Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP February 17, 2014 Volume 2, Issue 56 Doug s Corner SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In this issue: Doug s Corner 1 2 Traffic/Active Work 3-4 s 5-12 Project App 13 1
Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP Doug s Corner My Week in Pictures https://www.facebook.com/ doug.ststevens See additional Northwest Extension photos on Doug s Facebook Page Use your Smartphones QR reader below... 2
Contractor s Weekly Update Work activities/traffic control week of 2/17/2014 Dunlap Intersection Dunlap Ave one lane both East and Westbound w/ left turn lanes (24 hrs.) Roadway widening, Install duct bank (train communications), Century Link vault, Raise manholes to grade Dunlap to Butler One lane both north and southbound will be maintained as well as turns at the signalized intersections Traffic signals, Curb, gutter, sidewalks, catch basins, drill and set OCS foundations, guideway curb Roadway Widening phase 1 page 5 and 6 19th Avenue and Townley, Alice, Orchid and Seldon Closures Page 7 Butler to Northern Huge turnout at the Love Our Community event held at the Open Door Fellowship Church One lane both north and south bound will be maintained as well as turns at the signalized intersections Water, sewer, gas Los Palmaritas/El Caminito closures page 8 Northern Intersection 2/24 3/21, Night Work 7pm 5am: One lane both east and west bound with no left turn pockets. Water work Northern to Orangewood One lane both north and south bound will be maintained as well as turns at the signalized intersections Century Link, private irrigation removals, sewer, joint trench, gas, SSW brought out a few pieces of equipment the kids had the opportunity to sit in with the help of staff Frier closed 2/11 thru 2/19/14 page 9 3
Contractor s Weekly Update Work activities/traffic control week of 2/17/2014 Orangewood to Glendale One lane both north and south bound will be maintained as well as turns at the signalized intersections Joint trench, water, overhead conversions, street lights, gas (night work) Glendale Intersection One lane both north and south bound will be maintained as well as turns at the signalized intersections 7pm-5am 2/24 3/14, one lane both east and west bound w/ left turn lanes. Glendale to Maryland One lane both north and south bound will be maintained as well as turns at the signalized intersections Water, SRP Irrigation Removals, storm drain Crews forming an Overhead Cantanary Pole Foundation and double checking the tolerances Closures (West) Lawrence, Ocotillo, and Tuckey page 10 Maryland to Bethany Home Road One lane north and southbound for waterline work. Turn movements will be maintained 2/17 thru 2/21/14 Water, SRP irrigation removals, sewer removals Rovey closed 2/10 thru 2/24 (extended) page 11 Bethany Home Road Intersection BHR one lane both East and Westbound turns maintained 2/17 2/21. Then switch to nights restrictions 2/24. No day restrictions starting 2/24. Bethany Home Road to Montebello One lane both north and south bound will be maintained as well as turns at the signalized intersections Crews pouring the Traction Electrification ductbank that will feed the light rail with the overhead power 4
Northwest Extension Outreach Coordinators Carla Kahn (623) 261-2605 Jessica Blazina (602) 510-5491 19th Ave Restrictions: Dunlap to Alice Underground Utilities and Roadway Widening Traffic Restrictions: December 6, 2013 - February 28, 2014 1 Access off 19th Ave will remain open for Circle K at all times 1 Access off 19th Ave will remain open for El Monte Plaza at all times On 19th Ave,1 lane both Northbound and Southbound be maintained with left turn lanes at Dunlap and Butler Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at For more information on the NW Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 5
Northwest Extension Outreach Coordinators Carla Kahn (623) 261-2605 Jessica Blazina (602) 510-5491 19th Ave Restrictions: Alice to Butler Underground Utilities and Roadway Widening Traffic Restrictions: December 6, 2013 - February 28, 2014 1 road will remain open at all times for access onto the 19th Ave Frontage Road. On 19th Ave,1 lane both Northbound and Southbound be maintained with left turn lanes at Dunlap and Butler Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at www.valleymetro.org/northwest For more information on the NW Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 6
Northwest Extension Carla Kahn Outreach Coordinator (623) 261-2605 19th Avenue and Townley, Alice, Orchid and Seldon Closures Roadway Widening Townley Avenue, Alice Avenue, Orchid Lane and Seldon Lane will be closed intermittently for sewer line removal. Traffic Restrictions: July 26 to June 1, 2014: 24 Hour Closures (Townley plus 1 of the other 3) No right turn from 19th Avenue (northbound) No left turns from 19th Avenue (southbound) For alternate access use Orchid or Alice Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at www.valleymetro.org/ northwest For more information on the Northwest Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 7
Northwest Exten- Outreach Coordinators Carla Kahn (623) 261-2605 Jessica Blazina (602) 510-5491 19th Avenue-Las Palmaritas/El Caminito Closures Utility Relocations Beginning 2/5/2014 thru 2/28/2014 both Las Palmaritas and El Caminito will alternate closures. When one is closed SSW will make sure the other is open and has clear access. This first pieces of work for these closures will be sewer install and removals of the old lines. If you have any questions please do not hesitate to call or Jessica Blazina. Thank you all for your patience! www.valleymetro.org/northwest For more information on the Northwest Light Rail Extension, please visit: 8
Northwest Exten- Outreach Coordinators Carla Kahn (623) 261-2605 Jessica Blazina (602) 510-5491 19th Avenue and Frier Closure Storm Drain Installation Traffic Restrictions February 11 to February 19, 2014: 24 Hour Closure No right turn from 19th Avenue (northbound) No left turns from 19th Avenue (southbound) For alternate access use Augusta Ave or Morten Ave Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at www.valleymetro.org/northwest For more information on the Northwest Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 9
Northwest Extension Carla Kahn Outreach Coordinator (623) 261-2605 Lawrence, Ocotillo and Tuckey Closures at 19th Avenue Utilities Installation During the Utilities (underground) construction portion of the project, the above streets will be closed periodically. Only one road to be closed at a time. 2 roads or all 3 roads will never be closed simultaneously Use 21st Ave as access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at www.valleymetro.org/northwest For more information on the Northwest Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 10
Northwest Extension Outreach Coordinators Carla Kahn (623) 261-2605 Jessica Blazina (602) 510-5491 Rovey Closed at 19th Ave Water Installation 24 hour closure Traffic Restrictions: February 10th to February 24th 2014 EXTENDED No right turn from 19th Ave northbound No left turn from 19th Ave southbound For alternate access use Rose Lane to N 18th Dr. or Bethany Home Rd to N 18th Ave. Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, For more information on the Northwest Light Rail Extension, please visit: www.valleymetro.org/northwest Facebook/METROrailconstruction 24-Hour Project Hotline: 602-254-RAIL (7245) 11
Contractor s Weekly Update Project App 12