Rail Grinding & support teams

Similar documents
Risk Assessment Form

2.0 Management Systems and Documentation

BHC-P-07.2 Health Hazards in Construction

Hautbois Risk Assessment

Collision Repair Shop Inspection Checklist

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

Contractor / Exhibitor Handbook

HAZARD IDENTIFICATION AND RISK ANALYSIS RECORD

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

Risk Assessment Form (Qualitative)

JOB HAZARD ANALYSIS FOR PPE

SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT

Module T7. Safe systems of work when walking or working on or near the line. Withdrawn Document Uncontrolled When Printed. GE/RT T7 Rule Book

Contractor handbook. Purpose

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

B S Glass Ltd Safety procedures- outsourced Workplaces

Hazard Identification and Risk Assessment Form. Risk Assessment

Work Activity (e.g. Road Work): Work Location:.

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL

FIRE HYDRANT TESTING METHOD STATEMENT.

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

You must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures.

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE OF MOWERS ASSESSMENT SCHEDULE

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK

SAFETY POLICY AND PROCEDURE MANUAL All Euramax Subsidiaries. Number K-3.0 Welding Safety Procedures

University College Dublin Machinery/Equipment Risk Assessment Template

Fire Safety Hot Work Permit Policy/ Procedures

CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY

Contractor Hazard Identification and Control Guide

PERSONAL PROTECTIVE EQUIPMENT

Safe Work Method Statement

The Yorkshire Waterways Museum, Dutch River Side, Goole, POND AND NATURE TRAIL RISK ASSESSMENT SHE/RA/00

SAFE WORK METHOD STATEMENT

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

Minimum Safety Requirements for Contractors Working on Railway Property

The Sample Company Pty Ltd

C-Consequence, P Probability, R-Risk Rating Value Page 2 of 2

Handbook 12. Issue 6. Duties of the engineering supervisor (ES) or safe work leader (SWL) in a possession. GERT8000-HB12 Rule Book

Personal Protective Equipment

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading

Western Sydney University Safety Inspection Checklist - Laboratory Environments

Working safely in an engineering environment

Field Instruction Storage, Handling, Transport and Disposal of Sulphur Hexafluoride (SF6) Gas

Appendix 4C - Sample SWMS Trenching

How severely could the risk hurt someone? Low/Insignificant First aid

Safe Work Method Statement Required for all High Risk Activities identified for the Project

Removing Frozen Clips

Bogo Operations Pollution Incident Response Management Plan

SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING

SAFETY MANAGEMENT SYSTEM

Risk Assessment June Skirmish Paintball Games Exeter

Automotive Safety Checklist

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title

TRADE AREA: ELECTRICAL INDUSTRY

Job Hazard/Safety Analysis For the Electrician

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS

75 Years of Health and Safety Guidance

Bitumen Delivery Driver Inductions Eurobitume UK

Potential risk of injury to staff

SAFE WORK METHOD STATEMENT Part B

SAFE WORK METHOD STATEMENT

Contractor OHS Induction. AOHS-05-GUI September 2016

HAZARDS AND RISKS ASSOCIATED WITH THE USE OF RIDE ON MOWERS

UETTDRRF06B PERFORM RESCUE FROM A LIVE LV PANEL LEARNER GUIDE

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS

Mine Dust Management Plan

Title: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11

Print PERSONAL PROTECTIVE EQUIPMENT

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...

How severely could the risk hurt someone? Low/Insignificant First aid

Safe Work Instructions For Oxygen Acetylene Equipment

Powerplay Paintball Brighouse Risk Assessment

Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015

APPENDIX A: Risk Assessment for all activities at Farm

Harbour Town Gold Coast Site Induction

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with?

Date Issued: November 2011 Revision Date: December 2012 Review Date: December 2015 Revision #

Airside Safety Airside Operational Instruction 07

Job Hazard/Safety Analysis For the Carpenter

TOOL BOX TALK NO3. Use of P.P.E

Temporary load-bearing support for structural alterations or repairs

Summary of Standards for Key Items of PPE

LPG SAFETY INFORMATION. Kwik-Gas. Safety Manual. Less talk more energy

EXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units

Personal Protective Equipment. Individual Unit Function: Safety Procedure No.: SOP-0147 Page: 1 of 9

HOT OILING OPERATIONS ALL HSE PRC 172. Approved By: Manager, HSE Performance Assurance. Table of Contents

Contractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.

Equipment Risk Assessment

GERM8000. Rule Book. Possession Workers Manual. Published by Rail Safety and Standards Board Limited

Doc No: WELDHOT Midland Engineering Co., Inc. Initial Issue Date 12/14/15 Safety Management System

Risk Management Resources

Lecture Demonstrations Safety Manual & New Staff Induction

QCF Unit and Assessment Specification

Infrastructure Requirements for Personal Safety in Respect of Clearances and Access

Handbook 16. Issue 4. AC electrified lines. GERT8000-HB16 Rule Book. September 2018 Comes into force 01 December 2018

SAFETY/RISK/HAZARD ASSESSMENT

High visibility jacket/tabard to be worn by all staff working on site and on the yard.

Transcription:

Working with On Track Machines Rail & Support Teams RCS No: TCS006 Issue: 1 Key Risks! in Possessions in Tunnels Fire in Electrified areas Working in the vicinity of OHL Noise/ Dust / Fumes Personnel Involved E&P S&T Track Off Track Property Plant / Engineering train Rail & support teams Harsco Train, Ground Support, Teams Key Risks Struck by train Walking & working in darkness / tunnels Level Crossing Failure on track & in possessions Controls All staff shall access the track in accordance with their duties and in accordance with all modules of the Railway Group Standard GE/RT8000 Rule Book The visitor shall be briefed on the SWP and accompany the COSS / SWL at all times (RS/502 COSS / SWL Handbook 10.2) Use authorised walking routes where available Only access and egress the track through authorised access points. All Controllers of Site Safety shall provide a site specific briefing on all hazards, the safe system of work, including the position of safety and access to and from the worksite. Wear high visibility clothing worn at all times in accordance with the Network Rail Personal Protective Equipment Policy When walking to and from worksites face oncoming traffic wherever possible ES shall confirm that prior to them starting work the OTM Operator receives an appropriate safety brief for their role and activities within the worksite. All employees shall be provided with personal lighting e.g. torch or headlamp when working in darkness or tunnels All worksites shall be provided with suitable temporary or permanent lighting The COSS / SWL shall brief all staff on hazards of working in darkness / tunnels and check that appropriate controls are in place Where loading / unloading road vehicles or performing other tasks on the road then lights on vehicles shall be used and other suitable barriers, lighting put in place Keep tools and materials clear of walking routes, walkways, refuges or recesses Communication between Route Conductor, Machine driver, Signaller & PICOP Via Mobile phone or face to face Spark guards shall be used Grind stone inspection procedure Remove sharks teeth to reduce build-up of grinding slag Implemented By Line Manager / All staff/ COSS/ Team Leader / ES All staff Signaller /level Crossing Attendant COSS / PICOP / operators / Page 1 of 5

in Tunnels Manual Handling Fire on the infrastructure Fire Decanting fuel and refuelling small plant Deploy a spill kit in the event of failure Operation shall be in accordance with GE/RT8000 Rule Book, SRO Procedures and site instructions received from the COSS / SWL as per SWP procedure. Carry out work in accordance with Section T of the Rule Book Pre-inspect equipment including checking against date on tag Use water spray bars, water cannon A pre-grinding risk assessment shall be carried out COSS / SWL shall brief all staff on the SWP for the work within the tunnel including the limited of the exclusion zone. A Risk Assessment shall be undertaken to assess air flow in the tunnel versus the production of dust and fumes by the. Where appropriate ventilation shall be provided. Egress - A Risk Assessment shall be undertaken for emergency evacuation in the event of an emergency such as fire or injury. Risk Assessment shall be undertaken as to the proximity of the work to Electrical Conductors and isolations taken as appropriate. Working in tunnel risk assessment should be provided within the SWP pack. If not, Grinder Machine shall complete using Harsco document before starting work. Work shall not commence until Machine Operator is completely satisfied with tunnel risk assessment is fit for purpose. Staff are trained and informed on manual handling techniques Manual handling risk assessments shall be undertaken for all manual handling activities. Rotate staff to reduce manual handling activities and give them frequent breaks Gloves shall be worn Use of metatarsal protection shall be considered to protect feet when moving heavy objects Comply with risk assessments highlighted within the SWP Pack. Spark guards shall be deployed. Spark blankets shall be maintained. Site shall be cleared of flammable material prior to work commencing. Grinders shall be rotated accordingly so as to direct all sparks to the 4ft. Damp down of vegetation and line side equipment whilst grinding, maintain water suppression equipment. Train staff on the use of the water cannon. Stop grinding if the possibility of fire is identified. Communication procedures in accordance with the Rule Book shall be maintained at all times Once minimum level of water for grinding is reached, grinding shall stop. Rear cab fire marshal shall remain vigilant for fires or potential fires and stop grinding and attempt to extinguish fire with cannon or hand held fire extinguishers. Ground support staff shall be present with fire aids Carry all fuel in suitable containers of the appropriate colour and/or marked with contents Secure all fuel before transporting Only carry the minimum amount of fuel you need for the planned activity Check that appropriate size spill kits and a 2kg Dry Powder fire extinguisher are available when transporting fuels. Decanting: Instructed by COSS/ SWL / PICOP & ES COSS / SWL / operators / All staff Machine GSM Rail Supervisor / Page 2 of 5

Fire on the grinding or in Tunnel in Electrified Areas Decanting and fuelling of plant shall only be performed by competent persons Wear eye protection (goggles) to BS EN 166.B when fuelling / decanting fuel. Wear good fitting impervious (PVC, Nitrile, or similar) gloves. Remove gloves at the end of fuelling / decanting and dispose of in approved waste containers If fuel is splashed / spilled onto clothing the clothing shall be removed and replaced and the skin cleaned. Wash hands before smoking, eating or drinking If hand washing facilities are not immediately available use antibacterial hand rubs or wipes. Where possible refuel all plant at the depot, rather than on site. Wear personal protective equipment, as detailed in the COSHH risk assessments for fuel. Undertake a pre-use check of plant to check that there are no leakages, that the fuel cap fits correctly and that the seal is fitted During hours of darkness check that suitable lighting is available DO NOT use naked flames Refuel all plant at least 10 meters from any worksite, other s or naked flames Take the plant to the fuelling point and not the fuel to the plant Smoking is not permitted within 10 meters of plant or fuelling points Make a fire extinguisher available at all fuelling points Before fuelling small plant check that it has cooled down significantly Slowly release the pressure with the fuel cap on the plant as hot fuel may be released under pressure Decant / Re-fuel s from the container using a flexible spout or funnel DO NOT fill / decant direct from the container Avoid spilling any fuel over the / container, if spilling occurs wipe off the excess fuel dispose of any rags as hazardous waste and check that they are kept apart from any ignition sources leave the for approximately two minutes before starting it up Check that the seal is in place and the fuel cap has been replaced and tightened correctly before starting the plant. Check that the fuel container cap has been replaced and tightened. Comply with risk assessments highlighted within the SWP Pack. Machine specific fire suppression systems to be maintained and documented. Fire extinguishers to be routinely checked during works. Communication procedures in accordance with the Rule Book are to be maintained at all times. All combustible materials are to be stored in the correct manner and protected from heat or sparks. CoSHH items also stored in accordance with the MSDS. Network Rail No Smoking Policy to be adhered to. Strict maintenance regime of hydraulic, fuel Regular Fire Drills Head and hand held Torches maintained at all times, Tunnel Risk assessment to be applied. Request for removal of unneeded obstacles. SPML s to carry out specific pre tunnel grinding preparation All lines in tunnel bore blocked to traffic PIC to maintain safe area around the Grinder Personal Tract Safety (PTS) Certificate to include DC/AC Electrified Lines. SWP Pack to be adhered to. PIC / Rail Grinder Supervisor / COSS / SWL Page 3 of 5

Noise COSS / SWL / DP Brief to be complied with. Compliance with the Operational Brief Transiting, working moves and grinding on OLE electrified lines Compliance with the Rule Book GE/RT8000/AC-DC. Fire Fighting Training for all Operational Rail Staff. Regular Fire Drills are to be carried out and documented Vertical movement of the cannon is to be regularly checked Staff must be competent in the Communication procedures to the Signaller and ECO to switch power off Strictly controlled and monitored settings of a maximum field angle on third rail that must not exceed -13. Lifting of the carriages if equipment gaps are found to be inadequate. Operated under T3 with a B3 isolation. Transiting, working moves and grinding on D.C electrified lines Correct use of authorised PPE, including approved and appropriate hearing protection to standard BS EN 352. Observation of the agreed Exclusion zone. All Staff Vibration Staff rotation to reduce exposure and include rest periods Use of gloves to keep hands warm & dry Do not bridge anti vibration handles Diesel Fumes Exclusion zones around equipment of 3 metres for staff not working COSS / SWL on the Dust Exposure RPE to be used as required as per risk assessment / task risk control sheet Extraction to be used where available COSS / Where ballast is disturbed staff shall wear dust masks and eye protection Excessive dust to be reported to the operator via the COSS / SWL Dampen down wok site, if possible, to reduce dust levels Users shall wear dusk mask to EN149 Laser Operation Lasers on s shall be screened / shielded. Machine Operator/Driver Legionella Chemical spills Slips, Trips & Falls Burns Points Movements Tanks to be emptied and refilled with fresh water daily Precautions to be taken when atomising water If water has been stagnant in the heat water is to be dropped and refilled. Spill kits to be carried and deployed Emergency plan to be contained on Safe System of Work Spill kit training undertaken by all Grated steps on Use of appropriate & maintained footwear Handrails for access & alighting to be used at all times Avoid contact with hot equipment in particular the exhaust Flame retardant clothing to be worn Signalling Technician (S&T) to liaise with COSS / SWL/PIC & Machine crew on all movements through locally controlled S&C. S&T and Harsco Crew member to walk through all S&C to confirm route is set prior to movements being carried out Harsco engineer / COSS / SWL COSS Brief / All staff staff Harsco staff / NRL assure points settings Page 4 of 5

Wear Head Wear Foot PPE Required by NR / Maintenance Policy Wear Hi Visibility Clothing Wear Safety glasses to BS EN166.F If safety glasses introduce a risk (ie weather conditions) then the Team Leader shall assess the risk. The outcome of the assessment shall be recorded on the SWP s pack and safety glasses may be removed. This does not supersede the requirements for eye protection detailed on relevant Task Risk Control Sheets. Additional PPE Required by Task Risk Control Sheet Wear Face fitted FFP3 RPE Wear Hand suitable to the task Page 5 of 5