Minimum Approach Distances (MAD)

Similar documents
NESC WORKSHOP Revisions to Part 4 (Work Rules) Sam Stonerock. October 18, 2016

January 10, EEI OSHA Team

KMU SUBSTATION WORKSHOP

Nordel GRID DISTURBANCE AND FAULT STATISTICS

ARC FLASH HAZARD ANALYSIS

TVPPA Lineman Apprenticeship Program

Medium voltage standard-duty, heavyduty, and extreme-duty single-phase, unfused capacitor units and accessories

POWER PLANT RELAY REPLACEMENT DELIVERABLE ARC FLASH

arc flash hazard analysis

Draft Kenya Standard for Balloting Not to be Cited as Kenya Standard

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2014

: Electric Power Generation, Transmission, and Distribution. Region IV - OSHA

Major Changes. Standard. TECH TOPIC standards and. By Peter Walsh, PE

2017 NWHA TECHNICAL SEMINAR. Arc Flash Hazard Awareness MIKE BRENDLE LLC

This Procedure details the procedures to be followed in order to achieve Safety from the System when:

Engineering Technical Report 128. Risk Assessment for BT Operators Working In a ROEP Zone. Draft for Approval

Why do I need to do an Arc-Flash Analysis?

Arc Flash. Safety 21

September 23, 2016 Site Safe, Inc.

Oval Hanging Rods - User Guide.

S Surge Arresters. Handling and Storage. Standards. Acceptance and Initial Inspection

MIL-STD-883G METHOD

Power Unit 075. Maintain Substation Circuit Breakers

We re good at what we do! Anywhere, TX SITE

Preview to the 2018 NFPA 70E, the Standard for Electrical Safety in the Workplace

Ground Fault Circuit Interrupter(GFCI) Policy

Applications and Considerations Section 11

SUBSTATION EXPLOSION BARRY GASS HIGH VOLTAGE TRAINING. Barry Gass Training Manager High Voltage Training South Africa

Round Hanging Rods + Oval Brackets - User Guide.

Electrical Safety PPT-SM-ELECTSFTY V.A.0.0

Safewaze FS983 Cable Safety Climb System Ladder Mount Instructions

Time Current Curves Series NRX NF and RF Circuit Breakers PXR 20/25 Trip Units

Design Rules for PFC Systems

SG36KTL-M Quick Installation Guide. 1 Unpacking and Inspection

Safe Schools: A Health and Safety Check

Innovative Techniques for Mitigating Arc Flash Exposure

Welcome to a NECA Webinar based on the National Electrical Code. This seminar is the second in a series of electrical grounding and bonding Webinars

Journeyman Team Events

Connection Engineering Study Report for AUC Application: Fortis Okotoks 678S and High River 65S Upgrades

COOPER POWER SERIES. 200 A 15, 25, and 35 kv class portable feedthru installation instructions. Loadbreak Apparatus Connectors MN650037EN

Part 3: Safety Rules for the Installation and Maintenance of Underground Electric Supply and Communication Lines

WLCC BULLETIN. OSHA ET&D 10 Hour Refresher Training

S Surge Arresters

It is essential that the maintenance staff is qualified for electrical works and follows safety procedures.

Evaluation of Effectiveness and Safety of CO 2 Cleaning of Energized Contaminated Pad-Mounted Gear

Selection of Electrical PPE Tables

APPENDIX A. F107 & 380 Lines OYSTER RIVER DURHAM, NH

Required Courses. Total Hours 39

Field Instruction. The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP.

OSCILLATION MONITORING SYSTEM AT TVA

Electrical Safety Program

Leader s Guide ERI Safety Videos

" High Voltage Switch Yards & How Safe are these really" <Peter Rhodes> <Principal and High Voltage Solution. Com Ltd>

APPENDIX A. Appendix A: Fall Hazards Lesson Test Instructor Copy (answers bold/italic), Student copy to distribute follows

Electrical Hazard Assessments: OSHA & The NFPA 70E?

OSHA s Electric Power Standards

BUZZI UNICEM USA PENSACOLA TERMINAL MILTON, FLORIDA

SYSCO ALLARD VILLE DE QUEBEC, QUEBEC, CANADA

Evaluation of Three New Fit Test Protocols for Use with the TSI PortaCount

SG33KTL-M Quick Installation Guide. 1 Unpacking and Inspection

Compliance Is the First Step on the Safety Ladder Understanding the final walking-working surface rule from OSHA and how Honeywell ladder solutions

System Operating Limit Definition and Exceedance Clarification

Leading Edge Self-Retracting Lifelines

Electrical Shore Connections

Summary of Architecture Parallel Session. G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania

Electrical Safety. Unqualified Worker

Regulation Summary: Walking-Working Surfaces & Personal Protective Equipment (Fall Protection Systems); OSHA s Final Rule

Resiliency of Power Systems Earthquake, Wind, Ice, Fire

PSSI 6 Demarcation of Work Areas in Substations

Fall Protection / Open Holes & Guardrail

Original Date of Issue: 04/09

Tower Safety, Coax & RF Fittings, Network Analyzers

COOPER POWER SERIES. 600 A 15, 25 and 35 kv class bushing adapter installation instructions. Deadbreak Apparatus Connectors MN650058EN

USA Mobile, AL Electrical Safe Working Practices

Occupational Protective Equipment

Sub-Base Assembly For Type-ML 32 & VR-1 Step Voltage Regulator Single-Phase Liquid-Filled Part # GEK 35171

FINAL Albertville Business Park AUAR Update Traffic Study

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

POW ER EN GIN EER S, LLC Electrical Engineering, Power, Lighting, Technical Studies and Utility Consulting

UNDERSTANDING ARC FLASH REQUIREMENTS

Functional Example CD-FE-I-029-V30-EN Safety-related controls SIRIUS Safety Integrated

Removing Yourself from Hazards During Equipment Operation

Recent changes in workplace safety regulations have heightened the awareness of hazards associated with electrical arcs.

Rationale for FAC September 2017 August 2018

The Electrical Safety Guide. An Educational Training Manual for Industry Professionals

ELECTRIC OPERATING PROCEDURES Date: 11/01/06

STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests

PSSI 1 High Voltage Switching

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

Traffic Impact Analysis

2018 Public Power Lineworkers Rodeo General Rules for All Rodeo Competitors

CSA Z462 2 nd TO 3 rd EDITION DIFFERENCES CHANGES & UPDATES

70e Training - Electrical Safety in the Workplace

Monitoring of Real-Time SOL and IROL Exceedances

Workshop Information IAEA Workshop

OSHA s new walking working surfaces standards

Professional Arborist Association of Mississippi

You Just Experienced an Electrical Failure, What Should You Do Next? By Don Genutis Hampton Tedder Technical Services

EPIC Rectangular Connector Inserts. HBE Series. Technical Data Number of Contacts:

EPIC Rectangular Connectors HBE Series

Transcription:

Minimum Approach Distances (MAD) The final rule updated OSHA s default values for transient over voltages (TOV), selecting far more conservative values. As TOV is one of the major factors for calculating MAD, this change leaves utilities little option other than to calculate of system specific TOV values. A summary of the impacts follows: By January 31, 2016 the employer shall: Use the default TOV values in the final rule for calculating MAD for voltages above 72.5 kv; or Determine specific TOV values though engineering analysis (MAD for voltages 72.5 kv and below have minor changes).

500 kv Target TOV is 2.4 (per unit) The longest line meets existing TOVs and MAD when considering the existing installed mitigation [2.4] If all lines have line arresters or pre-insertion resistors, then all lines would meet old OSHA MAD even with high speed reclosing [1.8 to 2.3] If some lines do not have mitigation installed, then the high speed reclosing case would exceed old OSHA TOV values and require considerably larger MADs. (Consider one MAD for mitigated lines versus another for unmitigated lines.) [3.6] If a breaker restrike is considered, the TOV climbs and significantly exceeds the old OSHA values as well as new OSHA default rules [4.5] Shorter line lengths have little effect on the TOV for the high speed reclosing.

345 kv The target TOV is 3.0 (per unit) For the longest line, with no mitigation present (for example, line arresters or breaker pre-insertion resistors), at maximum system voltage, clearing a fault with no reclosing yields the worst case TOV of well under 3.0 [1.9] If high speed reclosing is considered with fault clearing, then for the no mitigation case, the TOV exceeds 3.0 [3.6]. This calculates to an additional MAD of 2-0 resulting in a MAD of 11-2 compared to the present MAD of 9-2 Shorter line lengths have little effects on the TOV for the high speed reclosing. Considering the existing mitigation that is in place on this longest line (arresters but no pre-insertion resistors) then the worst case TOV is less than 3.0 [2.4] If just line arresters are considered for TOV mitigation, then even for the high speed reclosing case, the TOV is less than 3.0 [2.4] If just pre-insertion resistors are considered for TOV mitigation, then even for the high speed reclosing case, the TOV is less than 3.0 at [1.9] If a breaker restrike is considered, the TOV climbs and significantly exceeds the old OSHA values as well as new OSHA default rules [4.7]

500 kv & 345 kv System 500 KV System 58 lines Arrestors at both ends = 44 No mitigation = 7 Unknown mitigation = 7 345 KV System 88 lines Arrestors at both ends = 41 No mitigation = 35 Unknown mitigation = 12 Recommendations Reclosing held-off for live line work Investigate unknowns (including foreign TO s) Create two MAD tables (mitigated and unmitigated lines) Assess impact on substation (breaker control cabinet) and tower climbing

MAD Tower Climbing MAD of 9 6 The NESC phase-toground work MAD used in this drawing was determined from NESC Rule 441.A of the 2007 NESC edition and was calculated to include an altitude adjustment (per NESC Rule 441.A.6.b) for elevations up to 4000 feet. The base value used in the calculation (9'-4") was taken from NESC Table 441-2, using an overvoltage factor 'T' of 2.0 and a maximum phase-to-phase voltage of 550 kv, and an additional 2 was added for the increased elevation requirements.

230 kv Target TOV is 3.0 (per unit) For the longest line, with no mitigation present (for example, line arresters or breaker pre-insertion resistors), at maximum system voltage, clearing a fault with no reclosing yields the worst case TOV of well under 3.0 [1.6] If high speed reclosing is considered with fault clearing, then for the no mitigation case, the TOV is less than 3.0 [2.9]. This requires no change to the current MADs. Considering the existing mitigation that is in place on this longest line (arresters but no pre-insertion resistors) then the worst case TOV is less than target [2.9] If just line arresters are considered for TOV mitigation, then even for the high speed reclosing case, the TOV is less than target [2.9] If a breaker restrike is considered, the TOV climbs and significantly exceeds the old OSHA values as well as new OSHA default rules [4.1]

138 kv The target TOV is 3.0 (per unit) For the longest line, with no mitigation present (for example, line arresters), at maximum system voltage, clearing a fault with no reclosing yields the worst case TOV of well under 3.0 [1.7] If high speed reclosing is considered with fault clearing, then for the no mitigation case, the TOV exceeds 3.0 [4.1]. This calculates to an additional MAD of 0-7 resulting in a MAD of 4-5 compared to the present MAD of 3-10. Shorter line lengths have little effects on the TOV for the high speed reclosing. Considering the existing mitigation that is in place on this longest line (rod gaps, arrestors, no reinsertion resistors) then the worst case TOV is less than 3.0 [2.4] If just line arresters are considered for TOV mitigation, then even for the high speed reclosing case, the TOV is less than 3.0 [2.4] If a breaker restrike is considered, the TOV climbs and significantly exceeds the old OSHA values as well as new OSHA default rules [4.3]

115 kv The target TOV is 3.0 (per unit) For the longest line, with no mitigation present (for example, line arresters), at maximum system voltage, clearing a fault with no reclosing yields the worst case TOV of well under 3.0 [1.5] If high speed reclosing is considered with fault clearing, then for the no mitigation case, the TOV exceeds 3.0 [4.1]. This calculates to an additional MAD of 7 resulting in a MAD of 3-11 compared to the present MAD of 3-4. Shorter line lengths have little effects on the TOV for the high speed reclosing. Considering the existing mitigation that is in place on this longest line (arrestors at one terminal only) then the worst case TOV is less than 3.0 [2.5] If a breaker restrike is considered, the TOV climbs and significantly exceeds the old OSHA values as well as new OSHA default rules [3.7]