TRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT

Similar documents
Harrah s Station Square Casino

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

Glenn Avenue Corridor Traffic Operational Evaluation

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Transportation Impact Study for Abington Terrace

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study

Troutbeck Farm Development

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Shockoe Bottom Preliminary Traffic and Parking Analysis

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017

THIS PAGE LEFT BLANK INTENTIONALLY

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning

King Soopers #116 Thornton, Colorado

Donahue Drive Corridor Traffic Operational Evaluation

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota

Traffic Impact Statement

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio

TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION

TRAFFIC ASSESSMENT River Edge Colorado

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas

Technical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams.

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...

Date: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study

Henderson Avenue Mixed-Use Development

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for:

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

PINESTONE TRAFFIC IMPACT STUDY Travelers Rest, South Carolina

MEMORANDUM. Matt Folden, AICP, MNCPPC Rebecca Torma, MCDOT. Nancy Randall, AICP, PTP Barbara Mosier, P.E., PTOE Kevin Berger

OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.

O HARA TOWNSHIP. O Hara Township Trail Feasibility and Planning Project, prepared by PBS&J TriLine, April 2005.

EXECUTIVE SUMMARY. Page 1 of 6

MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9

FINAL Albertville Business Park AUAR Update Traffic Study

QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

3.2.2 Proposed Road Network within Phase 1B Lands

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Traffic Study North Shore School District 112

Walton Acres at Riverwood Athletic Club Clayton, North Carolina

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.

Road Conversion Study Plumas Street

FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY

REDEVELOPMENT TRAFFIC IMPACT STUDY

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT

Draft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

Washington St. Corridor Study

Marina Loft (DRC 51-R-12)

Figure 1: Vicinity Map of the Study Area

TABLE TRAFFIC ANALYSIS SCENARIOS

Traffic Impact Analysis (TIA) Process and Procedures Manual. September 2017

FORM A PASCO COUNTY ACCESS CONNECTION PERMIT APPLICATION

Truck Climbing Lane Traffic Justification Report

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

DIMARCO CANANDAIGUA PROPERTIES HOUSING PROJECT CANANDAIGUA, ONTARIO COUNTY, NEW YORK

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for:

The proposed development is located within 800m of an existing Transit Station where infill developments and intensification are encouraged.

Grant Avenue Streetscape

Abrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677

Gateway Transportation Study

INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:

Subject: Solberg Avenue / I-229 Grade Separation: Traffic Analysis

ENKA INTERMEDIATE SCHOOL

Gene Dillon Elementary School Traffic Study Division Street Site

HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for:

DUNBOW ROAD FUNCTIONAL PLANNING

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.


STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine

TRAFFIC IMPACT ANALYSIS

Highway 111 Corridor Study

VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

Traffic Signal Optimization Project (Hosman Road) (Future Coordinated Corridor)

TRAFFIC STUDY GUIDELINES Clarksville Street Department

I-95 Northbound at US 1 (Exit 126) Design and Study Final Report

Magnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.

Michael A. Werthmann, PE, PTOE Principal

NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for:

Intersection Traffic Control Feasibility Study

4.0 TRAFFIC IMPACT STUDIES

APARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for:

9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd.

Date: 09/22/2016 Subject: To: From: PennDOT Engineering District 5-0. Dear Applicant,

TRAFFIC IMPACT STUDY CRITERIA

FINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM

Place Vanier 250 Montreal Road Transportation Impact Study Addendum. Prepared for Broccolini Construction September 20 th, 2012

ORLEANS GARDENS SHOPPING CENTRE 1615 ORLEANS BOULEVARD CITY OF OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for:

6060 North Central Expressway Mixed-Use Site Dallas, Texas

2016 Church Street Access Study. 100 Clinton Square 126 North Salina Street, Suite 100 Syracuse, NY

Meadowlake Ranch Traffic Impact Analysis (LSC #184600) August 27, 2018

Chapter 4 Traffic Analysis

Transcription:

November 2016 TRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT & Aspinwall Borough, Sharpsburg Borough & O Hara Township, Allegheny County, Pennsylvania Prepared for: Riverfront 47 LP 535 Smithfield Street Henry Oliver ing, Suite 2425 Pittsburgh, Pennsylvania 15222 Prepared by: Trans Associates Engineering Consultants, Inc. Robert E. Goetz, P.E. 4955 Steubenville Pike, Suite 400 Pittsburgh, Pennsylvania 15205

TABLE OF CONTENTS EXECUTIVE SUMMARY i PROJECT DESCRIPTION / DATA COLLECTION / EXISTING ROADWAY DESCRIPTION 1 Project Description 1 Data Collection 2 Existing Conditions 3 SITE TRAFFIC GENERATION AND DISTRIBUTION 6 Vehicular Trip Generation 6 Site Traffic Distribution 6 PROJECTED OPENING YEAR CONDITIONS 7 No (Base) Conditions 7 (Combined) Conditions 8 PROJECTED HORIZON YEAR CONDITIONS 9 No (Base) Conditions 9 (Combined) Conditions 10 ADDITIONAL ANALYSIS 11 Turn Lane Warrant and Storage Length Evaluation 11 Signal Warrant Evaluation 12 Queuing Analysis 13 Left Turn Phasing Evaluation 13 Sight Distance Evaluation-Site Access Intersections 14 CONCLUSIONS/RECOMMENDATIONS 14 TABLES Capacity Analysis Summary 1 Trip Generation Summary 2 Queue Analysis Summary 3 Sight Distance at Proposed Avenue Site Access 4 FIGURES Site Location 1 Site Plan 2 Study Intersections 3 2016 Existing Conditions Peak Hour Volumes 4 Phase 1 Primary Trip Distribution ( Avenue Access) 5A Phase 1 Primary Trip Distribution ( Avenue Access) 5B Full Development Primary Trip Distribution ( Avenue Access) 6A Full Development Primary Trip Distribution ( Avenue Access) 6B Phase 1 Pass-by Trip Distribution ( Avenue Access) 7A Phase 1 Pass-by Trip Distribution ( Avenue Access) 7B Full Development Pass-by Trip Distribution ( Avenue Access) 8A Full Development Pass-by Trip Distribution ( Avenue Access) 8B Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) 9A Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) 9B Phase 1 Pass-by Peak Hour Traffic Volumes ( Avenue Access) 10A Phase 1 Pass-by Peak Hour Traffic Volumes ( Avenue Access) 10B

FIGURES (cont d) Phase 1 Total Site Peak Hour Traffic Volumes ( Avenue Access) 11A Phase 1 Total Site Peak Hour Traffic Volumes ( Avenue Access) 11B Full Development Primary Peak Hour Traffic Volumes ( Avenue Access) 12A Full Development Primary Peak Hour Traffic Volumes ( Avenue Access) 12B Full Development Pass-by Peak Hour Traffic Volumes ( Avenue Access) 13A Full Development Pass-by Peak Hour Traffic Volumes ( Avenue Access) 13B Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) 14A Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) 14B Opening Year No Conditions Peak Hour Traffic Volumes 15 Rerouted River Avenue to Avenue Access Peak Hour Traffic Volumes 16 Elimination of Sunoco Peak Hour Traffic Volumes 17 Rerouted River Avenue to Avenue Access Peak Hour Traffic Volumes 18 Opening Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 19 Opening Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 20 Horizon Year No Conditions Peak Hour Traffic Volumes 21 Horizon Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 22 Horizon Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 23 Phase 1 Recommendations Avenue Access 24 Phase 1 Recommendations Avenue Access 25 Full Development Recommendations 19 th Street Access 26 Other Recommended Mitigation 27

TRANSPORTATION IMPACT STUDY FOR THE PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT Aspinwall Borough, Sharpsburg Borough & O Hara Township Allegheny County, Pennsylvania EXECUTIVE SUMMARY General Overview of the Development The 1.5 mile long, 47-acre site is located along the southern side of the Norfolk Southern railway and /, and the northern bank of the Allegheny River, between 13 th Street in Sharpsburg and River Avenue in Aspinwall, Allegheny County, Pennsylvania. The site currently includes Aspinwall s Riverfront Park, a marina and a former industrial area. Proposed development to occur in three phases consisting of a 14 acre park, 35 berth marina, 329 apartments, 192 townhouse /condominiums, 50,946 square feet of general office, 15,000 square feet of specialty retail, 5,000 square feet of high turnover (sit-down) restaurants and 186,000 square feet of research and development. Site access proposed from via a new at-grade crossing of the Norfolk Southern opposite Avenue in Aspinwall and via an existing underpass of the Norfolk Southern at 19 th Street from in Sharpsburg. As an alternative access to that proposed opposite Avenue, a new at-grade crossing of the Norfolk Southern was also studied along opposite Avenue in Aspinwall. List of Study Intersections / 8th Street / Ali Street* / reet* / reet / 18th Street / 19th Street / 21st Street* / Highland Park Bridge Ramps (SR 8082) / Highland Park Bridge Ramps (SR 8082) / Western Avenue* / Center Avenue* / Avenue / Proposed Site Access (Existing Sunoco) / Avenue / River Avenue* / Delafield Avenue* Delafield Avenue / 2nd Street * Indicates existing signalized intersection i

Trip Generation and Distribution Trip generation of the proposed development determined using rates and equations contained in the Institute of Transportation Engineers (ITE) publication Trip Generation Manual, Ninth Edition, 2012 for Land Use 220, Apartments, Land Use 230, Townhouse, Land Use 411, Public Park, Land Use 420, Marina, Land Use 710, General Office, Land Use 760, Research & Development, Land Use 826, Specialty Retail and Land Use 932, High-Turnover, Sit-Down Restaurant. Pass-by trip generation for the proposed high-turnover, sit-down restaurants determined using the PM peak hour rate contained in the ITE publication Trip Generation Handbook, Third Edition, 2014. A pass-by rate of 43 percent was used for the PM peak hour and a rate 10 percent less than the PM peak hour rate (33 percent) was used for the AM peak hour and the Saturday peak hour was used as no data for these peak hours is included in the Trip Generation Handbook, Third Edition. Anticipated Trip Generation of Full Development: Average Weekday: 7,830 Trip Ends AM Peak Hour: Entering 424 Primary / 10 Pass-By / 434 Total Exiting 365 Primary / 8 Pass-By / 373 Total Total 789 Primary / 18 Pass-By / 807 Total PM Peak Hour: Entering 343 Primary / 12 Pass-By / 355 Total Exiting 443 Primary / 8 Pass-By / 451 Total Total 786 Primary / 20 Pass-By / 806 Total Saturday Peak Hour: Entering 293 Primary / 12 Pass-By / 305 Total Exiting 277 Primary / 10 Pass-By / 287 Total Total 570 Primary / 22 Pass-By / 592 Total Primary trip distribution based on volumes at study intersections. Pass-by trip distribution based on individual observed peak hour volumes along Freeport Road/ at the site access intersections. Mitigation Measures to be Completed Concurrent with Development Phase 1 Preferred Avenue Access (See Figure 24) Construct a high volume local road crossing the Norfolk Southern at-grade to serve the site along opposite Avenue providing a left turn and through/right egress lane and a single ingress lane. This access is projected to serve approximately 3,000 trips per day. Note: The existing River Avenue access and at-grade crossing to be eliminated. Restripe at the access opposite Avenue to create a westbound left turn lane providing 170 feet of storage exclusive of taper. Widen at the access opposite Avenue to provide a right turn lane in the eastbound direction. The right turn lane should provide 220 feet of storage exclusive of taper. Note: The existing parking in this area to be relocated to an area within ii

the Sunoco station lot. Right-of-way will be needed from Norfolk Southern to construct this turn lane. Install a fully actuated traffic signal at the / Avenue / site access intersection. This signal should be coordinated with the adjacent signals along and provide protected/permitted left turn phases for the eastbound/westbound SR 1001 approaches and train preemption. Phase 1 Alternate Avenue Access (See Figure 25) Construct a high volume local road crossing the Norfolk Southern at-grade to serve the site along opposite Avenue providing a left turn and through/right egress lane and a single ingress lane. This access is projected to serve approximately 3,000 trips per day. Note: The existing River Avenue access and at-grade crossing to be eliminated. Restripe at the access opposite Avenue to lengthen the westbound left turn lane to provide 150 feet of storage exclusive of taper. Widen at the access opposite Avenue to provide a longer right turn lane in the eastbound direction. The right turn lane should provide 225 feet of storage exclusive of taper. Replace the signal at the and Avenue intersection with a fully actuated traffic signal. This signal should be coordinated with the adjacent signals along and provide protected/permitted left turn phases for the eastbound/westbound SR 1001 approaches and train preemption. Phase 1 Either Avenue or Avenue Access Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. Phase 2 and 3 Either Avenue or Avenue Access (See Figure 26) Stripe the 19 th Street underpass access at to provide left turn and right turn egress lanes back to the pier supporting the railroad overpass, and a single ingress lane. This access is projected to serve approximately 4,800 trips per day. Restripe at the 19 th Street access to create a westbound left turn lane providing 275 feet of storage exclusive of taper. Install a semi actuated traffic signal at the and 19 th Street access intersection. This signal should provide a protected/permitted left turn phase for the westbound SR 1001 approach and a right turn overlap for the 19 th Street approach. Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. iii

Other Mitigation Needed (See Figure 27) Install a semi actuated two-phase traffic signal at the and 16 th Street intersection. Note: This intersection satisfies warrants for the installation of a signal in the No condition. Install a fully actuated two-phase traffic signal at the and Highland Park Bridge Ramps intersection. Coordinate with signals along in Aspinwall. Note: This intersection satisfies warrants for the installation of a signal in 2016 existing conditions. PennDOT is currently performing a study of the Highland Park Bridge interchange at to determine if signals are needed. iv

TRANSPORTATION IMPACT STUDY FOR THE PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT Aspinwall Borough, Sharpsburg Borough & O Hara Township Allegheny County, Pennsylvania Trans Associates (TA) has completed this transportation impact study (TIS) for the proposed Riverfront 47 mixed use development to be constructed on a 1.5 mile long, 47-acre site located along the southern side of the Norfolk Southern railway and /, and the northern bank of the Allegheny River, between reet in Sharpsburg and River Avenue in Aspinwall, Allegheny County, Pennsylvania. The following sections of this report contain a: project description / data collection / existing roadway description; site traffic generation and distribution; projected opening year conditions; projected horizon year conditions; additional analysis; and conclusions and recommendations. PROJECT DESCRIPTION / DATA COLLECTION / EXISTING ROADWAY DESCRIPTION Project Description As shown in Figure 1, the proposed development is to be constructed between the Allegheny River and the Norfolk Southern railway, which is situated parallel to /, and extending from reet in Sharpsburg to River Avenue in Aspinwall. A portion of the ±47 acre site is presently occupied by Aspinwall s Riverfront Park and a marina. The park and marina are accessed via River Avenue, which intersects with at an unsignalized intersection located 140 feet west of the Avenue intersection. There is a second access to the site via 19 th Street in Sharpsburg, which intersects and is grade separated with the Norfolk Southern through an underpass. The majority of the site was previously used for industrial purposes, which have been largely removed. The development is proposed to occur in three phases. Phase 1 will contain the 14 acre park, a 35- berth marina, 49 apartment units, 175 townhouse/condominiums, 23,506 square feet of general office, 7,500 square feet of retail and a 2,500 square foot high-turnover sit-down restaurant at the eastern end of the site. Phases 2 and 3 will complete the site development and result in the following overall buildout: a 14 acre park, 35 berth marina, 329 apartments, 192 townhouse /condominiums, 50,946 square feet of general office, 15,000 square feet of specialty retail, 5,000 square feet of high turnover (sit-down) restaurants and 186,000 square feet of research and development. The site is zoned I-Industrial with a Riverfront Overlay in Sharpsburg, SM-Suburban Manufacturing in O Hara Township and AI-1-Limited Industrial / A-CD-Conservation in Aspinwall. Site access is proposed from via a new at-grade crossing of the Norfolk Southern opposite Avenue in Aspinwall and via an existing underpass of the Norfolk Southern at 19th Street from in Sharpsburg. As an alternative access to that proposed opposite Avenue, a new at-grade crossing of the Norfolk Southern was also studied along Freeport Road opposite Avenue in Aspinwall. The external access points would be connected internally via on-site roadways. A site plan that also identifies the phases of the proposed development is presented on Figure 2. 1

In accordance with a scope of study developed through discussions with representatives of the Pennsylvania Department of Transportation (PennDOT) Engineering District 11-0 at a scoping meeting held on September 26, 2016, the following intersections were selected for study: / 8th Street / Ali Street* / reet* / reet / 18th Street / 19th Street / 21st Street* / Highland Park Bridge Ramps (SR 8082) / Highland Park Bridge Ramps (SR 8082) / Western Avenue* / Center Avenue* / Avenue / Proposed Site Access (Existing Sunoco) / Avenue / River Avenue* / Delafield Avenue* Delafield Avenue / 2nd Street * Indicates existing signalized intersection A total of fourteen (14) intersections were studied. The study intersections with respect to the site are illustrated in Figure 3. The signed Transportation Impact Study Scoping Meeting Application is included in the Appendix. Data Collection Manual turning movement counts were performed by TA at each of the existing study intersections / driveways from 7:00 AM to 9:00 AM and from 4:00 PM to 6:00 PM, and on Saturday 3/12/16 from 11:00 AM to 2:00 PM, in May, June and October 2016. The weekday counts were performed when school was in session. The overall peak hours determined from these counts are as follows: AM Peak Hour 7:15 AM to 8:15 AM PM Peak Hour 4:30 PM to 5:30 PM Saturday Peak Hour 12:00 Noon to 1:00 PM The 2016 existing peak hour volumes determined from the turning movement counts are presented in Figure 4. Summaries of the data collected during the manual turning movement counts at each of the study intersections has been included in the Appendix to this report. TA also observed signal cycle lengths and phase split times at the study intersections during the peak hours. The observed signal cycle lengths and green times are included in the Appendix. Crash data for the study area was requested from the PennDOT Bureau of Highway Safety and Traffic Engineering and are included in a separately bound Crash Data Appendix. 2

Existing Conditions A field reconnaissance of the study area was conducted by TA to obtain information on roadway widths, roadway grades, and posted speed limits within the environs of each of the study intersections. The following provides a description of the study roadways. Unless otherwise identified, all roads are municipally owned. / Within the study area, SR 1001 is known as west of the Highland Park Bridge and east of the Highland Park Bridge. SR 1001 is a PennDOT minor arterial within the study area consisting of an 11 to 13 foot wide through lane in either direction. The cartway is predominantly curbed with a variable width from 32 feet in the Sharpsburg and Aspinwall business districts to 50 feet in the Highland Park interchange area. From 8 th Street to 10 th Street in Sharpsburg there is parallel parking on both sides of the street and 9.5 foot wide lanes. From 10 th Street to 23 rd Street there is parking along the southern side of. There is no parking within the Highland Park interchange area and an eastbound left turn lane for the northbound on ramp and a westbound right turn lane for the southbound on ramp to the Highland Park Bridge. There are also eastbound left turn lanes for the Western Avenue, Center Avenue, Avenue, Avenue and Delafield Avenue intersections. There is limited parallel parking along the northern side of near the Avenue intersection and angle parking along the southern side of between Center Avenue and River Avenue. The following provides the type of signal control by location, type of detection, number of phases and cycle length. Intersection Detection No. of Phases Cycle Length / 8 th Street / Ali Street Semi-Actuated 3 Phase Variable / 18 th Street Semi-Actuated 2 Phase Variable / 21 st Street Semi-Actuated 2 Phase Variable / Western Avenue Fully Actuated 3 Phase AM/PM-90 Sat-100 / Center Avenue Fully Actuated 3 Phase AM/PM-90 Sat-100 / Avenue Fully Actuated 2 Phase AM/PM-90 Sat-100 / Delafield Avenue Fully Actuated 3 Phase AM/PM-90 Sat-100 The four signals along in Aspinwall are currently operating in coordination while the signals in Sharpsburg operate in free mode. The posted speed limit of SR 1001 west of the Highland Park Bridge is 25 miles per hour (mph) and the posted speed limit east of the Highland Park Bridge is 35 miles per hour. There are three Port Authority of Allegheny County bus routes that serve the study corridor as follows: / : Route 1 and Route 91 Butler Street east of Highland Park Bridge: Route 75 Ellsworth There are between one and five buses on each route in each direction during the peak hours of study. The locations of bus stops and shelters are provided in the following descriptions. Ali Street/8 th Street Ali Street is offset from 8 th Street at by 50 feet. Ali Street is a dead-end street that provides an 11 foot wide approach lane to, an 11 foot wide receiving lane and 90 degree head-in parking along its eastern side. Eighth Street is one way southbound with a 10 foot wide approach lane to and parallel parking along both sides. 3

The signal at / 8 th Street / Ali Street provides separate phases for Ali Street and 8 th Street and a phase for. Neither Ali Street nor 8 th Street have a posted speed. There is a bus stop along at 8 th Street. 13 th Street 13 th Street provides a 24 foot wide cartway north of and parallel parking along the eastern side, and a 20 foot wide cartway south of with parallel parking along its eastern side. The approaches to are controlled with stop signs. There is a grade separated underpass of the Norfolk Southern south of that provides access to the Sharpsburg Islands Marina. There is no posted speed on 13 th Street. There is a bus stop along Main Street at 13 th Street. 16 th Street 16 th Street intersects the northern side of at a T intersection controlled with a stop sign. Sixteenth Street provides a 24 foot wide cartway and parallel parking along the eastern side. There is no posted speed on 16 th Street. There is a bus stop and shelter along Main Street at 16 th Street. 18 th Street 18 th Street is one way southbound and intersects the northern side of at a T intersection controlled with a traffic signal. Eighteenth Street provides a 24 foot wide cartway and parallel parking along both sides. There is no posted speed on 18 th Street. There is a bus stop along at 18 th Street. 19 th Street (south of ) 19 th Street intersects the southern side of at a T intersection controlled with a stop sign. Between and the Norfolk Southern underpass, 19 th Street provides a 43 foot wide cartway and parallel parking along the eastern side. The underpass of the Norfolk Southern is divided by piers and a median resulting in a single 19 foot wide northbound lane and a single 20 foot wide southbound lane. There is approximately 14 feet of overhead clearance under the underpass. There are sidewalks on both sides of 19 th Street and no posted speed. 21 st Street 21 st Street is one way southbound and intersects the northern side of at a T intersection controlled with a traffic signal. Twenty-first Street provides an 18 foot wide cartway and parallel parking along the western side. There is no posted speed on 21 st Street. There is a bus stop along at 21 st Street. Highland Park Bridge Ramps (SR 8082) Ramps to and from the southbound lanes of the Highland Park Bridge (SR 1005) intersect at a channelized intersection. Right turns from the off-ramp are controlled with a yield sign while left turns are controlled with a stop sign. Right turns from westbound to the on-ramp are free flow out of a dedicated lane. Right turns from eastbound enter the Highland Park Bridge on a separate ramp. There are no posted regulatory or advisory speed signs for the ramps except for the on-ramp from westbound which has a 15 mph advisory speed. Highland Park Bridge Ramps (SR 8082) Ramps to and from the northbound lanes of the Highland Park Bridge (SR 1005) intersect at a channelized intersection. Both right and left turns from the off-ramp are controlled with stop signs. Left turns from eastbound to the on-ramp have a dedicated lane. There is a separate ramp from the Highland Park Bridge to eastbound which is controlled with a yield sign. There are no posted regulatory or advisory speed signs for the ramps except for the on-ramp from the Highland Park Bridge to eastbound which has a 15 mph advisory speed. 4

PennDOT will be studying the Highland Park Bridge interchange with as well as the Route 28 interchange as part of the proposed reconstruction of these ramps and will evaluate the need for signalization at the Highland Park Bridge Ramps and. Western Avenue Western Avenue intersects the northern side of at a T intersection controlled with a traffic signal. Western Avenue provides a 28 foot wide cartway and parallel parking along both sides. The posted speed limit is 15 mph. There is a bus stop and shelter along at Western Avenue. Center Avenue Center Avenue intersects the northern side of at a T intersection controlled with a traffic signal. Center Avenue provides a 28 foot wide cartway. No parking is permitted in the block closest to. The posted speed limit is 15 mph. There is a bus stop along at Center Avenue. Avenue Avenue intersects the northern side of at a T intersection controlled with a stop sign. Avenue provides a 28 foot wide cartway with parallel parking permitted along the western side in the block closest to. The posted speed limit is 15 mph. There is a bus stop along at Avenue. River Avenue River Avenue intersects the southern side of at a T intersection approximately 140 feet west of the Avenue intersection. The River Avenue approach to is controlled with a stop sign. River Avenue provides a 16 to 20 foot wide cartway and crosses the Norfolk Southern at an at-grade crossing with flashing signals but no gates. River Avenue serves the Aspinwall Park and Marina, the Aspinwall Public Works facility and a Borough parking lot. There is no posted speed limit. Avenue Avenue intersects the northern side of at a T intersection controlled with a traffic signal. Avenue provides a 48 foot wide cartway with angle parking along the western side and parallel parking along the eastern side. The posted speed limit is 15 mph. There is a bus stop along at Avenue. Delafield Avenue Delafield Avenue intersects the northern side of at a T intersection controlled with a traffic signal. Delafield Avenue provides a 29 foot wide cartway with parallel parking along the western side. The posted speed limit is 25 mph. There is a bus stop and shelter along near Delafield Avenue. 2 nd Street 2 nd Street in Aspinwall intersects the western side of Delafield Avenue at a T intersection controlled via a three-way stop. Second Street provides a 25 foot wide cartway with parallel parking along the northern side between Delafield Avenue and Avenue. West of Avenue, 2 nd Street is one way eastbound with parallel parking along both sides. In addition to the intersection at Delafield Avenue, there is all-way stop sign control along 2 nd Street at Western Avenue, Center Avenue, Avenue, Avenue, Emerson Avenue, Virginia Avenue and Lexington Avenue. The posted speed limit is 15 mph. Photographs of the study roadways and intersections, along with copies of the traffic signal permit drawings for the signalized study intersections and sketches of the unsignalized intersections have been included in the Appendix to this report. Capacity calculations were performed for the existing study intersections using existing 2016 traffic volumes and conditions, and the observed signal timings for the weekday AM and PM peak hours, and the Saturday peak hour, using the methodologies published in the Highway Capacity Manual 5

2010, by the Transportation Research Board. This methodology determines how well an intersection, approach to an intersection, or movement at an intersection operates, and assigns to it a level of service (LOS) A through F, with LOS A representing the best operating conditions and LOS F, the worst. Detailed definitions of LOS have been included in the Appendix to this report. The results of the capacity calculations performed for existing conditions are summarized in Table 1. The results of the capacity analysis revealed that each of the study intersections currently operates at an overall intersection LOS D or better during each of the peak periods analyzed. Copies of capacity analyses performed for 2016 existing conditions are included in the Appendix to this report. Vehicular Trip Generation SITE TRAFFIC GENERATION AND DISTRIBUTION Vehicular trip generation for the proposed development was determined using the average rates and equations contained in the Institute of Transportation Engineers (ITE) publication Trip Generation Manual, 9th Edition, 2012 for Land Use 220 Apartments, Land Use 230, Townhouse, Land Use 411, Public Park, Land Use 420, Marina, Land Use 710, General Office, Land Use 760, Research & Development, Land Use 826, Specialty Retail and Land Use 932, High-Turnover, Sit-Down Restaurant. Although the mix of land uses could be expected to generate internal capture trips, that is, the interaction among land uses resulting in trips being made without using the off-site road system or by walking, this study conservatively did not assume any internal capture trips. Pass-by trips for the proposed high-turnover, sit-down restaurants in the proposed development were determined using the PM peak hour rate contained in the ITE publication Trip Generation Handbook, Third Edition, 2014. A pass-by rate of 43 percent was used for the PM peak hour. Since no pass-by trip data exists for the AM or Saturday peak hours, a rate 10 percent less than the PM peak hour was used. Therefore, a rate of 33 percent was used for the AM and Saturday peak hours. The total site generated trips for Phase 1 and the full development, including primary (new) and pass-by trips, are summarized in Table 2. Copies of the trip generation calculations are included in the Appendix to this report. Site Traffic Distribution The forecasted trips to be generated by the proposed development were then distributed through the study intersections. The overall distribution for primary trips was based on the volumes observed at the study intersections and major approach routes such as the Highland Park Bridge and Route 28 using PennDOT itms data. The distribution of pass-by trips for the restaurant portion of the development was based on the observed peak hour distribution of traffic on /Freeport Road. Since the Phase 1 development only assumes the access at Avenue or Avenue, and the full development assumes both the Avenue/ Avenue and 19 th Street accesses, separate distributions were developed for Phase 1 and the full development, as well as variations for the Avenue and Avenue accesses. The following figures present the primary and pass-by trip distributions for the Phase 1 and full development: Figure 5A - Phase 1 Primary Trip Distribution ( Avenue Access) Figure 5B - Phase 1 Primary Trip Distribution ( Avenue Access) Figure 6A - Full Development Primary Trip Distribution ( Avenue Access) 6

Figure 6B - Full Development Primary Trip Distribution ( Avenue Access) Figure 7A - Phase 1 Pass-by Trip Distribution ( Avenue Access) Figure 7B - Phase 1 Pass-by Trip Distribution ( Avenue Access) Figure 8A - Full Development Pass-by Trip Distribution ( Avenue Access) Figure 8B - Full Development Pass-by Trip Distribution ( Avenue Access) The aforementioned primary and pass-by distributions were applied to the Phase 1 and full development primary and pass-by trips in Table 2 to determine the forecasted primary and pass-by peak hour site traffic volumes for each access scenario. These volumes are shown as follows: Figure 9A - Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) Figure 9B - Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) Figure 10A - Phase 1 Pass-by Peak Hour Traffic Volumes ( Avenue Access) Figure 10B - Phase 1 Pass-by Peak Hour Traffic Volumes ( Avenue Access) Figure 11A - Phase 1 Total Site Peak Hour Traffic Volumes ( Avenue Access) Figure 11B - Phase 1 Total Site Peak Hour Traffic Volumes ( Avenue Access) Figure 12A - Full Development Primary Peak Hour Traffic Volumes ( Avenue Access) Figure 12B - Full Development Primary Peak Hour Traffic Volumes ( Avenue Access) Figure 13A - Full Development Pass-by Peak Hour Traffic Volumes ( Avenue Access) Figure 13B - Full Development Pass-by Peak Hour Traffic Volumes ( Avenue Access) Figure 14A - Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) Figure 14B - Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) PROJECTED OPENING YEAR CONDITIONS The proposed Phase 1 development is anticipated to be initially completed in ( opening year ). Therefore, traffic volumes were projected for the study intersections for opening year conditions. No (Base) Conditions Forecasted opening year no-build (base) traffic volumes for the weekday AM, weekday PM, and Saturday peak hours were determined by applying a background traffic growth rate of 1.05 percent per year, linear. This growth rate was obtained from the Southwestern Pennsylvania Commission (SPC) for Aspinwall Borough. It should be noted that of the three municipalities that the site is located in, Aspinwall has the highest traffic growth rate. Therefore, the background volumes may be considered to provide a conservative analysis. The peak hour background volumes are shown on Figure 15. For the no build-on conditions, a two phase signal was assumed at the and Highland Park Bridge ramps intersection. Capacity calculations were performed for forecasted opening year no-build (base) condition traffic volumes for the weekday AM, weekday PM, and Saturday peak hours. The results of the capacity calculations performed using forecasted opening year no-build (base) condition traffic volumes are summarized in Table 1. 7

The results of the capacity analysis performed using forecasted no-build (base) condition traffic volumes revealed that each of the study intersections are anticipated to operate at an overall intersection LOS D or better during each of the peak periods analyzed. Copies of capacity analyses performed for no build conditions are included in the Appendix to this report. (Combined) Conditions Forecasted opening year Phase 1 build (combined) traffic volumes for the weekday AM, weekday PM and Saturday peak hours were determined for preferred and alternative site access scenarios as follows: The preferred access scenario assumes a new at-grade crossing of the Norfolk Southern opposite Avenue in Aspinwall. This scenario assumes that the River Avenue access is eliminated and the Sunoco gas station along opposite Avenue is also eliminated. To adjust for the rerouting of existing River Avenue volumes to a proposed access opposite Avenue, the adjusted peak hour volumes shown in Figure 16 were applied to the background volumes. To account for the adjustments assuming the Sunoco was eliminated, see Figure 17. As an alternative access to that proposed opposite Avenue, a new at-grade crossing of the Norfolk Southern was also studied along opposite Avenue in Aspinwall. The adjusted volumes currently using River Avenue that would divert assuming an access opposite Avenue are shown in Figure 18. Forecasted opening year Phase 1 build (combined) traffic volumes for the weekday AM, weekday PM and Saturday peak hours assuming the Avenue site access were derived by combining the peak hour background volumes shown on Figure 15 with the adjustments shown on Figures 16 and 17, and adding the Phase 1 total site volumes shown on Figure 11A. The opening year Phase 1 combined volumes assuming the Avenue site access are shown on Figure 19. Forecasted opening year Phase 1 build (combined) traffic volumes for the weekday AM, weekday PM and Saturday peak hours assuming the Avenue site access were derived by combining the peak hour background volumes shown on Figure 15 with the adjustments shown on Figure 18, and adding the Phase 1 total site volumes shown on Figure 11B. The opening year Phase 1 combined volumes assuming the Avenue site access are shown on Figure 20. Capacity calculations were performed for forecasted opening year build (combined) condition traffic volumes for the weekday AM, weekday PM and Saturday peak hours for both access scenarios. For the opening year build conditions, the following was assumed for each access scenario: Avenue Access Scenario The River Avenue access is eliminated A westbound left turn lane is provided along for the proposed Avenue access; An eastbound right turn lane is provided along for the proposed Avenue access; and 8

A fully actuated traffic signal coordinated with adjacent signals is installed at and Avenue/proposed site access providing protected/permitted left turn phases for the eastbound/westbound approaches. Note: Turn lane and signal warrants are discussed in the Additional Analysis section. Avenue Access Scenario The River Avenue access is eliminated A westbound left turn lane is provided along for the proposed Avenue access; An eastbound right turn lane is provided along for the proposed Avenue access; and The traffic signal at and Avenue is modified/replaced with a signal providing protected/permitted left turn phases for the eastbound/westbound Freeport Road approaches. Note: Turn lane and signal warrants are discussed in the Additional Analysis section. The results of the capacity calculations performed using forecasted opening year build (combined) condition traffic volumes are summarized in Table 1. The results of the capacity analysis performed using forecasted build (combined) condition traffic volumes revealed that each of the study intersections are anticipated to continue to operate at an overall intersection LOS D or better during each of the peak periods analyzed with no intersection experiencing more than a 10 second overall increase in delay (not including unsignalized to signalized comparisons), provided that the following mitigation is implemented: Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. Copies of capacity analysis performed for build conditions are included in the Appendix to this report. PROJECTED HORIZON YEAR CONDITIONS In accordance with PennDOT policy and the TIS Scoping Meeting, conditions were analyzed for a future horizon year assuming full development. No (Base) Conditions Forecasted horizon year no-build (base) traffic volumes for the weekday AM, weekday PM and Saturday peak hours were determined by applying the SPC background traffic growth rate of 1.05 percent per year, linear, to the existing 2016 traffic volumes (Figure 4) to determine the background traffic volumes shown on Figure 21. Capacity calculations were performed for forecasted horizon year no-build (base) condition traffic volumes for the weekday AM, weekday PM and Saturday peak hours. The results of the capacity calculations performed using forecasted horizon year no-build (base) condition traffic volumes are summarized in Table 1. 9

The results of the capacity analysis performed using forecasted no-build (base) condition traffic volumes revealed that each of the study intersections are anticipated to operate at an overall intersection LOS D or better during each of the peak periods analyzed. Copies of capacity analysis performed for no build conditions are included in the Appendix to this report. (Combined) Conditions Forecasted horizon year build (combined) traffic volumes for the weekday AM, weekday PM, and Saturday peak hours were determined for both the Avenue access scenario and the Avenue access scenario. To adjust for the rerouting of existing River Avenue volumes to a proposed access opposite Avenue, the adjusted peak hour volumes shown in Figure 16 were applied to the background volumes. The adjustments also included assuming the Sunoco was eliminated, by applying the adjustments shown in Figure 17. Volumes for the alternative access scenario opposite Avenue in Aspinwall were derived by applying the adjusted volumes currently using River Avenue that would divert assuming an access opposite Avenue shown in Figure 18. Forecasted full build (combined) traffic volumes for the weekday AM, weekday PM and Saturday peak hours assuming the Avenue site access were derived by combining the peak hour background volumes shown on Figure 21 with the adjustments shown on Figures 16 and 17, and adding the full development total site volumes shown on Figure 14A. The full build combined volumes assuming the Avenue site access are shown on Figure 22. Forecasted full build (combined) traffic volumes for the weekday AM, weekday PM and Saturday peak hours assuming the Avenue site access were derived by combining the peak hour background volumes shown on Figure 21 with the adjustments shown on Figure 18, and adding the full development total site volumes shown on Figure 14B. The full build combined volumes assuming the Avenue site access are shown on Figure 23. Capacity calculations were performed for forecasted horizon year build (combined) condition traffic volumes for the weekday AM, weekday PM and Saturday peak hours. In addition to the assumptions used in the conditions, the following additional assumptions are included in the analysis: For the Avenue access scenario, a fully actuated traffic signal coordinated with adjacent signals is installed at and Avenue providing two phase operation; A westbound left turn lane is provided on at 19 th Street and a three phase signal. A two lane approach is provided on 19 th Street; and A two-phase signal is assumed at the intersection of and 16 th Street. Note: Turn lane and signal warrants are discussed in the Additional Analysis section. The results of the capacity calculations performed using forecasted horizon year build (combined) condition traffic volumes are summarized in Table 1. The results of the capacity analysis performed using forecasted build (combined) condition traffic volumes revealed that each of the study intersections are anticipated to operate at an overall 10

intersection LOS D or better during each of the peak periods analyzed with no intersection experiencing more than a 10 second overall increase in delay (not including unsignalized to signalized comparisons), provided that the following mitigation is implemented: Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. There is one exception to the 10 second overall increase. For the intersection of the Highland Park Bridge Ramp to eastbound there is a greater than 10 second increase during the PM peak hour. The intersection operates at an overall LOS C. This greater than 10 second increase can be mitigated if this ramp were eliminated and the Highland Park Bridge Ramp intersection along the north side of were signalized. This has not been assumed as PennDOT has undertaken a study of the Highland Park Bridge interchange and it is anticipated that the outcome of that study will be recommended mitigation for this ramp. Copies of capacity analysis performed for build conditions are included in the Appendix to this report. ADDITIONAL ANALYSIS Additional analyses performed included turn lane warrant evaluations, signal warrant evaluations, queuing analysis, left turn phasing evaluations and a sight distance evaluation at the proposed site driveways. Turn Lane Warrant and Storage Length Evaluation An evaluation of the guidelines for auxiliary turn lanes and storage lengths was performed in accordance with PennDOT Publication 46, Traffic Engineering Manual. The evaluation was performed for the highest hourly volumes. The following table summarizes the results of this evaluation. Condition Intersection/ Movements Main St & 19 th St/ WB Left & EB Right Freeport Rd & Ave/ WB Left & EB Right Freeport Rd & Ave/ WB Left & EB Right Warranted Storage Length (feet) Left Turn Lane Right Turn Lane AM PM Sat AM PM Sat Yes-275 Yes-200 Yes-175 Yes-100 Yes-100 No Yes-75 Yes-100 Yes-75 Yes-100 Yes-100 Yes-100 Yes-75 Yes-75 Yes-75 Yes-100 Yes-100 Yes-100 Although a right turn lane is shown being warranted on at 19 th Street, this lane was not assumed in the analysis since the right turn movement is less than 100 vehicles per hour, the posted speed is 25 mph and acceptable LOS are attained without it. For the turn movements at the Avenue access and alternate Avenue access grade crossings, queue calculations were also performed to determine the storage length of left and right turn lanes to accommodate a queue that would be obstructed by train movements. For the purposes of these calculations, it was assumed that a 3 minute blockage of the grade crossings would occur. The highest hourly volumes were used for these calculations. Based on the projected turn movements and a peak factor of 1.5 times, the calculations determined the following storage lengths: 11

Condition Intersection/ Movements Storage Length Based on Crossing Obstruction (feet) Left Turn Lane Right Turn Lane Freeport Rd & Ave/WB Left & EB Right 170 220 Freeport Rd & Ave/WB Left & EB Right 150 225 Note: Calculations rounded up to nearest 5 feet. Copies of the turn lane warrant evaluation worksheets and queue calculations assuming the crossing obstruction are included in the Appendix. Signal Warrant Evaluation An evaluation of applicable warrants for the installation of traffic signals at the following study intersections was performed in accordance with PennDOT Publication 212, Official Traffic Control Devices and the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD), 2009 Edition. and Avenue and the northbound Highland Park Bridge ramps and the southbound Highland Park Bridge ramps and 19 th Street and reet and 13 th Street It was determined that the following warrants were met under the following conditions: MUTCD Warrant Satisfied? Warrant 2. Condition / Intersection Four-Hour Vehicular Warrant 3. Peak Hour Volume 2016 Existing Conditions and the NB Highland Park Bridge ramps Yes Yes and the SB Highland Park Bridge ramps Yes Yes Opening Year Avenue Access and Avenue No No Opening Year Avenue Access and Avenue Yes Yes Opening Year Either Access and 19th Street No No and reet Yes No and reet No No 2020 Horizon Year No Either Access and reet Yes No MUTCD Warrant Satisfied? Condition / Intersection Warrant 2. Warrant 3. 12

Horizon Year Avenue Access Four-Hour Vehicular Volume Peak Hour and Avenue Yes Yes Horizon Year Either Access and 19th Street Yes Yes and reet No No Signalized intersection control was assumed at the aforementioned intersections for the condition that they initially satisfy warrants with two exceptions. At and the Highland Park Bridge Ramps, few vehicles turn left from the off-ramp and acceptable capacity is available for right turns from this ramp. Therefore, no signal was assumed in the analysis. At the intersection of and 16 th Street, acceptable capacity is available in the condition. A signal has been assumed in the No and conditions. Copies of the signal warrant evaluation worksheets are included in the Appendix. Queuing Analysis Traffic volumes at each of the study intersections were used to perform queuing analyses for each lane group, peak hour and scenario. These queuing analyses were performed using Synchro Traffic Signal Coordination Software by TrafficWare. No locations had Synchro queues reported with a # symbol in Synchro, indicating 95th percentile queue exceeds capacity and volume-to-capacity ratios are equal to or greater than 1.0. The queuing analysis is summarized in Table 3. Generally, the most significant queuing occurs in the through lanes along in Aspinwall. Several of these queues extend through adjacent intersections in both the no build and build conditions. In no case do the queues spill back onto the Highland Park Bridge on the ramps of the interchange. Copies of the queuing analysis performed for existing 2016, opening year no build, opening year build, horizon year no build and horizon year build conditions have been included in the Appendix to this report. Left Turn Phasing Evaluation An evaluation of the type of left turn phasing for the aforementioned warranted signals was performed in accordance with the left turns per signal cycle and conflict factor thresholds in PennDOT Publication 149, Traffic Signal Design Handbook. Based on projected opening year build and design year build volumes, the left turns per signal cycle and conflict factor thresholds are met for protected/permitted left turn phases for at the Avenue/ Avenue access intersection and at the Avenue/ Avenue access intersection. The left turns per signal cycle and conflict factor thresholds are also met for a protected/permitted left turn phase for westbound at 19 th Street. Copies of the left turn phase calculations are included in the Appendix. 13

Sight Distance Evaluation-Site Access Intersections Sight distance measurements were performed at the proposed site access intersections opposite Avenue and Avenue along, and at 19 th Street along Main Street using the methodologies published in PennDOT Publication 212, Official Traffic Control Devices, 2006. Available corner sight distance exceeds the safe stopping sight distance at all three site access locations. A summary of the available and the minimum corner sight distances at these locations is presented in Table 4. The worksheets used to verify the sight distance measurements have been included in the Appendix to this report. CONCLUSIONS/RECOMMENDATIONS This study concluded that the construction of the Riverfront 47 development will have minimal impact on the adjacent study roadways and intersections, provided that certain mitigation and site access is provided. A review of the crash history within the study area revealed that a crash problem does not exist at any of the study intersections. Therefore, no improvements are recommended at the existing study intersections based on the crash data available. Crash data is provided in a separate Crash Data Appendix. The results of the capacity analysis performed for each of the study intersections revealed that each intersection can be anticipated to continue to operate at either pre-development LOS under forecasted and forecasted build conditions, or within 10 seconds of overall delay, with the exception of the Highland Park Bridge Ramp to eastbound during the PM peak hour. This intersection operates at an overall LOS C. This greater than 10 second increase can be mitigated if this ramp were eliminated and the Highland Park Bridge Ramp intersection along the north side of were signalized. This has not been assumed as PennDOT has undertaken a study of the Highland Park Bridge interchange and it is anticipated that the outcome of that study will be recommended mitigation for this ramp. Generally, the most significant queuing occurs in the through lanes along in Aspinwall. Several of these queues extend through adjacent intersections in both the no build and build conditions. In no case do the queues spill back onto the Highland Park Bridge on the ramps of the interchange. Available sight distance exceeds the safe stopping sight distance at the site access locations along at Avenue and Avenue and along at 19 th Street. Based on the results of these analyses and evaluations, TA recommends the following: Phase 1 Preferred Avenue Access Construct a high volume local road crossing the Norfolk Southern at-grade to serve the site along opposite Avenue providing a left turn and through/right egress lane and a single ingress lane. This access is projected to serve approximately 3,000 trips per day. Note: The existing River Avenue access and at-grade crossing to be eliminated. 14

Restripe at the access opposite Avenue to create a westbound left turn lane providing 170 feet of storage exclusive of taper. Widen at the access opposite Avenue to provide a right turn lane in the eastbound direction. The right turn lane should provide 220 feet of storage exclusive of taper. Note: The existing parking in this area to be relocated to an area within the Sunoco station lot. Right-of-way will be needed from Norfolk Southern to construct this turn lane. Install a fully actuated traffic signal at the / Avenue / site access intersection. This signal should be coordinated with the adjacent signals along and provide protected/permitted left turn phases for the eastbound/westbound SR 1001 approaches and train preemption. These recommendations are presented graphically on Figure 24. Phase 1 Alternate Avenue Access Construct a high volume local road crossing the Norfolk Southern at-grade to serve the site along opposite Avenue providing a left turn and through/right egress lane and a single ingress lane. This access is projected to serve approximately 3,000 trips per day. Note: The existing River Avenue access and at-grade crossing to be eliminated. Restripe at the access opposite Avenue to lengthen the westbound left turn lane to provide 150 feet of storage exclusive of taper. Widen at the access opposite Avenue to provide a longer right turn lane in the eastbound direction. The right turn lane should provide 225 feet of storage exclusive of taper. Replace the signal at the and Avenue intersection with a fully actuated traffic signal. This signal should be coordinated with the adjacent signals along and provide protected/permitted left turn phases for the eastbound/westbound SR 1001 approaches and train preemption. These recommendations are presented graphically on Figure 25. Phase 1 Either Avenue or Avenue Access Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. Phase 2 and 3 Either Avenue or Avenue Access Stripe the 19 th Street underpass access at to provide left turn and right turn egress lanes back to the pier supporting the railroad overpass, and a single ingress lane. This access is projected to serve approximately 4,800 trips per day. Restripe at the 19 th Street access to create a westbound left turn lane providing 275 feet of storage exclusive of taper. 15

Install a semi actuated traffic signal at the and 19 th Street access intersection. This signal should provide a protected/permitted left turn phase for the westbound SR 1001 approach and a right turn overlap for the 19 th Street approach. Optimize the signal timings along at the Delafield Avenue, Avenue, Avenue, Center Avenue and Western Avenue intersections. These recommendations are presented graphically on Figure 26. Other Mitigation Needed Install a semi actuated two-phase traffic signal at the and 16 th Street intersection. Note: This intersection satisfies warrants for the installation of a signal in the No condition. Install a fully actuated two-phase traffic signal at the and Highland Park Bridge Ramps intersection. Coordinate with signals along in Aspinwall. Note: This intersection satisfies warrants for the installation of a signal in 2016 existing conditions. PennDOT is currently performing a study of the Highland Park Bridge interchange at to determine if signals are needed. Due to the low volumes on the minor streets at several of the signalized intersections in Sharpsburg, i.e. 18 th Street and 21 st Street, the irregular spacing of existing and proposed signals, and the current semi-actuated signal detection, a coordinated signal system may be of limited benefit along Main Street. These recommendations are presented graphically on Figure 27. This concludes TA s transportation impact study for the proposed Riverfront 47 mixed use development to be constructed on a 1.5 mile long, 47-acre site located along the southern side of the Norfolk Southern railway and /, and the northern bank of the Allegheny River, between reet in Sharpsburg and River Avenue in Aspinwall, Allegheny County, Pennsylvania. Included with this report is a Technical Appendix containing all counts, analysis and calculations. File: mosit00/15118/reports/riverfront 47 TIS DRAFT 2016-11-17 16

TABLES

TABLE 1 CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - AM PEAK HOUR (2) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST REET AND 8th STREET/ALI STREET Approach A (4.2) A (3.6) A (3.7) A (3.7) A (4.0) A (4.5) A (4.5) Approach A (5.4) A (4.6) A (4.8) A (4.8) A (5.3) A (5.8) A (5.8) Approach F (107.1) F (120.4) F (120.4) F (120.4) F (120.7) F (120.7) F (120.7) Approach E (57.4) E (75.5) E (75.5) E (75.5) E (79.0) E (79.0) E (79.0) A (8.5) A (8.9) A (8.8) A (8.8) A (9.7) A (9.6) A (9.6) REET AND 13th STREET Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (0.0) A (0.0) Approach C (17.4) C (18.1) C (19.7) C (19.7) C (20.3) D (25.8) D (25.8) Approach B (13.3) B (13.8) B (14.6) B (14.6) B (14.6) C (18.0) C (18.0) A (1.2) A (1.3) A (1.3) A (1.3) A (1.3) A (1.5) A (1.5) REET AND 16th STREET Approach A (0.6) A (0.5) A (0.5) A (0.5) A (0.5) A (0.0) A (0.0) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) B (11.1) B (11.1) Approach A (9.7) A (9.8) B (10.0) B (10.0) B (10.0) C (27.9) C (27.9) Approach D (31.5) E (37.6) F (53.3) F (53.3) F (58.9) D (40.9) D (40.9) A (7.4) A (8.6) B (11.8) B (11.8) B (13.4) B (13.9) B (13.9) REET AND 18th STREET Approach A (2.4) A (2.3) A (2.4) A (2.4) A (2.5) A (3.1) A (3.1) Approach A (2.9) A (2.7) A (2.9) A (2.9) A (3.1) A (3.7) A (3.7) Approach D (46.5) E (55.8) E (55.8) E (55.8) D (53.9) D (53.9) D (53.9) A (5.4) A (5.7) A (5.6) A (5.6) A (5.9) A (5.9) A (5.9)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - AM PEAK HOUR (cont'd) 19th ST 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB OFF-RAMP REET AND 19th STREET Through/Right N/A N/A N/A N/A N/A B (11.3) B (11.3) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) B (11.3) B (11.3) Left N/A N/A N/A N/A N/A A (7.5) A (7.5) Through N/A N/A N/A N/A N/A A (4.6) A (4.6) Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.2) A (5.5) A (5.5) Left N/A N/A N/A N/A N/A D (39.4) D (39.4) Right N/A N/A N/A N/A N/A D (52.0) D (52.0) Approach B (14.8) C (15.4) C (16.5) C (16.5) C (16.5) D (48.4) D (48.4) A (0.3) A (0.3) A (0.3) A (0.3) A (0.3) B (14.2) B (14.2) REET AND 21st STREET Approach A (1.6) A (1.7) A (1.8) A (1.8) A (1.8) A (2.6) A (2.6) Approach A (1.9) A (2.0) A (2.2) A (2.2) A (2.2) A (3.8) A (3.8) Approach E (64.8) E (62.1) E (62.1) E (62.1) E (62.1) E (62.1) E (62.1) A (3.2) A (3.2) A (3.2) A (3.2) A (3.4) A (4.2) A (4.2) FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Approach A (0.0) A (2.8) A (3.1) A (3.1) A (3.1) A (3.9) A (3.9) Approach A (0.0) A (3.3) A (3.8) A (3.8) A (3.7) A (5.9) A (5.9) Approach B (10.8) D (53.1) D (52.5) D (52.5) E (57.1) D (52.0) D (52.0) A (3.1) B (11.0) B (11.1) B (11.1) B (12.0) B (10.5) B (10.5) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left A (9.8) A (10.0) B (10.4) B (10.4) B (10.4) B (12.0) B (12.0) Through A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach A (1.9) A (1.8) A (1.7) A (1.7) A (1.9) A (1.9) A (1.9) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach C (16.0) C (16.7) C (18.3) C (18.3) C (18.7) E (35.0) E (35.0) A (1.9) A (1.9) A (1.9) A (1.9) A (2.1) A (3.6) A (3.6) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Approach B (12.6) B (13.3) B (14.5) B (14.5) B (14.3) C (19.2) C (19.2) A (2.6) A (2.8) A (2.9) A (2.9) A (3.0) A (3.3) A (3.3)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - AM PEAK HOUR (cont'd) WESTERN AVE CENTER AVE SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE FREEPORT ROAD AND WESTERN AVENUE Left A (3.2) A (5.2) A (3.4) A (3.4) A (3.5) A (4.5) A (4.5) Through A (3.5) A (3.7) A 4.1) A 4.1) A (4.3) A (5.9) A (5.9) Approach A (3.5) A (3.8) A (4.1) A (4.1) A (4.2) A (5.8) A (5.8) Approach A (1.7) A (6.9) A (2.2) A (2.2) A (2.2) A (4.3) A (4.3) Approach D (51.4) D (55.0) D (55.0) D (55.0) D (53.7) E (75.4) E (75.4) A (5.6) A (8.4) A (5.9) A (5.9) A (6.2) A (8.7) A (8.7) FREEPORT ROAD AND CENTER AVENUE Left A (3.8) A (5.8) A (3.9) A (3.9) A (7.1) A (4.2) A (4.2) Through A (4.7) A (5.0) A (5.4) A (5.4) A (5.8) A (7.1) A (7.1) Approach A (4.7) A (5.0) A (5.3) A (5.3) A (5.8) A (6.9) A (6.9) Approach A (1.6) A (9.1) A (2.4) A (2.0) B (10.8) A (4.1) A (4.2) Approach E (63.7) E (70.9) E (60.8) E (60.8) E (71.1) E (71.1) E (71.1) B (11.0) B (14.9) B (10.2) B (10.1) B (16.1) B (11.9) B (12.0) FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left A (8.9) A (9.1) A (9.4) A (6.0) A (9.3) A (1.8) A (3.6) Through A (0.0) A (0.0) A (0.0) A (0.8) A (0.0) A (1.1) A (1.2) Right N/A N/A N/A A (0.2) N/A N/A A (0.3) Approach A (0.5) A (0.4) A (0.4) A (0.9) A (0.5) A (1.1) A (1.1) Left N/A N/A N/A A (3.4) N/A N/A A (3.4) Through/Right N/A N/A N/A B (14.1) N/A N/A A (1.7) Approach A (0.0) A (0.0) A (0.0) B (12.8) A (0.0) A (2.2) A (1.9) Left N/A N/A N/A D (45.4) N/A N/A D (45.4) Through/Right N/A N/A N/A D (46.4) N/A N/A D (45.2) Approach D (27.4) D (30.6) E (38.4) D (45.9) E (36.4) D (44.5) D (45.3) Approach B (14.3) C (15.9) C (20.3) D (43.0) C (17.2) D (50.2) D (43.0) A (0.9) A (1.0) A (1.1) B (13.6) A (1.1) A (3.7) A (8.0)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - AM PEAK HOUR (cont'd) RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE 2nd ST DELAFIELD AVE DELAFIELD AVE FREEPORT ROAD AND RIVER AVENUE Approach A (0.0) A (0.0) N/A N/A A (0.0) N/A N/A Approach A (0.1) A (0.3) N/A N/A A (0.3) N/A N/A Approach C (16.5) C (20.7) N/A N/A C (23.2) N/A N/A A (0.2) A (0.9) N/A N/A A (0.9) N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left A (0.1) A (1.7) A (4.6) A (2.5) A (0.1) A (5.2) A (3.0) Through A (0.6) A (2.7) A (1.1) A (0.7) A (0.8) A (1.5) A (0.9) Right N/A N/A A (0.3) N/A N/A A (0.3) N/A Approach A (0.6) A (2.6) A (1.1) A (0.9) A (0.7) A (1.4) A (1.1) Left N/A N/A A (4.4) N/A N/A A (4.9) N/A Through/Right N/A N/A A (1.1) A (1.7) N/A A (1.8) N/A Approach A (1.0) A (1.1) A (1.5) A (1.7) A (0.9) A (2.1) A (3.1) Left N/A N/A D (43.8) N/A N/A D (43.5) N/A Through/Right N/A N/A D (40.8) N/A N/A D (38.9) N/A Approach N/A N/A D (42.5) N/A N/A D (41.6) N/A Approach E (61.6) E (61.5) D (41.0) E (59.8) E (60.0) D (40.7) E (79.3) A (5.4) A (6.3) A (9.7) A (5.7) A (5.7) A (9.1) A (8.1) FREEPORT ROAD AND DELAFIELD AVENUE Left A (5.1) A (5.2) A (5.8) A (5.8) A (6.1) A (9.7) A (9.7) Through A (3.8) A (0.5) A (0.6) A (0.6) A (0.6) A (0.8) A (0.8) Approach A (4.0) A (1.3) A (1.4) A (1.4) A (1.5) A (2.1) A (2.0) Approach A (8.6) A (9.0) A (9.9) A (9.9) B (10.4) B (15.0) B (15.0) Approach E (64.9) D (53.9) D (54.9) D (54.9) E (57.4) E (60.5) E (60.5) B (14.8) B (12.2) B (12.3) B (12.3) B (13.5) B (15.1) B (15.1) DELAFIELD AVENUE AND 2nd STREET Approach A (8.3) A (8.3) A (8.4) A (8.4) A (8.5) A (8.7) A (8.7) Approach A (8.2) A (8.3) A (8.4) A (8.4) A (8.5) A (8.7) A (8.7) Approach A (8.4) A (8.4) A (8.5) A (8.5) A (8.6) A (9.0) A (9.0) A (8.3) A (8.3) A (8.4) A (8.4) A (8.5) A (8.8) A (8.8)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - PM PEAK HOUR (3) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST REET AND 8th STREET/ALI STREET Approach A (5.1) A (4.5) A (4.7) A (4.7) A (5.2) A (5.8) A (5.8) Approach A (3.3) A (2.9) A (3.0) A (3.0) A (3.2) A (3.5) A (3.5) Approach F (138.4) F (157.7) F (157.7) F (157.7) F (158.2) F (158.2) F (158.2) Approach F (96.7) F (112.4) F (112.4) F (112.4) F (97.1) F (97.1) F (97.1) A (9.4) A (9.5) A (9.4) A (9.4) A (9.4) A (9.3) A (9.3) REET AND 13th STREET Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.0) A (0.0) A (0.0) Approach A (0.2) A (0.2) A (0.2) A (0.2) A (0.2) A (0.2) A (0.2) Approach C (21.9) C (22.5) C (24.3) C (24.3) D (27.2) D (34.7) D (34.7) Approach C (17.5) C (18.1) C (19.9) C (19.9) C (20.7) C (28.1) C (28.1) A (1.6) A (1.6) A (1.7) A (1.7) A (1.8) A (2.3) A (2.3) REET AND 16th STREET Approach A (0.5) A (0.5) A (0.5) A (0.5) A (0.5) A (0.0) A (0.0) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (7.1) A (7.1) Approach C (23.5) C (24.4) D (26.2) D (26.2) D (28.1) D (36.8) D (36.8) Approach E (44.6) E (49.3) F (72.1) F (72.1) F (85.0) D (45.5) D (45.5) A (5.6) A (6.1) A (9.1) A (9.1) B (10.4) A (9.0) A (9.0) REET AND 18th STREET Approach A (2.5) A (2.6) A (2.8) A (2.8) A (3.0) A (3.5) A (3.5) Approach A (2.4) A (2.5) A (2.6) A (2.6) A (2.8) A (3.4) A (3.4) Approach E (62.4) E (60.7) E (60.7) E (60.7) E (59.3) E (59.3) E (59.3) A (6.6) A (6.4) A (6.3) A (6.3) A (6.7) A (6.6) A (6.6)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - PM PEAK HOUR (cont'd) 19th ST 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB RAMPS REET AND 19th STREET Through/Right N/A N/A N/A N/A N/A B (18.1) B (18.1) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) B (18.1) B (18.1) Left N/A N/A N/A N/A N/A B (16.8) B (16.8) Through N/A N/A N/A N/A N/A A (6.2) A (6.2) Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (8.2) A (8.2) Left N/A N/A N/A N/A N/A C (34.8) C (34.8) Right N/A N/A N/A N/A N/A D (54.7) D (54.7) Approach C (16.7) C (17.1) C (18.3) C (18.3) C (19.1) D (49.2) D (49.2) A (0.3) A (0.3) A (0.3) A (0.3) A (0.4) B (19.8) B (19.8) REET AND 21st STREET Approach A (2.1) A (1.8) A (2.3) A (1.8) A (2.4) A (3.5) A (3.5) Approach A (2.1) A (2.0) A (2.2) A (2.0) A (2.3) A (2.7) A (2.7) Approach E (62.5) E (66.6) C (66.6) E (66.6) E (69.4) E (56.1) E (56.1) A (4.0) A (4.1) A (4.1) A (4.1) A (4.5) A (4.4) A (4.4) FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Approach A (0.0) A (6.0) A (6.6) A (6.6) A (7.0) B (10.2) B (10.2) Approach A (0.0) A (5.4) A (5.9) A (5.9) A (6.2) A (7.9) A (7.9) Approach E (38.6) D (53.0) D (52.4) D (52.4) D (52.1) D (52.7) D (52.7) B (10.2) B (15.4) B (15.6) B (15.6) B (16.0) B (16.3) B (16.3) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left B (11.2) B (11.4) B (11.9) B (11.9) B (12.3) B (14.6) B (14.6) Through A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach A (2.9) A (2.9) A (2.8) A (2.8) A (3.1) A (3.2) A (3.2) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach C (19.0) C (19.8) C (21.6) C (21.6) C (23.5) E (39.8) E (39.8) A (2.7) A (2.7) A (2.7) A (2.7) A (3.1) A (4.4) A (4.4) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Approach D (25.8) D (28.4) E (39.1) E (39.1) E (42.3) F (144.1) F (144.1) A (5.7) A (6.2) A (8.5) A (8.5) A (9.3) D (27.8) D (27.8)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - PM PEAK HOUR (cont'd) WESTERN AVE CENTER AVE SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE FREEPORT ROAD AND WESTERN AVENUE Left A (1.9) A (2.0) A (2.0) A (2.0) A (2.1) A (2.2) A (2.2) Through A (3.7) A (3.8) A (4.4) A (4.4) A (4.6) A (8.1) A (8.1) Approach A (3.5) A (3.6) A (4.2) A (4.2) A (4.3) A (7.5) A (7.5) Approach A (1.4) A (1.5) A (1.6) A (1.6) A (1.7) A (2.2) A (2.2) Approach E (58.5) E (58.6) E (58.6) E (58.6) E (57.9) E (75.4) E (75.4) A (4.5) A (4.6) A (4.8) A (4.8) A (5.0) A (7.4) A (7.4) FREEPORT ROAD AND CENTER AVENUE Left A (2.7) A (2.8) A (2.7) A (2.7) A (8.8) A (2.8) A (2.8) Through A (3.8) A (3.9) A (4.3) A (4.3) A (4.4) A (6.0) A (6.0) Approach A (3.6) A (3.7) A (4.1) A (2.2) A (5.1) A (5.6) A (5.6) Approach A (2.1) A (2.6) A (2.8) A (2.8) B (11.2) A (3.3) A (3.5) Approach D (54.7) E (70.0) E (70.0) E (70.0) E (73.2) E (78.5) E (78.5) A (6.0) A (7.2) A (7.1) A (6.8) B (11.9) A (8.2) A (8.3) FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left A (9.3) A (9.4) A (9.6) A (3.8) A (9.7) A (2.0) A (3.9) Through A (0.0) A (0.0) A (0.0) A (1.8) A (0.0) B (16.8) A (3.5) Right N/A N/A N/A A (0.1) N/A N/A A (0.1) Approach A (0.4) A (0.4) A (0.4) A (1.7) A (0.5) B (16.1) A (3.2) Left N/A N/A N/A A (3.7) N/A N/A A (3.8) Through/Right N/A N/A N/A A (1.4) N/A N/A A (0.3) Approach A (0.0) A (0.0) A (0.0) A (1.7) A (0.0) A (1.4) A (0.7) Left N/A N/A N/A D (50.4) N/A N/A D (49.9) Through/Right N/A N/A N/A D (52.0) N/A N/A D (48.5) Approach B (14.1) B (14.4) C (15.4) D (51.3) C (15.3) D (47.4) D (49.2) Approach D (26.7) D (29.8) E (45.6) D (48.2) E (40.7) E (61.8) D (48.0) A (1.5) A (1.6) A (2.3) A (8.7) A (2.2) B (11.8) A (7.9)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement 2016 Existing No Level of Service (Delay in Seconds) (1) - - No - - PM PEAK HOUR (cont'd) RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE 2nd ST DELAFIELD AVE DELAFIELD AVE FREEPORT ROAD AND RIVER AVENUE Approach A (0.0) A (0.0) N/A N/A A (0.0) N/A N/A Approach A (0.1) A (0.2) N/A N/A A (0.2) N/A N/A Approach D (28.2) E (36.9) N/A N/A E (48.5) N/A N/A A (0.5) A (1.6) N/A N/A A (1.9) N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left A (0.3) A (0.3) A (4.4) A (2.4) A (0.4) A (4.4) A (2.7) Through A (1.0) A (1.2) A (1.8) A (0.9) A (1.4) A (0.6) A (0.9) Right N/A N/A A (0.2) N/A N/A A (0.0) N/A Approach A (1.0) A (1.1) A (1.8) A (1.0) A (1.3) A (0.8) A (1.0) Left N/A N/A A (4.3) N/A N/A A (4.4) N/A Through/Right N/A N/A A (2.2) N/A N/A A (2.9) B (13.6) Approach A (2.0) A (2.1) A (2.4) A (4.3) A (2.4) A (3.0) B (13.6) Left N/A N/A D (49.4) N/A N/A D (51.3) N/A Through/Right N/A N/A D (45.9) N/A N/A D (45.6) N/A Approach N/A N/A D (47.6) N/A N/A D (48.4) N/A Approach F (80.1) F (80.3) D (47.7) F (123.2) F (81.3) D (50.8) F (138.4) A (5.6) A (5.5) A (8.6) A (9.0) A (5.8) A (8.0) B (14.3) FREEPORT ROAD AND DELAFIELD AVENUE Left A (9.6) B (12.4) B (14.8) B (14.7) B (17.3) C (28.4) C (28.3) Through A (0.8) A (0.9) A (1.0) A (0.9) A (1.0) A (1.3) A (1.0) Approach A (1.6) A (2.0) A (2.4) A (2.3) A (2.7) A (4.0) A (3.7) Approach B (14.4) B (16.6) B (19.1) B (19.0) C (22.1) D (36.4) D (36.4) Approach F (127.6) E (70.6) E (71.5) E (74.2) E (73.9) E (76.4) E (76.4) C (24.1) B (17.9) B (19.1) B (19.3) C (21.2) C (27.8) C (27.7) DELAFIELD AVENUE AND 2nd STREET Approach A (8.0) A (8.1) A (8.2) A (8.2) A (8.3) A (8.6) A (8.6) Approach A (8.3) A (8.3) A (8.4) A (8.4) A (8.6) A (8.8) A (8.8) Approach A (8.4) A (8.5) A (8.6) A (8.6) A (8.8) A (9.1) A (9.1) A (8.3) A (8.4) A (8.5) A (8.5) A (8.6) A (8.9) A (8.9)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - SATURDAY PEAK HOUR (4) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST REET AND 8th STREET/ALI STREET Approach A (3.3) A (2.8) A (2.9) A (2.9) A (3.0) A (3.3) A (3.3) Approach A (3.2) A (2.7) A (2.8) A (2.8) A (2.8) A (3.0) A (3.0) Approach F (126.8) F (139.8) F (139.8) F (139.8) F (140.6) F (139.9) F (139.9) Approach E (57.9) E (75.5) E (75.5) E (75.5) E (77.7) E (76.6) E (76.6) A (5.5) A (5.6) A (5.5) A (5.5) A (5.8) A (5.7) A (5.7) REET AND 13th STREET Approach A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) A (0.1) Approach A (0.3) A (0.3) A (0.3) A (0.3) A (0.3) A (0.3) A (0.3) Approach B (14.4) B (14.8) C (15.7) C (15.7) C (15.7) C (18.1) C (18.1) Approach B (12.0) B (12.2) B (12.9) B (12.9) B (12.8) B (14.4) B (14.4) A (1.5) A (1.5) A (1.6) A (1.6) A (1.6) A (1.7) A (1.7) REET AND 16th STREET Approach A (0.5) A (0.5) A (0.4) A (0.4) A (0.5) A (0.0) A (0.0) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (6.1) A (6.1) Approach C (15.1) C (15.6) C (16.6) C (16.6) C (16.8) D (38.6) D (38.6) Approach C (19.7) C (21.3) D (25.2) D (25.2) D (25.5) D (52.8) D (52.8) A (3.9) A (4.2) A (4.8) A (4.8) A (5.0) B (12.7) B (12.7) REET AND 18th STREET Approach A (1.8) A (1.9) A (2.0) A (2.0) A (2.1) A (2.3) A (2.3) Approach A (2.1) A (2.2) A (2.3) A (2.3) A (2.5) A (2.8) A (2.8) Approach E (65.8) E (63.6) E (63.6) E (63.6) E (61.7) E (61.7) E (61.7) A (6.0) A (5.8) A (5.6) A (5.6) A (5.9) A (5.7) A (5.7)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - SATURDAY PEAK HOUR (cont'd) 19th ST 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB RAMPS REET AND 19th STREET Through/Right N/A N/A N/A N/A N/A B (10.5) B (10.5) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) B (10.5) B (10.5) Left N/A N/A N/A N/A N/A A (7.1) A (7.1) Through N/A N/A N/A N/A N/A A (3.5) A (3.5) Approach A (0.3) A (0.3) A (0.3) A (0.3) A (0.3) A (4.4) A (4.4) Left N/A N/A N/A N/A N/A B (19.8) B (19.8) Right N/A N/A N/A N/A N/A B (17.8) B (17.8) Approach B (12.2) B (12.5) B (13.2) B (13.2) B (13.3) B (18.4) B (18.4) A (0.4) A (0.4) A (0.4) A (0.4) A (0.4) A (9.0) A (9.0) REET AND 21st STREET Approach A (1.7) A (1.7) A (1.8) A (1.8) A (1.9) A (2.4) A (2.4) Approach A (2.1) A (2.1) A (2.2) A (2.2) A (2.4) A (3.0) A (3.0) Approach E (67.0) E (68.5) E (68.5) E (68.5) E (65.7) E (66.2) E (66.2) A (5.3) A (5.2) A (5.1) A (5.1) A (5.3) A (5.2) A (5.2) FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Approach A (0.0) A (2.9) A (3.2) A (3.2) A (3.3) A (4.0) A (4.0) Approach A (0.0) A (3.1) A (3.4) A (3.4) A (3.5) A (4.4) A (4.4) Approach B (12.9) E (56.7) E (56.2) E (56.2) E (56.0) E (55.7) E (55.7) A (3.3) B (12.7) B (12.6) B (12.6) B (13.0) B (11.8) B (11.8) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left B (10.7) B (10.9) B (11.3) B (11.3) B (11.5) B (12.8) B (12.8) Through A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach A (2.0) A (1.9) A (1.8) A (1.8) A (2.0) A (2.0) A (2.0) Approach A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) A (0.0) Approach C (20.2) C (21.1) C (23.3) C (23.3) D (25.2) E (40.4) E (40.4) A (2.1) A (2.1) A (2.1) A (2.1) A (2.4) A (3.6) A (3.6) FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Approach C (19.2) C (21.1) D (26.6) D (26.6) D (27.5) F (54.5) F (54.5) A (4.8) A (5.2) A (6.4) A (6.4) A (6.8) B (12.2) B (12.2)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - SATURDAY PEAK HOUR (cont'd) WESTERN AVE CENTER AVE SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE FREEPORT ROAD AND WESTERN AVENUE Left A (1.9) A (1.9) A (2.0) A (2.0) A (2.1) A (2.5) A (2.5) Through A (3.2) A (3.4) A (3.8) A (3.8) A (4.0) A (5.6) A (5.6) Approach A (3.1) A (3.3) A (3.8) A (3.8) A (3.9) A (5.5) A (5.5) Approach A (1.7) A (1.8) A (2.0) A (2.0) A (2.1) A (2.8) A (2.8) Approach E (60.5) E (60.5) E (60.6) E (60.6) E (65.8) E (70.8) E (70.8) A (4.0) A (4.1) A (4.4) A (4.4) A (4.7) A (5.9) A (5.9) FREEPORT ROAD AND CENTER AVENUE Left A (3.9) A (4.1) A (4.3) A (4.3) A (4.5) A (4.5) A (4.5) Through A (4.1) A (4.3) A (4.6) A (4.6) A (4.9) A (5.9) A (5.9) Approach A (4.1) A (4.2) A (4.6) A (4.6) A (4.8) A (5.8) A (5.8) Approach A (3.7) A (4.0) A (5.2) A (3.8) A (5.4) A (6.5) A (6.6) Approach D (54.6) E (71.8) E (77.6) E (77.6) E (75.1) E (75.1) E (75.1) A (6.8) A (8.0) A (8.8) A (8.2) A (9.2) A (9.6) A (9.7) FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left A (9.7) A (9.8) B (10.2) A (4.1) A (9.8) A (2.0) A (4.1) Through A (0.0) A (0.0) A (0.0) A (1.4) A (0.0) A (4.5) A (2.0) Right N/A N/A N/A A (0.2) N/A N/A A (0.2) Approach A (0.4) A (0.4) A (0.4) A (1.3) A (0.4) A (4.4) A (1.9) Left N/A N/A N/A A (3.8) N/A N/A A (4.0) Through/Right N/A N/A N/A A (2.0) N/A N/A A (2.6) Approach A (0.1) A (0.0) A (0.0) A (2.1) A (0.0) A (3.0) A (2.7) Left N/A N/A N/A D (49.8) N/A N/A D (49.6) Through/Right N/A N/A N/A D (48.5) N/A N/A D (47.6) Approach E (46.3) F (51.7) F (66.9) D (49.1) F (52.9) D (47.6) D (48.6) Approach E (37.8) E (44.8) F (74.9) D (46.9) E (47.8) E (57.1) D (47.2) A (2.1) A (2.3) A (3.6) A (8.4) A (2.6) A (6.0) A (8.2)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Level of Service (Delay in Seconds) (1) Direction Approach / Movement 2016 Existing No - - No - - SATURDAY PEAK HOUR (cont'd) RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE 2nd ST DELAFIELD AVE DELAFIELD AVE FREEPORT ROAD AND RIVER AVENUE Approach A (0.0) A (0.0) N/A N/A A (0.0) N/A N/A Approach A (0.0) A (0.1) N/A N/A A (0.1) N/A N/A Approach C (24.6) D (33.6) N/A N/A E (43.0) N/A N/A A (0.1) A (1.3) N/A N/A A (1.5) N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left A (0.2) A (0.2) A (4.4) A (1.9) A (0.3) A (4.1) A (2.3) Through A (1.0) A (1.1) A (1.9) A (1.1) A (1.3) A (1.3) A (1.3) Right N/A N/A A (0.2) N/A N/A A (0.1) N/A Approach A (1.0) A (1.1) A (1.8) A (1.1) A (1.3) A (1.4) A (1.4) Left N/A N/A A (4.2) N/A N/A A (4.1) N/A Through/Right N/A N/A A (1.7) N/A N/A A (1.9) N/A Approach A (1.4) A (1.4) A (1.9) A (2.4) A (1.6) A (2.1) A (3.8) Left N/A N/A D (49.2) N/A N/A D (53.8) N/A Through/Right N/A N/A D (46.5) N/A N/A D (47.9) N/A Approach N/A N/A D (46.2) N/A N/A D (50.9) N/A Approach E (67.6) E (68.4) D (46.2) E (77.4) F (81.3) D (49.9) E (78.1) A (4.2) A (4.2) A (8.5) A (5.3) A (5.0) A (8.4) A (6.3) FREEPORT ROAD AND DELAFIELD AVENUE Left A (8.1) A (8.9) B (10.2) B (10.2) B (11.9) B (17.6) B (17.6) Through A (0.8) B (12.8) A (1.0) A (0.9) A (6.0) A (1.2) A (1.1) Approach A (1.1) B (12.6) A (1.4) A (1.4) A (6.3) A (2.1) A (2.1) Approach B (11.5) B (12.3) B (13.8) B (13.8) B (15.4) C (21.4) C (21.4) Approach E (76.0) E (64.8) E (68.6) E (68.6) E (70.8) E (75.8) E (75.8) B (14.7) B (18.2) B (14.7) B (14.7) B (17.9) B (19.2) B (19.2) DELAFIELD AVENUE AND 2nd STREET Approach A (8.2) A (8.2) A (8.3) A (8.3) A (8.4) A (8.7) A (8.7) Approach A (8.5) A (8.6) A (8.7) A (8.7) A (8.8) A (9.0) A (9.0) Approach A (8.9) A (9.0) A (9.1) A (9.1) A (9.3) A (9.7) A (9.7) A (8.6) A (8.7) A (8.8) A (8.8) A (9.0) A (9.3) A (9.3)

TABLE 1 (CONT'D) CAPACITY ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania (1) Level of service and vehicular delay calculated using methodologies published in Highway Capacity Manual 2010, published by the Transportation Research Board, 2010. (2) 7:15 AM to 8:15 AM (3) 4:30 PM to 5:30 PM (4) 12:00 PM to 1:00 PM Note: Inputs shaded green indicates a proposed traffic signal at that location. Source: Analysis by Trans Associates.

TABLE 2 TRIP GENERATION SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Phase Zone Development Component Size ITE Land Use Code Weekday Average Daily Traffic (1) Trip Type Vehicle Trips Generated (1) A.M. Peak Hour P.M. Peak Hour Saturday Peak Hour Enter Exit Total Enter Exit Total Enter Exit Total June 6, 2016 - Development Program A Phase 1 Zone 8 Zone 7 Zone 6 Public Riverfront Park 14.3 Acres 411 486 Primary 36 28 64 29 21 50 32 32 64 ZONE 8 TOTAL -- 486 Primary 36 28 64 29 21 50 32 32 64 Marina 35 Berths 420 104 Primary 1 2 3 4 3 7 4 5 9 ZONE 7 TOTAL -- 104 Primary 1 2 3 4 3 7 4 5 9 Apartment 49 Units 220 421 Primary 6 22 28 29 16 45 20 19 39 Townhouse/Condominium 175 Units 230 1,047 Primary 14 67 81 64 31 95 50 43 93 General Office 23,506 SF 710 259 Primary 33 4 37 6 29 35 5 5 10 Specialty Retail 7,500 SF 826 332 Primary 24 27 51 9 11 20 10 10 20 Primary 10 8 18 9 6 15 13 11 24 High Turnover (Sit-Down) 2,500 SF 932 318 Pass-By 5 4 9 6 4 10 6 5 11 Restaurant Total 15 12 27 15 10 25 19 16 35 Primary 87 128 215 117 93 210 98 88 186 ZONE 6 TOTAL -- 2,377 Pass-By 5 4 9 6 4 10 6 5 11 Total 92 132 224 123 97 220 104 93 197 Primary 124 158 282 150 117 267 134 125 259 TOTAL PHASE 1 2,967 Pass-By 5 4 9 6 4 10 6 5 11 SITE GENERATED TRAFFIC VOLUMES Total 129 162 291 156 121 277 140 130 270

TABLE 2 (CONT'D) TRIP GENERATION SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Phase Zone Development Component Size ITE Land Use Code Weekday Average Daily Traffic (1) Trip Type Vehicle Trips Generated (1) A.M. Peak Hour P.M. Peak Hour Saturday Peak Hour Enter Exit Total Enter Exit Total Enter Exit Total June 6, 2016 - Development Program A Phase 2 Zone 5 Zone 4 Apartment 219 Units 220 1,451 Primary 22 89 111 90 48 138 55 54 109 Townhouse/Condominium 17 Units 230 138 Primary 2 11 13 9 5 14 26 22 48 ZONE 5 TOTAL 1,589 Primary 24 100 124 99 53 152 81 76 157 Apartment 61 Units 220 493 Primary 7 27 34 33 18 51 22 22 44 Specialty Retail 7,500 SF 826 332 Primary 24 27 51 9 11 20 10 10 20 General Office 27,440 SF 710 303 Primary 38 5 43 7 34 41 6 6 12 Primary 10 8 18 9 6 15 13 11 24 High Turnover (Sit-Down) Res 2,500 SF 932 318 Pass-By 5 4 9 6 4 10 6 5 11 Total 15 12 27 15 10 25 19 16 35 Primary 79 67 146 58 69 127 51 49 100 ZONE 4 TOTAL 1446 Pass-By 5 4 9 6 4 10 6 5 11 Total 84 71 155 64 73 137 57 54 111 Primary 103 167 270 157 122 279 132 125 257 TOTAL PHASE 2 3,035 Pass-By 5 4 9 6 4 10 6 5 11 SITE GENERATED TRAFFIC VOLUMES Total 108 171 279 163 126 289 138 130 268

TABLE 2 (CONT'D) TRIP GENERATION SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Phase Zone Development Component Size ITE Land Use Code Weekday Average Daily Traffic (1) Trip Type Vehicle Trips Generated (1) A.M. Peak Hour P.M. Peak Hour Saturday Peak Hour Enter Exit Total Enter Exit Total Enter Exit Total Phase 3 Zone 3 Zone 2 Zone 1 Empty N/A -- 0 Primary 0 0 0 0 0 0 0 0 0 ZONE 3 TOTAL 0 Primary 0 0 0 0 0 0 0 0 0 Research and Development 154,000 SF 760 1,438 Primary 157 32 189 28 161 189 18 18 36 ZONE 2 TOTAL 1,438 Primary 157 32 189 28 161 189 18 18 36 Research and Development 32,000 SF 760 390 Primary 40 8 48 8 43 51 9 9 18 ZONE 1 TOTAL 390 Primary 40 8 48 8 43 51 9 9 18 Primary 197 40 237 36 204 240 27 27 54 TOTAL PHASE 3 1,828 Pass-By 0 0 0 0 0 0 0 0 0 SITE GENERATED TRAFFIC VOLUMES Total 197 40 237 36 204 240 27 27 54

TABLE 2 (CONT'D) TRIP GENERATION SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Phase Zone Development Component Size ITE Land Use Code Weekday Average Daily Traffic (1) Trip Type Vehicle Trips Generated (1) A.M. Peak Hour P.M. Peak Hour Saturday Peak Hour Enter Exit Total Enter Exit Total Enter Exit Total June 6, 2016 - Development Program A Phase 1 TOTAL PHASE 1 SITE GENERATED TRAFFIC VOLUMES 2,967 Primary 124 158 282 150 117 267 134 125 259 Pass-By 5 4 9 6 4 10 6 5 11 Total 129 162 291 156 121 277 140 130 270 Phase 2 TOTAL PHASE 2 SITE GENERATED TRAFFIC VOLUMES 3,035 Primary 103 167 270 157 122 279 132 125 257 Pass-By 5 4 9 6 4 10 6 5 11 Total 108 171 279 163 126 289 138 130 268 Phase 3 TOTAL PHASE 3 SITE GENERATED TRAFFIC VOLUMES 1,828 Primary 197 40 237 36 204 240 27 27 54 Pass-By 0 0 0 0 0 0 0 0 0 Total 197 40 237 36 204 240 27 27 54 TOTAL FULL BUILDOUT SITE GENERATED TRAFFIC VOLUMES 7,830 Primary 424 365 789 343 443 786 293 277 570 Pass-By 10 8 18 12 8 20 12 10 22 Total 434 373 807 355 451 806 305 287 592 (1) Total number of vehicle trips generated determined through the use of methodologies presented in Trip Generation, Ninth Edition published by the Institute of Transportation Engineers (ITE). Source: Analysis by Trans Associates.

TABLE 3 QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - AM PEAK HOUR (3) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST 19th ST REET AND 8th STREET/ALI STREET Through/Right 300 117 224 245 245 119 158 158 Left/Through 500 304 123 132 132 320 407 407 Left/Through/Right 220 8 0 0 0 9 9 9 Left/Through/Right 145 41 21 21 21 55 55 55 REET AND 13th STREET Left/Through/Right 730 0 0 0 0 0 0 0 Left/Through/Right 505 0 0 0 0 0 0 0 Left/Through/Right 275 3 8 8 8 3 3 3 Left/Through/Right 350 10 18 20 20 13 20 20 REET AND 16th STREET Left/Through/Right 320 3 3 3 3 3 203 203 Left/Through/Right 895 0 0 0 0 0 322 322 Left/Through/Right 75 0 3 3 3 0 0 0 Left/Through/Right 180 100 103 143 143 178 252 252 REET AND 18th STREET Through 900 105 176 201 201 130 190 190 Through 975 133 145 159 159 161 217 217 Left/Right 210 56 93 93 93 66 66 66 REET AND 19th STREET Through/Right 1,125 0 0 0 0 0 375 375 Left 275 N/A N/A N/A N/A N/A 68 68 Through 415 0 0 0 0 0 159 159 Left/Right 75 3 5 5 5 3 N/A N/A Left 85 N/A N/A N/A N/A N/A 78 78 Right 300 N/A N/A N/A N/A N/A 183 183

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - AM PEAK HOUR (3) 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB OFF-RAMP WESTERN AVE CENTER AVE REET AND 21st STREET Through 380 73 108 167 167 113 203 203 Through 345 90 123 147 147 137 312 312 Left/Right 230 39 56 56 56 40 40 40 FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Through 910 0 280 322 321 154 191 191 Through 825 0 157 238 157 228 197 246 Right 825 0 0 0 0 0 0 0 Left/Right 640 33 303 310 311 269 349 349 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left 850 8 25 28 28 10 15 15 Through 850 0 0 0 0 0 0 0 Through/Right 365 0 0 0 0 0 0 0 Left/Right 915 23 38 43 43 30 85 85 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Right 645 43 163 218 218 60 93 93 FREEPORT ROAD AND WESTERN AVENUE Left 95 4 16 26 16 4 3 5 Through 315 160 146 468 188 180 161 278 Through/Right 565 102 47 47 67 140 829 829 Left/Right 215 96 88 88 88 108 153 153 FREEPORT ROAD AND CENTER AVENUE Left 150 12 29 25 35 10 12 10 Through 345 85 152 142 182 85 223 174 Approach 490 318 585 446 141 235 723 193 Approach 245 76 86 86 86 80 80 80

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - AM PEAK HOUR (3) SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left 125 3 3 5 9 3 1 7 Through 510 0 0 0 289 0 10 99 Right 150 N/A N/A N/A 31 N/A N/A 25 Left 150 N/A N/A N/A 6 N/A N/A 21 Through/Right 500 0 0 0 103 0 260 258 Left/Through/Right 25 3 0 0 N/A 3 13 N/A Left -- N/A N/A N/A 150 N/A N/A 133 Through/Right -- N/A N/A N/A 134 N/A N/A 105 Left/Through/Right 115 10 40 63 117 13 50 86 FREEPORT ROAD AND RIVER AVENUE Through/Right 515 0 0 N/A N/A 0 N/A N/A Left/Through 75 0 3 N/A N/A 3 N/A N/A Left/Right 300 3 40 N/A N/A 15 N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left 35 18 14 10 10 3 6 8 Through 65/635 214 377 225 171 30 278 104 Right 150 N/A N/A 27 N/A N/A 30 N/A Left 150 N/A N/A 25 N/A N/A 20 N/A Through/Right 950 74 102 513 164 207 192 185 Left 225 N/A N/A 143 N/A N/A 149 N/A Through/Right -- N/A N/A 122 N/A N/A 94 N/A Left/Right 290 57 72 N/A 172 60 N/A 177 Left/Through/Right 290 N/A N/A 126 N/A N/A 129 N/A FREEPORT ROAD AND DELAFIELD AVENUE Left 105 11 20 16 26 5 41 40 Through 935 76 143 98 272 41 256 221 Approach 525 219 617 702 681 292 452 452 Approach 665 117 209 214 233 127 132 132

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - AM PEAK HOUR (3) 2nd ST DELAFIELD AVE DELAFIELD AVE DELAFIELD AVENUE AND 2nd STREET Approach 205 5 8 8 8 8 10 10 Approach 665 18 18 20 20 20 23 23 Approach 145 20 23 23 25 25 30 30

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - PM PEAK HOUR (4) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST 19th ST REET AND 8th STREET/ALI STREET Through/Right 300 228 107 116 116 275 336 336 Left/Through 500 123 267 295 295 144 185 185 Left/Through/Right 220 0 9 9 9 0 0 0 Left/Through/Right 145 20 52 52 52 26 26 26 REET AND 13th STREET Left/Through/Right 730 0 0 0 0 0 0 0 Left/Through/Right 505 0 0 0 0 0 0 0 Left/Through/Right 275 8 3 3 3 10 13 13 Left/Through/Right 350 15 10 13 13 23 35 35 REET AND 16th STREET Left/Through/Right 320 3 3 3 3 3 317 317 Left/Through/Right 895 0 0 0 0 0 395 395 Left/Through/Right 75 3 0 0 0 3 0 0 Left/Through/Right 180 95 120 163 163 158 230 230 REET AND 18th STREET Through 900 163 114 128 128 213 288 288 Through 975 136 140 160 160 172 240 240 Left/Right 210 96 62 62 62 101 101 101 REET AND 19th STREET Through/Right 1,125 0 0 0 0 0 524 524 Left 275 N/A N/A N/A N/A N/A 39 39 Through 415 0 0 0 0 0 216 216 Left/Right 75 5 3 3 3 3 N/A N/A Left 85 N/A N/A N/A N/A N/A 123 123 Right 300 N/A N/A N/A N/A N/A 294 294

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - PM PEAK HOUR (4) 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB OFF-RAMP WESTERN AVE CENTER AVE REET AND 21st STREET Through 380 140 97 108 108 177 454 454 Through 345 128 117 132 132 160 265 265 Left/Right 230 53 37 37 37 61 65 65 FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Through 910 0 108 122 122 333 580 580 Through 825 0 97 76 91 145 294 260 Right 825 0 0 0 0 0 0 0 Left/Right 640 175 249 261 261 326 361 361 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left 850 25 8 8 8 33 48 48 Through 850 0 0 0 0 0 0 0 Through/Right 365 0 0 0 0 0 0 0 Left/Right 915 38 25 28 28 53 103 103 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Right 645 145 50 60 60 235 483 483 FREEPORT ROAD AND WESTERN AVENUE Left 95 23 3 2 2 26 22 22 Through 315 279 147 125 125 288 757 490 Through/Right 565 119 345 79 108 52 62 50 Left/Right 215 85 101 101 101 94 118 118 FREEPORT ROAD AND CENTER AVENUE Left 150 18 12 16 11 35 25 25 Through 345 77 164 179 113 204 234 244 Approach 490 424 288 313 100 653 321 124 Approach 245 80 81 76 76 96 97 97

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - PM PEAK HOUR (4) SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left 125 3 3 3 3 5 8 7 Through 510 0 0 0 130 0 1.063 913 Right 150 N/A N/A N/A 31 N/A N/A 19 Left 150 N/A N/A N/A 12 N/A N/A 9 Through/Right 500 0 0 0 60 0 230 128 Left/Through/Right 25 0 3 3 N/A 0 0 N/A Left -- N/A N/A N/A 126 N/A N/A 143 Through/Right -- N/A N/A N/A 103 N/A N/A 130 Left/Through/Right 115 33 10 18 72 58 82 129 FREEPORT ROAD AND RIVER AVENUE Through/Right 515 0 0 N/A N/A 0 N/A N/A Left/Through 75 0 3 N/A N/A 3 N/A N/A Left/Right 300 10 13 N/A N/A 53 N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left 35 8 10 12 12 19 11 16 Through 65/635 105 122 126 108 560 296 316 Right 150 N/A N/A 45 N/A N/A 16 N/A Left 150 N/A N/A 20 N/A N/A 7 N/A Through/Right 950 176 111 164 188 153 415 1,062 Left 225 N/A N/A 134 N/A N/A 159 N/A Through/Right -- N/A N/A 94 N/A N/A 123 N/A Left/Right 290 122 57 N/A 104 76 N/A 201 Left/Through/Right 290 N/A N/A 102 N/A N/A 167 N/A FREEPORT ROAD AND DELAFIELD AVENUE Left 105 18 12 26 31 25 39 23 Through 935 167 44 163 135 230 460 343 Approach 525 494 245 283 283 799 1,012 1,012 Approach 665 267 115 116 116 250 266 266

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - PM PEAK HOUR (4) 2nd ST DELAFIELD AVE DELAFIELD AVE DELAFIELD AVENUE AND 2nd STREET Approach 205 8 5 8 8 10 13 13 Approach 665 18 18 20 20 20 23 23 Approach 145 23 23 23 23 28 30 30

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - SATURDAY PEAK HOUR (5) ALI ST 8th ST 13th ST 13th ST 16th ST 16th ST 18th ST 19th ST REET AND 8th STREET/ALI STREET Through/Right 300 105 104 113 113 116 139 139 Left/Through 500 128 125 135 135 141 166 166 Left/Through/Right 220 0 0 0 0 0 0 0 Left/Through/Right 145 4 1 1 1 4 4 4 REET AND 13th STREET Left/Through/Right 730 0 0 0 0 0 0 0 Left/Through/Right 505 0 0 0 0 0 0 0 Left/Through/Right 275 0 3 3 3 5 5 5 Left/Through/Right 350 45 8 8 8 8 10 10 REET AND 16th STREET Left/Through/Right 320 3 0 0 0 3 108 108 Left/Through/Right 895 0 0 0 0 0 166 166 Left/Through/Right 75 3 0 0 0 0 5 5 Left/Through/Right 180 95 50 65 65 68 298 293 REET AND 18th STREET Through 900 94 100 114 114 116 152 152 Through 975 128 133 148 148 157 194 194 Left/Right 210 79 77 77 77 82 82 82 REET AND 19th STREET Through/Right 1,125 0 0 0 0 0 258 258 Left 275 N/A N/A N/A N/A N/A 30 30 Through 415 0 0 0 0 0 91 91 Left/Right 75 3 3 3 3 3 N/A N/A Left 85 N/A N/A N/A N/A N/A 53 53 Right 300 N/A N/A N/A N/A N/A 86 86

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - SATURDAY PEAK HOUR (5) 21st ST HPB SB RAMPS HPB NB RAMPS HPB NB OFF-RAMP WESTERN AVE CENTER AVE REET AND 21st STREET Through 380 90 97 110 110 112 179 179 Through 345 128 135 149 149 159 242 242 Left/Right 230 67 69 69 69 74 75 75 FREEPORT ROAD AND SOUTHBOUND HIGHLAND PARK BRIDGE RAMPS Through 910 0 121 140 140 141 212 212 Through 825 0 206 86 209 235 155 113 Right 825 0 0 0 0 0 0 0 Left/Right 640 35 223 230 230 239 257 257 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMPS Left 850 10 10 13 13 13 18 18 Through 850 0 0 0 0 0 0 0 Through/Right 365 0 0 0 0 0 0 0 Left/Right 915 35 38 43 43 50 93 93 FREEPORT ROAD AND NORTHBOUND HIGHLAND PARK BRIDGE RAMP Right 645 118 135 175 175 188 310 310 FREEPORT ROAD AND WESTERN AVENUE Left 95 9 6 6 5 8 11 7 Through 315 236 284 162 271 362 394 257 Through/Right 565 162 75 88 116 91 1,043 1,043 Left/Right 215 73 75 76 76 86 98 98 FREEPORT ROAD AND CENTER AVENUE Left 150 11 16 14 11 13 10 17 Through 345 84 151 150 99 144 174 223 Approach 490 469 132 603 184 188 966 275 Approach 245 78 82 84 84 93 93 93

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - SATURDAY PEAK HOUR (5) SUNOCO DWY/ SITE ACCESS DWY EASTERN AVE RIVER AVE ARP ACCESS DWY BRILLIANT AVE DELAFIELD AVE FREEPORT ROAD AND EASTERN AVENUE/SITE ACCESS DRIVEWAY Left 125 3 3 3 5 3 5 4 Through 510 0 0 0 182 0 100 307 Right 150 N/A N/A N/A 23 N/A N/A 18 Left 150 N/A N/A N/A 5 N/A N/A 4 Through/Right 500 0 0 0 142 0 328 322 Left/Through/Right 25 5 8 3 N/A 8 0 N/A Left -- N/A N/A N/A 123 N/A N/A 133 Through/Right -- N/A N/A N/A 127 N/A N/A 127 Left/Through/Right 115 45 53 83 100 60 78 113 FREEPORT ROAD AND RIVER AVENUE Through/Right 515 0 0 N/A N/A 0 N/A N/A Left/Through 75 0 0 N/A N/A 0 N/A N/A Left/Right 300 3 35 N/A N/A 45 N/A N/A FREEPORT ROAD AND BRILLIANT AVENUE/ARP ACCESS DRIVEWAY Left 35 13 9 6 11 10 6 15 Through 65/635 218 132 362 166 152 332 334 Right 150 N/A N/A 42 N/A N/A 22 N/A Left 150 N/A N/A 28 N/A N/A 5 N/A Through/Right 950 371 21 699 64 34 71 869 Left 225 N/A N/A 126 N/A N/A 171 N/A Through/Right -- N/A N/A 118 N/A N/A 125 N/A Left/Right 290 60 60 N/A 64 64 N/A 70 Left/Through/Right 290 N/A N/A 101 N/A N/A 73 N/A FREEPORT ROAD AND DELAFIELD AVENUE Left 105 3 13 7 15 11 15 13 Through 935 143 377 383 354 397 347 350 Approach 525 459 546 596 596 643 917 917 Approach 665 222 189 196 196 224 251 251

TABLE 3 (CONT'D) QUEUE ANALYSIS SUMMARY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Direction Approach / Movement Available Capacity (2) (ft) (Exist/Prop ) 2016 Existing No 95th Percentile Queue Length (ft) (1) - - No - - SATURDAY PEAK HOUR (5) 2nd ST DELAFIELD AVE DELAFIELD AVE DELAFIELD AVENUE AND 2nd STREET Approach 205 8 8 10 10 10 10 10 Approach 665 20 20 23 23 23 25 25 Approach 145 28 30 33 33 35 40 40 (1) 95th percentile queue lengths were calculated utilizing Synchro Traffic Signal Coordination Software, Version 8.0.806.77. (2) Existing available queue capacity obtained through Google Earth, rounded to the nearest 5 feet. (3) 7:15 AM to 8:15 AM (4) 4:30 PM to 5:30 PM (5) 12:00 PM to 1:00 PM Note: Inputs shaded green indicates a proposed traffic signal at that location. Source: Analysis by Trans Associates.

TABLE 4 SIGHT DISTANCE AT PROPOSED SITE DRIVEWAY Riverfront 47 Development Transportation Impact Study Sharpsburg Borough/O'Hara Township/Aspinwall Borough, Allegheny County, Pennsylvania Location Measured Corner Sight Distance (ft) Speed Limit Approaching Roadway Grade Safe Stopping Sight Distance (ft) Sight Distance Acceptable? FREEPORT ROAD AND EASTERN AVENUE ACCESS DRIVEWAY Proposed Driveway Looking Left +500 35 mph -0.6% 251 YES Proposed Driveway Looking Right +500 35 mph 0.1% 249 YES Approaching From Rear on Major Street +500 35 mph 0.1% 249 YES Approaching From Opposite Direction +500 35 mph -0.6% 251 YES FREEPORT ROAD AND BRILLIANT AVENUE ACCESS DRIVEWAY Proposed Driveway Looking Left +500 35 mph -0.2% 249 YES Proposed Driveway Looking Right +500 35 mph 0.1% 249 YES Approaching From Rear on Major Street +500 35 mph 0.1% 249 YES Approaching From Opposite Direction +500 35 mph -0.2% 249 YES REET AND 19th STREET ACCESS DRIVEWAY Proposed Driveway Looking Left 317 25 mph -0.5% 148 YES Proposed Driveway Looking Right 384 25 mph 0.2% 147 YES Approaching From Rear on Major Street +500 25 mph 0.2% 147 YES Approaching From Opposite Direction +500 25 mph -0.5% 148 YES Source: Analysis by Trans Associates determined in accordance with PennDOT Chapter 212, Official Traffic Control Devices, 2006.

FIGURES

PLOTTED: 11/17/2016 8th St Ali St 18th St 19th St 21st St SITE Center Ave Ave Briliant Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Traffic Im pact Sum m ary 7-15-2016\Volum e Figures.dgn N SCALE: N.T.S. Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: Freeport Rd MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Site Location 1 D.B. CZ/MY C.B. MDS REV.

PLOTTED: 11/17/2016 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Traffic Im pact Sum m ary 7-15-2016\Recom m endation Figures.dgn N SCALE: N.T.S. Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Site Plan FIGURE 2 D.B. KBZ C.B. CAJ REV. CTZ

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend - Unsignalized Intersection - Signalized Intersection Highland Park Bridge N SCALE: N.T.S. Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Study Intersections FIGURE 3 D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [326] (510) 265 [4] (0) 2 35 (24) [14] 1 (0) [0] [1] (2) 2 17 (19) [12] [1] (2) 0 501 (339) [378] 1 (1) [2] 35 (27) [16] 1 (1) [4] 14 (29) [22] [3] (4) 3 [218] (563) 223 [22] (16) 1 0 (14) [6] 401 (306) [221] 3 (7) [10] [10] (6) 4 [1] (0) 0 [5] (13) 3 32 (32) [18] 0 (1) [2] 160 (103) [122] [224] (436) 235 [0] (1) 1 15 (44) [22] 380 (497) [341] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 16 (25) [17] 39 (43) [35] 378 (538) [319] 464 (456) [451] 7 (5) [12] [14] (26) 17 [338] (483) 378 [341] (545) 394 [357] (508) 401 [10] (5) 1 [5] (7) 7 [9] (12) 5 11 (15) [12] 9 (17) [33] 472 (506) [480] FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Ali St 19th St O'Hara/Aspinwall 128 (85) [75] 115 (228) [142] SB Ramps [292] (486) 251 [292] (486) 251 [113] (134) 205 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 391 (413) [415] 346 (387) [339] NB Ramps Highland Park Bridge 99 (121) [105] 1 (1) [0] [80] (181) 71 [354] (525) 299 82 (143) [199] 639 (668) [684] [411] (379) 269 70 (52) [32] 9 (9) [15] [31] (97) 8 [746] (792) 541 W estern Ave 10 (12) [12] 640 (741) [817] N 139 (59) [61] 23 (38) [36] [71] (122) 40 [690] (669) 508 SCALE: N.T.S. Center Ave 14 (38) [34] 523 (685) [764] 40 (58) [42] 1 (0) [2] [27] (37) 25 [594] (717) 456 [19] (20) 7 4 (15) [19] Sunoco Dwy Ave 12 (21) [30] 2 (2) [4] Tran s A SS O C IA T ES 512 (657) [685] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [4] (0) 4 [0] (0) 0 [2] (1) 0 [38] (50) 30 [594] (623) 412 [8] (3) 11 River Ave PROJECT NO. PROJECT: TITLE: 56 (51) [39] 1 (0) [0] [4] (12) 4 19 (30) [24] [0] (0) 0 [4] (11) 2 Briliant Ave 8 (5) [2] 2nd Street 25 (26) [31] 443 (823) [670] [37] (42) 41 [27] (63) 69 [576] (580) 368 MOSIT00-15118 19 (25) [21] [27] (28) 8 92 (109) [59] 149 (162) [180] 55 (109) [113] Riverfront 47 Development Transportation Impact Study Delafield Ave [8] (8) 3 2016 Existing Conditions Peak Hour Traffic Volumes [136] (138) 144 55 (101) [100] 382 (737) [679] D.B. C.B. REV. FIGURE 4 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St 17% (17%) 17% 2% (2%) (17%) 19% 8% (8%) (19%) 27% (27%) 27% (27%) 27% (27%) Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 9% Delafield Ave (9%) FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 27% 27% Legend 12% - Arrival Distribution (12%) - Departure Distribution 8% (15%) (27%) [81] (183) 72 Highland Park Bridge 35% (8%) (42%) 15% 50% (50%) N 50% SCALE: N.T.S. (50%) 3% 50% Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 (50%) 47% (3%) (47%) (4%) (43%) PROJECT NO. PROJECT: TITLE: 4% 9% 43% 34% (9%) (34%) MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Primary Trip Distribution ( Access) 5A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St 17% (17%) 17% 2% (2%) (17%) 19% 8% (8%) (19%) 27% (27%) 27% (27%) 27% (27%) Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 9% Delafield Ave (9%) FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 27% 27% Legend 12% - Arrival Distribution (12%) - Departure Distribution 8% (15%) (27%) [81] (183) 72 Highland Park Bridge 35% (8%) (42%) 15% 50% (50%) N 50% SCALE: N.T.S. (50%) 50% 3% Sunoco Dwy (3%) (50%) Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: 53% 4% 9% ARP Access 43% 34% (53%) (4%) (43%) (9%) (34%) MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Primary Trip Distribution ( Access) 5B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St (17%) 2% (2%) (17%) 17% 27% 17% 19% 8% (8%) (19%) (27%) 10% 17% (17%) (45%) (10%) 45% (45%) + 10% 45% + (10%) Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 9% Delafield Ave (9%) FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn (36%) + 10% (36%) + 10% (9%) Legend 12% (12%) - Arrival Distribution - Departure Distribution 5% 3% (6%) 40% + (10%) Highland Park Bridge 9% 1 (1) [0] (5%) (31%) + 13% (3%) 31% + (16%) 6% (31%) + 19% 31% + (19%) (31%) + 19% N SCALE: N.T.S. 31% + (19%) 1% (2%) (29%) 19% Site Access Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 (19%) 29% 18% (1%) (18%) (4%) (43%) PROJECT NO. PROJECT: TITLE: 4% 9% 43% (9%) (34%) MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study 34% Full Development Primary Trip Distribution ( Avenue Access) 6A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St (17%) 2% (2%) (17%) 17% 27% 17% 19% 8% (8%) (19%) (27%) 10% 17% (17%) (45%) (10%) 45% (45%) + 10% 45% + (10%) Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 9% Delafield Ave (9%) FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn (36%) + 10% (36%) + 10% (9%) Legend 12% (12%) - Arrival Distribution - Departure Distribution 5% 3% (6%) 40% + (10%) Highland Park Bridge 9% 1 (1) [0] (5%) (31%) + 13% (3%) 31% + (16%) 6% (31%) + 19% 31% + (19%) (31%) + 19% N SCALE: N.T.S. 31% + (19%) 2% (2%) (29%) 19% 1% Sunoco Dwy (1%) 29% + (19%) Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: 2% 2% (2%) (27%) 20% ARP Access 27% 16% (20%) (2%) (16%) 9% (9%) (34%) MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study 34% Full Development Primary Trip Distribution ( Avenue Access) 6B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 12% (12%) [12%] 12% ( 12%) - A.M. Arrival Distribution - P.M. Arrival Distribution - Saturday Arrival Distribution - A.M. Departure Distribution - P.M. Departure Distribution [ 12%] - Saturday Departure Distribution Highland Park Bridge N SCALE: N.T.S. [-47%] (-47%) -47% [47%] (47%) 47% Sunoco Dwy Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 53% 43%) 53%] ( [ -53% (-53%) [-53%] 53% (53%) [53%] 47% 47%) 47%] ( [ PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Pass-By Distribution ( Avenue Access) 7A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St O'Hara/Aspinwall W estern Ave Ali St 19th St SB Ramps NB Ramps Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 12% (12%) [12%] 12% ( 12%) - A.M. Arrival Distribution - P.M. Arrival Distribution - Saturday Arrival Distribution - A.M. Departure Distribution - P.M. Departure Distribution [ 12%] - Saturday Departure Distribution Highland Park Bridge N SCALE: N.T.S. Sunoco Dwy Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-47%] (-43%) -48% [47%] (43%) 48% PROJECT NO. PROJECT: TITLE: ARP Access 52% 47%) 53%] ( [ -52% (-57%) [-53%] 52% (57%) [53%] 48% 43%) 47%] ( [ MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Phase 1 Pass-By Distribution ( Avenue Access) D.B. C.B. REV. FIGURE 7B MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [-49%] (-50%) -52% [49%] (50%) 52% 48% 50%) 51%] ( -48% (-50%) [-51%] 48% (50%) [51%] 52% 50%) 49%] ( Ali St 19th St [ [ O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 12% (12%) [12%] 12% ( 12%) - A.M. Arrival Distribution - P.M. Arrival Distribution - Saturday Arrival Distribution - A.M. Departure Distribution - P.M. Departure Distribution [ 12%] - Saturday Departure Distribution Highland Park Bridge N SCALE: N.T.S. [-47%] (-47%) -47% [47%] (47%) 47% Site Access Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 53% 53%) 53%] ( [ -53% (-53%) [-53%] 53% (53%) [53%] 47% 47%) 47%] ( [ PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Full Development Pass-By Distribution ( Avenue Access) 8A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [-49%] (-50%) -52% [49%] (50%) 52% 48% 50%) 51%]( -48% (-50%) [-51%] 48% (50%) [51%] 52% 50%) 49%] ( Ali St 19th St O'Hara/Aspinwall [ [ SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 12% (12%) [12%] 12% ( 12%) - A.M. Arrival Distribution - P.M. Arrival Distribution - Saturday Arrival Distribution - A.M. Departure Distribution - P.M. Departure Distribution [ 12%] - Saturday Departure Distribution Highland Park Bridge N SCALE: N.T.S. Sunoco Dwy Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-47%] (-43%) -48% [47%] (43%) 48% PROJECT NO. PROJECT: TITLE: ARP Access 52% 47%) 53%] ( [ -52% (-57%) [-53%] 52% (57%) [53%] 48% 43%) 47%] ( [ MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Full Development Pass-By Distribution ( Avenue Access) D.B. C.B. REV. FIGURE 8B MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St Ali St 18th St 21st St [23] (26) 21 27 (20) [21] 2 (3) [3] 3 (2) [2] 27 (20) [21] [23] (26) 21 [26] (29) 23 10 (12) [11] 13 (9) [10] 30 (22) [23] [37] (41) 33 43 (31) [33] 43 (31) [33] [37] (41) 33 [37] (41) 33 43 (31) [33] 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street [4] (4) 5 4 (4) [4] 4 (5) [4] Delafield Ave [4] (4) 5 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn [37] (41) 33 [37] (41) 33 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 10 (12) [10] 24 (17) [19] 43 (31) [33] Highland Park Bridge [47] (53) 43 12 (9) [10] 67 (48) [52] [20] (22) 19 [67] (75) 62 79 (57) [62] [67] (75) 62 N SCALE: N.T.S. 79 (57) [62] 7 (10) [8] [67] (75) 62 Site Access 55 (65) [59] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [62] (57) 79 [7] (7) 9 [56] (53) 70 [9] (9) 11 [47] (44) 59 PROJECT NO. PROJECT: TITLE: 9 (9) [9] 4 (5) [4] 46 (56) [50] [4] (4) 5 [43] (40) 54 42 (51) [46] MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) 9A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [23] (26) 21 27 (20) [21] [23] (26) 21 2 (3) [3] 3 (2) [2] 27 (20) [21] [26] (29) 23 10 (12) [11] 13 (9) [10] 30 (22) [23] [37] (41) 33 43 (31) [33] [37] (41) 33 43 (31) [33] [37] (41) 33 43 (31) [33] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street [4] (4) 5 4 (4) [4] 4 (5) [4] Delafield Ave [4] (4) 5 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn [37] (41) 33 [37] (41) 33 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 10 (12) [10] 24 (17) [19] 43 (31) [33] Highland Park Bridge [47] (53) 43 12 (9) [10] 67 (48) [52] [20] (22) 19 [67] (75) 62 79 (57) [62] [67] (75) 62 N SCALE: N.T.S. 79 (57) [62] [67] (75) 62 4 (5) [4] Sunoco Dwy 5 (4) [4] 79 (57) [62] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [71] (80) 66 ARP Access PROJECT NO. PROJECT: TITLE: 12 (14) [13] 4 (5) [4] 46 (56) [50] [4] (4) 5 [66] (61) 84 [12] (12) 15 [47] (44) 59 [43] (40) 54 42 (51) [46] MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Primary Peak Hour Traffic Volumes ( Avenue Access) 9B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 (123) - A.M. Peak Hour Traffic Volumes - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] Highland Park Bridge N SCALE: N.T.S. [-3] (-3) -2 [3] (3) 2 Site Access -3 (-3) [-3] 3 (3) [3] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [3] (2) 2 [2] (2) 2 [-1] (-1) 0 [-1] (-1) 0 PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Pass-By Peak Hour Traffic Volumes ( Avenue Access) 10A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 (123) - A.M. Peak Hour Traffic Volumes - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] Highland Park Bridge N SCALE: N.T.S. Sunoco Dwy -1 (-1) [0] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-3] (-3) -2 [3] (3) 2 ARP Access PROJECT NO. PROJECT: TITLE: -3 (-3) [-3] 3 (3) [3] [3] (2) 2 [2] (2) 2 [-1] (-1) 0 MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Pass-By Peak Hour Traffic Volumes ( Avenue Access) 10B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St Ali St 18th St 21st St [23] (26) 21 26 (19) [21] [23] (26) 21 2 (3) [3] 3 (2) [2] 26 (19) [21] [26] (29) 23 10 (12) [11] 13 (9) [10] 29 (21) [23] 42 (30) [33] 42 (30) [33] [37] (41) 33 [37] (41) 33 [37] (41) 33 42 (30) [33] 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street [4] (4) 5 4 (4) [4] 4 (5) [4] Delafield Ave [4] (4) 5 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn [37] (41) 33 [37] (41) 33 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 10 (12) [10] 24 (17) [19] 42 (30) [33] Highland Park Bridge [47] (53) 43 12 (9) [10] 66 (47) [52] [20] (22) 19 [67] (75) 62 78 (56) [62] 78 (56) [62] [67] (75) 62 N SCALE: N.T.S. 7 (10) [8] [-3] (-3) -2 [70] (78) 64 Site Access -3 (-3) [-3] 58 (68) [62] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [65] (59) 81 [7] (7) 9 [58] (55) 72 [9] (9) 11 [46] (43) 59 PROJECT NO. PROJECT: TITLE: 9 (9) [9] 4 (5) [4] 46 (56) [50] [4] (4) 5 [44] (39) 54 42 (51) [46] MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Total Peak Hour Traffic Volumes ( Avenue Access) 11A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St Ali St 18th St 21st St [23] (26) 21 26 (19) [21] [23] (26) 21 2 (3) [3] 3 (2) [2] 26 (19) [21] 0 (0) [0] [26] (29) 23 10 (12) [11] 13 (9) [10] 29 (21) [23] [37] (41) 33 42 (30) [33] 42 (30) [33] [37] (41) 33 [37] (41) 33 42 (30) [33] 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street [4] (4) 5 4 (4) [4] 4 (5) [4] Delafield Ave [4] (4) 5 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn [37] (41) 33 [37] (41) 33 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 10 (12) [10] 24 (17) [19] 42 (30) [33] Highland Park Bridge [47] (53) 43 12 (9) [10] 66 (47) [52] [20] (22) 19 [67] (75) 62 78 (56) [62] [67] (75) 62 [67] (75) 62 N SCALE: N.T.S. 78 (56) [62] 4 (5) [4] Sunoco Dwy 5 (4) [4] 78 (56) [62] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 12 (14) [13] [-3] (-3) -2 [74] (83) 68 ARP Access PROJECT NO. PROJECT: TITLE: -3 (-3) [-3] 49 (59) [53] [69] (63) 86 [12] (12) 15 [49] (46) 61 4 (5) [4] [4] (4) 5 [42] (39) 54 42 (51) [46] MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Phase 1 Total Peak Hour Traffic Volumes ( Avenue Access) 11B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [50] (59) 72 62 (76) [47] 8 (7) [7] 7 (8) [5] 62 (76) [47] [50] (59) 72 [58] (66) 80 34 (28) [24] 29 (35) [22] 69 (84) [52] [81] (94) 114 98 (119) [74] 43 (31) [33] 219 (140) [115] [37] (41) 33 [148] (279) 185 [44] (53) 81 [41] (88) 55 [111] (238) 152 262 (171) [148] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 13 (9) [9] 13 (11) [9] [9] (14) 11 Delafield Ave [9] (14) 11 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 24 (16) [12] 10 (12) [10] [125] (230) 153 [125] (230) 153 [23] (49) 32 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 24 (17) [19] 238 (155) [136] Highland Park Bridge 45 (30) [24] [12] (26) 16 [123] (216) 147 12 (9) [10] 166 (65) [65] [20] (22) 19 9 (5) [5] [5] (10) 6 [138] (228) 160 220 (146) [136] [138] (228) 160 N SCALE: N.T.S. 220 (146) [136] 9 (6) [5] 7 (10) [8] [4] (9) 6 [67] (144) 92 [67] (75) 62 Site Access Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [62] (57) 79 132 (83) [69] 55 (65) [59] [7] (7) 9 [56] (53) 70 PROJECT NO. PROJECT: TITLE: 30 (21) [19] [19] (32) 26 [104] (165) 136 157 (127) [109] MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Full Development Primary Peak Hour Traffic Volumes 13 (11) [9] [9] (14) 11 [95] (151) 125 ( Avenue Access) 144 (116) [100] D.B. C.B. REV. FIGURE 12A MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [50] (59) 72 62 (76) [47] 8 (7) [7] 7 (8) [5] 62 (76) [47] [50] (59) 72 [58] (66) 80 34 (28) [24] 29 (35) [22] 69 (84) [52] [81] (94) 114 98 (119) [74] 43 (31) [33] 219 (140) [115] [37] (41) 33 [148] (279) 185 [44] (53) 81 [41] (88) 55 [111] (238) 152 262 (171) [148] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 13 (9) [9] 13 (11) [9] [9] (14) 11 Delafield Ave [9] (14) 11 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 24 (16) [12] 10 (12) [10] [125] (230) 153 [125] (230) 153 [23] (49) 32 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 24 (17) [19] 238 (155) [136] Highland Park Bridge 45 (30) [24] [12] (26) 16 [123] (216) 147 12 (9) [10] 166 (65) [65] [20] (22) 19 9 (5) [5] [5] (10) 6 [138] (228) 160 220 (146) [136] [138] (228) 160 N SCALE: N.T.S. 220 (146) [136] 9 (6) [5] [4] (9) 6 [134] (219) 154 4 (5) [4] Sunoco Dwy 5 (4) [4] Tran s A SS O C IA T ES 211 (140) [131] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: 21 (12) [10] 12 (14) [13] [10] (23) 15 [57] (121) 77 [71] (80) 66 ARP Access [66] (61) 84 111 (71) [59] 46 (56) [50] [12] (12) 15 [47] (44) 59 MOSIT00-15118 13 (11) [9] [9] (14) 11 [95] (151) 125 Riverfront 47 Development Transportation Impact Study Full Development Primary Peak Hour Traffic Volumes ( Avenue Access) 144 (116) [100] D.B. C.B. REV. FIGURE 12B MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St -1 (-2) [0] -1 (-2) [0] -1 (-2) [0] -3 (-4) [-3] -1 (-2) [0] 2 (3) [3] -1 (-1) [0] [-3] (-3) -3 [3] (3) 3 [3] (2) 2 [2] (2) 2 [-1] (-1) -1 Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 (123) [-1] (-1) -1 [-1] (-1) -1 - A.M. Peak Hour Traffic Volumes - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes Highland Park Bridge -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] [-1] (-1) -1 [-1] (-1) -1 [-1] (-1) -1 N SCALE: N.T.S. [-4] (-4) -3 [3] (3) 2 Site Access -3 (-3) [-3] 3 (3) [3] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [3] (2) 2 [2] (2) 2 [-2] (-2) -1 [-2] (-2) -1 PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Full Development Pass-By Peak Hour Traffic Volumes ( Avenue Access) 13A D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St -1 (-2) [0] -1 (-2) [0] -1 (-2) [0] -3 (-4) [-3] -1 (-2) [0] 2 (3) [3] -1 (-1) [0] [-3] (-3) -3 [3] (3) 3 [3] (2) 2 [2] (2) 2 [-1] (-1) -1 Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 (123) [123] [-1] (-1) -1 [-1] (-1) -1 - A.M. Peak Hour Traffic Volumes - P.M. Peak Hour Traffic Volumes - Saturday Peak Hour Traffic Volumes Highland Park Bridge -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] -1 (-1) [0] [-1] (-1) -1 [-1] (-1) -1 [-1] (-1) -1 [-1] (-1) -1 N SCALE: N.T.S. Sunoco Dwy -1 (-1) [0] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-4] (-4) -3 [3] (3) 2 PROJECT NO. PROJECT: TITLE: ARP Access -3 (-3) [-3] 3 (3) [3] [3] (2) 2 [2] (2) 2 [-2] (-2) -1 MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Full Development Pass-By Peak Hour Traffic Volumes ( Avenue Access) 13B D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [50] (59) 72 61 (74) [47] [50] (59) 72 8 (7) [7] 7 (8) [5] 61 (74) [47] [57] (66) 80 34 (28) [24] 29 (35) [22] 68 (82) [52] [81] (94) 114 97 (117) [74] [34] (38) 30 [47] (56) 84 [44] (90) 57 [113] (240) 154 40 (27) [30] 221 (143) [118] [147] (278) 184 261 (170) [148] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 13 (9) [9] 13 (11) [9] [9] (14) 11 Delafield Ave [9] (14) 11 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 24 (16) [12] 10 (12) [10] [124] (229) 152 [124] (229) 152 [23] (49) 32 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 24 (17) [19] 237 (154) [136] [12] (26) 16 [122] (215) 146 Highland Park Bridge 45 (30) [24] 12 (9) [10] 216 (141) [131] [20] (22) 19 9 (5) [5] [5] (10) 6 [137] (227) 159 219 (145) [136] [137] (227) 159 N SCALE: N.T.S. 219 (145) [136] 9 (6) [5] 7 (10) [8] [4] (9) 6 [63] (140) 89 [70] (78) 64 Site Access 129 (80) [66] 58 (68) [62] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [65] (59) 81 [7] (7) 9 [58] (55) 72 [19] (32) 26 [102] (163) 135 PROJECT NO. PROJECT: TITLE: 30 (21) [19] 157 (127) [109] [95] (149) 124 MOSIT00-15118 13 (11) [9] [9] (14) 11 Riverfront 47 Development Transportation Impact Study Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) 144 (116) [100] D.B. C.B. REV. FIGURE 14A MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [50] (59) 72 61 (74) [47] [50] (59) 72 8 (7) [7] 7 (8) [5] 61 (74) [47] [57] (66) 80 34 (28) [24] 29 (35) [22] 68 (82) [52] [81] (94) 114 97 (117) [74] [34] (38) 30 [47] (56) 84 [44] (90) 57 [113] (240) 154 40 (27) [30] 221 (143) [118] [147] (278) 184 261 (170) [148] Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street 13 (9) [9] 13 (11) [9] [9] (14) 11 Delafield Ave [9] (14) 11 FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 24 (16) [12] 10 (12) [10] [124] (229) 152 [124] (229) 152 [23] (49) 32 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 24 (17) [19] 237 (154) [136] Highland Park Bridge 45 (30) [24] [12] (26) 16 [122] (215) 146 12 (9) [10] 216 (141) [131] [20] (22) 19 9 (5) [5] [5] (10) 6 [137] (227) 159 219 (145) [136] [137] (227) 159 N SCALE: N.T.S. 219 (145) [136] 9 (6) [5] [4] (9) 6 [133] (218) 153 4 (5) [4] Sunoco Dwy 5 (4) [4] Tran s A SS O C IA T ES 210 (139) [131] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [10] (23) 15 [53] (117) 74 [74] (83) 68 PROJECT NO. PROJECT: TITLE: 21 (12) [10] 12 (14) [13] ARP Access [69] (63) 86 108 (68) [56] 49 (59) [53] [12] (12) 15 [49] (46) 61 [93] (149) 124 MOSIT00-15118 13 (11) [9] [9] (14) 11 Riverfront 47 Development Transportation Impact Study Full Development Total Site Peak Hour Traffic Volumes ( Avenue Access) 144 (116) [100] D.B. C.B. REV. FIGURE 14B MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [340] (520) 282 [4] (0) 2 35 (24) [14] 1 (0) [0] [1] (2) 2 17 (19) [12] [1] (2) 0 515 (349) [390] 1 (1) [2] 35 (27) [16] 1 (1) [4] 16 (30) [23] [3] (4) 3 [231] (574) 239 [22] (16) 1 1 (15) [7] 414 (315) [231] 3 (7) [10] [10] (6) 4 [1] (0) 0 [5] (13) 3 32 (32) [18] 0 (1) [2] 168 (106) [127] [14] (26) 17 [238] (447) 253 [0] (1) 1 19 (46) [25] 394 (509) [354] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 16 (25) [17] [358] (496) 404 39 (43) [35] 483 (470) [468] [361] (559) 420 [10] (5) 1 [5] (7) 7 [9] (12) 5 396 (553) [334] 7 (5) [12] 11 (15) [12] [377] (521) 427 9 (17) [33] 491 (520) [497] FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Ali St 19th St O'Hara/Aspinwall 129 (86) [76] 120 (232) [146] SB Ramps [311] (499) 276 [311] (499) 276 [114] (135) 207 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 403 (422) [425] 364 (400) [355] NB Ramps Highland Park Bridge 100 (122) [106] 1 (1) [0] [81] (183) 72 [377] (541) 328 86 (147) [203] 668 (689) [709] [423] (388) 284 71 (53) [32] 9 (9) [15] [31] (98) 8 [781] (815) 585 W estern Ave 10 (12) [12] 672 (765) [846] N 140 (60) [62] 23 (38) [36] [72] (123) 40 [724] (691) 551 SCALE: N.T.S. Center Ave 14 (38) [34] 553 (708) [792] 40 (59) [42] 1 (0) [2] [27] (37) 25 [627] (740) 499 [19] (20) 7 6 (16) [20] Sunoco Dwy Ave Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [4] (0) 4 13 (22) [31] 542 (680) [712] 2 (2) [4] [0] (0) 0 [2] (1) 0 [38] (51) 30 [600] (630) 416 [36] (19) 51 River Ave PROJECT NO. PROJECT: TITLE: 57 (52) [39] 1 (0) [0] [25] (29) 30 19 (30) [24] [0] (0) 0 [30] (37) 6 Briliant Ave 2nd Street 25 (26) [31] 448 (832) [677] 19 (21) [11] MOSIT00-15118 19 (25) [21] [37] (42) 41 [27] (28) 8 95 (113) [62] [32] (69) 71 [603] (607) 375 153 (167) [184] 56 (110) [114] Riverfront 47 Development Transportation Impact Study Delafield Ave [8] (8) 3 [142] (144) 147 56 (102) [101] 395 (758) [693] Opening Year No Conditions Peak Hour Traffic Volumes D.B. C.B. REV. FIGURE 15 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes Highland Park Bridge N SCALE: N.T.S. 3 (1) [1] [-32] (-19) -51 [32] (19) 51-2 (-1) [-1] Site Access Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [25] (29) 30-1 (-1) [-1] -30 (-29) [-25] 19 (21) [11] [1] (1) 1 [30] (37) 6 [34] (38) 6 [-36] (-19) -51 River Ave PROJECT NO. PROJECT: TITLE: -1 (0) [0] [-25] (-29) -30 [0] (0) 0 [-30] (-37) -6 19 (21) [11] -19 (-21) [-11] MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Access Peak Hour Traffic Volumes Rerouted River Avenue to Avenue D.B. C.B. REV. FIGURE 16 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St Ali St 19th St O'Hara/Aspinwall SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes Highland Park Bridge N SCALE: N.T.S. -1 (0) [-2] [19] (20) 7 [-19] (-20) -7 1 (0) [2] Sunoco Dwy 6 (2) [16] -2 (-2) [-4] Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-4] (0) -4 [0] (0) 0 [-1] (-1) 0 River Ave PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Elimination of Sunoco Peak Hour Traffic Volumes 17 D.B. MJY C.B. MDS REV.

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St O'Hara/Aspinwall W estern Ave Ali St Ave 19th St SB Ramps NB Ramps Center Ave Briliant Ave 2nd Street Delafield Ave FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Highland Park Bridge N SCALE: N.T.S. Sunoco Dwy [36] (19) 51 [-36] (-19) -51 Tran s A SS O C IA T ES River Ave Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [-25] (-29) -30 30 (29) [25] -19 (-21) [-11] [-30] (-37) -6 [-30] -37) -6 [36] (19) 51 PROJECT NO. PROJECT: TITLE: ARP Access [25] (29) 30-19 (-21) [-11] 19 (21) [11] [0] (0) 0 [30] (37) 6 MOSIT00-15118 Riverfront 47 Development Transportation Impact Study Rerouted River Avenue to Avenue Access Peak Hour Traffic Volumes D.B. C.B. REV. FIGURE 18 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [363] (546) 303 [4] (0) 2 35 (24) [14] 1 (0) [0] [1] (2) 2 17 (19) [12] [1] (2) 0 541 (368) [411] 1 (1) [2] 35 (27) [16] 1 (1) [4] 18 (33) [26] [3] (4) 3 [254] (600) 260 [22] (16) 1 4 (17) [9] 440 (334) [252] 3 (7) [10] [10] (6) 4 [1] (0) 0 [5] (13) 3 32 (32) [18] 0 (1) [2] 178 (118) [138] [14] (26) 17 [264] (476) 276 [0] (1) 1 32 (55) [35] 423 (530) [377] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 16 (25) [17] [395] (537) 437 39 (43) [35] 525 (500) [501] [398] (600) 453 [10] (5) 1 [5] (7) 7 [9] (12) 5 438 (583) [367] 7 (5) [12] 11 (15) [12] [414] (562) 460 9 (17) [33] 533 (550) [530] FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Ali St 19th St O'Hara/Aspinwall 129 (86) [76] 130 (244) [156] SB Ramps [348] (540) 309 [348] (540) 309 [114] (135) 207 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 427 (439) [444] 406 (430) [388] NB Ramps [81] (183) 72 [424] (594) 371 Highland Park Bridge 100 (122) [106] 1 (1) [0] 98 (156) [213] 734 (736) [761] [443] (410) 303 71 (53) [32] 9 (9) [15] [31] (98) 8 [848] (890) 647 W estern Ave 10 (12) [12] 750 (821) [908] [72] (123) 40 [791] (766) 613 N 140 (60) [62] 23 (38) [36] SCALE: N.T.S. Center Ave 14 (38) [34] 631 (764) [854] 40 (59) [42] 10 (11) [9] [27] (37) 25 [607] (738) 453 [106] (97) 115 5 (15) [21] Site Access Ave 12 (21) [30] 77 (89) [73] Tran s A SS O C IA T ES 515 (650) [700] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [90] (88) 111 [8] (8) 10 [89] (92) 78 [47] (60) 41 [680] (711) 481 PROJECT NO. PROJECT: TITLE: 66 (61) [48] 19 (30) [24] Briliant Ave 2nd Street 25 (26) [31] 513 (909) [738] [36] (73) 76 [647] (646) 429 MOSIT00-15118 23 (29) [25] [41] (46) 46 [27] (28) 8 99 (118) [66] 157 (172) [188] 56 (110) [114] Riverfront 47 Development Transportation Impact Study Delafield Ave [8] (8) 3 [146] (148) 152 56 (102) [101] Opening Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 437 (809) [739] D.B. C.B. REV. FIGURE 19 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [363] (546) 303 [4] (0) 2 35 (24) [14] 1 (0) [0] [1] (2) 2 17 (19) [12] [1] (2) 0 541 (368) [411] 1 (1) [2] 35 (27) [16] 1 (1) [4] 18 (33) [26] [3] (4) 3 [254] (600) 260 [22] (16) 1 4 (17) [9] 440 (334) [252] 3 (7) [10] [10] (6) 4 [1] (0) 0 [5] (13) 3 32 (32) [18] 0 (1) [2] 178 (118) [138] [14] (26) 17 [264] (476) 276 [0] (1) 1 32 (55) [35] 423 (530) [377] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 16 (25) [17] [395] (537) 437 39 (43) [35] 525 (500) [501] [398] (600) 453 [10] (5) 1 [5] (7) 7 [9] (12) 5 438 (583) [367] 7 (5) [12] 11 (15) [12] [414] (562) 460 9 (17) [33] 533 (550) [530] Ali St FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 19th St O'Hara/Aspinwall 129 (86) [76] 130 (244) [156] SB Ramps [348] (540) 309 [348] (540) 309 [114] (135) 207 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 427 (439) [444] 406 (430) [388] NB Ramps Highland Park Bridge 100 (122) [106] 1 (1) [0] [81] (183) 72 [424] (594) 371 98 (156) [213] 734 (736) [761] [443] (410) 303 71 (53) [32] 9 (9) [15] [31] (98) 8 [848] (890) 647 W estern Ave 10 (12) [12] 750 (821) [908] N 140 (60) [62] 23 (38) [36] [72] (123) 40 [791] (766) 613 SCALE: N.T.S. Center Ave 14 (38) [34] 631 (764) [854] 40 (59) [42] 1 (0) [2] [27] (37) 25 [694] (815) 561 [19] (20) 7 10 (21) [24] Sunoco Dwy Ave 18 (26) [35] 2 (2) [4] Tran s A SS O C IA T ES 620 (736) [774] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [4] (0) 4 [0] (0) 0 [2] (1) 0 PROJECT NO. PROJECT: TITLE: 57 (52) [39] 13 (14) [13] [38] (51) 30 [597] (627) 414 [110] (102) 119 19 (30) [24] ARP Access [94] (92) 116 Briliant Ave 2nd Street 25 (26) [31] 445 (829) [674] 68 (80) [64] [12] (12) 15 [79] (83) 67 [36] (73) 76 [645] (646) 429 MOSIT00-15118 23 (29) [25] [41] (46) 46 [27] (28) 8 99 (118) [66] 157 (172) [188] 56 (110) [114] Riverfront 47 Development Transportation Impact Study Delafield Ave [8] (8) 3 [146] (148) 152 56 (102) [101] 437 (809) [739] Opening Year Conditions Peak Hour Traffic Volumes ( Avenue Access) D.B. C.B. REV. FIGURE 20 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [371] (569) 307 [4] (0) 2 39 (27) [15] 1 (0) [0] [1] (2) 2 19 (21) [13] [1] (2) 0 563 (381) [426] 1 (1) [2] 39 (30) [18] 1 (1) [4] 17 (33) [25] [3] (4) 3 [252] (627) 260 [24] (18) 1 1 (16) [8] 452 (344) [252] 3 (8) [11] [11] (7) 4 [1] (0) 0 [6] (14) 3 35 (35) [20] 0 (1) [2] 183 (116) [139] [15] (29) 19 [260] (488) 276 [0] (1) 1 21 (51) [27] 430 (556) [386] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 18 (28) [19] [389] (542) 440 43 (48) [39] 527 (513) [510] [393] (610) 457 [11] (6) 1 [6] (8) 8 [10] (13) 6 432 (603) [364] 8 (6) [13] 12 (17) [13] [410] (569) 465 10 (19) [36] 536 (568) [542] FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Ali St 19th St O'Hara/Aspinwall 141 (94) [83] 131 (254) [160] SB Ramps [339] (545) 299 [339] (545) 299 [125] (148) 227 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 440 (461) [465] 396 (437) [387] NB Ramps Highland Park Bridge 109 (134) [116] 1 (1) [0] [88] (200) 78 [410] (590) 356 94 (160) [222] 728 (752) [774] [462] (424) 309 77 (57) [35] 10 (10) [17] [34] (107) 9 [851] (890) 636 W estern Ave 11 (13) [13] 732 (835) [923] N 154 (65) [67] 25 (42) [40] [78] (135) 44 [789] (754) 599 SCALE: N.T.S. Center Ave 15 (42) [38] 603 (773) [864] 44 (64) [46] 1 (0) [2] [30] (41) 28 [683] (807) 542 [19] (20) 7 6 (18) [22] Sunoco Dwy Ave 14 (24) [34] 2 (2) [4] Tran s A SS O C IA T ES 591 (742) [777] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [4] (0) 4 [0] (0) 0 [2] (1) 0 [42] (55) 33 [656] (688) 455 [36] (19) 51 River Ave PROJECT NO. PROJECT: TITLE: 62 (56) [43] 1 (0) [0] [25] (29) 30 21 (33) [27] [0] (0) 0 [30] (37) 6 Briliant Ave 2nd Street 28 (29) [34] 490 (909) [740] 19 (21) [11] MOSIT00-15118 21 (28) [23] [41] (46) 45 [30] (31) 9 104 (123) [67] [35] (75) 77 [657] (662) 410 167 (182) [201] 61 (120) [125] Riverfront 47 Development Transportation Impact Study Delafield Ave [9] (9) 3 [155] (157) 160 61 (112) [111] 431 (827) [757] Horizon Year No Conditions Peak Hour Traffic Volumes D.B. C.B. REV. FIGURE 21 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [421] (628) 379 [4] (0) 2 39 (27) [15] 1 (0) [0] [1] (2) 2 19 (21) [13] [1] (2) 0 624 (455) [473] 1 (1) [2] 39 (30) [18] 1 (1) [4] 25 (40) [32] [3] (4) 3 [302] (686) 332 [24] (18) 1 8 (24) [13] 513 (418) [299] 3 (8) [11] [11] (7) 4 [1] (0) 0 [6] (14) 3 35 (35) [20] 0 (1) [2] 217 (144) [163] [15] (29) 19 [317] (554) 356 [0] (1) 1 50 (86) [49] 498 (638) [438] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 18 (28) [19] [470] (636) 554 43 (48) [39] 624 (630) [584] [427] (648) 487 [58] (62) 85 [50] (98) 65 [123] (253) 160 472 (630) [394] 229 (149) [131] 12 (17) [13] [557] (847) 649 10 (19) [36] 797 (738) [690] Ali St FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn 19th St O'Hara/Aspinwall 165 (110) [95] 141 (266) [170] SB Ramps [463] (774) 451 [463] (774) 451 [148] (197) 259 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 464 (478) [484] 633 (591) [523] NB Ramps [100] (226) 94 [532] (805) 502 Highland Park Bridge 154 (164) [140] 1 (1) [0] 106 (169) [232] 944 (893) [905] [482] (446) 328 [39] (117) 15 [988] (1117) 795 86 (62) [40] 10 (10) [17] W estern Ave 11 (13) [13] 951 (980) [1059] [78] (135) 44 [926] (981) 758 N 154 (65) [67] 25 (42) [40] SCALE: N.T.S. Center Ave 15 (42) [38] 822 (918) [1000] 53 (70) [51] 10 (11) [9] [34] (50) 34 [729] (948) 587 [106] (97) 115 5 (17) [23] Site Access Ave 13 (23) [33] 77 (89) [73] Tran s A SS O C IA T ES 696 (795) [834] Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [90] (88) 111 [8] (8) 10 [89] (92) 78 [61] (87) 59 [792] (889) 596 PROJECT NO. PROJECT: TITLE: 92 (77) [62] 21 (33) [27] Briliant Ave 2nd Street 28 (29) [34] 666 (1057) [860] [50] (60) 56 [44] (89) 88 [752] (811) 534 MOSIT00-15118 34 (37) [32] [30] (31) 9 117 (134) [76] 180 (193) [210] 61 (120) [125] Riverfront 47 Development Transportation Impact Study Delafield Ave Horizon Year Conditions Peak Hour Traffic Volumes [9] (9) 3 ( Avenue Access) [164] (171) 171 61 (112) [111] 575 (943) [857] D.B. C.B. REV. FIGURE 22 MJY MDS

PLOTTED: 11/17/2016 Sharpsburg 8th St 18th St 21st St [421] (628) 379 [4] (0) 2 39 (27) [15] 1 (0) [0] [1] (2) 2 19 (21) [13] [1] (2) 0 624 (455) [473] 1 (1) [2] 39 (30) [18] 1 (1) [4] 25 (40) [32] [3] (4) 3 [302] (686) 332 [24] (18) 1 8 (24) [13] 513 (418) [299] 3 (8) [11] [11] (7) 4 [1] (0) 0 [6] (14) 3 35 (35) [20] 0 (1) [2] 217 (144) [163] [15] (29) 19 [317] (554) 356 [0] (1) 1 50 (86) [49] 498 (638) [438] 2 (0) [0] [1] (4) 0 [0] (0) 0 [0] (1) 2 18 (28) [19] [470] (636) 554 43 (48) [39] 624 (630) [584] [427] (648) 487 [58] (62) 85 [50] (98) 65 [123] (253) 160 472 (630) [394] 229 (149) [131] 12 (17) [13] [557] (847) 649 10 (19) [36] 797 (738) [690] FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Ali St 19th St O'Hara/Aspinwall 165 (110) [95] 141 (266) [170] SB Ramps [463] (774) 451 [463] (774) 451 [148] (197) 259 Legend 123 - A.M. Peak Hour Traffic Volumes (123) - P.M. Peak Hour Traffic Volumes [123] - Saturday Peak Hour Traffic Volumes 464 (478) [484] 633 (591) [523] NB Ramps Highland Park Bridge 154 (164) [140] 1 (1) [0] [100] (226) 94 [532] (805) 502 106 (169) [232] 944 (893) [905] [482] (446) 328 [39] (117) 15 [988] (1117) 795 86 (62) [40] 10 (10) [17] W estern Ave 11 (13) [13] 951 (980) [1059] N 154 (65) [67] 25 (42) [40] [78] (135) 44 [926] (981) 758 SCALE: N.T.S. Center Ave 15 (42) [38] 822 (918) [1000] 53 (70) [51] 1 (0) [2] [34] (50) 34 [816] (1025) 695 [19] (20) 7 10 (23) [26] Sunoco Dwy Ave Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 [4] (0) 4 19 (28) [38] 801 (881) [908] 2 (2) [4] [0] (0) 0 [2] (1) 0 PROJECT NO. PROJECT: TITLE: 83 (68) [53] 13 (14) [13] [52] (78) 48 [709] (805) 529 [110] (102) 119 21 (33) [27] ARP Access [94] (92) 116 Briliant Ave 2nd Street 28 (29) [34] 598 (977) [796] 68 (80) [64] [12] (12) 15 [79] (83) 67 [44] (89) 88 [750] (811) 534 MOSIT00-15118 34 (37) [32] [50] (60) 56 [30] (31) 9 117 (134) [76] 180 (193) [210] 61 (120) [125] Riverfront 47 Development Transportation Impact Study Delafield Ave [9] (9) 3 [164] (171) 171 61 (112) [111] Horizon Year Conditions Peak Hour Traffic Volumes ( Avenue Access) 575 (943) [857] D.B. C.B. REV. FIGURE 23 MJY MDS

EASTERN AVENUE PLOTTED: 11/17/2016 MAINTAIN EXISTING LEFT TURN LANE PROPOSED 3 PHASE SIGNAL WITH TRAIN PREEMPTION (COORDINATE) ADD 170' LEFT TURN LANE LEGAL RIGHT-OF-WAY LINE 44' FREEPORT ROAD FREEPORT ROAD LEGAL RIGHT-OF-WAY LINE ADD 220' RIGHT TURN LANE MATCH PAINT LINES TO EXISTING PAINT FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Freeport.dgn N SCALE: 1" = 50' Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. MIOST00-15118 PROJECT: Riverfront 47 Development Transportation Impact Study TITLE: Phase 1 Recommendations Avenue Access FIGURE 24 D.B. CTZ C.B. MDS REV. 7/15/16

PLOTTED: 11/17/2016 BRILLIANT AVENUE PROPOSED 3 PHASE SIGNAL WITH TRAiN PREEMPTION (COORDINATE) MAINTAIN LEFT TURN LANE LENGTHEN LEFT TURN LANE FROM 25'TO 150' LEGAL RIGHT-OF-WAY LINE FREEPORT STREET 44' LEGAL RIGHT-OF-WAY LINE LENGTHEN RIGHT TURN LANE FROM 35'TO 225' FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Freeport Briliant.dgn ADD 225'LEFT TURN LANE N SCALE: 1" = 50' ADD 225' THROUGH /RIGHT TURN LANE Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. MIOST00-15118 PROJECT: Riverfront 47 Development Transportation Impact Study TITLE: Phase 1 Recommendations Avenue Access FIGURE 25 D.B. JAB C.B. CAJ REV. 6/28/16

PLOTTED: 11/17/2016 REET PROPOSED 3 PHASE SIGNAL 275' TAPER REET 19TH STREET ADD 275' LEFT TURN LANE ADD 80' LEFT TURN LANE 275' TAPER FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Main - 19th Concept Plan.dgn N SCALE: 1" = 50' EXISTING TUNNEL WITH APPROX. 4' WIDE CENTER SUPPORT COLUMNS Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. MIOST00-15118 PROJECT: Riverfront 47 Development Transportation Impact Study TITLE: Full Development Recommendations 19th Street Access FIGURE 26 D.B. KBZ C.B. CAJ REV. 6/28/16

PLOTTED: 11/18/2016 Sharpsburg 8th St 18th St 21st St Install 2-Phase Semi-Actuated Signal By Ali St 19th St O'Hara/Aspinwall Install 2-Phase SB Ramps NB Ramps W estern Ave Center Ave Ave Briliant Ave 2nd Street Delafield Ave Fully Actuated Signal (Currently Warranted) FILE NAME:P:\MOSIT00\15118 47 Acre Site\Figures\Novem ber 2016 Figures\11-03-2016 Figures.dgn Highland Park Bridge N SCALE: N.T.S. Tran s A SS O C IA T ES Small Firm Client Experience, Big Firm Capabilities 4955 Steubenville Pike, Twin Towers Suite 400 Pittsburgh, Pennsylvania 15205, 412-490-0630 PROJECT NO. PROJECT: TITLE: MOSIT00-15118 FIGURE Riverfront 47 Development Transportation Impact Study Other Recommended Mitigation 27 D.B. MJY C.B. MDS REV.