R.H. Hobbs, Chair N.F. Nicholls, Commissioner October 6, 2006 L.A. O Hara, Commissioner O R D E R

Similar documents
B2-69. POLICy!MANAGEMENf PANEL SEA BREEZE CORPORATE PAUL MANSON BRIAN CHERNACK. DR. ZAK EL-RAML y

BC hydro REGENERATION

FortisBC Energy Inc. Annual Review for 2018 Delivery Rates Project No Final Order with Reasons for Decision

Banksia Securities Limited ACN: (Receivers and Managers Appointed)(In Liquidation) ("BSL")

B2-17. December 6, & COURIER

SPORT DISPUTE RESOLUTION CENTRE OF CANADA (SDRCC) AND AND DECISION

Order No. 55/18 CENTRA GAS MANITOBA INC.: PRIMARY GAS RATE APPLICATION, EFFECTIVE MAY 1, April 26, 2018

Environmental Appeal Board

Golf Professional Services - Independent Contractor

Environmental Appeal Board

Panel: Mr Malcolm Holmes QC (Australia), Sole Arbitrator

The following words and terms, when used in this rule, have the following meanings, unless the context clearly

25 April Sincerely,

Pacific Pilotage Authority. submission to the. Canada Transportation Act Review Panel. January 2015

Third District Court of Appeal State of Florida

BCAC ANTI DOPING POLICY

Order F14-53 BRITISH COLUMBIA LOTTERY CORPORATION. Tim Mots Adjudicator. December 18, 2014

PANEL DECISION. newcastlepaintball.com.au. Panel: Andrew Robertson. Hunter Valley Paintball Pty Ltd. Delta Force Properties Pty Ltd

(a) Advertised Jackpot Prize- The estimated annuitized Jackpot Prize amount as determined by the Mega

Arbitration CAS 2006/A/1110 PAOK FC v. Union des Associations Européennes de Football (UEFA), award of 25 August 2006 (operative part of 13 July 2006)

2013 AIBA WOMEN S JUNIOR AND YOUTH WORLD BOXING CHAMPIONSHIPS AUSTRALIAN TEAM SELECTION CRITERIA

Southwest Power Pool REGIONAL STATE COMMITTEE BYLAWS

Appendix A Canadian Football League Standard Player Contract

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

M A N I T O B A ) Order No. 123/13 ) THE PUBLIC UTILITIES BOARD ACT ) October 22, 2013

Arbitration CAS ad hoc Division (O.G. Sydney) 00/015 Mihaela Melinte / International Amateur Athletic Federation (IAAF), award of 29 September 2000

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. At a session of the Public Service Commission held in the City of Albany on August 20, 2003

BEFORE THE WORLD TRADE ORGANIZATION UNITED STATES MEASURES CONCERNING THE IMPORTATION, MARKETING AND SALE

Using the UK FOIA, part III

Environmental Appeal Board

Submission of Non-PTO Wheeling Data

Environmental Appeal Board

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

CONTACT: Robert A. Stein, acting chair, NCAA Infractions Appeals Committee

U.S. Figure Skating Travel and Expense Policy (March 2012)

126 FERC 61,182 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF FILINGS. (Issued February 27, 2009)

Request for Proposal Naming Rights for the Stadium (The Ball Park at Jackson)

Panel: Prof. Michael Geistlinger (Austrian), President; Mr Henri Alvarez (Canada); Prof. Ulrich Haas (Germany)

IN THE DISTRICT COURT OF THE FOURTH JUDICIAL DISTRICT OF THE STATE OF IDAHO, IN AND FOR THE COUNTY OF ADA. Case No.

ATHLETICS AUSTRALIA SELECTION POLICY 2017 WORLD PARA ATHLETICS WORLD CHAMPIONSHIPS LONDON, UNITED KINGDOM JULY 2017

TITLE 11. DEPARTMENT OF JUSTICE NOTICE OF PROPOSED RULEMAKING

A2:1 The Facility Standards are focused on ensuring appropriate standards for the benefit of the Game including:

STATE OF OHIO ) IN THE COURT OF APPEALS NINTH JUDICIAL DISTRICT COUNTY OF WAYNE ) DECISION AND JOURNAL ENTRY

1.1.1 Appeal Panel means the appeal panel appointed by the Union under the Disciplinary Rules;

DISPUTES RESOLUTION AUTHORITY Record No. 23/2005. GERARD MALONEY and JOE RYAN (as nominees of Cumann Sean Mac Diarmada Creachmhaoil) - and - DECISION

FIVB TRIBUNAL REGULATIONS

Environmental Appeal Board

SUBJECT: AMENDING PORT OF LOS ANGELES TARIFF NO. 4, SECTION THREE, ITEM NO CHARGES FOR PILOTAGE

REPORT General Committee

SINGAPORE edevelopment LIMITED (Incorporated in Singapore) (Company Registration No W)

Decision of the Single Judge of the Players Status Committee

NEW ENGLAND RUGBY INCORPORATED BY LAWS. Rule 3: METHOD OF CONDUCTING THE COMPETITION & FINAL SERIES

INTERNATIONAL INSTITUTE OF SPACE LAW MANFRED LACHS SPACE LAW MOOT COURT COMPETITION

BC Games Society 2016/ /19 SERVICE PLAN

NBL Salary and Contracting Rules

U.S. Figure Skating Travel and Expense Policy (July 2018)

Analysis of the Article Entitled: Improved Cube Handling in Races: Insights with Isight

Arbitration CAS ad hoc Division (O.G. Salt Lake City) 02/003 Bassani-Antivari / International Olympic Committee (IOC), award of 12 February 2002

BC GAMES SOCIETY 2014/15 ANNUAL SERVICE PLAN REPORT

Xcel Energy (Baa3/BBB-)

United States Figure Skating Association Eligible Skater s Compensation Agreement Program (ESCA)

World Bowling Tour Rules

Mississippi Prepaid Affordable College Tuition Plan Pricing Report for the 2018/2019 Academic Year

ENVIRONMENTAL APPEAL BOARD Province of British Columbia

NOTICE OF MOTION MOTION: # X Regulation 2.1 (Definitions)

Press Release New Bilateral Agreement May 22, 2008

ICC REGULATIONS FOR THE REVIEW OF BOWLERS REPORTED WITH SUSPECT ILLEGAL BOWLING ACTIONS

OFFICE OF THE ATHLETICS CANADA COMMISSIONER IN THE MATTER OF AN APPEAL. between. and ATHLETICS CANADA CARDING APPEAL DECISION

British Wheelchair Basketball Rio 2016 Paralympic Games Selection Policy

ITEM No. 20 g MOTION. PRESENTED BY: HERJLJ. WESSONyJr. Councilman, 10th District SECONDED BY

WEG SELECTION POLICY - EVENTING SELECTION POLICY 2018 WORLD EQUESTRIAN GAMES EVENTING

City of Moose Jaw: Ratifying Debentures

AUTHENTIC IBN NAWAAL 50 Dunkard Church Road Stockton, NJ Tele: (609) Fax: (609)

ATHLETICS AUSTRALIA SELECTION POLICY 16 th IAAF WORLD CHAMPIONSHIPS LONDON, GREAT BRITAIN 4 th to 13 th AUGUST 2017

Advertising Opportunities

Environmental Appeal Board

SUBMISSIONS OF THE CANADIAN BAR ASSOCIATION (BRITISH COLUMBIA BRANCH)

For such purposes, UEFA intends to organise a tendering process ( Tender ).

PARTIAL DECISION of the FEI TRIBUNAL. dated 2 February Event/ID: SEA Games-S Kuang Rawang (MAS)/2017_G-SE.AS_0002_S_S_01

2.1 STS Crane Glass Pricing - Savannah Crane # Drawing # Item # Type Of Glass Cost. Sav LV50:112-L1 1. Sav LV50:112-L1 2

In addition to the definitions provided in Paragraph 1.2 of Rule 1 and Rule 10, and unless the context in this Amended Rule 10.A otherwise requires:

ICC REGULATIONS FOR THE REVIEW OF BOWLERS REPORTED WITH SUSPECTED ILLEGAL BOWLING ACTIONS

Web.com Completes Acquisition of Yodle Deal strengthens Web.com s portfolio of products that help small businesses compete and succeed online

October 3/15 Board MINUTES. Sandman Hotel, Vancouver, B.C.

NOTICE of RACE Skiff Regatta 2010

WEG SELECTION POLICY ENDURANCE

TECHNICAL REGULATIONS

Selection Process for Great Britain Olympic Curling Team (Men s and Women s) 2018 Winter Olympic Games Pyeongchang, South Korea

MEMORANDUM OF UNDERSTANDING. between THE UNION OF EUROPEAN FOOTBALL ASSOCIATIONS. (hereinafter referred to as UEFA ) and

Arbitration CAS 2009/A/2011 Stephan Schumacher v. International Olympic Committee (IOC), award on costs of 6 May 2010

NEW JERSEY SIRE STAKES STANDARDBRED DEVELOPMENT FUND P.O. Box 330, Trenton, NJ (609) , fax (609)

Swansea University Commercial/Maritime Law Mooting Competition

Christilot Hanson Boylen v. Equine Canada. Christilot Hanson Boylen Equine Canada. Selection to Olympic Games Richard W. Pound, Q.C.

TO: FROM: SUBJECT: RECOMMENDATION

SINGAPORE POOLS (PRIVATE) LIMITED 210 MIDDLE ROAD, #01-01 SINGAPORE POOLS BUILDING, SINGAPORE

STANDARD TRAINING AGREEMENT

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

THE SCHOOL OF ORIENTAL AND AFRICAN STUDIES. Redundancy Policy

Case 9:11-cv DWM Document 64 Filed 06/21/11 Page 1 of 7

ANALYZING THE SHIP DISPOSAL OPTIONS

Transcription:

BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-124-06 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com TELEPHONE: (604) 660-4700 BC TOLL FREE: 1-800-663-1385 FACSIMILE: (604) 660-1102 IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and An Application by Sea Breeze Victoria Converter Corporation for a Reconsideration of the July 7, 2006 Commission Decision and Order No. C-4-06 relating to the British Columbia Transmission Corporation Application for a Certificate of Public Convenience and Necessity for the Vancouver Island Transmission Reinforcement Project BEFORE: R.H. Hobbs, Chair N.F. Nicholls, Commissioner October 6, 2006 L.A. O Hara, Commissioner O R D E R WHEREAS: A. By application dated July 7, 2005, the British Columbia Transmission Corporation ( BCTC ) requested that the British Columbia Utilities Commission (the Commission ) grant a Certificate of Public Convenience and Necessity ( CPCN ) pursuant to Sections 45 and 46 of the Utilities Commission Act (the Act ), for the Vancouver Island Transmission Reinforcement Project (the VITR ) to reinforce the electricity transmission system serving Vancouver Island and the Southern Gulf Islands (the VITR Application ); and B. The Public Hearing commenced on February 6, 2006 in Vancouver and the evidentiary phase of the proceeding closed on March 23, 2006. The Written Argument phase of the proceeding was completed when BCTC filed its Reply Submission on May 16, 2006, and the Oral Phase of Argument, including submissions regarding motions by a number of parties, was heard on May 30 and 31, 2006; and C. On July 7, 2006 the Commission issued its Decision ( VITR Decision ) pursuant to Sections 45 and 46 of the Act granting a CPCN to BCTC for the VITR Project; and D. By letter dated September 15, 2006 ( Reconsideration Application ), Sea Breeze Victoria Converter Corporation ( Sea Breeze ) requested a reconsideration of the VITR Decision; and

BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-124-06 2 E. By letter dated September 18, 2006, the Commission established a first phase process for the Reconsideration Application. The first phase process provided an opportunity for written comments from BCTC, Intervenors and Interested Parties on September 26, 2006 with written reply from Sea Breeze by October 4, 2006; and F. The Commission has reviewed the submissions and has prepared its Reasons for Decision. NOW THEREFORE the Commission denies the Reconsideration Application and issues its Reasons for Decision attached as Appendix A to this Order. DATED at the City of Vancouver, in the Province of British Columbia, this 6 th day of October 2006. Attachment BY ORDER Original signed by: Robert H. Hobbs Chair

Page 1 of 5 An Application by Sea Breeze Victoria Converter Corporation for a Reconsideration of the July 7, 2006 Commission Decision and Order No. C-4-06 relating to the British Columbia Transmission Corporation Application for a Certificate of Public Convenience and Necessity for the Vancouver Island Transmission Reinforcement Project REASONS FOR DECISION By letter dated September 15, 2006 (Reconsideration Application), Sea Breeze Victoria Converter Corporation ( Sea Breeze ) requested a reconsideration of the VITR Decision dated July 7, 2006 ( VITR Decision ). By letter dated September 18, 2006, the Commission established a first phase process for the Reconsideration Application. The first phase process provided an opportunity for written comments from BCTC, Intervenors and Interested Parties on September 26, 2006 with written reply from Sea Breeze by October 4, 2006. The Commission has reviewed the submissions, and provides the following reasons for denying the Reconsideration Application. Sea Breeze submits that the Commission erred in its assessment of the wheeling costs attributable to the JdF project in the amount of $10.2 million per year, the present value of which, coupled with system losses, was calculated to be $153.5 million over 40 years, as well as failing to properly take into account the revenues attributable to the JdF project, and which ought to have been considered as part of the Commission s costbenefit analysis for the purpose of the project comparison (Reconsideration Application, p. 1). Sea Breeze submits that the basis for its intervention in the VITR proceeding was that JdF would be less costly for BC ratepayers than the VITR project, and also would address many of the concerns of the opponents of VITR. Sea Breeze submits that by adding $153.5 million to the projected cost of JdF the Commission erroneously concluded that JdF would be more costly than VITR. Sea Breeze argues that the $153.5 million amount does not reflect an accurate assessment of the wheeling charges and does not adequately address or consider much of Sea Breeze s evidence regarding its proposed pricing and costing scenarios for JdF. Sea Breeze also submits that the Commission erred in determining that no revenues should be attributed to the JdF project for trade benefits. These three arguments by Sea Breeze will be considered in turn.

Page 2 of 5 Is $153.5 million an Accurate Assessment of the Wheeling Charges? The $153.5 million amount is found in the Summary Comparison of Project Alternatives at page 174 of the VITR Decision, and is described at page 161 of the VITR Decision as the incremental cost of wheeling and losses on the BPA system. As noted by BCTC, this amount does not include system losses. Sea Breeze is incorrect when it states that the $153.5 million included system losses. Based on the record, the Commission concluded that for cost comparison purposes, the costs for JdF should include firm transmission on the BPA system to meet reliability criteria for Vancouver Island (VITR Decision, pp. 167-168). Sea Breeze submits that the $153.5 million does not reflect an accurate assessment of the wheeling costs that would actually be incurred (Reconsideration Application, p. 2). Although Sea Breeze submits that this is an error, it does not identify whether it considers this error to be an error of fact or law as pointed out by BCTC. And as noted by BCTC, it also does not expressly identify how it says the Commission erred (BCTC Submission, p. 3). The issue of wheeling costs and losses on the BPA system was an issue that was in dispute throughout the proceeding and was well canvassed during cross-examination and in argument. The VITR Decision reviews the evidence and positions of the parties in some detail from pages 160 to 171. Clearly, the Commission did not accept the evidence and submissions of Sea Breeze with respect to whether or not firm transmission service was required on the BPA system, or the cost of firm transmission service. In the Reconsideration Application, Sea Breeze does not offer any new arguments with respect to this issue, but does repeat many of the arguments previously advanced and then claims that an error was made by the Commission. The Commission did not, and does not now, accept Sea Breeze s position with respect to whether or not firm transmission service is required to meet reliability criteria on Vancouver Island. On this ground for reconsideration, the Commission does not accept that a prima facie basis for an error has been established. With respect to the calculation of the cost of firm transmission service and losses on the BPA system, the Commission acknowledges uncertainty over the magnitude of the costs; however, as noted by BCTC and stated in the VITR Decision at page 171, the firm wheeling costs (or upgrade costs) would need to be reduced to below $2 million per year to make the ratepayer impacts of JdF equal to VITR, and even then there are still other considerations that would need to be factored into the comparison (e.g. different schedule risks). Furthermore, the Commission found no evidence on the record to conclude that estimated firm wheeling costs could reasonably be reduced by as much as $8 million given BPA s firm wheeling tariffs. Therefore, even if the

Page 3 of 5 Commission erred in its calculation of the magnitude of the wheeling costs, it does not necessarily follow that the error would be material to the Decision. Pricing and Costing Scenarios for JdF In Reply, Sea Breeze submits that at the end of negotiations, JdF would always be less expensive for ratepayers than the VITR Project (emphasis in original). Sea Breeze further submits in Reply that the only appropriate way to arrive at a price for JdF was through good faith negotiations between BC Hydro, BCTC and Sea Breeze, under the guidance of the Commission, in order to ensure that under any circumstances a savings to ratepayers over the cost of VITR would be realized (emphasis in original). Sea Breeze then submits that the Commission erred in failing to properly consider this fundamental position and the evidence in support of this position was in error. At page 198 of the VITR Decision, the Commission states: the Commission Panel finds that the level and timing of the capacity shortfall on Vancouver Island suggests a high weight should be given to certainty for reliability planning purposes. And then on page 199 of the VITR Decision, the Commission states: With respect to financing risk for JdF, the Commission Panel notes that the PV of an annual nominal payment (@ a nominal discount of 8 per cent) of $22.3 million over 20 years (the minimum guaranteed payment required by Sea Breeze to secure financing for JdF in Exhibit C31-57, Undertaking T36:6857-6858, 7037, 7091-7093) is equivalent to $219 million in 2009/10 or $201 million in constant $2005. That exceeds the lump sum payment for JdF estimated by the Commission Panel in Section 7 of the Decision. In the VITR Decision, the Commission considered both the pricing and cost scenarios for JdF and the financing risk for JdF. The submissions by Sea Breeze quoted above do not consider the financing risk for JdF. The Commission in the VITR Decision further states at page 201: In conclusion, the Commission Panel finds that if, due to this Decision and direction, JdF were to get a long-term, regulated contract with BCTC, there is still uncertainty relative to VITR as to whether Sea Breeze would be able to secure financing in the time required to meet ratepayer needs. More importantly, the proposed pricing of JdF and minimum guaranteed payment required by Sea Breeze do not provide sufficient savings to ratepayers to

Page 4 of 5 offset other costs associated with reliance on JdF to meet reliability planning criteria for Vancouver Island. The Commission found that even before taking into account indirect costs to ratepayers (e.g., wheeling costs), the present value of the minimum guaranteed payment required by Sea Breeze for financing would exceed the payment to Sea Breeze under its lump sum pricing formula based on the Commission determined costs of VITR. Sea Breeze provided no pricing formula or approach that could reconcile the minimum payment required for financing and the maximum price for JdF that would be in ratepayer interests given indirect costs to ratepayers. Contrary to the claims of Sea Breeze, the Commission did properly consider the fundamental position of Sea Breeze and the evidence in support of this position, but also considered the financing risk for JdF. Considering Sea Breeze s fundamental position with due consideration to the financing risk of JdF was not an error and was appropriate given the finding that the level and timing of the capacity shortfall on Vancouver Island suggests a high weight should be given to certainty for reliability planning purposes. Assessment of Export Revenues Attributable to JdF In the Reconsideration Application, Sea Breeze states at page 2: The Commission erred in determining that no revenues should be attributed to the JdF project for the purposes of project comparison, and should reconsider its determination on this issue. Unlike the evidence related to the wheeling charges, there was only limited evidence with respect to the amount of trade revenues that might be attributable to JdF. As stated in the Decision at page 170: the Commission Panel finds no compelling evidence on the record regarding the likelihood or magnitude of these benefits. The Commission Panel shares BC Hydro s concerns that the purported beneficiaries of these benefits have not been confirmed or corroborated such benefits. In a footnote to its Reply, Sea Breeze states: Sea Breeze stands by its position that wheeling charges in the amount assessed by the Commission will not be attributable to JdF and stands by its assessment of the export revenues that will be attributable to the JdF project, and believes that the Commission erred in both of these respects (as stated in the Application for Reconsideration).

Page 5 of 5 The Commission notes that Sea Breeze claims to have provided an assessment of the export revenue that will be attributable to the JdF project. However, Sea Breeze did not file an estimate of trade benefits with its pre-hearing evidence and did not provide an estimate of trade benefits until after the oral hearing had concluded. Furthermore, the estimate filed by Sea Breeze was a calculation of third party revenues under different levels of trade activity. Sea Breeze provided no compelling evidence to support the estimated trading activity used in its calculations. Sea Breeze now relies on the recent National Energy Board decision approving Sea Breeze s application to build the JdF project where: the Board accepts Sea Breeze s evidence with respect to the potential ability of the Project to support increased transfer capacity across the Canada/U.S. border. The Commission does not find the reference by Sea Breeze to the National Energy Board decision helpful to a reconsideration on the record in this proceeding, particularly when Sea Breeze does not claim that there has been a fundamental change in circumstances or facts since the VITR Decision. Furthermore, the finding of the National Energy Board quoted above does not identify specific trade activity that would arise from JdF but merely confirms the project would increase transfer capability. As stated by BCTC, even if trade benefits had been demonstrated, the Commission did not necessarily view incremental trade benefits to the province as a relevant consideration in the comparison of JdF and VITR (BCTC Submission, p. 5; VITR Decision, p. 170). The Commission does not find a prima facie basis for an error when it concluded that no trade benefits should be included in the comparison of JdF and VITR. Chapter 4 of A Participants Guide to the British Columbia Utilities Commission identifies the criteria that the Commission generally applies to determine whether a reasonable basis exists to allow a reconsideration. An application for reconsideration proceeds in two phases. In the initial screening phase, the applicant must establish a prima facie case sufficient to warrant full consideration by the Commission. For the reasons stated above, the grounds set forth in the Reconsideration Application do not meet the criteria for a reconsideration application to proceed to the second phase.