1 Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP March 11th 2013 Volume 2, Issue 7 Doug s Corner This week I got to spend some time in the field with the City of Phoenix traffic signal department. I would like to speak about the temporary traffic signals and why they are so important. Some very good questions came to mind and below I will do my best to convey the importance of this portion of our project. SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In order for us to work efficiently and to make it easier on the public, we have to look at the whole picture. Most are aware that there are temporary traffic signals but most don t know why its so important or even necessary. I will explain why. In order to start construction on the actual light rail itself, we need to widen the roads to make room for the track. To accommodate, the widening, the existing traffic signals must be moved back. Here s how it works. We put in the temporary traffic poles, then we run span wires (above ground) and traffic signal cables to each pole. Then we place the traffic signal heads just right so that oncoming traffic can easily see the light. These traffic signal heads are also easy to move as we continue to work on the project and it makes the process move a lot faster. We then remove the old traffic poles and signal heads. By doing this now, it saves us time and avoids any complications in the future. City of Phoenix installing traffic signal cabling on the span wire at 19th Ave and Butler Drive Normally, there are sensors in the roads which change the lights accordingly. In order to keep this system functioning, we have strategically placed cameras to sense that a car is in a left turn lane. This is important to the public because this minimizes traffic and reduces long wait times. In this issue: Page 1 Doug s Corner Page 2-3 Traffic Restrictions Work activities Page 4-7 Construction Notices This piece of work is critical not only for us, but for the public as well. Why? This allows us to move these signals out of our way so we can expand the road with ease. By having the traffic signal wires above the ground, it will help prevent any accidental or unplanned signal outages which will help keep traffic moving properly. The City of Phoenix traffic signal department is working hard to make sure that traffic runs smoothly through this project. It is their duty to work safely and efficiently, and they have been doing a great job! This week in the traffic section of the update I will continue listing the lane restrictions in each 1/2 mile in a little more general terms. I know that from my meetings I have had with some of you, it would be better to discuss what phase we are in (utility, roadway,track, etc.) It can be misleading to give a date to an item and then have 4 or 5 other crews fall in after. Water crew #1 will continue working nights as well as the sewer crew. Next week we will be adding a storm drain crew. The work they are performing have intrusive traffic setups near intersections which are better done at night. As we approach the summer months we will continue to add crews to nights. I expect we have 200 plus crew members by summer working both day and night in order to support the large amount of work and aggressive schedule. As the various utility lines cross the smaller, non signalized streets, these will open and close throughout the utility phase of the project. We will keep these in the traffic/work items section and give the best dates we can as we approach the intersections. Weather, unknowns below the surface, and various other factors obviously make an exact target date challenging at best. The signalized intersections will have a separate notice that goes out as this needs to reach farther than the local neighborhoods. Thanks...and enjoy the spring training games this weekend!! Doug 1
2 Work activities/traffic control week of 3/11/2013 Dunlap 7 PM to 5 AM Waterline lateral crossings on Dunlap west of 19th Ave will continue. One lane both East and Westbound on Dunlap. No Left turns will be placed East and Westbound, with the exception of Bus traffic. Sewer lateral work will continue working nights within the above time frames. Valley Metro Buses will be assisted with left turns by an officer from 7 PM to 10:30 PM. Dunlap to Butler Wet utility work continues throughout this reach. One lane both north and south bound will be maintained as additional wet utility work begins. Crews will work with business in order to maintain access. The intersection of Dunlap and 19th Avenue will be restricted to one lane both north and southbound as well as turns. Alice Road will be closed to help facilitate the installation of new private irrigation. See the attached map on page 4. Butler to Northern One lane both north and south bound will be maintained as well as turns at the signalized intersections. Locate existing utilities ahead of the water and sewer work. Water transmission main installation. A walkway designed with water barrier will provide pedestrian access. Northern to Orangewood One lane both north and south bound will be maintained as well as turns at the signalized intersections. Private irrigation Water transmission main Gas main 16 water line installation at Tuckey Lane 2
3 Work activities/traffic control week of 3/11/2013 Orangewood to Glendale One lane both north and south bound will be maintained as well as turns at the signalized intersections. Water transmission main installation. A walkway designed with water barrier will provide pedestrian access. W. Palmaire Ave will be closed to help facilitate the installation of new water line. See the attached map on page 5. Glendale to Maryland One lane both north and south bound will be maintained as well as turns at the signalized intersections. 7 PM to 6 AM storm drain installation begins. There will be no left hand turns heading north or southbound from Glendale Ave to Ocotillo Road. See the attached map on page 6. Ocotillo Road will continue to be closed to help facilitate the installation of new storm drain. See the attached map on page 7. Tree/Shrub Removal Maryland to Bethany Home Road One lane both north and south bound will be maintained as well as turns at the signalized intersections. SRP joint trench. Temporary traffic signal will be installed at the Bethany Home and 19th Ave. intersection. From 7AM to 4 PM one lane in each direction will be maintained as well as left turns at the Bethany Home intersection. 18 sewer line installation at Butler Drive. 3
4 4
5 5
6 6
7 7
Doug s Corner. Contractor s Weekly Update. In this issue: NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP SSWJV. Page 1-2.
Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP May 27th 2013 Volume 2, Issue 18 Doug s Corner SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In this issue: Page
More informationDoug s Corner. Contractor s Weekly Update. In this issue: NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP SSWJV SAFETY QUALITY COURTEOUS
Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP April 21, 2014 Volume 2, Issue 65 Doug s Corner SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In this issue: Doug
More informationDoug s Corner. Contractor s Weekly Update. In this issue: NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP SSWJV SAFETY QUALITY COURTEOUS
Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP February 17, 2014 Volume 2, Issue 56 Doug s Corner SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In this issue:
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE. February 2nd, 2015 Volume 2, Issue 107.
CONTRACTOR S WEEKLY UPDATE February 2nd, 2015 Volume 2, Issue 107 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-5 Construction Notices.6-10 Project
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP December 29, 2014 Volume 2, Issue 102 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP January 19, 2015 Volume 2, Issue 105 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More informationScarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017
Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 PROJECT LOCATION 2 SCARLETT ROAD BRIDGE Constructed in 1912, the bridge carries 4 active
More information^Lee County Jt Sotft^West T:foH^a Lee County
^Lee County Jt Sotft^West T:foH^a Lee County Department of Transportation 1500 Monroe Street FortMyers,FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE August 11th through August 17th, 2016
More informationIL Route 71 Construction Update
100 Parkers Mill Oswego, IL. 60543 (630) 554-3618 4.20.16 IL 71 TRAFFIC ADVISORY: Tentatively scheduled for April 21st A new traffic pattern from Paradise to Wolf Crossing on IL 71 will be in use. The
More informationCITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES
CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new
More informationINGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI
INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:
More information^ Lee County ^OU fewest T:foH^ Lee County
^ Lee County ^OU fewest T:foH^ Lee County Department of Transportation 1500 Monroe Street FortMyers,FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE August 18th through August 24th, 2016 Ben
More informationBlair/Williamson Intersection Expressed Needs
Blair/Williamson Intersection Expressed Needs NORTH Blair Street is a barrier for pedestrians and bicycles Relocate Capitol City Trail crossing from Blair Street and John Nolen Drive intersection to Williamson
More informationAppendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station
Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,
More informationTempe Streetcar Public Meeting
Tempe Streetcar Public Meeting April 19, 2017 Agenda Project Background and Status Design Progress Streetcar Stops Art Program Streetcar Vehicles Mill Avenue Configuration Utility Relocation 2 Route and
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: November 9, 2018 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction & Traffic Highlights
More informationEliminate on-street parking where it will allow for a dedicated bus only lane %
Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136
More informationSTAKING TRAFFIC CONTROL SIGNAL SYSTEMS
Locating the components of a traffic control signal is not an exact science; many factors influence the location of the components. These factors include: lane widths, radii, pedestrian curb ramp requirements,
More informationWhy invest in the 1 Street S.W. Corridor?
Why invest in the 1 Street S.W. Corridor? This project is an investment in the Beltline Community and Calgary s economy. It is anticipated that The City s investment along this corridor will help with
More informationLegislative Update Williamsburg Residency
Hampton Roads District Legislative Update Williamsburg Residency Jim Brewer, Resident Administrator 757-253-5140 Projects Under Way Warwick Boulevard Project http://www.warwickboulevard.org/ Contractors:
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE November 10 th, through November 16 th, 2016 Alico & Gator Road Intersection
More informationDesign Criteria. Design Criteria
F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road
More informationA number of inferences have been drawn from the observations, each of which is discussed below.
Technical Memo To: Steve Gramm, Study Advisory Team From: Rick Laughlin Project: I-190/Silver St. CC: Date: 4/4/2011 Job No: RE: Special event observation HDR conducted an observation of special event
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax RoadWatch Update December 6 December 12, 2018 South Pointe Boulevard & College Parkway:
More informationWork Session. Agenda Item # 4. Meeting Date September 8, Daryl Braithwaite Public Works Director. Prepared By. Suzanne R. Ludlow City Manager
Agenda Item # 4 Work Session Meeting Date September 8, 2015 Prepared By Approved By Daryl Braithwaite Public Works Director Suzanne R. Ludlow City Manager Discussion Item Background Temporary Neighborhood
More informationKalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission
FOR IMMEDIATE RELEASE Date: October 31, 2014 Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission Kalamazoo, MI- In a collaborative effort
More informationHospital Link Project Project Update September 2017
Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationPurple Line Extension. La Brea Decking Phase II Bus Detours Metro 720/20, 212/312 LADOT DASH Fairfax, Antelope Valley Transit
Purple Line Extension La Brea Decking Phase II Bus Detours Metro 720/20, 212/312 LADOT DASH Fairfax, Antelope Valley Transit La Brea Station Decking Schedule *Dates and work activities subject to change
More informationFitting Light Rail through Well-established Communities
Fitting Light Rail through Well-established Communities San Francisco 2008 Michael D. Madden Chief, Project Development, Maryland Transit Administration Project Setting Located inside the Capital Beltway
More informationWelcome to the Quebec Alternatives Analysis Public Meeting
Welcome to the Public Meeting Please sign in. Public Comment Please fill out a comment card and tell us what you think. Check back or comment any time at: www.quebecalternatives.com Project Area Technical
More informationReplacement of N. Carlin Springs Road Bridge over George Mason Dr.
Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans February 2017 Project Elements Removal of existing bridge
More informationNon-Motorized Transportation 7-1
Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel
More informationCalifornia Department of Transportation, District 4. Sloat Boulevard Project Skyline Blvd. to 19 th Ave. Community Update January 13, 2016
California Department of Transportation, District 4 Sloat Boulevard Project Skyline Blvd. to 19 th Ave. Community Update January 13, 2016 Agenda Welcome and introductions Project overview, history and
More informationTRAVEL PLAN: CENTRAL EUROPEAN UNIVERSITY CAMPUS REDEVELOPMENT PROJECT TRAVEL PLAN. Central European University Campus Redevelopment Project.
TRAVEL PLAN Central European University Campus Redevelopment Project Page 1 Table of Contents Introduction... 3 Background... 7 Building Users... 7 Transportation in Community Consultation... 7 Summary
More informationMission-Geneva Transportation Study Community Workshop 2 July 8, 2006
Community Workshop 2 July 8, 2006 Small Group Workbook 1 Basic Improvements on Mission Street Streetscape. Pedestrian-scale lighting; landscaping; community art on utility boxes; more (possibly unique)
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More informationCHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems
CHAPTER 8 STAKING STAKING Correct staking of traffic control signal or lighting systems is critical to the appropriate placement of system components. 8.1 Traffic Control Signal Systems Locating the components
More informationCreating the Future Bruce B Downs Blvd
Creating the Future Bruce B Downs Blvd How things look today May not be how things look in the future. Bruce B Downs PD&E Study 2003 Construction programmed 2009, Palm Springs to Pebble Creek Tampa Rail
More informationSANTA MONICA BOULEVARD CORRIDOR
CIRCULATION ELEMENT WHITE PAPER NO. 3 SANTA MONICA BOULEVARD CORRIDOR INTRODUCTION From the 1930s to the beginning of Los Angeles freeway era, Santa Monica Boulevard, (previously Route 66, the Beverly
More information4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL
4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL The Transportation Services Committee recommends the adoption of
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationAccommodating Pedestrians in the Work Zone
Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,
More informationCity of Seattle Edward B. Murray, Mayor
City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown
More information2016 Neighborhood Street Fund Application
2016 Neighborhood Street Fund Application 2016-109 #146 COMPLETE Collector: Web Link 1 (Web Link) Started: Sunday, April 17, 2016 2:29:58 PM Last Modified: Sunday, April 17, 2016 2:36:28 PM Time Spent:
More informationMeadow Woods Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Meadow Woods Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationPROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT
PROJECT NO. 093 MA 199 H 5807 01C FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENI HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT (INTERSECTION IMPROVEMENT) US 93/US 60 FINAL PROJECT ASSESSMENT April
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE October 12 October 18, 2017 Gunnery Road and 8th Street SW Intersection
More information5 Transit & Traffic. Overview
5 Transit & Traffic Overview Montgomery Place s roadways and overall traffic circulation are unique in the city due to the narrow streets and avenues with boulevards; however, no sidewalks or curbs in
More informationMASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018
MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018 AGENDA Introductions Project Benefits Progress to Date Schedule for Remaining Work Phase 3 Activities, Impacts & Traffic Detours Phase 4 Activities
More informationMINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY
MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY INTRODUCTION City Personnel Sign-in Sheet Comment Forms Please Write Down Any Feedback INTRODUCTION List of Topics for Presentation Study
More informationMcLEAN CITIZENS ASSOCIATION
McLEAN CITIZENS ASSOCIATION RESOLUTION DULLES RAIL SUPPLEMENTAL EIS With ATTACHMENT A - PEDESTRIAN AND BICYCLE ACCESS ISSUES DULLES CORRIDOR RAIL STATIONS IN TYSONS CORNER (Charts - 7 pages) Approved by
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax RoadWatch Update December 13 December 19, 2018 Alico Road Widening from Ben Hill Griffin
More informationWindy Ridge Elementary School
Windy Ridge Elementary School SCHOOL ROUTE PLAN For WINDY RIDGE ELEMENTARY SCHOOL LOCATION 54 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationCapital Beltway HOT Lanes Project
New Travel Choices Ahead Capital Beltway HOT Lanes Project Update January 2011 Major Milestones Reached in 2010 Project is 55% complete New bridge spans completed at every interchange; Second phase well
More informationJuly 9 Mom's the Bomb at Waseca Waterpark th Ave NE (Mom's get in free with a paid child's admission.)
MEMORANDUM DATE: July 7, 2017 TO: FROM: SUBJECT: Mayor & Council Members Mike Anderson, Assistant to the City Manager City Manager s Report Old TH HWY 14/Elm Ave Update *Please see attached document* Waseca
More informationRÉGION D OTTAWA-CARLETON
8 REGION OF OTTAWA-CARLETON RÉGION D OTTAWA-CARLETON REPORT RAPPORT Our File/N/Réf. Your File/V/Réf. 50 23-00-R030-H DATE 14 July 2000 TO/DEST. FROM/EXP. SUBJECT/OBJET Co-ordinator Transportation Committee
More informationInstitute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017
Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Northern Virginia
More informationComplete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA
Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,
More informationSan Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation
San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco Capital Needs In 2006, the Mayor and Board of Supervisors approved San
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton
More information2. executing a legal agreement with respect to the above.
2. MODIFICATIONS TO INNES ROAD AND BLAIR ROAD INTERSECTION TO ACCOMMODATE THE CONSTRUCTION OF THE INNES CENTRE - PUBLIC HEARING COMMITTEE RECOMMENDATION Having held a public hearing, that Council approve
More informationOrange Center Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Orange Center Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationTunnel Reconstruction Brooklyn CB 1 August 14, 2018
Tunnel Reconstruction Brooklyn CB 1 August 14, 2018 Reconstructing the Tunnel 2 Service During Tunnel Reconstruction April 2019 through July 2020 3 Projected Cross River Travel Paths of Customers The Service
More informationRoute 1 and Harrison Road Intersection Improvements
Route 1 and Harrison Road Intersection Improvements April 27, 2016 Randy McKinney, P.E. Virginia Department of Transportation, Fredericksburg District Area Construction Engineer Route 1 and Harrison Road
More informationC Line Rapid Bus Preliminary Station Design
C Line Rapid Bus Preliminary Station Design C Terrence Anderson, Community Outreach Coordinator Shawn Walding, Senior Engineer Metro Transit TAAC February 1, 2016 1 C Line project overview Substantially
More informationLee County Department of Transportation
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE New Updates & Revisions September 3 rd, through September 9 th, 2015
More informationWest Capitol Avenue Road Rehabilitation and Safety Enhancement Project
West Capitol Avenue Road Rehabilitation and Safety Enhancement Project Stakeholder Focus Group Meeting #2 Tuesday, August 28, 2018 7:00 8:00 a.m. West Sacramento City Hall 1110 West Capitol Avenue, West
More informationThe Consultation has now ended.
The Consultation has now ended. We have received Cabinet Member approval to undertake implementation of the Baker Street Two Way scheme. You are not viewing the most recent documentation. Please visit
More informationUniversity Avenue & Farley Avenue/University Bay Drive Area Scenario Base Conditions Multiple concerns
ped at signalized East of U-Bay North of Campus on Farley Ave./ U-Bay & Westbound Campus North of on Farley Ave./ U-Bay Near VA on MB1: Dual Eastbound Left-Turn Lanes Generally compatible with BRT and
More informationFMATS Transportation Improvement Program Project Nomination Form
FMATS 2015 2018 Transportation Improvement Program Project Nomination Form Project nominations are accepted from the public and are scored based on the adopted Project Scoring Criteria. These criteria
More informationADA on Construction. Guidance for Section C Plan Preparers
ADA on Construction Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However, good planning can minimize
More informationTerwillegar Drive Expressway Draft Concept Plan
Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction
More informationDESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS
DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS 4901 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax RoadWatch Update December 20, 2018 January 2, 2019 Alva Bridge & Big Carlos Pass Bridge:
More informationForest Hills Improvement Initiative
Forest Hills Improvement Initiative Transportation Action Plan Short Term Recommendations ONLY Final Draft as of April 30, 2008 For Community Review and Feedback Prepared for: The City of Boston Boston
More informationCopenhagen Cycling Map. Red Lines Cycling facilities
Copenhagen Cycling Map Red Lines Cycling facilities Copenhagen Cycling Facilities Design Approaches Transportation without Pollution Copenhagen s Strategy Where Cycling is one of the top key activities
More informationDuwamish Way-finding and CTR Report
V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail
More informationThe Northern Avenue Bridge is being replaced, and the city is debating just who will be allowed to use it
The Northern Avenue Bridge has been closed to vehicles since 1997 and to pedestrians since 2014. The Northern Avenue Bridge is being replaced, and the city is debating just who will be allowed to use it
More informationEXHIBIT R1. Neighborhood Cul-de-Sac Implementation
Neighborhood Cul-de-Sac Implementation The traffic study conducted for the Talaria project analyzed the amount of project traffic expected to use local, residential streets immediately north of the project
More information72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME. Public Information Meeting
72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME Public Information Meeting Project Goals About the Project The goal of this project is to address congestion along 72 Avenue and adjacent streets
More informationHidden Oaks Elementary School
Hidden Oaks Elementary School SCHOOL ROUTE PLAN For HIDDEN OAKS ELEMENTARY SCHOOL LOCATION 13 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationA-1 Arcadia with Signal
A-1 Arcadia with Signal Dakota St Variation: Half 3/4 with westbound left at Main 4 - Fewer downtown access points - Less efficient traffic operations - Highest project costs vanston. ote: traffic volumes
More informationWelcome. If you have any questions or comments on the project, please contact:
Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue
More informationHedgepeth Williams Middle School and Paul Robeson Elementary School Trenton, NJ. School Travel Plan
Hedgepeth Williams Middle School and Paul Robeson Elementary School Trenton, NJ School Travel Plan Hedgepeth Williams Middle School Description: Hedgepeth-Williams Middle School is located at 301 Gladstone
More informationPublic Involvement Outreach Requirements for Public Information Open House Meeting: C.N , HSIP-5003(12) 132 nd and West Center Road, Omaha
To: NDOR Environmental From: Randy McCart, HDR Date: 4 April 2017 RE: Public Involvement Summary Report, HSIP-5003(12) 132 nd and West Center Road, Omaha; C.N. 22629 Public Involvement Outreach Requirements
More informationPROJECT FACT SHEET May 25, 2018
SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient
More informationDepartment of Transportation 1500 Monroe Street. FortMyers,FL (239) (239) Fax ROAD WATCH UPDATE. July 19 - July 25, 2018
^Lee County Jt Southwest T:[o ln Onaa Lee County Department of Transportation 1500 Monroe Street FortMyers,FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE July 19 - July 25, 2018 Sanibel Bridge
More informationProject Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationLake Whitney Elementary School
Lake Whitney Elementary School SCHOOL ROUTE PLAN For LAKE WHITNEY ELEMENTARY SCHOOL LOCATION 18 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationWelcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.
BRIDGE REHABILITATION Welcome 53 Avenue Overpass over Whitemud Drive Rehabilitation Public Information Session Wednesday, March 9, 2016 4:30-8:00 p.m. Tonight you can: Learn about the 53 Avenue Overpass
More informationSouthwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.
Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW
More informationTunnel Reconstruction South 5 th Street Association October 16, 2018
Tunnel Reconstruction South 5 th Street Association October 16, 2018 Reconstructing the Tunnel 2 Service During Tunnel Reconstruction April 2019 through July 2020 3 Projected Cross River Travel Paths of
More informationControlled. Semi-Controlled PAGE 01 CHAPTER 12 INTERSECTIONS
PAGE 01 CHAPTER 12 INTERSECTIONS You will cross many intersections while driving. Intersections are especially dangerous because vehicles are crossing each other s driving path. Many crashes happen at
More informationMemorandum. Sunday, July 13, Saturday, July 19, 2014
Memorandum To: David Lowin, Brooklyn Bridge Park Corporation From: Daniel Schack, AICP, PTP Date: Re: Brooklyn Bridge Park Pier 5/6 Loop Road Traffic Study Project No: 14-01-2407 At the request of Brooklyn
More informationVehicular and Pedestrian Access to Herndon Metrorail Station. Robert B. Boxer, Director John Stuart, Clark Nexen October 28, 2015
Vehicular and Pedestrian Access to Herndon Metrorail Station Robert B. Boxer, Director John Stuart, Clark Nexen Project Location The project is located in the Town of Herndon along Herndon Parkway between
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 Item 31, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan
More informationLawrence Avenue Streetscape Concepts August 30, 2011
Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of
More informationALTERNATIVE A ONLY. Right Turn Only. BOTH ALTERNATIVES on southbound Mission from 23rd St to 25th St and on northbound Mission from 20th St to 23rd St
Proposal Detail: 22nd on southbound Mission from on both sides of Mission from to 23rd from at northbound Mission and 22nd St and at at northbound Mission and 23rd St Reconfigure Lanes ONLY No Parking
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax RoadWatch Update January 10-16, 2019 Summerlin Road & Colonial Blvd: Lee County DOT will
More information