Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime

Similar documents
SHELL FLAGS INSPECTION CASE STUDY

EMERGENCY PIPELINE REPAIR SYSTEMS DEVELOPED TO FACILITATE PIPELINE REPAIR OF UNPIGGABLE DEFECTS. By: Dale Millward, STATS Group, United Kingdom

Emergency Pipeline Repair Isolation System

USE OF ISOLATION STOPPLES FOR VALVE REPLACEMENT ON TRANS ALASKA PIPELINE

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

BACK PRESSURE / SUSTAINING

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

BACK PRESSURE / SUSTAINING

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

High-Pressure Boiler Inspection Procedures: A Complete Checklist

Efficient Pigging of Gathering Lines. Energy Management Workshop for Upstream and Midstream Operations

Reduce Turnaround Duration by Eliminating H 2 S from Flare Gas Utilizing VaporLock Scrubber Technology

Bermad Pressure Reducing. Model: 42T

Risks Associated with Caissons on Ageing Offshore Facilities

THE NATURAL CHOICE. High end valves for the natural gas value chain. Inspired By Challenge

Caltec. The world leader in Surface Jet Pump (SJP) and compact separation systems for upstream oil and gas production enhancement

Completion Workover Riser System. Enabling efficient operations by reducing interface complexities and minimizes operational risk

Every things under control High-Integrity Pressure Protection System (HIPPS)

Protecting People and the Environment during Stimulation Treatments in Offshore Settings

Decommissioning Ageing Infrastructure: Abandoning or Re-Routing Hydrocarbon Pipelines. Dave Vernon - Director of Isolation Services

Wedge Type Flow Meter Installation and Operation Manual

Flexible Engineered Solutions International CALM Buoy Swivels

Lockout / Tag out Program

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e.

FV Flash Vessel Installation and Maintenance Instructions

Model: 720-UL INSTALLATION OPERATION MAINTENANCE. Bermad Pressure Reducing Valve IOM. Model: FP -720-UL Sizes: 2"-12" BERMAD. Application Engineering

NORMAL OPERATING PROCEDURES Operating Parameter Information

Eliminating Medical Gas Shutdowns for 10 years

Improve Reliability of Turbomachinery Lubrication and Sealing Systems

MULTI-DIAMETER, BI-DIRECTIONAL PIGGING FOR PIPELINE PRE-COMMISSIONING

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Best Practice RBI Technology Process by SVT-PP SIMTECH

N2 Membrane+ Nitrogen Production Systems for Offshore. Where you are. Where you need to be. We are here too.

OPERATING PROCEDURES

FUNDAMENTALS OF PRESSURE RELIEF VALVES IN NATURAL GAS INSTALLATION - OPERATION - MAINTENANCE. Gary S. Beckett

Entry Level Requirements and Basic Introductory Course Outline for New Remotely Operated Vehicle (ROV) Personnel

ABIOSH INT L TECHNICAL CERTIFICATE IN OIL AND GAS SAFETY OPERATIONS (ONSHORE & OFFSHORE)

Periodic Survey of Fuel Installations on Ships other than Liquefied Gas Carriers utilizing gas or other low flash point fuels

ECS Protector Nitrogen Inerting Vent (PAV-WN)

TECHNICAL DATA Q= C. Table 1 - Specifications

Subsea Safety Systems

TECHNICAL DATA. the Viking Pilot Pressure Regulating Valve 1 Model A-1 Speed Control Assembly: OBSOLETE. the Viking Speed Control Assembly 1

E. MENDOZA, C. KEMPEN, Y. ESTERKIN, S. SUN, K. SUSKO and J. GOGLIA

Troubleshooting Lift Cylinder Drift and Tilt Cylinder Drift

BRINGING A NEW DIMENSION TO PIPELINE PIGGING. By: David Aitken, Aubin Group, UK

Flexibility Enhancements for Gas Turbines

Engineered solutions for complex pressure situations

Fuel Gas Pressure Control Solutions for Fired Heaters and Boilers

HIPPS Development Project

CHE Well Testing Package/Service:

Model: 43T. Bermad Pressure Relief Valve

RULES PUBLICATION NO. 119/P

2/15/06 Nora Ghobrial

TECHNICAL DATA. than the water inlet pressure to the concentrate

SEMS II: BSEE should focus on eliminating human error

WELL SCAVENGER. Versatile wellbore clean-up tool for the most demanding operations

Dynamic Underbalance (DUB)

Fully integrated solutions for improving safety, emissions control and product integrity

Isolation Lockout and Tagging

UNPIGGABLE NO MORE! PRACTICAL SOLUTIONS FOR CHALLENGING PIPELINES

Compiled by: B Beard. Approved by: SH Carstens. Description of requirements and procedures for compact provers to be used as verification standards.

THE IMPACT ON ENERGY CONSUMPTION CAUSED BY PRESSURE DROP IN A COMPRESSED AIR SYSTEM

TECHNICAL DATA. Table 1 - Specifications

OPERATING INSTRUCTIONS Pressure Control System PCS-20 through PCS-100

Installation Operation Maintenance. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow IOM.

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

ONSITE PROVING OF GAS METERS. Daniel J. Rudroff WFMS Inc West Bellfort Sugar Land, Texas. Introduction

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project

Type 1367 High-Pressure Instrument Supply System with Overpressure Protection

Internal Communication Systems for Maritime Operations. Ensuring safety and efficiency with clear and reliable communications

Connect with Confidence NO POWER NO PROBLEM

SA121, SA122, SA123, SA128 and SA1219 Self-acting Temperature Control Systems (Dial Adjustment)

Dynamic Simulation of the Norne Heidrun 10 x 16 Dewatering Pig

Why Do Not Disturb Is a Safety Message for Well Integrity

UIB30 and UIB30H Sealed Inverted Bucket Steam Traps for use with Pipeline Connectors

Performance Monitoring Examples Monitor, Analyze, Optimize

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks

Type S301 & S302 Gas Regulators INTRODUCTION INSTALLATION. Scope of Manual. Description. Specifications. Type S301 and S302. Instruction Manual

22. Specialty Valves.

Total Tank Protection

INSPECTION OF MULTI-DIAMETER PIPELINES OPERATING AT LOW PRESSURE. Stefan Vages > ROSEN Group

1 Scope... 2 Functions of cementing float equipment... 3 Definitions... 4 Calibration... 5 Test Categories... 6 General...

Safety Selector Valves Dual Pressure Relief Device System

Energy Control Procedures Lockout/Tagout 29 CFR

Committee on NFPA 85

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

I T T Pressure Reducing Valve WARNING INSTALLATION, OPERATION, AND MAINTENANCE MANUAL

Significant Change to Dairy Heat Treatment Equipment and Systems

"Although a good start with a good project, others are as much a hostage of the "human factor".

TSS21 Sealed Thermostatic Steam Tracer Trap

TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

TITAN FLOW CONTROL, INC.

APPLYING VARIABLE SPEED PRESSURE LIMITING CONTROL DRIVER FIRE PUMPS. SEC Project No

A hose layline contains important information for specifying the replacement assembly: manufacturer, hose trade name, working pressure and hose ID.

Model 420-HY Pressure Regulating Hydrant Valve

GAS COMPRESSION SYSTEM

Air Eliminators and Combination Air Eliminators Strainers

QuickHeat TM Packaged Heat Exchanger Solutions

Transcription:

CASE STUDY CS15-02 >> Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime What s Inside:» Explore Double Block & Monitor» Increase Operational Safety» Achieve Double Barrier Compliance» Reduce Disruption to Flow» Minimize Environmental Impact IN RECENT YEARS, OFFSHORE PIPELINE OPERATORS around the globe have come under intense pressure from regulatory bodies to prove and meticulously maintain the structural integrity of their networks. As a result, improving the efficiency of platform valve replacements has become a top priority. Several valve isolation options are available to offshore operators. However, non-intrusive inline isolations have become standard due to their excellent safety record and their ability to decrease downtime. As a case in point, we will explore the usage of non-intrusive inline isolation to replace an emergency shutdown valve (ESDV) on a spar platform located in the Gulf of Mexico. Executing a valve replacement is a complex operation that requires extreme precision and comprehensive planning to ensure that affected sections of pipe are securely isolated from pressure in the line before work commences. The challenge is to preserve safety while minimizing disruptions in flow. After examining a number of options, including both intrusive and non-intrusive isolation techniques, and inert purging, the operator chose a non-intrusive inline isolation using double block and monitor technology. As a result, the multi-valve replacement was executed successfully safely, on schedule, and without having to bleed down the line. T.D. Williamson 1

THE NEED In 2011, the operator of a spar platform located 320 Piping and Instrumentation Diagram kilometers (200 miles) off the coast of Louisiana made plans to replace an ESDV on a riser gas export pipeline because the valve had reached the critical limit for internal passage. The initial scope of the project included the isolation of a 16-inch riser connected to a Sales Gas Skid 42105 42106 KZ-4210 To PSV PT 42102 subsea pipeline network so the valve could be replaced. To Closed Drain Tank BSSE regulations mandate SDVs close within 45 seconds of emergency shutdown or sensor activation. 42102 SDV 42104 PXT 42101 To Fuel Gas Buy Back 42103 SDV 42101 PG 42104 Valve 1 (to be replaced) Valve 2 (to be replaced) After a series of preliminary risk assessments and piggability tests, the operator made the decision to expand the project scope and use the line isolation as an opportunity to replace two additional valves and install a launcher extension. Adding the extension would expand pigging capabilities by enabling the launcher to accommodate longer tools, thus facilitating future inline inspection tool runs. Beyond replacing the faulty ESDV for safety purposes, installing the new valves was critical to the operation of the platform due to Bureau of Safety and Environmental Reinforcement (BSSE) regulations that mandate ESDVs Valve close within 45 seconds of emergency shutdown (ESD) or sensor activation. SmartPlug tool provides double block and monitor isolation The operator asked T.D. Williamson (TDW) to provide all engineering-related work for the valve replacements, which included collaborating with the operator to select HV 42107 the isolation methodology, along with all necessary inspections and factory acceptance testing (FAT), communications tests, and friction pull-tests. PROJECT CHALLENGES Valve 3 (to be replaced) PV 2 To Gas Pipeline As is the case with any offshore operation, minimizing loss of production and maintaining the highest level T.D. Williamson 2

of safety on the platform were critical to successfully executing the valve replacements. Although the ESDV was experiencing an unacceptable internal passage rate, it did not present the same immediate safety threat to the platform or environment that an external leak would have. However, if unaddressed, it could have resulted in a number of regulatory issues for the operator had the passage rate continued to increase. In order to execute the valve replacements, a number of isolation techniques were considered:» Due to its impact on downstream operations, fully decommissioning the line and bleeding the affected section of pipe was a last resort for the operator.» It was determined that inert purging the line would result in more downtime and cost than an inline isolation, and because of this, it was removed from consideration.» A hot tap and bypass solution would have enabled product to continue to flow; however, for additional safety and operational purposes on the platform, it was deemed impractical.» The operator and TDW decided a non-intrusive, inline isolation utilizing double block and monitor technology would be the best fit for the project. In this context, double block and monitor entails isolating a section of pipe upstream of the valve using two independent plugs/modules. During the process, integrity of the two module seals is tracked by continually monitoring the contained pressure in the annulus. Any fluctuation in annulus pressure will alert personnel if a seal is compromised (see infographic on pg. 4 ). This approach avoids the need to vent product within the line and eliminates creation of a potential leak path between the two modules, ensuring that additional risk is not created and the inline isolation remains inherently safe. To ensure the highest level of safety, it was determined that the double block and monitor methodology used to isolate the gas export line should remain in accordance with all criteria outlined by DNV- RP-F113/3 for the definition of a Double Barrier. 1. Each Barrier Must Retain Full Pressure Alone: Each plug module must be capable of fully isolating the pipeline on its own. In addition, the pipeline stress induced by a single module at full pipeline pressure has to remain within the safety limits of the pipeline operation, so as to not put the pipeline at risk. (The introduction of a second plug module and the stepping down of the pressure across the two seals spreads the pipeline stress across both modules, further reducing the stress during a full line isolation.) 2. Each Plug Must Have an Independent Locking System: Each plug module must have its own locking system (slips). These slips are independent of one another, thus preventing movement within the pipeline and providing individual failsafe operation of each plug module alongside the plug module sealing arrangement (packer). 3. Each Plug Must Be Independently Tested: Each plug module has to be independently tested as part of the Factory Acceptance Test (FAT) in a test pipe to 1.43 times the operational pipeline pressure. This test must be witnessed and accepted by DNV GL for third-party verification. 4. Each Plug s Integrity Can Be Monitored: The integrity of each seal must be able to be monitored to ensure a successful isolation. 5. Each Plug Must Operate Independent of the Other: Both plug modules must operate independently of each other. They each have to be capable of isolating the pipeline on their own. THE SOLUTION As the SmartPlug double block and monitor technology fit DNV-RP-F113/3 criteria, it was chosen as the isolation method for the project. T.D. Williamson 3

1 Set Double Block and Monitor Tool at location HIGH LINE PRESSURE Monitoring and Tracking Module Plug Module #1 Plug Module #2 Control Module LOW LINE PRESSURE DNV-Certified Double Block and Monitor Isolation Method Offshore pipeline maintenance typically falls into one of four categories: valve replacement, tie-in, riser repair, or heavy lift protection. During these types of maintenance, operators rely on non-intrusive inline isolation methods to protect their people, achieve compliance, and mitigate reductions to production. The most common isolation is the DNV-certified double block and monitor method, as seen here. DNV Recommended Practice for Pipeline Subsea Repair Criteria (DNV-RP-F113/3):. Each barrier must be able to retain full line pressure. Independent locking system. Seal must be independently tested. Ability to monitor line integrity. Seals must be independent from each other ANNULUS PRESSURE Through the use of independently operated isolation barriers and continuous monitoring, the system allows high-pressure pipeline operators to carry out remedial pipeline work in a safe, controlled, and monitored environment. 2 3 4 5 Set Plug Module #1 100% Line Pressure Bleed Down LP Side to 50% of HP Side Set Plug Module #2 50% Line Pressure Bleed Down LP Side to Ambient Pressure 28 29 DP * Monitored DP * Monitored Annulus pressure monitored for verification of both seals DP * Monitored 50% LINE PRESSURE * Differential Pressure T.D. Williamson 4

To ensure that the inline isolation would achieve first-time run success* which would reduce operational complexity and improve safety during the critical plug setting process TDW verified the project engineering and performed all necessary communication and pull-tests, and executed in-depth FAT throughout 2012 and 2013. In addition, a comprehensive range of risk and peer reviews (internally and with the operator) were planned and carried out. The SmartPlug module s wide seal profile and short body design which provided more bend clearance and a larger extrusion gap to help maximize piggability were also major contributors to first-time run success. With the possibility of the leaking ESDV failing to meet regulatory function requirements during the preparation period, TDW also maintained a SmartPlug module and a FAT rig in Houston, where they remained on stand-by in the event they needed to be rapidly The SmartPlug module s wide seal profile and short body design which provided more bend clearance and a larger extrusion gap to help maximize piggability were also major contributors to first-time run success. Friction Pull-Test, 2013 (left); FAT, 2013 (right) deployed. Working in cooperation with the operator s team, a total of 3,500 hours were invested in preparation for the isolation In May 2014, the isolation commenced. With safety as the top priority, all non-essential personnel were transferred from the platform during the launch and setting of the tool. The SmartPlug tool was then pigged a distance of 18.28 meters (60 feet) into the riser toward its set location. TDW used the remote-controlled SmartTrack tracking and monitoring system which utilizes an ultra-low frequency transceiver to remotely track the tool s A total of 3,500 hours were invested in preparation for the isolation. The riser was securely isolated against a pressure of 118 bar (1711 psi) and maintained for a period of 79 days. progress, control its speed, and monitor conditions in real time. Upon reaching its location, the tool was set into position, and by 11 p.m. the same night that it was deployed, the isolation was confirmed and certified in accordance with DNV GL requirements. The riser was securely isolated against a pressure of 118 bar (1711 psi) and maintained for a period of 79 days. During the isolation, maintaining a 50 percent pressure value in the annulus between the first and second modules allowed for the integrity of both seals in the pipeline to be monitored. Any change in the annulus pressure would alert TDW to a possible breach of integrity of a seal. A positive pressure rise would indicate the second module had allowed passage. A negative change in pressure would indicate a leak across the first module. During the 11-week span, the three valves were replaced and the launcher extension was installed. Upon completion of these tasks, the isolation tool was safely retrieved and the operation concluded without incident. * First-time run success is based on 10 KPIs defined by TDW, the client, and key third parties. T.D. Williamson 5

Operator Benefits / Project Highlights 1. The double block and monitor isolation performed with SmartPlug technology enabled the safe replacement of three valves on a key section of the platform s gas export pipeline without having to bleed down the entire line. SmartPlug technology allowed the operator to comply with all DNV-RP-F113/3 Double Barrier criteria and line isolation requirements. 2. A continuous flow through multiple downstream connections was maintained throughout the duration of the project, and loss of production was kept to an absolute minimum. 3. Working in close cooperation, TDW and the operator maintained a high level of communication, making the isolation a first-time run success* and minimizing lost production time. 4. The line isolation made possible with SmartPlug technology allowed the operator to comply with all DNV- RP-F113/3 Double Barrier criteria and line isolation requirements. 5. The SmartPlug module s wide seal profile and short body design allowed for more bend clearance, a larger extrusion gap, and maximum piggability. These were major contributors to first-time run success, which shortened the overall duration of the project, improved safety, and decreased the complexity of the isolation. 6. The stress/strain applied by the SmartPlug isolation module was less than half of the calculated maximum allowable stress/strain for the pipeline. 7. Installation of the launcher extension greatly enhanced the ability of the operator to conduct future inline inspections by enabling the launcher to accommodate longer tools. * First-time run success is based on 10 KPIs defined by TDW, the client, and key third parties. Copyright 2015 All rights reserved. T.D. Williamson, Inc. www.tdwilliamson.com North & South America +1 832 448 7200 Europe / Africa / Middle East +47 5144 3240 Asia Pacific +65 6364 8520 T.D. Williamson 6