Initial Study Report Whitewater Boating

Size: px
Start display at page:

Download "Initial Study Report Whitewater Boating"

Transcription

1 Initial Study Report Whitewater Boating Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 PacifiCorp May 2015 South Fork of the Rogue River, 2007 Reproduced with permission from Peter Gandesbery, 12/10/2013

2 Methods Results Needs Conclusions Recommendations Overview South Fork of the Rogue River, 2007 Reproduced with permission from Peter Gandesbery, 12/10/2013

3 Project Study Area (PSA)

4 Methods Employed Level 1 Desktop Analysis consistent with Whittaker, Shelby, & Gangemi (2005) Literature reviews, hydrology summary, structured interviews Hydrology Analysis Compared impaired versus unimpaired (potential) flows WY 1990 to WY 2013 USGS Gage No (0.3 miles below diversion dam) Use and Demand Analysis May 20, 2014 Stakeholder Meeting To identify acceptable recreation flows, boater access, and potential boating needs within the Project Study Area Whitewater Boating Survey Questionnaire Needs Analysis Project effect comparisons Determination of the need to advance to Level 2 studies

5 Results - Hydrology 450 Flows, River Mile Q (CFS) UNIMPAIRED FLOWS IMPAIRED FLOWS 0 1-Jan 1-Feb 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec Existing Q at Bridge Unimpaired Q at Bridge

6 Results Stakeholder Meeting & Survey Questionnaire Stakeholder Meeting (May 20, 2014) Contacted members of American Whitewater and Southern Oregon Water Dogs Two attendees Survey Questionnaire Sent to 44 whitewater boaters Resulted in 10 participants Contacted 29 commercial guides or outfitters Resulted in 14 verbal responses

7 Results Participant Self Rating Expert (Class V) Advanced (Class IV) Intermediate (Class III) Novice (Class II) Novice Intermediate Advanced Expert (Class II) (Class III) (Class IV) (Class V) Participant Self Rating No. of Participant Votes

8 Results Whitewater Classification Class VI Class V Class IV Class III Class II Class I Class I Class II Class III Class IV Class V Class VI Whitewater Difficulty Poll No. of Participant Votes

9 Boating Obstacles Participant No. Rock Hits No. Boat Stops No. Boat Drags No. Boat Portages

10 Results Minimum & Optimum Flows 400 cfs 350 cfs 300 cfs Flow 250 cfs 200 cfs 150 cfs cfs 200 cfs 250 cfs 300 cfs 350 cfs 400 cfs Suggested Optimum Flows Suggested Minimum Flows No.of Participant Votes

11 Flows, River Mile OPTIMUM FLOW 300 Q (CFS) MINIMUM FLOW Jan 1-Feb 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec Existing Q at Bridge Unimpaired Q at Bridge Minimum Boating Flows Optimum Flows

12 Results Recreational Access River Mile Tax lot No. Owner Name - North Bank Owner Name - South Bank E2400 Tristar Southwest Oregon TI E Plum Creek Timberlands LP E2600 Tristar Southwest Oregon TI E Plum Creek Timberlands LP E1500 Tristar Southwest Oregon TI E Uram Forests LLC E1300 Tristar Southwest Oregon TI E Indian Hill LLC E700 Tristar Southwest Oregon TI E900 USA (U.S. DOI- BLM) USA (U.S. DOI- BLM) E Juniper Properties LLC Juniper Properties LLC E USA (U.S. DOI-BLM) USA (U.S. DOI-BLM) E USA (U.S. DOI-BLM) USA (U.S. DOI-BLM)

13 Results Alternate Boating Opportunities Nearby the PSA Publish Literature Soggy Sneakers: A Paddler s Guide to Oregon Rivers, p Paddling Oregon, p.269 Wild and Scenic Rivers of America, p.218 & 219 Summary of Nearby Opportunities The North Fork Rogue River Takilma Gorge is mentioned as a Class IV+ with flows year-round between 400 to 500 cfs. Length is 3.8 miles with a gradient of 38 fpm. The North Fork Rogue River Bridge Campground to North Fork Reservoir is listed as a Class III or possibly Class IV with year-round flows between 400 to 2,000 cfs. Length of the run is listed as 5 miles with a 40 fpm gradient. The North Fork Rogue River Mill Creek Falls to Lost Creek Lake is listed as a Class IV+ with seasonal (snowmelt) flows ranging from 500 to 1,000 cfs. The length is listed as three miles with a gradient of 94 fpm. The Middle Fork Rogue River Butte Falls Road to Lost Creek Lake is considered by this publication to be a Class V. The Middle Fork boasts a 6 mile run with flows ranging from 400 to 800 cfs during the rainy season or early spring during snowmelt. This reach is rated at an 88 fpm gradient. This published reference provides an overview of recreational paddling on the Rogue River. Running the North Fork from the North Fork Reservoir to Lost Creek Lake is mainly discussed as a run for expert paddlers who should expect Class IV+ waters. A quick mention of the Middle Fork Rogue River lists that this run contains obstacles like logs, brush, steep gradients, unportagable rapids, and plenty of pinning potential. The Rogue River is described in detail. The river difficulty is mentioned as upper, not run; lower, Class III with 2 Class IV rapids. This reference focuses primarily on the whitewater opportunities on the lower Rogue River (below William Jess Dam operated by the U.S. Army Corps of Engineers) where there is 55 mi of whitewater boating. available to the recreationalist above and below the wild & scenic section of the Rogue River.

14 Needs Project Effects on Recreation Flow Project operates in run-ofriver mode creating dependence on seasonal flows, rainfall, and accretions Using minimum boatable flow criteria of 200 cfs Impaired boatable days 31 (April 29 May 29) Unimpaired boatable days 116 (February 21 June 16) Using optimal boatable flow criteria of 350 cfs Unimpaired boatable days 31 (April 29 May 29) Q (CFS) Existing Q at Bridge Minimum Boating Flows OPTIMUM FLOW MINIMUM FLOW Unimpaired Q at Bridge Optimum Flows

15 Needs PSA Recreational Access Few Put-In or Take-Out locations as PSA is bounded primarily by private land owners to the north and south Remote region Steep, canyon geomorphology Few public roads Respondents main access point Butte Falls Prospect Road Bridge

16 Needs Potential Improvements & Flow Information Put-In or Take-Out location improvements are restricted by privately held lands to the north and south along the majority of the PSA Flow Information Add accretions to USGS gage flow data and incorporate Middle Fork confluence flows Use Dreamflows website to summarize PSA flows South Fork of the Rogue River, 2007 Reproduced with permission from Peter Gandesbery, 12/10/2013

17 Needs Recreation Opportunities Diminished or curtailed electric generation would only benefit a small number of skilled boaters who would boat the PSA when other quality boating opportunities are available in the region Importance of flow-dependent recreation opportunities Short boating window for minimum and optimum flows High skill level required Uncertainty of woody debris in channel Geomorphology of the PSA restricts put-in and take-out locations PSA is bounded by private property Nearby availability of highly accessible and equally challenging whitewater boating

18 Conclusions High level of skill required to boat the PSA limits the pool of potential boaters for this reach Boaters outside of the existing user group are likely willing to forgo the opportunity to boat the PSA in favor of other nearby whitewater boating opportunities Demand for future whitewater boating opportunities in the PSA is not expected to increase compared to the opportunities at the North Fork Rogue River or other nearby river systems.

19 Recommendations PSA enhancement measures are not proposed based on the results of the Level 1 analysis Enhancement measures are unlikely to increase use by whitewater boaters Based on sufficient whitewater boating data provided by the respondents, PacifiCorp believes that the Level 1 analysis adequately defines whitewater boating experiences, opportunities, and flow ranges for the PSA and believes this analysis precludes the need to pursue a Level 2 study

20 Thank You PacifiCorp would like to thank the participant boaters and other contributors who provided information regarding the South Fork Rogue River and participated in the interactive process of the Initial Whitewater Boating Study. The Initial Report would not have been possible without your input.

21 Questions

Appendix G Whitewater Recreation Flow Study Plan

Appendix G Whitewater Recreation Flow Study Plan Appendix G Whitewater Recreation Flow Study Plan Study Plan Whitewater Recreation Flow Study Grandfather Falls Hydroelectric Project FERC Project No. 1966 March 2013 An Integrys Energy Group Company Section

More information

APPENDIX 2E PHASE II CONTROLLED FLOW SURVEY INSTRUMENTS

APPENDIX 2E PHASE II CONTROLLED FLOW SURVEY INSTRUMENTS APPENDIX 2E PHASE II CONTROLLED FLOW SURVEY INSTRUMENTS February 2004 PacifiCorp KLAMATH BOATER PRE-FIELDWORK INFORMATION FORM Date: / / 2002 Your name: 1. For the following types of whitewater craft,

More information

Clackamas River Hydroelectric Project Whitewater Kayaking on the Oak Grove Fork

Clackamas River Hydroelectric Project Whitewater Kayaking on the Oak Grove Fork Clackamas River Hydroelectric Project Whitewater Kayaking on the Oak Grove Fork DRAFT Prepared for Portland General Electric 121 SW Salmon Street Portland, Oregon 97204 Prepared by Doug Whittaker and Bo

More information

Clackamas River Hydroelectric Project Flows and whitewater recreation: Updated information about Three Lynx and Bob s Hole boating

Clackamas River Hydroelectric Project Flows and whitewater recreation: Updated information about Three Lynx and Bob s Hole boating Clackamas River Hydroelectric Project Flows and whitewater recreation: Updated information about Three Lynx and Bob s Hole boating Prepared for Portland General Electric 121 SW Salmon Street Portland,

More information

TABLE OF CONTENTS LIST OF TABLES NONE LIST OF FIGURES NONE

TABLE OF CONTENTS LIST OF TABLES NONE LIST OF FIGURES NONE TABLE OF CONTENTS 7.4 RIVER-RELATED RECREATION SURVEYS (REC 4)... REC 4-1 7.4.1 Study Objectives... REC 4-1 7.4.2 Study Area... REC 4-1 7.4.3 Methods... REC 4-1 7.4.4 Key Questions... REC 4-3 7.4.5 Results...

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun Jul

More information

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) ICE HOUSE REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) ICE HOUSE REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) ICE HOUSE REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT Devine Tarbell & Associates, Inc. Sacramento, California

More information

Tuckasegee Paddling Flow Study Results FERC # s 2686, 2698, /20/02

Tuckasegee Paddling Flow Study Results FERC # s 2686, 2698, /20/02 Tuckasegee River Paddling Recreational Instream Flow Study East Fork, West Fork, and Dillsboro Hydroelectric Projects FERC # s 2698, 2686, 2602 Dillsboro and Whittier Sections - July 2-3, 2001 West Fork

More information

TAPOCO PROJECT FERC NO CHEOAH RIVER RECREATION STUDY FINAL REPORT

TAPOCO PROJECT FERC NO CHEOAH RIVER RECREATION STUDY FINAL REPORT TAPOCO PROJECT FERC NO. 2169 Prepared by Kleinschmidt Associates January 2002 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 1.0 INTRODUCTION... 5 2.0 RIVER CHARACTERIZATION AND CONTROLLED FLOW ASSESSMENT...

More information

Three-Year Summary Report. Prospect Whitewater Boating Flow Release. and. Whitewater Boating Access Monitoring Study

Three-Year Summary Report. Prospect Whitewater Boating Flow Release. and. Whitewater Boating Access Monitoring Study Three-Year Summary Report Prospect Whitewater Boating Flow Release and Whitewater Boating Access Monitoring Study Prospect Nos. 1, 2 and 4 Hydroelectric Project FERC No. P-2630 June 1, 2012 Prepared for

More information

Via . March 31, Whitewater Boating Flow Study Working Group

Via  . March 31, Whitewater Boating Flow Study Working Group Via Email March 31, 2016 TO: Whitewater Boating Flow Study Working Group SUBJECT: Bear Swamp Project (FERC Project No. 2669) Whitewater Boating Flow Study Survey Forms Dear Stakeholder: Bear Swamp Power

More information

Presented to Idaho Washington Aquifer Collaborative February 11, Spokane River Project License

Presented to Idaho Washington Aquifer Collaborative February 11, Spokane River Project License Presented to Idaho Washington Aquifer Collaborative February 11, 2014 Spokane River Project License Contact Speed Fitzhugh, Spokane River License Manager Telephone - (509) 495-4998 Email - speed.fitzhugh@avistacorp.com

More information

APPENDIX 2B PHASE I INTERVIEW FORMAT

APPENDIX 2B PHASE I INTERVIEW FORMAT APPENDIX 2B PHASE I INTERVIEW FORMAT February 2004 PacifiCorp The following provides the general format used during Phase I structured interviews. The document outlines the general interview topics and

More information

2.0 Resource Management Goals of Agencies with Jurisdiction Over the Resource to be Studied

2.0 Resource Management Goals of Agencies with Jurisdiction Over the Resource to be Studied Yuba River Development Project 1.0 Project Nexus Study 8.2 RECREATION FLOW November 2010 s (YCWA or Licensee) continued operation and maintenance (O&M) of the existing Yuba River Development Project (Project)

More information

PLEASE NOTE: The Black Canyon is a Class 5 Boating Opportunity. Experts Only

PLEASE NOTE: The Black Canyon is a Class 5 Boating Opportunity. Experts Only PLEASE NOTE: The Black Canyon is a Class 5 Boating Opportunity Experts Only The Black Canyon is rated Class 5 1 whitewater, appropriate for expert boaters only. Class 5 whitewater is described as extremely

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Morrisville Water & Light FERC No. P-2629 Morrisville Project Green River Development

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Morrisville Water & Light FERC No. P-2629 Morrisville Project Green River Development UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Morrisville Water & Light FERC No. P-2629 Morrisville Project Green River Development AMERICAN WHITEWATER AND VERMONT PADDLERS CLUB MOTION

More information

Recreation Resources. Attachment 7.8B. New Bullards Bar Dam Whitewater Study Results

Recreation Resources. Attachment 7.8B. New Bullards Bar Dam Whitewater Study Results Recreation Resources Attachment 7.8B New Bullards Bar Dam Whitewater Study Results 1.0 Introduction NEW BULLARDS BAR DAM WHITEWATER BOATING STUDY December 19, 2008 The (YCWA) intends to apply to the Federal

More information

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) WHITEWATER BOATING FEASIBILITY TECHNICAL REPORT

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) WHITEWATER BOATING FEASIBILITY TECHNICAL REPORT SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 211) WHITEWATER BOATING FEASIBILITY TECHNICAL REPORT Devine Tarbell & Associates, Inc. Sacramento, California Prepared by: The

More information

BLM Cottonwood Field Office ATTN: Draft RMP/EIS 1 Butte Drive Cottonwood, ID Submitted Via to:

BLM Cottonwood Field Office ATTN: Draft RMP/EIS 1 Butte Drive Cottonwood, ID Submitted Via  to: Kevin Colburn National Stewardship Director American Whitewater 1035 Van Buren St. Missoula, MT 59802 406-543-1802 Kevin@amwhitewater.org BLM Cottonwood Field Office ATTN: Draft RMP/EIS 1 Butte Drive Cottonwood,

More information

Re: Comments on Study Plans and Scoping Document 2 (SD2) for the Black Canyon Hydroelectric Project (FERC P )

Re: Comments on Study Plans and Scoping Document 2 (SD2) for the Black Canyon Hydroelectric Project (FERC P ) Thomas O Keefe, PhD Pacific Northwest Stewardship Director 3537 NE 87 th St. Seattle, WA 98115 okeefe@americanwhitewater.org Electronic Filing, December 6 th, 2012 Kimberly D. Bose, Secretary Federal Energy

More information

Clackamas River Hydroelectric Project Faraday Diversion Whitewater Boating Study

Clackamas River Hydroelectric Project Faraday Diversion Whitewater Boating Study Clackamas River Hydroelectric Project Faraday Diversion Whitewater Boating Study FINAL Prepared for Portland General Electric Prepared by Confluence Research and Consulting 6324 Red Tree Circle Anchorage,

More information

Wisconsin 511 Traveler Information Annual Usage Summary January 3, Wisconsin 511 Phone Usage ( )

Wisconsin 511 Traveler Information Annual Usage Summary January 3, Wisconsin 511 Phone Usage ( ) Wisconsin 511 Traveler Information 211 Annual Usage Summary January 3, 212 Overall to-date Summary 36 months of operation 1,16,63 total calls the 1 Million mark was passed on December 3, 212 3,627,527

More information

2013 Whitewater Survey Results

2013 Whitewater Survey Results If you paddled on If you paddled on Sunday Saturday at flows of 375, at flows of 400, score the score the quality of this quality of this flow for flow for your craft and your craft and skill level. skill

More information

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORK AND EDUCATION

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORK AND EDUCATION GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORK AND EDUCATION -- FINAL TOPLINE -- Timberline: 937008 IS: 786 Princeton Job #: 16-08-012 Jeff Jones, Lydia Saad August 3-7, 2016 Results are based on

More information

CCoWS. Central Coast Watershed Studies. Summary of Precipitation and Streamflow for Potrero and San Clemente Creeks in 2010

CCoWS. Central Coast Watershed Studies. Summary of Precipitation and Streamflow for Potrero and San Clemente Creeks in 2010 Central Coast Watershed Studies CCoWS Summary of Precipitation and Streamflow for Potrero and San Clemente Creeks in Water-Year 2010 Santa Lucia Preserve Monterey County, California Publication No. WI-2011-01

More information

2018 HR & PAYROLL Deadlines

2018 HR & PAYROLL Deadlines th (by payment date) EPAF 3rd PARTY FEEDS WTE Approval 2018 HR & PAYROLL s Normal Payroll day s 2017 B1-26 3 * 13-Dec-17 15-Dec-17 n/a n/a n/a 28-Dec-17 29-Dec-17 11:00 AM 16-Dec-2017 29-Dec-2017 JAN 2018

More information

Utility Debt Securitization Authority 2013 T/TE Billed Revenues Tracking Report

Utility Debt Securitization Authority 2013 T/TE Billed Revenues Tracking Report Utility Debt Securitization Authority 2013 T/TE Billed Revenues Tracking Report Billing Budgeted Billed Dollar Percent Month Revenues Revenues Variance Variance Jan 2018 11,943,180.68 12,697,662.47 754,481.79

More information

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS -- FINAL TOPLINE -- Timberline: 937008 IS: 954 Princeton Job #: 17-02-002 Jeff Jones, Lydia Saad February 1-5, 2017 Results are based on telephone

More information

FOR RELEASE: FRIDAY, MARCH 30 AT 5 AM

FOR RELEASE: FRIDAY, MARCH 30 AT 5 AM Interviews with 1,014 adult Americans conducted by telephone by ORC International on March 24-25, 2012. The margin of sampling error for results based on the total sample is plus or minus 3 percentage

More information

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS

GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS GALLUP NEWS SERVICE GALLUP POLL SOCIAL SERIES: WORLD AFFAIRS -- FINAL TOPLINE -- Timberline: 937008 JT: 165 Princeton Job #: 18-02-002 Jeff Jones, Lydia Saad February 1-10, 2018 Results are based on telephone

More information

Coquitlam/Buntzen Project Water Use Plan

Coquitlam/Buntzen Project Water Use Plan Coquitlam/Buntzen Project Water Use Plan Temperature Monitoring Lower Coquitlam River Project Year 3 Report Reference: COQMON#6 Study Period: March 2008 April 2009 Report Date: April 2009 Trow Associates

More information

Albeni Falls Dam Downstream Water Temperature Study Interim Results

Albeni Falls Dam Downstream Water Temperature Study Interim Results Albeni Falls Dam Downstream Water Temperature Study Interim Results Amy Reese, Chief Water Management Section Seattle District June 24, 2014 US Army Corps of Engineers What we hope to cover today Albeni

More information

CUPSIM Water Supply Variability Study All information subject to change.

CUPSIM Water Supply Variability Study All information subject to change. . 1 IN A NUTSHELL The CUP Water Supply Variability Study is an opportunistic, proactive example of responsible water system management The CUP is very complex and approaching full demand The study capitalizes

More information

Little Spokane River Stream Gage Report: Deadman Creek, Dragoon Creek, and the West Branch of the Little Spokane River

Little Spokane River Stream Gage Report: Deadman Creek, Dragoon Creek, and the West Branch of the Little Spokane River Little Spokane River Stream Gage Report: Deadman Creek, Dragoon Creek, and the West Branch of the Little Spokane River June 2010 Spokane County Conservation District N. 210 Havana St. Spokane, WA 99202

More information

LIFE HISTORY DIVERSITY AND RESILIENCE

LIFE HISTORY DIVERSITY AND RESILIENCE LIFE HISTORY DIVERSITY AND RESILIENCE SPRING CHINOOK IN THE WILLAMETTE RIVER BASIN Kirk Schroeder Brian Cannon Luke Whitman Paul Olmsted Oregon Department of Fish and Wildlife Corvallis Research Lab Thanks

More information

Tuesday, January 11, :11 AM (CST)

Tuesday, January 11, :11 AM (CST) Tuesday, January 11, 2011 11:11 AM (CST) -Assessment of current water conditions - Precipitation Forecast - Recommendations for Drought Monitor Upper Colorado Normal Precipitation Upper Colorado River

More information

APPENDIX C BLUEWAYS ASSESSMENT

APPENDIX C BLUEWAYS ASSESSMENT APPENDIX C Blueways Assessment Poor Fork of Cumberland River Section above Kingdom Come State Park and Cumberland, KY By Steve Spencer, Ed.D. Western Kentucky University The author is an American Canoe

More information

Lower Coquitlam River Project Water Use Plan. Temperature Monitoring Lower Coquitlam River Project Year 2 Report

Lower Coquitlam River Project Water Use Plan. Temperature Monitoring Lower Coquitlam River Project Year 2 Report Lower Coquitlam River Project Water Use Plan Temperature Monitoring Lower Coquitlam River Project Year 2 Report COQMON#6 Temperature Monitoring Study Lower Coquitlam River Study Period: Year 2-2007 Report

More information

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) CAMINO REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT

SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) CAMINO REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT SACRAMENTO MUNICIPAL UTILITY DISTRICT UPPER AMERICAN RIVER PROJECT (FERC NO. 2101) CAMINO REACH WHITEWATER BOATING FLOW STUDY TECHNICAL REPORT Devine Tarbell & Associates, Inc. Sacramento, California Prepared

More information

1 PEW RESEARCH CENTER

1 PEW RESEARCH CENTER 1 SEPTEMBER 2018 POLITICAL SURVEY FINAL TOPLINE SEPTEMBER 18-24, 2018 N=1,754 QUESTIONS 1-2, 7-8, 11-13, 28 PREVIOUSLY RELEASED NO QUESTIONS 3-6, 9-10, 14-27, 29-32, 34-43, 47-49 QUESTION 33 HELD FOR FUTURE

More information

Eulachon: State of the Science and Science to Policy Forum

Eulachon: State of the Science and Science to Policy Forum Eulachon: State of the Science and Science to Policy Forum August 27, 2015 Robert Anderson Eulachon Recovery Coordinator National Marine Fisheries Service FCRPS, Dams, and Water Management in the Columbia

More information

CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE UPDATE ON LANDINGS OF TUNA, SWORDFISH AND OTHER PELAGICS

CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE UPDATE ON LANDINGS OF TUNA, SWORDFISH AND OTHER PELAGICS Agenda Item H.2.c Supplemental CDFW Report 1 November 217 CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE UPDATE ON LANDINGS OF TUNA, SWORDFISH AND OTHER PELAGICS CDFW Summary of HMS Landings Data Improvement

More information

Project Award Presentation

Project Award Presentation University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

2018 Sport Fishing Regulations Exhibit B

2018 Sport Fishing Regulations Exhibit B 2018 Sport Fishing Regulations Exhibit B Mike Gauvin -Recreational Fisheries Program Manager Commission Rulemaking August 4 th 2017 1 Topics for Consideration Public involvement in 2018 regulation process

More information

GALLUP NEWS SERVICE 2018 MIDTERM ELECTION

GALLUP NEWS SERVICE 2018 MIDTERM ELECTION GALLUP NEWS SERVICE 2018 MIDTERM ELECTION Results are based on telephone interviews with a random sample of 1,508 -- national adults, aged 18+, living in all 50 states and the District of Columbia, conducted

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM 04/21/01 Page 1 TECHNICAL MEMORANDUM SUBJECT: Green River Basin Plan Surface Water Data Collection and Study Period Selection PREPARED BY: Meg Frantz and Linda Williams, Boyle Engineering Introduction

More information

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Luxemburg Creek.

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Luxemburg Creek. Minnesota F-29-R(P)-24 Area 315 Study 3 March 2016 Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries Stream Survey Report Luxemburg Creek 2015 Mark Pelham Sauk

More information

Central Oregon Intergovernmental Council

Central Oregon Intergovernmental Council Central Oregon Intergovernmental Council Regional Transit Master Plan (RTMP) Technical Advisory Committee Kick-Off Meeting May 16, 2012 Meeting Agenda Project Orientation Presentation of Survey Results

More information

Recent updates to Marine Impact Model for IFR Coho. Prepared by: Pieter Van Will, DFO Port Hardy

Recent updates to Marine Impact Model for IFR Coho. Prepared by: Pieter Van Will, DFO Port Hardy Recent updates to Marine Impact Model for IFR Coho Prepared by: Pieter Van Will, DFO Port Hardy Recent model updates Base period (BP) review Incorporation of uncertainty in Average BP exploitation rate

More information

SWISS reports stable load factors

SWISS reports stable load factors SWISS Corporate Communications Phone: +41 (0)848 773 773 Fax: +41 (0)44 564 2127 communications@swiss.com SWISS.COM Media release Zurich Airport, October 10, 2008 SWISS reports stable load factors SWISS

More information

MALL CROSSING STUDY. Testing the Effectiveness Of the 4th Street East Crossing. For: City of Charlottesville Neighborhood Development Services

MALL CROSSING STUDY. Testing the Effectiveness Of the 4th Street East Crossing. For: City of Charlottesville Neighborhood Development Services MALL CROSSING STUDY One-Year Evaluation Final Report Testing the Effectiveness Of the 4th Street East Crossing For: City of Charlottesville Neighborhood Development Services May 2007 By: CHARLOTTESVILLE

More information

Conference Welcome and Introduction

Conference Welcome and Introduction Conference 2013 Welcome and Introduction Housing stock Present day Owner occupation Private renting 17.5m 4m 66% 15.1% Housing associations Council housing 2.8m 2.2m 26.5m 10.6% 8.3% > 2.8m Social Housing

More information

Fossil Creek Native Fish Repatriation 2009 Implementation Plan Arizona Game and Fish Department

Fossil Creek Native Fish Repatriation 2009 Implementation Plan Arizona Game and Fish Department Fossil Creek Native Fish Repatriation 2009 Implementation Plan Arizona Game and Fish Department MONITORING: Annual monitoring is conducted for each species stocked, typically during late summer or early

More information

Upper Yuba River Watershed Chinook Salmon and Steelhead Habitat Assessment

Upper Yuba River Watershed Chinook Salmon and Steelhead Habitat Assessment Technical Report Upper Yuba River Watershed Chinook Salmon and Steelhead Habitat Assessment Prepared for California Department of Water Resources November 2007 Prepared by Upper Yuba River Studies Program

More information

Personnel Benchmarking Author: Ed Rehkopf

Personnel Benchmarking Author: Ed Rehkopf Author: Ed Rehkopf 2009 Club Resources International Table of Contents Background.................................. 1 Purpose.................................... 1 Sources of Information............................

More information

Conceptual Design Report for the Hamilton Dam Modifications Project. Flint, Michigan. Prepared For: City of Flint P.O. Box 99 Flint, MI

Conceptual Design Report for the Hamilton Dam Modifications Project. Flint, Michigan. Prepared For: City of Flint P.O. Box 99 Flint, MI Conceptual Design Report for the Hamilton Dam Modifications Project Flint, Michigan Prepared For: City of Flint P.O. Box 99 Flint, MI 48501-0099 Flint River Watershed Coalition 432 N. Saginaw St. Suite

More information

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 North Fork Lewis River Hydroelectric Project Yale FERC No. 2071 Prepared by: Jeremiah Doyle, PacifiCorp April 4, 2017 1.0 INTRODUCTION

More information

PROJECT OVERVIEW PROJECT AREA. FAHCE Fish Habitat Restoration Plan EIR

PROJECT OVERVIEW PROJECT AREA. FAHCE Fish Habitat Restoration Plan EIR PROJECT OVERVIEW PROJECT AREA FISH AND AQUATIC HABITAT COLLABORATIVE EFFORT (FAHCE) Fish Habitat Restoration Plan Project Area PROJECT OVERVIEW DOCUMENTS A Settlement Agreement Regarding Water Rights of

More information

County of Orange Resources and Development Management Department Harbors, Beaches and Parks. Strategic Plan. HBP Strategic Plan Workshop 1.

County of Orange Resources and Development Management Department Harbors, Beaches and Parks. Strategic Plan. HBP Strategic Plan Workshop 1. County of Orange Resources and Development Management Department Harbors, Beaches and Parks Strategic Plan HBP Strategic Plan Workshop 1 v18 PRESENTATION OUTLINE Harbors, Beaches & Parks (HBP) History

More information

Nantahala Whitewater Rafting Class II-III Fun!

Nantahala Whitewater Rafting Class II-III Fun! Nantahala Whitewater Rafting Class II-III Fun! Located in the beautiful mountains of Western North Carolina, the Nantahala River is one of the most popular rivers in the US! This eight mile, Class II-III,

More information

Upper Columbia Redband Trout: Conservation for the Future

Upper Columbia Redband Trout: Conservation for the Future Upper Columbia Redband Trout: Conservation for the Future Bryan Jones and Holly McLellan Colville Confederated Tribes Fish and Wildlife Department Historic Notes Upper Columbia River Large runs of steelhead,

More information

FREEDOM OF INFORMATION REQUEST

FREEDOM OF INFORMATION REQUEST FREEDOM OF INFORMATION REQUEST REQUEST NUMBER: FOI Request 003905-16 REQUEST DETAILS: As part of my research I am requesting information on the numbers of 'strip searches' that have taken place within

More information

FOR RELEASE: THURSDAY, MARCH 2 AT 4 PM

FOR RELEASE: THURSDAY, MARCH 2 AT 4 PM CNN/USA TODAY/GALLUP POLL FEBRUARY WAVE 2 -- FINAL TOPLINE -- Results are based on telephone interviews with 1,020 National Adults, aged 18+, conducted February 28- March 1, 2006. For results based on

More information

2017 Lake Winnebago Bottom Trawling Assessment Report

2017 Lake Winnebago Bottom Trawling Assessment Report 217 Lake Winnebago Bottom Trawling Assessment Report Adam Nickel, Winnebago System Gamefish Biologist, March 218 There were several highlights from the 217 Lake Winnebago bottom trawling survey, including

More information

SWISS Traffic Figures May 2004

SWISS Traffic Figures May 2004 SWISS Traffic Figures May 2004 SWISS continues seat load factor improvement in May SWISS s load factor for May was 4.8 percentage points better than for the same period last year. Seat load factor for

More information

MAR DASHBOARD MAR. Compliant % Breakdown Mar % Late % On-time MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

MAR DASHBOARD MAR. Compliant % Breakdown Mar % Late % On-time MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Positive Response Compliance 215 Compliant 215 Non-Compliant 216 Compliant 216 Non-Compliant 1% 87% 96% 86% 96% 88% 97% 89% 89% 88% 86% 92% 93% 94% 96% 94% 8% 6% 4% 2% 13% JAN 4% 14% FEB 4% 12% 3% 11%

More information

Lake Taneycomo Fisheries Management. Shane Bush : Fisheries Management Biologist

Lake Taneycomo Fisheries Management. Shane Bush : Fisheries Management Biologist Lake Taneycomo Fisheries Management Shane Bush : Fisheries Management Biologist Lake Taneycomo Empire District Electric Company Impoundment Completed in 1913 2,8 acres 22 miles long Lake Taneycomo Table

More information

Hood Canal Steelhead Project A conservation hatchery experiment. Joy Lee Waltermire

Hood Canal Steelhead Project A conservation hatchery experiment. Joy Lee Waltermire Hood Canal Steelhead Project A conservation hatchery experiment Joy Lee Waltermire Cooperating Project Partners: NOAA: NWFSC Behavioral Ecology Team Long Live the Kings WA Department of Fish and Wildlife

More information

Instream Flow Segments In the Wind/Bighorn Basin. Paul Dey Wyoming Game and Fish Department

Instream Flow Segments In the Wind/Bighorn Basin. Paul Dey Wyoming Game and Fish Department Instream Flow Segments In the Wind/Bighorn Basin Paul Dey Wyoming Game and Fish Department WGFD Mission: Conserving Wildlife - Serving People Fish Division Mission As stewards of Wyoming s aquatic resources,

More information

Little Athletics NSW. 2018/2019 Season. Age Group Information Handbook / 1

Little Athletics NSW. 2018/2019 Season. Age Group Information Handbook / 1 Little Athletics NSW Age Group Information Handbook 2018/2019 Season / 1 Little Athletics NSW 2018/19 Season Age Group Information Handbook Introduction From the commencement of the 2018/2019 competition

More information

DEC DASHBOARD. Positive Response Compliance DEC. Compliant Tickets : On-Time Performance Analysis. December % Late.

DEC DASHBOARD. Positive Response Compliance DEC. Compliant Tickets : On-Time Performance Analysis. December % Late. Positive Response Compliance 215 Compliant 215 Non-Compliant 216 Compliant 216 Non-Compliant 1% 87% 96% 86% 96% 88% 97% 89% 97% 89% 98% 88% 97% 86% 96% 92% 97% 93% 97% 94% 97% 96% 97% 94% 97% 8% 6% 4%

More information

JAN DASHBOARD. Positive Response Compliance JAN. Compliant Tickets : On-Time Performance Analysis. January % Late.

JAN DASHBOARD. Positive Response Compliance JAN. Compliant Tickets : On-Time Performance Analysis. January % Late. Positive Response Compliance 216 Compliant 216 Non-Compliant 217 Compliant 217 Non-Compliant 1% 96% 97% 8% 6% 4% 2% 4% 3% FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 8% Late Compliant Tickets : On-Time

More information

1 PEW RESEARCH CENTER

1 PEW RESEARCH CENTER 1 SEPTEMBER 2018 POLITICAL SURVEY FINAL TOPLINE SEPTEMBER 18-24, 2018 N=1,754 RANDOMIZE Q.1 AND Q.2 BLOCK Q.1 All in all, are you satisfied or dissatisfied with the way things are going in this country

More information

Annual Meeting June 17, Research Stewardship Education

Annual Meeting June 17, Research Stewardship Education Annual Meeting June 17, 2016 Research Stewardship Education 1 James Chandler, Intern from St. Lawrence University Christina Morrisett, Research Assistant Melissa Muradian, Post-Graduate Research Associate

More information

Mexico sugar towards 2014/15. Forget the inflexion point?

Mexico sugar towards 2014/15. Forget the inflexion point? Mexico sugar towards 20 Forget the inflexion point? Pablo Sherwell VP, Food & Agribusiness Research & Advisory pablo.sherwell@rabobank.com September 2014 1 Rabobank: Food & Agribusiness Research and Advisory

More information

Goldman Sachs Agricultural Biotech Forum New York, NY. March 7, 2012

Goldman Sachs Agricultural Biotech Forum New York, NY. March 7, 2012 1 Goldman Sachs Agricultural Biotech Forum New York, NY March 7, 2012 2 Forward Looking Statement Warning This presentation contains forward-looking statements about the business, financial condition and

More information

LUXURY BOUTIQUE CRUISES. Vietnam Cambodia Myanmar DEPARTURES. Ayeyarwady & Chindwin Myanmar

LUXURY BOUTIQUE CRUISES. Vietnam Cambodia Myanmar DEPARTURES. Ayeyarwady & Chindwin Myanmar Vietnam Cambodia Ayeyarwady & Chindwin Heritage Line operates with one luxury cruise vessel named in on the Ayeyarwady and the Chindwin River. features 23 cabins in five different categories. Heritage

More information

Economic Overview. Melissa K. Peralta Senior Economist April 27, 2017

Economic Overview. Melissa K. Peralta Senior Economist April 27, 2017 Economic Overview Melissa K. Peralta Senior Economist April 27, 2017 TTX Overview TTX functions as the industry s railcar cooperative, operating under pooling authority granted by the Surface Transportation

More information

Historical user impacts, and management, of river runners in Grand Canyon National Park.

Historical user impacts, and management, of river runners in Grand Canyon National Park. Historical user impacts, and management, of river runners in Grand Canyon National Park. By Levi Jamison Photo by Caitlin Barnes The Grand Canyon The Colorado River Wilderness Whitewater http://www.arizonaedventures.com/quick-links/maps/

More information

Study 9.5 Fish Distribution and Abundance in the Upper Susitna River

Study 9.5 Fish Distribution and Abundance in the Upper Susitna River Initial Study Report Meeting Study 9.5 Fish Distribution and Abundance in the Upper Susitna River October 15, 2014 Prepared by R2 Resource Consultants, Inc. 10/15/2014 1 Study 9.5 Objectives 1. Describe

More information

Pre-Application Document Kaweah Project (FERC Project No. 298)

Pre-Application Document Kaweah Project (FERC Project No. 298) Pre-Application Document Kaweah Project (FERC Project No. 298) TABLE OF CONTENTS Page 3.11 Recreation... 3.11-1 3.11.1 Information Sources... 3.11-1 3.11.2 Setting... 3.11-2 3.11.3 Existing Project Recreation

More information

Exhibit C. Mike Gauvin -Recreational Fisheries Program Manager. September 14 th 2018

Exhibit C. Mike Gauvin -Recreational Fisheries Program Manager. September 14 th 2018 2019 Sport Fishing Regulations Exhibit C Mike Gauvin -Recreational Fisheries Program Manager September 14 th 2018 1 Topics for Consideration Public involvement in 2019 regulation process Issue 1: OAR s,

More information

Susitna Watana Hydroelectric Project Document ARLIS Uniform Cover Page

Susitna Watana Hydroelectric Project Document ARLIS Uniform Cover Page Alaska Resources Library & Information Services Susitna Watana Hydroelectric Project Document ARLIS Uniform Cover Page Title: River recreation flow and access study, Study plan Section 12.7, 2014 Study

More information

Response of a Newly Created Marsh-Wetland Affected by Tidal Forcing, Upland Discharge, and Groundwater Interaction

Response of a Newly Created Marsh-Wetland Affected by Tidal Forcing, Upland Discharge, and Groundwater Interaction Response of a Newly Created Marsh-Wetland Affected by Tidal Forcing, Upland Discharge, and Groundwater Interaction Mouth of Columbia River, Cape Disappointment State Park, Washington 12 Hans R. Moritz

More information

April 16, Yosemite National Park Superintendent Don Neubacher Attn: Merced River Plan P.O. Box 577 Yosemite, CA 95389

April 16, Yosemite National Park Superintendent Don Neubacher Attn: Merced River Plan P.O. Box 577 Yosemite, CA 95389 www.americanwhitewater.org Dave Steindorf California Stewardship Director 4 Baroni Drive Chico, CA 95928 530-343-1871 dave@americanwhitewater.org April 16, 2013 Yosemite National Park Superintendent Don

More information

Undeveloped Zoning Inventory February 2004

Undeveloped Zoning Inventory February 2004 Undeveloped Zoning Inventory February 2004 Prepared by Planning Department Undeveloped Zoning Inventory February 2004 Project Description: The Undeveloped Zoning Inventory (the Inventory) is a periodic

More information

FOR RELEASE: TUESDAY, DECEMBER 11 AT 4 PM

FOR RELEASE: TUESDAY, DECEMBER 11 AT 4 PM Interviews with 1,002 adult Americans conducted by telephone by Opinion Research Corporation on December 6-9, 2007. The margin of sampling error for results based on the total sample is plus or minus 3

More information

September 2017 MLS Statistical Report. Residential Inventory

September 2017 MLS Statistical Report. Residential Inventory September 217 MLS Statistical Report Residential Inventory 2 2 1 1 21 216 217 Summary Inventories: Residential inventory is down 1%, Lots / Land inventory is down 13% and commercial inventory was down

More information

DEPARTURES. Ayeyarwady & Chindwin Myanmar

DEPARTURES. Ayeyarwady & Chindwin Myanmar Ayeyarwady & Chindwin Heritage Line operates with one luxury cruise vessel named in on the Ayeyarwady and the Chindwin River. features 23 cabins in five different categories. Heritage Line is cruising

More information

DESCRIPTION OF THE CHELAN RIVER

DESCRIPTION OF THE CHELAN RIVER DESCRIPTION OF THE CHELAN RIVER The following information contains excerpts from the Whitewater Boating Feasibility Study conducted on the Chelan River in July, 2000. The Chelan River begins below the

More information

KC Scout Kansas City s Bi-State Transportation Management Center

KC Scout Kansas City s Bi-State Transportation Management Center KC Scout Kansas City s Bi-State Transportation Management Center Operations Report August- 215 This report contains statistical and operational data of activities at the Scout TMC for the period Saturday,

More information

Future of the Lower White Salmon River Public Meeting Summary

Future of the Lower White Salmon River Public Meeting Summary Future of the Lower White Salmon River Public Meeting Summary Saturday, May 17, 2014 9 a.m. Noon Husum Fire Hall Notification and attendance: About 45 people attended the meeting, which had been publicized

More information

62. Gulkana River, Main Fork, Middle Fork, and West Fork

62. Gulkana River, Main Fork, Middle Fork, and West Fork 62. Gulkana River, Main Fork, Middle Fork, and West Fork The Gulkana, a National Wild and Scenic River, is one of Alaska s most popular whitewater rivers because of its road accessibility and because of

More information

Specialized Survey Methods for Recreational Reef Fish Fisheries in Florida

Specialized Survey Methods for Recreational Reef Fish Fisheries in Florida Specialized Survey Methods for Recreational Reef Fish Fisheries in Florida Beverly Sauls, Research Scientist Fish and Wildlife Research Institute Marine Fisheries Research Saint Petersburg, FL Reef Fish

More information

Bluetongue Disease (BT)

Bluetongue Disease (BT) Bluetongue Disease (BT) Analysis of ADNS data since 01/2018 Reporting period: 2018-01-01 2018-12-09 Data query: 2018-12-10 AGES DSR Austrian Agency for Health and Food Safety www.ages.at Parameters Data

More information

C R I TFC. Columbia River Inter-Tribal Fish Commission

C R I TFC. Columbia River Inter-Tribal Fish Commission Columbia River Inter-Tribal Fish Commission 700 NE Multnomah, Suite 1200 503.238.0667 Portland, OR 97232 www.critfc.org C R I TFC T E CHNI C AL R E P O R T 13-07 Analyses for Effect of Survey Week and

More information

Route 79/Davol Street Corridor Study

Route 79/Davol Street Corridor Study Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process

More information

Liquefied Natural Gas: Current Trends and Future Directions

Liquefied Natural Gas: Current Trends and Future Directions Liquefied Natural Gas: Current Trends and Future Directions ASPO Boston World Oil Conference October 26, 2006 Ezra D. Hausman, Ph.D. What s in store with LNG? LNG Basics Current and Future Sources of LNG

More information

2018 Soybean, Corn, & Wheat Outlook KY and TN Grain Conference

2018 Soybean, Corn, & Wheat Outlook KY and TN Grain Conference 2018 Soybean, Corn, & Wheat Outlook KY and TN Grain Conference S. Aaron Smith, Crop Marketing Specialist, Assistant Professor, Department of Agricultural and Resource Economics, University of Tennessee

More information

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A.

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A. Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon 1998- February 8, 2 By Greg A. Taylor Oregon Dept. of Fish & Wildlife 315 E. Main Street Springfield, OR 97478

More information