SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)

Similar documents
SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018

Safe Work Method Statement

Safe Work Method Statement

Safe Work Method Statement (SWMS)

Safe Work Method Statement

SAFE WORK METHOD STATEMENT Part B

How severely could the risk hurt someone? Low/Insignificant First aid

WORK METHOD STATEMENT STRUCTURAL STEEL

How severely could the risk hurt someone?

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN

SWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6

How severely could the risk hurt someone? Low/Insignificant First aid

Prevention of Falls and Working at Heights

FATAL AND SEVERE RISK PROGRAM

Temporary load-bearing support for structural alterations or repairs

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:

SAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.

WORK METHOD STATEMENT CARPET LAYING

Telco Antennas SWMS Working At Height Above 2m

Work Activity (e.g. Road Work): Work Location:.

Safe Work Method Statement

Building 43 Roof Safety Assessment

Building 9 Roof Safety Assessment

MR-051 ROOF ACCESS PERMIT

JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs

Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)

SAFE WORK METHOD STATEMENT

THE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.

SAFE WORK METHOD STATEMENT SWMS No Version

Building 21 Roof Safety Assessment. Multi Story Building with large metal roof areas Exteral access required for window cleaning UOW01613

Building 31A Roof Safety Assessment. UOW01628 Access Hatch from Second Floor Yes

SWMS No 009 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 4

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

SAFE WORK METHOD STATEMENT

WORK METHOD STATEMENT TERMITE PROTECTION

WHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)

WORK METHOD STATEMENT ALUMINIUM WINDOWS AND DOORS

International House Roof Safety Assessment. 3 storey student accomodation units with tile roofs. Nil - Anchor points are not compliant None

Conducting An Effective. Welcome!

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

SAFE WORK METHOD STATEMENT Part 1

WORK METHOD STATEMENT ELECTRICAL

SAFE WORK METHOD STATEMENT

The Sample Company Pty Ltd

TLILIC2001 Licence to Operate a Forklift Truck

Specific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).

Safe work method statements

SH&EWMS No: F-C-QLD-23 Revision Date: July 2018 Revision Due: July Brief Description of Work Activity: Use Petrol Hand Saw / Ring Saw

SAFE WORK METHOD STATEMENT

Hazard Management Making your workplace safer

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

SH&EWMS No.: F-C-QLD-10 Revision Date: July 2018 Revision Due: July 2019

Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324

Deans, Directors, Heads of Schools and Departments and Research Institute Directors and Managers

Building 30 Roof Risk Assessment

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading

SAFE WORK METHOD STATEMENT CARPENTER

Safety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1

WORKING AT HEIGHT RESOURCE BOOKLET. Working at Height 1

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

B S Glass Ltd Safety procedures- outsourced Workplaces

LADDERS FIXED AND PORTABLE

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:

Building 32A Roof Safety Assessment

Safe Work Procedure for installation of external cladding

8. Fall Protection Procedures WAC

1. SHEWMS DETAILS. Project No. Valid From

SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units

FALL PROTECTION PLAN INSTRUCTIONS

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

FALL PROTECTION WORK PLAN (Alstom Power Installation Canada)

Company Name: Address: ABN: Company Contact: Position: Phone No.: Date SWMS provided to Principal Contractor: Principal Contractor Signature: Date:

ACCREDITED SAFETY TRAINING FOR EQUIPMENT OPERATORS

JOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)

Important Safety Information Enclosed

SH&EWMS No.: F-C-QLD-14 Revision Date: July 2018 Revision Due: July 2019

How severely could the risk hurt someone? Low/Insignificant First aid

Harbour Town Gold Coast Site Induction

EVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1

SAFE WORK METHOD STATEMENTS

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:

Safety Risk Assessment Roofing Works / Surveying / Inspections

S31 Opening Statement Working at Height

Safe Work Method Statement (SWMS)

Safety at Work. Rules for Staying Alive

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

FALL PROTECTION GUIDELINE

Policy Redesign Project. Plant Safety Policy. Table of Contents

HEALTH & SAFETY ARRANGEMENTS FOR MANAGEMENT OF WORK AT HEIGHT

SAFE WORK METHOD STATEMENT (SWMS)

To comply with the OHS Act, the responsible manager must carry out and document the following:

Risk Controls Proposed: (in hierarchy order from the most preferred control)

Safety Checklist for Events Held at Hillbrook

QUEENSLAND UNIVERSITY OF TECHNOLOGY

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE

Chinthurst Preparatory School

Safe Work Method Statement

FALL PROTECTION PLAN FALL PROTECTION PROGRAM

Transcription:

Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required): Principal Contractor: ABN: Project: Project/Site Manager: Job Address: Job Description: Activity: Installation / Dismantle of Perimeter / Balcony Fallguard This SWMS has been developed in consultation with Buildsafe installers and: Name: Grant Edwards Signature: Job Title: Director (Buildsafe QLD) Date: Feb 2018 SWMS documented by: Bo Ceprnja Page 1 of 13 Peter Horton Chris Maddick Director (Buildsafe Australia) Field Operations Feb 2018 Feb 2018 Date: Feb 2018 Steven Gibbs Compliance Manager Feb 2018 Personnel responsible for monitoring and managing activity: Buildsafe Installers/Assistants Name: Contact no: Overall Risk Rating Level After Controls: Level 1 Level 2 Level 3 High Medium Low Page 1 Version 4.2

Personal Protective Equipment Safety Footwear and/or Non-Slip Footwear Hearing Protection (where req.) High Visibility Clothing Head Protection (Hard Hat/Sun Hat) Eye Protection (Safety/UV) Hand Protection Personal Fall Restraint system (if required) Day Operations Normal Requirements: Safety footwear, hearing protection (where required), high visibility shirt or vest, head protection (hard hats), sun protection (wide brimmed hat and SPF 30+ sunscreen lotion), eye/face protection (goggles/safety glasses/sun glasses), hand protection (gloves) as required, personal fall arrest system if required. Any other site specific PPE requirements (to be supplied by Principal Contractor) Safety Notes The SWMS covers general safety aspects associated with the installation and dismantling of Buildsafe proprietary Perimeter/Balcony Fallguard system. It does not contain detailed information in relation to plant and equipment (such as Truck mounted cranes, Forklifts, etc.) as these require a dedicated SWMS. Main hazards: Manual tasks, Gravity, Electricity, Machinery & Equipment, Extreme Temperatures, Noise Plant/Tools/Equipment required for this activity: Buildsafe Truck EWP (if applicable) Cordless Impact Driver Cordless Drill Reciprocating Saw Non powered hand tools Maintenance Details for this activity: Prestart weekly checklist for Buildsafe vehicles Prestart check EWP (if applicable) 3 monthly testing and tagging of electrical tools and equipment Inspection of Fallguard components Materials used for this activity Industrial rated ladder, platform ladder and ladder brackets Fallguard posts Rail (various lengths) Support brackets Buildsafe proprietary materials Page 2 Version 4.2

Method of identifying, assessing and managing work health and safety risks For each potential hazard identified a risk level will be determined by referring to the Risk Matrix below. The Hierarchy of Control will be used to manage the risks identified. Step 1 Determine Likelihood What is the possibility that the effect will occur? Step 2 Determine Consequence - What will be the expected effect? Step 3 Determine the risk level Step 4 Hazard Elimination or Risk Control Risk Matrix Step 2: Consequences Fatality Permanent disability Lost time injury Medical treatment injury First aid injury Step 1: Likelihood Certain to occur Very Likely Possible Unlikely Rare 1 H 1 H 1 H 2 M 2 M 1 H 1 H 1 H 2 M 2 M 1 H 2 M 2 M 3 L 3 L 2 M 2 M 3 L 3 L 3 L 3 L 3 L 3 L 3 L 3 L Risk Rating: Likelihood / Consequence This Risk Level 1 hazard has the potential to: permanently disable or kill cause major damage to the structure have significant impact on the surrounding population and environment This Risk Level 2 hazard has the potential to: temporarily disable or seriously injure cause minor damage to the structure breach the site boundary and pollute local environment This Risk Level 3 hazard has the potential to: cause minor injury be contained within the site boundary Risk Level Level 1: High Risk Level 2: Medium Risk Level 3: Low Risk Page 3 Version 4.2

The risk levels are ranked from highest to lowest using the following control measures. Hazard Elimination and Risk Control Control measures should be considered and implemented in the following order with Level 1 the highest level of protection and level 3 the lowest: Risk Rating Level Level 1 Level 2 Level 3 Preference of Control Hierarchy of Control Example of Control Measures to implement Highest level of protection Acceptable level of protection if Level 1 is not reasonably practicable Lowest level of protection and should only be used as a last resort or in conjunction with other levels of control Eliminate the hazard The most effective control involves elimination the hazard and associated risk. e.g. eliminating the risk of fall from height by working from the ground Substitute the hazard with Use a different, less dangerous piece of equipment or replace chemicals with a safer option safer materials. Isolate the hazard from Separate noisy equipment by soundproofing or install guard rails to exposed people edges and hole in floors Reduce the risk through Add machine guarding or use trolleys or hoists to move heavy loads engineering controls Reduce exposure to the hazard using administrative actions Use personal protective equipment Establish work methods or safe work procedures for tasks or erect signage to warn people of the hazard Limit the exposure to the hazard by implementing face masks, gloves, protective eyewear, UV protection and train people in their use. Page 4 Version 4.2

Arrival on site / Parking truck Site planning General planning Preparation of Site Collisions with other equipment, workers and pedestrians Untrained and Inexperienced workers on site No consultation and poor planning leading to non compliant set up 1 H 1. Access site as per principal contractor s sign posted traffic management. 2. Observe site No Go Zones. 3. Use Hazard lights as per site requirements if applicable. 4. Ensure access around site is confined to designated road ways if applicable. 5. Buildsafe assistant to spot when reversing or when blind spots are evident on site. 6. Witches hats are recommended if in high trafficable areas parked on roads. 1 H 1. Report to site office on arrival if applicable. 2. Installers / assistants may have to complete a site specific induction before work commences if applicable. 3. Installer to provide General Construction Inductions Cards upon arrival if requested and applicable. 4. Any other high risk work licenses are to be provided if requested and applicable. 1 H 1. Ensure adequate consultation with relevant Buildsafe Supervisors / Sales staff and with Principal contractor / builder is completed prior to the commencement of installation through reading paper work. 2. Ensure Paper work is accurate in respect to equipment required to install system safely (ladder required, EWP available, if harness is required etc.) 3. Ensure brackets selected are suitable for install. 4. Ensure structure is at correct stage for installation. Slips, Trips and Falls 1 H 1. Prior to commencing of works an assessment of additional hazards not contained in this SWMS is to be performed. 2. Items assessed may include location of electrical hazards, site conditions, as well as the identification of any additional site-specific hazards not addressed in this SWMS. 3. Control measures for any additional hazards are to be documented (prior to starting works) by using the area in Part 2 of the SWMS or on a separate Pre-start risk assessment/safety analysis sheet. 4. Ensure area is clear of debris and ongoing housekeeping is maintained throughout install as per contractor s plan if applicable. Truck Driver Site Supervisor (PC) Truck Driver Sales staff Site Supervisor (PC) Truck Driver Page 5 Version 4.2

Structural Failure 1 H 1. Inspect all structures where Perimeter/Balcony is to be installed, making sure all joists/walls/beams are adequately fitted and secured. 2. If not structurally secure, inform site supervisor and Buildsafe sales staff of problem and DO NOT install components to structure until safe to do so. Electrocution through exposure to power lines I H 1. Conduct visual inspection for the presence of overhead power lines including domestic service and lead in power lines. 2. If the works, including unloading, erection or proposed purpose of use of completed system encroaches the NO GO / EXCLUSION ZONE DO NOT COMMENCE WORK. Advise your supervisor or the office who will contact the principal contractor. 3. The principal contractor must then put in place control measures and obtain relevant permit from power supplier prior to works commencing. 4. Permit and conditions for works must be sighted, read and familiarised by Buildsafe site personnel. Site Specific SWMS must be created once Permit is obtained in order for work to commence. Site Supervisor (PC) Supervisor Truck Driver Site Supervisor (PC) NO GO / EXCLUSION ZONES VICTORIA Domestic/low voltage power lines Less than 4.6m horizontally and 5m vertically Industrial/high voltage power lines Less than 8m all round QUEENSLAND Domestic/low voltage power Less than 3m all round Industrial/high voltage power lines Less than 6m all round NSW Any work within 4m of ALL power lines need referral to the network operator for any special conditions which need to be complied with. Page 6 Version 4.2

Unloading and Loading of Transport (Truck) Falling Objects Striking others Manual Handling injuries 1 H 1. Inform other trades people on site of works being performed at an elevated level and to maintain safe distances. 2. Use an installation assistant to spot if required when installing and dismantling perimeter. 1 H 1. Correct manual handling techniques are to be used (refer SWMS 0001 General Site Activities - Correct manual handling techniques). 2. Position truck as close to work area, to minimise manual handling. 3. Gloves may need to be worn when handling equipment, tools or material that may be of extreme temperatures or contain sharp or dangerous edges. Falling objects 1 H 1. Head protection (hard hats) are to be worn at all times when working on site or around the truck with the exception of Temporary Fence workers. 2. Ensure any unused equipment is kept out of any void areas, and above ladder access hatch. Truck Driver Page 7 Version 4.2

Installing Bracket/ Clamp/ Dropper/ Face Plate Setups Falling from structure 1 H Installation of setups to be done from one of the following means where applicable and reasonably practicable: Hierarchy of Controls 1. Scaffold a) Only trained and competent personnel should alter/relocate scaffold. b) Scaffold/mobile to be complete with full deck, handrail, and handover certificate before use. EWP Operator (where EWP being used) 2. EWP a) Only trained and competent personnel are to operate the EWP. b) Ensure EWP is adequate for the terrain; keep clear of any potholes, open excavations, powerlines, retaining walls etc. c) Ensure safety harness is present and worn when using boom type EWP. 3. Harness a) Only trained and competent Installers to use and attach harnesses and anchor points where required. b) Safe access to roof must be present in order to set up and use harness. 4. Ladders Ladders used for access, will have a check performed to ensure the ladder provided is: a) Rated industrial standard and in good condition b) On a level and solid base c) Footed to prevent movement if applicable d) Extends a minimum of 1m above the area being accessed e) Placed at a ratio of 4:1 from the structure f) When using a ladder three (3) points of contact must be maintained at all times g) A gutter guard or proprietary non slip ladder bracket (i.e. Laddermate) must be used at all times to secure the ladder and prevent ladder movement. Page 8 Version 4.2

Incorrect use of harness (if used) resulting in falling System failure due to incorrect installation of setups / posts resulting in falling from height 1 H 1. A fall restraint system CANNOT be used on pre floor installations another procedure must be used (Scaffold, EWP, Ladder) 2. Inspect safety harness, adjustable lanyard and all components prior to use. DO NOT USE LANYARD OR HARNESS IF COMPONENTS ARE FRAYED, WORN OR TORN 3. Installers must be trained and competent in establishing belay / tether points. The system must be attached to structurally capable item. 1 H 1. Inspect all components before installing them, using Buildsafe lock out procedures if damaged/unsatisfactory for installing. 2. Screws used for fixing brackets must be Powers brand only. 3. Ensure all screws are correctly fixed for all brackets that utilize screws as per installation, use and limitation manuals. 4. Ensure all clamp systems are tight, secured and set up as per installation, use and limitation manual specifications. 5. Ensure all bracket/clamp/dropper/face plate set ups are spaced maximum 3.6 m apart. 6. All dropper brackets must be a minimum of 300 mm apart. 7. Maximum extension of super post up a balcony upright must not exceed 700 mm. 8. Adjust height of post elevation on bracket/face plate/balcony upright/down right to ensure the finished height of the top rail will be between 900 mm and 1100 mm from flooring. 9. Ensure all L bolts on all set ups are tight where applicable. 10. Ensure that face plates are not fixed solely to window lintels. Hearing damage 1 H 1. Hearing protection (muffs or plugs) may need to be worn when excessive drilling over a long period of time or when drilling into concrete. Page 9 Version 4.2

Eye Damage 1 H 1. Safety Glasses may need to be worn to avoid damage to eyes from airborne particles i.e. when drilling into concrete. 1. All the initial rail bays out from corners must be installed prior to accessing the work area and completing the remaining rail bays. 2. The installation of the initial bays is a two-person procedure: a. The installer on the ground puts the rail into the first cam support and passes the other end of the rail to the installer on the ladder b. The installer on the ladder installs the other end of the rail into the other cam support. Buildsafe: Page 10 Version 4.2

Installing rail Falls from heights from unprotected edges and in between joists/beams 1 H 1. Before gaining access to balcony/floor joists to install rail to posts ensure (using hierarchy of control): 2. Joists/Beams are fitted and secured in place and that max spacing is 600 mm apart 3. Other building material including floor sheeting is secured.installers are not to work of unsecured. 4. Installers are not to work off unsecured or partially laid floor sheets. 5. Installers and Assistants are not to walk across the centre of joists. 6. When walking on top of a joist, this must be done behind previously installed edge protection and the installer must always be in reach for a handhold of the top rail 7. The installer must have hand in contact with the top rail while moving into the next position to install a bay of rail 8. All appropriate corner sections of hand rail applicable are installed so that continuous rail installation in one direction can be achieved safely from behind secured rail. 9. An appropriate section of rail is installed at predetermined access point so that safe access and continuous installation of rail in one direction can be achieved safely from behind secured rail. 10. All short returns of rail to be installed from behind secured rail or using hierarchy of controls procedure. Page 11 Version 4.2

For the below procedure risk assessment must be completed, Installer is to communicate to the Branch Manager if they are able to do the job as per the below procedure or the frame is just not ready for the job to be done safely: 11. Installing pre-joist procedure is below: a. To be done from a ladder, either off a platform or 4.2m ladder b. Pre-joist installation can only be done on a timber frame c. Under no circumstance are installers to walk on the top plate to install rail d. The ribbon plate must be installed e. The installation of rail is a two-person procedure f. One installer is on the ladder the other is on the ground g. The installer on the ground puts the rail into the first cam support and passes the other end of the rail to the installer on the ladder h. The installer on the ladder installs the other end of the rail into the other cam support. 12. Parapet brackets installed off studs below for 2nd and 3rd storey perimeter so brackets can be removed safely from inside frame. Rail lengths slipping and falling striking others and property System Failure due to incorrect overlapping / height of rail 1 H 1. Ensure when leaning sets of rail up, pre installation, they are leant against a secure post or structure and are not going to slip in any direction. Especially in windy conditions. 1 H 1. Ensure rail overlapping past posts is minimum 100 mm. 2. Ensure rail overlapping past corner posts is between 100 mm and 500 mm 3. Ensure all rail is secured and continuously tied together throughout installation. 4. Ensure all rail joiners are fitted to top rails as per installation, use and limitation manuals. Page 12 Version 4.2

Dismantling Rafter All hazards included above 1 H 1. Position truck as close to working area as possible to minimize manual handling distances. 2. Inform all trades people on site of intention to work in area. 3. Dismantle system in reverse order to installing using all control measures above for all hazards. 4. When dismantling ensure equipment is passed down not thrown. References: Code of Practice: How to manage Work Health and Safety Risks Safe Work Australia 2011 Code of Practice: Hazardous Manual Tasks Safe Work Australia 2011 Code of Practice: Managing the Risks of Falls at Workplaces Safe Work Australia 2011 Electrical Safety Code of Practice 2010 Working Near Exposed Live Parts Electrical Safety Office Queensland Code of Practice: Work Near Overhead Power Lines 2006 WorkCover NSW Framework For Undertaking Work Near Overhead And Underground Assets Worksafe Victoria 2006 Work Health and Safety Act (Qld) 2011 Work Health and Safety Regulation (Qld) 2011 Work Health and Safety Act (NSW) 2011 Work Health and Safety Regulation (NSW) 2011 Occupational Health and Safety Act (Vic) 2004 Occupational Health and Safety Regulations (Vic) 2017 Buildsafe Induction Buildsafe Perimeter Fallguard Installation Manual Buildsafe Site Safety Management Plan Buildsafe SWMS 0001 General Site Activities AS/NZS 4994 Temporary Roof Edge Protection for Housing and Residential Buildings SAFE WORK METHOD STATEMENT Part 2 Additional Hazards Identified on this site Page 13 Version 4.2

Page 14 Version 4.2

SAFE WORK METHOD STATEMENT Part 3 Personal Qualifications, Training and Experience required for the job: General Construction Induction Card. : Scaffolder Ticket Minimum Basic Scaffold, Completion of Buildsafe Induction. : Completion of Buildsafe Induction. Truck Driver: Recognised state issued License for vehicle class. EWP License if EWP being used. Employee Sign-off This SWMS has been developed through consultation with Employees. I have read the above SWMS and I understand its content. I confirm that I have the skills and training, including relevant certification to conduct the task as described. I agree to comply with safety requirements within this SWMS including safe work instructions and Personal Protective Equipment described. Name Qualifications Signature Date Review No. 1 2 3 4 5 6 7 8 9 Name and Tony Lavin Grant Edwards Grant Edwards Anthony Young Bo Ceprnja Bo Ceprnja Bo Ceprnja Bo Ceprnja initials Date July 31, 2012 Nov 11, 2012 Feb 28, 2013 Feb 05, 2014 Feb 05,2015 Feb 28,2016 Feb 16,2017 Feb 2018 Page 15 Version 4.2