Inspection and Test Plan for Gas Circuit Breaker

Similar documents
STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL)

Project: Consultant : MEP Contractor: PREPARED BY: DORMAN SMITH SWITCHGEAR - DUBAI REVIEWED BY CONSULTANT : Page 1 of 15

QUALITY ASSURANCE SPECIFICATION NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"

Outline for Safety Performance Supervisory Inspection of Boiler and Pressure Vessel Products

C&G 2395 Exam Paper June Section A-All questions carry equal marks. Answer all three questions. Show all calculations.

Annex G (normative) Requirements for Nondestructive Examination

API 510: Pressure Vessel Inspection Code (API Exam Preparation Training)

MATERIAL REQUISITION FOR VALVES

SAMPLE WRITTEN PROGRAM for Control of Hazardous Energy LOCKOUT TAGOUT

ACCREDITATION OF ON-LINE LEAK SEAL ORGANIZATIONS

ES18 Security Theory/Regulations Answer Schedule

Sample Written Program for The Control of Hazardous Energy (Lockout/Tagout)

BODY OF KNOWLEDGE API-510 PRESSURE VESSEL INSPECTOR CERTIFICATION EXAMINATION

Fact Sheet Oil Sands hoses Trelleborg Engineered Products The Netherlands

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

PRESSURE RETEST. 49 CFR, (g) Co#: Vin#: DOT Spec: MAWP:

Regulations Respecting Compressed Gas Pressure Vessels

Electrical. Version 1.0

American Welding Society Accredited Test Facility Certification Candidate Orientation

Control of Hazardous Energy Program (Lockout/Tagout)

SUPPLY OF ISOLATION AND APPLIANCE VALVES PTS - APPLIANCE BALL VALVE

INSPECTION OF RECOVERY BOILERS

Guideline No.M-05(201510) M-05 AIR COMPRESSOR. Issued date: 20 October China Classification Society

i) Filtration machine, measuring equipment and other related machinery

F-08 HIGH-PRESSURE HOSE USED IN CO2 SYSTEM

CERTIFICATION OF COMPLIANCE OF THE USER S DESIGN SPECIFICATION

RESISTORS, HEATERS, FLEXIBLE, SINGLE AND DOUBLE LAYER. ESCC Detail Specification No. 4009/002

MSC Guidelines for Pressure Vessels

GUIDELINES. Systems. Pressure

PIP PNE00012 Piping Examination and Leak Test Guide

SUPPLY OF ISOLATION AND APPLIANCE VALVES PTS - ISOLATION BALL VALVE

Inspection Recommendations

HYDROSTATIC LEAK TEST PROCEDURE

Supervisory Inspection Rule for Safety Performance of. Boiler and Pressure Vessel Products

C&G 2395 Exam Paper April Section A - All questions carry equal marks. Answer all three questions. Show all calculations.

Technical Standard. API6D Ball & Plug Valve. Inspection & Test Procedure

Equipment Accuracy / Selection

I003 Lock Out - Tag Out - Try Out. Document information

South-Tek Systems - Nitrogen Generation Corrosion Inhibiting System. Designed for: Dry or Preaction Fire Protection Systems (FPS)

IE073: Intrinsic Safety, Galvanic Isolation and Zener Barriers Technology & Applications

Pressure Relief Device Investigation Testing Lessons Learned

Level 3 Diploma in Moving Loads in Construction. Qualification Specification

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE

CLASS DH - PNEUMATIC TESTING - GREATER THAN 1 BAR (15 PSIG)

WATER MADE EASY MARINE ENERGY MUNICIPAL INDUSTRIAL

Manual Power relay SR853

Procedure: Pressure equipment safety

Erik Backström, High Voltage breakers, After Sales & Service High voltage SF 6 live tank circuit breakers After Sales & Service Training course

PSSI 1 High Voltage Switching

TECHNICAL DATA. System water supply pressure enters the priming chamber of the deluge valve (A.1) through the 1/4 (8 mm) priming line, which

Pressure and Vacuum Switches for Process Applications

STS 650 PRESSURE EQUIPMENT

API-510 PRESSURE VESSEL INSPECTOR

Contents. Operating instructions. Pressure switch, heavy-duty version Model PSM-520

Abdullah Fahad Alhuzaim

MANUFACTURING PROCEDURE SPECIFICATION INSPECTION TEST PLAN

APPENDIX 1. PART 10: Leak Detection Inspector, Level 1, 2 and 3 CERTIFICATION SCHEME FOR PERSONNEL. 3 rd Edition, February 2016

Regulated Oil and Gas Companies under National Energy Board Jurisdiction

May08 Rev B

JAPANESE PD EXAMINATIONS FOR DEPTH SIZING OF SCC IN AUSTENITIC STAINLESS STEEL PIPES FROM 2006 TO 2012

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

American Petroleum Institute Purchasing Guidelines Purchase API Spec 6DSS online at

A. Evaluation of the written program

MODEL UM UNIVERSAL MANIFOLD ASSEMBLY (With or Without Control Valve) 1¼", 1½", 2", 2½", 76.1mm, 3", 4", 6",165.1mm, 8"

High Pressure Iron (HPI) Recertification Guidelines & Procedures

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA. Q = C v P S

GUIDELINES. Systems. Pressure. Guidelines Acceptance of equipment, establishment of safe operating limits and fitness for service

PRO Lifting Operations

2.1 Contractor The company that supplies the hot tap machine and its operating personnel.

RUPTURE HAZARD OF PRESSURE VESSELS

PGM PREPIPED GAS MANIFOLD

INSTRUCTIONS FOR USE

Circuit breakers PR 60

Installation and Operation Manual

TECHNICAL DATA 3 MODEL G-3000 DRY VALVE RISER ASSEMBLY

University of Aberdeen

Safety Standards. of the Nuclear Safety Standards Commission (KTA)

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13

Ground Fault Circuit Interrupter(GFCI) Policy

Accreditation for In-Service Inspection of Transportable Pressure Receptacles (TPRs)

Fire Apparatus Operator: Pumper

TECHNICAL DATA. Q= Cv S

Inspection and Testing

QPEO2/037N Credit Value: 15 QCF Level: 2 GLH: 68 Maintaining electrical equipment/systems

Requirements for the certification of movements and mechanical watches resistant to magnetic fields of 1.5 T ( G)

GRUNDFOS DATA BOOKLET. Hydro Solo-E. Complete pressure boosting systems 50/60 Hz

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

ELECTRICAL SAFETY. Unsafe work practices near electricity can kill you! You are responsible for protecting yourself from electrical shock.

Recent changes in workplace safety regulations have heightened the awareness of hazards associated with electrical arcs.

CPM CONSTRUCTORS 30 BONNEY STREET P.O. BOX B FREEPORT, MAINE FAX

700 SERIES BMS II BUBBLER MONITORING SYSTEM

THE PROCESS OF JOINT INTEGRITY

February 5, 2014 REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE MODEL NO PACKAGE

General maintenance engineering applications

MIL-STD-883G METHOD

Standard Practice for Eddy-Current Examination of Steel Tubular Products Using Magnetic Saturation 1

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

General Requirements of the NEC Advanced Course. Building Officials and Inspectors Educational Association

Transcription:

Inspection and Test Plan for Gas Circuit Breaker No. Inspection and Test Plan Reference Document Acceptance Criteria Verifying Document Activity By Remark Manuf. TPI Client 1 Pre Inspection Meeting Spec. Spec. MOM H H H Before Manufacturing 2 DWG, Design, Calculation Document DWG, Calculation book H R A 3 WPS&PQR ASME IX ASME IX Welding Book H R A 4 Welder Qualification ASME IX ASME IX H R 5 NDT procedures ASME V ASME V s H R A 6 NDE Personnel ASME IX ASME IX H R 7 Pressure Test ASME VIII ASME VIII 8 Leakage Test 9 Stored Energy System Test 10 Main Circuit Power Frequency Voltage Dry Tension Test 11 Voltage on Control and Auxiliary Circuit Test 1

12 Main Circuit Resistance Test 13 Mechanical Operation Test 14 Timing Test 15 Compressor Operation Test 16 Painting SSPC SSPC Materials 17 Raw Material Inspection ASTM ASTM Original Material H H 18 Review of ASTM ASTM H H 19 Material Identification ASTM ASTM Report H H During Fabrication 20 Assembly Inspection DWG DWG Report H SW 21 Welding Inspection for Required Welding Components WPS WPS Report H SW 2

22 23 Checking of Outline Dimensions, Interface Dimensions, Bus Bar Dimensions and Clearances and other Specified Dimensions Tightness/Torque of Terminals and Degree of Protection DWG DWG Report H SW DWG/Spec DWG/Spec Report H SW 24 Checking that all Instruments, Control Switches, Interlocks and etc. are Correctly Rated and are Correctly Located, with Specified Labeling. DWG/Spec DWG/Spec Report H SW 25 Pressure Test 26 Leakage Test 27 Stored Energy System Test 28 29 Main Circuit Power Frequency Voltage Dry Tension Test Voltage on Control and Auxiliary Circuit Test 3

30 Main Circuit Resistance Test 31 Mechanical Operation Test 32 Timing Test 33 Compressor Operation Test Final Inspection 34 Final Visual & Dimensional Check DWG DWG Report H H 35 Surface Preparation and Painting Report H W 36 Check of Final Book Spec. Spec. DWG/ P.O H R Documentation 37 Inspection Reports Spec./DWG Spec./DWG Report H R 38 NCR Spec./DWG Spec./DWG Report H R 39 Review Final Data Report Spec./DWG Spec./DWG Report H R Pre shipment Inspection 40 Preservation and Packing Spec. Spec. Report H H 41 Marking Spec. Spec. Report H H 42 Loading Inspection Spec. Spec. Report H H 4

43 Shipping Document Control Spec. Packing List H H Abbreviations: H: Hold Point = Hold on the production till TPI Inspector performs inspection and supervise the required test W: Witness Point = Manufacture shall notify client and TPI Inspector but there is no hold on the production; Client can waive this inspection based on his discretion and informs TPI Inspector accordingly. R: Document Review = Review means Review document, which includes of material test certificates, WPS, PQR, NDT s and etc. A: Approval SW: Spot Witness = for items with spot witness manufacture shall notify TPI inspector as fulfilling the monitoring; For example one random visit for whole UT tests or one or two visits for whole surface preparation works for painting. MOM: Minute of Meeting P.O: Purchase Order for more information review following articles: http:///third party inspection for gas circuit breaker.html http:///inspection and test plan for gas circuit breaker.html 5