FISH PROPAGATION 2012 ANNUAL REPORT

Size: px
Start display at page:

Download "FISH PROPAGATION 2012 ANNUAL REPORT"

Transcription

1 SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2012 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2012 MAY 31, 2013 BAKER RIVER HYDROELECTRIC PROJECT FERC No December 2013 BAK SA 101 Annual Report 2012.Doc PUGET SOUND ENERGY Baker River Hydroelectric Project Doc ID: BAK PSE.FERC-DC 19 December 2013

2 CONTENTS CONTENTS 1.0 Executive Summary Introduction Principal Management Activities Design and Planning Activities Documents Submitted Accounting Funding Expenditures Adjustments Supporting Documents References Review Comments and Responses Distribution List Transmittal Message Summary of Reviewer Replies Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page ii

3 List of Tables List of Tables Table 1. Fish Co-Managers preseason sockeye beach loading plan and actual beach loading, Table sockeye salmon beach loading records by data source (WDFW, PSE) and difference Table 3. One approach for sequential sockeye development at production facilities at Sulphur Springs, 2012 to Table 4. Salmon production from Baker fish propagation facilities, June 1, 2012 to May 31, Table 5. Sockeye broodstock and fry production from Baker fish propagation facilities, plus subsequent smolts counted for each brood year from 1999 through Table 6. Salmon releases from Baker River fish propagation facilities, June 1, 2012 to May 31, Table 7. Salmon rearing inventory at fish propagation facilities as of May 31, Table 8. Funds allocated to nutrient enhancement account, (1 st year) Table 9. ARG representatives who received the draft Fish Propagation 2012 Annual Report as part of the SA 102 review process List of Figures Figure 1. Baker fish hatchery site layout... 5 Figure 2. Baker fish hatchery constructed facilities... 6 Figure 3. Baker Fish Hatchery and improved Spawning Beach 4 during operation Figure 4. Spawning Beach Figure 5. The hatchery holding facilities contained 2,750 adult sockeye in 2012, and are capable of holding up to 6,000 broodstock Figure 6. Yearly number of sockeye fry released into the reservoirs from Baker fish propagation programs, Figure 7. Juvenile fish rearing facilities in use for sockeye and coho salmon and rainbow trout Figure 8. December 2012 landslide debris, debris removal, and riprap cleaning and replacement Figure 9. Aerial view of the site of Spawning Beach 1, 2, and Figure 10. Existing conditions at Spawning Beaches 1, 2, and 3. (PSE, 2013) Figure 11. Conditions at completion of decommissioning (April 18, 2013 design), showing infrastructure removed, site regrading, large woody debris structures in the channel alignment, and an overflow swale Figure 12. message from PSE accompanying the Fish Propagation 2012 Annual Report Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page iii

4 1.0 Executive Summary This annual report reviews activities undertaken by Puget Sound Energy (PSE) during the reporting period of June 1, 2012 May 31, 2013 to implement settlement agreement article 101, Fish Propagation (SA 101) of the Order on Offer of Settlement, Issuing New License and Dismissing Amendment Application as Moot (the license) issued by the Federal Energy Regulatory Commission (FERC) on October 17, 2008 for the Baker River Hydroelectric Project. It has been prepared in consistence with SA 102, Aquatics Reporting, and SA 101. The report covers the SA 101 reporting period of June 1, 2012 through May 31, 2013, as outlined in the reporting schedule contained in SA 102. In this reporting period, PSE efforts under SA 101 included: Continuing to implement the Fish Propagation Facilities Plan in accordance with the plan s schedule. Submitting the Baker Fish Hatchery Renovation Final Project Completion Report (October 5, 2012) to the FERC in accordance with SA 101 and the Fish Propagation Facilities Plan. Developing a Channel Creek Site Decommissioning Plan (December 2012), receiving documentation confirming U.S. Department of Agriculture Forest Service (USDA-FS) approval ( Notice to Proceed ) of the final design plan dated April 18, 2013, with construction to begin on July 16, Funding and operating fish propagation and enhancement programs for 2012 in the new hatchery and Sockeye Spawning Beach 4, and achieving a combined production of 5.3 million fry from a goal of 6 million. Approximately 3.2 million sockeye fry were from the third-year operation of the new hatchery, and 2.1 million were from the second-year operation of the improved Spawning Beach 4. Performance of these facilities increased sockeye fry production two-fold from levels prior to Reviewing conditions, planning, and initiating repairs to the Sulphur Springs water supply intake to control further sediment infusion by installing a graded filter following a significant landslide in December The filter materials were selected to cap the hatchery water intake area, shielding it from sliding materials in the event of a new landslide. Implementing a study approach in collaboration with the ARG for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits. PSE developed a study approach in collaboration with the ARG that identifies the number, type, and frequency of adult and smolt data collection efforts. 2.0 Introduction This Fish Propagation Report has been prepared for the Baker River Hydroelectric Project (the Project), pursuant to the Order on Offer of Settlement, Issuing New License and Dismissing Amendment Application as Moot dated October 17, 2008 (the license). In the Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 1

5 license, settlement agreement article (SA) 101, Fish Propagation (appendix A), sets forth the applicable requirements for the Fish Propagation Facilities Plan (the Plan), which in turn sets forth the requirements of this annual report. This annual report summarizes the activities conducted under SA 101 from June 1, 2012 through May 31, 2013, including management activities, monitoring, design and planning, surveys and data collection activities, consultation, documents prepared, modifications to or deviations from the Plan, issues and resolution, accounting, and purposed changes to the FERC-approved Plan. This report provides the ongoing format for future reports Principal Management Activities Principal activities during the 2012 reporting period (June 1, 2012 through May 31, 2013) included the following (which are described in greater detail in sections through 3.1.5). Continuing to implement the Fish Propagation Facilities Plan approved by the FERC on May 26, Filing the Baker Fish Hatchery Renovation Final Project Completion Report (October 5, 2012) to the FERC in accordance with SA 101 and the Fish Propagation Facilities Plan. Consulting with the U.S. Department of Agriculture Forest Service (USDA-FS) and ARG while developing a Channel Creek Site Decommissioning Plan (December 2012), receiving documentation confirming USDA-FS approval ( Notice to Proceed ) of the final design plan dated April 18, 2013, with construction to begin on July 16, Operating the newly-constructed fish culture facilities at the Sulphur Springs site for the third year, releasing 3.85 million sockeye fry to Baker Lake and 1.33 million sockeye fry to Lake Shannon, and retaining 0.13 million fry for the 20,000-pound production rearing program. Continuing the existing propagation and enhancement programs. The 20,000-pound production program, as determined by the Fish Co-managers (the Sauk-Suiattle Indian Tribe, Swinomish Indian Tribal Community, Upper Skagit Indian Tribe, and the Washington Department of Fish and Wildlife), remained unchanged from 2011 (status quo) for sockeye, coho, and rainbow trout production. Allocated to this extended rearing program were approximately 130,000 sockeye, 60,000 coho, and 20,000 rainbow trout fry. Rearing and release objectives were achieved during the reporting period. Cleaning and making repairs to the hatchery headworks infiltrated by a landslide in December PSE reviewed conditions, designed a repair method, and consulted with the USDA-FS. On May 28, 2013, the USDA-FS approved PSE s plan to repair the Sulphur Springs by capping the water supply intake with a graded filter to control further sediment infusion and shield the intake from sliding materials in the event of a new landslide. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 2

6 Consulting with the Washington Department of Fish and Wildlife (WDFW) on fish propagation plans, hatchery operational protocols, and the continuing PSE funding of fish propagation/enhancement programs and an onsite manager. Consulting with the ARG to implement a study approach that identifies the number, type, and frequency of adult and smolt data collection efforts to provide feedback on basin sockeye production limits Fish Propagation Facilities Plan Per SA 101, PSE is implementing the Fish Propagation Facilities Plan (FPFP) which FERC approved on May 26, The FPFP directs PSE to include information on a variety of programs and facilities in its annual SA 101 reports. A short update on each such project listed in the FPFP appears below. Sockeye Spawning Beach 4. A Baker Fish Hatchery Renovation Final Project Completion Report dated October 5, 2012, including as-built drawings, was provided to the FERC within 12 months following completion of the Baker fish hatchery renovation. The facility is operating. Section contains an update. Sulphur Springs fish culture facility. The Baker Fish Hatchery Renovation Final Project Completion Report listed above covers the Sulphur Springs facility. The facility is operating. Section contains an update. Sockeye smolt capacity. This study was completed during the 2010 reporting period. The final study report, including ARG comments and recommendations, was provided to the ARG and included with the 2010 annual report for SA 101. Empirically-derived sockeye production estimate. Following collaboration with the ARG, PSE implemented a study approach in April 2013 for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits. PSE developed the study approach in collaboration with the ARG to identify the number, type, and frequency of adult and smolt data collection efforts. PSE collects juvenile sockeye size information at the juvenile downstream fish passage facilities. The study approach document is attached to this report (see section 5.0, Supporting Documents ). Sockeye Spawning Beach 4 production limits. PSE maintains an enumeration system in Spawning Beach 4. A feasible enumeration system is necessary to evaluate production. As PSE implements the fish propagation program as directed by the Fish Co-managers, and the settlement agreement directs that population enhancement for sockeye will be sequential, production optimization testing will thus commence on a schedule to be determined in consultation with the ARG, and specifically the Fish Co-managers. Spawning Beaches 1 3 (Channel Creek site). A decommissioning plan, documentation confirming U.S. Forest Service approval of the decommissioning plan, and interim progress updates will be provided until completion of Channel Creek site decommissioning activities. PSE submitted a Channel Creek Site Decommissioning Plan in December The USDA-FS approved the final design plan dated April 18, 2013 (in their Notice to Proceed dated May 29, 2013), with project construction to begin on July 16, 2013 in accordance to plans. Section includes an update. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 3

7 Confirmation of annual PSE funding of the Fish Propagation and Enhancement Program and the annual fish production plan. The Fish Co- Managers will provide PSE with an annual fish production plan. Following completion of the Baker fish hatchery renovation, PSE requested that the Fish Co- Managers provide the annual fish production plan to PSE annually by September 30 to accommodate the PSE budget, reporting processes, and timeline requirements. PSE funded the fish propagation and enhancement program during the reporting period. The Fish Co-managers are continuing to work on a draft annual plan and progress updates have been provided at ARG meetings. Sufficient production planning information in lieu of a plan document was provided throughout the reporting period to successfully implement the fish production programs. The Fish Co-Managers provided a plan to PSE to distribute 2,750 adult sockeye from the 2012 return to the artificial incubation program in the new fish culture facilities, to distribute 3,400 adult sockeye from the 2012 return to Sockeye Spawning Beach 4, and to achieve a production goal of 6 million fry. The 20,000-pound production program, as determined by the Fish Co-managers, remained unchanged from 2011 (status quo) for sockeye, coho, and rainbow trout production. Allocated to this extended rearing program were approximately 130,000 sockeye, 60,000 coho, and 20,000 rainbow trout fry. In a subsequent ARG meeting on March 12, 2013, the WDFW informed PSE of fry ponding and planting plans for the resulting production of sockeye, directing 4 million fry into Baker Lake and 2 million into Lake Shannon. Section presents the results of the fish propagation programs, and section 4.2 describes expenditures during the reporting period. Annual confirmation of PSE funding of the Reservoir Nutrient Enhancement Program. Funding, which is not to exceed $60,000 annually, was placed into a PSE account for disbursements available to the Fish Co-managers. The use of funds will be at the discretion of the Fish Co-managers. The process to disburse funds will be determined in Funding is scheduled for license years Funding activity during the reporting period is reported in section 4.1. Fish facility operations manual for the Sulphur Springs site. Operations procedures, including abnormal operation and maintenance procedures in accordance to PSE standards, were developed during completion of the Baker fish hatchery renovation. PSE and the Baker fish hatchery design and construction contractor, McMillen-McDougall, prepared the procedures for inclusion in the updated manual replacing the April 2009 manual completed for the previous fish culture facilities. The new procedures are in use now for the operation and maintenance of Spawning Beach 4 and the new hatchery. Living as an electronic file collection, the operations manual provides easier user access and navigation to facility layout, descriptions and drawings, emergency, physical and biological operations, security and maintenance procedures, and makes future updates readily available. Annual contract and budgeting report governing operation of fisheries enhancement programs. This will report the annual budget and actual costs. WDFW is under a PSE contract, whereby PSE funds an onsite manager for operations. Expenditures from the WDFW contract during the reporting period are reported in section 4.2. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 4

8 Updates on fisheries enhancement studies approved by the Fish Co-managers to optimize program success. These will be provided annually following completion of the Baker fish hatchery renovation. A schedule will be determined in consultation with the ARG. Fish propagation facilities operations audit. This will be included with the annual fish propagation facilities and programs report based on a June 1 to May 31 operating year. The audit will address financial accounting, fish handling and disease management operations, hazardous materials handling, and spill prevention, control, and countermeasures (SPCC) compliance. PSE, per the FERC license, developed an SPCC plan for the project. This plan was submitted to the FERC, and compliance is mandatory. At the time of this report, there have been no incidents SA 101 A & B Sockeye Spawning Beach 4 and Sulphur Springs Fish Culture Facility Final Completion Report, Baker Fish Hatchery Renovation PSE completed the construction of new fish culture facilities and modification of Spawning Beach 4 at Sulphur Springs by December 31, 2011, based upon the Baker Fish Hatchery Renovation 100% Final Design Documentation Report (McMillen, 2009). Final project completion is documented in the 2011 annual report. A Baker Fish Hatchery Renovation Final Project Completion Report dated October 5, 2012, including as-built drawings, was provided to the FERC within 12 months following completion of the Baker Fish Hatchery renovation. The facilities are now in their 3 rd operating year. Figures 1, 2, and 3 show the Baker fish hatchery site layout and the completed facilities in operation. Figure 1. Baker fish hatchery site layout. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 5

9 Figure 2. Baker fish hatchery constructed facilities. Clockwise from top left: egg incubation, adult holding and fry transfer hoppers, outdoor rearing, early rearing. Figure 3. Baker Fish Hatchery and improved Spawning Beach 4 during operation Fish Propagation /Enhancement Programs This section presents the results of the fish propagation programs during the reporting period. The information and results also represent an audit of the existing propagation and enhancement program. The audit describes results of biological, operational, and maintenance efforts related to implementing fish propagation and enhancement facilities and programs, and report whether the program goals were met based on the biologicallyestablished June 1, 2012 to May 31, 2013 operating year. This calendar coincides with the operational cycle for the Baker Project fish propagation facilities, which starts with the first yearly adult sockeye returns to the Baker Project and ends with the completion of Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 6

10 fry emigration from the sockeye spawning beaches. The audit summarizes the production results of the sockeye spawning beach and artificial propagation facilities, as well as the production results of the coho supplementation and rainbow trout enhancement programs. The information reported includes: Sockeye and coho fry production numbers. A discussion of disease management and results. Remedial responses to a landslide at the water supply headworks. Reporting related to adult returns, facility loading, production totals, and release numbers for juvenile sockeye, coho, and the other fish propagation and enhancement programs for rainbow trout. The current fish production program at the Baker River Project is directed by the Fish Co-Managers and is a combination of sockeye, coho, and rainbow trout production. The program continues the previous propagation and enhancement programs established by PSE with the WDFW, the Upper Skagit Indian Tribe, the Sauk-Suiattle Indian Tribe, and the Swinomish Indian Tribal Community, the USFWS, NOAA Fisheries, and the USDA-FS except that these programs are now contained in an improved sockeye spawning beach and the newly-constructed Baker River fish hatchery, and will enable the continued sequential development of population enhancement for sockeye and a 20,000- pound-capacity production program made up of any one or any combination of several species. Program updates, directives, and changes are provided by the Fish Co-Managers and reviewed at scheduled ARG meetings. Fish propagation and enhancement program funding and operations in the new hatchery and improved Spawning Beach 4 during the reporting period were based on a production goal of 6 million sockeye fry and a juvenile rearing goal of 130,000 sockeye, 60,000 coho and 20,000 rainbow trout Sockeye Salmon Spawning Beaches Spawning Beach 4, completed in 1990 to replace the aging, isolated, and vulnerable Beaches 2 and 3, is operated as four isolated compartments (A, B, C, and D) to reduce and contain outbreaks of infectious hematopoietic necrosis (IHN), a viral disease endemic to sockeye populations. The WDFW provides on-site management of Spawning Beach 4, with support from PSE in the form of funds and personnel. The improved Spawning Beach 4 operated for the second year during this reporting period, as the modifications required by SA 101 had been completed. These modifications included an isolated water supply, concrete barriers for compartment isolation, a new pond liner, outlet structure improvements, and cranes and concrete pads for carcass removal and better access. If the IHN virus is detected above the threshold level for any one of the compartments during routine testing, a chlorination treatment system is activated and a protocol to stop collection of fry in that segment is triggered at the direction of the Fish Co-managers. The fry emerging from the infected compartment are terminated, and effluent is diverted to the chlorination treatment system in accordance with the disease management protocol developed by the Fish Co-Managers for the facility. The disease management protocol is a set of agreements on how to determine when to stop taking fry from a Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 7

11 beach section. This protocol has been in place for the past 15 years, and is revised annually as more is learned about the disease. During this reporting period, viral sampling of adult fish indicated that IHN virus was present in sockeye that returned to the Baker system in the fall of 2012, and detected IHN virus in adult fish placed in Spawning Beach 4 and in the artificial incubation adult holding ponds. The containment features of the Spawning Beach and hatchery, and operational procedures for disease management and biosecurity procedures worked to contain and limit infection episodes. Winter/spring (2013) viral sampling of fry produced from both these facilities confirmed that IHN was not present in fry produced from Spawning Beach 4. Surplus adult sockeye salmon may be released into Baker Lake for spawning in the upper Baker River and its tributaries. Spawning Beach 3 has been operated periodically as an unattended production facility until replacement production can be provided from the new fish culture facilities at Sulphur Springs. When operated, Spawning Beach 3 usually requires pumping to supplement the gravity water supply. PSE provides support in the form of equipment and personnel, at the request of the WDFW. The site of Spawning Beaches 1, 2, and 3 will be decommissioned as a requirement of SA 101. Spawning Beach 3 was not operated for fish production during this reporting period. Beach 3 has been used as additional site to release sockeye fry from the hatchery to Baker Lake Sockeye Adult Returns (2012 season) Each year, the Fish Co-Managers based the spawning beach loading goals and artificial incubation (AI) program goals on the predicted sockeye run size and ideal loading conditions. Spawning density goals help maximize production and manage for disease. It should be noted that the WDFW directs the facility s fish propagation program objectives on behalf of the co-managers. In 2012, the plan called for holding 3,400 adult sockeye in Spawning beach 4 and 2,750 sockeye as brood stock for the artificial incubation (AI) program. A total of 28,408 sockeye returned to the Baker River adult trap during The return exceeded the Fish Co-Managers 2012 allocation for the fish propagation facilities, so 17,511 sockeye were placed into Baker Lake, while 4,679 were allocated to tribal harvest. A distribution methodology developed by the Fish Co-Managers allocated fish between Spawning Beach 4, the artificial incubation program, lake release, and tribal harvest based on representative portions of the expected run timing. Beach 4 was seeded with a total of 3,407 fish. Artificial incubation raceways were seeded with a total of 2,752 fish. Combined, the facilities were seeded with a total of 6,159 fish. Beach 3 was not seeded with fish. The loading plan and actual loading count are reported in table 1. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 8

12 Figure 4. Spawning Beach 4. The beach was loaded with 3,407 adult sockeye in 2012, and is capable of holding over 3,400. Figure 5. The hatchery holding facilities contained 2,750 adult sockeye in 2012, and are capable of holding up to 6,000 broodstock. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 9

13 Table 1. Fish Co-Managers preseason sockeye beach loading plan and actual beach loading, Number of Adults Location/Program Loading Plan based on Pre-season Forecast Actual Loading based on Available Returns Spawning Beach 4, Section A Spawning Beach 4, Section B Spawning Beach 4, Section C Spawning Beach 4, Section D Artificial Incubation Program, Raceway Artificial Incubation Program, Raceway Artificial Incubation Program, Raceway Artificial Incubation Program, Raceway Total ,159 a See subsequent sections for discussion of sockeye returns, hauling totals, and numbers based on WDFW carcass counts. Table 2 summarizes the WDFW carcass count according to beach and PSE hauling counts. The WDFW reported a lower carcass count (3,278) for the spawning beaches and total stocking density compared to PSE hauling records (table 2). PSE records indicate that 3,407 sockeye were delivered to the spawning beaches. The total difference between the WDFW and PSE carcass counts (including non-spawned females) for Beach 4 is -129 fish. Discrepancies between WDFW records of total carcass counts and PSE hauling counts can be attributed to human error (recording error, counting other salmonids such as steelhead) and removal by predators/scavengers. The WDFW spawning beach carcass count is summarized in table 2. 1,417 female and 1,606 male carcasses were counted. An additional 255 unspawned females were counted, bringing the total carcass count at Beach 4 to 3,278. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 10

14 Table sockeye salmon beach loading records by data source (WDFW, PSE) and difference. WDFW Carcass Count Record PSE Hauling Count Difference (WDFW-PSE)* Beach 4A Females 326 Females n/a Males 418 Males n/a Unspawned Females 81 Unspawned Females n/a Total 825 Total Beach 4B Females 328 Females n/a Males 439 Males n/a Unspawned Females 23 Unspawned Females n/a Total 790 Total Beach 4C Females 403 Females n/a Males 371 Males n/a Unspawned Females 60 Unspawned Females n/a Total 834 Total Beach 4D Females 360 Females n/a Males 378 Males n/a Unspawned Females 91 Unspawned Females n/a Total 829 Total Combined Beach 4 Females 1,417 Females n/a Males 1,606 Males n/a Unspawned Females 255 Unspawned Females n/a Total 3,278 Total 3, Sum of Beach 4 3,278 Sum of Beach 4 3, * Carcass counts are considered more reliable data and are therefore utilized for management calculations such as estimation of egg production at the beaches Sockeye Artificial Incubation Program This hatchery program, which as a pilot program had produced 1 million fry annually in temporary incubation facilities, has now transitioned into the newly-constructed fish culture facilities that will enable the sequential development of additional population enhancement for sockeye up to the capacity for 7 million fry annually, and which provide added protection in the event of losses from infectious hematopoietic necrosis (IHN). The combined 2012 production goal for the spawning beach and the artificial incubation facility was 6 million fry, including 130,000 fry reserved for a delayed-release experiment in the hatchery. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 11

15 PSE will take a sequential approach for scheduling and increasing future sockeye fry production per SA 101 (c), Sequential Development of Sockeye Population, using both the spawning beach program and the artificial incubation (AI) program for enhancement. In this approach, projected by table 3, PSE would provide for facility operations as directed by the Fish Co-managers, with sequential increases of approximately 1 million fry per year until either Spawning Beach 4 plus phase 1 of the artificial incubation program reach their maximum capacity, or the Baker River system reaches its maximum capacity. Table 3. One approach for sequential sockeye development at production facilities at Sulphur Springs, 2012 to Brood Year Spawning Beach 4 AI Program Total Fry Production ,000,000+ 4,000,000 6,000, ,000,000+ 5,000,000 7,000, ,000,000+ 5,000,000 8,000, ,000,000+ 6,000,000 9,000, ,000,000+ 7,000,000 10,000, Sockeye Egg Production Spawning Beach 4 (SB4). Based on the carcass counts of spawned females and using an average fecundity of 3,000 eggs, as previously determined for the Baker River stock, it is estimated that approximately 4,251,000 eggs were deposited into the spawning beach gravels. Artificial incubation (AI). According to WDFW records, from 1,298 spawned females, the AI program yielded a total of 3,375,845 eyed-eggs which had developed on vertical stack egg incubation trays supplied by the hatchery. Inclining the egg incubation trays at 5% was a slight operational adjustment this past year to benefit egg survival Sockeye Fry Production Spawning Beach 4. According to WDFW records, the spawning beach program produced approximately 2,100,202 fry between February and May for the 2012 brood year (table 4). These fry after emerging from the beach gravel emigrate to a collection hopper and are transported as unfed fry. Artificial Incubation. According to WDFW records, the AI program produced approximately 3,262,645 fry between February and May of which 131,669 were reserved for a delayed-release experiment in the hatchery and the remaining for near immediate release, satisfying the fry production objectives established for 2012 by the Fish Comanagers for the artificial incubation program (table 4).In 2012, AI-program-produced fry were held and fed for up to 10 days. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 12

16 Table 4. Salmon production from Baker fish propagation facilities, June 1, 2012 to May 31, Production Year Feb. - May sockeye Brood Year Species Program Stock Number Artificial Incubation Release Size Baker 3,262,645 a fed fry Release Site Baker Lake, Lake Shannon Feb. - May sockeye Spawning Beach Baker 2,100,202 b unfed fry Baker Lake Feb. - May sockeye Extended Rearing Baker 117,990 c fed fry (see table 6) Feb. - May coho Extended Rearing Baker 93,406 d fed fry (see table 6) a Approximately 1,756,676 were released in Baker Lake, 1,329,520 were released in Lake Shannon. b All were counted into Baker Lake, during end of season annual shutdown a residual amount of remaining fry estimated at 20,000 were released into Lake Shannon. c Approximately 117,990 are held in the extended rearing program and will be released in November 2013 (table 7). d Approximately 132,220 were released in Lake Shannon (table 5), approximately 93,406 are held in the extended rearing program and will be released in May 2014 (table 7) Sockeye Fry Disposition Spawning Beach 4. The Fish Co-Managers determine the allocation percentages of fry to Lake Shannon and Baker Lake. According to WDFW records, most (99%) of the unfed Spawning Beach 4 fry (2,080,202) were released into Baker Lake. The other 1% that went into Lake Shannon consisted of approximately 20,000 residual remaining fry that were released into Lake Shannon when Beach 4 was shut down for the season. Artificial incubation. The Fish Co-Managers determine the allocation percentage of fry to Lake Shannon and Baker Lake. According to WDFW records, 1,756,676 (55%) fed fry from the artificial incubation program were released into Baker Lake, and 1,329,520 (41%) fed fry from the artificial incubation program were released into Lake Shannon. Artificial incubation fry were transported to swim-up troughs and fed for a minimum of one week before release into Baker Lake and Lake Shannon,. The intent of this action was to allow the fry to swim up and become active before release, to develop foraging behavior to increase survival, and to postpone release until zooplankton populations were more likely to be available in Baker Lake. Of these, 131,669 fed fry (4%) from the artificial incubation program are being reared for use in future studies and for continuing fish propagation and enhancement programs as of May 31, 2013 (the goal continues to be 130,000). Also, from the previous 2011 brood year production reserved for the delayed-release experiment in the hatchery were 147,653 juvenile sockeye released as sub-yearlings: 140,444 ad-clipped fish at 55 fish per pound (fpp) released into Baker Lake in November of 2012, and an additional 7,209 ad-clipped fish at 31 fpp released into the Baker River from the Lower Baker Stress Relief Ponds in March 2013 (table 6). All fish were raised to appropriate release sizes and released on schedule. Sockeye fry production was only slightly affected by infectious hematopoietic necrosis (IHN), a virulent rhabdoviral disease that occurs in the wild and can typically cause high mortality in juvenile sockeye. During this reporting period, viral sampling indicated that Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 13

17 IHN virus was carried in adult sockeye that returned to the Baker system fall 2012, and detected IHN virus in adult fish placed in Spawning Beach 4 and in the artificial incubation adult holding ponds. The containment features of the Spawning Beach and hatchery, operational procedures for disease management, and biosecurity procedures worked to contain and limit infection episodes in subsequent fry production. Winter/spring (2013) viral sampling confirmed that no IHN was present in fry produced from Spawning Beach 4. IHN infection was confirmed to a single episode in the artificial incubation program fry: the last remaining egg-take of the season (number 9, 44,767 sockeye fry) was euthanized on May 13, IHN infection was confirmed in juvenile sockeye. Of 12,118 sub-yearling sockeye transferred to the Lower Baker stress relief pond, 4,909 died from IHN after they were transported, leaving 7,209 for release to the Baker River on March 14, 2013 at 31 fpp. These sockeye were not euthanized like the others because the Fish Co-managers concluded that the IHN virus had run its course and the remainder should survive Yearly Sockeye Fry Propagation Sockeye fry recruitment to the reservoirs since 1957 has come from four constructed spawning beaches, hatchery production using artificial incubation, and limited natural spawning. Figure 6 shows the trend of fry releases from spawning beaches and hatchery production. Levels have increased significantly since the new Baker Hatchery began operation. Table 5 lists the most recent sockeye fry production from brood years dating back to PSE implemented a study approach April 2013 to monitor the numerical response to increased fry production. The approach to monitoring includes an annual accounting of the empirical data in this table. This includes fry production, plus subsequent smolts counted. During the 2012 reporting period, the total yearly sockeye fry propagation from the Baker Hatchery was 5,362,847, making 2012 the 4 th consecutive year in which fry production exceeded 5 million and was a two-fold increase from historical levels. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 14

18 Brood year Table 5. Sockeye broodstock and fry production from Baker fish propagation facilities, plus subsequent smolts counted for each brood year from 1999 through Spawning beach spawned females Counted fry out of spawning beach #4 Estimated fry from beach #3 AI spawned females Egg take for AI Fry produced from AI Fry to Baker Lake Fry to Lake Shannon Smolts from Baker Lake a ,393 1,856, ,000 2,078, , ,770 3,281, ,000 3,604, ,021 9, ,017 1,316, ,000 1,543,042 70, ,677 1,537, , , ,950 2,259, , ,698 4, ,854 2,089, , , ,944 2,971, , ,767 3, ,662 1,638, , ,212,800 1,188,524 2,801, , ,494 4,810 Smolts from Lake Shannon a ,656, ,157,300 1,134,742 2,791, ,014 41, ,807 1,990, ,246,190 1,224,356 2,914, , , ,892, , ,940 2,814, ,353 7, ,161 1,326, , ,506 2,291, ,297 1, ,713 3,511, ,713,599 1,596,630 5,108, ,550 5, ,637 5,199,858 5,089,860 4,139, , ,612 17, ,158, ,690 5,072,919 4,368,735 3,558,264 2,000, , , ,100, ,375,845 3,262,645 3,836,878 1,349,520 a Counts include all sockeye outmigrants but do not reflect smolt production by brood year because the majority of smolts outmigrate at age 1. 6,000,000 Resulting Fry Production New Baker Hatchery 5,000,000 4,000,000 Number of Fry 3,000,000 Spawning Beach 4 Pilot Hatchery (AI) 2,000,000 1,000,000 0 Beach Spawning Beach Spawning Beach Brood Year Figure 6. Yearly number of sockeye fry released into the reservoirs from Baker fish propagation programs, Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 15

19 Coho Supplementation program The coho supplementation program continues to produce juvenile coho from the stock of naturally-reproduced wild origin coho adults in the Baker River system for use in studies and for the ongoing fish propagation and enhancement objectives determined by the Fish Co-Managers. From the 2012 fry production, 116,536 surplus coho fry (190 fpp) were released into Lake Shannon at Sulphur Creek in May Approximately 60,000 fry were allocated for extended rearing and release as smolts in the spring of 2013 to continue migration experiments and contribute to adult returns. These fry, reared in raceways at Upper Baker, resulted in a total of 62,420 yearlings. Of these fish, 6,386 (22 fpp) were released into net pens in Lake Shannon to be used for juvenile passage biological studies. The remaining 56,034 yearling fish (24 fpp) were released below both dams into the Baker River stress relief ponds (SRP) in April 2013 to contribute to future fall adult returns. All fish were raised to appropriate sizes and released on schedule (table 6). Table 6. Salmon releases from Baker River fish propagation facilities, June 1, 2012 to May 31, Release Date Brood Year Species Stock Number Size (fish/lb.) Pounds Planted Release Site May 30, coho Baker 116, Sulphur Creek Nov 13, sockeye Baker 76, ,380 Baker Lake Nov 15, sockeye Baker 64, ,169 Baker Lake March 14, sockeye Baker 7, SRP April 9, coho Baker 2, Shannon Pens April 10, coho Baker 2, Shannon Pens April 10, coho Baker 2, Shannon Pens April 17, coho Baker 56, ,373 SRP May 15, coho Baker 132, Sulphur Creek Total Releases 458,829 6, Coho Adult Returns (2012 season) A total of 5,566 coho adults returned to the Baker River trap in 2012, of which 201 were removed from the trap for the supplementation program. These fish were held at the Baker hatchery until sexually mature and then spawned. The coded wire tags were recovered from their carcasses for stock identification Coho Egg and Fry Production For the 2012 brood year (2013 fry production), 97 Coho females were spawned and an estimated total of 233,822 eyed eggs were incubated at the hatchery. An inventory of fry based on eyed egg weight samples less ponding loss provided a count of 231,870. Approximately 60,000 fry will be allocated to the extended rearing program (the program goal is 60,000), resulting in a surplus of Coho fry. The 132,220 surplus fry of (461 fpp) were released into Lake Shannon at Sulphur Creek in May 15 th Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 16

20 The estimated 60,000 fry allocated for extended rearing will be released as yearlings (~20 fpp) in the spring of 2014 to continue migration experiments and contribute to adult returns. An additional 6,500 will be used for juvenile passage biological studies. All of these fish reared at the Baker hatchery will be used for the annual mark-recapture (reservoir migration response) experiments. The remaining 53,500 yearling fish will be released into the Baker River stress relief ponds below both dams to contribute to future fall returns. A salmon rearing inventory is shown in table 7. Table 7. Salmon rearing inventory at fish propagation facilities as of May 31, Planned Release Date Brood Year Nov Sockeye May Coho Species Program Stock Inventory Extended Rearing Extended Rearing Planned Release (fish/lb.) Baker 117, Baker 93, Planned Release Site Baker Lake Baker/ Shannon/ Baker River Rainbow Trout Production WDFW provided 20,000 rainbow trout fingerlings for the program in July PSE supplied labor, rearing facilities, and food from July to January 16 th. Because of the December 2012 landslide at the hatchery water supply intake, the fish were moved to the SRP ponds on December 6th, held there until January 16 th, and then relocated to Marblemount Hatchery, which supplied labor and rearing facilities until the trout were released. During the reporting period, approximately 8,586 rainbow trout were released into Depression Lake for recreational fishing and 2,400 rainbow trout were released into Grandy Lake as an expansion of this recreational fishing program. 1,000 trout were allocated to the Upper Skagit Indian Tribe for their fishing derby. All fish were raised to appropriate target sizes averaging 3 fpp and released on schedule. Additional releases of the remaining trout into Depression Lake would continue into June Figure 7 shows the Baker fish hatchery in operation for juvenile fish rearing for the 20,000 pound capacity production program directed by the Fish Co-managers annual fish production goals. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 17

21 Figure 7. Juvenile fish rearing facilities in use for sockeye and coho salmon and rainbow trout. Raceways and rectangular and circular tanks are provided for program flexibility and multiple species Facilities Operations Monitoring Repairs to Water Supply Monitoring alarms detected a turbidity event on December 5, 2012 in the primary water supply to the Upper Baker fish rearing facilities at Sulphur Springs. Because of the potential for soil slippage at the springs supplying water to the fish production facilities, turbidity events are monitored by alarm systems. Past events have resulted in temporary turbidity excursions in the water supply. PSE has responded to these by switching to an alternate (domestic) water supply until the primary supply could be restored. The newlyinstalled sand separators are designed to have sediment protection and removal built into the primary water supply to address these events. The event on December 5 th was followed by a more substantial landslide on December 10 th, which resulted in large amounts of sediments infiltrating the water supply and overwhelming the sand separators. PSE mobilized quickly to respond to the December 2012 landslide and temporarily restored water supply by removing rip rap (large boulders), cleaning and removing the sediment buildup, and replacing the riprap back into the spring channel while monitoring for turbidity (figure 8). Juvenile fish in the hatchery (155,000 sockeye, 60,000 coho and 20,000 rainbow trout) were relocated to offsite locations, including the stress relief ponds at Lower Baker. Only a few adult sockeye broodstock remained and were spawned, and adult coho broodstock were connected to the backup water system. Incubating sockeye and coho eggs already on the domestic water supply remained on the back-up water supply system. PSE began planning for permanent repairs to begin in June 2013 during the normal annual hatchery maintenance shutdown in preparation for the next brood cycle, so that it Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 18

22 would have the least effect to fish. June is also part of the drier season, making new landslides unlikely during the repairs. Making these repairs to the hatchery headworks required PSE to review conditions, consult with the USDA-FS and the ARG, and then plan and initiate repairs following USDA-FS approval of planned work. PSE designed a repair method employing a graded filter and geotextile filter fabric at the Sulphur Springs water supply intake to control further sediment infusion. The filter materials were selected to cap the hatchery water intake area, protecting it from sliding materials in the event of a new landslide. The repair method was approved by the USDA-FS on May 28, 2013 (USDA-FS, 2013a) and PSE immediately initiated construction work based on the approved design (PSE, 2013a). Figure 8. December 2012 landslide debris, debris removal, and riprap cleaning and replacement. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 19

23 3.1.4 SA 101 d Maintain, Then Restore Natural Conditions at Spawning Beaches 1, 2, and 3 Before the renovation and construction of the Baker fish hatchery was complete, PSE initiated discussion with the USDA-FS to develop a decommissioning plan that outlines decommissioning procedures for the site of Sockeye Spawning Beaches 1, 2, and 3. Actual decommissioning of the Channel Creek site will occur after the USDA-FS (the land owner) authorizes decommissioning. PSE consulted with the USDA-FS towards an understanding of the decommissioning procedures. PSE and the USDA-FS sought input from the ARG and the Cultural Resources Advisory Group (CRAG) at meetings. The consultation process resulted in a USDA-FS scope-of-work document (June 9, 2011), an agreement on a general approach that considered the input of the ARG and CRAG, and the development of conceptual design options presented to the ARG in June 2012, followed by the ARG s selection of restoration Alternative 5, in July The following restoration goals for the decommissioning of the site were determined during a workshop with PSE, and the ARG, held on June 26, 2012 (PSE, 2012). Salmon Spawning Habitat: Provide spawning habitat for adult salmon throughout the existing natural channel in the project area (to the most practicable extent). Maintain Pond Hydrology: Maintain the open water component of the upstream pond by implementing some type of downstream grade control structure (or similar) to help maintain pond water elevations. Overflow Swale: Provide an overflow swale to direct overflows from the upstream pond to the downstream pond and channel. This will prevent water from flowing overland to the south away from the channel and pond network. The following site decommissioning goals were identified by the USDA-FS. Remove Infrastructure: All surface and subsurface infrastructure constructed and installed as part of the spawning beaches will be removed and hauled off-site for appropriate disposal or recycle. Decommission Gravel Surfacing: The gravel surfacing within the site will be decommissioned to USFS standards (roadway decommissioning may involve removal of the gravel surface and the sub-base scarified to a depth of approximately 1 foot). Re-grade Site: Upon removal of the site facilities (surface and subsurface), the site will be re-graded to emulate natural, pre-facility grades and contours. Cut and Fill Volume: Decommissioning will generate cut and fill. To the extent practicable, cuts and fills will be balanced on-site to minimize or eliminate the need for the import and export of fill materials. Alternative 5, which meets these goals, includes enhancement along the existing Channel Creek alignment with grade control (large woody debris structures) placed in the channel to help maintain the water surface elevations in the upstream pond. In addition, an overflow swale will connect the upstream pond to the downstream pond to help keep water in the existing channel and pond complex. The overflow swale will provide a flow pathway during higher-flow drainage events, and if beaver activity in the main channel creates backwater conditions (with the potential for overflow) in the pond. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 20

24 PSE provided an alternatives assessment report to the ARG in August 2012 as documentation for moving forward with the Alternative 5 design. PSE developed a Channel Creek Site Decommissioning Plan that outlines the progress that PSE has made in planning for decommissioning and the procedures for decommissioning based on the Alternative 5 design. Following ARG review, PSE provided the ARG with an updated plan including ARG comments and PSE responses (December 2012). PSE finalized the design with a plan set dated April 18, 2013 (Anchor QEA, 2013). PSE received documentation ( Notice to Proceed ) confirming that the USDA-FS had completed its review and approved the decommissioning (USDA-FS, 2013), with construction to begin on July 16, Construction is expected to be complete by the end of Figure 9. Aerial view of the site of Spawning Beach 1, 2, and 3. Doc ID: BAK PSE.FERC-DC Baker River Hydroelectric Project Page 21

25 Fish Propagation 2012 Annual Report Figure 10. Existing conditions at Spawning Beaches 1, 2, and 3. (PSE, 2013) BAK SA 101 Annual Report 2012.Doc Doc ID: BAK PSE.FERC-DC PUGET SOUND ENERGY Baker River Hydroelectric Project 19 December 2013 Page 22

FISH PROPAGATION 2010 ANNUAL REPORT

FISH PROPAGATION 2010 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2010 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2010 MAY 31, 2011 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 April 2012 BAK SA 101 Annual Report 2010.Doc

More information

FISH PROPAGATION 2015 ANNUAL REPORT

FISH PROPAGATION 2015 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2015 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2015 DECEMBER 31, 2015 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 November 2016 PUGET SOUND ENERGY

More information

FISH PROPAGATION 2014 ANNUAL REPORT

FISH PROPAGATION 2014 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2014 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2014 DECEMBER 31, 2014 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 November 2015 PUGET SOUND ENERGY

More information

UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT

UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 103 UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2015 DECEMBER 31, 2015 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 November 2016 PUGET SOUND ENERGY

More information

THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT

THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT LICENSE ARTICLE 410 THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT REPORTING PERIOD JANUARY 1 DECEMBER 31, 2010 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 Puget Sound Energy Bellevue,

More information

P U B L I C U T I L I T Y D I S T R I C T N O.

P U B L I C U T I L I T Y D I S T R I C T N O. P U B L I C U T I L I T Y D I S T R I C T N O. 1 o f C H E L A N C O U N T Y P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org

More information

Yakima/Klickitat Fisheries Project

Yakima/Klickitat Fisheries Project Yakima/Klickitat Fisheries Project Lower Yakima River Supplementation and Research Project Operations and Maintenance Annual Report 2002-2003 March 2004 DOE/BP-00006677-1 This Document should be cited

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, September 4, 27 9: a.m. : a.m. Place: CONFERENCE CALL ONLY Contacts: Frank

More information

Cushman Hydro Project Public Meeting. Cushman Fire Hall Dec. 6, 2018

Cushman Hydro Project Public Meeting. Cushman Fire Hall Dec. 6, 2018 Cushman Hydro Project Public Meeting Cushman Fire Hall Dec. 6, 2018 Reservoir Operations Florian Leischner Fish and Habitat Biologist Cushman Reservoirs Cushman dams were built in 1924-30 New Cushman license

More information

APPENDIX D: LEWIS RIVER HATCHERY REVIEW

APPENDIX D: LEWIS RIVER HATCHERY REVIEW APPENDIX D: LEWIS RIVER HATCHERY REVIEW JANUARY 14, 2004 Prepared for PacifiCorp and Cowlitz PUD Prepared by S.P. Cramer & Associates, Inc. 600 NW Fariss Gresham, Oregon 97030 www.spcramer.com D-1 TABLE

More information

Baker River Project License Implementation. Aquatics Resource Group Meeting Final Conference Call Notes. March 9, 2010 ~ 9:00-11:00 am

Baker River Project License Implementation. Aquatics Resource Group Meeting Final Conference Call Notes. March 9, 2010 ~ 9:00-11:00 am Baker River Project License Implementation Aquatics Resource Group Meeting Final Conference Call Notes March 9, 2010 ~ 9:00-11:00 am Team Leader: Arnie Aspelund, PSE (arnie.aspelund@pse.com) PRESENT: Arnie

More information

FISH CONNECTIVITY IMPLEMENTATION PLAN

FISH CONNECTIVITY IMPLEMENTATION PLAN FISH CONNECTIVITY IMPLEMENTATION PLAN SETTLEMENT AGREEMENT ARTICLE 104 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 October 2011 BAK SA 104 Fishconnectivityimplan.Doc PUGET SOUND ENERGY Baker River

More information

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT FEDERAL AID JOB PROGRESS REPORTS F-20-52 2016 Lake Tahoe Rainbow Trout Study WESTERN REGION NEVADA DEPARTMENT OF WILDLIFE, FISHERIES DIVISION

More information

Attachment 1. Agenda Item Summary BACKGROUND

Attachment 1. Agenda Item Summary BACKGROUND Attachment 1 Agenda Item Summary BACKGROUND Spring Chinook Salmon: Prior to the late 1970s, non-treaty spring Chinook fisheries in the mainstem Columbia River occurred from February through May and harvested

More information

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell:

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell: From: To: Cc: Subject: Date: Attachments: Hemstrom, Steven "Lewis, Stephen" Sokolowski, Rosana 2014 Rocky Reach Bull Trout Report Wednesday, June 18, 2014 3:01:07 PM Final 2014 Rocky Reach Bull Trout Observations

More information

***Please Note*** April 3, Dear advisory committee members:

***Please Note*** April 3, Dear advisory committee members: April 3, 29 Dear advisory committee members: The fifth meeting of the CHF advisory committee will be held April 13 in Grants Pass from 6:-8:3 PM, and the purpose of this document is to help committee members

More information

145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Public Utility District No. 1 of Douglas County, Washington Project No. 2149-163 ORDER APPROVING BULL TROUT STRANDING, ENTRAPMENT,

More information

Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery

Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery Jeffrey P. Koenings, PhD. Washington Department of Fish and Wildlife American Fisheries Society

More information

Hatchery Scientific Review Group Review and Recommendations

Hatchery Scientific Review Group Review and Recommendations Hatchery Scientific Review Group Review and Recommendations Lochsa River Spring Chinook Population and Related Hatchery Programs January 31, 2009 Lochsa River Spring Chinook Population Report Page - 1

More information

Don Pedro Project Relicensing

Don Pedro Project Relicensing Don Pedro Project Relicensing M ODESTO I RRIGATION D ISTRICT TURLOCK I RRIGATION D ISTRICT FERC PROJECT N O. 2299 Resident Fish in Don Pedro Reservoir Don Pedro Reservoir Fish Stocking (1971-Present) CDFG

More information

FINAL Caples Lake Fisheries Management Plan. Version 4.0

FINAL Caples Lake Fisheries Management Plan. Version 4.0 FINAL Caples Lake Fisheries Management Plan Version 4.0 August 15, 2008 Purpose The Caples Lake Fisheries Management Plan (Plan) outlines the stocking plan to reestablish a sport fishery in Caples Lake

More information

SALMON RIVER HATCHERY

SALMON RIVER HATCHERY SALMON RIVER HATCHERY PROGRAM MANAGEMENT PLAN 2018 Salmon River Hatchery INTRODUCTION Salmon River Hatchery is located seven miles north of Lincoln City off Highway 18 near Otis. Site is at an elevation

More information

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. Public Utility District No. 1 of

More information

Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities

Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities Antibiotic Use The antibiotic use at the Platte River State Fish Hatchery (Hatchery) in 2012 only focused on disease

More information

Ned Currence, Nooksack Indian Tribe

Ned Currence, Nooksack Indian Tribe Ned Currence, Nooksack Indian Tribe Problem Status Distribution Habitat Hatcheries Harvest 25000 20000 Natural-Origin Spawners 15000 10000 22500 5000 0 Historic catch Spawners (2011-2015) Problem Status

More information

THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON

THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON To: Branch of Natural Resources P.0. Box C, Warm Springs, Oregon 97761 Phone (541) 553-2002/2003 Fax (541) 553-1994 The Independent Science

More information

Kootenay Lake Kokanee and other Fish 2017 Status

Kootenay Lake Kokanee and other Fish 2017 Status Kootenay Lake Kokanee and other Fish 2017 Status Friends of Kootenay Lake 5th Annual Kootenay Lake Summit November 2017 Matt Neufeld and Jeff Burrows BC Fish and Wildlife Nelson Outline Kootenay Lake Fish

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP

OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP Hatchery 13 Article 07 OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP 1 9 8 8 A n n u a l R e p o r t b y Brent R. Snider, Fish Hatchery Superintendent I March 1993 TABLE OF CONTENTS Page ABSTRACT... 1

More information

Subject: Wells Hydroelectric Project FERC Project No Bull Trout Management Plan and Incidental Take Annual Report

Subject: Wells Hydroelectric Project FERC Project No Bull Trout Management Plan and Incidental Take Annual Report Ms. Jessica Gonzales April 15, 2015 Wenatchee Office Lead Central Washington Field Office U. S. Fish and Wildlife Service 215 Melody Lane, Suite 119 Wenatchee, WA 98801-5933 Subject: Wells Hydroelectric

More information

CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018

CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 Cedar Creek Hatchery INTRODUCTION Cedar Creek Hatchery is located 1.5 miles east of Hebo off Highway 22, adjacent to Three Rivers, a Nestucca River tributary.

More information

Yakima River Basin Coho Reintroduction Feasibility Study

Yakima River Basin Coho Reintroduction Feasibility Study Yakima River Basin Coho Reintroduction Feasibility Study Yakima Klickitat Fisheries Project Goals and Mission The purposes of the YKFP are to: enhance existing stocks of anadromous fish in the Yakima and

More information

Hatcheries: Role in Restoration and Enhancement of Salmon Populations

Hatcheries: Role in Restoration and Enhancement of Salmon Populations Hatcheries: Role in Restoration and Enhancement of Salmon Populations Hatcheries play a large role in the management, ecology, and evolution of Pacific salmon. Why were/are they built? What are the assumptions

More information

FISH PASSAGE IMPROVEMENT in California s Watersheds. Assessments & Recommendations by the Fish Passage Forum

FISH PASSAGE IMPROVEMENT in California s Watersheds. Assessments & Recommendations by the Fish Passage Forum FISH PASSAGE IMPROVEMENT in California s Watersheds Assessments & Recommendations by the Fish Passage Forum FISH PASSAGE IMPROVEMENT in California s Watersheds The mission of the Fish Passage Forum is

More information

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ OKANAGAN RIVER RESTORATION INITIATIVE - FAQ Initiative background: The health of the q awsitk w (Okanagan River) has been severely impacted by the channelization works that occurred in the mid-1950 s.

More information

Conditions affecting the 2011 and 2012 Fall Chinook Adult Returns to Spring Creek National Fish Hatchery.

Conditions affecting the 2011 and 2012 Fall Chinook Adult Returns to Spring Creek National Fish Hatchery. FISH PASSAGE CENTER 1827 NE 44 th Ave., Suite 240, Portland, OR 97213 Phone: (503) 230-4099 Fax: (503) 230-7559 http://www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: Liz Hamilton, NSIA FROM:

More information

Managing for IHNV in Rainbow Trout at Leaburg Hatchery. Erik Withalm

Managing for IHNV in Rainbow Trout at Leaburg Hatchery. Erik Withalm Managing for IHNV in Rainbow Trout at Leaburg Hatchery Erik Withalm erik.j.withalm@state.or.us Background Mitigate for lost recreational fishing opportunities due to the construction of Blue River and

More information

OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO.

OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO. OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO. 1 Columbia River Compact/Joint State Hearing June 28, 2018 Fisheries under consideration: Treaty commercial

More information

Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River. Kris Homel

Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River. Kris Homel Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River Kris Homel NW Fish Culture Concepts Wilsonville, OR 2015 Historic distribution and abundance

More information

OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018

OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018 OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018 Oxbow Hatchery and Satellites (Upper and Lower Herman Creek Ponds) INTRODUCTION Oxbow Hatchery is located approximately 1 mile east of Cascade Locks, Oregon,

More information

SANDY HATCHERY OPERATIONS PLAN Sandy Hatchery Plan Page 1

SANDY HATCHERY OPERATIONS PLAN Sandy Hatchery Plan Page 1 SANDY HATCHERY OPERATIONS PLAN 2014 Sandy Hatchery Plan Page 1 Sandy Hatchery INTRODUCTION Sandy Hatchery is located along Cedar Creek (a Sandy River tributary) 1.5 miles north of Sandy, Oregon, off Highway

More information

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A.

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A. Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon 1998- February 8, 2 By Greg A. Taylor Oregon Dept. of Fish & Wildlife 315 E. Main Street Springfield, OR 97478

More information

NORTH NEHALEM HATCHERY

NORTH NEHALEM HATCHERY NORTH NEHALEM HATCHERY PROGRAM MANAGEMENT PLAN 2018 Nehalem Hatchery Plan Page 1 North Nehalem Hatchery INTRODUCTION The North Nehalem Hatchery is located on the North Fork Nehalem River 12 miles East

More information

ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017

ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017 ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017 Rock Creek Hatchery INTRODUCTION Rock Creek Hatchery is located on the North Umpqua River, 23 miles east of Roseburg, just off Highway 138. The site is

More information

SALMON RIVER HATCHERY

SALMON RIVER HATCHERY SALMON RIVER HATCHERY OPERATIONS PLAN 2006 Salmon River Hatchery Plan Page 1 Salmon River Hatchery INTRODUCTION Salmon River Hatchery is located four miles north of Lincoln City off Highway 18 near Otis.

More information

UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT

UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 103 UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2013 MAY 31, 2014 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 January 2015 PUGET SOUND ENERGY Baker

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, February 14, 219 9: a.m. 1:3 a.m. Place: CONFERENCE CALL ONLY Contacts:

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, August, 27 9: a.m. :45 a.m. Place: CONFERENCE CALL ONLY Contacts: Frank

More information

NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT

NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT Attachment 4 NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT Figures in Draft Plan of February 28, 27 Figure 1. Map of the Rogue River Basin. PASSAGE ESTIMATES

More information

Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation

Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation Tim Hoffnagle, Rich Carmichael, Joseph Feldhaus, Deb Eddy, Nick Albrecht and Sally Gee Oregon Department of Fish and

More information

MARION FORKS HATCHERY

MARION FORKS HATCHERY MARION FORKS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Marion Forks Hatchery INTRODUCTION Marion Forks Hatchery is located along Marion and Horn Creeks (Santiam River tributaries in the Willamette Basin) about

More information

IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018

IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018 IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018 Irrigon Hatchery INTRODUCTION Irrigon Hatchery is located along the Columbia River above John Day Dam 3 miles west of Irrigon, Oregon. The facility is at an

More information

Lakelse Sockeye Recovery Program

Lakelse Sockeye Recovery Program Lakelse Sockeye Recovery Program The Ninth Annual BC Interior Stewardship Workshop May 7 th and 8 th, 2013 DFO North Coast Resource Restoration Unit Presentation Overview History/background Stock and habitat

More information

LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report

LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report Oregon Department of Fish and Wildlife Fish Research and Development, NE Region Fred R.

More information

BOGUS CREEK SALMON STUDIES 2002

BOGUS CREEK SALMON STUDIES 2002 BOGUS CREEK SALMON STUDIES 2002 BY: JEANNINE RICHEY California Department of Fish and Game KLAMATH RIVER PROJECT 303 SOUTH STREET YREKA, CALIFORNIA 96097 (530) 842-3109 California Department of Fish and

More information

The Blue Heron Slough Conservation Bank

The Blue Heron Slough Conservation Bank 1 The Blue Heron Slough Conservation Bank CONSERVATION BANKING July 19-23, 2010 CASE STUDY SERIES The Blue Heron Slough Conservation Bank (Washington) I. OVERVIEW & BACKGROUND: Location: Snohomish River

More information

Shasta Dam Fish Passage Evaluation. Public Stakeholder Webinar

Shasta Dam Fish Passage Evaluation. Public Stakeholder Webinar Shasta Dam Fish Passage Evaluation Public Stakeholder Webinar 9-24-2015 Today s Topics 1. Introduction Craig Moyle (MWH) 2. Project Overview John Hannon (Reclamation) 3. Sacramento River Conditions and

More information

R & E Grant Application Biennium

R & E Grant Application Biennium R & E Grant Application 15-17 Biennium Project #: 15-053 Elk River Hatchery Maintenance Project Information R&E Project Request: Total Project: Start Date: End Date: Organization: $116,262 $139,300 8/8/2016

More information

Study Update Fish Distribution and Species Composition

Study Update Fish Distribution and Species Composition Study Update Fish Distribution and Species Composition Goals and Study Area Gain a better understanding of fish species composition and abundance in waters associated with the Packwood Lake Hydroelectric

More information

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington for Energy Northwest's Packwood Lake Hydroelectric Project FERC No. 2244 Lewis County, Washington Submitted to P.O. Box 968 Richland, Washington 99352-0968 Submitted by EES Consulting 1155 North State

More information

BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018

BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 Big Creek Hatchery INTRODUCTION Big Creek Hatchery is located 16 miles east of Astoria, Oregon, 2 miles south of Knappa off Highway 30, and is approximately

More information

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1 COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Cole Rivers Hatchery Plan Page 1 Cole Rivers Hatchery INTRODUCTION Cole Rivers Hatchery is located on the Rogue River, 30 miles northeast of Medford, Oregon,

More information

Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist

Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist 1 1. Chester Fish Ladder Project history Monitoring progress 2. Buffalo River

More information

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1 COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN 2019 Plan Page 1 INTRODUCTION is located on the Rogue River, 30 miles northeast of Medford, Oregon, on Highway 62, about ½ mile downstream of Lost Creek Dam.

More information

TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING

TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING August 2011 1 INTRODUCTION This document describes the policy adopted by the Tay District Salmon Fisheries Board for the artificial stocking

More information

LOOKINGGLASS HATCHERY

LOOKINGGLASS HATCHERY LOOKINGGLASS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Lookingglass Hatchery And Imnaha Satellite Facility INTRODUCTION Lookingglass Hatchery is located along Lookingglass Creek, a tributary to the Grande

More information

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017 Final for the Wallowa Falls Hydroelectric Project (FERC No. P-308) June 2017 Prepared by: Jeremiah Doyle PacifiCorp 825 NE Multnomah Street Portland, OR 97232 June, 2017 Page 1 of 8 Table of Contents 1.0

More information

Ecology of Place: What salmon need Eric Beamer Skagit River System Cooperative. November 2010

Ecology of Place: What salmon need Eric Beamer Skagit River System Cooperative. November 2010 Ecology of Place: What salmon need Eric Beamer Skagit River System Cooperative November 2010 Acknowledgements NOAA Fisheries NW Fisheries Science Center Tim Beechie George Pess Correigh Greene Talk overview

More information

FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP)

FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP) FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP) Hatchery Program: Sandy Hatchery Spring Chinook Species or Hatchery Stock: Sandy River Spring Chinook (Stock 11) Agency/Operator: Oregon Department of

More information

Blue Creek Chinook Outmigration Monitoring Technical Memorandum

Blue Creek Chinook Outmigration Monitoring Technical Memorandum Blue Creek Chinook Outmigration Monitoring 2012 Technical Memorandum Prepared by: Andrew Antonetti and Erika Partee Yurok Tribe Fisheries Program PO Box 1027 Klamath, California 95548 In Partnership with:

More information

FISHERIES BLUE MOUNTAINS ADAPTATION PARTNERSHIP

FISHERIES BLUE MOUNTAINS ADAPTATION PARTNERSHIP FISHERIES A warming climate, by itself, substantially affects the hydrology of watersheds in the Blue Mountains. Among the key hydrologic changes projected under all scenarios for the 2040s and beyond

More information

Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin

Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin ACC Participants Present (13) Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin Eli Asher, Lower Columbia River Fish Recovery

More information

CHAPTER 4 DESIRED OUTCOMES: VISION, GOALS, AND OBJECTIVES

CHAPTER 4 DESIRED OUTCOMES: VISION, GOALS, AND OBJECTIVES CHAPTER 4 DESIRED OUTCOMES: VISION, GOALS, AND OBJECTIVES Vision One of the first steps in developing this Plan was articulating a vision - a clear statement of what the Plan strives to achieve and what

More information

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT FEDERAL AID JOB PROGRESS REPORTS F-20-49 2013 LAKE TAHOE WESTERN REGION NEVADA DEPARTMENT OF WILDLIFE, FISHERIES DIVISION ANNUAL PROGRESS REPORT

More information

18 March 2016 Oregon Department of Fish and Wildlife

18 March 2016 Oregon Department of Fish and Wildlife 18 March 2016 Oregon Department of Fish and Wildlife Background Joint OR/WA policy adoption 2012 OR re-adoption of rules 6/13 Transition period (2013-2016) Phased allocation shift Mainstem gillnets allowed

More information

Reproductive success of hatchery chinook salmon in the Deschutes River, Washington

Reproductive success of hatchery chinook salmon in the Deschutes River, Washington Reproductive success of hatchery chinook salmon in the Deschutes River, Washington Howard Fuss Hatchery Wild Interactions Team Washington Department of Fish and Wildlife Acknowledgments HSRG for providing

More information

Kirt Hughes Washington Department of Fish and Wildlife Region 6 - Fish Program Manager

Kirt Hughes Washington Department of Fish and Wildlife Region 6 - Fish Program Manager Kirt Hughes Region 6 - Fish Program Manager Habitat Hatcheries Harvest Clean Water Act Shorelines Harvest Hydro Habitat Forest Practices Non-regulatory Programs Water Supply & Conservation Growth Management

More information

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 North Fork Lewis River Hydroelectric Project Yale FERC No. 2071 Prepared by: Jeremiah Doyle, PacifiCorp April 4, 2017 1.0 INTRODUCTION

More information

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT FEDERAL AID JOB PROGRESS REPORTS F-20-52 2016 LAKE TAHOE WESTERN REGION NEVADA DEPARTMENT OF WILDLIFE, FISHERIES DIVISION ANNUAL PROGRESS REPORT

More information

Cowlitz River Fisheries and Hatchery Management Plan (FHMP)

Cowlitz River Fisheries and Hatchery Management Plan (FHMP) Cowlitz River Fisheries and Hatchery Management Plan (FHMP) Final August 2004 Prepared by Tacoma Power Table of Contents Executive Summary... ix 1.0 Introduction...1 2.0 Settlement Principles and License

More information

Strategies for mitigating ecological effects of hatchery programs

Strategies for mitigating ecological effects of hatchery programs Strategies for mitigating ecological effects of hatchery programs Some case studies from the Pacific Northwest Kathryn Kostow Oregon Department of Fish and Wildlife Ecological risks occur when the presence

More information

Okanagan Sockeye Reintroduction

Okanagan Sockeye Reintroduction Okanagan Sockeye Reintroduction Backgrounder Elders accounts, and other forms of Traditional Ecological Knowledge (TEK) tell us that many species of salmon once came into the Okanagan Valley and tell us

More information

TUTKA BAY LAGOON HATCHERY ANNUAL REPORT 2005

TUTKA BAY LAGOON HATCHERY ANNUAL REPORT 2005 TUTKA BAY LAGOON HATCHERY ANNUAL REPORT 2005 Cook Inlet Aquaculture Association Trenten T. Dodson, CIAA Biologist December 2005 This year s operation of the Tutka Bay Lagoon Hatchery was made possible

More information

2016 Annual Work Plan

2016 Annual Work Plan Rocky Reach Hydroelectric Project FERC No. 2145 2016 Annual Work Plan 2015 Progress Report d per Rocky Reach Settlement Agreement, Sections 15.1.1 & 15.6.5 Reports provided by Chelan PUD Leads: Ray Heit

More information

!Skagit River Basin. Overview FISHERIES 16

!Skagit River Basin. Overview FISHERIES 16 !Skagit River Basin Overview This region includes the watersheds contained by the Skagit River Basin. For the purposes of this review, the Scientific Group reviewed the hatchery programs involving each

More information

Project Award Presentation

Project Award Presentation University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

The Fishery. Newfoundland Region Stock Status Report D2-05

The Fishery. Newfoundland Region Stock Status Report D2-05 Fisheries Pêches and Oceans et Océans DFO Science Newfoundland Region Stock Status Report D2-05 ATLANTIC SALMON INSULAR NEWFOUNDLAND, SOUTHWEST COAST, SALMON FISHING AREAS 12-13 Background Salmon Fishing

More information

ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN Round Butte Hatchery Plan Page 1

ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN Round Butte Hatchery Plan Page 1 ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN 2018 Round Butte Hatchery Plan Page 1 Round Butte Hatchery and Satellite (Pelton Ladder) INTRODUCTION Round Butte Hatchery is located on the Deschutes River

More information

Hatchery Scientific Review Group Review and Recommendations

Hatchery Scientific Review Group Review and Recommendations Hatchery Scientific Review Group Review and Recommendations Lower Snake River Fall Chinook Population and Related Hatchery Programs January 31, 2009 Lower Snake River Fall Chinook Population Report Page

More information

BONNEVILLE HATCHERY PROGRAM MANAGEMENT PLAN 2018

BONNEVILLE HATCHERY PROGRAM MANAGEMENT PLAN 2018 BONNEVILLE HATCHERY PROGRAM MANAGEMENT PLAN 2018 Bonneville Hatchery INTRODUCTION Bonneville Hatchery is located 4 miles west of Cascade Locks, off of Interstate 84 (Exit 40) within the Bonneville Dam

More information

D.B. Wilson Station CCR Landfill

D.B. Wilson Station CCR Landfill D.B. Wilson Station CCR Landfill Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule Closure and Post-closure Care Plan October 11, 2016 Prepared By: Project ID: 160030A Big

More information

11426 Moorage Way P.O. Box 368 LaConner, WA Phone: Fax:

11426 Moorage Way P.O. Box 368 LaConner, WA Phone: Fax: Skagit River System Cooperative 11426 Moorage Way P.O. Box 368 LaConner, WA 98257-368 Phone: 36-466-7228 Fax: 36-466-447 www.skagitcoop.org BULL TROUT USE OF SWINOMISH RESERVATION WATERS Eric Beamer, Rich

More information

Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys

Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys FEDERAL AID IN FISH RESTORATION Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys By Judy Hall-Griswold, Fishery Technician

More information

Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006

Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006 Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006 The following are talking points for the WDFW SEPA Scoping Meetings regarding the preparation of the State-wide and the Puget Sound

More information

LEAVENWORTH COMPLEX HATCHERY PROGRAMS. Presentation to the Independent Science Advisory Board

LEAVENWORTH COMPLEX HATCHERY PROGRAMS. Presentation to the Independent Science Advisory Board LEAVENWORTH COMPLEX HATCHERY PROGRAMS Presentation to the Independent Science Advisory Board FACILIT Y LOCATION AND PURPOSE Leavenworth NFH Spring Chinook (unlisted) and YN Coho production Entiat NFH Summer

More information

McKENZIE RIVER HATCHERY

McKENZIE RIVER HATCHERY McKENZIE RIVER HATCHERY PROGRAM MANAGEMENT PLAN 2017 McKenzie River Hatchery INTRODUCTION McKenzie River Hatchery is located along the McKenzie River approximately 22 miles east of Springfield, Oregon.

More information

Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director

Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director Research Proposal Homing Homing behavior is a striking feature of the biology of Pacific salmon, and is the basis for

More information

MEMORANDUM. Ron Boyce, ODFW Bob Heinith, CRITFC. Michele DeHart. DATE: November 30, Operations

MEMORANDUM. Ron Boyce, ODFW Bob Heinith, CRITFC. Michele DeHart. DATE: November 30, Operations FISH PASSAGE CENTER 1827 NE 44 th Ave., Suite 240, Portland, OR 97213 Phone: (503) 230-4099 Fax: (503) 230-7559 http://www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: Ron Boyce, ODFW Bob Heinith,

More information

Union Pacific Railroad

Union Pacific Railroad Input Questions: 404/401 Pre Application Meeting, December 18, 2013, Portland, Oregon 1. What is the project purpose and need? The purpose of the project is to improve the efficiency and average velocity

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, December 14, 2017 9:00 a.m. 11:15 a.m. Place: Merwin Hydro Control Center

More information