Unit 2 Primary Containment Vessel Internal Investigation

Similar documents
Development of a technology to investigate inside the Reactor Primary Containment Vessel (PCV)

Tokyo Electric Power Company Holdings, Inc. November 30, 2017

Leaks from Unit-3 PCV and steam release in a large amount

Analysis of the hydrogen explosion at the Unit-1 Reactor Building

HTR Systems and Components

Series IRV1000/2000/3000

ESA Elbow Sealing Adapter Kit

RB70 Automatic Diluent Valve Maintenance Manual. Version 1.1 November 2006 Written by Tino de Rijk. Page 1 of 23

CS150 CAP STAPLER OWNER S MANUAL

1 THE TEST FACILITY DISCO-C

TOOL BOX 033- HOSEREEL SERVICE / FAULT FINDING

Measure to solve technical subjects in MARICO-2 subassembly retrieval. Experimental Fast Reactor Joyo Oarai R&D Center, JAEA

Type Testing Procedure for Crankcase Explosion Relief Valves

Mitsubishi Heavy Industries Technical Review Vol. 53 No. 4 (December 2016)

System Pressure Manager Standard & System Pressure Manager Plus

ExtendAire TM II. Intermediate Pressure Accessory Kit USER INSTRUCTIONS


TEPCO s Safety Assurance Philosophy on Nuclear Power Generation Plants

ASVAD THE SIMPLE ANSWER TO A SERIOUS PROBLEM. Automatic Safety Valve for Accumulator Depressurization. (p.p.)

MECHANICAL POWER-TRANSMISSION APPARATUS SELF INSPECTION CHECKLIST

VRS Assembly & Operating Instructions

Installation, operating and maintenance Instructions for Seemag bypass level indicator

Auto-Rewind Hose Reels INSTRUCTION MANUAL FOR OXY-LPG MODEL

Model VR6 System. Installation, Operation & Maintenance

OXYGEN ACETYLENE WELDING & CUTTING EQUIPMENT

FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS. This work covers part of outcome 2 of the Edexcel standard module:

INSTALLATION & MAINTENANCE INSTRUCTION

TEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125

User's Manual. MixRite TF 10. Edition 05.08

East Japan Earthquake on March 11, 2011 and Fukushima Dai-ichi Nuclear Power Station

250 ton mt Lattice Crawler Crane

ACCUMULATOR OPERATING & MAINTENANCE INSTRUCTIONS

Description. Lesson Outcomes. Assumptions. Terminology. Welding. Automotive

Instrumentation systems of BWR

Water Weir Flow Controller. Introduction. Safety Precautions. Mounting the Hardware

ATV 90 Y-12 YOUTH 2-STROKE RED (A2004ATB2BUSR) Page 1 of 52 A-ARM, FLOOR PANEL, AND BUMPER ASSEMBLY

SV5 Safety Valve Installation and Maintenance Instructions

WHAT IS GAS TANK/CYLINDER?

SUMMITTM 400 & 600. Natural Gas Barbecues. Step-By-Step Guide

ATD LB PRESSURE BLASTER INSTRUCTION MANUAL

PZN-plus. Application example. Pneumatic 3-Finger Centric Gripper Universal Gripper. Sizes Gripping force 580 N..

INSTRUCTIONS AND MAINTENANCE MANUAL SERIES: RT

(51) Int Cl.: A61B 1/00 ( )

Reliance Industries, LLC Operating instructions for the / Bolt-on D-Ring Anchorage. Model # 3071

INSTRUCTION MANUAL. Gas Salamander

BENEFITS SAMPLERS FOR SUSPENDED SEDIMENT P Watertrap sampler. The winch of the Watertrap is fixed to the railing of a bridge.

INSTRUCTIONS FOR THE 7FT REVOLVER 3-IN-1 MULTIGAMES TABLE

6. EXPERIMENTAL METHOD. A primary result of the current research effort is the design of an experimental

30T A/Manual Hydraulic Shop Press

Gas Cylinder Cabinets

Evaluation of the fraction of Unit-3 vent gas that flowed into Unit-4 reactor building

Summary of the MRA LPG Codes of Practice

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

Rear Drive System SERVICE INSTRUCTION. Specifications SI-R670B

Warning: NEVER ALTER TEST EQUIPMENT

REGISTRATION EXAMINATION, JUNE 2017 CERTIFYING PLUMBER ANSWER SCHEDULE

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

Nuclear safety Lecture 4. The accident of the TMI-2 (1979)

Transferring and Storage

Air Tractor Preventative Maintenance Manual And Troubleshooting

Periodical surveys of cargo installations on ships carrying liquefied gases in bulk

DETAILS OF THE ACCIDENT PROGRESSION IN 1F1

Miniball Coulomb Excitation Target Chamber

Alkylphosphines. Storage and Handling Recommendations

Armatures for analytical probes

Responding to Natural Gas Pipeline Emergencies

HCMTCB MATERIALS SAMPLING & TESTING PERFORMANCE CHECKLIST

Portable Soccer Goal Safety Program

STRONGMAN. High Security U-Lock 100% HARD. ENGLISH 2-x DEUTSCH x-x ESPANOL x-x ITALIANO x-x JAPANESE x-x FRENCH x-x. LOCKS BY KNOG

Unit 24: Applications of Pneumatics and Hydraulics

General Inspection Guidance for Waste Management Units Requiring Air Emission Controls Under RCRA Air Standard Subpart CC

USER MANUAL. MACMAG magnetic separator MHK MHF

IMCA Safety Flash 10/11 September 2011

Surface exploration drilling

Hot Tapping Machine. OPERATIONS MANUAL and OPERATING INSTRUCTIONS

Hatch Sure MkII Inspection of Watertight Doors

GAS STRUT SAFETY INFORMATION

Installation and Operating Instructions for Automotive Winch Synthetic Rope

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS])

WFO-*P Series Floor Diffuser - Plenum installation and maintenance instructions

Power Supply Facilities Failure (Units 3-4 Temporary M/C (A), etc.) March 22, 2013 Tokyo Electric Power Company

GUIDELINES FOR CONDUCTING HYDROGENATION REACTIONS

PERMA-CYL 230/450/1000/1500/2000. Installation Manual Manual # Revision B

IC67 - Pre-Instructional Survey

1.0 - OPENING AND CLOSING THE DOOR

Components for air preparation and pressure adjustment. OUT port position ( ) connected Rear side. of IN port. Air tank. directly.

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL

Crystal Spring Feeder Protocols

A Rationale for Pressure Relief Device(s) Qualification Requirements (LH2)

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

LUBRICATOR ASSEMBLY AND OPERATING INSTRUCTIONS

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT

DPZ-plus. Application example. Pneumatic 3-Finger Centric Grippers Sealed Grippers. Gripping force 520 N N. Sizes

The Nitrogen Threat. The simple answer to a serious problem. 1. Why nitrogen is a risky threat to our reactors? 2. Current strategies to deal with it.

INSTALLATION INSTRUCTIONS

Allspeeds Ltd. Royal Works, Atlas St Clayton le Moors Accrington Lancashire England BB5 5LW. Tel +44 (0)

Latvin Luxury Shower Panel. Telephone Product Specification. ~ Minimum Working Pressure 1.0 bar ~ Maximum Working Pressure 3.

COMMON PRECAUTIONS Data Sheet - Be Sure To Read Before Handling Page 1 of 6

Tripod Setup Guide (M-TPx)

Universal Elevator Mount Owners Manual Customer Service Center N53 W24700 South Corporate Circle Sussex, WI U.S.A.

Transcription:

Unit 2 Primary Containment Vessel Internal Investigation December 21, 2017 Tokyo Electric Power Company Holdings, Inc.

1. Conditions inside the Unit 2 Primary Containment Vessel According to accident development analysis, it is assumed that part of the melted fuel fell to the plenum at the bottom of the Reactor Pressure Vessel (RPV) or onto the pedestal, with some still remaining in the core. PCV Internal Investigation January, March 2012 Muon measurement suggests that most of the fuel debris is at the bottom of the RPV. FW CS Muon measurement suggests that there is fuel on the outer periphery of the core X-53 penetration It is assumed that there is a hole either at or near the center of the RPV based on the conditions of the surrounding CRD observed during the PCV Internal Investigation and from the damage seen to grating. X-6 penetration Pedestal Internal Investigation January, February 2017 CRD Rail Investigation August 2013 Past Investigation Area Steam was observed during the PCV Internal Investigation. 1

2. Primary Containment Vessel Internal Investigation results in Jan. Feb. 2017 It was found that a part of grating was missing during the pre-investigation of the inside of the pedestal conducted through the guide pipe during the Primary Containment Vessel (PCV) Internal Investigation from January to February, 2017. Lower part of CRD CRD housing support brackets PIP cable CRD replacer Access to underground Platform Slot Opening Pedestal TIP guide pipe support Fallen grating Flat bar Slot opening CRD rail end Reference Inside Unit 5 pedestal Fallen object TIP guide pipe support Deformed grating Flat bar Area not complied with image processing TIP guide pipe Reference Photo taken during periodic inspection inside Unit 2 pedestal The TIP guide pipe and its supports were removed to inspect Unit 5. Images provided and processed by the International Research Institute for Nuclear Decommissioning (IRID) 2

3. Outline of the next PCV Internal Investigation Plan :Conditions under the platform where fuel debris may exist will be examined. Investigation area Pedestal Pedestal opening Control Rod Drive (CRD) replacement rail Primary Containment Vessel(PCV) Point where investigation unit will be lowered It may not be possible to lower the unit due to condition below the platform RPV Control Rod Drive (CRD) Housing PCV penetration pipe used before (X-53 penetration) Approx. 7.2m Platform PCV penetration pipe to be used (X-6 penetration) Area to be investigated Access hatch for workers Basement 3

4. Investigation method (1/2) The telescopic device used in the PCV internal investigation conducted between Jan. to Feb. 2017 will be improved so that it can extend further and has an investigation unit (camera, dosimeter and temperature gauge) affixed to the end. After the investigation device reaches the area above the missing part of the grating inside the pedestal, the investigation unit will be lowered to examine under the platform. This improvement will enable the investigation device to reach the end of the guide pipe inside the pedestal, much further than during the investigation conducted in January~February, and allow conditions above the platform, such as the CRD housing, to be reexamined. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters (extendable pipe) Pedestal PCV penetration pipe (X-6 penetration) Platform Cable drum Alternative shield Cable Control Rod Drive Cable feeding machinery Birdʼs eye view camera Investigation unit Dosimeter, Temperature gauge Investigation end device overview Pan-tilt camera, light Outline of pre-investigation inside the pedestal (Telescopic investigation device) 4 Images provided by the International Research Institute for Nuclear Decommissioning (IRID)

4. Investigation method (2/2) Just like the PCV internal investigation conducted in January~February, a boundary will be formed as shown below by sealing the sliding part of the guide pipe with double O-rings and pressurizing the pipe with nitrogen to prevent gas inside PCV from leaking outside and affecting the surrounding environment during the investigation. A similar boundary will be formed for the sliding part of the cable as well. Dust concentration will be monitored during the operation to check that gas inside the PCV does not leak or affect the surrounding environment. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters (extendable pipe) Pedestal PCV penetration pipe (X-6 penetration) Platform Cable drum Control Rod Drive Pressured nitrogen Isolation valve (open) Inside of PCV Cable Boundary Pressured nitrogen Sliding part of guide pipe is sealed with O- rings. Sliding part of cable is sealed with O-rings. Sliding part of cable sealed Pan-tilt camera, lighting 5

5. Main equipment improvements (1/4) No. Coming investigation Previous investigation 1 2 3 4 Guide pipe and extendable pipe have been lengthened. End of the device can reach about 1.4m from the inside wall of the pedestal. Lowering mechanism added. (Cable feeding mechanism added) Dosimeter and temperature gauge mounted in addition to camera Fogging countermeasures added. (Distance between camera and light can be adjusted to improve visibility.) End of the device could reach about 0.1m from the inside wall of the pedestal. No lowering mechanism Only camera mounted Distance between camera and light was fixed. 6

5. Main equipment improvements (2/4) 1 Lengthening of guide pipe and extendable pipe The guide pipe has been lengthened by making the investigation device on the end (investigation unit) smaller and lighter, and by strengthening the guide pipe. End device used during the previous investigation Smaller and lighter end device (investigation unit) Pedestal End device can reach approx. 1.4m this time. Guide pipe Extendable pipe End device could only reach approx. 0.1m previously. 7 Images provided by the International Research Institute for Nuclear Decommissioning (IRID)

5. Main equipment improvements (3/4) 2Lowering mechanism, 3dosimeter and temperature gauge Cable feeding mechanism 2 Can lower the unit on a cable. Investigation Unit Birdʼs eye view camera Camera Skirt to prevent from mixing with alien substances and jamming Light Before being lowered on cable Dosimeter, Temperature gauge Cable winding motor Timing belt Details of cable feeding mechanism When lowered on a cable Tilt axis Pan axis 3Temperature gauge and dosimeter mounted Investigation End device outline view 8 Images provided by the International Research Institute for Nuclear Decommissioning (IRID)

5. Main equipment improvements (4/4) 4 Fogging countermeasures Distance Light between camera transmission :100% and light Distance:5m Before countermeasures: Approx. 5cm Light transmission : 20%/3m Distance :5m Image before processing Image after processing 4 Distance between camera and light can be enlarged. Original position When light is distanced After countermeasures: Approx. 10cm Camera Light Previous investigation Motion of light when responding to fog (concept diagram) 9 Images provided by the International Research Institute for Nuclear Decommissioning (IRID)

6. PCV internal investigation point CRD housing Telescopic investigation device Grating missing1 Grating missing2 Investigation route CRD replacement equipment Platform Investigation point Expected information Lower part of the CRD housing Damage to lower part of the CRD housing CRD rail Hole (may 垂直断面図 not exist) Intermediate operation mount Cable tray Upper part of the platform Intermediate operation mount Conditions above the grating (fallen objects, fuel debris deposits, etc., missing grating) Conditions above the grating (fallen objects, fuel debris deposits, etc., missing grating) Hole (may not exist) Pedestal bottom Fallen objects on the pedestal bottom and fuel debris deposits, etc. Damage to cable tray(to assume whether fuel debris has fallen to the pedestal base) Pedestal bottom Access hatch for workers Access hatch for workers Damage to the cable tray to assume whether debris leaked outside the pedestal 10

7. Process flow plan Operation FY2017 December January February Advance preparation Training As of 12/21 Shipping On site preparation PCV internal investigation PCV internal investigation 11