SP3 Design and implementation of solutions at test sites WP3.5 Bremen tram track replacement techniques operator: BSAG
|
|
- Ross Matthew Atkinson
- 6 years ago
- Views:
Transcription
1 SP3 Design and implementation of solutions at test sites WP3.5 Bremen tram track replacement techniques operator: BSAG presented by Ingo Schnieders, BSAG and Nils Jänig, TTK at the Urban Track Final Conference June 24, 2010 in Prague
2 Objectives Challenges: Bremen track replacement works, state of the art: track replacement during action weekend (app. since 2000) total closure for individual traffic during construction phase full closure during action weekend performance of app. 200 m per action weekend Challenge for Urban Track replacement of a 375 m double track section plus 25 m adaption to link to the existing track section (with smaller track centre distance) 4 weeks closure for individual traffic, but open for tramway operation 57 h full closure action weekend Final Conference, June 25, Prague 2
3 Description Overall situation Final Conference, June 25, Prague 3
4 Description Overall situation Final Conference, June 25, Prague 4
5 Description Local situation i Access to site Final Conference, June 25, Prague 5
6 Description Initial situation: mixed operation with maximum speed of 50 km/h worn out rails and defective substructure high maintenance effort for paved surfaces noisy surface with car traffic narrow track centre distance (2,75m) Final Conference, June 25, Prague 6
7 Description Beginning and end of replacement section including crossroads Bei den drei Pfählen / Stader Straße End and connection to existing track Beginning incl. crossroads Final Conference, June 25, Prague 7
8 Planning Layout plans beginning end Final Conference, June 25, Prague 8
9 Planning Cross sections Final Conference, June 25, Prague 9
10 Planning Composition of Superstructure 3,5 cm mastic asphalt as top layer 0/11 S, PmB 45A separating layer (e.g. fibre glass) 3,5 cm mastic asphalt as sub-layer 0/11 S, PmB 45A 3 cm Underpour e.g. Icosit KC 340/65 Fillings (e.g. SEDRAPUR SPEZIAL) 14,5 cm base layer made out of concrete C30/37 with high resistance to frost and de-icing salt 20 cm concrete base plate C30/37, rapidly setting concrete with gritting material and high resistance to frost and de-icing salt, not reinforced 25 cm mineral layer B2 Final Conference, June 25, Prague 10
11 Planning Reference to STUVA testing Final Conference, June 25, Prague 11
12 Test facilities (circuit-machine) green track: V = 30 km/hr Axle Load 7t 18,000 crossings Embedded tracks V =50 km/hr Axle load = 10t 1 Mio crossings Axle Extra weight Revolving turret, drive Rubber wheels 16 Test bodies 35 cm Video Final Conference, June 25, Prague 12
13 Planning Reference to STUVA testing rail underpour: Icosit 340/65 fill in material: Edilon Sedra, prefabricated, glued to the rail mastix asphalt as top layer on concrete base plate rail 59 Ri 2 STUVA recommends: The tested construction is suitable for streets with a low percentage of heavy load traffic Final Conference, June 25, Prague 13
14 Planning Time schedule construction sequence working hours 6:00 22:00 working hours action weekend 0:00 24:00 working hours 6:00 22:00 week 1 week 2 week 3 week 4 time assembly of parts, Preparatory work 57h action weekend subsequent work, evacuation of building site facilities Tramway operation of the concerned 2 lines stopped only for the 57 h on the action weekend Final Conference, June 25, Prague 14
15 Preparation before construction Coordination with local authorities and residents Public relations utilities detour of individual traffic detour of public transport road marking accessibility of residents emergency accessibility coordination of working times night shifts coordination with local events e.g. football matches Final Conference, June 25, Prague 15
16 Planning Preparation Phase shift operations between 6:00 a.m. and 10 p.m. Preparation of construction site Delivery of all material necessary for action weekend Cutting and removal of paving and asphalt Removal of old ballast Mounting of track sections Glueing of fillings Determination of ductwork and piping positions Final Conference, June 25, Prague 16
17 Construction sequence I Preparation Phase Final Conference, June 25, Prague 17
18 Construction sequence I Preparation Phase Final Conference, June 25, Prague 18
19 Construction sequence I Preparation Phase Final Conference, June 25, Prague 19
20 Construction sequence I Preparation Phase Corrosion at old tracks due to stray current Final Conference, June 25, Prague 20
21 Construction sequence I sequence plan for 57 h action weekend Final Conference, June 25, Prague 21
22 Action weekend p.m. to a.m. Activities during action weekend 3-shift operations Dismantling of tracks Earthworks Ductworks Pouring of concrete base plate Installation of tracks Connection to existing tracks Underpouring of rails Connection to drainage Pouring of concrete surface in junction Stader Straße Final Conference, June 25, Prague 22
23 Action weekend p.m. to a.m. Friday, 19 September 2008 Last tram passing construction machinery Friday, 19 September 2008 Cutting off of rails Final Conference, June 25, Prague 23
24 Action weekend p.m. to a.m. loading of worn rails Final Conference, June 25, Prague 24
25 Action weekend p.m. to a.m. ductwork for wires Prefabrication of ductwork Final Conference, June 25, Prague 25
26 Action weekend p.m. to a.m. Sat 20 September 2008 Preparation for concrete slab Sat 20 September 2008 delivery of track sections Final Conference, June 25, Prague 26
27 Action weekend p.m. to a.m. Sat 20 September 2008 continuous earthworks along section Final Conference, June 25, Prague 27
28 Action weekend p.m. to a.m. installation of shuttering and adjustment Final Conference, June 25, Prague 28
29 Action weekend p.m. to a.m. Sat 20 September 2008 Pouring of concrete slabs at starting point Sat 20 September 2008 Laying out the track sections Final Conference, June 25, Prague 29
30 Action weekend p.m. to a.m. Sat 20 September 2008 welding St 20 September 2008 drilling holes for fixations Final Conference, June 25, Prague 30
31 Action weekend p.m. to a.m. drainage Final Conference, June 25, Prague 31
32 Action weekend p.m. to a.m. Sat 20 September 2008 fixation Final Conference, June 25, Prague 32
33 Action weekend p.m. to a.m. underpour rails Sun 22 September 2008 Final Conference, June 25, Prague 33
34 Action weekend p.m. to a.m. Facts: mass: length of site: 375 m (+25m adaption) length of rails: 800 m Fillings: 4,300 tie bars: 500 weldings: 110 fixations: concrete slab: 2,400 m² (or 750 m³) underpour: 9,000 l mastic asphalt: 100 to ground: 1,000 m³ pipings: 1,750 m drainage 50 incl. pipes staff workers on site: Final Conference, June 25, Prague 34
35 Action weekend p.m. to a.m. Re-start of public transport services: Monday 4 a.m. Final Conference, June 25, Prague 35
36 Construction sequence II Activities from week 2 to 4 2-shift operations between 6 a.m. and 10 p.m. Connection welding to existing track Run cables Pouring concrete base layer Building in 2-layer mastix asphalt Pouring joints Cutting asphalt alongside Road marking Clearing construction site Final Conference, June 25, Prague 36
37 Construction sequence II Finished Final Conference, June 25, Prague 37
38 Summary and lessons learned Replacement of 400 m double track within a 57 h action weekend is possible! The length of the track to be converted was close to what is possible and sensible from a staff and technical feasibility point of view. In future Bremen will choose rather shorter conversion lengths ( m) to be on the safe side. Final Conference, June 25, Prague 38
39 Summary and lessons learned To achieve objectives all logistic activities have to be planned precisely and optimised accurately all the coordination work with local authorities and residents has to be done in advance weather conditions have to be favourable the contractor has to be reputable, skilled workers and technicians are essential the construction firm must be well equipped unforeseen circumstances have to be kept in mind a permanent physical presence of the employer at any time is essential Final Conference, June 25, Prague 39
40 Thank you for your attention! Final Conference, June 25, Prague 40
Application of Value Engineering The Crosstown Project
Application of Value Engineering The Crosstown Project Presented To: CSVA Conference, Toronto November 15, 2011 Presented by: Rick Thompson, Chief Project Manager SRT/Yards Agenda 1. Eglinton Scarborough
More informationFlowtite GRP manholes Installation Manual
Flowtite GRP manholes Installation Manual Technical Documentation 09-18 EN V2 0 Contents 1 Introduction 03 1.1 Foreword 03 1.2 Safety 03 1.3 Material 03 2 Shipping, Handling and Storage 04 2.1 Inspection
More informationCHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems
CHAPTER 8 STAKING STAKING Correct staking of traffic control signal or lighting systems is critical to the appropriate placement of system components. 8.1 Traffic Control Signal Systems Locating the components
More informationFoundation Products. Poured In Ground Anchor Bolts E1 - E4. Structural Foundations E5 - E12. Copyright 2016 s Industry Inc. SIE-RA-CMP EN
Foundation Products Poured In Ground Anchor Bolts E1 - E4 Structural Foundations E5 - E12 EA EB Poured in Ground Anchor Bolts Layout SIEMENS Anchor Bolts 131702-4X shown for reference purposes only! Actual
More informationSTAKING TRAFFIC CONTROL SIGNAL SYSTEMS
Locating the components of a traffic control signal is not an exact science; many factors influence the location of the components. These factors include: lane widths, radii, pedestrian curb ramp requirements,
More informationIL Route 71 Construction Update
100 Parkers Mill Oswego, IL. 60543 (630) 554-3618 4.20.16 IL 71 TRAFFIC ADVISORY: Tentatively scheduled for April 21st A new traffic pattern from Paradise to Wolf Crossing on IL 71 will be in use. The
More informationHospital Link Project Project Update September 2017
Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationRoadNews 14 // September VÖGELE pavers rehabilitate race track in Brno, Czech Republic. Paving at Top Speed
VÖGELE pavers rehabilitate race track in Brno, Czech Republic. Paving at Top Speed VÖGELE pavers rehabilitate race track in Brno, Czech Republic. Paving at Top Speed Seite 1/11 Job Site Details 1/2 Rehabilitation
More informationINGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI
INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:
More informationMade in U.S.A. Narrow-U Bike Rack Heavy Duty Submittal Sheet. Materials: Finishes: Mount Options: Setbacks:
Submittal Sheet Materials: 2 Schedule 40 Steel Pipe (2.375 OD) Finishes: Galvanized An after fabrication hot dipped galvanized finish is available Powder Coat Our powder coat finish assures a high level
More informationMILEGROUND - AIRPORT ROAD. Fall 2018/ Spring Fall 2020 TBD. US 119 Monongalia County HOW WILL TRAFFIC CONTROL BE HANDLED: KNOW BEFORE YOU GO
MILEGROUD - AIRPORT ROAD US 119 Monongalia County The Mileground - Airport Road project on US 119 involves upgrading the three-lane facility to a five-lane facility to help eliminate congestion and improve
More informationbetter measurement Simply a question of SCHMIDT Flow Sensor SS The cost-effective alternative in pressurised systems up to 10 bars.
Simply a question of better measurement SCHMIDT Flow Sensor SS 20.261 The cost-effective alternative in pressurised systems up to 10 bars. Compressed air technology Industrial processes A cost analysis
More informationBids MAY 24, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $7,500,000.00)
General Info Number: PROJECT NO. 43-18-02 Description: BRIDGE DECK REPAIR AND REHABILITATION PERRYSBURG-HOLLAND ROAD OVER THE OHIO TURNPIKE, M.P. 59.0 HESSVILLE ROAD OVER THE OHIO TURNPIKE, M.P. 84.4 LUCAS
More informationTips on Permanent Powered Fencing and Temporary Powered Fencing
Tips on Permanent Powered Fencing and Temporary Powered Fencing The following outlines various simple, yet proven, methods in constructing both fixed and portable fencing systems as well as providing information
More informationWeymouth - Abington Route 18 Widening and Reconstruction Project File No
Weymouth - Abington Route 18 Widening and Reconstruction Project File No. 601630 PROJECT LOCATION Project Limit Previously Completed Signalized Intersections (Typical) Route 18 Widening Bridge No. W-32-013
More information20', 15', AND 12' BALL STOPS ASSEMBLY INSTRUCTIONS
20'-0" 15'-0" 1 739020 739020A 20' BALL STOP; STRAIGHT POLE 739015 739015A 15' BALL STOP; STRAIGHT POLE 739012 739012A 12' BALL STOP; STRAIGHT POLE Read all of the instructions before beginning. Make sure
More informationLockout / Tag out Program
Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control
More informationTaylor Road Resurfacing Project
Project General Information: Contractor: Perk Company, Inc. Awarded: July 28, 2011 Signed Contract: August 25, 2011 Project Bid Price: $3,600,000 Project Length: 1.5 miles 2 General Information: Project
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP December 29, 2014 Volume 2, Issue 102 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More information1. SCOPE 2. REFERENCED DOCUMENTS. 2.1 SC Test Methods SC-T Forms SCDOT Electronic Forms SUMMARY OF TEST METHOD
Standard Method of Test for Field Determination of Target Density for Plant Produced Asphalt Mix by Use of the Control Strip Technique SCDOT Designation: SC-T-65 (08/18) 1. SCOPE 1.1 This test method is
More informationSöll GlideLoc vertical rail system
Created in cooperation with Europoles GmbH & Co. KG Söll GlideLoc vertical rail system Continuous fall protection system for fixed ladders Engineered for smooth operation for ascending/ descending Durable
More information4. Guided Bus Explained
4. Guided Bus Explained Contents 1 INTRODUCTION... 2 Structure of this report... 2 2 KERB GUIDED BUS... 3 Overview... 3 Kerb guidance... 3 Figures Figure 2.1 Figure 2.2 Figure 2.3 Figure 2.4 Figure 2.5
More informationCincinnati Dayton Rd Widening
Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge
More informationKalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission
FOR IMMEDIATE RELEASE Date: October 31, 2014 Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission Kalamazoo, MI- In a collaborative effort
More informationNZQA registered unit standard 1178 version 7 Page 1 of 6
Page 1 of 6 Title Follow safe practices in an electrical workplace Level 2 Credits 3 Purpose This unit standard covers general safety practices for workers in the electrical and related industries. People
More informationConstructive Ideas. Assessing the risk of sprains and strains CI Introduction. Step 1: Identify hazards. What is musculoskeletal injury (MSI)?
Constructive Ideas Innovative ideas to reduce soft tissue injuries in the construction in dus try! Assessing the risk of sprains and strains Introduction What is musculoskeletal injury (MSI)? Musculoskeletal
More informationMASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018
MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018 AGENDA Introductions Project Benefits Progress to Date Schedule for Remaining Work Phase 3 Activities, Impacts & Traffic Detours Phase 4 Activities
More informationSummary of Findings Concerning Longitudinal Cracking on 16' Wide Ramps
Summary of Findings Concerning Longitudinal Cracking on 16' Wide Ramps Office of Pavement Engineering October 14, 2003 Abstract: This paper summarizes the current practice in ODOT regarding the construction
More informationADA on Construction. Guidance for Section C Plan Preparers
ADA on Construction Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However, good planning can minimize
More informationProvided by. Personal Protective Equipment. Workers Health & Safety Division HS96-101C (07-04)
Provided by Personal Protective Equipment Workers Health & Safety Division 08-02 HS96-101C (07-04) PERSONAL PROTECTIVE EQUIPMENT PROGRAM TABLE OF CONTENTS Development... 3 Hazard Assessment... 3 Choosing
More informationAccommodating Pedestrians in the Work Zone
Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,
More informationSTRAIGHT POLE TENSIONED BATTING TUNNEL POLE LAYOUT
STRAIGHT POLE TENSIONED BATTING TUNNEL POLE LAYOUT SOFTBALL: 55' x 14' Nets BASEBALL: 75' x 14' Nets No. 330155 No. 330175 63'-0" 83'-0" SINGLE NET 1 1 No. 330255 No. 330275 63'-0" 83'-0" DOUBLE NET No.
More informationFloor Mount Socket. T: +44 (0) F: +44 (0)
G-Davit : Floor Mount Socket USER INSTRUCTION MANUAL A davit socket for installation bolted to a high strength flooring material. Suitable for both fall arrest use and lifting. EN795 Class B, PPE Anchor
More informationLEVEL CROSSING SIGHTING DISTANCES
Ref No: HGR-A0458 Issue No: 01 Issue Date: September 2012 HERITAGE RAILWAY ASSOCIATION GUIDANCE NOTE LEVEL CROSSING SIGHTING DISTANCES for Footpath and Vehicular User-Worked Crossings Purpose This document
More informationA P TA J U N E TO M G E R E N D, E X E C U T I V E D I R E C TO R - O V ERVIEW KC S T R E E TC A R A U T H O R I T Y
A P TA J U N E 2 0 1 7 TO M G E R E N D, E X E C U T I V E D I R E C TO R - O V ERVIEW KC S T R E E TC A R A U T H O R I T Y J A S O N WA L D R O N, S T R E E TC A R P R O G R A M M A N A G E R - B LO
More informationBackCountry ebikes 2019 MULE Assembly
BackCountry ebikes 2019 MULE Assembly Required Tools: Cutting Pliers (to cut box poly strapping and heavy bike banding) Scissors (to remove bubble wrap) Allen wrenches (3mm, 4mm, 5mm, 6mm) Wrenches (10mm,
More informationOverspeed governors (113 OG Моment 250 MR, 114 OG Moment 250 A3, 115 OG Moment 250 MRL, 119 OG Moment 250 MRL/1)
Overspeed governors (113 OG Моment 250 MR, 114 OG Moment 250 A3, 115 OG Moment 250 MRL, 119 OG Moment 250 MRL/1) Instructions for installation and operation 113 OG Моment 250 MR 115 OG Moment 250 MRL Overspeed
More informationMetal Expansion Joints. System solutions for reliable connections in plant engineering and construction.
Metal. System solutions for reliable connections in plant engineering and construction. GASKETS TECHNICAL TEXTILES EXPANSION JOINTS INSULATION NEW MATERIALS Standard- and tailor-made : economic solutions
More informationConstitution Instructions
Constitution Instructions This kit will build a 1:48 scale hull for the USS Constitution frigate. The kit contains the following parts. 1/8 deck with laser etched deck lines 1/8 railing Ribs Center keel
More informationWORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES
WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES April 1, 2017 WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES Table of Contents
More informationBARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S
ACCEPTABLE (TCB) TYPES AND ANCHORING DETAILS BASED ON UNDERLYING SURFACE TYPE AND BARRIER OFFSET FROM DROP-OFF BARRIER OFFSET UNDERLYING SURFACE 0" A 6" 6" A 12" 12" A 26" A 26" TCB TYPE DETAIL TCB TYPE
More informationDiaSafe. Systems. Ballasted Fall Protection. DiaSafe Ballasted Single Solo DiaSafe Ballasted Single Duo DiaSafe Ballasted Line Multi. w w w.diadem.
DiaSafe Ballasted Fall Protection Systems DiaSafe Ballasted Single Solo DiaSafe Ballasted Single Duo DiaSafe Ballasted Line Multi DIASAFE INTRODUCTION DiaSafe Ballasted Fall protection Systems Product
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP January 19, 2015 Volume 2, Issue 105 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More informationSUPPLEMENT TO AIRCRAFT FLIGHT MANUAL FOR MOTOR-DRIVEN ROPE WINCH TYPE RPM 11/01
SUPPLEMENT TO AIRCRAFT FLIGHT MANUAL FOR MOTOR-DRIVEN ROPE WINCH TYPE RPM 11/01 (Langenthaler-Winch) Aircraft-Manufacturer: Avions Robin SA Type of Aircraft: Robin DR 300-180R DR400-180R DR 400-200R DR
More informationHospital Link Project Project Update November 2017
Hospital Link Project Project Update November 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationBiboBlock. Fall arrest system for flat roofs
BiboBlock Fall arrest system for flat roofs BiboBlock Fall arrest system for flat roofs Despite the great risk of falling when people work on flat roofs, these spaces have to be accessed regularly for
More informationPerched Box Caisson Overview. January 2014
Perched Box Caisson Overview January 2014 Why perched box caissons? Perched box caissons are used to construct the portion of the river piers that will support the steel arch spans Construction can occur
More informationHAZARD IDENTIFICATION & RISK ASSESSMENT
Clearheart Construction Co., Inc. Hazard Identification & Risk Assessment HAZARD IDENTIFICATION & RISK ASSESSMENT If all employees and subcontractors followed established OSHA compliant procedures to accomplish
More informationAdvantage Lockers & Bike
Advantage Lockers & Bike Advantage Bike Racks & Lockers Inc. is the #1 supplier of Storage Lockers and Bike Racks to the Lower Mainland s residential construction industry. With 25+ years of experience
More informationPUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT
PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. PN #MBPPT Push Pier Systems About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair and new construction
More informationThe Highways Agency is working to improve the M1 between junction 28 (near Alfreton) and junction 35a (the A616 Stocksbridge bypass).
Welcome The Highways Agency is working to improve the M1 between junction 28 (near Alfreton) and junction 35a (the A616 Stocksbridge bypass). The M1 is a vital part of the strategic road network, connecting
More informationFloat operated valve TYPE (SWDS)
Float operated valve TYPE (SWDS) Assembly and Operating Instructions for all models Float operated valve Type SWDS Assembly and Operating Instructions Rev.0 Page 1 of 12 Table of Contents 1 General 3 2
More informationMoai Bike Rack Heavy Duty Submittal Sheet. Materials: 2.0 Schedule 40 Pipe (2.375 OD) Finishes: Capacity: Mount Options: Setbacks: 2 Bikes
Submittal Sheet Materials: 2.0 Schedule 40 Pipe (2.375 OD) Finishes: Galvanized An after fabrication hot dipped galvanized finish is available. Powder Coat Our powder coat finish assures a high level of
More informationASSEMBLY INSTRUCTIONS S-Dome system
ASSEMBLY INSTRUCTIONS S-Dome system USA Table of contents TABLE OF CONTENTS THE COMPANY SAFETY REGULATIONS MATERIALS REQUIRED TOOLS REQUIRED ASSEMBLY TERMS AND CONDITIONS 2 3 4 5 7 9 14 Table of contents
More informationQUALITY ALUMINUM BOAT LIFTS, INC. INSTRUCTIONS. Dominator Lake Lift
INSTRUCTIONS Dominator Lake Lift PHONE:251-986-3882 * FAX:251-986-3136 QABLDOMINATORINST.2014 P a g e 1 Quality Aluminum Boat Lifts, INC. Installation Instructions: Dominator Lake Lift Thank you for your
More informationSecurity and confidence at height.
A Security and confidence at height. Vertical Systems DISTRIBUTED BY M DBI-SALA Vertical Systems are designed to complement your ability to work while meeting all applicable OSHA and ANSI standards. Vertical
More informationInstallation Instructions MODEL VSTI-A020 Tank Indicator Installation Model: VSTI-A020, Stainless Reverse Read System Versa Steel Inc. Guide Cables No
Tank Indicator Installation Model: VSTI-A020, Stainless Reverse Read System Guide Cables No Guide Cables 1 August 4, 2011 Assembly Instructions: (Shown with a 2 board, 12 ft kit) ITEM NO. PART NUMBER DESCRIPTION
More informationOSHA s new walking working surfaces standards
OSHA s new walking working surfaces standards changes and new requirements Inspection of walking working surfaces 1910.22(d) Regularly and as needed and correct, repair, or guard against hazardous conditions;
More informationFINALIZATION OF THE HAND DUG WELL. Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf
ST 1.6 FINALIZATION OF THE HAND DUG WELL Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf Disclaimer This manual is part of the main manual, named
More informationSwim Spa Pre-delivery Guide
Swim Spa Pre-delivery Guide Hello! This document is designed to provide all the information you need to ensure the smooth delivery and installation of your spa or swim spa. Please read it carefully and
More informationBMX Track Guide. Developing the Sport of BMX Racing
BMX Track Guide Developing the Sport of BMX Racing Contents Introduction... 2 Version in Force... 2 How to Use this Guide... 3 Developing the Sport of BMX Racing... 3 Preparing to Build the BMX Track...
More information***PROJECT NO AWARDED TO E.S. WAGNER VIA RESOLUTION NO ON JANUARY 19, 2016***
General Info Number: PROJECT NO. 43-16-03 Description: Deadline: BRIDGE DECK REPLACEMENT AND REHABILITATION, CLIFTON-GUNN ROAD OVER OHIO TURNPIKE M.P. 21.4, RUEGER-SHETLER ROAD OVER OHIO TURNPIKE M.P.
More informationPERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 4
PERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 1 WORK DESCRIPTION 2 WORK DESCRIPTION 3 WORK DESCRIPTION 4 Repair Install Remove Clean 306 DRAINAGE PIPE ACTIVITY DESCRIPTION Install, repair, clean,
More informationSafe Work Method Statement
Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry
More informationThe latest automotive systems require innovative leak test methods and fixturing.
Leak Testing Auto Parts The latest automotive systems require innovative leak test methods and fixturing. In the past, automobile manufacturers only required basic forms of leak testing to check standard
More informationUnit 24: Applications of Pneumatics and Hydraulics
Unit 24: Applications of Pneumatics and Hydraulics Unit code: J/601/1496 QCF level: 4 Credit value: 15 OUTCOME 2 TUTORIAL 9 ACCUMULATORS The material needed for outcome 2 is very extensive so there are
More informationTraffic Control Inspection Checklist Segment:
Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager
More informationGUIDELINE: Roadside Worksites
Title: GUIDELINE: Roadside Worksites Version 1.0 Short description Relevant to Authority Responsible officer Responsible office A guideline on ensuring a safe method of works on or near roadways within
More informationModel PIV UL/FM Post Indicator Valve. Maintenance and Operation Manual UL/FM Post Indicator Valve Configuration AWWA C515
Model 2010 -PIV UL/FM Post Indicator Valve Maintenance and Operation Manual UL/FM Post Indicator Valve Configuration AWWA C515 2 LAYOUT AND SITING At the design stage, it should be considered where valves
More informationH ow To Buil d A Wa ter Rocket
H ow To Buil d A Wa ter Rocket DESIGN AND DEVELOPMENT Brainstorm The first step in the design of a water bottle rocket is brainstorming. Brainstorming is a problem-solving technique that involves the spontaneous
More informationKlassikDrain Section. Technical Handbook and Product Catalog. General purpose trench drainage
Technical Handbook and Product Catalog Surface Drainage 6 Surface drainage options 8 Product selection 10 Trench drain hydraulics 16 Loadings 22 Material data 24 End user requirements Standard Products
More informationMeasuring the Training Rig
TRADE OF Industrial Insulation PHASE 2 Module 6 Insulation & Cladding The Training Rig UNIT: 1 Produced by In cooperation with subject matter expert: Michael Kelly SOLAS 2014 Table of Contents Introduction...
More informationDUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM
DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Introduction 2 Regulatory Requirements 2 Protective Materials
More information^ Lee County ^OU fewest T:foH^ Lee County
^ Lee County ^OU fewest T:foH^ Lee County Department of Transportation 1500 Monroe Street FortMyers,FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE August 18th through August 24th, 2016 Ben
More informationRIIWMG203D Drain and Dewater Civil Construction Site Learner Guide
RIIWMG203D Drain and Dewater Civil Construction Site Table of Contents 1.1 Introduction... 3 1.1.1 Drainage and Dewatering... 3 1.2 Site Policies and Procedures... 5 1.3 Work Instructions... 6 1.3.1 Reading
More informationFLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS. This work covers part of outcome 2 of the Edexcel standard module:
FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS This work covers part of outcome 2 of the Edexcel standard module: UNIT 21746P APPLIED PNEUMATICS AND HYDRAULICS The material needed for outcome
More informationDepth sensor. Product reference : REV 1. USER GUIDE and INSTALLATION GUIDE. nke Sailing competition
Depth sensor Product reference : 90-60-456 REV 1 USER GUIDE and INSTALLATION GUIDE nke Sailing competition Z.I. Kerandré Rue Gutenberg 56700 HENNEBONT- FRANCE http://www.nke.fr After sale service n 33
More informationOSHA's New Silica Rule Everything You Need to Know. Defined. Respirable Crystalline Silica Dust
OSHA's New Silica Rule Everything You Need to Know Chris Hall, CHST 12 West Vermont Street Indianapolis, IN 46204 800.641.5990 www.safetyresources.com Defined Respirable Crystalline Silica Dust Common
More informationBids DECEMBER 21, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $4,700,000.00)
General Info Number: PROJECT NO. 43-19-03 Description: BRIDGE DECK REPAIR AND REHABILITATION OHIO TURNPIKE RAMP OVER STATE ROUTE 420 M.P. 71.4, SOUTH BILLMAN ROAD OVER OHIO TURNPIKE M.P. 75.2, WOOD AND
More informationBasketball system mobile
Basketball system mobile DIN-EN 1270 class C, TÜV-GS-APPROVED Completely made of aluminium Base frame and arm welded in one piece Holding fixture for counterweights in the base frame for stability and
More informationCOMPLETE STREETS DURING CONSTRUCTION
COMPLETE STREETS DURING CONSTRUCTION MAINTAINING ACCESSIBILITY FOR ALL Presented by Robbie Burgess, P.E., PTOE Associate Principal Construction Services Manager Howard Stein Hudson rburgess@hshassoc.com
More informationIllini Union Champaign, IL. February 24, Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering
Illini Union Champaign, IL February 24, 2015 Paul Lorton, P.E. Safety Programs Unit Chief IDOT, Division of Highways, Bureau of Safety Engineering Temporary Concrete Barrier Pinning and Drop-off Policy
More informationTRAFFIC FIELD OPERATIONS (1 of 7) - ADMINISTRATION
TRAFFIC FIELD OPERATIONS (1 of 7) - ADMINISTRATION Field Operations Director 003513 Sr. Community Educator 003542 Asst. Field Operations Director 001046 Stormwater Operations Analyst 003833 Special Projects
More informationSafe distances when using explosives
Guidance note Safe distances when using explosives Information for employers and contractors about safe distances for general explosive blasting operations at sites other than mines and quarries, and setting
More informationRio Intersection Traffic Restrictions Begin Monday
May 18, 2016 8 Rio Intersection Traffic Restrictions Begin Monday This special edition of the Route 29 Solutions e mail newsletter includes everything you need to know about the May 23 through September
More informationskate-park models 2011 EN 14974
skate-park models 2011 EN 14974 2011 HMG sports systems.com e.u., A 9220 Velden, Sonnental 122 Skate park Equipment Skate park 4 25m 16m L W m² GRP concrete total: 25,00 16,00 400 0,00 0,00 Nr. Sp 4 K
More informationAES Raptor, LLC Raptor R1000 Instruction Manual
AES Raptor, LLC Raptor R1000 Instruction Manual Published by AES Raptor, LLC, North Kansas City, MO AES RAPTOR COMPLETE MOBILE FALL PROTECTION SYSTEM is a registered trademark of Architectural Exterior
More informationRISK ASSESSMENT FOR Philips Smart Touch Installation 03/04/2012
RISK ASSESSMENT FOR Philips Smart Touch Installation Myatt Garden Primary School Myatt Garden Primary School Rokeby Road London SE4 1DF Tel: 020 8691 0611 03/04/2012 INTRODUCTION The purpose of this method
More informationFALL PROTECTION PLAN INSTRUCTIONS
Sonic Drilling Ltd. FALL PROTECTION PLAN INSTRUCTIONS Each employer must ensure that a fall protection system is used when work is done at a place from which a fall of 3 m (10 ft) or more may occur, or
More informationUPDATES 11/14/2018: 10/25/2018: CLOSED 10/22/2018: 10/12/2018: 10/05/2018: 09/27/2018:
Veterans Boulevard (formerly Boundary Road) This two-year construction project will widen and pave all of Veterans Boulevard. In 2017, the first portion of the road from Highway 16A to 44 Avenue was completed.
More informationGAS PIPELINE SAFETY GUIDE.
GAS PIPELINE SAFETY GUIDE. Date of issue 27/02/2017 Date of next review 27/02/2018 Page 1 Vector Limited 2017 Gas Pipeline Safety Guide February 2017 CONTENTS CONTENTS...2 WORKING SAFELY... 3 Your Legal
More informationModel Safety Program
Model Safety Program DATE: SUBJECT: Safety Procedures for Servicing Single and Multi Piece Rim Wheels. REGULATORY STANDARD: OSHA 29 CFR 1910.177 RESPONSIBILITY: The company Safety Officer is. He/she is
More informationCASE STUDY OXLEY HIGHWAY SLIP STABILISATION
MAY 2015 CASE STUDY OXLEY HIGHWAY SLIP STABILISATION IRF & ROADS AUSTRALIA REGIONAL CONFERENCE ASIA AND AUSTRALASIA DR SUDAR ARYAL LOCATION STOPPING BAY, OXLEY HIGHWAY 2 Armidale Nambucca Heads Tamworth
More informationQ&A for Safety Code. Prepared by the HAUC-UK Safety Code working group
Q&A for Safety Code Prepared by the HAUC-UK Safety Code working group 1 What is the latest version of the Safety Code? At the time of writing, the last time any amendments were made to the Safety Code
More informationRoad Condition Statistics: Notes and definitions
Road Condition Statistics: Notes and definitions This note provides definitions used for road condition statistics. It also includes useful information on the source of the data 1. Source The statistics
More informationDELUXE LOW PROFILE 18 & 30 STARTING PLATFORMS
DELUXE LOW PROFILE 18 & 30 STARTING PLATFORMS INSTALLATION INSTRUCTIONS CORPORATE HEADQUARTERS WESTERN SALES AND MANUFACTURING PLANT P.O. Box 400 1017 SW Berg Parkway Canby, Oregon 97013 (503) 266-2231
More informationBRUCE HAMMER SUCCESS STORY, BRIDGE PILING Model SGH-4719 Pile Hammer (Max. Energy 89.3 ton.m)
The Bruce SGH-4719 successfully completed the pile driving of Sakonnet River Bridge at RI, USA By Portsmouth Patch (www.patch.com), August 27, 2010 Government RI DOT : Pile Driving Completed at Sakonnet
More informationWarner Instruments, Inc Dixwell Avenue, Hamden, CT (800) / (203) (203) fax
DH-40i, Rev. 04.03.02 Micro-Incubation Platform For RC-40 Chambers Model DH-40i 1125 Dixwell Avenue, Hamden, CT 06514 (800) 599-4203 / (203) 776-0664 (203) 776-1278 - fax DH-40i, Rev. 04.03.02 Table of
More informationI.H.S INSTALLATION INSTRUCTIONS
I.H.S INSTALLATION INSTRUCTIONS TOOLS REQUIRED The following tools will be required for installation of your I.H.S. system. Item Qty Needed 9/16 Open End Wrench 2 3/4 Open End Wrench 1 1/2 Open End Wrench
More informationSpecial instruction of installation for SAINT FH-M800/RD-M800 and FH-M805/RD-M805
Technical Service Instructions SI-5VB0E t RD-M805 / RD-M800 Rear derailleur Special instruction of installation for SAINT FH-M800/RD-M800 and FH-M805/RD-M805 A hub axle is an essential component for the
More information