EIA Studies for the Development of CBM Activities in Jharia CBM Block

Similar documents
Quantitative Risk Assessment for Jaigarh Dabhol Natural Gas Pipeline

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Part 2.5 Dispersion Modeling Using ALOHA

EIA for Development /Exploratory Wells, Group Gathering Station and pipeline laying from KSAC to Borholla GGS at Kasomarigaon, Assam

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT

THE SIGNIFICANCE OF HAZARD ENDPOINTS IN QUANTITATIVE RISK ANALYSIS

DIGITAL SOLUTIONS TRAINING CATALOGUE. QRA and CFD simulation. Phast, Safeti and KFX SAFER, SMARTER, GREENER

PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT


Gerga Pressure Reduction Station

Tema Pressure Reduction Station

Practical Modelling & Hazard Assessment of LPG & LNG Spills

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines

Abstract. 1 Introduction

Annexure 2: Rapid Risk Assesment RISK ANALYSIS

Introduction to Emergency Response & Contingency Planning

RISK ASSESSMENT & DISASTER MANAGEMENT PLAN

State of the Art in the Technical Assessment of DOMINO EFFECT

DET NORSKE VERITAS. Report Corrib Onshore Pipeline QRA. Shell E&P Ireland Ltd. Report no/dnv Reg No.: 01/ 12LKQW5-2 Rev 01,

Using Consequence Modeling to Help Make Emergency Decisions

A Method of Quantitative Risk Assessment for Transmission Pipeline Carrying Natural Gas

Risks Associated with Caissons on Ageing Offshore Facilities

Figure-28 shows the methodology adopted for the rapid risk assessment of the drilling operation.

INHERENTLY SAFER DESIGN CASE STUDY OF RAPID BLOW DOWN ON OFFSHORE PLATFORM

A Generic Model To Assess Major Incident Frequencies For Offshore Assets

A quantitative risk analysis method for the natural gas pipeline network

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

Quantitative Risk Assessment (QRA) For

Introduction to consequence modelling

Determination of Safety Zones of Gas (NG and NGL) Pipelines

Modelling Hazardous Consequences of a Shale Gas Well Blowout

Blast Damage Consideratons for Horizontal Pressure Vessel and Potential for Domino Effects

1.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN 1.2 DEFINITION

Evaluation of Northwest Citizen Science Initiative (NWCSI) March 7,2015 Report Summary

Responding to Natural Gas Pipeline Emergencies

For. M/s. LOHITHA LABORATORIES AT KIADB, MUNDARGI INDUSTRIAL AREAA VILLAGE: MUNDARGI TALUK: BELLARY DISTRICT: BELLARY STATE: KARNATAKA

Quantitative Risk Assessment Study (QRA) For North of Giza Thermal Power Plant. November Submitted to Ministry of Electricity & Energy

Determination of the Design Load for Structural Safety Assessment against Gas Explosion in Offshore Topside

ON-SITE EMERGENCY PLAN

CONCLUSIVE SUMMARY OF CARBON DIOXIDE

Identification of hazardous units and storage units based on relative ranking technique, viz. Fire-Explosion and Toxicity Index (FE&TI).

Module 03 Accident modeling, risk assessment and management Lecture 04 Explosions

PSM TRAINING COURSES. Courses can be conducted in multi-languages

Using LOPA for Other Applications

ALOHA. Example Scenarios. September 2016

IGEM/TD/1. Background, Development, Changes J V Haswell

INTRODUCTION UNIFIED COMMAND

Quantitative Risk Assessment (QRA) For. Indian Oil Corporation Limited

7. ADDITIONAL STUDIES

The Science of Quantitative Risk Assessment for Explosives Safety

DISASTER MANAGEMENT PLAN

Expert System for LOPA - Incident Scenario Development -

Module No. # 04 Lecture No. # 3.1 Case studies (continued) (Refer Slide Time: 00:10)

This in an internal Commission document provided to Industry for reference purposes only.

USING PREDICTIVE RISK ASSESSMENTS TO DEVELOP USER-FRIENDLY TOOLS FOR ON- AND OFF-SITE EMERGENCY PLANNING

For. Indian Oil Corporation Limited

Inherently Safer Design Analysis Approaches

EGIG. European Gas Pipeline Incident data Group. Dick van den Brand Co-ordinator (external) safety Gasunie, the Netherlands Projectmanager EGIG

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England

QUANTITATIVE RISK ASSESSMENT (QRA) REPORT

Consequences on port facilities of a tanker explosion

Addendum 4 Levels of Response

Quantitative Risk Analysis (QRA)

2. IMMEDIATE RESPONSE ACTIONS AND NOTIFICATION PROCEDURES

Process Safety Journey

QUANTITATIVE RISK ASSESSMENT (QRA) REPORT INDIAN OIL CORPORATION LIMITED

Integrated Design for Demonstration of Efficient Liquefaction of Hydrogen (IDEALHY) Fuel Cells and Hydrogen Joint Undertaking (FCH JU)

Hazardous material transport accidents: analysis of the D.G.A.I.S. database

Rapid Risk Assessment Of. Proposed Expansion for the Manufacturing of Pigment and Intermediate Products, Clariant Chemicals (India) Limited

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36

Carmen Hamchevici - RWNA Francisc Senzaconi GIES Septimiu Mara - MEF

Gulfstream Natural Gas System

Section 1 - Identification of the Material and Supplier. Many industrial, medical and other applications.

Uncertainty in the analysis of the risk of BLEVE Fireball in process plants and in transportation

Establishment of Emergency Management System Based on the Theory of Risk Management

Answer: B Objective: NFPA 472, 5.2.4(3); Level: Operations Subject: Estimating the Potential Harm or Severity of the Incident; Chapter 4; Page 86

Fire & Explosion Prevention Strategy in Refineries

Hazard Operability Analysis

BASF Flash Fire FRC Assessment Tool

Marine Risk Assessment

APPENDIX A1 - Drilling and completion work programme

Comparison of Large-Scale Vented Deflagration Tests to CFD Simulations for Partially Congested Enclosures

Transient Analyses In Relief Systems

ERCBH2S A Model for Calculating Emergency Response and Planning Zones for Sour Gas Wells, Pipelines, and Production Facilities.

MAXIMUM CREDIBLE LOSS SCENARIO (MCLS)

The modern, fast and easy to use risk analysis tool. Advanced Features. Using HAZID in BowTie Pro

DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS

NPTEL CERETIFICATE EXAMINATION HSE practices in offshore & petroleum industries- SET 2

SAFETY PIPELINE. Simonette Expansion Pipeline Project

RISK ASSESSMENT 1.1 RISK ASSESSMENT

Hazard Identification

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN

RISK ASSESSMENT FOR SUN PHARMACEUTICAL INDUSTRIES LIMITED BULK DRUG AND INTERMEDIATES MANUFACTURING UNIT AT PLOT NO

Design Accidental Load for Explosion Resistant Design

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR

UGER Oilfield Rental Solutions EMERGENCY OPERATING PROCEDURES

Transcription:

Risk Assessment EIA Studies for the Development of CBM Activities in Jharia CBM Block Prepared for: Oil and Natural Gas Corporation Limited Prepared by: SENES Consultants India Pvt. Ltd. December, 2015

1. Quantitative Risk Assessment This section on Quantitative Risk Assessment (QRA) aims to provide a systematic analysis of the major risks that may arise as a result of ONGC Phase III development program plans which involves drilling of additional 77 development wells, installation of 5 Gas Collection Stations (GCS) and laying of inter-connecting and transportation pipeline network (4 dia) for CBM transportation. The QRA process outlines rational evaluations of the identified risks based on their significance and provides the outline for appropriate preventive and risk mitigation measures. Results of the QRA provides valuable inputs into the overall project planning and the decision making process for effectively addressing the identified risks. This will ensure that the project risks stay below As Low As Reasonably Practicable (ALARP) levels at all times during project implementation. In addition, the QRA will also help in assessing risks arising from potential emergency situations like a blow out and develop a structured Emergency Response Plan (ERP) to restrict damage to personnel, infrastructure, and the environment. The risk study for the onshore CBM development activities has considered all aspects of operation of the drilling rig and other associated activities during the development phase. Pipeline rupture and GCS leaks constitute the major potential hazards that may be associated with the proposed onshore development of Jharia CBM Block. The following section describes objectives, methodology of the risk assessment study and then presents the assessment for each of the potential risk separately. This includes identification of major hazards, hazard screening and ranking, frequency and consequence analysis for major hazards. The hazards have subsequently been quantitatively evaluated through a criteria based risk evaluation matrix. Risk mitigation measures to reduce significant risks to acceptable levels have also been recommended as a part of the risk assessment study. 1.1. OBJECTIVE OF THE QRA STUDY The overall objective of this QRA with respect to the proposed project involves identification and evaluation of major risks, prioritizing risks identified based on their hazard consequences and formulating suitable risk reduction/mitigation measures in line with the ALARP principle. Hence, in order to ensure effective management of any emergency situations (with potential individual and societal risks) that may arise during the development drilling activities, following specific objectives need to be achieved. Identify potential risk scenarios that may arise from the proposed CBM gas development activities particularly during transportation of CBM and GCS operation. Analyze the possible likelihood and frequency of such risk scenarios by reviewing historical accident related data for the onshore oil and gas industries. Predict the consequences of such potential risk scenarios and if consequences are high, establish the same by through application of quantitative simulations. Recommend feasible preventive and risk mitigation measures as well as provide inputs for drawing up of Disaster Management Plan (DMP) for the project. SENES/K-20240/ December 2015 2 ONGC

1.2. RISK ASSESSMENT METHODOLOGY An overview of the methodology employed is provided here to briefly introduce the study approach. A site reconnaissance visit was conducted to identify all hazards, both generic and site specific. Reviews of literature and accident databases were also undertaken. These formed the basis for identifying all hazardous scenarios for the QRA Study. The frequencies, or the likelihood, of the various possible outcomes resulting from a methane gas release scenario were derived from historical accident databases and, where necessary, these were modified to take into account local factors. For all identified hazards assessed, the consequences of each release were modeled using ALOHA consequence modeling software. 1.2.3 Hazard Identification Hazards associated with the proposed project have been identified based on site reconnaissance visit, understanding of existing operations and detailed review of known incident records worldwide, and experience gained from operations at similar facilities. In addition, based on the discussion with ONGC representative it is understood that methane gas will be handled both at the pipeline and GCS facility in the gas phase. A release from piping and valves/flanges of GCS facility will result in a gaseous phase release directly. As the gas disperses, it mixes with the surrounding air and warms up. The vapour cloud will only ignite if it encounters an ignition source while concentrated within its flammability range. Hazard Effects In the event of an accidental natural gas release (in gaseous phase) from piping or equipment, the characteristics of the possible hazardous effects are described below. Jet Fire Jet fires result from ignited releases of pressurized flammable gas or superheated/pressurized liquid. The momentum of the release carries the materials forward in a long plume entraining air to give a flammable mixture. Jet fires only occur where the CBM gas is being handled under pressure or when handled in gas phase and the release are unobstructed. This is considered to be the most credible risk scenario for the proposed project given the pipeline and metering facility will be operated at a design pressure of ~50 kg/cm 2. Flash Fire Following CBM gas release under high pressures, a cloud of methane may be formed, initially located around the release point. If this cloud is not ignited immediately, it will move with the wind and be diluted as a result of air entrainment. The dispersing vapour cloud may subsequently come in contact with an ignition source and burn rapidly with a sudden flash. If the source of material which created the cloud is still present, then the fire will flash back to the source giving a jet fire. Direct contact with the burning vapour may cause fatalities but the SENES/K-20240/ December 2015 3 ONGC

short duration of the flash fire generally means that thermal radiation effects are not significant outside the cloud and thus no fatalities are expected outside of the flash fire envelope. Fireball Immediate ignition of releases caused by a rupture in a gas piping may give rise to a fireball upon ignition. Fireballs have very high thermal radiation, similar to jet fires although the duration of the event is short. Vapour Cloud Explosion A flash fire is the most likely outcome upon ignition of a dispersing vapour cloud from a methane gas release. If the gas is ignited in areas where there is significant degree of confinement and congestion, an explosion may result. However, if the ignition happens in open (unconfined) areas as in this case, pure methane is not known to generate damaging overpressures (explode). To summarize a gas phase release can result in a flash fire, fireball or jet fire. A liquid phase release is generally associated with flash fire, vapour cloud explosion, pool fire or jet fire. 1.2.4 Scenarios for QRA study Scenarios for the QRA study were identified based on the hazard identified in the aforesaid section based on the site visit undertaken and review of incident records. Loss of containment events have been identified for each section of the GCS facility and pipeline, corresponding to the relevant process conditions, as listed in Table 1-1. TABLE 1-1: SCENARIOS FOR QRA STUDY Sl. No 1 Plant Section Valves/Flanges of GCS facility Initiating Event Risk Scenario Potential Outcome Scenario Leaks Leak from 1 dia Jet fire 2 Pipeline Rupture 4 pipeline rupture Jet fire, flash fire 1.2.5 Frequency Analysis Pipeline Failure Frequency Analysis An effort has also been made to understand the primary failure frequencies of CBM gas pipeline which is the result of the number of incidents within a period divided by the corresponding total system exposure. Based on the European Gas Pipeline Incident Data Group (EGIG) database the evolution of the primary failure frequencies over the entire period and for the last five years has been provided in Table 1-2 below. SENES/K-20240/ December 2015 4 ONGC

Period TABLE 1-2: PRIMARY GAS PIPELINE FAILURE FREQUENCY No. of Incidents Total System Exposure (km.yr) Primary failure frequency (1000 km.yr) 1970-2007 1173 3.15.10 6 0.372 1970-2010 1249 3.55.10 6 0.351 1971-2010 1222 3.52.10 6 0.347 1981-2010 860 3.01.10 6 0.286 1991-2010 460 2.25.10 6 0.204 2001-2010 207 1.24.10 6 0.167 2006-2010 106 0.654.10 6 0.162 Source: 8 h EGIG Report As referred in the above table the overall failure frequency (0.35) of the entire period (1970-2010) is slightly lower than the failure frequency of 0.37 reported in the 7 th EGIG report (1970-2007). The failure frequency of the last 5 years was found to be half the primary failure frequency over the entire period showing the improved performance over the recent years. Incident Causes CBM gas pipeline failure incidents can be attributed to the following major causes viz. external interference, construction defects, corrosion (internal & external), ground movement and hot tap. The distribution of incidents with cause has been presented in the Figure 1.1 below. FIGURE 1.1: GAS PIPELINE FAILURE DISTRIBUTION OF INCIDENT & CAUSES Source: 8th EGIG Report SENES/K-20240/ December 2015 5 ONGC

The interpretation of the aforesaid figure indicated external interference as the major cause of pipeline failure contributing to about 48.4% of the total failure incidents followed by construction defects (16.7%) and corrosion related problems (16.1%). Ground movement resulting from seismic disturbance, landslides, flood etc. contributed to only 7.4% of pipeline failure incident causes. The pipeline failure frequency viz. leaks or rupture from CBM gas transportation pipeline with respect to the proposed project has been established based on the interpretation of the database of European Gas Pipeline Incident Data Group (EGIG) representing almost 2 million kilometer year of pipeline operations. The failure rate reported by EGIG for on-shore gas pipeline with design pressure greater than 15 bar is 4.76 x 10-4 km/year. Full Bore Rupture (FBR) represents 13% of the cases (6.188 x 10-5 failure /km/yr) and 87% of the cases represents Leaks (4.14 x 10-4 failure /km/yr). The frequency of pipeline failure computed for the proposed project based on EGIG failure frequency is presented in the Table 1-3 below. TABLE 1-3: CBM GAS PIPELINE FAILURE FREQUENCY Sl. No Pipeline Failure Case EGIG Failure Frequency (per km.year) Pipeline Length (km) Project Pipeline Failure Frequency (per year) 1 Gas Pipeline Rupture 6.188 x 10-5 10 6.188 x 10-4 2 Gas Pipeline Leak 4.14 x 10-4 10 4.140 x 10-3 Source: 8 h EGIG Report Pipeline Failure Ignition Probability In the period 1970-2010, only 4.4% of the gas releases recorded as incidents in the EGIG database ignited. Ignition depends on the existence of random ignition sources. The EGIG database gives the opportunity to evaluate the link between ignition and leak size. The ignition probability of pipeline failure (rupture & leaks) with respect to the proposed project is derived based on the following equations as provided in the IGEM/TD/2 standard P ign = 0.0555 + 0.0137pd2; for 0 pd2 57 P ign = 0.81; for pd2>57 (Ignition Probability for pipeline ruptures) P ign = 0.0555 + 0.0137(0.5pd2); for 0 0.5pd2 57 (Ignition Probability for pipeline leaks) P ign = 0.81; for 0.5pd2>57 SENES/K-20240/ December 2015 6 ONGC

Where: P ign = Probability of ignition p = Pipeline operating pressure (bar) d = Pipeline diameter (m) The ignition probability of CBM gas release from 4 pipeline leak or rupture is calculated based on the above equations utilizing the following input parameters as discussed below. Pipeline Inlet Pressure (bar) = p= 50 kg/cm 2 or 49 bar Pipeline diameter = d = 4 inches or 0.101 m For 4 pipeline rupture pd 2 = (49) X (0.101) 2 = 0.499 For 4 pipeline leak 0.5 pd 2 = 0.5 X (49) X (0.101) 2 = 0.249 Since 0 pd 2 57 and 0 0.5pd 2 57, the following equation has been utilized for deriving the ignition probability for pipeline failure. P ign for 4 pipeline rupture = 0.0555 + 0.0137pd 2 = 0.0555 + 0.0137 (0.499) = 0.062 P ign for 4 pipeline leak = 0.0555 + 0.0137(0.5pd 2 ) = 0.0555 + 0.0137 (0.249) = 0.058 Based on the aforesaid calculation, the probability of jet fire occurring from accidental gas release from pipeline leak or rupture and subsequent ignition has been presented in Table 1-4 below: TABLE 1-4: CBM GAS CONNECTIVITY - PROBABILITY OF JET FIRE Sl. No Pipeline Failure Case Project Pipeline Failure Frequency (per year) Ignition Probability Jet fire Probability 1 4 Gas Pipeline Rupture 6.683 x 10-4 0.06 4.009 x 10-5 2 4 Gas Pipeline Leak 4.471 x 10-3 0.05 2.235 x 10-4 Process Leak Frequency Analysis The frequency of process leaks can be estimated directly from analysis of historical data obtained from E & P Forum hydrocarbon leak database (E&P forum 1992), World Offshore Accident Database (WOAD) and OREDA. Although onshore data is available for process leaks, the information is not considered representative of the actual scenario. Under such circumstances historical data available on hydrocarbon leaks in the OGP authenticated offshore accident databases have been considered for purpose of process leak frequency analysis. Failure frequencies of process equipment as in this case where leaks have been considered from valves and flanges of the GCS facility has been presented in Table 1.5 below. SENES/K-20240/ December 2015 7 ONGC

TABLE 1-5: LEAK FREQUENCIES FROM PROCESS EQUIPMENT Equipment Type Frequency (per equipment item year) Source: HSE Hydrocarbon Release Database 1.2.6 Consequence Analysis Flanges 8.8 X 10-5 Valves 2.3 X 10-4 Pipeline generally contains large inventories of oil or gas under high pressure; although accidental releases from them are remote, they have the potential of catastrophic or major consequences if related risks are not adequately analyzed or controlled. The consequences of possible pipeline failure is generally predicted based on the hypothetical failure scenario considered and defining parameters such as meteorological conditions (stability class), leak hole & rupture size and orientation, pipeline pressure & temperature, physicochemical properties of chemicals released etc. As discussed earlier, jet fire have been identified as the possible consequences resulting from release and is dependent on the ignition time. Taking into account the GCS facility and pipeline, the hypothetical risk scenarios as provided in Table 1-1 have been considered for failure consequence modeling with respect to proposed project. In addition to the above, the following design specifications as presented in Table 1-6 have been considered for consequence modeling TABLE 1-6: LEAK FREQUENCIES FROM PIPELINE & GCS Sl. No. Parameters Values 1 Pipeline diameter (inch) 4 inch 2 Pipeline length (km) 10 km 4 Design pressure (bar)* 49 5 Design temperature (in C) 40 In the present study, we have estimated the consequence of each reference scenarios (as mentioned in Table 1-1) in terms of fatality only. For each effect type (i.e. radiation, overpressure and toxic release), a set of threshold values were considered having 1, 5, 10, 20 and 50% fatality (Table 1-7). These threshold values were derived from Probit functions using the following equations: Thermal Radiation [1] : Pr = -14.9 + 2.56 x In (Q 4/3 x t)... Eq. Overpressure [2] : Toxic release [3] : Pr = 1.47 + 1.37 ln (p)... Eq. Pr = a +b x In (C n x t)... Eq. where, SENES/K-20240/ December 2015 8 ONGC

Pr = Probit Q = heat radiation (W/m 2 ) t = exposure time (s) p = peak overpressure (psig) a, b, n = constants describing the toxicity of a substance C = concentration (mg/m 3 ) t = exposure time (minutes) TABLE 1-7: THRESHOLD VALUES FOR EACH EFFECT LEVEL Fatality (%) Radiation (kw/m 2 ) Overpressure (psi) 50 26.50 13.10 20 20.78 7.15 10 18.25 5.20 5 16.42 3.95 1 13.42 2.40 [N. B. The values were derived using the above mentioned Probit equations] Based on these threshold values, effect distances were calculated to delineate different threatzones for each reference scenario. The analysis made use of the ALOHA model, one of the most commonly used effect models to generate the consequence effects showing the estimated distances for each scenario considered to a specified hazard end-point. These zones are displayed on a single Threat Zone plot displayed as red, orange, and yellow with red representing the worst hazard. The threat zone displayed by ALOHA represent thermal radiation levels and also indicates the effects on people who are exposed to those thermal radiation levels but are able to seek shelter within one minute. Predominant local meteorological conditions and composition of the CBM gas as provided during discussions with ONGC personnel was also considered for this study (refer Annexure 2.8). Nearly about 66-98% of the CBM gas is constituted by methane with the remaining represented by ethane (0-6.5%), propane (0-1.3%), carbon dioxide (0-11.5) and nitrogen (1-26.4). Case I: Release of CBM gas from valves/flanges of GCS hole size (1 dia) The jet fire threat zone plot for release and ignition of flammable CBM gas from GCS facility valves/flanges leak of size - diameter 1 inch is represented in Figure 1.2 below. SENES/K-20240/ December 2015 9 ONGC

FIGURE 1.2: THREAT ZONE PLOT FOR JET FIRE 1 DIA LEAK THREAT ZONE: Threat Modeled: Thermal radiation from jet fire Orange: 11 meters --- (10.0 kw/ (sq m) = potentially lethal within 60 sec Yellow: 16 meters --- (5.0 kw/ (sq m) = 2nd degree burns within 60 sec Taking into consideration established probit values that are linked to fatality caused by thermal radiation from fire, no endpoint distances have been computed below thermal radiation of 13.42 kw/sq.m. Case II: Ignition of natural gas from complete rupture of 4 pipeline The complete rupture of 4 pipeline will result in the release of methane gas (in gaseous phase) the ignition of which is likely to result in jet fire. The threat zone plot of jet fire resulting from pipeline rupture is derived using ALOHA and represented in Figure 1.3. SENES/K-20240/ December 2015 10 ONGC

FIGURE 1.3: THREAT ZONE PLOT FOR JET FIRE - 4 PIPELINE RUPTURE THREAT ZONE Threat Modeled: Thermal radiation from jet fire resulting from full bore rupture Red : 10 meters --- (26.50 kw/ (sq m) = 50% fatality Orange: 12 meters --- (16.42 kw/ (sq m) = 10% fatality Yellow: 14 meters --- (13.42 kw/ (sq m) = 1% fatality The worst hazard for release and ignition of natural gas from complete rupture of 4 dia pipeline will be experienced to a maximum radial distance of 10 m from the source with 50% fatality. For various hypothetical scenarios considered with respect to proposed CBM development project, the threat zones calculated using ALOHA for defined thermal radiation intensities have been presented in the Table 1-8 below. SENES/K-20240/ December 2015 11 ONGC

Case No TABLE 1-8: THREAT ZONE DISTANCE FOR HYPOTHETICAL RISK SCENARIOS Pipeline Failure Case Hole Size (inch) Distance to 26.50 kw/m 2 (m) 50% fatality Distance to 16.42 kw/m 2 (m) 10% fatality Distance to 13.42 kw/m 2 (m) 1% fatality I Valves/flanges leak 1.00 <10 <10 <10 II 4 pipeline rupture 4.00 10 12 14 Modeling Risk of Overpressure from Vapour Cloud Explosion A flash fire is the most likely outcome upon ignition of a dispersing vapour cloud from a natural gas release. If ignited in open (unconfined) areas, pure methane is not known to generate damaging overpressures (explode). However, if the gas is ignited in areas where there is significant degree of confinement and congestion an explosion may result. Although an unconfined explosion is considered to be unlikely for the proposed project an effort has been made to establish the overpressure (blast force zone) that may result from delayed ignition of vapour cloud generated from any such accidental release from ruptures. For over pressure risk modeling using ALOHA a delayed ignition time of 15 minutes was considered of the vapour cloud mass. However the threat modeled revealed that Level of Concern (LOC) was never exceeded that may possibly lead to loss of life within the blast radius. This is in agreement with the earlier assessment that no damaging overpressure is likely to be generated from unconfined ignition of natural gas vapour cloud. The results have been provided in Figure 1.4 below FIGURE 1.4: VCE MODELING RESULTS FOR OVERPRESSURE SENES/K-20240/ December 2015 12 ONGC

1.2.7 Individual Risk Individual risk is the probability at which an individual may be expected to sustain a given level of harm from the realization of specified hazards. In simple terms it is a measure to assess the overall risk of the area concerned thus to protect each individual against hazards involving hazardous chemicals, irrespective of the size of the accident that may occur. Graphically it represents as iso-risk contour which connects all of the geographical locations around a hazardous activity with the same probability of fatality. In order to generate different level of iso-risk curves for the area concerned, it is required to estimate the respective contribution of each reference scenario. Accordingly, individual risk of each scenario was estimated by combining the frequency of the initiating event, the conditional probability of that scenario sequence and the Probit value of the effect footprints. In particular following expression was used to estimate the Individual Risk (IR) at a given geographical location for each reference scenario: IR(x, y, i) = fi. PFi (Eq. iv) Where, fi is the frequency of the accident scenario i (year -1 ); calculated as multiplicative factor of the frequency of the initiating event and the probability that the sequence of events leading to the accident scenario i will occur: fi = fincident i. Psequence i PFi is the probability of fatality that the accident scenario i will result at location (i.e. Probit). The individual risk so obtained is then compared with the Tolerance Criteria of Individual Risk as provided in the Figure 1.5 below. FIGURE 1.5: TOLERANCE CRITERIA FOR INDIVIDUAL RISKS Hence, for the proposed project the individual risk has been considered only for pipeline rupture as no predicted fatality has been established for the consequence modeling undertaken SENES/K-20240/ December 2015 13 ONGC

for CBM gas release ignition from valves/flanges of the GCS facility. Based on the above equation the individual risk as calculated including the tolerance criteria has been presented in the Table 1-9 below. TABLE 1-9: INDIVIDUAL RISK PIPELINE RUPTURE Accident Scenario Frequency Fatality Probability Individual Risk Individual Risk Criterion 4 inch Pipeline Rupture 4.009 x 10-5 0.50 2 x 10-5 ALARP 4.009 x 10-5 0.10 4 x 10-6 Tolerable 4.009 x 10-5 0.01 4 x 10-7 Tolerable 1.3 DISASTER MANAGEMENT 1.3.1 OBJECTIVE The primary objective of the DMP is to provide a safe, timely, effective, and coordinated response by the onsite Emergency Response Team (ERT), along with the other local and government agencies/departments to prevent or minimize any major emergencies that may arise from possible failures of CBM gas transportation pipeline during implementation of Jharia Phase III project. The main objectives of this plan are: Minimize the risk for human life, environment and common property resources, by means of an effective and efficient intervention; Protection of the environment; Protection of public safety; Initiate the early and efficient response throughout the utilization of all available resources. 1.3.2 PURPOSE The purpose of the DMP is to effectively manage and control the emergencies occurring during project operations. This DMP ensures, emergency response group is effective & adequate; clear roles and responsibilities of key personnel & support groups; availability and adequacy of emergency infrastructure & resources; and efficient emergency communication 1.3.3 Emergency Classification Due consideration is given to the severity of potential emergency situation that may arise as a result of storage tank and pipeline accident events as discussed in the Quantitative Risk Analysis (QRA) study. Not all emergency situations call for mobilization of same resources SENES/K-20240/ December 2015 14 ONGC

or emergency actions and therefore, the emergencies are classified into three levels depending on their severity and potential impact, so that appropriate emergency response procedures can be effectively implemented by the ONGC Emergency/Crisis Management Team. The emergency levels/tiers defined with respect to this project based on their severity have been discussed in the subsequent sections with 'decision tree' for emergency classification being depicted infigure 1-6: Emergency Classification Decision Tree Figure 1-6. FIGURE 1-6: EMERGENCY CLASSIFICATION DECISION TREE EMERGENC Y Activate Disaster Management Plan Mobilization of equipment/human resources available onsite is sufficient to contain the emergency NO YES LEVEL 1 EMERGENCY Containment of emergency requires involvement of additional resources and local emergency responder group s viz. local police, fire brigade etc YES LEVEL 2 EMERGENCY NO Management of emergency requires the involvement of District/State Disaster Management Team YES LEVEL 3 EMERGENCY Level 1 - Emergency An event that can be dealt with by on-site/location personnel and resources; the event does not have any effect outside the site and external agencies are unlikely to be involved. There is unlikely to be danger to life, to the environment, or to Company assets or reputation. The Disaster Management Plan and relevant procedures are activated; the Site Head is notified. SENES/K-20240/ December 2015 15 ONGC

Level 2 - Emergency It is an event which may be dealt by the ONGC Emergency/Crisis Management Team but requires involvement of wider Company support and external services. The initial event may be on-site, have some effect outside the site or be off-site, and external emergency services will be involved. There is likely to be danger to life, the environment, or to company assets or reputation. The Disaster Management Plan and relevant procedures are activated; local administrative bodies and Emergency Response Groups including ONGC Corporate are notified. Level 3 - Emergency It is a major event which requires the involvement of District or State Crisis Management Group. For Company this may result from insufficient local resources and/or because the incident has broader implications such as reputation, legal prosecution, financial loss etc. Under such circumstances, the Disaster Management Plan is activated; ONGC Corporate, District/State Administrative Authorities, and other Emergency Response Groups are notified. The criteria for classification of various levels of emergencies and associated response have been presented in the Figure 1-7 below. FIGURE 1-7: EMERGENCY RESPONSE LEVELS Level Type Criteria for Classification Level 1 Small Minor medical or injury case requiring no external support Equipment damage without any significant impact on operation Minor fire without any personnel injury or plant damage Net negative financial impact of <1 crores. Local stakeholder concern and public attention Level 2 Medium Fire and explosion which requires external assistance Requires evacuation of injured personnel and locals through assistance from local emergency groups. Loss of corporate image and reputation Net negative financial impact of 1-5crore Level 3 Large Incident leading to multiples injuries or fatalities Requires assistance from District/State emergency responding groups. State/nationwide media coverage Net negative financial loss of >5crore 1.3.4 ONGC DISASTER MANAGEMENT PLAN ONGC has in place a Disaster Management Plan which has been developed to set up the appropriate mechanism and course of action to mitigate the impact of an Emergency event viz. blow out, fire, explosion etc. The plan provides a procedure allowing all those involved in and outside ONGC to mobilize their resources in an orderly manner and react effectively in time. The plan therefore, aims at immediate response to an Emergency event to prevent escalation to SENES/K-20240/ December 2015 16 ONGC

a Disaster and also the response in the event of such escalation. The plan will be updated as and when necessary, but at least once in every year by Basin HSE in consultation with Surface Team, Sub surface Team, Drilling Services, and Well Services Group. ONGC has been also accredited with ISO 9001:2008; 14001:2004 and OHSAS 18001. The roles and responsibilities of both ONGC emergency response team to combat with any emergency situation are discussed below, while the details of the resources available onsite with the Crisis Management Team to control key emergency events particularly blow outs has been presented in Annexure 6.4. Offsite disaster management plan is presented in Annexure 6.5. Disaster Management Team Members Following are the members of Contingency team constituted at CBM development project to meet any emergency situation: Project Manager Head Drilling Services Head Surface Team Head Engineering Services Location Manager Work Over Services Location Manager WSS Location Manager drilling Services Responsibility of disaster management team is detailed in Table 1-10. TABLE 1-10: ROLE & RESPONSIBILITIES OF DISASTER MANAGEMENT TEAM MEMBERS Role Responsibility Project Manager Will function as Chief Emergency Co-ordinate and have overall control Responsible for taking all major decisions Decision for taking external help, if situation is beyond in-house capability Updating and interacting to head quarter and board level Conducting kick-off meeting and activating SOP Planning of VIP visits Calling review meeting every two days Block Manager Geological Correlation Calculation of Reservoir pressure Support Manager Assistance in procurement and supply of materials. Assistance in getting clearance from Custom, Port Authorities and Air Lines Co-ordination of stores function within ONGC and outside the Organization Settlement of insurance claims SENES/K-20240/ December 2015 17 ONGC

Role Responsibility Head Drilling Services Assessment of gravity of situation and declaring a state of emergency Executive control of operation Interaction with RCMT and Head Corporate CMT Mobilization of resources Control of rescue operations Situation reports Post emergency operation Head Well Services Assessment of gravity of situation and declaring state of emergency. Executive control of operation Interaction with RCMT and Head Corporate CMT Mobilization of resources Control of rescue operations Situation reports Post emergency operation Pass instruction to LM WSS, LM-WOS and LM WC&T Head Surface Team Assessment of gravity of situation and declaring state of emergency. Executive control of operation Interaction with RCMT and Head Corporate CMT Mobilization of resources Control of rescue operations Situation reports Post emergency operation Head-Subsurface Team Co-ordination with services Ensuring smooth operational activity Head Engineering Services Provide technical support related to Civil, Electrical & Mechanical Services Location Manager Work over Services To provide & approve drawing and design required for emergency operations Assessment of gravity of situation and declaring state of emergency. Executive control of operation Interaction with RCMT and Head Corporate CMT Mobilization of resources Control of rescue operations Situation reports Post emergency operation Incharge Cementing Services To arrange cementing unit and act in co-ordination with Head CMT Incharge HSE Incharge HSE, CBM Development Project will be the Safety Coordinator Overall assessment of safety situation Assessment of Environmental Impact and suggest method for containment Ensure use of PPE and safety requirements To keep a chronological record of all events SENES/K-20240/ December 2015 18 ONGC

Role Responsibility Assist in post-emergency enquires Draw up corrective measures based on gained experience. In charge Security Head of the fire and security will be the security Co-ordinator. Responsibilities and functions of the security Co-ordinator are as follows Directs fire officer. Dispatches fire tenders to emergency site Identifies special firefighting equipment s Arranges security forces (Civil Defense, TA Personnel, CISF) at the emergency site. Ensures cordoning off the emergency site area, banning entry of unauthorized person and security of property of the ONGC, important records etc. Prevents theft, looting, sabotage and espionage Co-ordination with police / defense if required Arranges evacuation Controls mob and inspires confidence among a crowd of disorganized, confused and frightened individuals Responsible for post emergency scrutiny Suggests corrective steps for future implementation In charge Fire Organize and supervise firefighting operation Responsibility for putting off fire In charge Logistic Transport of personnel and materials to emergency site Control of helicopter operations In charge Infocom Setting up control room at site and base Operate all in-house communication facility round the clock basis Mobilize additional communication equipment s as required In charge F & A Financial assistance in mobilizing equipment/ services & materials Obtaining approval for foreign exchange Assistance in documentation for insurance claims Financial assistance in compensation for damage of life and property SENES/K-20240/ December 2015 19 ONGC