DESIGN FOR NATURAL GAS INSTALLATIONS ON INDUSTRIAL AND COMMERCIAL PREMISES WITH RESPECT TO DSEAR

Similar documents
Commissioning of gas-fired plant on industrial and commercial premises

IGEM/GM/7B Edition 2 Communication 1804 Hazardous area classification for gas metering equipment

Design and application of interlock devices and associated systems used with gas appliance installations in commercial catering establishments

IGEM/SR/29 Communication 1760 Dealing with gas escapes

Non-domestic meter installations

IGEM/GL/5 Edition 3 Communication 1783 Managing new works, modifications and repairs

IGEM/GM/7A Edition 2 Communication 1803 Electrical connections for gas metering equipment

Safe working practices to ensure the integrity of gas assets and associated installations

IGEM/SR/4 Edition 3 Communication 1752 Variable volume gasholders storing lighter than air gases

IGEM/UP/11 Edition 3 Communication 1821 Gas installations for educational establishments

Tightness testing and direct purging of small Liquefied Petroleum Gas/Air, Natural Gas and Liquefied Petroleum Gas installations

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines

IGEM/UP/12 Edition 2 Communication 1778 Application of burners and controls to gas fired process plant

Medium pressure two-stage meter regulators for gas flow rates not exceeding 6 m 3 h -1

Meter regulators of nominal diameter 32 mm (1¼ inch) and not exceeding 150 mm (6 inch) and for inlet pressures not exceeding 75 mbar

Non-domestic meter installations

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

Installation pipework on industrial and commercial premises

IGEM/GM/6 Edition 2 Communication 1750 Non-domestic meter installations. Standard designs

Safe working practices to ensure the integrity of gas pipelines and associated installations

INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015

EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT

IGEM/SR/15 Edition 5 Communication 1746 Integrity of safety-related systems in the gas industry

Horizontal Directional Drilling and Impact Moling

Network Regulator Maintenance Operatives LS (Non-Accredited)

IGEM/UP/2 Edition 3 Communication 1771 Installation pipework on industrial and commercial premises

INSTITUTION OF GAS ENGINEERS AND MANAGERS

IGE/TD/12 Edition 2 Reprint with Amendments Communication 1757 Pipework stress analysis for gas industry plant

Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant

1.8 INDUSTRIAL PROCESS WEIGHING IN HAZARDOUS AREAS

User Information Sheet 015

Overview EUSDSG3.6. Gas tightness testing and direct purging

ARCHIVED. Compliance Document for New Zealand Building Code Clause G11 Gas as an Energy Source. Prepared by the Department of Building and Housing

ACS.TPCP1A SAFETY ASSESSMENT CRITERIA INITIAL AND RE-ASSESSMENT NON-DOMESTIC NATURAL GAS TESTING AND PURGING

Overview EUSSAM12. Carry out tightness testing and direct purging of gas installations

AIDGC PRESENTATION MARCH 2006 HAZARDOUS AREAS STANDARDS & CLASSIFICATION

ACS.TPCP1 SAFETY ASSESSMENT CRITERIA INITIAL AND RE-ASSESSMENT NON-DOMESTIC NATURAL GAS; LPG; OTHER GASES TESTING AND PURGING

BCGA GUIDANCE NOTE 17

LEGIONELLA MANAGEMENT PROCEDURE

Pressure Systems Safety Regulation

The routine maintenance and inspection of local exhaust ventilation (LEV)

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

SUP 15 Health & Safety Management Pressure Systems. Unified procedures for use within NHS Scotland

Module 6. Tightness Testing

Contractor / Exhibitor Handbook

Changes to the Gas. (Safety and Measurement) Regulations. effective 1 July 2013

Examples of pressure systems and equipment are:

Drum / cylinder handling

Assessing the safety of gas installations in buildings

E PGN-11. Part of NTW (O)32 Estates Operations and Maintenance Policy Paul McCabe Head of Estates and Facilities-NTW Solution Ltd

CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS

Facilities and Estates. Natural Gas: Standard Operating Procedure. Document Control Summary. Contents

CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY

DSEAR-Classification of Hazardous Areas (Zoning) and Selection of Equipment

(2) but does not include a shaft, trench or tunnel that is a mine or is part of the workings of a mine.

Gas Safety Code of Practice

SOP. Working in Confined Spaces


GAS INDUSTRY GUIDANCE ON WORK ON METER INSTALLATIONS

PRESSURE SYSTEMS POLICY

Compliance with Health & Safety legislation

Overview EUSDSG3.12. Install gas meters and regulators (2.5 to 16.0m3/hr)

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

TABLE OF CONTENTS PART 2 - CONFINED SPACES

MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS

INSTITUTION OF GAS ENGINEERS AND MANAGERS

MAGB HEALTH and SAFETY GROUP Working In Confined Spaces

A guide to Part 10 of the

NZQA registered unit standard version 3 Page 1 of 6

1.0 Scope and Application. 2.0 Definitions. Cal Poly Risk Management Confined Space Program Page 1

Personal Protective Equipment

IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL

Dangerous Substances & Explosive Atmospheres Regulation 2002 The Basics. Richard Cowen Dip SH, Dip RSA, CMIOSH, MIIRSM, FRSPH, GI Fire E

6-5 Maintenance Manual

Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT. Health and Safety Policy

GUIDELINES. Systems. Pressure. Guidelines Acceptance of equipment, establishment of safe operating limits and fitness for service

Class 2 Gases Learning Tool

INSPECTION, TESTING AND CERTIFICATION OF GASFITTING WORK DONE UNDER SUPERVISION

ACS.CoNGLP1 SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC NATURAL GAS TO LPG GENERIC

Dangerous Substances and Explosive Atmosphere Regulations 2002 Appendix 2 Detailed assessment & zone classification where DSEAR applies to an area

RISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992

POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY

IMPLEMENTATION OF EIGA CARBON DIOXIDE STANDARDS

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.

INSTITUTION OF GAS ENGINEERS AND MANAGERS

GUIDANCE IN-SERVICE INSPECTION PROCEDURES

Petrol Filling Stations - Safety Implications of Leaking Drop Tubes & Vapour Retention Devices

Gas Pressures FAQs. Why only 19 mbar inlet pressure and 15 mbar outlet pressure? MOV: meter outlet valve ECV: emergency control valve

To comply with the OHS Act, the responsible manager must carry out and document the following:

Health & Safety Policy HSP 08 Control of Substances Hazardous to Health (COSHH) Version Status Date Title of Reviewer Purpose/Outcome

Safe work method statements

SAFETY POLICY AND PROCEDURE MANUAL All Euramax Subsidiaries. Number K-3.0 Welding Safety Procedures

HEALTH & SAFETY GUIDANCE

COSHH Hazardous Substances Health & Safety Management Standard Issue 2 (September, 2010)

The evolution of the Ex-proof flame path

PRESSURE REDUCING STATION INSTALLATION, OPERATIONS & MAINTENANCE MANUAL

Installing, Repairing or Modifying Construction Resources by Heating, Welding, Brazing, Soldering and Thermal Cutting in the Workplace L/505/0144

Control of Vibration at Work

WHITEPAPER: ATEX IN PRACTICE (EXPLOSION PROTECTION)

Transcription:

INSTITUTION OF GAS ENGINEERS AND MANAGERS IGEM/TSP/18/195 Founded 1863 IGEM/UP/16 Edition 2 Royal Charter 1929 Communication 1824 Patron Her Majesty the Queen DESIGN FOR NATURAL GAS INSTALLATIONS ON INDUSTRIAL AND COMMERCIAL PREMISES WITH RESPECT TO DSEAR DRAFT FOR COMMENT 1 This draft Standard IGEM/UP/16 Edition 2 has been prepared by a Panel under the chairmanship of Geoff Winckles. 2 This is a draft document and should not be regarded or used as a fully approved and published Standard. It is anticipated that amendments will be made prior to publication. It should be noted that this draft Standard contains intellectual property belonging to IGEM. Unauthorised copying or use by any unauthorised person or party is not permitted. 5 This is a copyright document of the Institution of Gas Engineers and Managers. Enquiries should be addressed in the first instance to: Thomas Bancroft IGEM IGEM House 26-28 High Street Kegworth Derbyshire, DE74 2DA Tel: 0844 375 4436 Fax: 01509 678198 Email: thomas@igem.org.uk Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen

IGEM/UP/16 Edition 2 Communication 1824 Design for Natural Gas installations on industrial and commercial premises with respect to DSEAR Draft for Comment Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen

IGEM/UP/16 Edition 2 Communication 1824 Design for Natural Gas installations on industrial and commercial premises with respect to DSEAR Draft for Comment Price Code: C4S The Institution of Gas Engineers and Managers IGEM House 26-28 High Street Kegworth Derbyshire, DE74 2DA Tel: 0844 375 4436 Fax: 01509 678198 Email: general@igem.org.uk

IGEM/UP/16 Edition 2 Draft for Comment Copyright 2018, IGEM. All rights reserved Registered charity number 214001 All content in this publication is, unless stated otherwise, the property of IGEM. Copyright laws protect this publication. Reproduction or retransmission in whole or in part, in any manner, without the prior written consent of the copyright holder, is a violation of copyright law. ISBN 978 1 9996747 0 0 ISSN 0367 7850 Published by the Institution of Gas Engineers and Managers Previous Publications: Communication 1756 (2011) 1 st Edition For information on other IGEM Standards please visit our website, www.igem.org.uk

IGEM/UP/16 Edition 2 Draft for Comment CONTENTS SECTION PAGE 1 Introduction 1 2 Scope 4 3 Legal and allied considerations 6 3.1 Health and Safety at Work etc. Act 6 3.2 Construction (Design and Management) Regulations 6 3.3 Dangerous Substances and Explosive Atmospheres Regulations 6 3.4 Gas Safety (Installation and Use) Regulations 7 4 Determination of hazardous area zone classification 8 4.1 Risk assessment 8 4.2 Containment 9 4.3 Zoning 9 4.4 Electrical discharges 10 4.5 Adverse conditions 10 4.6 Design 10 4.7 Commissioning 11 4.8 Safe maintenance 11 4.9 Ventilation 11 5 Information for commercial and industrial installation designs 13 5.1 Design and installation 13 5.2 Confined and congested installations 14 5.3 Confined installation 14 5.4 Congested installation 16 5.5 Ventilation 16 6 System design checklist for Zone 2 NE compliance 18 6.1 General 18 7 Inspection and maintenance 25 8 DSEAR risk assessments 26 8.1 Risk assessment 26 APPENDIX 1 Glossary, acronyms, abbreviations, units and symbols 27 2 References 29 3 Concepts and requirements for hazardous areas 31

IGEM/UP/16 Edition 2 Draft for Comment FIGURES 1 Operational pressure limits 2 2 Signposts to hazardous area classification 5 3 An example of pipework layouts showing preferred pipe locations for Zone 2 NE classification 15 4 Example of an installation with congested leak locations 16 5 Extent of the hazardous area surrounding potential leak sources 34 TABLE 1 Ventilation rates required to meet a Zone 2 NE classification 17 2 Assessment for above ground pipework with OP not exceeding 75 mbar 19 3 Assessment for above ground pipework with OP exceeding 75 mbar and not exceeding 2 bar 21 4 Assessment for above ground pipework in ceiling spaces or ducts 23

SECTION 1 : INTRODUCTION 1.1 This Standard has been drafted by an Institution of Gas Engineers and Managers (IGEM) Panel, appointed by IGEM s Gas Utilization Committee, and has been approved by IGEM s Technical Co-ordinating Committee on behalf of the Council of IGEM. 1.2 The Dangerous Substances and Explosive Atmospheres Regulations (DSEAR) came into force in December 2002 and the requirements for the preparation of risk assessments to determine any hazardous area classification first came into force on 30 th June 2003. They applied retrospectively to all installations within workplaces from 30 th June 2006. 1.3 The intent of this Standard is to provide basic design information to enable designers and those undertaking risk assessments to achieve a gas installation that can be classified and maintained as Zone 2 Negligible Extent (Zone 2 NE). It is intended primarily for designers of new industrial and commercial pipework systems, downstream of the primary gas meter installation. It will also be useful for site occupiers who have the responsibility for compliance with DSEAR and for the production of site risk assessments for new and existing installations. Hazardous area assessment is normally a specialist activity requiring the application of IGEM/SR/25 Edition 2. Where doubt exists about the applicability of IGEM/UP/16, reference is to be made to IGEM/SR/25 Edition 2. Note 1: Negligible extent (NE) is as described in BS EN 60079-10-1. Note 2: This document is intended for guidance to achieve a Zone 2NE classification and does not provide a procedure for a quantitative Zone analysis. 1.4 The advice on the preparation of risk assessments assumes that industrial and commercial gas installations and pipework have been designed, installed, commissioned and operated according to recognised standards such as IGEM/UP/2 and IGEM/UP/10. These assessments determine whether electrical equipment marked and declared as being suitable for use in a hazardous area are considered or used or if controls are required over other potential ignition sources such as hot surfaces, flames or sparks. 1.5 The Standard does not purport to cover every gas installation (see clause 1.6). The diversity of gas installations is such that it is inappropriate to provide detailed requirements for all types of installation covered by the scope of this Standard. It is recognised that special circumstances may occur, on an installation, for which some of these requirements will not, necessarily, be appropriate. In such cases, methods need to be developed by personnel of adequate competency and experience. 1.6 The scope of this Standard has been limited to methane based gas (for example, Natural Gas (NG)) installations with a nominal operating pressure (OP) not exceeding 2 bar due to in-depth test work performed within the United Kingdom (UK). For installations at pressure above 2 bar, specialist assistance is required and is outside the scope of this document. This may be obtained from equipment manufacturers or IGEM Consultants listed on IGEM s website. No advice can be given on hazardous areas for heavier-than-air-gases as they fall outside the scope of IGEM/SR/25 Edition 2 Nonetheless, a risk assessment is required and its recommendations complied with. Additional advice may be available from the fuel supplier or by referring to Energy Institute (EI) guidance IP-MCSP-P15 (see Appendix A2.5). These requirements will apply to all installations. DSEAR requires the minimisation and early detection of gas leakages together with good local ventilation; this may be achieved by design or by the use of safety controls and a suitable maintenance and inspection regime. It is recognised that the new 1

advice given in this Standard relating to DSEAR and the classification of hazardous areas may be difficult to comply with for existing systems. 1.7 Terms such as maximum operating pressure (MOP), maximum incidental pressure (MIP) and operating pressure (OP) reflect gas pressure terminology used in European standards. Referring to Figure 1, attention is drawn to how OP oscillates about the set point (SP). Note also that MOP can be declared at a higher value than OP. The strength test pressure (STP) has to be at least MIP and, in many cases, will exceed MIP. This means that, at least with respect to integrity, the installation will withstand a fault pressure from the upstream system. STP MIP Pressure MOP SP OP Time STP = Strength test pressure MIP = Maximum incidental pressure OP = Operating pressure MOP = Maximum operating pressure SP = Maximum set point of, typically, the active regulator. FIGURE 1 - OPERATIONAL PRESSURE LIMITS 1.8 This Standard makes use of the terms must, shall and should. Notwithstanding clause 1.13: the term must identifies a requirement by law in GB at the time of publication the term shall prescribes a requirement which, it is intended, will be complied with in full and without deviation the term should prescribes a requirement which, it is intended, will be complied with unless, after prior consideration, deviation is considered to be acceptable. Such terms may have different meanings when used in legislation, or Health and Safety Executive (HSE) Approved Codes of Practice (ACoPs) or guidance, and reference needs to be made to such statutory legislation or official guidance for information on legal obligations. 1.9 The primary responsibility for compliance with legal duties rests with the employer. The fact that certain employees, for example responsible engineers, are allowed to exercise their professional judgement does not allow employers to abrogate their primary responsibilities. Employers must: have done everything to ensure, so far as is reasonably practicable, that there are no better protective measures that can be taken other than relying on the exercise of professional judgement by responsible engineers 2

have done everything to ensure, so far as is reasonably practicable, that responsible engineers have the skills, training, experience and personal qualities necessary for the proper exercise of professional judgement have systems and procedures in place to ensure that the exercise of professional judgement by responsible engineers is subject to appropriate monitoring and review not require responsible engineers to undertake tasks which would necessitate the exercise of professional judgement that is beyond their competence. There should be written procedures defining the extent to which responsible engineers can exercise their professional judgement. When responsible engineers are asked to undertake tasks which deviate from this, they should refer the matter for higher review. 1.10 It is now widely accepted that the majority of accidents in industry generally are in some measure attributable to human as well as technical factors in the sense that actions by people initiated or contributed to the accidents, or people might have acted in a more appropriate manner to avert them. It is therefore necessary to give proper consideration to the management of these human factors and the control of risk. To assist in this, it is recommended that due regard be paid to HSG48. 1.11 Notwithstanding clause 1.10, this Standard does not attempt to make the use of any method or specification obligatory against the judgement of the responsible engineer. Where new and better techniques are developed and proved, they can be adopted without waiting for modification to this Standard. Amendments to this Standard will be issued when necessary, and their publication will be announced in the Journal of the Institution and other publications as appropriate. 1.12 Requests for interpretation of this Standard in relation to matters within the scope, but not precisely covered by the current text, may be addressed in writing to Technical Services, The Institution of Gas Engineers and Managers (IGEM), IGEM House, High Street, Kegworth, Derbyshire, DE74 2DA and will be submitted to the relevant Committee for consideration and advice, but in the context that the final responsibility is that of the engineer concerned. If any advice is given by or on behalf of IGEM, this does not relieve the responsible engineer of any of his or her obligations. This Standard was published in xxxxx. 3

SECTION 2 : SCOPE 2.1 This Standard covers new gas installation pipework, controls and associated gas appliances including appliance connections and pipework with an OP not exceeding 2 bar installed downstream of the primary meter installation in industrial and commercial premises. It may also apply to parts of common pipework within multi-occupancy domestic premises; for example, between pipework risers downstream of the meter installation and also to the central boiler plant (see Figure 2). For hazardous area analysis of installations outside the scope of this Standard, reference may be made to IGEM/SR/25 Edition 2. Note 1: Installation pipework includes appliance connection, pipe joints and fittings. Appliance pipework located within appliance casings or integral with the appliance is subject to the requirements of appliance Standards and thus outside the scope of IGEM/UP/16. Note 2: In this Standard where the term joint is used, it refers to all joints other than welded, soldered or brazed joints. Note 3: Gas appliances (where the gas is at a temperature of 15 O C under a pressure of 1 bar) which are used for cooking, heating, hot water production, refrigeration, lighting or washing; and have, where applicable, a normal water temperature not exceeding 10 o C are excluded from DSEAR. Industrial process plant may, however, need a DSEAR risk assessment. 2.2 This Standard covers gas installations containing predominantly methane such as Natural Gas. It applies to all gases, including landfill or biogases, with a combined proportion of methane-plus-inerts of greater than 89% by volume; a gross calorific value not exceeding 45 MJ m -3 ; molecular weight not exceeding 20 kg kmol -1 ; LFL of not less than 4.4%; a temperature range of 20 C to 50 C and specific gravity not exceeding 0.8. Ambient temperatures are assumed to be in the range 20 C to 35 C. Note: The general principles in this document may be applied to other gases, zone classifications and zoned extents are not covered by this document, reference should be made to the fuel supplier or appropriate reference documents such as EIIE 15 and SANTON R., IVINGS M.J., WEBBER D.W. and KELSEY A. New Methods for Hazardous Area Classification for explosive gas atmospheres Hazards XXIII, 12-15 Nov 2012 2.3 This Standard provides basic design information which will help designers and those undertaking risk assessments (including those required by DSEAR) to achieve a gas installation that will achieve a hazardous area analysis permitting the use of standard electrical equipment and other potential ignition sources and to be classified as Zone 2 NE (that is, not require the provision of electrical equipment suitable for areas/spaces classified as Zone 0, 1 or 2 or removal of the other potential ignition sources). The description of this topic is given in Appendix 3. A description of duties under DSEAR is given in Sub-Section 3.3. Note 1: Zone 2 NE is defined as an area in which an explosive atmosphere consisting of a mixture of air with gas, vapour or mist is not likely to occur in normal operation, but if it does occur, will exist for a short period only before detection and repair and would be of negligible extent. The resultant ignition if it did occur would be such that it would be unlikely to injure persons or damage buildings. Note 2: Zone 2 NE is achieved when the background concentration in the enclosure is less than 10% Lower Explosive Limit (LEL). Note 3: HSE RR630 and IGEM/SR/25 introduced a criteria by setting an upper limit of 1 g/s for allowing a Zone 2NE classification. Note 4: There will be areas which in general will not be classified as NE, such as terminations i.e. vent outlets, pipe vents and relief valves. 2.4 The following are not covered by this Standard: installation pipework downstream of the ECV within a domestic dwelling any part of a primary meter installation (see IGEM/GM/7B). 4

2.5 Pressures quoted are gauge pressures unless otherwise stated. 2.6 This Standard considers the specific gravity of air to equal 1. 2.7 Italicised text is informative and does not represent formal requirements. 2.8 Appendices are informative and do not represent formal requirements unless specifically referenced in the main Sections via the prescriptive terms must, shall or should. INSTALLATION PIPEWORK Requires hazardous area classification Is the premises industrial or commercial? It may also apply to parts of common pipework within multi-occupancy domestic buildings, e.g. to pipe risers downstream of the meter installation and central boiler plant. NO OUT OF SCOPE OF THE STANDARD YES Does the MOP exceed 2 bar? Are there unusual site circumstances? See Note ANY YES GO TO IGEM/SR/25 NO CLARIFY INSTALLATION IN ACCORDANCE WITH IGEM/UP/16 FIGURE 2 - SIGNPOSTS TO HAZARDOUS AREA CLASSIFICATION Note: Unusual site circumstances would include the presence of persons, processes or conditions that have potential to increase the risk of an incident. 5

SECTION 3 : LEGAL AND ALLIED CONSIDERATIONS This Standard is set out against a background of legislation in force in the GB at the time of publication. The devolution of power to the Scottish, Welsh and Northern Ireland Assemblies means that there may be variations to the legislation described below for each of them and consideration of their particular requirements must be made. Similar considerations are likely to apply in other countries where reference to appropriate national legislation is necessary. All relevant legislation must be applied and relevant ACoPs, official Guidance Notes and referenced codes, standards, etc. need to be taken into account. Note: Appendix 2 is relevant in this respect. Where British Standards, etc. are quoted, equivalent national or international standards, etc. equally may be appropriate. Note: With particular respect to standards quoted, it is essential that the equivalent standard will achieve at least the same level of gas integrity and acceptable risk to life and property. This Standard has been written to assist designers, installers, contractors and asset owners of Natural Gas systems to comply with the requirements of DSEAR. 3.1 HEALTH AND SAFETY AT WORK ETC. ACT (HSWA) HSWA applies to all persons involved with work activities, including employers, the self-employed, employees, designers, manufacturers, suppliers, etc. as well as the owners of premises. It places general duties on such people to ensure, so far as is reasonably practicable, the health, safety and welfare of employees and the health and safety of members of the public who may be affected by the work activity. 3.2 CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS (CDM) CDM Regulations require Designers for all construction projects (not just notifiable ones) to eliminate hazards and reduce risks during design. They must also provide information about remaining risks. 3.3 DANGEROUS SUBSTANCES AND EXPLOSIVE ATMOSPHERES REGULATIONS (DSEAR) 3.3.1 DSEAR require the responsible person for the premises (the employer ) to perform a risk assessment of each part of the gas installation to determine whether or not there are risks of gas leakage leading to potentially explosive atmospheres. The responsible person then has to determine whether protective measures (for example, such as the use of electrical equipment certificated for use in hazardous areas or the removal of other potential ignition sources) are required. Furthermore, employers are required to classify places at the workplace as hazardous (that is, where explosive atmospheres may occur) or non-hazardous areas. Any person engaged in the preparation of a risk assessment of gas installations with respect to DSEAR must be suitably competent. 3.3.2 DSEAR require the responsible person for the premises to co-operate with others working on the site to share safety information relating to the safety of the gas installation. 6

3.3.3 It is recognised by the gas industry and the HSE that it could be helpful to provide generic risk assessments and other information to site operators and installers. 3.3.4 DSEAR is an expansion of the general duty to manage risks under the Management of Health and Safety at Work Regulations (MHSWR) and require good practices that reduce risk to persons from explosions and fires etc. which, in turn, are caused by dangerous substances. DSEAR identifies requirements for the preparation of risk assessments to determine any hazardous area classification. This applies retrospectively to relevant installations within buildings from 30 th June 2006. 3.3.5 DSEAR deals with fires, explosions and similar energy releasing events, for example exothermic chemical reactions, arising from dangerous substances (chemical agents) and the explosive atmospheres created by those substances. 3.3.6 This Standard provides information relating to those risk assessments for wellengineered gas installations. These requirements indicate whether equipment certified for use in a hazardous area should be considered or applied or if other potential ignition sources need to be removed from the area. It is recognised that not all existing installations installed before the publication of this Standard will comply with this new advice. In these cases, the conclusions of the Risk Assessment need to be applied and complied with. In particular, routine inspections and checks (carried out at least annually) for the presence of combustible gas should be recommended. 3.4 GAS SAFETY (INSTALLATION AND USE) REGULATIONS (GS(I&U)R) 3.4.1 GS(I&U)R are relevant statutory provisions of HSWA setting out general and detailed requirements dealing with the safe installation, maintenance and use of gas systems, including gas fittings, appliances and flues. Note: GS(I&U)R does not apply to certain premises (see HSL56 Guidance Notes 28 and 29). However, where they do not apply, the principles of GS(I&U)R need to be applied. 3.4.2 GS(I&U)R place responsibilities on those installing, servicing, maintaining or repairing gas appliances, pipework, etc., as well as suppliers and users of gas. 3.4.3 GS(I&U)R define the type of work that requires persons carrying out such work, or their employers, to be an approved class of person, for example currently Gas Safe registered. 3.4.4 The installer must check the safety of any appliance or pipework they install or work on and take appropriate action where they find faults. Where the premises are let or hired out, the landlord or hirer has special responsibilities to ensure that any installer they use for the gas fitting, service or maintenance or safety is a member of an approved class of persons and is competent to carry out such work. If any serious fault is found, the installer must inform both the landlord/hirer, as well as the user, so that such faults can be rectified before further use. 7

SECTION 4 : DETERMINATION OF HAZARDOUS AREA ZONE CLASSIFICATION The UK gas industry s past safety record indicates that properly installed, tested and maintained equipment does not pose significant explosion risks. This Standard uses assumptions made to enable a simplified approach for hazardous area classification for installation pipework, to enable a Zone 2 NE to be adopted whenever possible (see Appendix 3). It is not intended as a procedure to enable the assessor to quantitively provide a zone analysis. This Standard does not address either Continuous or Primary Grade release (see Appendix 3) or catastrophic failure, for example regulator diaphragm rupture or a fractured pipe. A simplified overview of the various terms used within the gas industry for hazardous areas are given in Sub-Sections 4.1 to 4.9. For more detailed information see IGEM/SR/25 Edition 2. Modern gas installation Standards require designers and installers to consider the overall safety of the system using risk assessment techniques. These considerations are mostly from a viewpoint of combustion and potential explosions associated with gas leakage with respect to the safety of the structure and of persons. The intention is to have any potential problems designed out before construction. It is important however, to consider the existence of hazards from other sources, for example flammable dusts, solvents, corrosive substances in the local environment. An internal zone classification within gas pipes is not required for the purposes of DSEAR because there is no risk of ignition of the gas. 4.1 RISK ASSESSMENT 4.1.1 Dangerous substances can put peoples safety at risk from fire and explosion. DSEAR places duties on employers and the self-employed to protect people from risks to their safety from fires, explosions and similar events in the workplace, this includes members of the public who may be put at risk by the work activity. Thus specific risk assessments shall be prepared for work procedures to ensure the safety of the work. 4.1.2 One of the duties under DSEAR is that the site occupier must prepare and keep up to date risk assessments for flammable gas installations on the site. These assessments will often be prepared during the design and construction stages of a project and are then checked and verified prior to commissioning. They should form part of the overall site risk assessment. Note 1: The gas system designer and the equipment manufacturer are often best able to advise companies on the content of the Risk Assessments (see Section 8 and Appendix 3 and 4). Note 2: Primary meter installations are the responsibility of the Gas Supplier/Meter Asset Manager who is responsible for the Risk Assessment and area zoning, where the meter installation is on the consumer s site it should be incorporated in the site DSEAR. 4.1.3 The occupier shall ensure the risk assessments are competently completed and kept under review as site changes occur. 4.1.4 There are many methods of producing these assessments and detailed advice can be found in IGE/SR/24. However HSE publish a simple guide called "5 Steps to risk assessment" (INDG163) and the appendices of this Standard use that simpler format as a guide to what actions and precautions should be put into place when assessing flammable gas installations. 8

4.2 CONTAINMENT 4.2.1 Gas pipework Standards have been developed in the UK and elsewhere over many years with the objective of long-term safe containment. In the UK these are encompassed in IGEM/UP/2, BS EN 50001 and BS 6891. In association with tightness testing procedures as given in IGE/UP/1, IGE/UP/1A and IGE/UP/1B, pipework systems shall be adequately validated for gas tightness from new and during their lifetime. 4.2.2 To achieve a zonal classification of Zone 2 NE, pipework containing joints and associated system/appliances should be installed in areas with sufficient ventilation. The industry uses the terms confined (see Sub-Section 5.3) and congested (see Sub-Section 5.4) to try to categorise this issue. However, both need a degree of engineering judgement with a confined installation being the most severe (see IGEM/SR/25). 4.2.3 Where unodorised gas is used, the risk assessment and operational procedures shall take account of the lack of smell. Local gas detection and/or increased inspection frequency may be necessary (see IGEM/SR/25 Edition 2). 4.2.4 In considering leakage rates from joints and fittings, this Standard uses the term Notional Leak Size. For the purposes of this Standard the following categories shall be used: for pipework with OP not exceeding 100 mbar a leak size equivalent to that which would escape from a hole of 0.025 mm 2 is used for calculation purposes for pipework with OP exceeding 100 mbar and not exceeding 2 bar a leak size equivalent to that which would escape from a hole of 0.25 mm 2 is used for calculation purposes. This size is also used for those installations with OP not exceeding 100 mbar where there are vibration issues to be considered for pipework with OP exceeding 100 mbar and not exceeding 2 bar, where there are vibration issues to be considered, a leak size equivalent to that which would escape from a hole of 2.5 mm 2 is used for calculation purposes. 4.3 ZONING Note 1: The larger hole sizes are applicable where the vibration is such as may lead to premature failure. This may be relevant to some shaft seals and flexible pipes used on reciprocating machines. Note 2: Catastrophic pipe failures are not required to be considered for area classification. However, suitable control measures will need to be applied. 4.3.1 Work by the Health and Safety Laboratories (HSL) and subsequent considerations within IGEM/SR/25 Edition 2 have indicated that low pressure gas pipework, joints and fittings may not generate a hazardous area of Zone 2 classification. However, low pressure gas pipework joints and other leakage sources will always require a minimum Zone 2 NE classification. This classification of Zone 2 NE assumes that the pipework and associated controls have been designed and installed to recognised Standards such as IGEM/UP/2, located in an sufficiently ventilated area and are well maintained. Where this is not the case, then the classification of the Zone shall be at least Zone 2 and consideration shall be given to seeking more specialist advice. 4.3.2 This Standard provides assistance to the designer and risk assessors to determine if the design could be classified as Zone 2 NE. Further information is provided on the detail of designs in IGEM/UP/2 and IGEM/UP/10. Designs not meeting the requirements for Zone 2 NE must use electrical equipment suitable for use in the zoned area and the removal of other potential ignition sources and a more detailed analysis and risk assessment by competent persons. 9

4.4 ELECTRICAL DISCHARGES Metallic gas pipework systems should be cross bonded to earth, not only to reduce electric shock risk to persons, but to also reduce any dangers of sparking due to electrical faults leading to ignition of any gas leakage, however caused. Non-metallic gas pipework is not normally permitted above ground inside buildings. Note: Further information can be found in IGEM/UP/2. 4.5 ADVERSE CONDITIONS 4.6 DESIGN To determine whether adverse conditions are present, the following factors shall be considered, whether: there is any vibrating equipment which may lead to premature failure of any part of the gas system or components the gas is potentially corrosive the installation is operating in a potentially corrosive atmosphere/ environment, for example a coastal site. If any of the above factors exist, the installation shall be treated as operating in adverse conditions. 4.6.1 The initial design of the complete gas system downstream of the ECV needs to be such that as far as practicable it can be classified as Zone 2 NE. 4.6.2 To achieve Zone 2 NE, sufficient local ventilation around every gas pipework joint (other than welded, soldered or brazed joints) or potential gas leakage source shall be provided. Confinement (see Sub-Section 5.3) and congestion (see Sub-Section 5.4) will normally restrict the availability of ventilation which may restrict the possibility of achieving a Zone 2 NE classification unless other measures are taken, for example, by the use of lower gas pressures, increased local ventilation or more frequent inspections. Note: A zone of negligible extent is not the same as a safe area, even though neither requires action with regard to the installation of zoned equipment or removal of other potential ignition sources. It is important to note that both a safe area and a zone of negligible extent can become more onerous if changes are made to the system, for instance pipework alterations are made or ventilation is reduced during modifications to buildings. 4.6.3 For existing installations, changes shall not be made to any pipework installation or the nearby environment that may adversely affect the assessment as Zone 2 NE. This may include for example, altering ventilation, addition of a boiler, changes to the structure where the change may affect ventilation air flows. 4.6.4 It is not a requirement to sign the area or to produce drawings of installations showing Zone 2 NE classification. However, site technical files shall include both the risk assessments and information on those sections of pipework that are declared Zone 2 NE. This may be identified on the site line diagram. 10

4.7 COMMISSIONING 4.7.1 DSEAR and the GS(I&U)R require that any gas installation is verified as being safe before gas is admitted to the pipework and first use of equipment. Systems shall also continue to remain safe. 4.7.2 If a workplace contains areas that are, or will be, classified as hazardous under Regulation 7(1) of DSEAR, the employer must ensure that work equipment in the hazardous area is safe. Protective systems in use within these areas must be safe for use, and work activities may need to be detailed so that they can be carried out safely, before the workplace is used. These actions, collectively, are termed verification. The employer must ensure that the person(s) who carries out the verification is competent to consider the risks in the space and to determine the adequacy of the safety measures in order to ensure explosion safety. 4.8 SAFE MAINTENANCE Consideration shall be given to the adequacy of ventilation and removal of sources of ignition before and during maintenance. This may form part of a Permit to Work system. 4.9 VENTILATION 4.9.1 Ventilation should provide local air movement in all positions where a pipe joint or leakage source is located to provide good dispersion of any leaking flammable gas. Soldered, welded and brazed pipework has a major design advantage over jointed systems using screwed, flanged or mechanical joints. In this respect, to limit the potential for gas leakage IGEM/UP/2 permits the use of threaded pipe joints up to and including 50 mm nominal bore for pressures up to and including 500 mbar and for 25 mm nominal bore above 500 mbar. When determining ventilation, air change rates can be misleading since a large room with a low air change rate could have the same air flow for dispersion of a leak as a small one with a high air change rate. For example, a large warehouse or a boiler house might only have a small local gas pipe to an appliance in one corner and only require local ventilation. Similarly a small volume boiler space could be densely packed with boilers and the pipework require intensive ventilation and good air flows throughout. 4.9.2 Most methane based gases, being lighter than air will rise to a high point in a space. Thus any space above the highest ventilator location will not continue to be as well diluted. Additional measures should be applied if there are joints/leakage sources above the highest ventilation location. 11

4.9.3 As far as practicable for natural ventilation of internal spaces, the ventilation grilles should be located on all four walls and at both high and low levels. Note 1: This is not always a reasonable solution in all installations. For instance, a large installation with a boiler in the corner of a warehouse will require a different solution. For confined or congested installations or dead areas where the local ventilation is poor, the design of the pipework shall require a greater use of welded/jointfree systems (see Section 6). Note 2: Leakage locations can be described as being obstructed (where the installation is confined and/or congested (see Sub-Section 5.2 and 5.3) or unobstructed. Note 3: For open air external locations, it is unlikely that the congestion will be so severe that it would require classification as Zone 2 for pressures not exceeding 2 bar. To prevent gas leakage from passing from one space to another, joints/leakage sources immediately adjacent to openings should be avoided. Joints/leakage sources should be at least 0.5 m from such openings. Note 4: More frequent inspection and maintenance visits may be required for jointed systems (see Section 6). 4.9.4 In very congested areas, even well designed natural ventilation may not be enough to attain classification as Zone 2 NE. Equally areas within a space that are poorly ventilated, that is stagnated or if dead areas are present they may be not be able to attain classification as Zone 2 NE. Then they should be classified as Zone 2 and reference made to IGEM/SR/25 Edition 2. 12

SECTION 5 : INFORMATION FOR COMMERCIAL AND INDUSTRIAL INSTALLATION DESIGNS It is recognised that many employers, site occupiers and responsible persons may not be conversant with the implications of DSEAR. Consequently, those installing gas installations should where appropriate, advise on gas safety for the employer, site occupier or responsible person. 5.1 DESIGN AND INSTALLATION 5.1.1 During the initial design and when changes are being planned it is important to minimise the number of pipework joints, to ensure adequate ventilation and to provide access for inspection and maintenance. Therefore adopting all welded/brazed or soldered construction and/or thicker walled pipework, use of corrosion resistant materials and freedom from adverse conditions will be a major advantage. The installation shall comply with IGEM/UP/2, which amongst other things includes requirements on wall thickness and corrosion prevention. In addition the following shall be considered during the design and subsequent installation. 5.1.1.1 In un-obstructed locations, the areas around the pipework joints with an OP not exceeding 2 bar may be considered as Zone 2 NE provided they are in a space that has sufficient ventilation (see Table 1). Note: A plant room will require the provision of ventilation for combustion, cooling and gas safety dispersion using the largest requirement. 5.1.1.2 In congested or confined locations (See Sub-Sections 5.3 and 5.4) the areas around pipework joints will be considered as Zone 2 with a discrete zoning distance. If the ventilation requirements set out in Table 1 are met then the zone may be classified as of negligible extent i.e. Zone 2 NE. Note: Gas detectors are not a substitute for sufficient ventilation. 5.1.1.3 Where joints are located in vertical ducts they shall have top and bottom ventilation direct to outside or normally habitable spaces (see BS 8313 and IGEM/UP/2). Any duct or void containing gas pipework shall be ventilated to a level that ensures a gas escape does not cause the atmosphere within the duct or void to become unsafe, this is an essential requirement for a Zone 2 NE classification. To achieve Zone 2 NE the duct or void will need to comply with the ventilation rates in Table 1. Any ventilation opening shall lead to a safe place, preferably to outside air. Where a duct, is contained solely within a room or space, it may be ventilated within that room, provided the room is sufficiently ventilated (see Table 1) and that the duct does not contain other pipe services (see IGEM/UP/2) which require a fire separation barrier to be maintained (refer to the Building Regulations). Note: Where grilles are installed in the ceiling to ventilate via the room, it should be ascertained that circulation of ventilation air provides sufficient air flow over the potential leak sources. 5.1.1.4 Where joints are located in horizontal ducts (not buried) and small spaces may be considered Zone 2 NE provided they have an internal volume not less than 10 m 3 and adventitious ventilation above sufficient ventilation. If it does not meet ventilation requirements or is less than 10 m 3 then the space will need to be zoned in accordance with IGEM/SR/25. 13

5.1.1.5 Where pipework with potential leak sources and an OP not exceeding 500 mbar is located in below ground spaces such as basements or rooms that are visited less than six monthly, ventilation shall be such as to ensure the air change rate is above sufficient ventilation (see Table 1). Where this inspection is not practicable, consideration shall be given to the provision of gas detection with flow interlocks and AIVs. Note: Gas detectors are not a substitute for sufficient ventilation but may be used as additional protection as part of a risk assessment For below ground spaces where the OP exceeds 500 mbar see Table 3 or see IGEM/SR/25 Edition 2. 5.2 CONFINED AND CONGESTED INSTALLATIONS 5.2.1 In a situation where the jetting effect is hampered the crucial dilution of the leak is affected may need to be zoned differently. IGEM/SR/25 leaves the evaluation of a confined or congested zone down to subjective judgement. IGEM/SR/25 however does provide guidance and gave a quantitative definition that a leak within location of within 0.5 m of two walls and a floor/ceiling could not be classified as Zone 2 NE without addition ventilation.(see note below) In this case where the potential leak location is close (less than 0.5 m) to three or more significant obstructions, for example walls and a large item of plant then the space around the potential leak location should be described as confined, see Figure 3. The floor will often count as one of the significant obstructions, which means that a leak located in the corner of an enclosure (where two walls and the floor meet) will be confined. Note: The distance to the obstructions has been reduced from the 1 m quoted in IGEM/SR/25 to 0.5 m due to the lower pressures applicable to this standard. 0.5 m is the hazardous distance in IGEM/SR/25 for a confined or congested release at 2 bar with more than adequate ventilation. 5.2.3 For large enclosures (>100 m 3 ) the effectiveness of the ventilation at the release sources will need to be assessed and verified if necessary. 5.2.4 For installations 75 mbar where a joint is within 0.5 metre of 3 surfaces Zone 2 NE can be achieved by the provision of natural or mechanical local ventilation to provide gas dispersion at the joint. The effectiveness of the ventilation at the release sources will need to be verified. Where local ventilation cannot be provided the classification of Zone 2 NE can be achieved by increasing the inspection frequency to 3 months. Where the inspection frequency is increased a system design verification notice (SDVN) to that effect is required to be displayed to assist the duty holder and those performing work on the installation. In this respect, the adoption of this procedure needs to be made by a Competent Person with respect to gas safety issues. Note: The inspection is intended to identify small leaks before they develop into a hazard. Alternatively to increasing the maintenance frequency a Zone 2 may be applied (see clause 5.3.1). 5.3 CONFINED INSTALLATION 5.3.1 A confined leak location within the above criteria which cannot be considered as 2 NE will require an assessment of the degree of local ventilation in comparison to the leak size and therefore Zone 2 rather than Zone 2 NE may need to be applied or alternatively local ventilation would need to be applied, such as ventilation grilles or a mechanical air supply (see Section 7). 14

Where a Zone 2 is applied no ignition sources which includes electrical equipment and appliances shall be installed within 0.5 metre radius of the joint. Where confining surfaces or components will disrupt the jetting effect from the leak source, confined installations will usually be internal locations. Figure 3 illustrates an example of a confined joint (5.2.4) within the red sphere where its location is within 0.5 m of three surfaces, this would need to be considered as Zone 2, unless specific sufficient local ventilation can be introduced. The blue sphere illustrates an alternative scenario where the third surface and 0.5m are no longer present which subject to sufficient ventilation can be considered Zone 2NE. FIGURE 3 - AN EXAMPLE OF PIPEWORK LAYOUTS SHOWING PREFERRED PIPE LOCATIONS FOR ZONE 2 NE CLASSIFICATION 15

5.4 CONGESTED INSTALLATION A congested leak location is one where there is a significant amount of small scale obstacles that compromises the ventilation flow rate through that area. It is possible that such an area, while congested, may not be described as confined if there are no (or very few) large scale obstructions (surfaces) to the ventilation flow in that area to disrupt the jetting effect. 5.4.1 In cases that are initially identified as congested, but not confined, it is possible that by further investigation (for example through tracer gas techniques, the use of artificial smoke or mathematical modelling), it may be possible to demonstrate that the leak location is in fact reasonably well-ventilated. In such cases, assuming that other requirements are met, then Zone 2 NE may be applicable. Where the pipework in an outside location and is congested, where wind speeds in the area are typically above 0.5 m/s they can be considered as an open space. A Zone 2 classification requires the absence of any ignition sources, with the area have an adequate Ex rating there are no issues with gas pipework in that area. FIGURE 4 - EXAMPLE OF AN INSTALLATION WITH CONGESTED LEAK LOCATIONS 5.5 VENTILATION The minimum natural ventilation requirements for jointed pipework to provide Zone 2 NE classification are shown in Table 1. 5.5.1 The ventilation should be on all four walls of the space where possible. Where this is not achievable, the ventilation should be located on as many walls as possible. The ventilation shall be located to provide good air distribution throughout the space and especially where the pipework is located. High level vents should be as high as practicable. 16

5.5.2 Where good internal air movement cannot be provided by natural ventilation, it shall be enhanced by the use of interlocked mechanical ventilation to ensure Zone 2 NE remains applicable. Note: Where natural draft appliances are installed see IGEM/UP/10 for ventilation requirements. 5.5.3 In mechanically ventilated spaces there should be good mixing of the air and any potential gas leakages to avoid dead spaces and re-entrainment of gas into the dispersing gas/air mixtures. Good mixing is promoted by open location of pipe joints, proper sizing and placement of ventilation grilles to ensure air movement across the potential leak locations. Room Volume (m 3 ) Pressure (mbar Air Changes/h Ventilation rate (m 3 /s) * Air changes/h (congested) see note Air changes/h (congested or see note confined) Pressures up to 100 mbar (0,025 mm 2 leak size) Non adverse condition 10-100 Up to 100 0.5 0.001 0.5 0.5 Pressures 100 2000 mbar (0.25 mm 2 leak size) 10 100 1 0.003 2 3 500 2 0.006 4 6 2000 4 0.011 8 12 50 100 0.5 0.003 0.5 0.5 500 0.5 0.005 1 2 2000 1 0.011 2 3 100 100 0.5 0.003 0.5 0.5 500 0.5 0.006 0.5 1 2000 0.5 0.011 1 2 Pressures 100 2000 mbar (2.5 mm 2 leak size) 10 100 11 0.5 24 36 500 24 0.1 50 75 2000 60 0.2 120 180 50 100 3 0.5 6 19 500 5 0.1 10 15 2000 12 0.2 24 36 100 100 2 0.5 4 6 500 3 0.1 6 9 2000 6 0.2 12 24 TABLE 1 - VENTILATION RATES REQUIRED TO MEET A ZONE 2 NE CLASSIFICATION (non adverse condition) Note 1: Table 1 covers a single leak scenario and that with multiple potential leak sources and infrequently visited sites reference should be made to SR/25. Note 2*: These figures are for broad guidance, it is necessary to ensure the actual ventilation rate will achieve at least 0.5 ac/h. For small room volumes adventitious ventilation may be sufficient. Note 3: A minimum rule of thumb of 1.4 cm 2 /m 3 /ach may be applied to both inlet and outlet grilles as a sizing conversion factor for velocity to area, however account must be taken of specific grill pressure drops and grill location, sheltered locations may require larger areas. 17

SECTION 6 : SYSTEM DESIGN CHECKLIST FOR ZONE 2 NE COMPLIANCE 6.1 GENERAL 6.1.1 The following Tables are a guide to a good Zone 2 NE compliant design. Consideration of the information should provide the minimum ventilation required for DSEAR compliance. In many cases the installed ventilation will be in excess of the sizes to satisfy standards such as BS 8313 and IGE/UP/10. Note: Where mechanical ventilation is used to provide DSEAR ventilation the fans shall be interlocked with the gas supply. The checklists are designed to take the reader through the thought process starting from question 1 in the appropriate Table. The answer is simply yes or no and the solution is explained to each. If the solution is in red text this signifies what further action is required and the green text signifies reaching a conclusion to the assessment. 6.1.2 For installations which are both mechanically and naturally ventilated, an assessment should be carried out in using Tables 2 to 4. 18

QUESTION YES ANSWER NO 1a Does the fuel gas being utilised have a SG not exceeding 0.8? Go to Question 2a (See Note 2) Note 1: SG of Natural Gas is 0.6. Note 2: BS EN 67009-10 and EI IP-MCSP-P15 give guidance on other gases, these may not contain the same degree of practical advice as given in this Standard for Natural Gas. Advice from the gas supplier could also be sought. 2a Is the OP not exceeding 75 mbar? Go to Question 3a 3a Is the installation in an external space with no confinement/congestion (see Sections 5.2 and 5.3)? 4a Is the space greater than 10 m 3 volume? 5a 6a 7a 7b 7c 7d 7e 8a Is the pipe work installation in good condition and correctly installed and free of vibration with any equipment likely to cause vibration connected by flexible connections? Is the installation and all pipe joints located below the high level ventilation grilles? Are all pipe joints more than (0.5) 1 m from 3 surfaces (see Sub- Section 5.2)? Is local ventilation provided for all pipe joints within 0.5 m of 3 surfaces Has a documented local Zone 2 been applied around the joints and is the Zone 2 free of any ignition sources? Is the area subject to a documented inspection regime and visited at least three monthly to detect any leakage of gas or is gas detection fitted Is a supplier s design verification notice (SVDN) displayed in the installation advising of inspection requirements and any Zone 2 areas. Is the area visited at least six monthly to detect any smells of gas? Classify and maintain Zone 2 NE Go to Question 5a Go to Question 6a Go to Question 7a Go to Question 8a if ventilation is compliant with SR/25 Go to Question 8a Remaining area could be Zone 2 NE Go to Question 8a Go to Question 7e Go to Question 8a Go to Question 8b See Table 3 See Question 4a Non-Compliant comply with IGEM/SR/25 Edition 2 Non-Compliant Non-Compliant improve local ventilation or comply with IGEM/SR/25 Edition 2 See Question 7b See Question 7c Remaining area could be Zone 2 NE go to 7d Non-Compliant Apply inspection regime Or fit gas detection Non-Compliant Non-Compliant Apply inspection regime 8b Is the pipework installation subject to a documented inspection regime? Go to Question 9a Non-Compliant Apply inspection regime 9a Is the area free of congestion? Go to Question 9b Go to Question 9c 9b Is Natural ventilation provided for >1 (0.5?) air change per hour. Minimum Grille area 1.4 cm 2 per m 3 of enclosure (see Note 3) 9c Is Natural ventilation provided for >3 air change per hour. Minimum Grille area 4.2 cm 2 per M 3 of enclosure (see Note 3) Go to Question 10a Go to Question 10a Go to Question 9d Go to Question 9d 19