Talk 2 Tree & Wellhead Valve Testing Leak Rate Acceptance. Talk 3 DHSV Control Line hydrocarbon Ingress measurement & acceptability

Similar documents
Well Integrity - Christmas Tree Acceptable Leakage Rate and Sustained Casing Pressure

Is my well safe? Terje Løkke-Sørensen, CTO, add energy

Subsea Safety Systems

117 NORWEGIAN OIL AND GAS RECOMMENDED GUIDELINES FOR WELL INTEGRITY

Subsea Tree Valve Actuator Permanent Reinstatement Systems. Dr Lev Roberts-Haritonov General Manager, Subsea Engineering

Barrier Philosophy for Wells on Gas lift and Ways of Reducing HSE Risks. Alan Brodie Feb 2011 For more info visit

NORSOK Standard D-010 Rev 4, August 2012

Challenging Subsea Gas Lift Application, Offshore Norway.

The report gives a summary of the background and motivation for the audit activity and summarizes the observations made at the meetings.

Engineered solutions for complex pressure situations

PROOF/ÉPREUVE. Part 2: Well integrity. Well integrity for the operational phase. Titre manque. First edition. Reference number ISO/TS :2013(E)

Captain Wellhead & Tree

1. UPDATE 12/12/2014: What wells are regulated under the MIA Program? Must they be drilled, stimulated, and completed? Must they be in production?

31 st Gas-Lift Workshop

NORSOK STANDARD D-002 Edition 2 (2013)

Module No. # 04 Lecture No. # 3.1 Case studies (continued) (Refer Slide Time: 00:10)

Success Paths: A Risk Informed Approach to Oil & Gas Well Control

Why Do Not Disturb Is a Safety Message for Well Integrity

Contact Information. Progressive Optimization Service. We Provide: Street Bay #2. Grande Prairie, AB T8V - 4Z2

BENNEX Advanced Cable Termination ACT Subsea Electrical Termination

APPENDIX A1 - Drilling and completion work programme

2/15/06 Nora Ghobrial

Completion Workover Riser System. Enabling efficient operations by reducing interface complexities and minimizes operational risk

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS

NORSOK standard D-010 Rev. 3, August 2004

International Well Control Forum. Well Intervention Pressure Control Level 2 Syllabus July 2015 Version 7.0

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

COGCC OPERATOR GUIDANCE MECHANICAL INTEGRITY TEST GUIDANCE: PRACTICES AND PROCEDURES

Valve Inspection & Testing

CHE Well Testing Package/Service:

Development of a Subsurface Mudline Packer to Reduce Risk of Flow after Cementing and Sustained Casing Pressure, While Providing a Platform for P&A.

Captains Meeting 2009 Introduction to Well Testing- Expro. Edwin Schoorl

Oil Industry Safety Directorate

IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack)

NORSOK Standard D-010 Rev 4. August 2012

RPSEA UDW Forum June 22 & 23, Secure Energy for America

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

NORSOK STANDARD SYSTEM REQUIREMENTS BOP, DIVERTER AND DRILLING RISER SYSTEM (SYSTEM NO.: 12-30, 12-40)

Decommissioning Ageing Infrastructure: Abandoning or Re-Routing Hydrocarbon Pipelines. Dave Vernon - Director of Isolation Services

HPHT Annular Casing Packer. Obex Annular Casing Packer

SUPPLEMENT Well Control for Drilling Operations Workover & Completion for Drillers Core Curriculum and Related Learning Objectives

IWCF Equipment Sample Questions (Surface Stack)

DRILLING HOSE SOLUTIONS

Casing Design. Casing Design. By Dr. Khaled El-shreef

Colorado Oil and Gas Conservation Commission

Recommended Practice for Analysis, Design, Installation, and Testing of Safety Systems for Subsea Applications

Hose Management Inspection Guidelines for HP Drilling and Production Hoses

Disposal/Injection Well Pressure Test Report (H-5)

Well Testing Operations. Turkey, Istanbul, Points Taksim Hotel. Training Course : One Weeks Training Course In. As Under Details :

API Piping Plan 62: A Reliable Quench System

Every things under control High-Integrity Pressure Protection System (HIPPS)

Perforating Options Currently Available in Horizontal Shale Oil and Gas Wells. Kerry Daly, Global BD Manager- DST TCP

Risks Associated with Caissons on Ageing Offshore Facilities

Leak testing of Valves. Standards for acceptable Rates of Valve Leakage

CTG Certification Protocol -- Version 3.0 SUMMARY

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

Protecting People and the Environment during Stimulation Treatments in Offshore Settings

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD

A Generic Model To Assess Major Incident Frequencies For Offshore Assets

AWHEM RECOMMENDED PRACTICE

Reclassification and Recompletion

New Solutions for Annulus Pressure Management to Avoid Premature Failure in ESP Wells Joe Allan PTC.

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

Performance and Value of the invision System : Offshore in Coiled Tubing Operations

MSC-P and MSC-N Manifolds for Steam Distribution and Condensate Collection

Offshore Managed Pressure Drilling Experiences in Asia Pacific. SPE paper

1 Scope... 2 Functions of cementing float equipment... 3 Definitions... 4 Calibration... 5 Test Categories... 6 General...

PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

BERMAD Fire Protection Hydraulic Control Valves

HIPPS Development Project

Simplicity in VRU by using a Beam Gas Compressor

A practical solution for managing risk during locked to bottom operations

Operating Procedure TITON SUBSEA BOLT TENSIONER

Weatherford Inverse Gas Lift System (IGLS)

White Paper. Electrical control valve actuators on oil and gas production separators

Acoustic Liquid Level Testing of Gas Wells

AADE 2009NTCE-04-04: PRACTICAL ASPECTS AND VALUE OF AUTOMATED MPD IN HPHT WELLS

"Although a good start with a good project, others are as much a hostage of the "human factor".

Beyond Switches for Pump Monitoring:

OIL POLLUTION IN THE ARCTIC - RISKS AND MITIGATING MEASURES

Pressure Relief Valves is there a need when there are EDVs?

Case History. North Sea Platform Wellhead Isolation Tubing Hanger Body Seals Locking Device 20-3/4 x 13-3/8 Mandrel Neck Seal

WELL SUSPENSION AND ABANDONMENT GUIDELINES AND INTERPRETATION NOTES OFFICE OF THE REGULATOR OF OIL AND GAS OPERATIONS

Model 7989T Steel Pipe Squeezer Sch. 40 & Sch. 80. Operations Manual

SWAGED CONNECTION SYSTEM FOR STRUCTURAL & PRESSURE TIGHT APPLICATIONS. Providing Total Solutions Through Swaging Technology

Nye rapporteringskrav til brønnkontrollhendelser Monica Ovesen Petroleumstilsynet (Ptil)

Removal of hydraulic load holding valve incident causing injury

Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1

Improve Reliability of Turbomachinery Lubrication and Sealing Systems

Lockout/Tagout Training Overview. Safety Fest 2013

Intrinsically Safe Acoustic Instrument Used in Troubleshooting Gas Lift Wells

Retrievable Bridge Plugs

3(752/(80 SPECIALTY 3(752/(80 SPECIALTY 5(17$/,1& 5(17$/,1&

TESCOM 50-4X Series Safety, Installation & Start-Up Procedures

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

SUPPLEMENT Well Control for Drilling Operations Workover & Completion for Supervisors Core Curriculum and Related Learning Objectives

INSTALLATION COMMISSIONING, OPERATION & MAINTENANCE MANUAL

Берг АБ Тел. (495) , факс (495) Turning Ideas Into Engineered Solutions KAYDON RING & SEAL, INC.

SEMS II: BSEE should focus on eliminating human error

Acid Gas Progress Report Requirements

Transcription:

Talisman energy COIN Virtual Meeting # 17 26 th January 2011 Darren Bewick Graeme Douglas Martin Forbes David McGuckien Matt Morrison Martin Mosley Talisman Energy UK Ltd (TLMUK), Aberdeen 1

Presentations Offered for VM#17 Slide 2 Talk 1 TLM UK Barrier Philosophy Talk 2 Tree & Wellhead Valve Testing Leak Rate Acceptance Talk 3 DHSV Control Line hydrocarbon Ingress measurement & acceptability

Talk 1 Talisman UK Well Barrier Philosophy Slide 3 When acquiring Norwegian Assets TLMUK assessed well integrity processes for potential standardisation of TENAS & TLMUK Norsok D010 Rev 3 August 2004 was not adopted due to inconsistencies with UK policies and procedures for SCE. Some reasons why D010 not adopted: Premise in UK Regulations is to limit uncontrolled release potential difference in concept / philosophy - containment not barriers D010 examples of Barriers and verification not practical for certain TLMUK scenarios Overly complicated definitions of barriers well barrier, primary well barrier, secondary well barrier, common well barrier element, permanent well barrier, ultimate well barrier stage, well barrier element Prefer more practical guidance on how to manage containment continually, but also particularly during interventions Concentrates on two barriers need to be aware of all barriers (& barrier elements) in the well and often in attached systems Emphasis is on physical barriers less on monitoring and assessment of pressure and continuing confirmation of containment (barriers) TLMUK already had Wellbore Schematics, Completion schematics and use Handover certificates to fully describe all barriers and their status Well Barrier Schematics may not represent the whole story nor current status Norwegian Petroleum Safety Authority - Well control and well integrity 29.01.2008 Well barriers are to prevent unintended influx (kick), cross-flow and outflow to the external environment. The primary well barrier is the first obstacle against undesirable flow from the source. The secondary well barrier prevents further unwanted flow should the primary well barrier fail.

Talk 1 TLMUK Barrier Philosophy Sections Slide 4 2. SINGLE BARRIER CONTAINMENT During normal operation of a well a single physical barrier may be relied upon to provide fluid or pressure containment. A monitored fluid column, adaptor spool, Xmas Tree Body, Instrument Gauge or other single component may be the primary and only containment barrier. For significant periods of the well life-cycle, pressure containment may be reliant upon various single components. The provision of double or multiple barriers or multiple redundant barriers may relate to concern over potential failure of certain types of single barrier. Reasons for having secondary barriers may include: Failure of a barrier in an emergency situation requiring either protection of the failed barrier or secondary containment. The need to achieve a leak-tight combination barrier especially of valves for isolation purposes. Providing a second barrier for the purpose of confirming absence of leakage or verification testing of the primary barrier. Barrier designs where ongoing verification of the primary barrier / seals is not possible secondary or tertiary barrier components being provided as insurance / back-up. 3. REQUIREMENTS FOR DOUBLE BARRIERS The generally accepted oilfield practice is to provide as a minimum two-barrier isolation between the reservoir and all outlets from the Xmas tree / Wellhead and other formations through which the wellbore passes. This practice is particularly important for non-routine well work or for valve repair work when the level of well isolation required must be clearly defined and carefully controlled. Whilst it is generally accepted that a two-barrier system provides for safe operations, it is important to note that: This is not legally binding. It is based on the assumption that a well can sustain natural flow to surface. During normal operation of a well, surface containment of well fluids is reliant upon the Xmas tree body (and associated seals and spools) as a single barrier.

Talk 1 TLMUK Barrier Philosophy Sections Slide 5 4. WELLS GROUP REQUIREMENTS FOR BARRIER INTEGRITY 4.1 ACCEPTANCE OF A SINGLE BARRIER FOR INTERVENTION ACTIVITIES 5. TYPES OF BARRIER 5.1 DRILLING, 5.2 WELL TESTING & DST, 5.3 COMPLETION & WORKOVER,5.4 WELL OPERATION, 5.5 INTERVENTION EQUIPMENT, 5.7 PUMPING OPERATIONS, 5.8 SUSPENSION & ABANDONMENT 6. CATEGORIES OF WELL RISK POTENTIAL 6.1 RISK CATEGORIES AND DEGREE OF PROTECTION 6.2 SUBSEA WELLS 7. CONFIRMATION OF BARRIER INTEGRITY 7.1 BARRIER INTEGRITY TEST PROCEDURES 7.2 CONFIRMING BARRIER INTEGRITY 7.3 TEST FAILURE 7.4 BARRIER LEAK RATE ACCEPTANCE CRITERIA 7.5 INSPECTION & MONITORING 7.6 LEAKAGE FROM SUBSEA WELLS 8. LOSS OF BARRIER INTEGRITY OF THE 5 SAFETY CRITICAL ELEMENTS 9. DISPENSATION FROM BARRIER PHILOSOPHY

Talk 1 TLMUK Barrier Philosophy Part of Process Slide 6 Barrier Philosophy is part of Well Integrity Management Process which includes procedures on; Well Examination, Well Verification, Monitoring, Pressure Testing and procedures for the management of the five well Safety Critical Elements: Xmas tree Integrity Wellhead Integrity Annulus Integrity Down Hole Safety Valve Integrity Well Intervention Equipment Integrity There is also an interface (potential conflict of concepts!) with installation procedures: Mechanical Isolation Breaking Containment Pressure Testing And the Permit to Work ISSOW processes which are open to varying interpretation by different asset teams / individuals! Many issues relating to operational well containment occur during interventions Well Control is separate!

Talk 2 Well Valve Leak Rate Acceptance Criteria Potential for a standard for Operational Tree & wellhead valve testing / verification acceptance criterion? A field Proven Method. Talisman use 2cc per min per inch of valve leak criteria for verification testing of all Xmas Tree and Wellhead valves. Talisman has 12 years quantitative data using this acceptance criteria. This data allows direct comparison of; Effectiveness of maintenance. Reliability of equipment by component, position on well, manufacturer, Well conditions, comparison between assets. 40 times more stringent than API RP14B (ALARP) Once understood by maintenance & testing personnel, provides clarity of interpretation of a measured pressure change / leak rate Time testing a complete well can be shorter Talisman experience of 5000 valve tests per year indicates that valves tested to this criterion can usually be relied on to provide a leak-tight barrier when required for intervention purposes. Slide 7

Talk 2 - API 14B for tree / wellhead valves?

Talk 2 - Talisman Acceptance Criteria Acceptable Pressure Build Up Calculation Insert following data to calculate PBU Valve Bore 2.0625 Inches Enclosed Volume 0.006 Cubic Feet Test Duration 10 Minutes Maximum Acceptable Pressure Build Up Talisman Oil 17353 psi 1180.4 Bar Talisman Water 80978 psi 5508.7 Bar Talisman Gas 17433 psi 1185.9 Bar API 14b Oil 1682667 psi 114467.1 Bar API 14b Water 7852375 psi 534175.2 Bar API 14b Gas 367500 psi 25000.0 Bar Volume Conversions Enter value below from to or 1 m3 6.290 bbl 35.315 cubic ft 0.001 bbl 0.000 m3 0.006 cubic ft 1 cubic ft 0.178 bbl 0.028 m3 Xmas Tree Valves Acceptance Criteria: Table 6 gives the acceptance criteria for the maximum allowable pressure change for the XT valves. The values are the increase or decrease in pressure measured in psi over a ten minute period. Table 6: Pressure change Acceptance Criteria for XT Valves Gas Oil Water FWV (Inflow) 11 psi 11 psi 53 psi FWV (Water inj. Inflow) 553 psi 550 psi 2658 psi UMV 553 psi 550 psi 2658 psi LMV 453 psi 451 psi 2103 psi SV 1335 psi 1328 psi 6199 psi KWV 3381 psi 3365 psi 15705 psi

Talk 2 TLMUK Valve Testing Findings A total of 3729 valve are tests per year applying the Talisman criteria. The results of these tests can be reviewed by valve location, and shows both the As Found and Post Service failure rates. Applying the Talisman leak criteria, approximately 10% of all well valves failed the As Found test, and 3% continued to fail Post Service. Total number of Valves tested during 2008 Total Tested Failed as found Failed post remedial 600 500 472 511 Total number of valves 400 300 200 381 385 385 356 377 183 210 202 267 100 0 72 50 40 51 32 23 11 15 13 10 19 5 6 1 LMV UMV SV FWV KWV GMV MGMV 'A' Ann Valve type Valve inner 39 16 23 1110 8 9 2 'A' Ann Valve outer 'B' Ann Valve 'C' Ann Valve

Talk 2 TLMUK Valve Testing Findings 450 Xmas Valves tested during 2008 Total Tested Failed as found Failed post service 400 401 350 350 356 Total number of Valves tested 300 250 200 150 100 140 145 130 190 194 108 50 0 38 39 44 28 30 18 12 17 19 2 6 0 2 8 14 17 3 3 A B C D E F G H I Offshore Asset

Talk 2 Test Criterion Summary Apart from API RP 14B, which applies to DHSV, there is no standard leak rate criterion for tree and wellhead valves in operational service. API Standards relating to manufactured valve testing are not adopted for field testing of valves. Talisman UK leak rate acceptance criteria of 2 cc/min/inch (0.35 scf/min/inch for gas) proven in use for all tree and wellhead integrity verification testing. This criterion provides a consistent basis for testing a wide range of valve types / configurations under varying well conditions across all TLMUK assets. TLMUK have a history of consistent testing which provides evidence for valve integrity issues (by site, service, manufacturer) and the efficacy of valve maintenance. Operationally, the test criterion also ensures that the valves are maintained with a low leak rate with the benefit of more easily

Talk 3 - DHSV Control Line Hydrocarbon Ingress 6 monthly PMR routines include verification of DHSV and control lines 25 wells have been shown to have hydrocarbon ingress into DHSV / ASV control lines Concerns with Hydrocarbon Ingress: Contamination of the ESD system and potential gas release from open hydraulic fluid system Equalise the pressure in the DHSV control line and re-open the DHSV Early indication of potential operational failure of DHSV Response - Dispensation with Platform standing instructions to shut wellhead Control Line Isolation valve during well shut down Remediation several options (Insert valve, install swellables, modify hydraulics, workover) but need to assess leak risk I ti ti l k t t t d t i i k d

Talk 3 - Aker Qserv LMS system

Catchpot to measure liquid leak rate and fluid quality

Talk 3 DHSV CL Leak Measurement Plan LMS system will allow us to understand the leak rates and potential leak paths Provides quantitative data to determine severity of leak and potential deterioration with time? Field trial on Saltire (five DHSV & ASV) finished 21 st January 2011. Do not have leak measurement data, test durations and gas composition analysis yet. Preliminary indications are that leak rates are all low much less than API 14B Will extend trial to cover all wells with DHSV Control Line ingress during 2011 PMR Campaigns On the basis of findings a plan of appropriate remediation for each well or control system will be developed