CONTRACTOR S WEEKLY UPDATE February 2nd, 2015 Volume 2, Issue 107 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-5 Construction Notices.6-10 Project App.. 11
CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP DOUG s CORNER MY WEEK IN PICTURES
CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP DOUG s CORNER MY WEEK IN PICTURES Doug St. Stevens
CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP WORK ACTIVITIES AND TRAFFIC CONTROL WEEK OF 2.2.15 Dunlap / 19th Intersection No restrictions Dunlap to Butler One (1) lane both northbound and southbound will be maintained Butler to Northern OCS, duct bank, grading for TPSS building NORTH DUNLAP ORANGEWOOD One (1) lane northbound and southbound will be maintained. Turns at the signalized intersections will be maintained. Northern / 19th Ave Intersection Water line removal, install traffic signal, demo and grade. One lane both eastbound and westbound Northern Avenue Jan 26th thru March 9th. No left turns from Northern to 19th Ave in either direction from February 4th to February 22nd. Northern to Orangewood Duct bank, OCS, roadway widening, water line removal Morten closed west side of 19th Ave Feb 5th through February 12th.
WORK ACTIVITIES AND TRAFFIC CONTROL Orangewood to Glendale Demo asphalt from Orangewood to Myrtle One (1) lane both northbound and southbound will be maintained. Turn lanes at the signalized intersections will be maintained. Glendale / 19th Intersection No restrictions. Glendale to Maryland Construct track, install conduit, form and pour track CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP WEEK OF 2.2.15 SOUTH ORANGEWOOD -MONTEBELLO One (1) lane both northbound and southbound will be maintained. Turn lanes at the signalized intersections will be maintained. Maryland to Bethany Home Road Construct track, duct bank, OCS, form and pour track One (1) lane both northbound and southbound will be maintained. Turn lanes at the signalized intersections will be maintained. Bethany Home / 19th Intersection Turn restrictions - no left turn southbound 19th Ave to eastbound Bethany Home or westbound Bethany Home to southbound 19th Ave February 2nd through February 12th. One lane eastbound and westbound Bethany Home Road February 2nd through February 12th. Bethany Home Road track installation February 12, 2015 to February 17, 2015. No thru traffic on Bethany Home Road at 19th Avenue Feb 12 thru Feb 17th. Right turns only from Bethany Home Rd. eastbound and westbound Feb 12 thru Feb 17. Bethany Home Road to Montebello Guideway curb, duct bank installation, OCS One (1) lane both northbound and southbound will be maintained. Turn lanes at signalized intersections will be maintained.
CONSTRUCTION NOTICE NORTHWEST EXTENSION QUESTIONS? VALLEY METRO Community Outreach Coordinators Carla Kahn (623) 261-2605 Lisa Saldin (602) 495-8213 SSWJV Superintendent Mike Howard (602) 619-5813 Roadway Widening & Paving Northern Ave February 4th, 2015 to February 22nd, 2015 WORK DESCRIPTION Roadway widening and paving. Installation of new sidewalk, curb and gutter. Traffic Restrictions One lane eastbound and westbound Northern Ave. No left turns from Northern Ave to 19th Ave in either direction February 4th through Feb 22nd. STAY CONNECTED Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest facebook.com/valleymetro 24-Hour Project Hotline 602-254-RAIL (7245)
CONSTRUCTION NOTICE NORTHWEST EXTENSION Roadway Widening & Paving QUESTIONS? VALLEY METRO Community Outreach Coordinators Carla Kahn (623) 261-2605 Lisa Saldin (602) 495-8213 SSWJV Superintendent Mike Howard (602) 619-5813 Northern Ave January 26, 2015 to March 9, 2015 WORK DESCRIPTION Roadway widening and paving. Installation of new sidewalk, curb and gutter. Traffic Restrictions Shell access from 19th Ave will be closed. Enter Shell gas station from Northern Ave.. Del Taco access from 19th Ave will be closed. Enter Del Taco from Northern Ave. Restricted to one lane eastbound and westbound Northern Ave. STAY CONNECTED Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest facebook.com/valleymetro 24-Hour Project Hotline 602-254-RAIL (7245)
CONSTRUCTION NOTICE NORTHWEST EXTENSION QUESTIONS? VALLEY METRO Community Outreach Coordinators Carla Kahn (623) 261-2605 Lisa Saldin (602) 495-8213 SSWJV-Superintendent Mike Howard (602) 619-5813 West Morten Avenue Water Line Removal Feb 5th thru Feb 12th, 2015 WORK DESCRIPTION Water line pipe removal, on the west side of 19th Ave. TRAFFIC RESTRICTION Road closure at Morten Ave. west of 19th Ave. Hayward and Orangewood will remain open. Use 21st Ave as alternate access to Morten. STAY CONNECTED Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest facebook.com/valleymetro 24-Hour Project Hotline 602-254-RAIL (7245)
CONSTRUCTION NOTICE NORTHWEST EXTENSION QUESTIONS? VALLEY METRO Community Outreach Coordinators Carla Kahn (623) 261-2605 Lisa Saldin (602) 495-8213 SSWJV Superintendent Mike Howard (602) 619-5813 WORK DESCRIPTION Bethany Home Road & 19th Ave Track Guideway Construction February 2nd through February 12th, 2015 Constructing track and pouring concrete. TRAFFIC RESTRICTION One lane eastbound and westbound on Bethany Home Road. No left turns from 19th Ave southbound to Bethany Home eastbound. No left turns from Bethany Home Rd. westbound to 19th Ave southbound STAY CONNECTED Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest facebook.com/valleymetro 24-Hour Project Hotline 602-254-RAIL (7245)
CONSTRUCTION NOTICE NORTHWEST EXTENSION QUESTIONS? VALLEY METRO Community Outreach Coordinators Carla Kahn (623) 261-2605 Lisa Saldin (602) 495-8213 SSWJV Superintendent Mike Howard (602) 619-5813 WORK DESCRIPTION Bethany Home Road & 19th Ave Track Guideway Construction February 12, 2015 (8pm) to February 17, 2015 (5am) Constructing track and pouring concrete. TRAFFIC RESTRICTION No left turns from 19th Ave (Northbound) No left turns from 19th Ave (Southbound) Right only from Bethany Home Road (Eastbound) Right only from Bethany Home Road (Westbound) STAY CONNECTED Construction dates and restrictions may change. For the latest information, Visit the project website: www.valleymetro.org/northwest facebook.com/valleymetro 24-Hour Project Hotline 602-254-RAIL (7245)
CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP PROJECT APP City of Phoenix