A27 Worthing and Lancing: facilities for walking, cycling, and horse riding [nonmotorised

Similar documents
Response by the A27 Working Group for Worthing and Adur

Cycle traffic and the Strategic Road Network. Sandra Brown, Team Leader, Safer Roads- Design

Introduction. Prince Street Cycling Ambition Fund Public Realm Project

SCHEME DESIGN AND ENGINEERING

Oxfordshire Local Transport Plan 4 Science Vale Cycle Network Project Proposal Didcot Ladygrove Link

Chelmsford City Growth Package

The Cabinet Member for Highways & Streetscene. Aurang Zeb - Head of Highways & Transport

Frascati Road and Temple Hill Route Improvements. Outline Design Report to Accompany Public consultation

March Maidstone Integrated Transport Strategy Boxley Parish Council Briefing Note. Context. Author: Parish Clerk 2 March 2016

Comments on the Hailsham to Eastbourne Sustainable Transport Corridor

Background. Caversham a vision for the future. Joint public meeting arranged by:

Roads and public rights of way

Cycle Superhighway 4 from Tower Bridge to Greenwich

Cabinet Member for Highways & Streetscene. Highway Infrastructure Manager

IMPACT OF THE BERMUDA CONNECTIVITY PROJECT ON CYCLING

Progress update on the Sustainable Movement Corridor scheme Guildford Borough Council, June 2016

Nottingham Cycle City Frequently Asked Questions

CAIRNGORMS NATIONAL PARK AUTHORITY FOR DECISION

Derby Cycling Group, c/o 126, Station road, Mickleover, Derby, DE3 9FN. Date: 20 th November, 2018.

LET US KNOW WHAT YOU THINK

TRANSPORT AND MOVEMENT

Public Consultation on Braintree Integrated Transport Package (ITP) HAVE YOUR. Consultation open from 24 September to 5 November 2018 SAY

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm

CHURCH ROAD. Public consultation document TELL US YOUR VIEWS.

Douglas Land Use and Transportation Strategy (DLUTS) Summary. August 2013

Cycle Traffic and The Strategic Road Network. John Parkin and Phil Jones Presenting on behalf of Highways England

A127/A130 Fairglen Interchange Improvement Schemes. Information Leaflet February 2017

National Cycle Network Funding Scheme 2012/2012 Application Form. Waterford City Council. Paul Cleary, Executive Engineer. 3.2km 289, ,000

Map 1 shows the two roads, and how they fit into the public transport network in and around Cambridge.

Design and Installation of Low Level Cycle Signals

Phone: Ref No: 06/2018/0884

Transport Workshop Dearbhla Lawson Head of Transport & Infrastructure Policy & Funding University of the Third Age.

CUERDEN TRANSPORT PROPOSALS

A future cycle route network for North Staffordshire mb/08/16 Need for a strategy. Existing cycle route network

STONY PLAIN ROAD STREETSCAPE

North West Non-Technical Summary of the Transport Assessment September 2011

E4 Cycle Route Exeter University to Redhayes Bridge. - Recommendations from Exeter Cycling Campaign

Easton Safer Streets - Final Project Report BRISTOL

AWDM/0961/17 New Monks Farm Site Non-Motorised Users Design Review

Appendix N(b): Portishead Station Outline Travel Plan

MAGNA PARK Lutterworth. DHL SUPPLY CHAIN: Design and Access Statement. June

Maynooth Cycling. Presentation to Maynooth Community Council 14 December 2015

Space for Cycling. A guide for decision makers

1.5 On this basis it is fundamental that the Transport Strategy for the site focuses on the following key criteria,

Design Workshops Summary of all Feedback January 2017

ENFIELD TOWN THE REVISED DESIGN

Strategy for Walking & Cycling Action Plan

Appendix 11 Barton Greenway Review

GD 0043/18 ACTIVE TRAVEL STRATEGY

THE PLANNING AND. Transport and the law Integrated transport planning Strategies Responsibilities of local government and road controlling authorities

Milton Road Project Update. Paul van de Bulk 30 January 2018

MILTON ROAD LLF PROJECT UPDATE

Dodder Greenway Emerging Preferred Route Consultation - October 2018

Bulwell Cycling Consultation

Welcome. If you have any questions or comments on the project, please contact:

The Wincheap Society

BELFAST RAPID TRANSIT. Ciarán de Búrca Director, Transport Projects Division Department for Regional Development

PAGHAM NEIGHBOURHOOD PLAN INFRASTRUCTURE GROUP

Cycle Network Background Paper

Marcus Jones, TRL. Presented by Name Here Job Title - Date

Principles. 4biii. Good Urban Design

Chelmsford City Growth Package

Moving Cambridge. City of Cambridge Transportation Master Plan Public Consultation Centre. March 7, :00 8:00 PM.

Mill Hill Broadway Capacity Improvement

DRAFT for a State Policy for Healthy Spaces and Places

Launceston's Transport Futures. Greater travel options for the people of Launceston

A27 East of Lewes improvement scheme Have your say

Active Travel Towns Funding Scheme Project Proposal. Sligo. Sligo Local Authorities

Bicycle Master Plan Goals, Strategies, and Policies

City of Wells Cycle Network

MARKHOUSE ROAD IMPROVEMENTS

ABERDEEN: CITY OF THE FUTURE

Canada s Capital Region Delegation to the Velo-City Global 2010 Conference

Chelmsford City Growth Package

Regional Cycle Programme Update

Issues at T junctions:

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

2. Context. Existing framework. The context. The challenge. Transport Strategy

Milton Road Bus Stop and Crossings Workshop WSP. 19th September 2017

HAMILTON BIKING PLAN OUR VISION: A BIKE FRIENDLY CITY

LEA BRIDGE ROAD - A STREET FOR EVERYONE Public consultation document

Cycle network linking Wolverhampton city centre and Bilston town centre with employment sites and residential areas:

Cycle Routes. Traffic Advisory Leaflet 3/95 March Introduction. Implementation. Project aims. Design

Your views are important. Please fill in a form before you leave. Or alternatively

Amendments to Essex Highway Maintenance Strategy Maintenance Policy and Standards April 2008

July 2018 to June 2019

Chapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails

TS 109 DURHAM ROAD QTC PHASE 4 PROJECT PROPOSAL. Page 1

London Cycle Network Annual Report 2000

Lea Bridge Road A street for everyone Tell us

Chapter 4 Route Window C3 Hyde Park and Park Lane shafts. Transport for London

Prepared For: Shieldbay Developments Inc. c/o Matson, McConnell Ltd. 2430A Bloor Street West Toronto, Ontario M6S 1P9.

Tel: Karime Hassan Chief Executive Exeter City Council Civic Centre Paris Street Exeter EX1 1JN

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

Sevenways Roundabout, and the need for a Road Safety Scheme:

PEDESTRIAN ACTION PLAN

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

WELLINGTON CITY COUNCIL CYCLING NETWORK DRAFT FRAMEWORK

Active Travel Strategy Dumfries and Galloway

Transcription:

A27 Worthing and Lancing: facilities for walking, cycling, and horse riding [nonmotorised users (NMUs)] Introduction This note describes our understanding of the needs of Non-Motorised Users (NMUs) as they use or cross the A27, and the impacts new infrastructure may have on the Public Rights of Way (PRoW) network. It sets out the context for the facilities we would provide as a part of the proposed scheme, and how they connect with the existing facilities. Whilst outlining the context for funding to improve and maintain the Strategic Road Network (SRN), the 2015 Road Investment Strategy also states: The Government is committed to improving active travel options, such as cycling and walking. Too often the SRN often acts as a barrier to these activities, so we are committed to improving access through building new bridges, crossings and cycle paths. We have prepared a baseline review of the current facilities and identified the need for linkages between different local communities and facilities, taking into account opportunities and proposals contained within The West Sussex Walking and Cycling Strategy 2016-2026 and the Worthing and Adur Local Plans. These findings and proposed linkages have been discussed with the local authorities. Where do people currently walk and cycle? The key movements in Worthing are between areas north of the A27 (including the Findon Valley area) and the railway station, town centre and seafront, by bus, walking or cycling. In Lancing, there are similar movements between North Lancing, the station and the seafront, in addition to connections to Worthing and Shoreham. Walking and cycling to destinations further afield such as Bognor Regis, Littlehampton and Brighton are also important. We have noted where existing facilities for crossing the road and bus stops are located. We also have details of land uses within a corridor either side of the A27 that are likely to generate or attract pedestrians and cyclists. Further information is provided in the Non- Motorised Users Context Report on the project website (www.highways.gov.uk/a27worthingand-lancing). What facilities are currently provided? Error! Reference source not found.1 shows the current network of Public Rights of Way (PRoW) and existing cycle facilities in the area affected by our proposals.

Figure 1 Existing Rights of Way crossing or close to the junctions

What changes are we proposing to make to these facilities? We are proposing to provide 3 metre wide footways where we consider there may be demand for a shared pedestrian and cycle path. In some cases there may not be the need for such a facility and in a few cases there may be a requirement for segregated (separated) facilities for pedestrians and cyclists. We will design the facilities in more detail during the next stage of the study.our proposals do not require any existing rights of way to be rerouted. The existing rights of way provide important links from urban areas to the South Downs National Park and we will enhance crossing facilities to improve access where we can. Descriptions of the proposed alterations at each of the junctions are provided in Table 1 below. Table 1 NMU improvements at the junctions through Worthing and Lancing Ref Junction Proposed NMU Facilities 1 2 Durrington Hill / Salvington Hill junction Offington Corner Junction Roundabout A24 Findon Road / Offington Lane (Durrington Cemetery) 3 Grove Lodge junction 4a & 4b 5 6 Lyons Farm Retail Part 1 Junction (Sompting Road) & Lyons Farm Retail Part 2 Junction (Lyons Way) Busticle Lane / Halewick Lane junction Grinstead Lane / Manor Road junction The new junction arrangement would replace the existing pelican crossing with a toucan crossing with dedicated pedestrian and cyclist crossing times on the A27 approaches. The new junction arrangement would replace the existing roundabout with a traffic signalled cross roads. Toucan crossings would provide dedicated pedestrian and cyclist crossing times on each approach of the A27. The new signalled arrangement would benefit cyclists and pedestrians (compared to the current roundabout) as the signal timings would provide protected crossing for pedestrians and cyclists across each approach of the A27. The signal arrangements proposed at these junctions would replace and enhance the existing pedestrian crossing facilities and incorporate dedicated cycle and pedestrian only crossing times. The proposed signal arrangements would replace and enhance the existing pedestrian crossing facilities and would incorporate dedicated cycle and pedestrian only crossing times. The new junction arrangement would replace the existing roundabout with a traffic signalled junction further east with toucan crossings with dedicated pedestrian and cyclist crossing times on each approach of the A27. We are also considering how we can improve connections between our proposed facilities and other parts of Worthing, with discussions with West Sussex County Council. As we are unable to provide a continuous cycle path along the A27, we have considered the possibility of creating a southern parallel route using more lightly trafficked roads (this is shown in Figure 2). We welcome your views on the merits of such a route before we consider it further. In addition to the improved junctions, the scheme would also connect with the cycle / pedestrian paths between Grinstead Lane / Manor Lane junctions and the Sussex Pad traffic signalled junction further east. This would help residents of North Lancing cycle to the railway station and south to the Coastal cycle route, improving cycle link to Shoreham and the long distance Downs Link (shared route for walkers, horse riders and cyclists linking the North Downs Way with the South Downs Way).

Figure 2 Parallel cycle route using local roads

Horse riding We have not shown any new facilities for horse riders within the scheme drawings, but we would welcome any comments on this topic. What happens next? As a part of the A27 Worthing and Lancing improvements consultation we want to ensure that we clearly understand the needs of all road users. Please tell us what you think about our ideas and if there is anything you think we have missed. We will consider all the comments and suggestions received and where possible make improvements to better meet local needs. How will these improvements be funded? The new facilities outlined in this document will be funded as part of the A27 Worthing Lancing improvements scheme. We will also be looking at the funding available for local authorities and other organisations to improve or provide routes that connect with or enhance our new facilities, through a funding source known as Designated Funds. These are funds set up as part of the Road Investment Strategy (RIS) to complement routine maintenance and management of the strategic road network or major improvements in order to meet the strategy s objectives set for walking, cycling, safety, integration and environment. Further information The Non-Motorised Users Context Report on the project website (www.highways.gov.uk/a27worthing-and-lancing) provides further details.