Olmsted Locks & Dam. Inland Waterways Users Board. MR. DAVID DALE, SES, PE, PMP DIRECTOR, Programs Great Lakes and Ohio River Division 01 April 2016

Similar documents
MR. DAVID DALE, SES, PE, PMP DIRECTOR, US

Kentucky Lock Project Update Inland Waterways Users Board

MR. DAVID DALE, PE, PMP, SES DIRECTOR, Programs Great Lakes & Ohio River Division. 12 August Braddock Dam

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Utility Debt Securitization Authority 2013 T/TE Billed Revenues Tracking Report

Wisconsin 511 Traveler Information Annual Usage Summary January 3, Wisconsin 511 Phone Usage ( )

Financial Project ID No(s).: and ETDM No(s).: and 14181

Inland Marine Transportation System Capital Investment Strategy

2018 HR & PAYROLL Deadlines

CLAIBORNE LOCK AND DAM PERTINENT DATA

3. EXCEL FORMULAS & TABLES

Company A Company A. Company A Board Meeting Presentation 12 th May 20XX

Inland Marine Transportation System

May 2018 FY Key Performance Report

Farm Energy IQ. Wind Energy on Farms. Objectives of this Module. How windy is it? How windy is it? How windy is it? 2/16/2015

Response of a Newly Created Marsh-Wetland Affected by Tidal Forcing, Upland Discharge, and Groundwater Interaction

PUBLIC MEETINGS. Please see the City of Geneva Public Meeting Guide for more information regarding City Council and Committee of the Whole meetings.

City of Wilsonville 5 th Street to Kinsman Road Extension Project

SOLTRANS BOARD MEETING SUPPLEMENTAL REPORTS / HANDOUTS January 15, 2015 MEETING HANDOUTS

Albeni Falls Dam Downstream Water Temperature Study Interim Results

September 2016 Financial Results

I 595 Express Corridor Improvements Project. February 2014 Update

September 2018 FY Key Performance Report

3. EXCEL FORMULAS & TABLES

Public Works Update Safety Campaign. Second Quarter Report

North Carolina Transportation Issues

Appendix G Whitewater Recreation Flow Study Plan

January 2019 FY Key Performance Report

ARTICLE 8. Any Other Business a. Library Gathering Space Plan January 24, 2017, 5:30 7:00 p.m. b. Update on Planning Activities

91 Express Lanes Model Update 2006 State Route 91 Implementation Plan. Gerald V. Nielsten May 18, 2007

Site C Clean Energy Project

1 PEW RESEARCH CENTER

Nenescape. A Heritage Lottery Funded Landscape Partnership. 15 Partnership Projects. Phase I Project Development Jan-16 to May-17

Tysons-Old Meadow Road Bike/Ped Improvements

WATER WELL DRILLER AND PUMP INSTALLER LICENSING REPORT ADVISORY BOARD MEETING January 5, 2018

Mouth of the Columbia River Jetties Three-Phase Construction Plan

Progress Report on the Design and Planning of an Infrastructure Improvement Project for the Sunnyside TIF District (Phase II)

JULY 2013 RIDERSHIP REPORT MTA METRO-NORTH RAILROAD EXECUTIVE SUMMARY

Short-Term Transit Ridership and Revenue Forecasting

CPS Attachment 1. Calgary Combative Sports Commission Year in Review 2015 ISC: UNRESTRICTED

Hard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division

Goldman Sachs Agricultural Biotech Forum New York, NY. March 7, 2012

GAZIFÈRE INC. Prime Rate Forecasting Process 2015 Rate Case

Leveraging RBFF s 2016 National Media Plan RBFF State Webinar Series May 10, 2016

Preston s Edmond Market Report

Economic Overview. Melissa K. Peralta Senior Economist April 27, 2017

PUBLIC AGENDA STREET ACTIVITY STEERING COMMITTEE

Performance Measures Year End 2018

Item 5.1 TRANSIT DAY 2018 BUDGET PRESENTATION. Public Works Department TRANSIT

FOR RELEASE: TUESDAY, DECEMBER 11 AT 4 PM

Presented to Idaho Washington Aquifer Collaborative February 11, Spokane River Project License

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

September 2017 MLS Statistical Report. Residential Inventory

Housing Recycle. APRIL 2017 Recycle Monthly Average Pounds Per Home 89 Tons collected UNCLASSIFIED 1. Goal is 36 Pounds per Household

2016 MOBILITY BOND PROGRAM

Greenup Lock Filling and Emptying System Study

Foreign overnights in the Nordic countries 2015

Performance Evaluation of the Wavestar Prototype

DEFENSE POW/MIA ACCOUNTING AGENCY

FEASIBILITY STUDY DANBURY BRANCH ELECTRIFICATION PROJECT

SAS Quality Scorecard August 2011

PROPOSED EP BOWLS CALENDAR; January 2019 Version 2 Approved 22 November 2018

Lake Taneycomo Fisheries Management. Shane Bush : Fisheries Management Biologist

RF Timeline for July 2018

DATE: FY2016 PB Cycle February PRIOR YR FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 TO COMP TOTAL PROG QUANTITY End Cost

2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018

Initial Study Report Whitewater Boating

VEHICLE / PEDESTRIAN COLLISIONS

Little Athletics NSW. 2018/2019 Season. Age Group Information Handbook / 1

Mogden Sewage Treatment Works

SWISS reports stable load factors

July 2015 Sept Cork City Pedestrian Counter Report

Farm Energy IQ. Farms Today Securing Our Energy Future. Wind Energy on Farms

County of Orange Resources and Development Management Department Harbors, Beaches and Parks. Strategic Plan. HBP Strategic Plan Workshop 1.

REVENUE & RIDERSHIP REPORT SEPTEMBER 2018

CARTA East Cooper Transit Service Transportation Committee Town of Mount Pleasant. February 5, 2013

Inlet Specific and Seasonal Variation in Vessel Use Patterns: The case of the Northeast Florida Region

INNCOM SYSTEM MONITORING MARRIOT HOTEL DOWNTOWN PHILADELPHIA, PA. Report 9. July 2, CH2M HILL Project No

Design of Spillway Upgrades

Interlake Tunnel WRA Board Workshop. August 25, 2014

May 2018 MLS Statistical Report

MPTS Committee meeting, 19 September Annex A: MPTS Performance Dashboard

MEDIA PACK September 2017 Issue 190» 3.00» We put security FIRST because 85% of homeowners do!

Agricultural Weather Assessments World Agricultural Outlook Board

Agricultural Weather Assessments World Agricultural Outlook Board

Instances of 1 Minute or Less Between Buses 4 5% 55% 3.9% 3.5% 3.5% 3.5% 2.9% 2.8% Sep- Sep 07 Oct-07 Nov-07 Dec-07 Jan- Jan 08 Feb- Feb 08 Mar-08

Greater Manchester Police Hate Crime and Hate Incident Data 01/04/14 to 31/03/15

U.S. Army Corps of Engineers Navigation Fiscal Overview

United Nations Conference on Trade and Development

UNCLASSIFIED. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

Performance Measures Year End 2015

Concept Design for Emergency Closure System for Inland Navigation Structures

MAR DASHBOARD MAR. Compliant % Breakdown Mar % Late % On-time MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

FOUR Revolutions: What Will the U.S. Do About Them? Brig. Gen. Duke DeLuca

UK Integrated Behaviour Change Programmes

Nasdaq Dubai AED TRADING HOLIDAYS AND SETTLEMENT CALENDAR 2018 For Equities Outsourced to the DFM (T+2)

BMO Capital Markets 2013 Farm to Market Conference New York, New York. May 14, 2013

2015 Data review. Capturing Ready Lane NEXUS vehicles

Bicycle Crashes. Number of Bike Crashes. Total Bike Crashes. are down 21% and severe bike crashes down 8% since 2013 (5 years).

Jillian C. Burgoyne Syracuse University. IAC Student Webinar March 25, 2015

Transcription:

Olmsted Locks & Dam Inland Waterways Users Board MR. DAVID DALE, SES, PE, PMP DIRECTOR, Programs Great Lakes and Ohio River Division 01 April 2016 US Army Corps of Engineers

Agenda Status BLUF/Project Overview 2015 LWS Wrap-Up 2016 Plan-to-Complete 2016 Milestone Identification Project Scorecard Summary Discussion LWS = Low Water Season 2

Bottom Line Up Front BLUF All 2015 baseline milestones and identified stretch goal achieved. Capability funding allows the team to actively mitigate risk exposure. 2016 Plan-to-Complete and performance trending align with an early operational delivery of Oct/2018 ($65M under budget, two years ahead of schedule). 3

Olmsted Project Overview - Status Fixed Weir Navigable Pass Foundation prep complete Grout Mat placement complete All 2015 LWS Shell & PB Baseline Milestones complete 2016 LWS Shell NP No. 6 (2015 Stretch Goal) complete 2016 LWS Shell NP No. 7 pre-cast in-progress 2016 LWS Shell NP No. 8 pre-cast in-progress Locks & Approach Walls Left Boat Abutment Foundation Pile complete Tainter Gates TG-1 and TG-2 erected TG-3 scheduled for delivery 30 Jun TG-4 scheduled for delivery 30 Sep Service Bridges (SB-1, SB-2) pre-cast inprogress Hydraulic machinery installation for TG-1/TG-2 complete Operations Facilities Maintenance Bldg (2017) Lock Masters Bldg (2017) Resident Engineers Office Wicket Lifter Design underway (MDC) Scheduled FY16 4 th Qtr Award Estimated delivery (Dec/2017) Dam Access Road River Dikes Design underway (LRL) Scheduled FY16 3 rd Qtr Award IDIQ pending PARC approval 4 Completed Under Contract Future

1 2015 LWS Images 2 3 4 5 6 1. First Commercial Lockage 2. River Chamber Unwatering 3. NP-3 Wicket Installation 4. TG-1 Cylinder Installation 5. TG Bay 1 Unwatering 6. NP-6 Transiting Skid Way 5

2016 Plan-to-Complete 10 * Eight shells set in LWS 2015 including one shell set outside contractual LWS limits (15 Jun 30 Nov) 6

2016 LWS Milestones Scheduled Milestones Set NP #7-9 (of 12) Set PB #9-12 (of 12) Erect TG #3-4 (of 5) Preparatory Milestones Complete LBA Thin-Wall Cofferdam Complete all NP Foundation Pile Complete all NP M/S Pile Stretch Goal Milestone Set NP #10 (of 12) PB-9 PB-10 PB-11 PB-12 NP-7 NP-8 NP-9 TG-3 TG-4 Legend BASELINE (FY16-$268M) (FY17-$225M) XX Jun XX Jun XX Jul XX Jul XX Sep XX Oct XX Nov XX Aug XX Nov LP Lower Pier TG Tainter Gate SB Service Bridge GM Grout Mat FP Foundation Pile M/S Master/Sheet RBA Right Boat Abutment LBA Left Boat Abutment PB Paving Block NP Nav Pass Shell (Monolith) 7

Olmsted Project Time and Cost Scorecard Dec 2015 Expenditures Planned (BCWS) $2.103B Earned (BCWP) $2.034B Actual (ACWP) $2.111B BCWP: Reports the value (based on % complete) of the work performed to date. Schedule (PACR)/(Current) Project Complete Sep 2024/Mar 2022 Dam Operational Sep 2020/Oct 2018 Measures: Planned project completion and Dam contract operational dates TEP in Billions Target: Actual as compared to Planned: ( <1% = Green) (>1%and <3% = Yellow) and (>3% = Red) Olmsted Project TEP Trend 3.150 3.100 3.050 3.000 2.950 2.900 2.850 2.800 2.750 Sep-15 Oct-15 Nov-15 Dec-15 Sep-15 Oct-15 Nov-15 Dec-15 PACR w/risk 3.099 3.099 3.099 3.099 COE TEP 2.887 2.882 2.884 2.883 Target: Green: Current = PACR-12 months Yellow: Current = PACR-11 months to PACR-7 months Red: Current = PACR-6 months to after PACR date Major Activity Schedule 8

Olmsted Project Construction Management Score Card Dec 2015 Acquisition Quality of Construction Quality of Design Wicket Maintenance Box Addressing Design Issues from Ops Lessons Learned LRL In-House Design Effort Engineering & Ops Reviewing and Exploring COA s Target Design Complete Milestone - 1 May 2016 River Dikes LRL In-House Design Incorporating ERDC Modeling Scheduled Design Complete Milestone - 31 Mar 2016 Wicket Lifter Marine Design Center Turnkey Delivery (approx. 2 Years) Required 2017 Safety Contractor DART Tolerance: Green: 1.04 or less Amber: 1.05 1.39 Red: 1.40 + Contractor Hours/Rate FY 13 FY 14 FY 15 FY-16 AECOM/Alberici J/V Hours: 1,122,387 1,374,143 1,543,532 469,978 # DART: 3 5 5 0 Rate: 0.53 0.73 0.65 0 Adjusting TG-1 to Sill Shell interface. Tolerance 1/32. SS Nos.1 & 2 set in 2010. High Risk Activities Trends - Dive Operations. 1,731 dives, 2 Mishaps, no injuries. - Crane Operations. FY-15 47,642 crane hours, 27 Mishaps. - FY-16 11,389 hours, 3 Mishaps. Focus areas for next quarter - Crane hazards. Third Party Load Handling Equipment SME site audit. - Diving program. Third Party Diving SME site audit. 9

$3,500,000,000 $3,300,000,000 PACR (Fully Funded) = $3.099B Olmsted L&D Project Earned Value Analysis (Based on DOD Gold Card) Dec 2015 Remaining Contingency = $216M Current COE Estimated TEP is $2.883B in March 2022 $3,100,000,000 $2,900,000,000 $2,700,000,000 $2,500,000,000 $2,300,000,000 $2,100,000,000 $1,900,000,000 $1,700,000,000 $1,500,000,000 2,110,000,000.00 2,060,000,000.00 2,010,000,000.00 1,960,000,000.00 1,910,000,000.00 1,860,000,000.00 Time Now Dam Operational Oct 2018 (Current working schedule) Sep-11 Jan-12 May-12 Sep-12 Jan-13 May-13 Sep-13 Jan-14 May-14 Sep-14 Jan-15 May-15 Sep-15 Jan-16 May-16 Sep-16 Jan-17 May-17 Sep-17 Jan-18 May-18 Sep-18 Jan-19 May-19 Sep-19 Jan-20 May-20 Sep-20 Jan-21 May-21 Sep-21 Jan-22 May-22 Sep-22 Jan-23 May-23 Sep-23 Jan-24 May-24 Sep-24 ACWP BCWP BCWS Olmsted Project Complete Mar 2022 (Current working schedule) Olmsted Project Complete Sept 2024 (PACR) 10

In Summary Project cost (risk-informed) at completion is $65M under the fully funded $3.1B PACR Baseline Project completion schedule is 2 years ahead of the PACR baseline schedule, 2022 in lieu of 2024 Capability funding (FY16 - $268M/FY17 - $225M) aligns resources for most expeditious and efficient completion. 11

Discussion 12