Safety in Precast Erection

Similar documents
Dangerous Occurrence: Collapse of mobile crane

Mr. Teo Han Ping Head, Programme Management, Occupational Safety & Health Division, Ministry of Manpower

LIFTING PLAN PERMIT TO WORK RISK ASSESSMENT

HEALTH & SAFETY ARRANGEMENTS FOR MANAGEMENT OF WORK AT HEIGHT

IIUM EVENT SAFETY RISK ASSESSMENT

Biomedical Laboratory: Its Safety and Risk Management

??????? is committed to providing a safe work environment for its employees and preventing occupational injuries due to falls.

Appointed person Note: It is recommended that you read the Supporting Information page before you read this factsheet.

Hazard & Risk Management

Load Falls From Crane

Accident/Incident Reporting and Investigation Procedures

CPCS renewal test factsheet

Worker s Safety Handbook for Rigger and Signalman

Prevention of Falls and Working at Heights

FATAL AND SEVERE RISK PROGRAM

Conducting An Effective. Welcome!

Section 16B. Fall Protection. Falls are the second leading cause of death in the workplace. Factors contributing to falling incidents:

OPERATIONL RISK ASSESSMENTS

Work Health and Safety Risk Management Procedures

ESSENTIAL SAFETY RESOURCES

To comply with the OHS Act, the responsible manager must carry out and document the following:

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018

LOOK. THINK. DO. Basic Workplace Safety and Health (WSH) Rules 6for Working at Heights. Secure safety harness when working at heights.

Work Activity (e.g. Road Work): Work Location:.

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

Walking-Working Surfaces and Fall Protection Standards Update. OSHA General Industry

LADDERS FIXED AND PORTABLE

1. Objective of the initiative To ensure that all employees and subcontractors are aware of the risks associated with working at height.

TUDOR PARK EDUCATION TRUST. Working at Heights and Risk Assessment

VALE # Name: Dave Duczeminski Position: Manager Department: Maintenance Engineering

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.

Safe Work Method Statement

Fall Protection. 29 CFR Appendix C 29 CFR 1926 Subpart M

User Instructions 1789 Parapet Wall Anchor

HS329 Risk Management Procedure

Signature: Director of Environmental Health & Safety. Fall Protection

EVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1

Section J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS

1.2 LIMITATIONS: Consider the following application limitations before using this equipment:

HAZARD RECOGNITION EVALUATION & CONTROL. Procedure No. HR-405-PR-2 Division Human Resources. Supersedes n/a Board Policy Ref.

Job Hazard Analysis (JHA) What is Job Hazard Analysis (JHA)?

Activity Hazard Analysis (AHA) EM A.13 FIGURE 1-2 CONTRACTOR REQUIRED AHA TRAINING

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

Worksite Analysis Techniques & Tools. Bobbi K. Samples Owner/Principal Consultant The Safety Firm, LLC. Why Analyze The Workplace?

Accident Investigation and Hazard Analysis

PRO Lifting Operations

HAZARD RECOGNITION EVALUATION and CONTROL

DREW UNIVERSITY FALL PROTECTION PROCEDURE (DRAFT 12/11)

Group Guidance Risk Assessment Form

University College Dublin Machinery/Equipment Risk Assessment Template

Work At Height Health & Safety Management Standard Issue 3 (April 2011)

Contents. Page Introduction 2 Scope 2 Roles and Responsibilities 3. Risk Management Process 5 Figure 1 The Risk Management Process 6

Contractor / Exhibitor Handbook

8. Fall Protection Procedures WAC

RISK ASSESSMENT POLICY

Safe Work Method Statement

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN

Recognition, Evaluation, and Control of Hazards

B S Glass Ltd Safety procedures- outsourced Workplaces

OSHA s new walking working surfaces standards

A GUIDE TO BUYING FALL ARREST EQUIPMENT. uk.rs-online.com (UK customers) (International customers)

Reporting, Recording & more Walking Working Surfaces Local Emphasis Program Your Questions

Risk Control at United Fire Group

WARNING! DO NOT THROW AWAY THESE INSTRUCTIONS! READ AND UNDERSTAND BEFORE USING EQUIPMENT!

Accidents and accident prevention

Region: USA Language: EN Number : TB0031 Revision : B. Total Page: 3 Page n : 1 First Issue: 10/2014 Rev. Date: 10/08/2014

Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324

Duties of WAH Competent Persons

Work At Heights Toolkit. for Supervisors

WH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations

Fall Protection Resource Guide P AGE 1

User Instruction Manual Fixed Beam Anchor

Safe High Pressure Water Washing (HPWW) Requirement

Fall Protection Checklist. Guardrail System

New Mexico Institute of Mining & Technology. Fall Protection Program

This subject outlines procedures to prevent accidents or injuries to you and others from inappropriate selection and use of fall protection equipment.

User Instructions 1790 Rail Anchor

Safe Work Method Statement (SWMS)

Risks and Hazards Identified Now What?

Safe Work Practices (SWP) SWP (6) FALL PROTECTION PROGRAM

Occupational Protective Equipment

Hazard Management Making your workplace safer

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

2.2. Anchorage Point A secure point of attachment for Lifelines, lanyards or deceleration devices.

FALL PROTECTION PLAN July 2012

Example of an Occupational Health Risk Assessment

Figure 1 - Parts Identification. Copyright 2002, DB Industries, Inc.

Safe Use of Access Equipment

Safe Work Method Statement

Safe work method statements

McKay Moore Drainage Ltd. Health and Safety Policy

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:

Barricades and Falling Object Protection Plans

Design of Fall Arrest Systems: A Review of the Current Issues in the Singapore Construction Industry

This guidance explains what hazards and risks are and provides an overview of requirements under the Health and Safety at Work Act 2015 (HSWA).

HAZARD MANAGEMENT PROCEDURE

SAFE WORK METHOD STATEMENT SWMS No Version

MANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY FALL HAZARD CONTROL REQUIREMENTS SERIES & NO. SMI - 157

Transcription:

Safety in Precast Erection C. Kirubakaran R Star Consultants Pte Ltd, Singapore Abstract: Construction industry is known to be one of the most hazardous among different industries all over the world. The potential chances for accidents and near miss cases are very high during precast erection. It is therefore important to conduct risk assessment to plan and implement control measures during erection stage. The primary causes of incidents in precast erection are due to lifting operations and working at height. Author will cover the risk management, lifting related hazards and working at height that can lead to accidents and share Singapore good practices. The precast erection involves lifting operations and working at height in construction industry. This needs careful safety planning and ensure risks are eliminated or minimized to most extent. The Singapore accidents statistics shows (Figure 1) an increase in the rate of accidents in 2006 in general and pre-cast sector( Figure 2) in particular. Risk Management In Singapore, the contractors/employers are required to eliminate or reduce workplace risks under the Workplace Safety & Health (WSH) Regulations. The first thing they have to do is assess the workplace risks and then take steps to remove or reduce them in order to protect workers safety and health. Formal procedures are available to indentify and assess the hazards that can lead to accidents and to implement control measures to eliminate or minimize risks. Risk Assessment/ Management should cover all work activities related to precast and in particular precast erection at site. These include storage, handling, transportation and erection. Carrying out Risk Assessment A multidisciplinary Risk Assessment team should be formed to carryout risk assessment of the risks in precast production and erection together with contractors, sub-contractors and associated worker representatives. Step 1: Identifying hazards Employers/contractors plan to identify dangers and risks and deal with them, Methods of identifying hazards include; - Consultation with workers - Consulting with industry associations and governments - Consulting specialist practitioners - Past incident records Step 2: Assess the level of risks involved 84 Figure 1. Workplace Injuries in Precast Sector, Singapore (2001-2006) (Source: Singapore Ministry of Manpower, Singapore) Figure 2. Fatality rate in Precast Sector, Singapore (2006) ( Source: Singapore Ministry of Manpower, Singapore) Find out how severe the risks are and determine the likelihood of it happening, given the existing control measures in place. Risk is defend as combination of two factors - Likelihood of hazard and - Severity of hazard A simplest way of evaluating the risk in certain hazardous task is to quantify its likelihood and the severity of its consequences (Table 1). Each of the two factors may be given the values of 1 to 3 in 3 Point Scale. Severity is the degree or extent of injury or harm caused by accidents/incidents arising from workplace hazards. Severity is classifies in to 3 categories, Minor(1), Moderate(2), major (3). Likelihood of occurrence of an accident, incident or ill health is also classified into 3 categories; Remote(1), Occasional (2) and frequent (3) The risk is calculated as the product of likelihood and severity value. This product range from 1 (Low) to 9 ( high) Generally, low is acceptable, medium risk required to take

Likelihood Severity Remote (1) Occasional (2) Frequent (3) Major (3) Medium Risk (3) High Risk (6) High Risk (9) Moderate (2) Low Risk (2) Medium Risk (4) High Risk (6) Minor (1) Low Risk (1) Low Risk (2) Medium Risk (3) Table 1 Typical Risk Assessment on risks and hazards additional control measures and high risk is intolerable, where work can t start until appropriate control measures in place. Step 3 Risk Control Measures The control of hazards and reduction of risks can be accomplished by following hierarchy of control measures as shown in Figure 3. These control measures are not usually mutually exclusive. e.g Engineering controls can be implemented together with administrative controls like training and safe work procedures (SWP s). Common Lapses involving Lifting Activities Accident involving lifting activities occur due to many reasons. However, investigations into such accidents often reveal that the primary causes could be attributed to poor planning, supervision and coordination of lifting operations. The common lapses involving Lifting activities are - Absence or lack of RA ( Risk Assessment) prior to lifting operation - Absence of lifting plan - Absence of PTW ( Permit to Work) system implementation - Failure to adopt proper rigging methods - Poor maintenance of lifting equipments - poor site control Common hazards Associated with Unsecured/ Slippage of loads Many accidents occurred due to unsecured loads that slipped off during lifting. The following are some common hazards associated with lifting loads - Defective or damaged lifting gears such as slings, hooks, insers, eye, shackles - improper rigging of loads - Under capacity of lifting gears Figure 3 Hierarchy chart on control of hazards and reduction of risks Common hazards Associated with Lifting Operations Involving Cranes Lifting, Handling & Installation In Singapore study, accident statistics shown (Figure 4) that fatalities and dangerous occurrences at work place involving lifting equipment such as cranes has been on uptrend over the last few years. Such accidents include failure of heavy lifting equipments such as cranes during lifting activities. Figure 4 Workplace Injuries by Lifting Equipment ( 2002-2006), Singapore ( Source: Singapore Ministry of Manpower, Singapore) Accidents involving cranes are one of the more common types of crane-related incidents. Many accidents occurred due to either structural failure of the load bearing part of crane or toppling or collapsing of cranes when they became unstable The following are some common hazards associated with lifting operations involving cranes. - Structural Failure - Such as boom, jib, wire rope due to crane being loaded beyond capacity - Contactor collision due to insufficient safe clearance space between mobile crane and other buildings or structures - Falling objects as result of improper securing of loads during lifting operations or during precast erection activities - The typical lifting incident scenarios are shown in Figure 5. Precast Erection In precast erection lifting activities and multiple handling of precast elements are very critical, therefore care planning is crucial. Considerations shall be given to; - Planning of Lifting Operations - Erection Preparation - Rigging - Planning Cranes 85

Figure 5 Typical lifting Incident scenarios - Erection crew - Erection sequence - Tilting of panels - Leveling of shims - Fixing inserts - Unsuitable Lifting points - Temporary bracing etc. Lifting Plans The purpose of lifting Plan is to facilitate common understanding amongst the lifting team for safe lifting operations. A typical lifting plan incorporated with Permit-to Work System is recommended. It addresses some key factors affecting safe lifting operations such as Edge Protection, Perimeter Guard-Railing Edge protection (often referred to as a guard rail ) is used to reduce the risk of a person falling from open sides and through openings. Wherever, a person is at risk of falling from open sides. The protection must also be able to withstand the impact of a person falling against it. Typical proper and improper end protections are shown in Figure 5. - Details of the load - Details of lifting equipment/lifting gears - Means of communication - Personnel s involved in lifting operations - Sequence /special precautions - Sketch/Zone of operations Working at Height 86 Generally the precast installation of stairs, columns, beams etc will require operatives to work at height. This work will require careful planning with control measures to reduce risk of working at height. Work Environments that pose a Fall from Height Risk - Unprotected edges - Uncovered openings - Building materials, large tools or equipment that need to be manually carried - Overloading of working platforms, which may lead to collapse - Struck by moving object or equipment, for example load from lifting operation - Not use of personnel protective equipment Access and egress safety Safe means of access to the working area also requires careful planning particularly where work progress during installation. In providing safe and proper access to and egress from a work area by taking in to account the tools and equipments that people will be required to carry. The risk of falls due to tripping and slipping can be reduced by proper planning for material storage and good housekeeping. Such good practices not only result in a cleaner and safer workplace, it can also improve productivity. Figure 6 Typical proper and improper end protections The edge protection must also be provided at any other edge at the workplace where a person could fall. Such protection must adhere to dimensions and other requirements. The guard rail system must be of good construction and in good condition and be able to withstand the weight of person. Guarding of Openings Openings on floors present significant hazards. A person may fall through an opening, which may result in serious injury or death. If the opening that is stepped upon is small, cuts and bruises may result on the legs or feet. When opening is protected by a cover, a suitable signage should be placed nearby or onto the cover itself to warn people of hazard. Fall Arrest System A personnel fall arrest system is a collection of components that work in conjunction to; - Safely stop a person from falling an uncontrolled distance

87

required to carry out their work near unprotected edge such as rigging and erection. Fall Prevention Plan A site specific fall prevention plan shall be established and implemented for the purpose of reducing or eliminating risks of fall. A fall prevention plan shall address, fall from height hazards comprehensively shall be communicated among the parties involved for better understanding hazards. Conclusion Precast Erection can be a very risky operation, unless its hazards are clearly identified and control measures implemented. Singapore s consistent efforts are steadily improving its hazards control. With clear understating of better implementation of Risk Management, Lifting Plan and fall prevention plan at work place will relatively improve safety performance in precast erection in construction industry. References Figure 6 Cover Openings ( Source: Singapore Ministry of Manpower, Singapore) and reduce impact of fall - In general, a complete personal fall arrest system consists of three vital components - Anchorage - Body support - Connectors It is critical to note individually, these components will not provide protection from a fall. It is only when they are used correctly and in conjunction with each other that they will be able to arrest or sustain a fall. This can be used where workers are 1. WSHC & MOM,(2013) Code of practice for working Safely at Height, Workplace Safety Health Council & Ministry of Manpower, Singapore, March 2013 2. WSHC, (2013) Guidebook for Lifting Supervisors, Workplace Safety Health Council & Ministry of Manpower, Singapore, July 2011. 3. Approved Code of practice for The Safe Handling, Transportation and erection of Precast Concrete, Department of Labor, Wellington, New Zealand, May 2002 4. Thomas Teo, Asst Manager, Planning 7 Development, OHS Division, Dialogue Session on Programme based Engagement for Precast Sector, Overview of accidents Statistics and Trends involving Precast industry, Ministry of Manpower, Singapore Feb 2007. 5. Krishnamurthy, N.(2013) Safety During Steel Erection The Pacific Structural Steel Conference (PSSC- 2013) 6. The Safe Installation of Precast Concrete flooring and associated components, Precast Flooring Federation, 2013 88