BLEED DOWN OF THE GMA HIGH PRESSURE AT VAFB

Similar documents
GMA SLEEP PROCEDURE AT VAFB

BLEED DOWN OF THE HIGH GMA PRESSURE

INTERNAL LEAKAGE CHECK OF THE FLIGHT GMA

SCRUB LAUNCH RECOVERY PROCEDURE FOR THE GMA

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

GMA VENT EXTENSION SERVICE PROCEDURE

GMA PREPARATION FOR E28 TESTING

GDS OPERATING PROCEDURE

TEST OF GMA SPINUP ASSEMBLY PRESSURE SENSOR CALIBRATION

CALIBRATING THE GMA PRESSURE SENSORS AND THE ECU ENGINEERING UNIT

GMA TO SPACE VEHICLE PLUMBING HOOKUP

GMA FUNCTIONAL TEST SETTING & TESTING OF SPIN UP PARAMETERS. P0586 REV -- 20, June 2000 GPB SCIENCE MISSION PROCEDURE

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

LOW PRESSURE VOLTAGE BREAKDOWN TEST PROCEDURE FOR GSS FSU FLIGHT SPARE HVA BOARD October 28, P0938 Rev

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Spacecraft Battery Magnetic Field Survey

DESIGN VERIFICATION AND QUALIFICATION OF NEW POPPET AND BUSHING ON GMA FLIGHT SOLENOID VALVES

Vibration/leak Test 2.5 and 6 Vatterfly Valves (3179 and 3223) spare units. GP-B Engineering Procedure P0761 Rev.-

GSE CAGING BALLAST SYSTEM INSTALLATION

GUARD TANK PRESSURIZATION FOR TRANSPORT

GSE CAGING AND SPINUP BUFFER LINE INSTALLATION

CHECK READOUT LOOP CONTINUITY IN PROBE C

(PTP) PROBE PRESSURE MEASUREMENT SYSTEM INSTALLATION AND LEAK CHECK PROCEDURE

PREPARE FOR CRYO OPS FOLLOWING TRANSPORT TO B1610 To be performed at Vandenberg Air Force Base building 1610

CERTIFICATION OF THE TEMPERATURE MONITOR AND ALARM

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

PROBE-C CAGING VALVE INSTALLATION

Proton Monitor Thermal Vacuum Test Procedure GP-B P0635

CLEANLINESS TEST OF PROBE SPINUP EXHAUST LINES

POROUS PLUG CHARACTERIZATION TEST

Reduce Liquid Level in Main Tank- Liquid at NBP To be performed at Vandenberg Air Force Base building 1610

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Configure SMD for Transport to SLC-2W To be performed at Vandenberg Air Force Base building 1610

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Burst Disk on SMD

NPDGamma LH2 Target OJT Lesson Plan: Senior Operator for the NPDGamma LH2 Target Operators

GUARD TANK LIQUID LEVEL REDUCTION To be performed at Vandenberg Air Force Base building 1610

PROCEDURE FOR THERMAL CYCLING IN LIQUID NITROGEN

ASSEMBLY OF GAS FLOW HARDWARE INTO SM GMA

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Prepare Payload for Mass/CG Measurements and Condition Payload During Spin Balance Test

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

DRAFT. Operating Procedures for the NPDGamma Liquid Hydrogen Target in TA-53, Building MPF-35

Proto-qual Vibration Test Procedure 2.5 and 6 Vacuum Valves (3179 and 3223) Retest of Flight Spare Valves. GP-B P0735 Rev.-

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL.

(PTP) REMOVE PROBE SPINUP GAS/VAC. LINES (HORIZ.)

Piped Air SCBA Refilling System Standard

HYDROSTATIC LEAK TEST PROCEDURE

SEMASPEC Test Method for Determination of Cycle Life of Automatic Valves for Gas Distribution System Components

PROCEDURE TO MEASURE READOUT LOOP RESISTANCE

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018

Gettysburg College. Energy Control Program

September 2018 Pressure Test

Pressure Regulators. Operating Instructions. Instrumentation

LOCKOUT/TAGOUT PROGRAM

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR REGULATE GUARD TANK PRESSURE

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR DISCONNECT MAIN TANK VENT LINE FROM GAS MODULE MAIN TANK SUBATMOSPHERIC

Lockout/Tagout Training Overview. Safety Fest 2013

1020 Industrial Drive, Orlinda, TN fax

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR STOP PUMPING ON SMD VACUUM SHELL / DISCONNECT VACUUM MODULE

Energy Control Procedures Lockout/Tagout 29 CFR

TABLE OF CONTENTS PART 2 - CONFINED SPACES

2 Sentry MCL Installation, Operation & Maintenance

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Relief Assembly on SMD

KJ1000 Operating Instructions & Parts Manual NSN

The Discussion of this exercise covers the following points:

Types 749B and R130 Changeover Manifolds

TR Electronic Pressure Regulator. User s Manual

553 Series.

Pressurize Well to One Atmosphere with Probe Installed

BRAKE SYSTEM BLEEDING

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER FILTER DRYER

Solenoid Valves used in Safety Instrumented Systems

CLASS DH - PNEUMATIC TESTING - GREATER THAN 1 BAR (15 PSIG)

Integrity Testing LifeASSURE BNA045 and BNA065 Series Filter Cartridges

Section 1.3: PRESSURE VESSEL COMPONENTS AND SYSTEMS AND COMPRESSED GAS CYLINDERS

Irrigation System Winterization and Pressurization Procedures

WIKA INSTRUMENT CORPORATION

INSTALLATION & MAINTENANCE INSTRUCTIONS

Exhibit 4. Determination of Static Pressure Performance of the Healy Clean Air Separator (Executive Orders VR-201-N and VR-202-N)

Mass Spec will not Autotune

Pressure Relief Device Investigation Testing Lessons Learned

TECHNICAL DATA. than the water inlet pressure to the concentrate

OPERATION MANUAL NTF-15

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR CONNECT VACUUM MODULE / PUMP ON SMD VACUUM SHELL

TECHNICAL DATA Q= C. Table 1 - Specifications

Title: Standard Operating Procedure for Dasibi Model 5008 Gas Dilution Calibrator

Lockout / Tagout Safety Program

SAFETY MANUAL FOR FLAMMABLE PRODUCT TRANSFER

Thank You for Attending Today s Webinar. Today s Featured Speaker

SECTION P4 SEPARATION SYSTEMS

INSTALLATION, OPERATION AND SERVICE MANUAL ABS AIR BAG LIFT

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT)

High-Pressure Boiler Inspection Procedures: A Complete Checklist

I T T Pressure Reducing Valve WARNING INSTALLATION, OPERATION, AND MAINTENANCE MANUAL

Inert Air (N2) Systems Manual

SECRETARY OF THE AIR FORCE 17 APRIL 2000 LOADMASTER MAFFS CHECKLIST. Summary of Revisions: Redundant pages removed.

OPERATION MANUAL BFX-2

CO 2. (R744) Service Station Presentation. Contents. Goals Basic functions Specification Recovery R477 Vacuum Charge Safety Other features Prototype

AcornVac Vacuum Plumbing Systems - Trouble Shooting Guide

Lab 1c Isentropic Blow-down Process and Discharge Coefficient

Cable Pressurization Buffering

OPERATION MANUAL NTF-60 Plus

Transcription:

SU/G-B 0968 Rev - STANFORD UNIVERSITY W.W. HANSEN EXERIMENTAL HYSICS LABORATORY GRAVITY ROBE B, RELATIVITY GYROSCOE EXERIMENT STANFORD, CALIFORNIA 94305-4085 BLEED DOWN OF THE GMA HIGH RESSURE AT VAFB G-B ENGINEERING ROCEDURE To be performed at Vandenberg Air Force Base Building 1610 27 February, 2003 THIS DOCUMENT CONTAINS HAZARDOUS OERATIONS 0968 Rev - REARED S. Buchholz, Technical Writer Date AROVED C. Gray, GMA Responsible Engineer Date AROVED Harv Moskowitz, LMSSC Safety Engineer Date AROVED NASA/KSC Safety Date AROVED D. Ross, Quality Assurance Date

AROVED R. Brumley, Hardware Manager Date age ii

REVISION RECORD Rev Date Comments - 2/27/03 age i

TABLE OF CONTENTS A SCOE...... 2 B SAFETY...... 2 B.1 General... 2 B.2 Mishap Notification... 2 C QUALITY ASSURANCE... 2 C.1 QA Notification... 2 C.2 Red-line Authority... 2 C.3 Discrepancies... 2 D TEST ERSONNEL... 3 D.1 ersonnel Responsibilities... 3 D.2 ersonnel Qualifications... 3 D.3 Required ersonnel... 3 E REQUIREMENTS.... 3 E.1 Electrostatic Discharge Requirements... 3 E.2 Lifting Operation Requirements... 3 E.3 Hardware/Software Requirements...... 3 E.4 Instrument retest Requirements... 4 E.5 Configuration Requirements...... 4 E.6 Optional Non-flight Configurations...... 4 E.7 Verification/ Success Criteria...... 4 E.8 Constraints and Restrictions...... 4 F REFERENCE DOCUMENTS... 4 F.1 Drawings....... 4 F.2 Supporting documentation... 4 F.3 Additional rocedures...... 4 G OERATIONS...... 4 G.1 Verify Appropriate QA Notification......... 4 G.2 Verify Configuration Requirements...... 6 G.3 Setting up the GMA...... 6 G.4 Bleed down of GMA Downstream ressure...... 7 G.5 GMA Tank Bleed Down...... 7 G.6 GMA Final Configuration...... 8 G.7 Diagrams......... 9 G.8 D-Logs......... 10 G.9 re-test Checklist...... 12 G.10 ost-test Checklist...... 13 G.11 Contingency/Emergency Responses...... 14 H ROCEDURE SIGN OFF...... 15 age ii

List of Abbreviations and Acronyms D-Log DR ECU ESD GDS GMA G-B He LM Discrepency Log Discrepency Report Electronic Control Unit Electro Static Discharge Gas Delivery System Gas Management Assembly Gravity robe B Helium Lockheed Martin NASA psi psia psig QA SU VAFB National Aeronautics and Space Administration pounds per square inch pounds per square inch absolute(=psig+14.7) pounds per square inch gauge Quality Assurance Stanford University Vandenberg Air Force Base age iii

LIST OF SECIFIC HEADING DEFINITIONS Each type of alert message will precede the procedural step to which it applies 1. NOTE: Used to indicate an operating procedure of such importance that it must be emphasized 2. CAUTION: Used to identify hazards to equipment 3. WARNING: Used to identify hazards to personnel age 1

A B SCOE In general, this procedure is used to bleed excess pressure from the Gas Management Assembly (GMA). It starts by bleeding the pressure from the downstream portion of the system through the GMA Vent. Optionally, the supply tanks may be bled down as well. This procedure assumes that the areas of the GMA below the Gyroscope Valves (Zones 6 and 7 on Diagram 2) are at the correct pressure and therefore leaves them untouched. This procedure is a revision of 0942, which was used at LM and SU. The revision incorporates requirements for VAFB. SAFETY B.1 General The GMA is a gas pressure vessel. Under normal operations, the GMA requires no safety measures or equipment beyond those required for the use of a supply gas cylinder. ersonnel rotective Equipment (E) will be worn during hazardous operations as required by location. When any of the systems are pressurized and connected to a vacuum system, be cautious not to vent high pressure through the pumping portions of the system. Only allow high pressure to vent through approved ports and make sure that these are open at time of venting. Note that the GMA is an extremely high value piece of space flight equipment. The GMA tanks located under the GMA pallet are also fracture critical items, so care must be taken not to damage them in any way. B.2 Mishap Notification B.2.1 Injury In case of any injury or illness requiring medical treatment - Dial 911 B.2.2 Hardware Mishap In case of an accident, incident, or mishap, notification is to proceed per the procedures outlined in Lockheed Martin Engineering Memorandum EM SYS229 and Stanford University G-B 0879. Additionally, VAFB NASA Safety and 30 th Space Wing Safety will be notified as required. B.2.3 Contingency Response Responses to contingencies/emergency (e.g., power failure) are listed in Section G.11. C QUALITY ASSURANCE C.1 QA Notification This test will be conducted on a formal basis to approved and released procedures. The QA program office and NASA program and NASA Safety representative shall be notified 24 hours prior to the start of this procedure. A Quality Assurance Representative, designated by D. Ross shall be present during the procedure and shall review any discrepancies noted and approve their disposition. Upon completion of this procedure, the QA rogram Engineer, D. Ross or her designate, will certify her concurrence that the effort was performed and accomplished in accordance with the prescribed instructions by signing and dating in the designated place(s) in this document. C.2 Red-line Authority Authority to redline (make minor changes during execution) this procedure is given solely to the Test Director or his designate and shall be approved by the QA Representative. Additionally, approval by the ayload Technical Manager shall be required if, in the judgement of the TD or QA Representative, experiment functionality may be affected. Within hazardous portions of this procedure, all steps shall be worked in sequence. Out-of-sequence work or redlines shall be approved by NASA Safety prior to their performance. C.3 Discrepancies age 2

Discrepancies will be recorded in a D-log or as a DR per Quality lan 0108. D TEST ERSONNEL D.1 ersonnel Responsibilities The Test Director shall be Chris Gray or an alternate that he shall designate. The person performing the operations (Test Director or Test Engineer) has overall responsibility for the implementation of this procedure and shall sign off the completed procedure and relevant sections within it. D.2 ersonnel Qualifications The Test Director must have a detailed understanding of all procedures and experience in all of the GMA operations. The Test Director shall designate a Test Engineer as required. D.3 Required ersonnel The following personnel are essential to the accomplishment of this procedure: FUNCTIONAL TITLE NUMBER AFFILIATION Test Director/Test Engineer 1 Stanford G-B Quality Assurance 1 Stanford NASA Safety Rep 1 SFAO or ANALEX E REQUIREMENTS E.1 Electrostatic Discharge Requirements When working on the space vehicle, proper ESD protection is required. All wrist straps will be checked using a calibrated wrist strap checker prior to use. E.2 Lifting Operation Requirements N/A E.3 Hardware/Software Requirements ECU Appropriate software for controlling GMA on the spacecraft, this includes a null script which enables command-line control of the GMA. Flight GMA Vacuum system (Alcatel pump cart or equivalent) lumbing lines, cleaned consistently with Class 100 practices Clean check valve Clean manual valves (2), one of which should be a multi-turn bellows valve CSTOL Scripts as required lumbing gender changers, elbows, etc. as required, cleaned consistently with Class 100 practices Class 100 down flow hood, if required Hand held particle counter, if required Calibration Date: S/N: Model #: age 3

E.4 Instrument retest Requirements E.5 All GMA instrumentation used in taking data shall be in calibration at time of test. E.5 Configuration Requirements GMA work will be performed under Class 100 flow hood or in clean room. (class 1000 or better) E.6 Optional Non-flight Configurations N/A E.7 Verification/ Success Criteria N/A E.8 Constraints and Restrictions Normal clean room practices apply under down flow hood and in clean room. F REFERENCE DOCUMENTS F.1 Drawings Drawing No. Title 26273 GMA Schematic, G-B Dwg F.2 Supporting documentation Document No. S0681 SU/G-B 0108 SU/G-B 059 LM/479945 EM SYS229 EWR 127-1 KHB 1710.2 rev E Title CSTOL Scripts for GMA Testing Quality lan G-B Contamination Control lan Missile System relaunch Safety ackage Accident/Mishap/Incident Notification rocess Eastern and Western Range Safety Requirements Kennedy Space Center Safety ractices Handbook F.3 Additional rocedures Document No. SU/G-B 0879 SU/G-B 0875 Various 0962 Title Accident/Incident/Mishap Notification rocess G-B Maintenance and Testing at all Facilities ECU operations as applicable GMA Sleep rocedure G OERATIONS G.1 Verify Appropriate QA Notification QA Notified: NASA rogram and Safety Representative Notified: age 4

Date & Time) Date & Time) age 5

G.2 Verify Configuration Requirements Verify GMA is situated in a Class 1000 or better clean room or under a Class 100 or better flow hood. If GMA is under flow hood, verify the environment with a hand held particle counter. Counts under the hood shall average better than 10 per 0.1 cubic feet measured of size 0.5 micron or greater. G.3 Setting up the GMA Started on: Quality Note: Mark off each step of this section as it is completed. This section is a non-hazardous operation. G.3.1 G.3.2 Complete re-test Checklist (Section G.9) Verify the ECU is connected to the GMA and start up the ECU and appropriate software. Record script used here: G.3.3 Connect plumbing to the GMA vent per Diagram 1. G.3.4 G.3.5 G.3.6 G.3.7 G.3.8 With OM Vent 1 closed and OM Vent2 fully closed, start the vacuum system and evacuate the new plumbing. Slowly open OM Vent1 and evacuate up to the GMA solenoid valves. Close OM Vent1. Use the ECU to close all GMA solenoid valves. Read the GMA pressure transducers and fill in the table below. Table 1, GMA pressures, SIA: G1 G2 G3 G4 G5 G6 Expected >299 300 300 railed Actual (~36 psia) railed (~36 psia) railed (~19 psia) Quality age 6

G.4 Bleed down of GMA Downstream ressure Started on: Note: Mark off each step of this section as it is completed. Warning: Hazardous operations are about to begin, these operations involve working with mediumpressure helium. Use standard practices for handling of medium-pressure gas. (500 to 3000 psi per EWR 127-1). G.4.1 G.4.2 G.4.3 G.4.4 G.4.5 G.4.6 Request the area operation light be changed to Amber. Establish a 10 foot diameter controlled area. Request a A announcement that a hazardous task is about to begin. Ensure all nonessential personnel are clear of controlled area Verify that GMA solenoid valves OM Vent 1, OM Vent 2 and OM Vent 3 are all closed. Open OM Vent 2 (check valve cutoff). G.4.7 Open GMA solenoid valves V3, V4, V5, V6, V27 and V29. G.4.8 Open OM Vent 3 a small amount to slowly bleed the pressure from the GMA. G.4.9 When flow stops, close OM Vent 2. G.4.10 Monitor G2 and use OM Vent 1 to throttle pressure. G.4.11 When the pressure at G2 and G3 reaches desired pressure (<330 psia) close OM Vent 1 and record pressure at G3 here. G.4.12 Open V1 and V2 then wait 1 minute then Close V1, V2, V3, V4, V5, V6, V27 and V29. G.4.13 The Test Director or engineer will determine if GMA tank is to be vented as well. If not, skip to section G.6. Quality G.5 GMA Tank Bleed Down Started on: Note: Mark off each step of this section as it is completed. G.5.1 Verify that sections G.3 and G.4 have been successfully completed. G.5.2 Read the GMA pressure sensors and verify the following: G2 and G3 are greater than 270 psia; G4 and G5 are approximately 25 psia; and G6 less than 25 psia (it might be railed). G.5.3 Determine desired final GMA tank pressure and record it here (300 psia if preparing for shipping). G.5.4 If G1 reads below the pressure recorded in G.5.2 for G2 and G3, repeat section G4. G.5.5 Open GMA solenoid valves V1, V2, V3, V4, V5, V6, V27, and V29. G.5.6 Monitor pressure at G1. G.5.7 Open OM Vent 3 and OM Vent1/ 2 as required. age 7

G.5.8 When pressure reaches desired level (300 psia if preparing for shipping) close OM Vent 3 and record final pressure at G1 here. (This step may take several hours.) Quality G.6 GMA Final Configuration Started on: G.6.1 Note: Mark off each step of this section as it is completed. Verify that sections G.4 and G.5 (if necessary) have been successfully performed and all GSE valves are closed. G.6.2 Open solenoid valves V1, V2, V3, V4, V5, V6, V27, and V29. G.6.3 Monitor pressure at G6 until it stabilizes or rails (~ 19 psia). G.6.4 Close solenoid valves V29, V27, V6, V5, V4, V3, V2, and V1. G.6.5 Run GMA sleep procedure, 0962, if desired by the Test Director. NOTE: THIS HAZARDOUS OERATION IS NOW COMLETE. G.6.6 Request A announcement that hazardous operations are now complete. G.6.7 Ensure area warning light is returned to green. G.6.8 Disband controlled area. G.6.9 Disconnect the vacuum system and GSE from the GMA if desired by the Test Director. G.6.10 Cap the GMA vents if exposed. G.6.11 Shut down the ECU. G.6.12 Compete ost-test Checklist (Section G.10) Quality age 8

G.7 Diagrams Outlet Manifold Leak Detector Top Hat Vent Manifold Vent/Supply OM Leak Valve OM Valves Fill and Drain Valves OM Vent 2 OM Vent 1 OMG-2 OMG-1 OMG-3 OM Vent 3 OMG-4 OMG-1A l OM urge Valve l FMV-4 S2 S1 S3 S4 1A Vent MV4 GMA MV3 MV1 FMV-3 He MV2 FMV-2 Legend GDS 500 psi l Gamah Connection AN Connection ressure Gage l Regulator Valve (GSE) Valve (Flight) Check Valve Filter Vacuum Source Low- ressure Outlet High- ressure Outlet 3500 psi Fill Manifolds Oct. 4, 2002 GMA Integration to S/V SJB age 9

Diagram 2: GMA Schematic Zone VI Zone II Zone IV Zone V Zone VII Zone I GAS SULY BOTTLE 2000 SI GAS SULY BOTTLE 2000 SI Zone III G.8 D-Logs age 10

ART NAME: DRAWING No: LOT OR SERIAL No: No: Description of Discrepancy Disposition/ Correction Date Accepted Rework Transfer to DR No: QE Approval RE Approval age 11

G.9 re-test Checklist DATE CHECKLIST ITEM COMLETED REMARKS 1. Verify the test procedure being used is the latest revision. 2. Verify all critical items in the test are identified and discussed with the test team. 3. Verify all required materials and tools are available in the test area. 4. Verify all hazardous materials involved in the test are identified to the test team. 5. If helium is to be used verify that a blue HELIUM tag is around the neck of the helium cylinder. 6. Verify all hazardous steps to be performed are identified to the test team. 7. Verify each team member is certified for the task being performed and know their individual responsibilities. 8. Confirm that each test team member clearly understands that he/she has the authority to stop the test if an item in the procedure is not clear. 9. Confirm that each test team member clearly understands that he/she must stop the test if there is any anomaly or suspected anomaly. 10. Notify management of all discrepancy reports or d- log items identified during procedure performance. In the event an incident or major discrepancy occurs during procedure performance management will be notified immediately. 11. Verify/erform an Engineering and Safety high-bay walk down. Ensure all discrepancies are corrected prior to start of operations. 12.Confirm that each test team member understands that there will be a post-test team meeting. TEAM LEAD SIGNATURE: age 12

G.10 ost-test Checklist DATE CHECKLIST ITEM COMLETEDREMARKS 1. Verify all steps in the procedure were successfully completed. 2. Verify all anomalies discovered during testing are properly documented. 3. Ensure management has been notified of all major or minor discrepancies. 4. Ensure that all steps not required to be performed are properly identified. 5. If applicable sign-off test completion. Team Lead Signature: age 13

G.11 Contingency/Emergency Responses In the event of an emergency requiring shutdown and/or evacuation which does allow time for steps to be taken without endangering personnel, the following general steps should be taken, in order of priority (operator to determine sequence): Isolate the flight hardware wetted surfaces (fluid flow paths) from the exterior environment by closing GSE valves (GDS V-24, GDS V-25, OMurge, and OMVent, or similar, as applicable to the state of assembly.) Use ECU to close all GMA solenoid valves. Record state of GMA and related flight volumes as known (valves open/closed, current pressures, ECU status, etc.). Shut down GSE as desired (leak detectors, vacuum sources, ECU control systems, GDS, etc.). In the event of a power failure, the Test Director shall implement similar steps as applicable (see above emergency shutdown steps). In the event that these steps have been taken (in part or whole), when it safe for personnel to return to the equipment: The Test Director shall perform an evaluation of the current state of the hardware. With concurrence of the GMA, Responsible Engineer and QA, the Test Director shall issue a d-log detailing the steps required to return the flight equipment to its prior state and to establish which step the procedure shall continue from. The test director may issue partial instructions (i.e. start up GSE) for the purpose of better evaluation of the flight hardware status. If the Test Director, Responsible Engineer, or QA believe it necessary, a discrepancy report may be issued for MRB review age 14

H ROCEDURE SIGN OFF The results obtained in the performance of this procedure are acceptable: Test Director date: Discrepancies if any: Approved: date: C. Gray, GMA Responsible Engineer Approved: date: QA Representative Approved: date: D. Ross, QA age 15