Automatic LN2 Fill Station Instructions

Similar documents
Chem Bio Liquid Nitrogen Facility

Standard Operating Procedure

THE UNIVERSITY OF NEWCASTLE- DISCIPLINE OF MEDICAL BIOCHEMISTRY. STANDARD OPERATING PROCEDURE PROCEDURE NO: GLP 022 MOD: 1st Issue Page: 1 of 8

Liquid Gas Cylinder (LGC)

MODEL 269DF-LCF-LCF/WS FILLING SYSTEM

DUQUESNE UNIVERSITY. Liquid Nitrogen Safety

from Thames Cryogenics Ltd Total Cryogenic Solutions Cryogenic Cluster Day 22/09/2010

USER MANUAL OPERATION AND THE USE OF A CAR WITH. Diego G3 / NEVO SEQUENTIAL GAS INJECTION SYSTEM

MMRC PVD Evaporator Instructions

Standard Operating Manual

Usage Policies Notebook for Thermco Atmospheric Diffusion Furnace system

BP OIL -- TOLEDO REFINERY

Usage Policies Notebook for Trion RIE / ICP Dry Etch

LIQUID OXYGEN. General. Health Effects. Safety Considerations

Section 1.3: PRESSURE VESSEL COMPONENTS AND SYSTEMS AND COMPRESSED GAS CYLINDERS

THERMAL EVAPORATION UNIT (for Al evaporation)

UNLOADING PROCEDURE OF AN AIRFLOW CONTAINER

Cryogenic Materials Operating Procedure and Safety Requirements

Superconducting Susceptometer (MPMS-5S) Quantum Design Room 296 (MPMS)

Compressed Gases Safety Program

Periodic Survey of Fuel Installations on Ships other than Liquefied Gas Carriers utilizing gas or other low flash point fuels

I. Subject: Medical Gas Systems Utility Failure Interim Procedure III. Purpose:

TEM Lab Chemical Hygiene Plan

Usage Policies Notebook for NanoFurnace Furnace (EasyTube 3000 System)

Page 2 of 10. SOP SF SOP For LN 2 System and LN 2 Freezer Room Operations

Operating Procedures for Metal Evaporator I

Product Manual APPS-160. Designed and Built by: Chart Inc th Street NW New Prague, MN USA (800)

Product Manual. Cryo-Cyl Liquid Cylinder 35/50 LP. Designed and Built by: Chart Inc Airport Dr. Ball Ground, GA USA (800)

OAI Model 200 Tabletop Mask Aligner Portland State University

Eco Snow CO2 Clean System Operation

Updated: Variable Temperature

Cryogenics is the science of ultra low temperatures. Low temperatures are achieved by the liquefaction of gases.

Compressed Gases and Cryogens

CLASSE. L0E Safety Meeting. July 27, 2015

Rev. 1. Cryogenics Thermoflasks. 2122, 2123, 2124, 2129, and 2130

MANAGEMENT OF LIQUID NITROGEN

RULES PUBLICATION NO. 119/P

Each cryogenic liquid has its own specific properties, but most cryogenic liquids can be placed into one of three groups:

Rhino VE CE Bulk Unloader Operator s Card

Cryogenic Equipment. Accessories. Directors. Director Series Storage Vessels Specifications

WELDING, CUTTING AND BRAZING

School of Plant Biology - Liquid Nitrogen Induction

Standard Operating Manual

Vacuum Pumpdown and Venting Procedure, CRaTER Thermal Vacuum System. Dwg. No

BP OIL -- TOLEDO REFINERY

Section - III SYSTEMS DESCRIPTION

Step By Step Instructions for VT Experiments on the Bruker 300 MHz Spectrometer

Product Manual. ADF105 Automatic Dewar Filling Station. Designed and Built by: Chart Inc Landing Parkway Fremont, CA USA (800)

Compressed Gas Properties. Introduction. Compressed Gas Properties. Definition of a Compressed Gas

[USING THE VITROBOT April 9, Using the Vitrobot

Procedure for Filling 2 T Bruker Magnet with Nitrogen

256 Pneumatic Pressure Indicator

Standard Operating Procedure (SOP)

5.1.3 Mechanical Hazards Drive assemblies have sufficient power to cause injury. Keep hands, fingers, clothing and tools clear of moving parts.

Australian Standard The storage and handling of non-flammable cryogenic and refrigerated liquids SWP055

THE UNIVERISTY OF NEWCASTLE - SCHOOL of BIOMEDICAL SCIENCES

Oerlikon Sputtering Evaporator SOP

Cylinder Exchange Training Manual

Standard Operating Procedure Porosity Analyzer - The Micromeritics Tri-Star II (surface area) with Micrometrics VacPrep 061 (Sample Degas System)

PURPOSE OF THE POLICY

Developing Safety Guidelines for Cryogenic Liquids.

Equipment Operating Procedure Glove Box

Home Oxygen Therapy in NHS Scotland. Level 1 Education for Patients & Carers

Confined Space ACOP L101

AUTO FILL STATION USER MANUAL MMR TECHNOLOGIES INC Rev 2

Gianluca Gemme LN2 DISTRIBUTION PLANT

SETUP GBW/GBWE SETUP. upper or lower position. Placing the lock in the upper position will provide 1 foot (305 mm) more height.

B. Working with liquid nitrogen local rules when using the X-ray facility, room 5.20, Flowers building

MJB4 Mask Aligner Operating Procedure. Effective Date: 07/12/2012 Author(s): Jiong Hua Phone:

NO SMOKING WHEN OXYGEN IS IN USE.

Login to ilab Kiosk. Revised 05/22/2018. Load your sample:

University of Minnesota Nano Center Standard Operating Procedure

1 Purpose. 2 Responsibilities. 3 Policy Content ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS. TITLE: CONFINED SPACE ENTRY Document Number: *

Series Environmental Chambers

Liquid Oxygen- Helios & Helios Marathon A Guide for Patients in the Home

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming,

Fokker 50 - Air Conditioning & Pressurization

CryoWiz Liquid Nitrogen Cryogenic Switchover

Plant Isolation Lock out/tag out Procedure

Hazardous Substances Policy - Control Measures POLICY

EXPERIENCE WITH CRYOGENICS SAFETY, PROBLEMS AND SOLUTIONS

Introduction. Medley TM Medication Safety System. Alaris Medical Systems

EMERGENCY EQUIPMENT TABLE OF CONTENTS CHAPTER 8

Operation manual Level sensor DC-LS-50 Operation Manual Level Sensor DC-LS-50

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Compressed Gas Safety Standard

Working with Cryogenic Liquids

USER S INFORMATION MANUAL

COMELEC C-30-S Parylene Coating System

Compressed Gas Cylinder Safety Program April 4, 2017

EHS Laboratory Guidance: Cryogenic Material

March Asher Operation

TANK MANAGER FOR TWO TANKS OPERATING MANUAL. 10/31/11 C-More T6C L color touch panel

1. Cryogen Tanks. N2 Fill Tutorial for Vanderbilt Magnets. Contents: CSB NMR Facility

0RGHO /6 /6/6/6 /LTXLGÃ/HYHOÃ(TXLYDOHQWV

Virtual Pipeline Emergency Response Guide

APPS-160 Gen 2 User Manual

Operation of the mask aligner MJB-55

Compressed Gas Cylinder Safety

OPERATING & HANDLING INSTRUCTIONS

Transcription:

Automatic LN2 Fill Station Instructions Roger Robbins 6/7/2010 Introduction: This is a step by step pictorial instruction document on how to fill a portable Liquid Nitrogen (LN2) Dewar from the Automatic LN2 Fill Station on the back dock of the NSERL Building at UTD. Before you can obtain authorization for this operation, you must be trained by the Clean Room Staff. You must have a knowledgeable buddy with you during the filling operations. No one can ride the elevator with an LN2 Dewar whether it is empty or full. Keys will be issued to authorized and trained representatives of various research groups. Key holders must be the person filling the Dewar if keys are passed to unauthorized users for Dewar filling, disciplinary action will be taken. Be aware that Nitrogen gas does not support life if the Oxygen level in a confined space drops below 19% (normal level is 21%) the space is considered a hazardous space. Also note that N2 asphyxiation may have no symptoms before unconsciousness occurs. THIS IS A HAZARDOUS OPERATION. Instructions: Step 1: Obtain a Buddy to work with you during the LN2 fill operation. (Cleanroom Staff is exempt from the Buddy system) Step 2: If you originate from an upper floor, load the Dewar to be filled onto the elevator and hang the Do Not Enter Liquid Nitrogen Dewar on Elevator sign across the door. Push the Floor 1 button and step out of the elevator. Have your buddy on the first floor to receive the Dewar. 1

Step 3: Roll the portable Dewar to the back dock and set it upright on the floor next to the fill station. Step 4: Fill out the Logbook (Mandatory). Print so we can read it. Step 5: Connect the fill line to the fill tap on the portable Dewar. Step 6: Connect the vent line to the vent tap on the portable Dewar. Step 7: Open both the fill valve and the Vent valve on the portable Dewar 2

Step 8: Unlock the power switch and the LN2 input valve. Step 9: Make sure that the automatic back dock external door is not obstructed Step 10: Turn on the LN2 Fill station the red power on LED will light and the back dock automatic door will open. Step 11: Put on the cryogenic gloves and face mask. Step 12: Open the LN2 Source valve and make sure that the Fill Line Vent Valve is closed. 3

Step 13: Push the FILL button on the front of the fill station console the amber FILLING LED will light and LN2 will flow into the portable Dewar. Note that the portable Dewar pop-off valve will probably spew cold N2 gas. Also note that under some circumstances (empty & warm portable LN2 tank) you may need to hold the FILL button down for just over 3 seconds before the station will start filling. Step 14: When the portable Dewar is full, the fill station will detect a small amount of liquid Nitrogen in the vent line and shut off the fill valve. The green FULL LED will light at this time. NOTE: If the portable LN2 tank is venting through the pop-off valve, the sound will not change when the FULL LED comes on. Step 15: Immediately close the LN2 Source Valve. Step 16: Close both the fill valve and the vent valve on the portable Dewar. 4

Step 17: Immediately open the Fill Line vent valve at the LN2 Fill Station. Step 18: Remove the Vent line from the portable Dewar make sure you are wearing the face mask and cryogenic gloves. Re-hang the line on its hanger. Step 19: Remove the Fill line from the portable Dewar make sure you are still wearing the facemask and cryogenic gloves. Re-hang the line on its hanger. 5

Step 20: Turn off the Fill station power and replace the locks on both the power and LN2 Source valve. The back dock door will automatically close. Step 21: Close the Fill Line Vent Valve at this point. Step 22: Load the Dewar onto a proper transport dolly. Step 23: If your portable Dewar lives on the upper floors, roll the Dewar onto the Freight Elevator and hang the Do Not Enter Liquid Nitrogen Dewar on Elevator sign across the elevator door. Send your Buddy to the home floor to await the arrival of the Dewar. Push the go-to-floor-number button on the elevator control panel and step out of the elevator. Climb the stairs or ride the personnel elevator in the front of the building to your floor and remove the sign and take your Dewar to its home. DO NOT RIDE THE ELEVATOR WITH THE LN2. 6