The vessel Nova K, will be undertaking survey and PLGR work on the array cable routes.

Similar documents
Notice of operations at London Array Offshore Wind Farm. Date of Notice: 20 th May 2012 Notice no: 75. London Array Offshore Wind Farm

Other vessel's involved in the Swale cable pull in and burial operations will be the multicat Wiltango, and the barges Wilcarry 300, & Wilcarry 342.

The Array cable installation vessel Stemat 82 and Assist tugs Lydia D and Claudia B are expected to commence installing array cables during week 5.

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 03 rd June 2012 Notice no: 77. London Array Offshore Wind Farm

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 01 st July 2012 Notice no: 81. London Array Offshore Wind Farm

Notice of operations at London Array Offshore Wind Farm

All Array cables have been installed and the cables have now been buried.

London Array Offshore Wind Farm. Vessel Data Matrix

Notice of operations at London Array Offshore Wind Farm

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Survey Vessel ) Guard Vessels...

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 4

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 5

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Rock bag removal Export cable ends...

Contents. 3) WTG Installation Vessel ) Hotel vessel ) Substation works ) Survey Vessel... 5

Safety Zone Application Construction Phase Sheringham Shoal Wind Farm Project

Contents. 3) WTG Installation Vessel ) Array cable burial Vessel ) Hotel vessel ) Substation works... 5

Notice to Mariners No 24 / 2017 Blyth Offshore Demonstrator Project 9 th September 2017

ADANI PORTS & SEZ LTD. ++ MUNDRA PORT ++ GENERAL INFORMATION

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

Admiralty Leisure Folio SC5601 East Devon and Dorset Coast, Exmouth to Christchurch

For live Kingfisher updates of offshore activities, visit and on Twitter. 1 of 10

The shaded blocks below indicate the areas of activity published within this Bulletin.

Chart Features Maritime maps and Admiralty charts have these features:

GVqQ(6)+LFl.15s, from: 56 16' 62N., 6 24' 91W.

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

Notices to Mariners. OSTEND march 29th 2012 NR. 07

Imray Correction Notice 28 March 2018

LIST OF CORRECTIONS. INT Belg. 101 Chart

IMO ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS

LIST OF NOTICES TO MARINERS 2017 PAC 201 JUAN DE FUCA STRAIT AND STRAIT OF GEORGIA, FIRST EDITION, 2012

IALA Buoyage System and Visual Aids to Navigation. by Aleksandr D. Pipchenko

G9 Stakeholder Forum Marine Operations

The shaded blocks below indicate the areas of activity published within this Bulletin.

The shaded blocks below indicate the areas of activity published within this Bulletin.

Astrolabe Reef Access Plan Stakeholder Presentation

SECTION I NM 25/16 CHART CORRECTIONS

CHAPTER 8 BUOYAGE 8.1 GENERAL

To be read in conjunction with the 2018 MYCQ Sailing Instructions, Revision H. RACE: The Great Bay Race TYPE: Summer 5

The shaded blocks below indicate the areas of activity published within this Bulletin.

National Maritime Center

That is why. April 24, 2008

Nemo Link s puxo campaign

Protection for Vessels Engaged in Servicing Submarine Cables

Thanet Extension Offshore Wind Farm Shipping and Navigation - Pilotage Study

Sailing Season

The Marking of Offshore Wind Farms. Provide guidance for a response to IALA. M-4 B445.8 &.9 (& B for on-shore wind farms).

Gorgon - Pilotage - Passage Plan Materials Offloading Facility (MOF) to PBG

Gorgon - Pilotage - Passage Plan PBG to Materials Offloading Facility (MOF)

SAILING INSTRUCTIONS

NOTICE TO MARINERS. Issue Date: 17 th March, Western HVDC Link Project - Shallow water cables installation in Liverpool bay

COMBINED OCEAN POINTSCORE SAILING INSTRUCTIONS 2018 / 2019

NOTICE TO MARINERS. Western Link Project. Shallow and Deep water cable installation

Visiting Lake Macquarie

Offshore Racing SAILING INSTRUCTIONS


The shaded blocks below indicate the areas of activity published within this Bulletin.

G+ Global offshore wind health and safety organisation

West of Ireland Offshore Racing Association Foynes Yacht Club West Coast Championships 11 th 14 th July 2012

Offshore Wind Vessels. Steven Kopits Douglas-Westwood LLC

Whitstable Harbour Pilotage Information

The shaded blocks below indicate the areas of activity published within this Bulletin.

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

LOCAL NOTICE TO MARINERS

NavRule Practice Exam, 70 Series Practice April 24, Labeled F (I received a reply from the testing service that all these answers were

Offshore Racing. SAILING INSTRUCTIONS Amendment 1 Change to sect 11 Time limit

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

The shaded blocks below indicate the areas of activity published within this Bulletin.

Tacoma Yacht Club Summer Vashon Regatta Saturday, June 2, 2018 SAILING INSTRUCTIONS

ROUND-THE-ISLAND RACE

NOTICE TO SHIPPING #1 NIAGARA REGION WELLAND CANAL GENERAL INSTRUCTIONS 1. HOLDING POSITION - 'HEAD OF THE LOCK'

National Maritime Center

ESTABLISHING AN OFFSHORE MUSSEL FARM IN FEDERAL WATERS IN THE GULF OF MAINE

The shaded blocks below indicate the areas of activity published within this Bulletin.

OFFSHORE WIND: A CRASH COURSE

CHAPTER I SUEZ CANAL NAVIGATION FEATURES SECTION 1 APPROACHES

LIST OF CORRECTIONS. 02 / January /052(T) - 07/125(T) - 08/136(T) - 08/137(T) - 12/177(T) - 15/212(T) - 18/232-22/285(T)

Chapter 8. Port hand buoy. Starboard hand buoy. Canadian Aids to Navigation System (CANS) 8.1 Introduction. 8.2 Lateral Buoys

THE 2012 SUMMER SAILSTICE REGATTA June 23, 2012 SAILING INSTRUCTIONS (rev 6/18/12)

112 INDIAN OCEAN, Îles Crozet - Depth. Depth 126m, extend 200m contour NW to enclose depth,. *113 NAMIBIA, Walvis Bay - Buoyage.

National Maritime Center

SECTION I NM 5/17 CHART CORRECTIONS

THE SYLLABUS FOR WRITTEN EXAMINATION PILOT'S FOURTH CLASS LICENCE (TEES AND HARTLEPOOL) AND

Summer Solstice Ocean Race CCVracing.org

The shaded blocks below indicate the areas of activity published within this Bulletin.

BookletChart. Intracoastal Waterway Matecumbe to Grassy Key NOAA Chart A reduced-scale NOAA nautical chart for small boaters

THE GREAT VALLEJO RACE MAY 1 and 2, 2010 SAILING INSTRUCTIONS

The shaded blocks below indicate the areas of activity published within this Bulletin.

ROUTEING MEASURES OTHER THAN TRAFFIC SEPARATION SCHEMES

Pioneer Array Micro-siting Public Input Process Frequently Asked Questions

BookletChart. Sand Key to Rebecca Shoal NOAA Chart A reduced-scale NOAA nautical chart for small boaters

Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement

Regulations and safety instructions. Code of conduct for a safe passage through windfarms

Transcription:

London Array Ltd. Construction Management Port of Ramsgate Military Road Ramsgate CT11 9LG www.londonarray.com Notice of operations at London Array Offshore Wind Farm Date of Notice: 29 th April 2012 Notice no: 72 The offshore construction work for London Array is now well underway. We are issuing weekly notices on the progress and resources involved in the offshore project. The intention is to give an overview of activities and vessels involved. Should anyone have questions to the operations, we kindly ask you to put them forward well in advance. London Array Offshore Wind Farm For general information on the London Array project, see: www.londonarray.com If you have any questions on the offshore activities, or request further information, please direct them to: londonarraytraffic@dongenergy.dk 1. Work planned for week 18 (30/04/12 to 06/05/12) Foundation installation vessel MPI Adventure will install J11 K12 and J12. Whilst construction is taking place at this position a 500m safety zone is established, and vessels are to keep clear. The Wind Turbine installation jack up Sea Worker and assist tugs Sea Alfa, Sea Echo, will install H19, F18 and I19. Whilst construction is taking place at these positions a 500m safety zone is established, and vessels are to keep clear. The Wind Turbine installation vessel MPI Discovery will install F07 E07 D08 C06 C07 B08 and then return to Esbjerg to load further units. Whilst construction is taking place, a 500m safety zone is established, and vessels are to keep clear. The Array cable installation vessel Stemat 82 and assist tugs Lydia D and Yvonne W will return to site from Sheerness to install array cable SS1 to E15 and D20 to C19. Whilst construction is taking place, a 500m safety zone is established, and vessels are to keep clear. The Array cable installation vessel Stemat Olso and assist tugs Sea Charlie and Maggie M will return to site from Sheerness to install array cable M19 to M20 and then L19 to M19. Whilst construction is taking place, a 500m safety zone is established and vessels are to keep clear. The Array cable installation vessel Pontra Maris and assist tugs Amstel Stroom and Odin, will complete mobilization in Sheerness and will deploy to site. Whilst construction is taking place, a 500m safety zone is established and vessels are to keep clear. The multipurpose vessels Ocean Dragon and Magellan Echo will carry out rectification works infield during the week involving diving operation during which a 500m safety zone is established and vessels are to keep clear. The Array cable installation Ship Normand Flower will complete mobilization at Sheerness and will deploy to site. Whilst construction is taking place, a 500m safety zone is established and vessels are to keep clear. The two Cable crossings between the London Array export cable and the Kentish Flats export cable and the Britned cable, are guarded by the guard vessel "Sorrento". The vessel Coastal Worker assisted by the Sara Maatje 6 will be carrying on with export cable burial in the Swale and at the Kentish Flats cable crossing. During these operations a 500m safety zone is established, and vessels are to keep clear. The vessel Nova K, will be undertaking survey and PLGR work on the array cable routes. Name & Registered Office: London Array limited, Westwood Way, Westwood Business Park, Coventry CV4 8LG. Company no. 04344423

The vessel 'Sea Weasel' will be undertaking Marine Mammal Observation duties, prior to and during piling operations. Construction site guard vessel duties will be covered by the Mary Ann 1. Crew boats Marian Array, Smeaton Array, Conwy Bay, Towyn Bay, Cemaes Bay, Svend T, MPI Rucio, Cwind Alliance, Cwind Athenia, MCS Maestro, Transporter, Distributor, Voyager, Bayard 1, Bayard 2, Bayard 3, Bayard 4, Cathrin, Windcat 4, Windcat 6, Windcat 7, Gardian 1, Gardian 3, Gardian 7, Gardian 8 Gardian 9, Windspeed 4, Dalby Humber, Dalby Tees, Dalby Esk and Cardinal P will take offshore technicians to the installed foundations and construction vessels, and perform personnel transfer duties. The Hotel ships Wind Ambition and Sea Discoverer are situated to the NE and SW of the construction site respectively and act as accommodation for offshore technicians working on foundations and WTG s. The vessel Waterfall, 'Valkyrie' and Coral Wind to undertake site survey work. 2. Vessel on site For details of vessels on site, see attached vessel data matrix. 3. Installations Structures installed: Sub-Station 1 & 2 foundation and topsides Name Position (WGS 84) Name Position (WGS 84) SS1 51 37.815N 001 26.209E SS2 51 36.148N 001 32.085E Sub-Station; SS1 and SS2, are illuminated and equipped with lights: Mo(U). Foundation Monopoles and transition pieces installed at the locations as listed below (128 installed). Those shaded in RED have had Wind Turbines installed. (Total - 46) No Name Position (WGS 84) No. Name Position (WGS 84) 1 C18 51 37.369N 001 25.191E 2 B17 51 36.738N 001 25.090E 3 F19 51 38.820N 001 26.475E 4 C19 51 37.599N 001 24.765E 5 H19 51 39.626N 001 27.631E 6 I17 51 39.582N 001 29.038E 7 L19 51 41.265N 001 29.899E 8 L20 51 41.481N 001 29.523E 9 F20 51 39.001N 001 26.048E 10 M20 51 41.902N 001 30.042E 11 D20 51 38.024N 001 24.612E 12 I18 51 39.812N 001 28.612E 13 K19 51 40.858N 001 29.328E 14 H18 51 39.405N 001 28.041E 15 M19 51 41.672N 001 30.468E 16 H17 51 39.192N 001 28.435E 17 I19 51 40.042N 001 28.186E 18 G14 51 38.077N 001 29.176E 19 I20 51 40.276N 001 27.753E 20 G15 51 38.307N 001 28.749E 21 G16 51 38.537N 001 28.323E 22 H16 51 38.945N 001 28.894E 23 F17 51 38.360N 001 27.327E 24 C17 51 37.138N 001 25.616E 25 G18 51 39.006N 001 27.482E 26 F18 51 38.590N 001 26.901E 27 E17 51 37.953N 001 26.757E 28 G19 51 39.228N 001 27.045E 29 E16 51 37.723N 001 27.183E 30 F16 51 38.130N 001 27.753E 31 B16 51 36.501N 001 25.473E 32 H15 51 38.714N 001 29.319E 33 K17 51 40.402N 001 30.164E 34 L17 51 40.805N 001 30.750E 35 G20 51 39.458N 001 26.619E 36 H20 51 39.865N 001 27.190E 37 E15 51 37.493N 001 27.609E 38 D14 51 36.855N 001 27.465E 39 C14 51 36.448N 001 26.895E 40 A13 51 35.400N 001 26.175E 41 D19 51 38.006N 001 25.335E 42 M18 51 41.428N 001 30.864E 43 D07 51 35.247N 001 30.433E 44 B13 51 35.811N 001 26.751E 45 E14 51 37.263N 001 28.035E 46 E18 51 38.183N 001 26.331E 47 L18 51 41.035N 001 30.324E 48 D15 51 37.086N 001 27.039E 49 F03 51 35.139N 001 33.290E 50 B15 51 36.271N 001 25.899E

51 H14 51 38.484N 001 29.746E 52 K20 51 41.100N 001 28.879E 53 F06 51 35.834N 001 32.004E 54 D17 51 37.535N 001 26.206E 55 G03 51 35.546N 001 33.860E 56 C15 51 36.678N 001 26.469E 57 I06 51 37.051N 001 33.723E 58 A14 51 35.634N 001 25.755E 59 G17 51 38.767N 001 27.897E 60 I15 51 39.122N 001 29.890E 61 H06 51 36.643N 001 33.123E 62 D16 51 37.316N 001 26.613E 63 G06 51 36.244N 001 32.601E 64 J15 51 39.530N 001 30.463E 65 F02 51 34.909N 001 33.716E 66 J06 51 37.452N 001 34.282E 67 J19 51 38.149N 001 33.019E 68 E06 51 35.422N 001 31.442E 69 E19 51 38.413N 001 25.904E 70 E07 51 35.652N 001 31.016E 71 J18 51 40.220N 001 29.185E 72 I05 51 36.821N 001 34.149E 73 E02 51 34.501N 001 33.146E 74 J20 51 40.681N 001 28.332E 75 K18 51 40.628N 001 29.754E 76 J17 51 39.990N 001 29.611E 77 F15 51 37.900N 001 28.179E 78 M17 51 41.212N 001 31.320E 79 H13 51 38.254N 001 30.172E 80 J16 51 39.760N 001 30.037E 81 B10 51 35.121N 001 28.029E 82 I16 51 39.352N 001 29.464E 83 F14 51 37.670N 001 28.605E 84 G13 51 37.847N 001 29.601E 85 A15 51 35.875N 001 25.410E 86 A10 51 34.713N 001 27.459E 87 A12 51 35.174N 001 26.607E 88 A11 51 34.944N 001 27.033E 89 D09 51 35.705N 001 29.595E 90 B11 51 35.351N 001 27.603E 91 D10 51 35.935N 001 29.169E 92 C10 51 35.528N 001 28.599E 93 B12 51 35.581N 001 27.177E 94 C12 51 35.988N 001 27.747E 95 C09 51 35.298N 001 29.025E 96 D11 51 36.170N 001 28.733E 97 C11 51 35.758N 001 28.173E 98 M15 51 40.752N 001 32.173E 99 M16 51 40.982N 001 31.747E 100 D12 51 36.395N 001 28.317E 101 C13 51 36.220N 001 27.324E 102 K15 51 39.954N 001 30.995E 103 D08 51 35.475N 001 30.021E 104 L16 51 40.575N 001 31.176E 105 K16 51 40.167N 001 30.607E 106 D13 51 36.625N 001 27.891E 107 E05 51 35.192N 001 31.868E 108 F07 51 36.059N 001 31.586E 109 L15 51 40.345N 001 31.602E 110 D05 51 34.785N 001 31.298E 111 D04 51 34.554N 001 31.724E 112 B08 51 34.659N 001 28.881E 113 C08 51 35.068N 001 29.450E 114 C07 51 34.838N 001 29.876E 115 E14 51 37.263N 001 28.035E 116 C06 51 34.607N 001 30.302E 117 D06 51 35.015N 001 30.872E 118 I14 51 38.892N 001 30.316E 119 J07 51 37.681N 001 33.856E 120 B09 51 34.891N 001 28.455E 121 I08 51 37.511N 001 32.871E 122 K11 51 39.017N 001 32.736E 123 L11 51 39.424N 001 33.306E 124 J09 51 38.149N 001 33.019E 125 J10 51 38.380N 001 32.593E 126 L12 51 39.654N 001 32.880E 127 M14 51 40.522N 001 32.599E 128 H10 51 37.564N 001 31.450E 129 I09 51 37.741N 001 32.447E 130 I10 51 37.971N 001 32.020E All Foundations are installed with Lights : Fl(Y) 2.5sec 2Nm Description of the foundations: Yellow cylindrical steel towers with a concrete platform on top. The unique ID number is displayed on signs spaced 120º. Each foundation is equipped with a solar powered amber light Fl(Y) 2.5 s 2nm. Array cables Installed 1 B17-C17 (1) 2 SS1-D19 (25) 3 K17-L17 (44) 4 SS1-E16 (47) 5 SS1-F18 (36) 6 SS1-D17 (30) 7 D17-C17 (31) 8 M18-L18 (48) 9 SS1-E19 (58) 10 D09-D10 (93) 11 B10-B11(100) 12 J17-K17 (43) 13 L17-M17 (45) 14 SS1-E18 (68) 15 F20-G20 (20) 16 F19-G19 (15) 17 D20-D19 (5) 18 B13-B15 (60) 19 J20-K20 (27) 20 C18-B17 (2) 21 E17-F17 (23) 22 D11-D12 (95) 23 H15-G15 (22) 24 G16-H16 (21) 25 F18-G18 (14) 26 E19-F20 (59) 27 G19-H19 (16) 28 E15-f15 (32) 29 F15-G15 (33) 30 H17-I17 (11) 31 SS1-E17(24) 32 H18-G18 (13) 33 H19-I19 (17) 34 H16-I16 (63) 35 G20-H20 (19) 36 K19-L19 (6) 37 E18-F19 (69) 38 M19-M20 (8) Some submarine cables are still unburied and exposed on the surface of the seabed.

Wave rider Buoys Identity Lat (WGS 84) Long (WGS 84) Light Knock Deep (North) 51º 36.96 N 001º 30.31 E Fl (5) Y 20s 2nm Knock Deep (South) 51 35.00' N 001 29.93' E Fl (5) Y 20s 2nm The wave rider buoys are protected by 2 guard buoys (Lt. Fl (5) Y 20sec 2nm) approximately 50 metres to the North and South of each wave rider buoy Description of wave rider buoys: Yellow spherical buoys, top transparent dome with solar panels and flashing light Description of guard buoys: Yellow spar buoys with flashing light and radar reflector. Knock Deep South Buoy off station and position marked with unlit orange buoy. Relevant plans to current activity A B C D E Name Contractors method statements and risk assessments Marine Coordination Procedure Notices to Mariners issued Marine Licence London Array Emergency Response Cooperation Plan (ERCOP) 4. Other notes Reduced clearances at the Kentish Flats and BritNed cable crossings. Kentish Flats cable crossings (51 25'.217N, 001 06'.033E). At these three crossings the typical sea bed level was -4m LAT. Due to the newly installed rock berm the depth in some areas is now -1.0m LAT. BritNed cable crossing (51 28'.583N, 001 17'.417E). At this crossing the seabed level varies from -6.5m LAT to -9m LAT. Due to the newly installed rock berm the depth in some areas is now -4m LAT. The start and end coordinates of the rock berm are given in the following table:- Crossing Latitude Longitude Easting Northing Kentish Flats From 51 25'.203N 001 05'.895E 367769.05 5698254.77 To 51 25'.252N 001 06'.169E 368088.74 5698335.72 BritNed From 51 28'.549N 001 17'.372E 381212.69 5704127.66 To 51 28'.599N 001 17'.457E 381313.32 5704217.47 See Overview at end of this document WGS84 - UTM Zone: 31N Safe distance Whilst installation is ongoing at the individual positions a 500m radius safety zone is established around the installation upon which the construction vessel is installing or maintaining. The only vessels permitted to enter and remain in the safety zone are vessels involved in activities related to construction and major maintenance works. Mariners should be aware that anchor lines can extend from the construction vessels for distances greater than 500m. During the construction period of the wind farm, a 50m radius safety zone is established around each wind turbine, offshore sub-station platform and associated foundation structures, installed, complete or incomplete (until commissioned as part of the London Array Offshore Wind Farm). All vessels are reminded that the J-tube/Bell Mouth configuration extend several meters out from the TP perimeter. All vessels should proceed with caution when approaching the foundations. A number of wet store locations are established at the constructions site. The areas are used for storing anchors and connected pennant buoys when not in use. Positions of wet stores or other obstacles can be obtained from Marine Coordinators office or the onsite guard vessel

The Guard vessels (Mary Ann 1 and Sorrento) are in place at the offshore construction site and the export cable crossings, - the vessels can be contacted at all times on VHF Ch16 & 69. The address of the Construction Management office is: London Array Ltd. Construction Management, Port of Ramsgate, Military Road, Ramsgate, CT11 9LG, UK The Marine Coordinators office is manned on a 24hr basis and can be contacted on +44 07920854358 or londonarraytraffic@dongenergy.dk A Kingfisher flyer has been issued, showing the details of the planned offshore installations. The flyer can be downloaded from www.londonarray.com, and will be handed out through the Fishery Liaison Officers and others. A flyer for the yachting community on the reduced water depth at the cable crossing has been issued. The flyer can be downloaded from the LAL website Latest Notice to Mariners published UKHO Notice to Mariners No 0849/2011 Precautionary note on the construction of London Array Wind Farm and 2448/2011 - Temporary withdrawal of Foulgers Gat buoys---- 3191(P) London Array Offshore Windfarm to the Swale. Cleve Marshes. Submarine power cables. 0622/2012 Obstructions, reduced depths (Rock berms) 0930/2012 Obstructions, reduced depths. Port of London Notices to Mariners No. L2. Issued 10/01/11, and L18. Issued 15/09/11, London Array export cable laying operations. No. L3 2012 Issued 13/01/2012: Installation of second export cable. Medway Ports Notice to Mariners - No.26-2011 Issued 23/09/11: Swale Channel - London Array Export cable pull in arrangements. No.30 Issued 18/10/2011: East Swale - London Array Export cable pull in arrangements. No 31 Issued 28/10/2011: East Swale - London Array Export cable pull in arrangements. Notice No 5 issued 13/01/12 London Array East Swale cable pull in. Notice 6 issued 31/01/12 Swale Location of anchors for Stemat Spirit. Trinity House Notice to Mariners No 24/2011 C9 - Foulgers Gat removal of buoyage and navigation of Foulgers Gat not recommended. No 7 2012 Swale temporary relocation of buoys Distribution of this Notice. - The distribution of this notice is as per email recipient's header. If you are not the appropriate recipient of these notices, or do not wish to receive the notices in the future, please contact us at the address at the head of this notice or reply to this email. Report made by: Marine Coordinator Anker Lauritsen Email: londonarraytraffic@dongenergy.dk Phone: +44(0)7909414690 or +45 31727585 Attachments Chartlet of foundations installed, (At the end of this document) Lay out of wind farm. (At the end of this document) Spread sheet of vessels. (Separate attachment to this e-mail) Chartlet of installed foundations, WTGs and array cables (note this was publised 27/04/12)

Layout of London Array Offshore Wind Farm, and Export cable route