SOUTHBANK PLACE Asbestos Removal (Brief Guide)
|
|
- Alban Hood
- 6 years ago
- Views:
Transcription
1 SOUTHBANK PLACE Asbestos Removal (Brief Guide) The removal of asbestos is regulated by the Control of Asbestos Regulations 2012 and is only undertaken by licensed contractors. The licensing procedures are a permission regime and are in addition to the general framework of health and safety law. The license process is enforced by the Health and Safety Executive (HSE). Other examples of permissioning regime are Nuclear Installations and Railways. The work on the Southbank Place project is being undertaken by McGee Demolition who currently hold a three year license ( the longest duration permitted) issued by the HSE. All works have been notified to the HSE using an ASB5 form, which was sent to the HSE, as required by the regulations, 14 days prior to the commencement of all notifiable works. All works are being carried out in compliance with the requirements set out in the Control of Asbestos Regulations Only competent workers and managers, provided with suitable information, instruction and training and using appropriate respiratory and other protective equipment, are being used to undertake the asbestos removal work. All operatives are briefed on company removal procedures and they are briefed on the controlled methods on a daily basis to reflect the varying types/ products of Asbestos Containing Material (ACM) that require safe removal on this project. These briefings are carried out by contractors supervisors. Each worker has their own medical records & face-fit test for respiratory protection equipment (RPE) and all have current annual refresher training.
2 Enclosures The working areas are enclosed, and all openings such as windows, doors and ventilation sealed to prevent the escape of hazardous fibres. Negative pressure units (NPU s) are used to manage air flow and to also prevent the escape of hazardous fibres. Regular checks of NPU s using anemometers are carried out to ensure they are working to full capacity at all times, replacements are readily available in case of failure Two separate three stage airlock systems are attached to each enclosure wall, one of which will be designated for access/egress of personnel and the second for waste removal. Sheeting used to cover the working area will be a minimum of 1000 gauge (250 microns) polythene. Prior to any asbestos removal work starting the enclosure is smoke tested to ensure its integrity which will be witnessed by independent analyst as well as asbestos supervisor for that particular area. Each enclosure also has viewing panels and CCTV to allow those outside to inspect the work to ensure the safe working methods agreed in the risk assessments and method statements are being followed. Airlock
3 CCTV monitoring system Vision panel
4 Decontamination Units and Hygiene Facilities Each operative must decontaminate after coming into contact with hazardous materials in order to prevent contamination outside the enclosure. Masks are wet wiped with wet sponges and operatives use Type H vacuums to clean their protective coveralls (red) and work boots before removing them in a controlled area and exiting the enclosure. These are then exchanged for a set of clean coveralls (white) and transit shoes which are worn to the decontamination area. Thus, the contaminated coveralls always remain in the safety of the enclosure and are bagged as contaminated waste after each shift. When the operative leaves the enclosure they go straight to the dirty end of the decontamination unit where they will remove their transit coveralls and shoes before entering the middle stage (shower) keeping their mask on until they are wetted. Each operative cleans the mask as part of showering process, shampoo and nail brushes are a minimum requirement in each unit. On completion of showering they will enter the clean area where they will use disposable towels to dry themselves and then put on normal clothes. They leave the decontamination unit after putting their mask on charge and carrying out the relevant checks. Decontamination Unit
5 Negative Pressure and Vacuum Cleaners To control the removal of asbestos fibres, negative pressure units (NPU s) with a High Efficiency Particle Absolute (HEPA) filter is connected. All vacuum cleaners are also fitted with a HEPA filter, and are checked daily and tested every 6 months for worthiness. Air Monitoring In order to ensure that all asbestos fibres have been removed from the enclosure, airborne fibre levels are measured upon completion of the work. These measurements are undertaken by an independent approved testing laboratory. If the levels of fibres per millilitre are below the clearance indicator of 0.01fb/ml, the enclosure can be removed and area returned to normal use. Regular background readings are taken outside of all work areas as well as regular personal monitoring within enclosure. There are 2 full time independent analysts working on the Southbank Place project Removal and Disposal The method of asbestos removal involves wet stripping and injection of all asbestos materials to minimise dust and fibre dispersion. Once removed, the waste and debris is immediately placed into red asbestos bags and sealed, before being moved into the bagging airlock where it is sprayed and sealed inside a second bag, known as double-bagging, before transit to a sealed, lockable skip. This skip is finally transferred following the special waste consignment note procedure to a licensed waste disposal landfill site. Once the bulk of asbestos is cleared, fine cleaning is carried out with vacuum cleaners/ wet cloths to ensure that all traces of asbestos fibres are removed. Both the contractors supervisor and the independent analyst carry out visual checks of each enclosure before air testing to ensure it is dust / debris free. Once the enclosure is removed a second visual check as well as additional air test is carried out prior to releasing the area back for normal operations.
Refresher Licensed Asbestos Supervisor Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS Refresher Licensed Asbestos Supervisor Training This unit has nineteen learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationSite Details. Comments / Corrective Actions Required. Preliminary Requirements Y N N/A SITE MONITORING PROCEDURE ASBESTOS AUDIT FORM.
Site Details Site Address Client and Address Name of Project Supervisor Licensed Contractor Name and Address Description of removal project (ACM) & size of project Project Number Auditor Date Time on site
More informationSyllabus for Licensable Work with Asbestos (Category C)
Syllabus for Licensable Work with Asbestos (Category C) Introduction This syllabus sets out the guidance issued by the UK Asbestos Training Association (UKATA) for the provision of licensed asbestos training
More informationNew Licensed Asbestos Operative Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Operative Training This unit has twenty-two learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationNew Licensed Asbestos Manager Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Manager Training This unit has twenty-three learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationLevel 4 Certificate in Asbestos Removal for Contract Managers
Level 4 Certificate in Asbestos Removal for Contract Managers January 2012 This qualification has a Credit Value of SEVENTEEN Guided Learning Hours: 94 Ofqual Qualification Number: 600/4478/0 Description
More informationUK ASBESTOS TRAINING ASSOCIATION GUIDANCE
UK ASBESTOS TRAINING ASSOCIATION GUIDANCE MINIMUM STANDARDS FOR TRAINING CENTRES Document No: MG003 Issue Date: 18/09/2017 Issue No: 01 UK Asbestos Training Association Limited / MG003 / Page 1 of 5 MINIMUM
More informationList materials, trade names (if applicable), and where they are found on the site:
SAFETY WALKAROUND CHECKLIST ASBESTOS 1994 Date Prepared: Project Name/No: By: Location: Check the box if the statement is true. Fill in the blanks where the appears. HAZARD IDENTIFICATION The company has
More informationIntroduction. B1) Initial training with NO previous asbestos awareness training undertaken;
Syllabus For Non-Licensable Work With Asbestos Including NNLW (formerly known as Category B) Introduction This syllabus sets out the guidance issued by the UK Asbestos Training Association (UKATA) for
More informationRainham Industrial Services Ltd. Plan of Works
Rainham Industrial Services Ltd Plan of Works Enquiry No.: 22246 10 Client : BGCBC Site: Market Hall Cinema Market Square Brynmawr NP23 4AJ Project Title: Asbestos Removal and Encapsulation Prepared by
More informationAsbestos Regulation and Compliance
Asbestos Regulation and Compliance Asbestos workshop for the elevator industry Yvonne Nann Occupational Hygiene Officer WorkSafeBC Yvonne.Nann@worksafebc.com November 25, 2015 Definition of Asbestos-containing
More informationAsbestos Operations and Maintenance Plan
Comprehensive Safety Plan Asbestos Operations and Maintenance Plan Internal Procedure: July 1, 2013 Effective date: July 1, 2013 Last Modified: April 2013 Approved by: Bob Wells Contents Program Objective...3
More informationPLAN OF WORK. Site Address Block 1 4 to 21 Fountain Place Brixton Lambeth SW9 7RE INDEX
PLAN OF WORK Site Address Block 1 4 to 21 Fountain Place Brixton Lambeth SW9 7RE INDEX 13-537 Block 1 4-21 Fountain Place Brixton Lambeth SW9 7RE Page 1 of 22 Section 1 Details of Contract 1.1 Name and
More informationControl of Work. Introduction This procedure describes the management of Asbestos. Definitions
Home Knowledge Control of Work Search Asbestos Introduction This procedure describes the management of Asbestos. The management approach shall be in accordance with the requirements of the Control of Asbestos
More informationNew Asbestos Analyst Guide
New Asbestos Analyst Guide BOHS Conference April 2016 Dr Martin Gibson HSE, Edinburgh New Analyst Guide: Agenda Introduction Analyst Guide Initial feedback on Consultation Quick overview of approach Main
More informationBEGINNING THE MEETING
Asbestos This safety talk is designed for discussion leaders to use in preparing safety meetings. Set a specific time and date for your safety meeting. Publicize your meeting so everyone involved will
More informationExposure Control Plan for Drilling/Grinding Concrete
Exposure Control Plan for Drilling/Grinding Concrete Drilling or grinding into concrete without proper dust controls can generate high levels of silica-containing dust. Breathing in this fine dust can
More informationWILL NOT DISTURB ASBESTOS CONTAINING MATERIAL!
Title: Asbestos Awareness and Safety Effective Date: 11/17/2014 Control Number: THG_0036 Revision Number: 2 Date: 6/23/2015 Annual Review Completed: 5/13/2015 Asbestos Safety NOTE: Currently The Hillis
More informationCSU Channel Islands Lead Operations and Maintenance Program
CSU Channel Islands Lead Operations and Maintenance Program 1.0 Policy It is the policy of California State University Channel Islands to provide employees and visitors with a safe and healthful environment.
More informationSafe Work Practices / Procedures / Instruction ASBESTOS. (See also Asbestos Exposure Control Plan )
ASBESTOS (See also Asbestos Exposure Control Plan ) The owner or the principal contractor must ensure that the WCB receives a Notice of Project at least 24 hours before beginning work on the following
More informationEstates & Facilities Management - Management and Control of Asbestos Policy and Procedures
Estates & Facilities Management - Management and Control of Asbestos Policy and Procedures V 3 May 2018 Estates Division Estates and Facilities Management Headington Campus Gipsy Lane Headington Oxford
More informationAbrasive Blasting Removal Systems
Appendix 6/17 Minutes of the 19 th meeting of the ALG Technical Working Group, 17 October 2017 Abrasive Blasting Removal Systems Appendices are attached to Technical Working Group minutes when the nature
More informationARCA Guidance Note. Guidance on Air Management in Asbestos Enclosures
Guidance on Air Management in Asbestos Enclosures 1 GUIDANCE ON AIR MANAGEMENT IN ASBESTOS ENCLOSURES 1. BACKGROUND 1.1 This guidance note is intended to clarify expectations with regard to air management,
More informationR2D2P. Working group report
R2D2P Working group report Working group members: Clédola Cassia Oliveira de Tello (Brazil), Farouk Abdel-Rahman (Egypt), Ibrahim Muhamad (Malaysia), Milan Vujovic (Serbia), Quang Huy Pham (Vietnam) Team
More informationSECTION LEAD-BASED PAINT REMOVAL AND DISPOSAL
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 02 83 33.13 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationSECTION LEAD-PAINT REMOVAL
SECTION 02090 LEAD-PAINT REMOVAL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies abatement and disposal of lead-based paint (LBP) and controls needed to limit occupational and environmental exposure
More informationAsbestos Management Plan
Asbestos Management Plan Prepared by: Health, Safety and Emergency Management Date of Issue: 30 November 2016 Version 7.0 Uncontrolled document when printed Page 1 of 23 TABLE OF CONTENTS 1. Introduction
More informationIn addition to the responsibility for managing the elements of the respiratory protection program, he/she will be responsible for:
EBBE (1 of 7) EBBE RESPIRATORY PROTECTION POLICY The Muskogee School District is acknowledged as the employer, and as outlined under current Federal regulations, is assigned the responsibility to provide
More informationOPERATIONAL GUIDELINE P R O C E D U R E
OPERATIONAL GUIDELINE O.G. # 2.23.12.04 TITLE: HAZMAT HAZARDOUS SUBSTANCES- ASBESTOS PURPOSE: SCOPE: POLICY: To provide information to Burnaby Fire Department personnel regarding a consistent response
More informationSilica Dust Safety Program
Silica Dust Safety Program Prepared by: The Ohio State University Environmental Health and Safety Occupational Safety & Industrial Hygiene 1314 Kinnear Road Columbus, OH 43212-1168 614-292-1284 Phone 614-292-6404
More informationASBESTOS STANDARD SYSTEMS OF WORK
ASBESTOS STANDARD SYSTEMS OF WORK SFR MPS-006 Issue 7 Rev 1 H.E.S Asbestos Standard Systems of Work Page - 1 - of 28 ASBESTOS STANDARD SYSTEMS OF WORK Author Checked Issue Date Issue Number DC KB 03.10.14
More informationControl of Allergies to Laboratory Animals
Health and Safety Policy Control of Allergies to Laboratory Animals UHSP/21/CALA/03 This document sets out in more detail the arrangements for compliance with University Health and Safety Policy at Budget
More informationPLEASE DO NOT WRITE ON THIS EXAM
PLEASE DO NOT WRITE ON THIS EXAM Your instructor will provide you with the registration form you completed at the beginning of this course. Please use the back of the signed registration form to record
More informationPLEASE DO NOT WRITE ON THIS EXAM
PLEASE DO NOT WRITE ON THIS EXAM Your instructor will provide you with the registration form you completed at the beginning of this course. Please use the back of the signed registration form to record
More informationLead Exposure Control Plan
Prepared for: Operations and Maintenance Department School District #27 Cariboo-Chilcotin Lead Exposure Control Plan Prepared by #210-2950 Douglas Street Victoria, British Columbia V8T 4N4 Version 1.0
More informationManaging worker exposure to dust in mines and quarries
Managing worker exposure to dust in mines and quarries Contents 1 Introduction 1 2 Terminology 2 Silica 2 Respirable Crystalline Silica (RCS) 2 Exposure monitoring 2 Health monitoring 2 Spirometry 2 3
More informationSECTION ASBESTOS ABATEMENT. Removal of asbestos-containing materials and paint preparation work. A. Section 01015: Summary of Work.
I PART 1 GENERAL I.1 SECTION INCLUDES Removal of asbestos-containing materials and paint preparation work. I.2 RELATED DOCUMENTS AND SECTIONS A. Section 01015: Summary of Work. B. Section 01300: Submittals.
More informationPalm Beach State College. Florida s First Public Community College SILICA EXPOSURE CONTROL PLAN
Palm Beach State College Florida s First Public Community College SILICA EXPOSURE CONTROL PLAN 2018 Purpose The purpose of this document is to establish and implement a written exposure control plan that
More informationHelping you to correctly select and use respirators. With support from
Helping you to correctly select and use respirators With support from Damage to your workers lungs and other parts of their bodies can seriously affect their health it can also affect your business! Don
More informationNewport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Sewage
Newport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Sewage Newport News Shipbuilding Page 1 SEWAGE 1. Hazard, Reference and Requirements a. Sewage is a potential hazard
More informationE3628 THE RESPIRATORY PROTECTION PROGRAM: EMPLOYEE TRAINING. Leader s Guide ERI Safety Videos EMPLOYEE TRAINING
E3628 THE RESPIRATORY PROTECTION PROGRAM: EMPLOYEE TRAINING Leader s Guide 2007 ERI Safety Videos THE RESPIRATORY PROTECTION PROGRAM: EMPLOYEE TRAINING This easy-to-use Leader s Guide is provided to assist
More information2.0 Management Systems and Documentation
SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This
More informationLABORATORY ANIMAL ALLERGEN PREVENTION PROGRAM
CONTENTS 1.0 PURPOSE 2.0 DEFINITIONS 3.0 SCOPE AND APPLICATION 4.0 RESPONSIBILITIES 5.0 PROGRAM ELEMENTS 6.0 SOP REVIEW/REVISION 1.0 PURPOSE The purpose of this program is to reduce or eliminate exposure
More informationBREATHE SAFELY: The Proper Use of Respiratory Protection
BREATHE SAFELY: The Proper Use of Respiratory Protection This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of
More informationWHS F029 Job Safety Analysis (JSA) and volume less than 10m2
Handling Archaeological Asbestos Fragments Non-friable Title and volume less than 10m2 School/Business Unit Humanities Location (building/lab/ workshop if applicable) JSA Development 9 June 2017 JSA Development
More information1 ASBESTOS CEMENT PIPE CUTTING AND HANDLING
1 ASBESTOS CEMENT PIPE CUTTING AND HANDLING City of Surrey 2 PURPOSE The City of Surrey Water, Sanitary and Storm Sewer Systems exposure to asbestos is from Asbestos Cement (AC) pipe. Asbestos cement pipe
More informationUniversity of Delaware Respirable Crystalline Silica Dust Program June 2018
University of Delaware Respirable Crystalline Silica Dust Program June 2018 Prepared by: University of Delaware Department of Environmental Health and Safety 222 S. Chapel Street Newark, DE 19716 www.udel.edu/ehs
More informationAsbestos Management Plan
Asbestos Management Plan Ratified by the Finance and Buildings Committee: July 2018 ASBESTOS MANAGEMENT PLAN CONTENTS Policy Statement 4 Introduction 5 Purpose 5 Scope 5 Definitions 6 Abbreviations 6
More informationRemoval of Lead-Based Paint
Safety Management System SP24-61 Process Authority: HS Manager Removal of Lead-Based Paint Approval: Chief Operating Officer Version Date:30/03/2015 Revision: B 1 Purpose To define the requirements for
More informationChapter 7 Inspector Safety
Inspector Safety Safety requirements and/or guidelines for government employees involved in asbestos activities are addressed in one form or another in regulations and policies developed by several federal
More informationCHAPTER 39: SILICA AWARENESS
CHAPTER 39: SILICA AWARENESS 511 Purpose To reduce team member exposure to airborne crystalline silica to below the OSHA Permissible Exposure Limit (PEL) by means of substitution, engineering controls,
More informationAsbestos: The analysts guide for sampling, analysis and clearance procedures
Asbestos: The analysts guide for sampling, analysis and clearance procedures This is a free-to-download, web-friendly version of HSG248 (First edition, published 2006). This version has been adapted for
More informationAirborne Activity Sampling and Monitoring at Hinkley Point A Site. David Williams, Hinkley Point A Site
Airborne Activity Sampling and Monitoring at Hinkley Point A Site David Williams, Hinkley Point A Site Presentation objectives Ventilation controls in use at Hinkley Point A Site The air sampling and monitoring
More informationSpring Student News. Construction (Design and Management) Regulations 2007: A Briefing
Spring 2007 Student News Welcome to the Spring 2007 RRC Student Focus. We hope you find it a useful source of information. Construction (Design and Management) Regulations 2007: A Briefing The Construction
More informationPOLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY
POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY Written By: Nursery Manager Date approved by Directors: Signature: Date for Review: November 2018 COSHH (CONTROL OF SUBSTANCES HAZARDOUS
More informationAsbestos. August 1986 SHELL SAFETY COMMITTEE
Asbestos The companies belonging to the Royal Dutch/Shell Group of companies are separate and distinct entities, but in this document the collective expressions "Shell" and "Group" are sometimes used for
More informationHealth and Safety Executive. Asbestos: The analysts' guide for sampling, analysis and clearance procedures
Health and Safety Executive Asbestos: The analysts' guide for sampling, analysis and clearance procedures Health and Safety Executive Asbestos: The analysts' guide for sampling, analysis and clearance
More informationSAFETY AND HEALTH IN THE USE OF CHEMICALS AT WORK
THEME nº44: RESPONSIBLE: Basics Principles of Prevention FOUR PRINCIPLES OF OPERATIONAL CONTROL The general objective in the control of hazards relating to chemicals in the workplace is to eliminate or
More information1. The laboratory supervisor must enforce the institutional policies that control access to the laboratory.
APPENDIX E-3: Biosafety Level 3 (BSL-3) The following is taken from the Biosafety in Microbiological and Biomedical Laboratories (BMBL) 5 th Edition, February 2009 Centers for Disease Control and Prevention
More informationDoc No: ARSENIC Midland Engineering Co., Inc. Initial Issue Date 12/09/15 Safety Management System
Midland Engineering Co., Inc. Revision Page 1 of POLICY The purpose of this Program is to define the key elements of an Arsenic Program to minimize and/or eliminate worker exposures to inorganic arsenic
More informationRPE with a UK Standard Assigned Protection Factor 10 (APF10)
Health and Safety Executive R COSHH essentials: Supplementary advice RPE with a UK Standard Assigned Protection Factor 10 (APF10) Control approach R Respiratory protective equipment (RPE) The Control of
More informationTEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY
Page 1 of 9 ISSUED: 5/00 REVISED: 08/06 Introduction Purpose: In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to Ethylene Oxide. Applicability
More informationEffective Date: 24-April-2017 Version: 6 Page: 1 of 8 TITLE: SAF-370, PERSONAL PROTECTIVE EQUIPMENT GUIDELINES. Table of Contents
24-April-2017 Version: 6 Page: 1 of 8 Table of Contents 1.0 Introduction... 2 1.1 Purpose... 2 1.2 Scope... 2 1.3 Definitions... 2 1.4 Responsibilities... 3 Environmental Health and Safety Office (EHSO),
More informationRESPIRATORS & FIT TESTING
RESPIRATORS & FIT TESTING Presented By: Jamie Papian Licensed Lead & Asbestos Inspector Licensed Lead & Asbestos Abatement Supervisor HUD Housing Quality Standards Inspector State of Iowa, Illinois and
More informationSYLLABUS RESPIRATORY PROTECTIVE EQUIPMENT COMPETENT PERSON
Introduction This syllabus sets out the guidance for the provision of respiratory protective equipment training for competent persons as detailed within HSG53 Respiratory Protective Equipment at Work and
More informationTEMPLE UNIVERSITY A Commonwealth University Environmental Health & Radiation Safety (EHRS)
Page 1 of 8 TEMPLE UNIVERSITY A Commonwealth University Environmental Health & Radiation Safety (EHRS) Standard Operating Procedure (SOP) Bromodeoxyuridine (BrdU) Principal Investigator: Room & Building
More informationU.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL
SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to
More informationContractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.
Working Together Contractor Control Procedures November 2014 Borders College 24/11/2014 1 Working Together 1. Introduction This procedure aims to control the health and safety of contractors working on
More informationRepair FRC Building 1553 Work Order Number: RM NS, Mayport, FL SECTION ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
SECTION 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications
More informationSILICA EXPOSURE PREVENTION PROGRAM
SILICA EXPOSURE PREVENTION PROGRAM A. BEFORE ANY EMPLOYEE GRINDS OR SAW CUTS CONCRETE AND WEARS A RESPIRATOR HE OR SHE MUST HAVE: 1. A medical examination, medical and occupational history to collect data
More informationTEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY
Purpose In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to glutaraldehyde. Applicability This policy is applicable to all Temple University
More informationMidwest Consortium 8HR Modular Exam Inspect/Don/Doff
8HR Modular Exam Inspect/Don/Doff 1. Important reasons to inspect respirators include: A. All of the following B. Make sure the elastic parts are still stretchy C. Valves have not been removed or damaged
More informationHealth, Safety and Environment Management System. Crystalline Silica Exposure Control Plan PROCEDURE
Health, Safety and Environment Management System Crystalline Silica Exposure Control Plan PROCEDURE APPROVAL AND VERSION HISTORY Approved by: Crystalline Silica Exposure Control Plan Version # 00 (signature)
More informationSTANDARD OPERATING PROCEDURE (SOP): URETHANE
TEMPLE UNIVERSITY A Commonwealth University Environmental Health & Radiation Safety (EHRS) STANDARD OPERATING PROCEDURE (SOP): URETHANE LABORATORY/USER INFORMATION Principal Investigator (PI): Phone #
More informationThe routine maintenance and inspection of local exhaust ventilation (LEV)
The routine maintenance and inspection of local exhaust ventilation (LEV) This document details the standards for inspection and maintenance that should be achieved for all local exhaust ventilation owned
More informationHealth, Safety, Security and Environment
Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change; text clarification-no
More informationGuide Asbestos Regulations 2001
Published: March 2003 Department of labour Guide Asbestos Regulations 2001 Chief Directorate: Occupational Health and Safety NO: OHC 1 2 FOREWORD The purpose of this document is to provide guidance to
More informationGlossary. Terms in CAPITALS are defined in the glossary. ABATEMENT
Glossary Terms in CAPITALS are defined in the glossary. ABATEMENT ACM ADEQUATELY WET AGGRESSIVE SAMPLING AHERA AIRLOCK AIR - PURIFYING AIR SAMPLES AIR-SUPPLIED ALVEOLI Lessening the HAZARD of ASBESTOS.
More informationSeed Treatment Safety and Regulations Crop Protection Perspective. Chip Witcher / Staff Industrial Hygienist / Syngenta Crop Protection
Seed Treatment Safety and Regulations Crop Protection Perspective Chip Witcher / Staff Industrial Hygienist / Syngenta Crop Protection Objectives The objectives of this presentation are to... - Describe
More informationMSE CONTROLLED DOCUMENT. Radiological HSE Precautions for Pigging Operations
MSE CONTROLLED DOCUMENT Radiological HSE Precautions for Pigging Operations Document No: Supersedes Revision no: 1 1/10/2004 Custodian: MSE Revision no: 1 1/10/2006 Filename: NORMMGT. DOC Administered
More informationPERSONAL PROTECTIVE EQUIPMENT
C H A P T E R 9 PERSONAL PROTECTIVE EQUIPMENT 9.1. General Personal protective equipment (PPE) when properly used and maintained saves lives and reduces injury and illness. PPE includes equipment for eyes,
More informationTitle: Hexavalent Chromium Compliance. Preparer: Owner: Approver: Texas EHS EHS Team Member
Procedure No.: PA-020-0059 Page: 1 of 8 Port Arthur, TX. Reviewed: 06/18 Effective: 08/01/18 Supersedes: 03/12/12 (Rev. 2) Preparer: Owner: Approver: Texas EHS Hub Team Members EHS Team Member EHS Manager
More informationUniversity of Dayton Respiratory Protection Program 29 CFR
University of Dayton Respiratory Protection Program 29 CFR 1910.134 What to expect from this training: Employees who are required to use respirators must be trained such that they can demonstrate knowledge
More informationSilica Protection Plan
Title: Silica Protection Plan Effective Date: 12/1/2014 Control Number: THG_0043 Revision Number: 1 Date: 10/23/2015 Annual Review Completed: 5/13/2015 Silica Protection Plan CONTENTS I. INTRODUCTION II.
More informationPresented by: Laura Cullom Phillips 66 Rodeo Jay Prescott Shell Martinez Refinery
Presented by: Laura Cullom Phillips 66 Rodeo Jay Prescott Shell Martinez Refinery WHAT IS CRYSTALLINE SILICA? Silica is a naturally occurring mineral found in rock, sand, stone, concrete, brick, mortar,
More informationCanada Labour Code Part II Occupational Health and Safety
Canada Appeals Office on Bureau d appel canadien en Occupational Health and Safety santé et sécurité au travail 165 Hôtel de Ville, Hull, Quebec, K1A 0J2 Fax : (819) 953-3326 Canada Labour Code Part II
More informationRESPIRATORY PROTECTIVE EQUIPMENT ADVICE FOR PERSONS CONDUCTING A BUSINESS OR UNDERTAKING
H E A LT H & S A F E T Y AT WO R K HSWA AC T FACT SHEET RESPIRATORY PROTECTIVE EQUIPMENT ADVICE FOR PERSONS CONDUCTING A BUSINESS OR UNDERTAKING This fact sheet is for persons conducting a business or
More informationWelcome. Contractors Forum Safety. Thursday 21 April Queensland Urban Utilities
Welcome Contractors Forum Safety Thursday 21 April 2016 2014 Queensland Urban Utilities Housekeeping & agenda Michael Broadbent Contracts & Assurance Services Leader 1. Workplace Health and Safety Queensland,
More informationStandards of Practice Respiratory Protection: Appendix C
Document Authority: EHS Coordinator Standards of Practice Respiratory Protection: Appendix C Document Custodian: EH&S Coordinator Effective Date: 09.01.15 Issuing Dept: College of Agriculture EH&S Next
More informationProficiency Module Syllabus. P601 - Thorough Examination and Testing of Local Exhaust Ventilation Systems
Proficiency Module Syllabus P601 - Thorough Examination and Testing of Local Exhaust Ventilation Systems Aim To provide the methodology, theoretical and practical knowledge to enable candidates to: Understand
More informationInstructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.
APPENDIX F - RISK CONTROL PLAN FORMAT FOR CONTRACTORS OF THE PANAMA CANAL Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply,
More informationOccupational Health and Safety. Bulletin. Asbestos Containing Materials in Buildings to be Demolished. Superseded
Occupational Health and Safety Bulletin Asbestos Containing Materials in Buildings to be Demolished During previous revisions to the occupational health and safety legislation, asbestos requirements from
More informationHAZWOPER 8-Hr Refresher Aug. 20, 2012
Institute for Tribal Environmental Professionals Tribal Lands and Environment: A National Forum on Solid Waste, Emergency Response, Contaminated Sites and USTs August 20-23, 2012 Coos Bay, Oregon HAZWOPER
More informationOSHA s Proposed Silica Rule Randy Nicholls Northwestern Energy
OSHA s Proposed Silica Rule 1910.1053 Randy Nicholls Northwestern Energy Exposure Limit Comparison Previous Permissible Exposure Limit from Table Z- 3, Mineral Dusts, had to be calculated as follows: Quartz
More informationCSTMC Asbestos Management Policy and Procedures
ASBESTOS MANAGEMENT PLAN FOR COLLECTIONS at the CANADA SCIENCE AND TECHNOLOGY MUSEUM CORPORATION October 2010 1. FOREWORD 1.1. This document specifies the Canada Science and Technology Museum Corporation
More informationGeneral Health & Safety Information Sheet
General Health & Safety Information Sheet 1. Products & Company Identification Greenspan UK Ltd. distributes the following products on behalf of Everest Industries for the United Kingdom and Republic of
More informationLaboratory Self Inspection Checklist LAB01
Laboratory Self Inspection Checklist LAB01 General Chemical/Biological Laboratories Location Assessor Date This core checklist is provided by the Health and Safety Department as a template, which provides
More informationChemical Spill Clean-up Protocol
Protocol Department of www.rms.ubc.ca UBC-RMS-OHS-PRO 17-002 Date created: November 3, 2015 Date revised: April 28 th, 2017 Chemical Spill Clean-up Protocol Scope Laboratory-specific safe work procedures
More informationMSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for NORM Contaminated Tanks, Vessels & Separators
MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for NORM Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE/32 Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered
More informationCONFINED SPACE PROGRAM
CONFINED SPACE PROGRAM Last updated: November 2017 1.0 PURPOSE Entry into a confined space represents a significant risk of serious injury or death to individuals not prepared for the hazards they may
More information