequently Asked Questions (FAQ)

Traffic signs used, including signs giving orders, warning signs, direction signs, information signs and road works signs.

A plan for improved motor vehicle access on Railroad Avenue in Provincetown

Appendix FRANCE Lyon Croix-Rousse Tunnel

PAGHAM NEIGHBOURHOOD PLAN INFRASTRUCTURE GROUP

March Maidstone Integrated Transport Strategy Boxley Parish Council Briefing Note. Context. Author: Parish Clerk 2 March 2016

Replacement of N. Carlin Springs Road Bridge over George Mason Dr.

Entry Treatments. Traffic Advisory Leaflet 2/94 August Introduction. Design. Vertical Deflections. Locations

CHAPTER 3. Transportation and Circulation

Attachment A: Traffic Mitigation Measures

TRAFFIC SIGNAL WARRANT STUDY

MOBILITY CHALLENGES IN HILL CITIES

Kings Road, Herne Bay: Proposed Crash Remedial Measure

Introduction Methodology Study area and data collection Results and recommendation Conclusion References

Statement of Evidence of Judith Makinson

Report to Cabinet. 18 May 2016

Commonwealth Heads of Government Meeting: London 2018

TGSI Tactile Ground Surface Indicators

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

Transcription:

Chapter 4 Route Window C3 Hyde Park and Park Lane shafts Transport for London

HYDE PARK AND PARK LANE SHAFTS 4 Route Window C3 Hyde Park and Park Lane shafts Introduction 4.1 In this route window, which lies entirely within the City of Westminster, Crossrail s twin bored tunnels will pass between Lancaster Gate in the west and Park Street in the east, running just south of Bayswater Road and Oxford Street. The permanent works will consist of: twin bored running tunnels; a shaft at Hyde Park; and a shaft at Park Lane. 4.2 The construction of the Hyde Park shaft will take up to four years and the Park Lane shaft 3 years and 10 months. There will be two worksites in this route window: Hyde Park Worksite In the park on a large section of the North Carriage Drive. It will be used for constructing the Hyde Park shaft. Park Lane Worksite On the central reservation of Park Lane between Cumberland Gate and Brook Gate. It will be used for constructing the Park Lane shaft. 4.3 The maps provided at the end of this chapter present the main features of the route window and the assessed construction lorry routes. Baseline conditions Transport for London 4.4 Hyde Park and residential properties to the north of Bayswater Road dominate land uses within this part of London. There are various commercial land uses on the north side of Oxford Street and residential areas to the east of Park Lane. The alignment runs through the Royal Park and Mayfair Conservation Areas. The Crossrail tunnels pass under Grade II listed buildings on Bayswater Road and Park Lane. 4.5 The Hyde Park Worksite is just inside the northern boundary of Hyde Park, a large Royal Park. The Park Lane Worksite is situated on a large central reserve on Park Lane. 4.6 Hyde Park is bounded by busy, important roads and the adjacent properties are large commercial and residential properties, some of which are listed. Park Lane forms part of the Transport for London Road Network (TLRN) and is the western boundary road of the Congestion Charging Scheme, which currently operates in central London between 0700 and 1830 hours, Monday to Friday (excluding public holidays). Bayswater Road on the north side of the park is an important road access to central London. North Carriage Drive and West Carriage Drive are private park roads, but are used by through traffic, although commercial vehicles are banned. They are open from 0500 until 2400 hours. 4.7 The area has excellent transport facilities, including Underground stations close to the worksites at Marble Arch and Lancaster Gate and numerous bus routes along both Bayswater Road and Park Lane. Park Lane also contains major pick-up and set-down points for the tour bus circuit. Bayswater Road is a well used bus corridor that has a bus lane on the eastbound carriageway. 4.8 There are parking restrictions along all roads surrounding the two worksites. There is pay and display parking off West Carriage Drive and a 679 space car park under Hyde Park, with access points off Park Lane. The car park also operates a park and ride service to Bond Street and Oxford Street. 4.9 Hyde Park contains a network of cycle routes, including part of the London Cycle Network, and equestrian bridleways. In total Hyde Park contains over five miles of bridleways. The main stables operate from 0715 to 1700 hours, Monday to Friday, and from 0830 to 1600 hours at weekends. 4.10 Hyde Park also contains a network of footpaths and pedestrian access can be gained by a series of gates on the perimeter of the park. The northern edge of Hyde Park contains four pedestrian access points Victoria Gate, Clarendon Gate, Albion Gate and Stanhope Place Gate. Hyde Park is open between 0500 and 2400 hours all year round. 4.11 Pedestrian subways are provided under Park Lane and Marble Arch. There are 14 entrance/exit points over two separate systems. The system at Marble Arch also provides access to the Underground station. 4.12 The main roads, including Bayswater Road and Park Lane, are heavily trafficked, resulting in high noise levels and poor air quality. The permanent works Running tunnels 4.13 Two 6 m diameter running tunnels will descend to a depth of 34 m at Hyde Park shaft. From here they will climb to a depth of 27 28 m below street level at Park Lane shaft. C3 page 3

ROUTE WINDOW C3 Hyde Park shaft 4.14 To comply with HMRI requirements, Crossrail will construct two shafts between Paddington and Bond Street stations. One facility is needed in the Hyde Park/Sussex Gardens area, which is 660 m from Paddington station. 4.15 A ventilation and emergency intervention shaft will be constructed on the northern boundary of Hyde Park, in the vicinity of Victoria and Clarendon Gates. A ventilation terminal building of 2 m in height will be constructed immediately west of Victoria Lodge and next to the Pet Cemetery. A basement structure of approximately 15 m by 10 m in area by 12 m deep will contain service equipment. From this point, a horizontal tunnel of between 8 and 13 m width will run eastwards to the shaft itself, located under North Carriage Drive. The vertical shaft to the running tunnels will be 13 m in internal diameter. Two permanent access points to mechanical and electrical equipment and the ventilation fans will be constructed in the vicinity of the shaft. 4.16 The Hyde Park vent shaft provides emergency access and mechanical ventilation to the tunnels between Paddington station and Park Lane shaft. The main shaft is to be sunk between the Crossrail tunnels where they pass beneath North Carriage Drive. However the permanent outlet will be a small structure above the ground so it cannot be in this location. For aesthetic reasons, it is to be sited some 220 m away in an existing shrubbery next to the pet cemetery to the west of Victoria Gate. The connection from the deep shaft to the outlet is to be by a large box tunnel beneath the surface. Park Lane shaft 4.17 The other shaft is required in the Park Lane area because the tunnelled distance between Bond Street station and the Hyde Park shaft will be over 1500 m. 4.18 A ventilation and emergency intervention shaft will be constructed within the central reservation of Park Lane immediately south of Marble Arch and opposite Green Street. A ventilation terminal of 7.5 m diameter and 2.1 m height will be constructed, with equipment rooms provided in a concrete box below. The vertical shaft to the running tunnels will have an internal diameter of 12.5 m. An access stair to the surface will be provided. 4.19 The Park Lane shaft mechanically ventilates the tunnels between Hyde Park shaft and Bond Street station. It also provides emergency access to the Crossrail Tunnels. Temporary impacts and mitigation Worksite assessment (group 1) Hyde Park worksite 4.20 The Hyde Park worksite and lorry holding area will be sited on a large section of North Carriage Drive (which will be closed for the duration of the works), including the footways and part of the equestrian bridleways. (See fig. 4.1.) The flow in North Carriage Drive is comparatively small and the road is often closed to through traffic while park events are under construction and in progress. The alternative route for traffic displaced from North Carriage Drive is Bayswater Road. Figure 4.1 North Carriage Drive 4.21 Access to and exit from the underground car park will not be directly affected but drivers will only be able to reach them from Marble Arch. 4.22 Alternative facilities for pedestrians, cyclists and horse riders will be provided immediately to the south of the worksite. The worksite will not encroach on the pedestrian and horse riders links to Clarendon Gate. 4.23 The junction of West Carriage Drive and North Carriage Drive will be severely affected by the works, as the cut and cover tunnel is built beneath it. Vehicular and pedestrian access from Victoria Gate to West Carriage Drive will be maintained during construction, for part of the time on a temporary diversion. 4.24 The works will be carried out in two main stages and a final fitting out stage. The boundaries of the worksite will be changed for each of these. Stage 1 (Duration 8 months) West Carriage Drive (The Ring) will remain on its original alignment (but will be reduced in width and the footway will be removed from the eastern side) while works are undertaken to the east of that road. These works will include the construction of the ventilation tunnel under the area to be subsequently used for a temporary realignment of West Carriage Drive. Stage 2 (Duration 15 months) During this stage West Carriage Drive will be temporarily realigned through the worksite as shown on the plan. A narrow footway is proposed for both sides of the road. Works will continue to the east of the realigned road and will be started to the west. Stage 3 (Duration 25 months) During this final stage fitting out work will be completed. The worksite will be reduced to two smaller areas. One will cover the area immediately around the ventilation outlet west of Victoria Gate and the other will cover the area on C3 page 4

HYDE PARK AND PARK LANE SHAFTS top of the main vertical shaft under North Carriage Drive. This road will remain closed but West Carriage Drive will be restored to its permanent alignment 4.25 All worksite boundaries and realigned routes will avoid important trees wherever possible, but the size of the site means that many smaller trees will be lost. These will be replaced. 4.26 The impact on traffic at each stage has been modelled using TRANSYT and LINSIG; the modelling and this has shown that the reduction in width of West Carriage Drive during the two main stages will cause additional delay for traffic at busy periods. This will be a significant impact. The distribution of the delay between the roads that meet at the Victoria Gate junction depends on the signal settings installed by Transport for London at the time, but it is expected that the main delays will occur in West Carriage Drive. In addition the absence of a footway on the eastern side of the road during Stage 1 requires pedestrians to cross the road twice to avoid walking on the highway. 4.27 Part of North Carriage Drive, immediately to the east of the site, will be used as a lorry holding area. 4.28 North Carriage Drive is also used as a lorry holding area and temporary car park by Royal Parks during the construction of temporary buildings and stages for summer events. A temporary turning area will be provided to enable the lorry holding use to continue but it may be necessary to limit the number of parked cars. The precise location and size of the lorry turning area will be selected with Royal Parks to minimise the effect on trees. Lorry route assessment 4.29 Arrangements for lorry access and turning differ in each of the three stages: Stage 1 Lorries will leave the TLRN at Marble Arch and travel along North Carriage Drive to the lorry holding area and then enter the site. In order to enable them to turn it is proposed that part of the proposed temporary alignment of West Carriage Drive be constructed south of the worksite and used as a turning area. Vehicles will return to the TLRN at Marble Arch by way of North Carriage Drive. Stage 2 Lorries will enter and leave the holding area and site as in Stage 1. To access the western part of the site they will cross the re-aligned West Carriage Drive under the control of a banksman. They will turn in the parts of the existing road alignment within the site. Stage 3 Lorry use at this stage will be considerably reduced. Lorries will continue to access the site from the east but will leave at Victoria Gate. They will then travel via Lancaster Gate and Sussex Gardens to reach the TLRN at Marylebone Road, from where they will continue to their final destinations. 4.30 The peak flow of 98 lorry movements per day (i.e. 49 lorries in and out) in North Carriage Drive for a period of five months when construction traffic will be heaviest is not considered to be a significant environmental issue for this road in view of the fact that over 7000 vehicle trips per day will be removed from the road. 4.31 There is likely to be a loss of amenity for pedestrians, cyclists and horse riders on North Carriage Drive. It should be noted that this road forms part of Route 5 of the London Cycle Network. 4.32 The construction of the cut and cover tunnel under West Carriage Drive will necessitate the temporary diversion of part of that road. This road is private but it is considerably busier than North Carriage Drive. The need to avoid damaging tree roots or canopies acts as a constraint, which may further reduce capacity and amenity when the works are carried out. Worksite assessment (2) Park Lane worksite 4.33 The worksite occupies the central reservation on Park Lane between Cumberland Gate to the north and Brook Gate to the south. 4.34 Access and exit will be from the western carriageway, north of Brook Gate. There is an existing build-out on the side of the central median just north of Brook Gate which provides a shadow in which the lorries could safely slow down to turn into the site. Exit from the site will be on to the same carriageway further north under the control of a banksman. This movement will be assisted by the platooning of traffic caused by the traffic signals. If required, a link could be installed to the signalled pedestrian crossing at Brook Gate. This will be operated by the banksman or driver to ensure safe exit from the site. The detailed arrangements will be agreed with Transport for London prior to the commencement of the works. 4.35 No significant traffic or transport impacts have been associated with this worksite but strict control of lorries will be necessary. Park Lane is a very important road for buses and tourist coaches as well as through traffic and the need to design and operate the site correctly will need to be a fundamental requirement of the construction contract. This will be dealt with in the traffic management plan for the site, which will be prepared in consultation with Transport for London in accordance with the Crossrail s construction mitigation measures (refer Volume 8a and Appendix B1 of the Environment Statement). Lorry holding area assessment 4.36 No lorry holding area is required in normal circumstances for the Park Lane site. When required the holding area in North Carriage Drive could also be used, but this will require lorries to make two journeys through the busy Marble Arch junction. Note: a lorry holding area is proposed in Park Lane, south of Upper Grosvenor Street, exclusively for the Bond Street station worksites. This is assessed in Route Window C4. Lorry route assessment 4.37 Access to the Park Lane worksite will be directly from Park Lane, which forms part of the TLRN. No specific lorry routes are therefore required. 4.38 The northbound section of Park Lane between Grosvenor Gate and Marble Arch will experience an extra 44 lorry movements daily for the period of four weeks when construction traffic will be heaviest. The road will also experience lorry movements for almost six years during the construction of Crossrail, although at a lower level. C3 page 5

ROUTE WINDOW C3 Mitigation and temporary impacts 4.39 The impacts identified in the assessment section above are included in Table 4.1 and the corresponding mitigation also identified. Mitigation and permanent impacts 4.40 Both the Hyde Park shaft and the Park Lane shaft will require minimal maintenance and there are no operational traffic impacts to note. Table 4.1 Route Window C3 Temporary impacts Works and potential impact Significance Committed mitigation Residual impact Description Significance HYDE PARK VENT SHAFT WORKSITE Worksite impacts Traffic levels and delays to vehicle occupants CT1d The Hyde Park worksite is situated on the western end of North Carriage Drive, which therefore has to be completely closed in this area. North Carriage Drive is used for site vehicles and staff parking during the setting-up of major events that are held in the park. North Carriage Drive is adjacent to, and parallel with, Bayswater Road. It is proposed that signing be provided to indicate that Bayswater Road should be used as the diversionary route for the duration of the project. The use by the Royal Parks, which will continue while the works are in progress, will require a temporary turning facility to be provided. This will be provided in a location agreed with the Royal Parks and will take account of trees. These amendments do not form part of the works authorised by the Bill and so will require further consents. The nominated undertaker will work with the Royal Parks Authority to bring about the necessary changes. In line with the approach set out in Volume 8a an assessment of the impact of Crossrail has been carried out assuming that such measures are in place. North Carriage Drive does not carry heavy traffic flows. The alternative vehicular route has, in normal circumstances, including peak periods, sufficient spare capacity to take the displaced traffic. Not significant CT1d The cut and cover ventilation tunnel will be built through the junction of West Carriage Drive and North Carriage Drive. The work in the junction will be undertaken in stages so that West Carriage Drive will remain open. For part of the time a temporary diversion route will be used. The north-south vehicular and pedestrian route through Hyde Park will be maintained but the reduced width will lead to congestion at the junction with Bayswater Road, which could affect traffic on all roads at the junction. Vulnerable road user delay and loss of amenity CT5c The closure of the western end of North Carriage Drive includes the footway, cycle path and equestrian path. A temporary equestrian path and footway/cycle path will be provided outside the worksite boundary for the duration of construction activity. These amendments do not form part of the works authorised by the Bill and so will require further consents. The nominated undertaker will work with the Royal Parks Authority to bring about the necessary changes. In line with the approach set out in Volume 8a an assessment of the impact of Crossrail has been carried out assuming that such measures are in place. A footway, cycle path and equestrian route will be maintained along the northern side of Hyde Park. This includes Route 5 on the London Cycle Network. Not significant Parking and loading CT4c Royal Parks use the North Carriage Drive for vehicle waiting and storage while constructing, operating and maintaining the temporary stage and associated facilities used every summer. A temporary turning head will have to be provided for these vehicles. It will be mainly on the existing road and footways but will incorporate some areas of grassland. Trees will be avoided. Sufficient space will remain for the parking of vehicles required for construction and use of the facilities, though it may be necessary for people working on the site to park their private vehicles elsewhere or use public transport. Not significant C3 page 6

HYDE PARK AND PARK LANE SHAFTS Works and potential impact Lorry route impacts No adverse impact expected. The route will consist of the section of North Carriage Drive not required for the work site. This leads directly to/from Marble Arch and 98 lorry movements per day will replace the current 7600 vehicle trips. Lorry holding area impacts It is proposed that part of the section of North Carriage Drive adjacent to the worksite should be used as a lorry holding area. This area will not be used by other traffic, pedestrians, cyclists or horse riders. Significance Committed mitigation Residual impact Description Significance N/a N/a N/a N/a Not significant N/a N/a Not significant PARK LANE VENT SHAFT WORKSITE Worksite impacts Accidents and safety CT6 Lorries will enter and leave the site to and from the outside lane of Park Lane. To minimise the risk of accidents site access and exit will be confined to the northbound carriageway, will incorporate the standard features for temporary works (Chapter 8 of the Traffic Signs Manual) and will have a link to upstream signals as well as banksman control. The presence of the access and exit points will be as clear as possible and drivers will be able to take advantage of assured gaps in the traffic flow. Not significant Lorry route impacts The site is on the TLRN so no specific lorry routes are required. C3 page 7