SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT
|
|
- Clyde Andrews
- 6 years ago
- Views:
Transcription
1 SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT Personal Protective Equipment Foot Hearing High Visibility Head Eye Day Operations Normal Requirements: Safety footwear, hearing protection, high visibility shirt or vest, hard hat and eye/face protection (goggles) Ensure all PPE meets relevant Australian Standards. Inspect, and replace PPE as needed. Provide UV sun protection where required, (broad brimmed hat, UV rated clothing, SPF 30+ sunscreen, tinted safety glasses with adequate UV protection). Safety Notes This SWMS covers the use of an Auger when attached to an excavator. This SWMS must be used in conjunction with Safety Culture s Excavator SWMS. Main hazards: - Loss of attachment - Noise - Excavator roll-over - Ejected materials and flying debris Page 1 of 6
2 NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Task Breakdown Planning - fatality roll over of plant - electric shock - Hit by moving - Hit by ejected - Crushed by falling 4A Ensure equipment suitable for task (know the capabilities/limitations of excavator model, example: SWL and gradient of acceptable slopes). Inspect intended work area. Ensure: - ground surface is suitable - no steep slopes, unprotected drop offs, pits or trenches - work is not conducted in close proximity to underground utilities (dial before you dig) - work is not conducted in close proximity to electrical power lines - sufficient room to operate equipment - remove any debris or equipment (wire, shovels, etc) Ensure excavator, quick-hitch device (if used) and attachment are compatible and within required SWL. Pre-Operational Inspection - Crushing from falling 4A Inspect Auger attachment. Ensure: - Safety decals are attached and legible - Correct level of hydraulic oil for proper operation - Hydraulic oil is not contaminated or discoloured - No leaks - Hoses and fittings are free of damage - All fasteners are in good working order and tightened as required - Teeth are sharp and undamaged - Guards are in place and functional - No damage to unit or cracked welds. - Maintained as per manufacturer s instructions Page 2 of 6
3 Task Breakdown Pre-Operational Inspection continued - Crushing from falling 4A Inspect quick-hitch device (if applicable). Ensure: - Designed for use with attachment - Maintained and in good working order - Safety pins and locks available, in good working order - Marked with the following o Manufacturer s name, make, model and serial number o Quick hitch weight o Maximum rated capacity o Capacity of each lifting point If damage or faults detected, do not use. Follow tag-out/lockout procedures and report to supervisor immediately. Connecting Attachment - Manual Handling - Crushed by falling Attach per manufacturer s instructions. Example: - Ensure attachment is on a flat, level surface - With tool facing excavator, operate the excavator into proper position - Connect hydraulic hoses as required. Tighten bolts/cap to proper torque. - Ensure all locking pins are secured in place. - Check correct flow and pressure (as per manufacturer). - Remove non-essential persons from area - Operator to raise excavator arm slowly and test attachment is secured for use - Check for oil leaks. Operation - Noise - Crushed from falling Ensure no persons are working within 15m (or distance specified by manufacturer) during operation. Place barricades/signs. Work must cease is person enters designated work area. Operation must be single-person. Operator to remain in cabin, sitting on the excavator seat with hands and feet on controls at all times during shear operation. Attachment must only be used as specified by manufacturer. Page 3 of 6
4 Task Breakdown Operation (continued ) - Noise - Crushed from falling Follow manufacturers operation manual and site/task specific SWMS Ensure excavator in Neutral with park brake engaged. Align auger point to intended dig site. As auger penetrates, lower using hydraulic systems; do not let itself screw into the ground. Refer manufacturers instructions for recommended revs/rpm (do not exceed). If auger does not dig: - Disengage hydraulics, lift auger from hole (not more than 12 inches above ground) and inspect teeth for damage, blockage by grass etc. NEVER: - assist machine by hand when in operation - use tools (such as shovels) to help move dirt from around the hole during operation - use persons as counterweights, hang counterweights off assembly or rock auger from side to side - move excavator when auger in operation - walk under raised auger (unless blocked) - operate on steep ground (In hilly terrain, position excavator with post hole digger uphill) - position by hand or tools with excavator running Never leave excavator running. When completed, apply hand brake, lower the boom and turn off engine. No repairs or inspection with excavator running or boom lifted. Secure in position as specified by manufacturer for transport. Page 4 of 6
5 Task Breakdown On completion - Manual handling - Burns (hot fluid). Lower boom down so that auger is laying flat on ground. Follow manufacturer s instructions for detaching. Check whether hose pressure needs to be relived before detaching. Use caution, fluid is and hot. Clean unit and inspect for any damage, leaks or faults. Report as required. Use lifting equipment to transport unit for storage. Maintenance - Manual handling Follow manufacturer s instructions for maintenance schedule. Ensure all maintenance is performed by competent Persons. Keep log book of service and maintenance history. Emergency Procedures - fatality roll over of plant - electric shock - Hit by moving - Crushed by falling Develop and implement an emergency response plan for the site. Include - assembly points - communication - responsible persons - emergency contacts (including nearest medical facility) Page 5 of 6
6 RISK ASSESSMENT Risk Management Code of Practice 2007, AS/NZS Risk Management Principles and guidelines Step 1 Determine Likelihood What is the possibility that the effect will occur? Step 2 Determine Consequence - What will be the expected effect? Criteria Description Level of Effect Example of each level Almost certain Likely Expected in most circumstances. Will probably occur in most circumstances. Effect is a common result Effect is known to have occurred at this site or it has happened Possible Might occur at some time Effect could occur at the site or I ve heard of it happening Unlikely Rare Almost certain Could occur at some time May occur only in exceptional circumstances Effect is not likely to occur at the site or I have not heard of it happening Effect is practically impossible. 3 High 3 High 4 Acute 4 Acute 4 Acute Likely 2 Medium 3 High 3 High 4 Acute 4 Acute Possible 1 Low 2 Medium 3 High 4 Acute 4 Acute Unlikely 1 Low 1 Low 2 Medium 3 High 4 Acute Rare 1 Low 1 Low 2 Medium 3 High 3 High Insignificant/Acceptable Minor Moderate Major Catastrophic No effect or so minor that effect is acceptable First aid treatment only; spillage contained at site. Medical treatment; spillage contained but with outside help. Extensive injuries; loss of production Death; toxic release of chemicals Step 3 Determine the risk score Step 4 Record risk score on worksheet (Note Risk scores have no absolute value and should only be used for comparison and to engender discussion.) CONSEQUENCE Score Action LIKELIHOOD Insignificant Minor Moderate Major Catastrophic 4 ACT NOW Urgent - do something about the risks A: Acute immediately. Requires immediate attention. 3 H: High Highest management decision is required urgently. 2 M: Moderate Follow management instructions. 1 L: Low OK for now. Record and review regularly, and if any equipment/ people/ materials/ work processes or procedures change. Page 6 of 6
SAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.
SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: ABN: Contact Name, Position and Phone number: Address: Project details Project: Area: Job Address: Job Description: Activity: Installation
More informationSAFE WORK METHOD STATEMENT Part 1
SAFE WORK METHOD STATEMENT Part 1 Company Details: Aztech Integrated Systems Pty Ltd ABN: 50 142 740 172 Director : Aaron Caruana +61 418 178 719 7/227A Brisbane Road, Labrador, QLD, 4215. Project Details:
More informationSAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING
SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Entanglement Hired From All Master Hire Stores Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationOperation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015
Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039 Name Date Signature Author Jarred Hearle 27/11/2015 Reviewed FMG Site Team 27/11/2015 ---------- Approved Geoff Selfe 27/11/2015
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationWHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)
WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL
More informationParts & Operators Manual
Parts & Operators Manual (888) 317-5878 www.talet.ca To The Owner General Comments Congratulations on the purchase of your new Talet Mat Grapple. Your unit was carefully designed and manufactured to give
More informationREL-46 WARNING NOTICE 15 TON SINGLE ACTING REMOTE HYDRAULIC CRIMPING HEAD. Compatible with RELIABLE R15 and P Style dies. REL-46 Manual
OPERATORS ORS GUIDE REL-46 15 TON SINGLE ACTING REMOTE HYDRAULIC CRIMPING HEAD Compatible with RELIABLE R15 and P Style dies. RELIABLE EQUIPMENT & SERVICE CO., INC. 301 Ivyland Road Warminster, PA 18974
More informationREL-510H WARNING NOTICE 12 TON SINGLE ACTING REMOTE HYDRAULIC CRIMPING HEAD
OPERATORS ORS GUIDE REL-510H 12 TON SINGLE ACTING REMOTE HYDRAULIC CRIMPING HEAD Compatible with U style and RELIABLE R12 shell type 12 ton compression dies. RELIABLE EQUIPMENT & SERVICE CO., INC. 92 Steamwhistle
More informationHazards Requiring Attention: AS AT Friday, 29 January Next Review Saturday, 28 January Total Hazards Recorded 39. Critical Risk Hazards 0
EF26 Risk Assessment CAT Excavator Hazards Requiring Attention: AS AT Friday, 29 January 2016 0 Next Review Saturday, 28 January 2017 Total Hazards Recorded 39 Critical Risk Hazards 0 High Risk Hazards
More informationWORK METHOD STATEMENT FENCING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationJOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs
Personnel Involved Manager Project Operators Assistant Notes re Operator/Off-Sider Training Allan McConnell In situ testing is a niche business with very few rigs in Australia. There are no specific training
More informationHazards Requiring Attention: AS AT Friday, 1 April Next Review Saturday, 1 April Total Hazards Recorded 43. Critical Risk Hazards 0
EF26 Risk Assessment Kubota U35-4 s Requiring Attention: AS AT Friday, 1 April 2016 0 Next Review Saturday, 1 April 2017 Total s Recorded 43 Critical Risk s 0 High Risk s 0 Moderate Risk s 10 Low Risk
More information1. SAFETY 2. PREPARATION 3. FRAME 4. TRANSMISSION 5. DRIVE 6. ROW UNIT 7. OPTIONAL EQUIPMENT
TABLE OF CONTENTS 1. SAFETY 2. PREPARATION 3. FRAME 4. TRANSMISSION 5. DRIVE 6. ROW UNIT 7. OPTIONAL EQUIPMENT This symbol means: ATTENTION - BECOME ALERT YOUR SAFETY IS INVOLVED. When you see this symbol
More informationSafe Work Method Statements (SWMS)
Safe Work Method Statements (SWMS) The purpose of a SWMS is to list the steps of a particular task in your workplace, identify the hazards and associated risks in each step and recommend key safety controls
More information35 TON HYDRAULIC PUNCH WARNING
OPERATORS GUIDE REL-35T-PNC 35 TON HYDRAULIC PUNCH NOTICE Sizes, weights and tool specifications listed in this manual are subject to change without notice. Please consult factory for information and updates.
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationTN548 TRENCHER OPERATOR S MANUAL
TN548 TRENCHER OPERATOR S MANUAL DEC 2014 T A B L E O F C O N T E N T S S E C T I O N D E S C R I P T I O N P A G E 1 Introduction................... 1 1.1 Overview................... 1 1.2 Intended Use
More informationSAFE WORK METHOD STATEMENT (SWMS)
SAF WORK MTHOD STATMNT (SWMS) Organisation Name: ABN: Address: Project: Activity: SWMS prepared by: Name Signature Date Area: Client: This makes mandatory: Organisation Details Contact Name: Contact Position:
More informationPDY TON HYDRAULIC CRIMPING TOOL WARNING
OPERATORS ORS GUIDE PDY-1220 12 TON HYDRAULIC CRIMPING TOOL All information found in this guide must be read and understood before use or testing of this tool. Failure to read and understand these warnings
More informationPlant Hazard Identification and Risk Assessment
Plant information Plant item: Water Truck Plant identification details (asset/plant no.): Project: Competency required to operate the plant: MR/HR Licence / VOC List all legislation, codes of practice
More informationOPERATOR'S & PARTS MANUAL
MULTI-TASK ATTACHMENT OPERATOR'S & PARTS MANUAL OM638 8963 11-5-04-3 REV. 3 75538 IMPORTANT: Read this manual carefully. It contains information about your safety and the safety of others. Also become
More informationJOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)
Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationSAFE WORK METHOD STATEMENT Part 1
SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: The Doorman ABN: 32 306 274 897 Contact Name, Position and Phone number: Jasmin Soames - Proprietor - 14 Hampden Park Road Kelso NSW 2795
More informationHow severely could the risk hurt someone?
Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationThis section provides general information and recommendations required prior to installing, operating or maintaining your KAT Master Hitch.
WBM Parts and Installation Manual for KAT Master Hitch General Information This section provides general information and recommendations required prior to installing, operating or maintaining your KAT
More informationBRUSH CUTT CXC550 CUTTER
BRUSH CUTT CXC550 CUTTER OPERATOR S MANUAL Issue Date: April 2017 TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Overview... 1 1.2 Intended Use And Foreseeable Misuse... 1 2 SAFETY... 2 2.1 Safety Alert Symbol
More informationTitle: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11
Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:
More informationPLANT RISK ASSESSMENT
PLANT RISK ASSESSMENT Forktruck: Year of Manufacture Make: Model: Serial : TCM FD30T3 Attachment: Name: Mfg: Model : Owner: Business/Organisation: Address: This header page and the following 5 pages have
More informationCompany Name: Address: ABN: Company Contact: Position: Phone No.: Date SWMS provided to Principal Contractor: Principal Contractor Signature: Date:
Page 1 of 15 ACTIVITY: Heights - Working at SWMS No.: SAFE WORK METHOD STATEMENT (SWMS) - Part 1 Company Name: Address: ABN: Company Contact: Position: Phone No.: Project Details Project: Job Address:
More informationWORK METHOD STATEMENT STRUCTURAL STEEL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationWBM Installation Manual KAT Master Hitch
WBM Installation Manual KAT Master Hitch General Information This section provides general information and recommendations required prior to installing, operating or maintaining your KAT Master Hitch.
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationSAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units
Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More information1 2 CONTENTS INTRODUCTION Owner Information 4 Warranty Registration 5 Safety Instructions Safety 6 Safety Decals 7 Safety Identification Labels 8 Safety Notice 10 Safety Standards 11 Risk Assessment 13
More informationRISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager
RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Traineeship Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE: / /
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationWARNING. RELIABLE EQUIPMENT & SERVICE CO., INC. 301 Ivyland Road Warminster, PA USA Phone: Fax:
OPERATOR'S GUIDE Pivot style control valves may be operated with one hand, leaving the second hand free to control the head. Lever locks in the forward position for tool advance, and in the rear position
More informationRISK ASSESSMENT. Bobcat Excavator. Models , (Series D & G) For. Version 1.2
PO Box 50, Hornsby, NSW 2077 Phone: 1800 643 853 Web: www.bobcat.com.au RISK ASSESSMENT For Bobcat Excavator Models 322 341, (Series D & G) CONTENTS Applicability Standards referenced in the preparation
More informationONSITE PLANT ASSESSMENT: PH: MOBILE PLANT RISK ASSESSMENT 2010.
OSITE PLAT ASSESSMET: PH: 0400 536 983 MOBILE PLAT RISK ASSESSMET 2010. This form is to be completed in accordance with the Hazard Management Policy/Procedure and Plant and Equipment Safety Management
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE STAR 10 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or struck
More informationRIIWMG203D Drain and Dewater Civil Construction Site Learner Guide
RIIWMG203D Drain and Dewater Civil Construction Site Table of Contents 1.1 Introduction... 3 1.1.1 Drainage and Dewatering... 3 1.2 Site Policies and Procedures... 5 1.3 Work Instructions... 6 1.3.1 Reading
More informationPlant Hazard Identification and Risk Assessment
Plant information Plant item: Drott Plant identification details (asset/plant no.): Project: Competency required to operate the plant: LS Ticket / VOC List all legislation, codes of practice and Australian
More informationEVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1
EVENT SAFETY RISK ASSESSMENT (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) EVENT SAFETY MANAGEMENT INFORMATION SHEET September 2010 #3 RISK ASSESSMENT IT S A MUST The success of your event is measured in many
More informationAccident/Incident Reporting and Investigation Procedures
Accident/Incident Reporting and Investigation Procedures Policy reference Workplace Health and Safety Policy Procedure reference Workplace Health and Safety Risk Assessment Procedures Procedure It is imperative
More informationBogo Operations Pollution Incident Response Management Plan
Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More informationPPE and Tools PPE and Tools
PPE and Tools PPE and Tools PPE Definition Personal protective equipment (PPE) refers to protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer's body from
More informationProduct Risk Assessment
Product Risk Assessment Flextool (Aust.) Pty Ltd, Brunswick, Vic. Product Description Artizan ub Floor Grinder Model Number ART-UB Risk Assessment Date 19-Jun-08 Product Risk Assessment Number 0010 PRA
More informationTemporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationINSTALLATION INSTRUCTIONS FOR ROLLOVER PROTECTION SYSTEM (ROPS)
INSTALLATION INSTRUCTIONS FOR ROLLOVER PROTECTION SYSTEM (ROPS) This manual contains assembly, operating, maintenance and safety instructions for your ROPS. Before Installing the ROPS or operating a machine
More informationSAFE WORK METHOD STATEMENT CARPENTER
HOST EMPLOYER DECLARATION I declare the worker/s named on this work authority have been provided with a site specific safety induction that complies with the requirements of the Workplace Health & Safety
More informationLEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS
NPTC Registered Charity No. 1096429 NATIONAL AGRICULTURAL CENTRE STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7669 6553 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE
More informationCIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS
Title: Circuit Breaker Testing Purpose and Scope: Provide guidelines for testing of Circuit Breakers. Staffing Resources: Staff will have the minimum requirement of an Electrical Fitter/Mechanic Licence
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationPROCESS HAZARD ANALYSIS FOR THE SEPTIC TANKS AND SYSTEMS REMOVALS AT BUILDING 4005, 4009 AND 4100.
HDMSP00036449 Page 1 PROCESS HAZARD ANALYSIS FOR THE SEPTIC TANKS AND SYSTEMS REMOVALS AT BUILDING 4005, 4009 AND 4100. Introduction As part of the Area IV Remediation Project, the septic tanks and piping
More informationMETHODOLOGY RISK TABLES TABLE 1 - QUALITATIVE MEASURES OF CONSEQUENCE OR IMPACT TABLE 2 - QUALITATIVE MEASURES OF LIKELIHOOD
METHODOLOGY This Assessment has been performed as outlined in Australian Standard AS/NZS ISO 31000:2009 with reference to tables 1, 2 and 3 below, for the use of leased land for the purposes of performing
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE OPTIMUM 8.1 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or
More informationWerk-Brau D-Lock Coupler Installation and Operation Manual
Werk-Brau D-Lock Coupler Installation and Operation Manual SERIAL NUMBER: The D-Lock Coupler (Fully Automatic with Dual Pin Locking) International Patents pending IMPORTANT: The booklet should be kept
More informationSWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationPACKSETTER HAND PUMP
PACKSETTER HAND PUMP 1 CONTENTS Introduction...3 1. Product Description 3 2. Design Criteria.. 3 3. Risk Assessment Team.. 3 4. Objectives... 4 5. Hazard Classification...4+5 Risk matrix..6 FACTOR/INDEX
More informationWORK METHOD STATEMENT CARPET LAYING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationCULTIVATOR SAFETY SECTION
CULTIVATOR SAFETY SECTION The above safety-alert symbol means ATTENTION! Be Alert! Your personal safety is involved This symbol draws your attention to important instructions concerning your personal safety.
More informationJob Safety & Environment Analysis
Job Safety & Environment Analysis To be used when the risk is greater than LOW and / or Defined Hazardous Work and there is no standard procedure for the task. All sections of this JSEA form must be completed.
More informationRISK ASSESSMENT. Bobcat Skid Steer Loader. Series F & G (incl. S Models) For. SSL Version 2
PO Box 50, Hornsby, NSW 2077 Phone: 1800 643 853 Web: www.bobcat.com.au RISK ASSESSMENT For Bobcat Skid Steer Loader Series F & G (incl. S Models) CONTENTS Applicability Standards referenced in the preparation
More informationWORK METHOD STATEMENT TERMITE PROTECTION
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSafety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1
Safety Guidelines for Live Entertainment and Events Part 2. Hazard Identification and Risk Management Contents Disclaimer... 1 1. Principles of Risk Management... 2 2. The Risk Management Process... 2
More informationSpecific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).
OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,
More informationPLANT RISK ASSESSMENT REPORT
PLANT RISK ASSESSMENT REPORT SECTION 1: PLANT IDENTIFICATION Report Number: 407/201-03 Assessment Date: 5 th June 2012 Company: Wacker Neuson Plant Type: Twin Drum Rollers Assessment Purpose: Operational
More informationTASK DAY RISK ASSESSMENT FORM
TASK DAY RISK ASSESSMENT FORM Assessment date Location and Activity details: Site Address Step One - Identify the activity and hazards Consider the activity or work area and identify if any of the hazards
More informationPLANT RISK ASSESSMENT REPORT
PLANT RISK ASSESSMENT REPORT SECTION 1: PLANT IDENTIFICATION Report Number: 407/201-03 Assessment Date: 5 th June 2012 Company: Wacker Neuson Plant Type: Twin Drum Rollers Assessment Purpose: Operational
More informationUniversity of Vermont Department of Physical Plant Personal Protective Equipment Program
University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE
More informationSAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required):
More informationOperating Instructions for BAIR22-6 AIR-POWERED CRIMPING TOOL
Operating Instructions for BAIR22-6 AIR-POWERED CRIMPING TOOL Read and understand all of the instructions and safety information in this manual before operating or servicing this tool. Table of Contents
More informationContractor OHS Induction. AOHS-05-GUI September 2016
Contractor OHS Induction AOHS-05-GUI-002 8 September 2016 1 About AQWEST AQWEST is a Government Trading Enterprise responsible for supplying drinking water to Bunbury. Formed in 1906 as the Bunbury Water
More informationHazard Management Making your workplace safer
Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,
More informationTube-Line Accelerator Spinner Kit
Tube-Line Accelerator Spinner Kit Operator's Manual PP-00799 (19/09/11) 2 TO THE OWNER This manual contains information concerning the adjustment, assembly and maintenance of your Tube-Line Spinner Kit.
More informationPLANT/EQUIPMENT/ASSET HAZARD REPORT
Asset Description: EL-09100-060 : Gantry hoist system Sale Type For what use is this asset being sold? Re-Use Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other use is at the
More informationMACHINE DETAILS Contains standard machine specifications and details of any extras fitted
RISK MANAGEMENT REPORT TYPE MAKE MODEL Excavator - Small Kubota KX080-3GLA SERIAL NUMBER 27471 PLANT NUMBER AHSH22 Report Number AHH 20180314-1554 Date Created By Assessor Assist. Assessor(s) Completed
More informationImportant Safety Information Enclosed
Important Safety Information Enclosed ShedBoss Safety Pack NOTE: ENSURE YOUR CONSTRUCTION CREW RECEIVES THIS PACK TO COMPLY WITH SAFE WORK AUSTRALIA CODE OF PRACTICE www.shedboss.com.au Important Safety
More informationPLANT RISK ASSESSMENT REPORT
PLANT RISK ASSESSMENT REPORT SECTION 1: PLANT IDENTIFICATION Report Number: 407/201-11B Assessment Date: 30 th January 2013 Company: Wacker Neuson Plant Type: Excavator Models: 803, 1404, 1703, ET18, 2003,
More informationCONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc.
CONSTRUCTION SAFETY PROGRAM FOR Golder Acoustics Inc. TABLE OF CONTENTS Topic... Page Safety and Health Policy... 2 Safety and Health Objectives... 3 Job Site Inspections... 4 Contractor Safety Administrator...
More informationRevision 1. Review Date 1/9/2013
/9/203 Page of 2 Description: Toyota 5 Series Huski Skid Steer Loader. 5SDK5, 5SDK8, 5SDK9, 5SDK0 and 5SDK. Material Structure: A steel framed, internal combustion powered with a hydraulic boom arm which
More informationSAFE WORK METHOD STATEMENT
ACN: 141 20 591 ABN: 41 149 34 727 P: 07 3843 149 F: 07 3395 2083 A: U15, 8 Metroplex Avenue Murarrie Qld 4172 This SWMS has been prepared and authorised by Eagle Alliance Earthmoving Pty Ltd Date: Last
More information20 Ton SD Shop Press Operating Instructions
20 Ton SD Shop Press Operating Instructions MODEL NO. 850SD Hazard Symbols Used in the Manuals This manual includes the hazard symbols defined below when the operations or maintenance job involves a potential
More information310 SERIES TILT-TO-LOAD ROTATOR. The Specialist In Drum Handling Equipment
OPERATOR S MANUAL FOR MORSE TILT-TO-LOAD DRUM ROTATOR SAFETY INFORMATION: While Morse Manufacturing Co. drum handling equipment is engineered for safety and efficiency, a high degree of responsibility
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30
More information