SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:
|
|
- Natalie Osborne
- 5 years ago
- Views:
Transcription
1 PCBU: ALL TRADES ABSEILING ABN: PO Box 774 NEWPORT NSW 2106 LIC: C P: Principal Contractor (PC): Date SWMS provided to PC: Work activity: Workplace location: High risk construction work: (Check all that are applicable) Person responsible for ensuring compliance with SWMS: Person responsible for reviewing SWMS control measures: Risk of a person falling more than 2 metres. Temporary load-bearing support for structural alterations or repairs Work in an area with movement of powered mobile plant Work on a telecommunication tower Demolition of load-bearing structure Likely to involve disturbing asbestos Tilt-up or precast concrete elements Work in or near a confined space Work on or near energised electrical installations or services Work on or near chemical, fuel or refrigerant lines Work on, in or adjacent to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians Work in or near a shaft or trench deeper than 1.5 m or a tunnel Work in an area that may have a contaminated or flammable atmosphere Date SWMS received: Date SWMS received by reviewer: Work on or near pressurised gas mains or piping Work in or near water or other liquid that involves a risk of drowning What measures are in place to ensure compliance with the SWMS? How will the SWMS control measures be reviewed? Review date: Reviewer s signature: Page 1
2 NOTE: Assessment based on: IRATA International code of practice for industrial rope access (ICOP 2013); AS/NZS : Industrial rope access systems: Part 1: Specifications; AS 1891: Fall Arrest Systems; AS/NZS : Industrial rope access systems, Part 2: Selection, use and maintenance; WHS legislation and safe work practices. ROPE ACCESS CHECKLIST (Select all applicable) WORKERS EQUIPMENT LIST (Select all applicable) GEAR CHECKLIST OTHER ITEM CHECKLIST Abseiling equipment including: Setup access equipment in accordance with the Australian Standard AS/NZS for workers to access the structure to carry out rope access maintenance works. Barricades/signage to be erected in areas where the safety of any workers and/or the public could be impacted. Full Body harness securely fastened with a single rope descender (i.e. PETZL I D) Back-up descending device (i.e. PETZL Grigri) Knife (in preparation for rescue at all times) Worker(s) to be attached at two independent points of attachment to a secured anchor rated to 120kg SWL. Building management notified of worker(s) abseiling on building externals. Notification made to the public as applicable. Appropriate P.P.E for the given task at hand (i.e. gloves, ear protection, eye protection) Worker(s) to be suspended with Kernmantle rope, an industrial twin core rope with a protective sheath (two parts to fail in case of abrasion). All personnel to be supervised by other Level II abseiler at all times. (Buddy spotting system) Safety helmet worn and secured when abseiling All equipment to be checked on site before each decent, and to be attached to the one working. All tools as well as any other loose items to be attached to a rated safety lanyard to prevent falling objects. 2 way radio and/or mobile phone securely attached Safety fall arrest shock absorbing rope grab device to be attached to the backup safety line in case of gear failure to prevent further shock load in case of a fall. Rope protectors to be laid over any edges that ropes may come into contact with. Both ropes must extend all the way to the ground or to a safe landing area at all times and noted down. Page 2
3 RISK ASSESSMENT Applicable (Tick) Activity / Hazard Associated Risks Pre-controlled Risk Assessment Controls Break the job down into steps that involve any potential hazards Identify the risks associated with each step. Examine each to find Possibilities that could lead to an accident or adverse environmental impact Likelihood* Consequence* Risk Class* What actions are necessary to eliminate or minimize the hazards that could lead to an accident, injury or occupational illness. Post Controls Risk Assessment Risk Class* Remaining Action List any of the reactive control measures that will be implemented in the event of an accident / incident (i.e. Emergency response procedures,). 1. ARRIVAL AT SITE/SITE INDUCTION OVERHEAD OBJECTS / POSSIBLE MOD HIGH P.P.E, BEING HELMET, GLOVES, EYES, EARS AND SKIN PROTECTION IMPLEMENTED SITE EMERGENCY UNLIKELY MOD KNOWLEDGE OF SITE EVACUATION PROCEDURES REVIEW AND DOCUMENT 2. MOVE EQUIPMENT TO WORK AREA OVERHEAD OBJECTS / UNLIKELY MOD AS PER ITEM 1. ENSURE THE EQUIPMENT IS STORED IN A SAFE AND MANAGABLE AREA. ENSURE SAFE MANUAL HANDLING AT ALL TIMES REPORT AND DOCUMENT ANY INJURIES. CEASE WORK IMIATELY IF INJURED. DOCTOR REFERRAL INJURY FROM LIFTING POSSIBLE MOD HIGH 2 PERSONS TO LIFT ANYTHING ABOUVE 20 KG AS PER ATA HOUSE RULES 3. SETTING UP OF WORK AREA AT GROUND LEVEL (BARRICADES AND CLEAR SIGNAGE BE WORK AREA) OVERHEAD OBJECTS / UNLIKELY MOD AS FOR ITEM 1. INSPECT PATHS OF TRAVEL FOR BUMP AND TRIP HAZARDS REPORT AND DOCUMENT ANY INJURIES. CEASE WORK IMIATELY IF INJURED. DOCTOR REFERRAL INJURY FROM LIFTING POSSIBLE MOD HIGH 2 PERSONS TO LIFT ANYTHING ABOUVE 20 KG AS PER ATA HOUSE RULES FALLING OBJECTS UNLIKELY MAJ HIGH AS FOR ITEM 1. EXCLUSION ZONE WITH BARRICADES AND SIGNAGE BE WORK AREA OBTAIN PERMISSIONS FOR PATHWAY BARRICADING SYSTEM 4. SETTING UP FOR RIGGING OF ROPES (USING CERTIFIED ANCHOR POINTS ON THE ROOF OR COUNTER WEIGHTS) OVERHEAD OBJECTS / UNLIKELY MOD AS FOR ITEM 1. INSPECT PATHS OF TRAVEL FOR BUMP AND TRIP HAZARDS REPORT AND DOCUMENT ANY INJURIES. CEASE WORK IMIATELY IF INJURED. DOCTOR REFERRAL INJURY FROM LIFTING POSSIBLE MOD HIGH 2 PERSONS TO LIFT ANYTHING ABOUVE 20 KG AS PER ATA HOUSE RULES FALL POTENTIAL POSSIBLE CAT EXTREME WORKER HARNESSED AND CONNECTED WITHIN 3 METRES OF ANY EDGE. ALL ROPES TO BE RIGGED IN ACCORDANCE WITH AS4488.1&2 AND IN ACCORDANCE WITH WHS ACT 2011 ENSURE ROOF WORKPLACE REMAINS TDY AND FREE FROM TRIP HAZARDS. ENSURE ANCHOR POINTS ARE TESTED EVERY 12 MONTHS. ONGOING TRAINING PROCEDURES THROUGH IRATA QUALIFICATION OR SIMILAR Page 3
4 Applicable (Tick) Activity / Hazard Associated Risks Pre-controlled Risk Assessment Controls Break the job down into steps that involve any potential hazards Identify the risks associated with each step. Examine each to find Possibilities that could lead to an accident or adverse environmental impact Likelihood* Consequence* Risk Class* What actions are necessary to eliminate or minimize the hazards that could lead to an accident, injury or occupational illness. Post Controls Risk Assessment Risk Class* Remaining Action List any of the reactive control measures that will be implemented in the event of an accident / incident (i.e. Emergency response procedures,). 5. ENTER ROPE SYSTEM FALL POTENTIAL UNLIKELY CAT EXTREME WORKERS TO CONNECT TO ROPES IN ACCORDANCE WITH AS4488.1&2 AND SUITABLE FUL BODY HARNESS AND HELETS TO BE WORN. ALL WORK IN ACCORDANCE WITH WHS ACT 2011 COMMUNICATION BETWEEN WORKERS TO ENSURE CLEAR AND SAFE WORK. EACH WORKER TO REVIEW THE OTHERS ROPE SYSTEM BEFORE DESCENSION DROPPING EQUIPMENT POSSIBLE MAJ VERY HIGH ALL TOOLS TO BE CONNECTED TO THE WORKER WITH A DAMAGE TO FACADE POSSIBLE MAJ VERY HIGH EXTREME CARE WHEN ENTERING SYSTEM AND DESCENDING TO ENSURE NO DAMAGE OCCURS TO FAÇADE COMMUNICATION BETWEEN WORKERS TO ENSURE CLEAR AND SAFE WORK 6. DESCENDING FAÇADE BEFORE COMMENCING ANY MAINTENACE WORK (ABSEILING PROCEDURE) SCRAPES, GRAZES OR HAND BURN FROM ROPE FRICTION POSSIBLE MOD HIGH AS FOR ITEM 1 DISTURBANCE OF LOOSE MATERIAL POSSIBLE MAJ VERY HIGH INSPECT FAÇADE TO SEE THE CONDITION OF LOOSE MATERIALS DURING ABSEILING. DESCEND AT A CONTROLLED PACE DURING DESCENSION INSPECT EITHER SIDE OF DROP FOR POTENTIAL HAZARDS DURING THE NEXT DROP 7. COMMENCE WORK : ROPE ACCESS CLEAN WINDOWS WITH MOP AND SQUEEGEE AND WIPE DOWN FRAMES WITH RAGS MINOR SITE RELATED HAZARDS, BEING OPEN GLASS PANELS / SHARP EDGES / FALLS POSSIBLE MOD HIGH AS FOR ITEM 1 DROP TOOLS POSSIBLE MAJ VERY HIGH ALL TOOLS TO BE CONNECTED TO THE WORKER WITH A ONGOING TRAINING PROCEDURES THROUGH IRATA QUALIFICATION OR SIMILAR FALL POTENTIAL UNLIKELY CAT EXTREME ENSURE ROPES ARE NOT GOING TO BE CUT, SNAGGED OR DAMAGED IN ANY WAY, USE ROPE PROTECTERS WHERE NEEDED. ALL PERSONELL MUST BE TRAINED IN ROPE ACCESS RESCUE PROCEDURES. HAVE AN EXIT STRATERGY IN CASE OF EMERGENCY ONGOING TRAINING IN RESCUE PROCEDURES THROUGH IRATA QUALIFICATION AND/OR SIMILAR. DOCUMENT ANY NEAR MISSES Page 4
5 Applicable (Tick) Activity / Hazard Associated Risks Pre-controlled Risk Assessment Controls Break the job down into steps that involve any potential hazards Identify the risks associated with each step. Examine each to find Possibilities that could lead to an accident or adverse environmental impact Likelihood* Consequence* Risk Class* What actions are necessary to eliminate or minimize the hazards that could lead to an accident, injury or occupational illness. Post Controls Risk Assessment Risk Class* Remaining Action List any of the reactive control measures that will be implemented in the event of an accident / incident (i.e. Emergency response procedures,). 8. COMMENCE WORK: ANY ROPE ACCESS MAINTENACE WORK INVOLVING THE USE OF NON- POWERED TOOLS MINOR SITE RELATED HAZARDS, BEING OPEN GLASS PANELS / SHARP EDGES / FALLS CUTS FROM BLADES AND CHIZELS ETC POSSIBLE MOD HIGH AS FOR ITEM 1. WORKERS TRAINED IN THE USE OF SPECIFIC HAND TOOLS DROP TOOLS POSSIBLE MAJ VERY HIGH ALL TOOLS TO BE CONNECTED TO THE WORKER WITH A ONGOING TRAINING PROCEDURES THROUGH IRATA QUALIFICATION OR SIMILAR FALL POTENTIAL UNLIKELY CAT EXTREME ENSURE ROPES ARE NOT GOING TO BE CUT, SNAGGED OR DAMAGED IN ANY WAY, USE ROPE PROTECTERS WHERE NEEDED. ALL PERSONELL MUST BE TRAINED IN ROPE ACCESS RESCUE PROCEDURES. HAVE AN EXIT STRATERGY IN CASE OF EMERGENCY ONGOING TRAINING IN RESCUE PROCEDURES THROUGH IRATA QUALIFICATION AND/OR SIMILAR. DOCUMENT ANY NEAR MISSES 9. COMMENCE WORK: ANY MAINTENACE WORK INVOLVING THE USE OF POWERED TOOLS MINOR SITE RELATED HAZARDS, BEING OPEN GLASS PANELS / SHARP EDGES / FALLS POSSIBLE MOD HIGH AS FOR ITEM 1. WORKERS TRAINED IN THE USE OF SPECIFIC HAND TOOLS DROP TOOLS POSSIBLE MAJ VERY HIGH ALL TOOLS TO BE CONNECTED TO THE WORKER WITH A ONGOING TRAINING PROCEDURES THROUGH IRATA QUALIFICATION OR SIMILAR FALL POTENTIAL UNLIKELY CAT EXTREME ENSURE ROPES ARE NOT GOING TO BE CUT, SNAGGED OR DAMAGED IN ANY WAY, USE ROPE PROTECTERS WHERE NEEDED. ALL PERSONELL MUST BE TRAINED IN ROPE ACCESS RESCUE PROCEDURES. HAVE AN EXIT STRATERGY IN CASE OF EMERGENCY ONGOING TRAINING IN RESCUE PROCEDURES THROUGH IRATA QUALIFICATION AND/OR SIMILAR. DOCUMENT ANY NEAR MISSES ELECTRICUTION POSSIBLE MAJ VERY HIGH ANY POWER TOOLS TESTED AND TAGGED. USE SURGE PROTECTED POWER BOX WHEN CONNECTING ANY ELECTRICAL TOLS ONGOING TESTING AND TAGGING OF POWER TOOLS. REVIEW ALL POWER TOOLS TO ENSURE ALL DEVICES ARE SAFE. Page 5
6 RISK MATRIX As a priority, any Extreme, Very High or High risks identified need to be re-evaluated and addressed after additional control measures have been implemented to reduce any hazards. If the residual risk is still rated as Extreme or Very High then no work is permitted to proceed. PLEASE USE THIS MATRIX AS A GUIDE TO ASSESS THE RISK ASSESSMENT TABLE LIKELIHOOD CONSEQUENCE Almost certain Likely Possible Unlikely Rare Catastrophic (CAT) EXTREME EXTREME EXTREME VERY HIGH HIGH Major (MAJ) EXTREME EXTREME VERY HIGH HIGH IUM Moderate (MOD) VERY HIGH HIGH HIGH IUM Minor (MIN) IUM IUM IUM Insignificant (INS) IUM RISK CLASS LEGEND LIKELIHOOD EXTREME Extreme Risk: No work to proceed Almost Certain 75% - 100% Expected to occur in most circumstances VERY HIGH Very High Risk: No work to proceed Likely 60% - 75% Will probably occur in most circumstances HIGH High Risk: Additional task review required Possible 40% - 60% Might occur at some time in the future IUM Medium Risk: Manage by routine procedures Unlikely 20% - 40% Could occur but doubtful Low Risk: Manage by routine procedures Rare 0% - 20% May occur but only in exceptional circumstances Page 6
7 Catastrophic - The hazard has the potential to: Major - The hazard has the potential to: Moderate - The hazard has the potential to: Minor - The hazard has the potential to: Insignificant - The hazard has the potential to: CONSEQUENCE Permanently disable or kill Cause severe damage to the structure Have significant impact on the surrounding population and environment Temporarily disable or very serious injury Cause major damage to the structure Serious breach of the site boundary and pollution of the local environment Temporarily disable or serious injury Cause moderate damage to the structure Breach the site boundary and minor pollution to the local environment Moderate injury Cause minor damage to the structure Be contained within the site boundary Cause minor injury (first aid) Insignificant impact contained within the site boundary Name of Worker(s) (Check applicable workers) Worker(s) Title Worker Signature(s) Date SWMS received by workers: NOTE: Work must be performed in accordance with this Safe Work Method Statement (SWMS). This SWMS must be kept and be available for inspection until the high risk construction work to which this SWMS relates is completed. If the SWMS is revised, all versions should be kept. If a notifiable incident occurs in relation to the high risk construction work in this SWMS, the SWMS must be kept for at least 2 years from the date of the notifiable incident. Page 7
Temporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationWork Activity (e.g. Road Work): Work Location:.
Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting
More informationSafe work method statements
Information about Safe work method statements How to prepare and use a safe work method statement (SWMS) for high risk construction work (HRCW) and who needs to prepare one. October 2018 Key concepts Hazard
More informationSAFE WORK METHOD STATEMENTS
Recips 11/56 Norcal Road Nunawading Vic. 11 ABN: 48 04 075 70 Contact Person: Dean Spicer Contact Number: 9878 9006 SAFE WORK METHOD STATEMENTS for Format 1 Various Service Clients for Service work and
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationSAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030
SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More informationHow severely could the risk hurt someone?
Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationBSBWHS404A Contribute to WHS hazard identification, risk assessment and risk control Learning Guide
BSBWHS404A Contribute to WHS hazard identification, risk assessment and risk control BSB41412 Certificate IV in Work Health and Safety BSB41412-Learning-Guide-Sample-V2 BSB41412-Learning-Guide-Sample-V2
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More informationWORK METHOD STATEMENT STRUCTURAL STEEL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationWORK METHOD STATEMENT CARPET LAYING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd
More informationSWMS No 009 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 4
Samark North Qld Pty Ltd SWMS Manual SWMS No 009 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C72 Page 2 of Safe Work Method Statement Title: SWMS:009 Confined Space Work
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30
More informationSpecific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).
OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,
More informationSAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required):
More informationWH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations
Workplace Address: Page 1 of PART 1: TASK DETAILS Client: JOB/TASK: Using Water blaster PART 2: RESOURCES Relevant Legislation/Codes Practice: Training Required: Equipment Used: Materials Used: Substances
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationWORK METHOD STATEMENT ELECTRICAL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationWORK METHOD STATEMENT TERMITE PROTECTION
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSAFE WORK METHOD STATEMENT Part 1
SAFE WORK METHOD STATEMENT Part 1 Company Details: Aztech Integrated Systems Pty Ltd ABN: 50 142 740 172 Director : Aaron Caruana +61 418 178 719 7/227A Brisbane Road, Labrador, QLD, 4215. Project Details:
More informationProcedure: Work health and safety hazard management
Procedure: Work health and safety hazard management Purpose This procedure describes how the Australian National University (ANU) manages Work Health Safety hazards for the health, safety, rehabilitation
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationJOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs
Personnel Involved Manager Project Operators Assistant Notes re Operator/Off-Sider Training Allan McConnell In situ testing is a niche business with very few rigs in Australia. There are no specific training
More informationINDUCTION GUIDE. USC Low-risk Contractor
INDUCTION GUIDE USC Low-risk Contractor usc.edu.au Rise, and shine. INDUCTION GUIDE USC Low-risk Contractor Contents 1 Definitions... 1 2 Introduction... 2 3 General responsibilities of Contractors...
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationSWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional
More informationCONTRACTOR SAFETY INDUCTION HANDBOOK
CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationContractor OHS Induction. AOHS-05-GUI September 2016
Contractor OHS Induction AOHS-05-GUI-002 8 September 2016 1 About AQWEST AQWEST is a Government Trading Enterprise responsible for supplying drinking water to Bunbury. Formed in 1906 as the Bunbury Water
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationSH&EWMS No: F-C-QLD-23 Revision Date: July 2018 Revision Due: July Brief Description of Work Activity: Use Petrol Hand Saw / Ring Saw
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG 4034 ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS
More informationSAFE WORK METHOD STATEMENT CARPENTER
HOST EMPLOYER DECLARATION I declare the worker/s named on this work authority have been provided with a site specific safety induction that complies with the requirements of the Workplace Health & Safety
More informationWORK METHOD STATEMENT ALUMINIUM WINDOWS AND DOORS
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationTelco Antennas SWMS Working At Height Above 2m
Telco Antennas SWMS Working At Height Above 2m A SWMS shall be developed for a task where the risk has been assessed as Medium or Higher Division: Date: SWMS No: (e.g. Installation, Engineering Workshop)
More informationSafety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1
Safety Guidelines for Live Entertainment and Events Part 2. Hazard Identification and Risk Management Contents Disclaimer... 1 1. Principles of Risk Management... 2 2. The Risk Management Process... 2
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph 07 3265 6537 ABN: 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-05
More informationSAFE WORK METHOD STATEMENT
ACN: 141 20 591 ABN: 41 149 34 727 P: 07 3843 149 F: 07 3395 2083 A: U15, 8 Metroplex Avenue Murarrie Qld 4172 This SWMS has been prepared and authorised by Eagle Alliance Earthmoving Pty Ltd Date: Last
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT LOADING AND UNLOADING VEHICLES Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationConfined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).
Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This
More informationSAFE WORK METHOD STATEMENT (SWMS)
SAF WORK MTHOD STATMNT (SWMS) Organisation Name: ABN: Address: Project: Activity: SWMS prepared by: Name Signature Date Area: Client: This makes mandatory: Organisation Details Contact Name: Contact Position:
More informationJOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)
Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative
More informationSAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.
SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: ABN: Contact Name, Position and Phone number: Address: Project details Project: Area: Job Address: Job Description: Activity: Installation
More informationTLILIC2001 Licence to Operate a Forklift Truck
Learner Name: Learner ID: Learner Contact Number: Learner Email Address: Date Training Commenced: This Book Contains: Course Information. Review Questions. The following review questions are to be completed
More informationAbseiling Risk Management Plan
Abseiling Risk Management Plan Lutanda Mt Victoria School: Year: Dates: Program: Supervising Staff: Activity Context Abseiling at Lutanda Mt Victoria involves descending a natural rock face at Mt York,
More informationWheeler Cranes 6 McIntyre Rd Tomago NSW 2324
Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324 ABN: 34 088 229 190 This SWMS has been developed and authorised by: Name Albie Wheeler Position Managing Director Date 1/7/12 Signature Phone 0249649991 Mobile
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph 07 3265 6537 ABN: 45 081 359 613 OHS-FRM-100 Rev 6 (07/14) Page 1 SH&EWMS No.: F-C-QLD-01
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationWork Health and Safety Risk Management Procedures
Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard
More informationGuidance on Using Temporary Suspended Access Equipment
Guidance on Using Temporary Suspended Access Equipment SPECIALIST ACCESS ENGINEERING AND MAINTENANCE ASSOCIATION CONTENTS: 1. Responsibilities of the user- appointed person 2. Regulations and Standards
More informationPrevention of Falls and Working at Heights
Workplace Safety Schools Cleaning Prevention of Falls and Working at Heights It is the policy of the Company to avoid working at heights above 2 metres wherever practical. When avoidance is not an option,
More informationCompany Name: Address: ABN: Company Contact: Position: Phone No.: Date SWMS provided to Principal Contractor: Principal Contractor Signature: Date:
Page 1 of 15 ACTIVITY: Heights - Working at SWMS No.: SAFE WORK METHOD STATEMENT (SWMS) - Part 1 Company Name: Address: ABN: Company Contact: Position: Phone No.: Project Details Project: Job Address:
More informationSH&EWMS No.: F-C-QLD-14 Revision Date: July 2018 Revision Due: July 2019
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 11 (07/19) Page 1 SH&EWMS No.:
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationWHS F029 Job Safety Analysis (JSA) and volume less than 10m2
Handling Archaeological Asbestos Fragments Non-friable Title and volume less than 10m2 School/Business Unit Humanities Location (building/lab/ workshop if applicable) JSA Development 9 June 2017 JSA Development
More informationAbseiling Risk Management Plan Lutanda Yarramundi
Abseiling Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context Abseiling at Lutanda Yarramundi is located on the activity tower on the wall facing the
More informationSWMS No 001 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 5
Samark North Qld Pty Ltd SWMS Manual SWMS No 00 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C372 Page 2 of Safe Work Method Statement Title: SWMS:00 USING PORTABLE LADDERS
More informationSafe Working at Heights Theory Assessment
Safe Working at Heights Theory Assessment Version 4.00 Safe Working at Heights Theory Assessment This Theory Assessment will form part of the formal assessment for the following unit/s of competency: RIIWHS204D
More informationSAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units
Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person
More informationBuilding 21 Roof Safety Assessment. Multi Story Building with large metal roof areas Exteral access required for window cleaning UOW01613
Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Campus BUILDING: 21 Early Start Facility DESCRIPTION: RISK ASSESSMENT # ROOF ACCESS: Multi Story Building with large metal roof areas Exteral access
More informationEVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1
EVENT SAFETY RISK ASSESSMENT (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) EVENT SAFETY MANAGEMENT INFORMATION SHEET September 2010 #3 RISK ASSESSMENT IT S A MUST The success of your event is measured in many
More informationSITE SPECIFIC SAFETY PLAN (SSSP)
SITE SPECIFIC SAFETY PLAN (SSSP) This plan shall be completed and reviewed with the Corporate Safety Department before work commences. Completed plans shall be maintained and kept on site with the project
More informationLADDERS FIXED AND PORTABLE
CONTRACTOR WHS HAZARD STANDARD LADDERS FIXED AND PORTABLE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationHealth & Safety Policy & Plan. Rightway Roofing.
Health & Safety Policy & Plan. Rightway Roofing. Valid: 02/2012-02/2013 Contents ( 1 ) Policy Statement. ( 2 ) Hazard Identification. ( 3 ) Hazard Management. ( 4 ) Induction & Training. ( 5 ) Monitoring
More informationSAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING
SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing
More informationAccident/Incident Reporting and Investigation Procedures
Accident/Incident Reporting and Investigation Procedures Policy reference Workplace Health and Safety Policy Procedure reference Workplace Health and Safety Risk Assessment Procedures Procedure It is imperative
More informationProcedure: Confined space safety
Purpose To define the requirements for the control of hazards associated with the use of confined spaces at the Australian National University to ensure compliance with the Work Health and Safety Act 2011
More informationApplication of rope access methods in the construction, inspection, repair and maintenance of wind turbines
Application of rope access methods in the construction, inspection, repair and maintenance of wind turbines Introduction IRATA International s rope access system is a safe method of working at height,
More informationSafe Work Method Statements (SWMS)
Safe Work Method Statements (SWMS) The purpose of a SWMS is to list the steps of a particular task in your workplace, identify the hazards and associated risks in each step and recommend key safety controls
More informationSafe Work Method Statement Tasks
Safe Work Method Statement Tasks SWMS Venue: Date Created: Address: Contact: Adelaide and surrounding suburbs 23 rd August 2017 27 Valetta Rd Kidman Park SA 5025 Daniel Renshaw CONTROLLED DOCUMENT Page
More informationBuilding 43 Roof Safety Assessment
Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Campus BUILDING: Building 43 Building 43 Roof Safety Assessment DESCRIPTION: RISK ASSESSMENT # : ROOF ACCESS: SIGNAGE: COMPLIANCE PLATES: SAFE
More informationRock Climbing Risk Management Plan Lutanda Yarramundi
Rock Climbing Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context The rock climbing wall at Lutanda Yarramundi is located next on the side of the Activity
More informationSAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information
More informationCONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition WHS
More informationHS329 Risk Management Procedure
HS329 Risk Management Procedure Work Health and Safety Act 2011 Policy hierarchy link Work Health and Safety Regulation 2011 Work Health and Safety Policy Code of Practice How to Manage Work Health and
More information7 Hazard assessment 8 Worker participation 9 Hazard elimination and control
This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Businesses in this industry
More informationHazard Management Making your workplace safer
Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,
More informationSH&EWMS No.: F-C-QLD-10 Revision Date: July 2018 Revision Due: July 2019
OHS-FRM-103 Rev11 (07/18) SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG ABN 45 081 359 613 Phone: 07 3889 8827 Mobile: 0411 756 719 Page 1 SH&EWMS No.:
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Use of a Mobile Elevated Work Platform (MEWP) Boom SWMS No. 19 Authorized
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Entanglement Hired From All Master Hire Stores Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More informationWHS CONTRACTOR INFORMATION PACKAGE
WHS CONTRACTOR INFORMATION PACKAGE Introduction This information package provides Informa exhibitors and contractors with important information that will be required to plan and manage work on all stages
More informationSAFE WORK METHOD STATEMENT
ACN: 141 20 591 ABN: 41 149 34 727 P: 07 3843 149 F: 07 3395 2083 A: U15, 8 Metroplex Avenue Murarrie Qld 4172 This SWMS has been prepared and authorised by Eagle Alliance Earthmoving Pty Ltd Date: Last
More informationINDUSTRIAL ROPE ACCESS EXAM PAPER
Student name: Date: INDUSTRIAL ROPE ACCESS EXAM PAPER Read each question carefully then answer in the manner required. Please sign your paper at the end. You must write clearly in permanent ink (do not
More informationAppendix 4C - Sample SWMS Trenching
Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :
More informationFATAL AND SEVERE RISK PROGRAM
FATAL AND SEVERE RISK PROGRAM LEADER SESSION FALL FROM HEIGHTS Only do the task if it can be done safely FALL FROM HEIGHTS OUR COMMITMENT LIFE SAVING BEHAVIOUR: I WILL ALWAYS USE ADEQUATE PROTECTION WHERE
More informationHazard & Risk Management
Hazard & Risk Management Introduction The Church recognises WHS hazards and risks must be appropriate managed to ensure, so far as reasonably practicable, the health and safety of all workers at Church
More information??????? is committed to providing a safe work environment for its employees and preventing occupational injuries due to falls.
Intent??????? is committed to providing a safe work environment for its employees and preventing occupational injuries due to falls. Fall Protection is an integral part of our commitment to a safe work
More informationApplication 15.1 This Part applies to every workplace where a worker works in a confined space.
PART 15 CONFINED SPACES GENERAL REQUIREMENTS Application 15.1 This Part applies to every workplace where a worker works in a confined space. Safe work procedures 15.2(1) An employer must (a) develop and
More informationAccident /Incident/Injury Report & Investigation Form
Accident /Incident/Injury Report & Investigation Form Incident Details: Location/s of Incident: Address of Incident: Person Involved Details: Person Involved: Witness Name (If Applicable): Time of Incident
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationSOP. Working in Confined Spaces
Purpose This procedure outlines the requirements for the management of entry into confined spaces in all work areas with the intention of minimising risks to health and safety from any potential hazards
More informationConfined Space Management
Confined Space Management Latest revised date: October 26, 2011 Page 1 of 8 1.0 Preamble Memorial has implemented workplace procedures to prevent unauthorized and unsafe confined space entry to guide the
More informationHigh Ropes Management Plan
High Ropes Management Plan Lutanda Mt Victoria School: Year: Dates: Program: Supervising Staff: Activity Context High Ropes is fun way to challenge participants in their confidence, teamwork, decision
More informationNZQA Expiring unit standard version 7 Page 1 of 8. Demonstrate knowledge of safe working practices in telecommunications.
Page 1 of 8 Title Demonstrate knowledge of safe working practices in telecommunications Level 2 Credits 4 Purpose This unit standard covers basic instruction in safe working practices in the telecommunications
More information