B741 TEMPORARY CONCRETE BARRIERS - OPSS 741

Size: px
Start display at page:

Download "B741 TEMPORARY CONCRETE BARRIERS - OPSS 741"

Transcription

1 B741 TEMPORARY S - OPSS GENERAL Temporary concrete barriers (TCBs) are precast units that are installed with interlocking devices connecting consecutive sections. The following types of connections are acceptable for use on roadways with posted speeds less than 70 km/h: I-Lock Type J Type M Type T The following types of connections are acceptable for use on roadways with posted speeds of 70 km/h and greater: Type J Type M Type T The contractor shall select the type of TCB according to the specification and applicable special provisions TCB Restraint Systems TCBs are often used to provide separation between traffic and work zones. In locations where inadequate offset is available to allow for deflection of the TCBs (e.g. at edges of excavations, edges of structures, or adjacent to structures not designed for impacts), it may be necessary to restrain the barrier to minimize deflection. Restraining details have been successfully crash tested to NCHRP Report 350 TL-3 for the Type M TCB. The three restraint systems acceptable for use in MTO contracts include the following: 1) Pinning to asphalt pavement 2) Strapping to concrete pavement or bridge deck (with or without asphalt overlay) 3) Bolting through concrete bridge deck (with or without asphalt overlay) Only the TCB Type M connection shall be used with restraint systems. February 2014 Page 1 of 5 B741

2 Unrestrained TCB shall be transitioned to restrained TCB as shown on the applicable OPSD. Similarly, unrestrained TCB shall be transitioned to permanent concrete barrier as shown on the applicable OPSD. The three TCB Restraint System tender items cover only the supply, installation, and removal of the restraint system. Temporary Concrete Barrier and Temporary Concrete Barrier, Relocation tender items are computed separately. Designers should refer to the Roadside Safety Manual for guidance on when to consider restraining TCB REFERENCES Roadside Safety Manual Highway Design Bulletin TENDER ITEMS Temporary Concrete Barrier Temporary Concrete Barrier Relocation Temporary Concrete Barrier, Drainage Gap Temporary Concrete Barrier Restraint System Pinned Temporary Concrete Barrier Restraint System Strapped Temporary Concrete Barrier Restraint System Bolted The tender item "Temporary Concrete Barrier" is used for the following work: a) Supplying and transporting the barriers to the site; b) The initial installation and including any additional barriers required for subsequent staging; and c) Removal of barriers after construction has been completed. The tender item "Temporary Concrete Barrier Relocation" is used for the following work: a) Relocating the barriers within the work area as required for staging or seasonal shutdown for carryover projects; and b) The temporary storage of barriers at the site or other designated locations as necessitated by staging or seasonal shutdown for carryover projects. February 2014 Page 2 of 5 B741

3 741.4 SPECIFICATIONS The requirements for TCBs and TCB restraint systems are contained in OPSS SPECIAL PROVISIONS Refer to Chapter 'E' of this Manual to review the applicable standard special provisions. Non-standard special provisions are required to specify and provide payment for: TCB that is to remain on a project upon its completion; The identification of specific temporary storage sites for TCB that cannot be accommodated within the project limits during staging or seasonal shutdown on carryover projects; and Restoration of asphalt and concrete surfaces that are disturbed during the installation and removal of TCB restraint systems STANDARD DRAWINGS Applicable standard drawings are contained in the 900 series of the Ontario Provincial Standards Drawings (OPSD) DESIGN TCB drainage gaps shall only be used when warranted based on the results of a hydraulic analysis. Prior to the 60% completion stage of detail design, the designer shall send to the Ministry s Design and Contract Standards Office and Bridge Office the proposed location and quantity of TCB restraint systems along with a typical section(s) showing lane widths, shoulder widths, and offset of the TCB to edge of the excavation or structure COMPUTATION These are Plan Quantity Payment items. Quantities are computed in metres. Measurements are scaled or measured along the centreline of each installation. February 2014 Page 3 of 5 B741

4 The turned down and/or flared end treatment is included in the computed length. Energy attenuators are not included in the computed length. The unit of measurement for TCB drainage gaps is each complete installation. Transitions from restrained TCB to unrestrained TCB are included in the computed length for the appropriate TCB restraint system. When a transition from unrestrained TCB to permanent concrete barrier is included in the contract, the length of the transition is included in the computed length for the appropriate TCB restraint system DOCUMENTATION TCBs are depicted on the contract drawings with the designation TCB or TCB Relocation shown adjacent to the symbol. Detail the station and offset for the start and end of each change in direction and/or offset of TCB. Show the locations of the TCB drainage gaps on the contract drawings with the OPSD reference and station shown adjacent to the symbol. Temporary Concrete Barrier - this item pays for the supply of the precast units, the total cannot exceed the largest number of units in place at any one time during the contract. Measurement is from end to end of all locations including end sections. Temporary Concrete Barrier, Relocation - This item will be comprised of all relocations during the contract. Measurement is from end to end of each individual relocation, including end sections. Temporary concrete barrier and temporary concrete barrier, relocation lengths are computed and entered on the Quantities-Miscellaneous" sheets, showing station to station and location, left or right of centreline. Provide offsets if required. For contracts that include multiple construction stages, the quantities shall be broken down by each individual stage. Enter each TCB drainage gap installation in the Quantities Miscellaneous sheets as a separate line entry under the appropriate column heading showing station and location, left or right of centreline. Provide offsets if required. For contracts that include multiple construction stages, the quantities shall be broken down by each individual stage. TCB restraint system locations are depicted on the contract drawings with the appropriate OPSD number shown adjacent to the symbol. The limits of restraint shall February 2014 Page 4 of 5 B741

5 be clearly indicated. The applicable standard drawings shall be included in the contract. TCB restraint system lengths are computed and entered on the Quantities- Miscellaneous" sheets under the appropriate column heading, showing station to station and location, left or right of centreline. Provide offsets if required. Total each column and transfer the tender totals to the tender document. For contracts that include multiple construction stages, the quantities shall be broken down by each individual stage Documentation Accuracy Station and quantity entries are recorded to the nearest whole metre. Offsets when required are recorded to 0.1 of a metre. Spot checking required. February 2014 Page 5 of 5 B741

B741 - TEMPORARY CONCRETE BARRIERS - OPSS 741

B741 - TEMPORARY CONCRETE BARRIERS - OPSS 741 B741 - - OPSS 741 741.1 GENERAL Temporary concrete barrier (TCB) is a portable barrier system consisting of freestanding precast concrete segments that are positively connected together to form a continuous

More information

Illini Union Champaign, IL. February 24, Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering

Illini Union Champaign, IL. February 24, Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering Illini Union Champaign, IL February 24, 2015 Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering Temporary Concrete Barrier Pinning and Drop-off Policy

More information

Traffic Management Guidelines for Structure Rehabilitation Projects

Traffic Management Guidelines for Structure Rehabilitation Projects , Traffic Management Guidelines for Structure Rehabilitation Projects February 2009 1 Purpose & Background These guidelines were prepared in order to assist the Regional Structural Office in determining

More information

Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion

Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion The SMART Steel Crash Cushion is accepted for use on the New South Wales classified road network. The acceptance is based on the determination

More information

Accommodating Pedestrians in the Work Zone

Accommodating Pedestrians in the Work Zone Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,

More information

SMART STEEL CRASH CUSHION

SMART STEEL CRASH CUSHION APRIL 2015 DETAIL SHEET SMART STEEL CRASH CUSHION VicRoads Requirements Refer to Austroads - Safety Barrier System Acceptance Conditions for the SMART Steel Crash Cushion. All requirements listed by Austroads

More information

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

BARRIER OFFSET 0 A 6 6 A 12 12 A 26 A 26 3A OR 4A L OR S * ** L OR S L OR S ACCEPTABLE (TCB) TYPES AND ANCHORING DETAILS BASED ON UNDERLYING SURFACE TYPE AND BARRIER OFFSET FROM DROP-OFF BARRIER OFFSET UNDERLYING SURFACE 0" A 6" 6" A 12" 12" A 26" A 26" TCB TYPE DETAIL TCB TYPE

More information

ADA on Construction. Guidance for Section C Plan Preparers

ADA on Construction. Guidance for Section C Plan Preparers ADA on Construction Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However, good planning can minimize

More information

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways WYDOT DESIGN GUIDES Guide for Non-NHS State Highways 2014 GUIDE FOR Non-NATIONAL HIGHWAY SYSTEM (Non-NHS) STATE HIGHWAYS PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION This Guide is directed to

More information

Plan prepared for: Brennan Paving and Construction. Plan prepared by: Direct Traffic Management

Plan prepared for: Brennan Paving and Construction. Plan prepared by: Direct Traffic Management Traffic Control Plan Hwy 401 - Bridgeland Avenue / Site 37-283 Grading, Drainage, Garnular Base, Hot Mix Paving, Electrical, Structural and Plan prepared for: Plan prepared by: General Notes WB 401 Collector

More information

CHAPTER 1 STANDARD PRACTICES

CHAPTER 1 STANDARD PRACTICES CHAPTER 1 STANDARD PRACTICES OBJECTIVES 1) Functions and Limitations 2) Standardization of Application 3) Materials 4) Colors 5) Widths and Patterns of Longitudinal Pavement Marking Lines 6) General Principles

More information

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate)

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate) WYDOT DESIGN GUIDES Guide for NHS Arterial (Non-Interstate) 2014 GUIDE FOR NATIONAL HIGHWAY SYSTEM (NHS) HIGHWAYS (NHS ARTERIALS, Non-Interstate) PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION

More information

Traffic Control Inspection Checklist Segment:

Traffic Control Inspection Checklist Segment: Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager

More information

Design Criteria. Design Criteria

Design Criteria. Design Criteria F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road

More information

Errata Date February 2016 Errata Edition Field. Ontario Traffic Manual Book 7 Field Edition (FE) - ERRATA

Errata Date February 2016 Errata Edition Field. Ontario Traffic Manual Book 7 Field Edition (FE) - ERRATA Errata Date February 2016 Errata Edition Field Ontario Traffic Manual Book 7 Field Edition (FE) - ERRATA Errata Reference Number Item Number 100 Page No. 39 Errata 7FE/001/16 The first bullet point under

More information

DISTRIBUTION: Electronic Recipients List TRANSMITTAL LETTER NO. (13-01) MINNESOTA DEPARTMENT OF TRANSPORTATION. MANUAL: Road Design English Manual

DISTRIBUTION: Electronic Recipients List TRANSMITTAL LETTER NO. (13-01) MINNESOTA DEPARTMENT OF TRANSPORTATION. MANUAL: Road Design English Manual DISTRIBUTION: Electronic Recipients List MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards Unit ISSUED BY: Office of Project Management and Technical Support TRANSMITTAL LETTER NO.

More information

MANUAL OF TEMPORARY TRAFFIC CONTROL ON CITY STREETS

MANUAL OF TEMPORARY TRAFFIC CONTROL ON CITY STREETS MANUAL OF TEMPORARY TRAFFIC CONTROL ON CITY STREETS PUBLIC WORKS DEPARTMENT 2015 REVISION 1-2016 REVISION SUMMARY - MARCH 2016 Introduction 1.05 - Specifications for Traffic Control Devices Temporary Traffic

More information

MNDOT PAVEMENT DESIGN MANUAL

MNDOT PAVEMENT DESIGN MANUAL MNDOT PAVEMENT DESIGN MANUAL Chapter 6 Ramps, Shoulders, Turn Lanes & Miscellaneous Pavements MnDOT Pavement Engineer Date Contents Introduction... 1 600 Ramps and Loops... 1 610 - Shoulders... 2 620 -

More information

CHAPTER 6H. TYPICAL APPLICATIONS

CHAPTER 6H. TYPICAL APPLICATIONS Section 6H.01 Typical Applications Support: CHAPTER 6H. TYPICAL APPLICATIONS Chapter 6G contains discussions of typical temporary traffic control activities. Chapter 6H presents typical applications for

More information

Manual Of Standard Traffic Signs And Pavement Markings Alberta

Manual Of Standard Traffic Signs And Pavement Markings Alberta Manual Of Standard Traffic Signs And Pavement Markings Alberta Traffic Accommodation and Control Alberta Highway Pavement Marking Guide and made available by Alberta Transportation, please see the following

More information

Temporary Vehicle Restraint System Policy

Temporary Vehicle Restraint System Policy Temporary Vehicle Restraint System Policy Prepared By; J Wilkinson H&S Manager, Civils Prepared for: Installation of TVRS on all triio highways projects including JV s. Page 1 of 8 Contents 1.0 Introduction

More information

H3 Roadside Design Process

H3 Roadside Design Process H3 Roadside Design Process FIGURE H3.1 Roadside Design Process H3.1 Introduction This section summarizes the design process used to determine the most appropriate and costeffective design strategies for

More information

72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME. Public Information Meeting

72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME. Public Information Meeting 72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME Public Information Meeting Project Goals About the Project The goal of this project is to address congestion along 72 Avenue and adjacent streets

More information

Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017

Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 WELCOME Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 Purpose of the Open House The purpose of this Open House is to gain public input on the bicycle lanes proposed

More information

GDOT Cross Section Elements. Course ID: GDOT PDH Credits

GDOT Cross Section Elements. Course ID: GDOT PDH Credits GDOT Cross Section Elements Course ID: GDOT-01 2 PDH Credits Civil Engineer Educators LLC 1026 Timberwolf Lane Juneau, AK 99801 Email: support@civilpdh.com Chapter 6 Contents 6. CROSS SECTION ELEMENTS

More information

Driveway Design Criteria

Driveway Design Criteria Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved

More information

CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS

CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS 2011 Edition - Revision 2 Page 275 Section 2G.01 Scope CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS 01 Preferential lanes are lanes designated for special traffic uses such as high-occupancy vehicles

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS SECTION 01550 TRAFFIC REGULATIONS PART 1 - GENERAL 1.01 OBJECTIVES A. The Contractor shall provide for safe movement of vehicular, bicycle and pedestrian traffic, including persons with disabilities in

More information

Township of Springwater

Township of Springwater Township of Springwater Approved: November 2008 Effective: Date of Passing Next Review: TBD Department: Public Works Subject: Sidewalks Policy Number: A09 SI A. Authority This policy shall be approved

More information

H3 Roadside Design Process

H3 Roadside Design Process H3 Roadside Design Process FIGURE H3.1 Roadside Design Process H3.1 Introduction This section summarizes the design process used to determine the most appropriate and costeffective design strategies for

More information

Developed by: The American Traffic Safety Services Association (ATSSA) 15 Riverside Parkway, Suite 100 Fredericksburg, VA

Developed by: The American Traffic Safety Services Association (ATSSA) 15 Riverside Parkway, Suite 100 Fredericksburg, VA Addendum Developed by: The American Traffic Safety Services Association (ATSSA) 15 Riverside Parkway, Suite 100 Fredericksburg, VA 22406-1022 800-272-8772 This material is based upon work supported by

More information

11 CHECKLISTS Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT

11 CHECKLISTS Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT 11 CHECKLISTS 11.1 Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT 1.1 General topics 1. Scope of project; function; traffic mix 2. Type and degree of access to property and developments

More information

City of Prince Albert Statement of POLICY and PROCEDURE. Department: Public Works Policy No. 66. Section: Transportation Issued: July 14, 2014

City of Prince Albert Statement of POLICY and PROCEDURE. Department: Public Works Policy No. 66. Section: Transportation Issued: July 14, 2014 Page: 1 of 8 1 POLICY 1.01 The City shall follow all of the specifications in the Manual of Uniform Traffic Control Devices for Canada, prepared by the National Committee of Uniform Traffic Control, and

More information

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed

More information

Designing Pedestrian Facilities for Accessibility. Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in Work Zones

Designing Pedestrian Facilities for Accessibility. Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in Work Zones Designing Pedestrian Facilities for Accessibility Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in s Maintenance of Accessible Features Title II (28 CFR 35.133(a))

More information

Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering. Minnesota Department of Transportation (the Department)

Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering. Minnesota Department of Transportation (the Department) To: From: Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering Date: March 20, 2001 Subject: Roadway Geometric Design Criteria Project: TH 14/218 Design-Build Project, SP 7408-29,

More information

SECTION 3 STREET DESIGN

SECTION 3 STREET DESIGN 3.01 GENERAL SECTION 3 STREET DESIGN For purposes of geometric and structural design, streets shall be classified according to the following table. The City Engineer will determine the class of all proposed

More information

TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects

TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects January 2012 TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects 1. PURPOSE OF REPORTING The purpose of Tangible Capital Asset (TCA) reporting is to comply with PSAB 3150 reporting

More information

Section 3A.04 Colors. Section 3B.10 Approach Markings for Obstructions

Section 3A.04 Colors. Section 3B.10 Approach Markings for Obstructions Section 3A.04 Colors Markings shall be yellow, white, red, or blue, or purple. The colors for markings shall conform to the standard highway colors. Black in conjunction with one of the above colors shall

More information

DEFINITIONS Activity Area - Advance Warning Area Advance Warning Sign Spacing Advisory Speed Approach Sight Distance Attended Work Space

DEFINITIONS Activity Area - Advance Warning Area Advance Warning Sign Spacing Advisory Speed Approach Sight Distance Attended Work Space DEFINITIONS Activity Area - that part of a TTC zone activity area where the work actually takes place. It consists of the work space, traffic space and one or more buffer spaces. Advance Warning Area -

More information

ASSET ASSET IDENTIFICATION SIGNAGE

ASSET ASSET IDENTIFICATION SIGNAGE PART PART E E: ASSET ASSET IDENTIFICATION SIGNAGE Manual No. SM051 E-1 7 ASSET IDENTIFICATION SIGN DESIGN AND PLACEMENT General The location referencing system does not include asset identification. However,

More information

General Notes. Project No /15/2018 Page 1 of 1

General Notes. Project No /15/2018 Page 1 of 1 5025 Page 1 of 10 General Notes 5/15/2018 Page 1 of 1 Project No. 82 18-18- 82 KA D 5025-01 0307-19 1 2 Note The contractor is responsible for establishing and maintaining centerline of the traveled way

More information

MUTCD Part 6G: Type of Temporary Traffic Control Zone Activities

MUTCD Part 6G: Type of Temporary Traffic Control Zone Activities MUTCD Part 6G: Type of Temporary Traffic Control Zone Activities 6G.01 Typical Applications Each temporary traffic control (TTC) zone is different. Many variables, such as location of work, highway type,

More information

General Notes. Project No /15/2018 Page 1 of 1

General Notes. Project No /15/2018 Page 1 of 1 5081 Page 1 of 13 General Notes 5/15/2018 Page 1 of 1 Project No. 82 183-82 KA D 5081-01 0309-19 1 2 Note The contractor is responsible for establishing and maintaining centerline of the traveled way for

More information

Weymouth - Abington Route 18 Widening and Reconstruction Project File No

Weymouth - Abington Route 18 Widening and Reconstruction Project File No Weymouth - Abington Route 18 Widening and Reconstruction Project File No. 601630 PROJECT LOCATION Project Limit Previously Completed Signalized Intersections (Typical) Route 18 Widening Bridge No. W-32-013

More information

TRAFFIC ACCOMMODATION IN WORK ZONES

TRAFFIC ACCOMMODATION IN WORK ZONES TRAFFIC ACCOMMODATION IN WORK ZONES 2017 Date of Issue: January 2017 This document has been published under the authority of the General Manager of Infrastructure Services 1 P age Table of Contents SECTION

More information

STATEMENT of POLICY and PROCEDURE

STATEMENT of POLICY and PROCEDURE SCHEDULE B to BY-LAW NO. 96-2013 STATEMENT of POLICY and PROCEDURE No. Responsibility: Roads Date: October 21, 2013 Policy: Road Design Standards Revised: Approved by: By-law No. 96-2013 Pages: 6 Purpose:

More information

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999 Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999,1'(; A ACCELERATION Data on acceleration from stop D-29 Effects of grade D-35 Intersections D-97, D-99 Lanes D-97, F-5, F-7, F-15, F-21,

More information

Topic No January 2000 Manual on Uniform Traffic Studies Revised July Chapter 8 GAP STUDY

Topic No January 2000 Manual on Uniform Traffic Studies Revised July Chapter 8 GAP STUDY Chapter 8 8.1 PURPOSE GAP STUDY (1) The Gap Study is used to determine the size and the number of gaps in the vehicular traffic stream for unsignalized intersections and access points, pedestrian studies,

More information

CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS

CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS 'HYHORSPHQW (QJLQHHULQJ 5LFKDUGV %OYG UG )ORRU 6DFUDPHQWR &$ Phone: 916-808-8300 Fax: 916-808-1984 (QJLQHHULQJ 6HUYLFHV 'LYLVLRQ CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS

More information

Off-Road Facilities Part 1: Shared Use Path Design

Off-Road Facilities Part 1: Shared Use Path Design Off-Road Facilities Part 1: Shared Use Path Design Presentation by: Eric Mongelli, P.E. Tom Huber October 9, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar @tooledesign

More information

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge

More information

COMPLETE STREETS DURING CONSTRUCTION

COMPLETE STREETS DURING CONSTRUCTION COMPLETE STREETS DURING CONSTRUCTION MAINTAINING ACCESSIBILITY FOR ALL Presented by Robbie Burgess, P.E., PTOE Associate Principal Construction Services Manager Howard Stein Hudson rburgess@hshassoc.com

More information

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS Section Page 48-1 GENERAL...48.1 48-2 THERMOPLASTIC TRAFFIC STRIPES AND PAVEMENT MARKINGS...48.1 48-3 PAINTED TRAFFIC STRIPES AND PAVEMENT

More information

SECTION 12 ROAD MARKINGS AND DELINEATION

SECTION 12 ROAD MARKINGS AND DELINEATION SECTION 12 ROAD MARKINGS AND DELINEATION (Blank Page) MANUAL OF TRAFFIC SIGNS AND MARKINGS - Part III: Motorways and Expressways 12-1 12.1 GENERAL 12.1.1 INTRODUCTION The markings and delineation details

More information

Clear Zone Conflicts in AASHTO Publications

Clear Zone Conflicts in AASHTO Publications Clear Zone Conflicts in AASHTO Publications Dick Albin Washington State Department of Transportation Presented at the AASHTO Sub Committee on Design Meeting June 2007 Burlington, Vermont Clear Zone is

More information

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS SECTION 13 BIKEWAYS 13-1 GENERAL The City of Roseville bikeway standards are designed to insure that transportation and recreational bikeways are constructed in a manner that would provide a safe and comfortable

More information

Presented By: Jim Roth, P.E. Signing Engineer Office of Traffic Engineering Ohio Department of Transportation 1980 West Broad Street Columbus, Ohio

Presented By: Jim Roth, P.E. Signing Engineer Office of Traffic Engineering Ohio Department of Transportation 1980 West Broad Street Columbus, Ohio 1 Presented By: Jim Roth, P.E. Signing Engineer Office of Traffic Engineering Ohio Department of Transportation 1980 West Broad Street Columbus, Ohio 43223 (614) 752-0438 Fax: (614) 644-8199 jim.roth@dot.state.oh.us

More information

MUTCD Part 6: Temporary Traffic Control

MUTCD Part 6: Temporary Traffic Control MUTCD Part 6: Temporary Traffic Control OMUTCD English units are preferred. OHIO MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES TABLE OF CONTENTS PREFACE INTRODUCTION TABLE OF CONTENTS PART 1. GENERAL Chapter

More information

PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT

PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT 405 LIMB MANAGEMENT ACTIVITY DESCRIPTION Cut and/or remove and/or grind tree limbs from the right-of-way. TRAFFIC CONTROL Utilize intermittent mobile operations

More information

REVOCABLE PERMIT FOR STREET BANNER APPLICATION PACKAGE

REVOCABLE PERMIT FOR STREET BANNER APPLICATION PACKAGE Development Engineering 300 Richards Blvd., 3rd Floor Sacramento, CA 95811 Engineering Services Division REVOCABLE PERMIT FOR STREET BANNER APPLICATION PACKAGE Phone: 916-808-8300 Fax: 916-808-1984 Preparation

More information

FOR HISTORICAL REFERENCE ONLY

FOR HISTORICAL REFERENCE ONLY To: From: Subject: Electronic Distribution Recipients MINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No. 12-14-B-03 December 18, 2012 Jon M. Chiglo, P.E. Division

More information

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program 40 Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program OVERVIEW The City of Ottawa Pedestrian Crossover (PXO) Program provides the basis for PXO implementation in Ottawa. The program s processes

More information

REPORT. Engineering and Construction Department

REPORT. Engineering and Construction Department REPORT COMMUNITY SERVICES COMMITTEE MEETING DATE: JUNE 11, 2013 FROM: Engineering and Construction Department DATE: May 24, 2013 SUBJECT: Great Lakes Boulevard Mini Roundabout LOCATION: Great Lakes Boulevard

More information

SECTION 1A NEW JERSEY TURNPIKE GEOMETRIC DESIGN

SECTION 1A NEW JERSEY TURNPIKE GEOMETRIC DESIGN SECTION 1A NEW JERSEY TURNPIKE GEOMETRIC DESIGN Table of Contents Page No 1A.1 GENERAL...1 1A.1.1 DESIGN CONTROLS...1 1A.2 MAINLINE ROADWAYS...4 1A.2.1 ROADWAY DESIGNATION...4 1A.2.2 DESIGN SPEED...4 1A.2.3

More information

SPEED CONTROL AT ROUNDABOUTS USE OF MAXIMUM ENTRY PATH RADII

SPEED CONTROL AT ROUNDABOUTS USE OF MAXIMUM ENTRY PATH RADII 23 rd ARRB Conference Research Partnering with Practitioners, Adelaide Australia, 2008 SPEED CONTROL AT ROUNDABOUTS USE OF MAXIMUM ENTRY PATH RADII Dr Owen Arndt, Queensland Department of Main Roads, Australia

More information

To position power poles a safe distance from the road to minimise the likelihood of being accidentally hit by vehicles.

To position power poles a safe distance from the road to minimise the likelihood of being accidentally hit by vehicles. Policy Statement Subject Placement of Rigid Distribution Poles Along Roads With Speed Limits Exceeding 70KM/H Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

APPENDIX L. Design Criteria

APPENDIX L. Design Criteria APPENDIX L Design Criteria DRAFT PRELIMINARY DESIGN CRITERIA Page 1 of 18 APPROVALS MANAGER, ENGINEERING CITY OF HAMILTON MANAGER, ENGINEERING REGION OF HALTON DATE This Design Criteria for the New East-West

More information

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES CONTROL OF TRAFFIC C201 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C201 ISSUE: NO:1 October 2007 TABLE OF CONTENTS CLAUSE CONTENTS

More information

SPECIFICATION FOR INSTALLATION OF RAISED PAVEMENT MARKERS. This specification shall apply to the installation of raised pavement markers.

SPECIFICATION FOR INSTALLATION OF RAISED PAVEMENT MARKERS. This specification shall apply to the installation of raised pavement markers. SPECIFICATION FOR INSTALLATION OF RAISED PAVEMENT MARKERS 1 SCOPE This specification shall apply to the installation of raised pavement markers. 2 DEFINITIONS Type A Marker - Retroreflective raised pavement

More information

SECTION 12 ROAD MARKINGS AND DELINEATION

SECTION 12 ROAD MARKINGS AND DELINEATION SECTION 12 20 June 2009 Part 3: Motorways and Expressways CONTENTS Reference Page Page Number Date SECTION 12: MARKINGS AND DELINEATION 12.1 GENERAL... 12-1 June 2009 12.1.1 INTRODUCTION... 12-1 June 2009

More information

(This page left intentionally blank)

(This page left intentionally blank) (This page left intentionally blank) 2011 Edition - Revision 1 Page 553 Section 5A.01 Function CHAPTER 5A. GENERAL 01 A low-volume road shall be defined for this Part of the Manual as follows: A. A low-volume

More information

2004 Traffic and Safety Notes. Cross Reference between the Old Note Number and the New Note Number

2004 Traffic and Safety Notes. Cross Reference between the Old Note Number and the New Note Number Michigan Department of Transportation 2004 Traffic and Safety Notes Cross Reference between the Old Note Number and the New Note Number OLD NEW Number Number Title (Prior to 2004) 1.1.1 101-Series General

More information

The Corporation of the City of Sarnia. School Crossing Guard Warrant Policy

The Corporation of the City of Sarnia. School Crossing Guard Warrant Policy The Corporation of the City of Sarnia School Crossing Guard Warrant Policy Table of Contents Overview And Description... 2 Role of the School Crossing Guard... 2 Definition of a Designated School Crossing...

More information

l Civil Engineering Group of PSRA Techn ical Plan Review Team. '\J \

l Civil Engineering Group of PSRA Techn ical Plan Review Team. '\J \ GOVERNMENT OF THE DISTRICT OF COLUMBIA District Department of Transportation Public Space Regulation Administration PSRA.. *.. d ~ oc == *. * GENERAL TRAFFIC CONTROL PLAN (TCP) SUBMITTAL GUIDELINES 18

More information

On Road Bikeways Part 1: Bicycle Lane Design

On Road Bikeways Part 1: Bicycle Lane Design On Road Bikeways Part 1: Bicycle Lane Design Presentation by: Nick Jackson Bill Schultheiss, P.E. September 04, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar

More information

Safety Barriers (including Erratum No. 1, dated June 2013, and Amendment No. 1, dated February 2014)

Safety Barriers (including Erratum No. 1, dated June 2013, and Amendment No. 1, dated February 2014) Volume 2 Section 2 Part 8A NRA TD 19/13 Safety Barriers (including Erratum No. 1, dated June 2013, and Amendment No. 1, dated February 2014) March 2013 St. Martin s House, Waterloo Road, Dublin 4. Tel:+353

More information

CHAPTER H ROADSIDE DESIGN GUIDE

CHAPTER H ROADSIDE DESIGN GUIDE February 2012 ACKNOWLEDGEMENTS PREFACE PART I PRACTICES, GUIDELINES, AND PROCESSES H1 OVERVIEW... H1 1 H1.1 Introduction... H1 1 H1.2 Historical Perspective... H1 2 H1.3 Testing Procedures for Roadside

More information

MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017

MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017 MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017 RECOMMENDED ACTION: Update on the NDDOT US Business 2 Project Programmed for 2019 Matter of the NDDOT US Business

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

Traffic Safety Plan Second Avenue

Traffic Safety Plan Second Avenue Traffic Safety Plan Second Avenue April 2017 City of Greater Sudbury Roads & Transportation Services Division Overview Overview... 2 1.0 Project Overview... 4 2.0 Pedestrian Safety... 4 2.1 Current Infrastructure...

More information

H8 Signs, Supports and Poles

H8 Signs, Supports and Poles Alberta Infrastructure and Transportation Roadside Design Guide November 2007 H8 Signs, Supports and Poles H8.1 Introduction This section identifies the appropriate roadside safety treatment for signs,

More information

Attachment No. 4 Approved by National Committee Council

Attachment No. 4 Approved by National Committee Council Attachment No. 4 Approved by National Committee Council The Signals Technical Committee distributed a technical committee recommendation to sponsors concerning pedestrian hybrid beacons following the January

More information

Roadway Design Manual

Roadway Design Manual Roadway Design Manual Revised December 2013 2013 by Texas Department of Transportation (512) 302-2453 all rights reserved Manual Notice 2013-1 From: Manual: Mark A. Marek, P.E Roadway Design Manual Effective

More information

10.0 CURB EXTENSIONS GUIDELINE

10.0 CURB EXTENSIONS GUIDELINE 10.0 CURB EXTENSIONS GUIDELINE Road Engineering Design Guidelines Version 1.0 March 2017 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services

More information

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT PROJECT NO. 093 MA 199 H 5807 01C FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENI HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT (INTERSECTION IMPROVEMENT) US 93/US 60 FINAL PROJECT ASSESSMENT April

More information

Access Management Standards

Access Management Standards Access Management Standards Section 1: Application of Access Standards This chapter describes the Department's access management standards for access connections on the county roadway system. The standards

More information

Agenda Item # Page # RECOMMENDATION

Agenda Item # Page # RECOMMENDATION TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 2, 2016 JOHN BRAAM, P. ENG. MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER FIELD MARSHAL WOLSELEY

More information

Printed copies of this document may not be current. Refer to SafetyNet (Domino.Doc) for the official, controlled version.

Printed copies of this document may not be current. Refer to SafetyNet (Domino.Doc) for the official, controlled version. SASKPOWER TRAFFIC CONTROL PLANNING GUIDELINES INTRODUCTION page 3 DEFINITIONS page 3 PLANNING AND PREPARATION page 6 Pedestrian Safety within an Active Work Area page 7 Excavations page 8 Partial Lane

More information

American Railway Engineering and Maintenance of Way Association Letter Ballot. Draft

American Railway Engineering and Maintenance of Way Association Letter Ballot. Draft American Railway Engineering and Maintenance of Way Association Letter Ballot 1. Committee and Subcommittee: Committee 5 Track Subcommittee 9 Road Crossings 2. Letter Ballot Number: 05-17-16 3. Assignment:

More information

Work Zone Safety A Look At Best Practices. AASHTO SCOTE June 6, 2016

Work Zone Safety A Look At Best Practices. AASHTO SCOTE June 6, 2016 Work Zone Safety A Look At Best Practices AASHTO SCOTE June 6, 2016 1 Work Zone Safety Innovations 2 Positive Protection Measures Pedestrian Accommodations Temporary Bicycle Facilities Work Area Lighting

More information

ITEMIZED LIST FOR TRAFFIC CONTROL TOTAL UNITS S

ITEMIZED LIST FOR TRAFFIC CONTROL TOTAL UNITS S STATE OF SOUTH DAKOTA PROJECT SHEET TOTAL SHEETS ( ) 029S-288 10 2 7 MAINTENANCE OF TRAFFIC Removing, relocating, covering, salvaging and resetting of permanent traffic control devices, including delineation,

More information

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS Section Page 48-1 GENERAL... 48.1 48-2 THERMOPLASTIC TRAFFIC STRIPES AND PAVEMENT MARKINGS... 48.1 48-3 PAINTED TRAFFIC STRIPES AND

More information

2017 Temporary traffic control guidelines for pedestrians. v.2

2017 Temporary traffic control guidelines for pedestrians. v.2 2017 Temporary traffic control guidelines for pedestrians v.2 Temporary Traffic Control Guidelines for Pedestrians (2017) The safety and mobility of pedestrians, cyclists and motorists must be considered

More information

Inspector MUST Sign and Date Each Inspection

Inspector MUST Sign and Date Each Inspection Work Area: Applicant: Mercer County Department of Transportation - Highways Division Application and Permit for Road Work in Mercer County, New Jersey NO. East Windsor Ewing Hamilton Hopewell Lawrence

More information

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS SECTION 48 TRAFFIC STRIPES AND PAVEMENT MARKINGS 48-1 GENERAL Traffic stripes and pavement markings shall

More information

CHAPTER 6H. TYPICAL APPLICATIONS

CHAPTER 6H. TYPICAL APPLICATIONS 2006 Edition Page 6H-1 CHAPTER 6H. TYPICAL APPLICATIONS Section 6H.01 Typical Applications Support: Whenever the acronym TTC is used in this Chapter, it refers to temporary traffic control. Standard: The

More information

COUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca

COUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca OCTOBER 2014 Municipal Class Environmental Assessment COUNTY ROAD 22 HORSESHOE VALLEY ROAD Project A Truck Climbing Lanes Project B Intersection Improvements simcoe.ca CORPORATE COMMUNICATIONS DEPARTMENT

More information

City of Conway Mayor s Office 1201 Oak Street Conway, AR Invitation and Bid

City of Conway Mayor s Office 1201 Oak Street Conway, AR Invitation and Bid City of Conway Mayor s Office 1201 Oak Street Conway, AR 72032 www.cityofconway.org Invitation and Bid 2010-25 INVITATION TO THE VENDOR ADDRESSED: Bidders are invited to furnish the items listed herein

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information