Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP April 21, 2014 Volume 2, Issue 65 Doug s Corner SSWJV SAFETY QUALITY COURTEOUS RESPONSIVE DEPENDABLE In this issue: Doug s Corner 1 2 Traffic/Active Work 3-4 Construction Notices 5-14 Aerials 15 Project App 16 1
Contractor s Weekly Update NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP Doug s Corner My Week in Pictures https://www.facebook.com/ doug.ststevens See additional Northwest Extension photos on Doug s Facebook Page Use your Smartphones QR reader below... 2
Contractor s Weekly Update Work activities/traffic control week of 4/21/2014 Dunlap Intersection No restrictions 2 lanes East and Westbound w/ left turn lanes Track drainage, systems, guideway curbs Dunlap to Butler One lane both north and southbound will be maintained as well as turns at the signalized intersections Gas, SRP irrigation, ductbank, traffic signals Butler closed 4/26 to 5/9/14 page 5 Butler to Northern One lane both north and south bound will be maintained as well as turns at the signalized intersections Water, gas Northern Intersection One lane eastbound and westbound for sewer removals with potential left turn restrictions thru May 2nd 2014 Night work 8pm-8pm 4/18 thru 4/19/14 Northern to Orangewood One lane both north and south bound will be maintained as well as turns at the signalized intersections Water, sewer, Century Link Morten closed 4/23 to 5/2/2014 page 6 Orangewood closed 4/14-4/26/14 page 7 Water work continues here near the Phoenix Day School for the Deaf Storm drain crews attend to daily housekeeping in front of Chris Ridge Village 3
Contractor s Weekly Update Work activities/traffic control week of 4/21/2014 Orangewood to Glendale One lane both north and south bound will be maintained as well as turns at the signalized intersections Water, storm drain, Century Link Myrtle closed 4/28 to 5/2/2014 page 8 Northview closed 4/22 to 4/29/14 page 9 Glendale Intersection Eastbound shoulder restricted page 10 Glendale to Maryland One lane both north and south bound will be maintained as well as turns at the signalized intersections Roadway widening, OCS, ductbank, storm drain Closures (West) Lawrence, Ocotillo, and Tuckey page 11 Multiple crews carry on with the gas relocations Ocotillo closed 4/3 thru 4/25/14 page 12 Tuckey closed 4/3 thru 4/25/14 page 13 Maryland to Bethany Home Road Roadway widening, water, SRP irrigation Bethany Home Road Intersection BHR one lane both East and Westbound turns maintained thru 4/25/14 Bethany Home Road to Montebello One lane both north and south bound will be maintained as well as turns at the signalized intersections Water Chris Town Mall access changes 4/28 to 5/5/2014 page 14 SSW crews get a lesson in barricading and a small taste of what it s like to be visually impaired from City of Phoenix streets Guru Rick F. This will help all crews as they plan their work! 4
Outreach Coordinators Jessica Blazina (602) 510-5491 Butler Ave Closed at 19th Ave Sewer and Storm Drain Work Traffic Restrictions: April 26th to May 9th (24 hr) No right turn from 19th Ave northbound No left turn from 19th Ave southbound Use Dunlap Ave and Northern Ave as alternate access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 5
Northwest Exten- Outreach Coordinators Jessica Blazina (602) 510-5491 19th Avenue and Morten Sewer Line Installation Traffic Restrictions April 23rd to May 2nd, 2014: 24 Hour Closure No right turn from 19th Avenue (southbound) No left turns from 19th Avenue (northbound) For alternate access use 21st Avenue Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 6
Outreach Coordinators Jessica Blazina (602) 510-5491 Orangewood Closed at 19th Ave Water Installation 24 hour closure Traffic Restrictions: April 14 to April 26, 2014 No left turn from 19th Ave northbound No right turn from 19th Ave southbound Use Morten Ave or Myrtle Ave to 21st Ave as alternate access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 7
Outreach Coordinators Jessica Blazina (602) 510-5491 Northview Ave Closed at 19th Ave Waterline Installation Traffic Restrictions: April 22 April 29 (24 hr) No right turn from 19th Ave southbound No left turn from 19th Ave northbound Use Gardenia and Myrtle as alternate access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 8
Outreach Coordinators Jessica Blazina (602) 510-5491 Myrtle Ave Closed at 19th Ave Waterline Removals Traffic Restrictions: April 28th to May 2nd (24 hr) No left turn from 19th Ave northbound No right turn from 19th Ave southbound Use Orangewood Ave and Glendale Ave as alternate access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 9
Outreach Coordinators Jessica Blazina (602) 510-5491 Glendale and 19th Avenue Civil work Traffic Restrictions: beginning 4/22/14 Eastbound Shoulder restricted (Southwest Corner) Left and right turns will be maintained Curb, gutter, sidewalk, removals and restorations Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 10
Carla Kahn Outreach Coordinator (623) 261-2605 Lawrence, Ocotillo and Tuckey Closures at 19th Avenue Utilities Installation During the Utilities (underground) construction portion of the project, the above streets will be closed periodically. Only one road to be closed at a time. 2 roads or all 3 roads will never be closed simultaneously Use 21st Ave as access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at 11
Outreach Coordinator Jessica Blazina(602)510-5491 19th Ave & Ocotillo - West Side Closure Roadway Widening Traffic Restrictions: April 3, 2014 to April 25,2014; 24 hours No right turns from 19th Ave to Ocotillo Rd (Southbound to Westbound) No left turns from 19th Ave to Ocotillo Rd (Northbound to Westbound) No right turns from Ocotillo Rd to 19th Ave (Eastbound to Southbound) No left turns from Ocotillo Rd to 19th Ave (Eastbound to Northbound) Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at 12
Outreach Coordinator Jessica Blazina(602)510-5491 19th Ave & Tuckey - West Side Closure Roadway Widening Traffic Restrictions: April 3, 2014 to April 25,2014; 24 Hours No right turns from 19th Ave to Tuckey Rd (Southbound to Westbound) No left turns from 19th Ave to Tuckey Rd (Northbound to Westbound) No right turns from Tuckey Rd to 19th Ave (Eastbound to Southbound) No left turns from Tuckey Rd to 19th Ave (Eastbound to Northbound) Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest restriction information, visit the project website at 13
Outreach Coordinators Jessica Blazina (602) 510-5491 Mall Entrance at 19th Ave Water Installation 24 hour closure Traffic Restrictions: April 28 to May 5, 2014 No right turn from 19th Ave northbound No left turn from 19th Ave southbound Use the south Montebello or Bethany for business access Construction dates and restrictions may change, due to weather or unforeseen conditions. For the latest Restriction information, visit the project website at 14