1 Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Residential BUILDING: International House International House Roof Safety Assessment DESCRIPTION: RISK ASSESSMENT # : ROOF ACCESS: SIGNAGE : COMPLIANCE PLATES: SAFE WORK AREA: ROOFING SYSTEM: HEIGHT OF BUILDING: PITCH: ROOF CONSTRUCTION: STRUCTURAL INTEGRITY: 3 storey student accomodation units with tile roofs. Nil Nil - Anchor points are not compliant None 4 x Three storey accomodation units, single storey student amenities area Concrete tile Sound but some tiles could be cracked or loose VEGETATION: ADJOINING ROOFES: Yes - some section of roofing have a large amount of leaf litter from overhanging trees Nil SERVICES: Gutters Yes Satellite Dishes Yes A/C Units No Antenna Yes Exhaust Fans No Skylights Domes Yes Ducts No Glass Skylights Yes Roof Ventilators No Pipework No EXISTING SAFETY ITEMS: Horizontal Lifelines No Handrail No Anchor Points Yes Walkway No Vertical Lifelines No Parapets No WORK ACTIVITY DETAILS: Clean Gutters / Routine Maintenance Frequency Yearly Note: Before commencing any work obtain Roof Permit from Accomodation Services
2 Roof Safety Survey RISK ASSESSMENT Risk Assessment / Task Location Kooloobong Note: The hazards identified do not include hazards that related to specific work tasks. These should be identified in the Safe Work Method Statement (SWMS) of the contractor. Hazard Identification Risk Assessment & Control Measures Risk Control What is the Activity/Service Item What are the potential Hazards What is the Risk Level List any Control Measures already Implemented Describe what can be done to eliminate risk or reduce the harm Access to Roof Temporary Ladder - Falling M Maintain 3 points of connection and secure ladder at top and bottom Access to Roof EWP falling H Suitable access to roof to be determined. All access points to roof are locked and made Access to Roof Unauthorised access M secure so are not accessable by unauthorised persons; signage Access roof Steep pitch H Establish temporary fall arrest system Access roof Falling H Establish temporary fall arrest system Access roof Slips, trips - Vegetation H Regular cleaning of gutters. Glass Roofs Falling near or through skylight. There is no safe access around the glazing. H Nil Gutter Maintenance on Roof and Awnings Falling H Nil General Trip Hazard - Roof tiles (loose or cracked) H Safe Work Procedure Ladder bracket for securing ladder. Maintain 3 points of connection and secure ladder at top and bottom Trained operators- tiled roof - steep pitch and unprotected. Risk Assessment and Roof Safety Survey Works to be undertaken in retraint mode only. Works to be undertaken in retraint mode only. On-going cleaning and removal of over-hanging tree limbs Signage or barriers to prevent access or as a minimum ensure Horizontal Lifeline and Anchors used correctly Work Platform, Handrail, Horizontal Lifeline, or a minimum of anchor points Walkway or minimum awareness in Safe Work Procedure Work Platform, Handrail, Horizontal Lifeline, or a minimum of anchor points Gutter Maintenance Falling H Nil General Environmental Hazards - Spiders, Wasps, and other insects M Appropriate PPE and insect repellent; Pest control On-going pest control measures as required Do not work while roofs are wet or General Weather Trips/Slips - Wet Roofs H Safe Work Procedure have dew General Weather - Windy Condition H Safe Work Procedure Do not work in windy conditions General Weather - Hot Conditions M Thermal Comfort Guidelines Use suncream, hats and remain hydrated and take appropriate breaks
3 Reference Documentation Legislation NSW Work Health and Safety Regulation 2011 Part 4.4 Falls Australian Standards AS : Fixed platforms, walkways, stairways and ladders - Design, construction and installation AS : Industrial fall-arrest systems and devices - Harnesses and ancillary equipment AS : Industrial fall-arrest systems and devices - Horizontal lifeline and rail systems AS : Industrial fall-arrest systems and devices - Fall-arrest devices AS : Industrial fall-arrest systems and devices - Selection, use and maintenance AS : Safety, protective and occupational footwear - Guide to selection, care and use AS : Temporary edge protection - General requirements AS : Temporary edge protection - Roof edge protection - Installation and dismantling Code of Practice WorkCover - Safe Work on Roofs. Part 1 - Commercial and industrial buildings UOW Documentation Working at Heights Guidelines Thermal Comfort Guidelines UOW Roof Access Permit UOW Roof Access Certificate Other WorkCover Safety Guide - Portable Ladders February 1999 WorkCover - Safe Working at Heights Guide 2006
4
5 Student Amentities looking north from ABC wing Roof access in J K L wing Student Amenities looking south west towards DEF wing Antenna on G H I wing Student Amentities looking north from ABC wing NW roof of Student Amenities looking towards DEF wing M N O Wing
6
Building 9 Roof Safety Assessment
Roof Safety Survey GENERAL INFORMATION Building 9 Roof Safety Assessment CAMPUS: Wollongong Campus BUILDING: Sports Hub (9) DESCRIPTION: Two storey metal roof building with no internal roof access and
More informationBuilding 31A Roof Safety Assessment. UOW01628 Access Hatch from Second Floor Yes
Roof Safety Survey GENERAL INFORMATION Building 31A Roof Safety Assessment CAMPUS: Wollongong Campus BUILDING: Facilities Management Division (31 A) DESCRIPTION: Two storey metal roof building comprising
More informationBuilding 43 Roof Safety Assessment
Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Campus BUILDING: Building 43 Building 43 Roof Safety Assessment DESCRIPTION: RISK ASSESSMENT # : ROOF ACCESS: SIGNAGE: COMPLIANCE PLATES: SAFE
More informationBuilding 21 Roof Safety Assessment. Multi Story Building with large metal roof areas Exteral access required for window cleaning UOW01613
Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Campus BUILDING: 21 Early Start Facility DESCRIPTION: RISK ASSESSMENT # ROOF ACCESS: Multi Story Building with large metal roof areas Exteral access
More informationBuilding 32A Roof Safety Assessment
Roof Safety Survey GENERAL INFORMATION Building 32A Roof Safety Assessment CAMPUS: Wollongong Campus BUILDING: Print & Distribution (32A) Building is a two storey metal warehouse structure with steeply
More informationBuilding 30 Roof Risk Assessment
Roof Safety Survey GENERAL INFORMATION Building 30 Roof Risk Assessment CAMPUS: Wollongong Campus BUILDING: Woolyungah Indigenous Centre / UOW College (30) DESCRIPTION: L shaped 2 storey building with
More informationBuilding 24 Roof Safety Assessment
Roof Safety Survey GENERAL INFORATION CAPUS: Wollongong Campus BUILDING: Teaching Building (24) DESCRIPTION: odern three storey building with low pitch metal roof. orizontal lifelines located 2 metres
More informationBuilding 68 Roof Safety Assessment
Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong BUILDING: Building 68 Kooloobong Stage 2 DESCRIPTION: Modern E shaped unit accommodation block comprising of three wings. Pitch and level of roof
More informationBuilding 16 Roof Safety Assessment
Building 16 Roof Safety Assessment Roof Safety Survey GENERAL INFORMATION CAMPUS: Wollongong Campus BUILDING: Library (16) DESCRIPTION: Original flat concrete roof surrounded by handrail and parapet. More
More informationSafety Risk Assessment Roofing Works / Surveying / Inspections
One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 One Direct Operatives accessing roof
More informationFATAL AND SEVERE RISK PROGRAM
FATAL AND SEVERE RISK PROGRAM LEADER SESSION FALL FROM HEIGHTS Only do the task if it can be done safely FALL FROM HEIGHTS OUR COMMITMENT LIFE SAVING BEHAVIOUR: I WILL ALWAYS USE ADEQUATE PROTECTION WHERE
More informationSAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationDevelop and sign off on risk assessment/work method statement for the task, considering task specifics elements that will affect the user s safety:
Safe Use Step 1 Complete your site induction with the RIS Altitude system owner and confirm that the users can demonstrate competence in the activity of working at heights by provision of a nationally
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More informationHarbour Town Gold Coast Site Induction
Harbour Town Gold Coast Site Induction At Harbour Town Gold Coast we believe that safety is integral to the way we do business. We are committed to operating a safe environment for all where we are incident
More informationPrevention of Falls and Working at Heights
Workplace Safety Schools Cleaning Prevention of Falls and Working at Heights It is the policy of the Company to avoid working at heights above 2 metres wherever practical. When avoidance is not an option,
More information1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6
CONTENTS PAGE 1 AIM 2 2 APPLICATION 2 3 DEFINITIONS 2 4 REASONS FOR INCLUSION 3 5 REQUIREMENTS 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 APPENDIX
More informationLADDERS FIXED AND PORTABLE
CONTRACTOR WHS HAZARD STANDARD LADDERS FIXED AND PORTABLE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationSAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required):
More informationWORKING AT HEIGHTS MANUAL
WORKING AT HEIGHTS MANUAL 1300 301 755 SAYFA.COM.AU 1 ABOUT SAYFA Sayfa Group leads the industry in the design, installation and management of access, fall protection and ground safety systems. The In-Action
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Work Activity/Description: Site Name: Date: Site Address: Name Position Signature Document No: Prepared By: OHS Manager Revision: Reviewed By: National Program Manager
More informationAnchor on the Go. Portable Roof Anchor for Metal Roofs. Part Number Patent Number Installation and Operating Instructions
Anchor on the Go Portable Roof Anchor for Metal Roofs Part Number 762998 Patent Number 2003258383 Installation and Operating Instructions WARNING: This product is part of a fall protection system. Users
More informationApplying Construction Fall Protection Concepts to General Industry
Applying Construction Fall Protection Concepts to General Industry Applying Construction Fall Protection Concepts to General Industry Michael Tesmer, CSP and David Jewell, CSP Conney Safety Products This
More informationFALL PROTECTION
115500 FALL PROTECTION PART 1 GENERAL 1.01 General A. Cornell University seeks to prevent exposures to fall hazards whenever possible and protect personnel that may be exposed to fall hazards. Therefore,
More informationOrmiston Academies Trust. Ormiston Horizon Academy. Working at Height Policy October 2016
Ormiston Academies Trust Ormiston Horizon Academy Working at Height Policy Project/job number: Author: Sharlene Smith/Handsam Date: 25/10/16 Contributors: Sharlene Smith Version number: 1.1 Reviewed by:
More informationThis subject outlines procedures to prevent accidents or injuries to you and others from inappropriate selection and use of fall protection equipment.
Page 1 of 7 REFERENCES Personal Protective Equipment Standards 1.31 PURPOSE This subject outlines procedures to prevent accidents or injuries to you and others from inappropriate selection and use of fall
More informationDeans, Directors, Heads of Schools and Departments and Research Institute Directors and Managers
Working at Height 1. PURPOSE 1.1 To ensure that any work at height is carried out in accordance with the legal requirements and associated guidance. This includes the use of scaffolds, towers, ladders,
More information8. Fall Protection Procedures WAC
1.0 Fall Protection Introduction 8. Fall Protection Procedures WAC 296-155-245 If an employee is exposed to a fall hazard of ten (10) feet or more in height, the employee must use a fall restraint, fall
More informationMR-051 ROOF ACCESS PERMIT
Instruction 1 State the job Details. Date: Site Name: Site Supervisor: Number of workers: Work description: Blocks being accessed: Existing weather conditions: Instruction 2 State and verify competency/
More information7 Hazard assessment 8 Worker participation 9 Hazard elimination and control
This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Businesses in this industry
More informationCompany Name: Address: ABN: Company Contact: Position: Phone No.: Date SWMS provided to Principal Contractor: Principal Contractor Signature: Date:
Page 1 of 15 ACTIVITY: Heights - Working at SWMS No.: SAFE WORK METHOD STATEMENT (SWMS) - Part 1 Company Name: Address: ABN: Company Contact: Position: Phone No.: Project Details Project: Job Address:
More informationFALL PROTECTION WORK PLAN (Alstom Power Installation Canada)
FALL PROTECTION WORK PLAN (Alstom Power Installation Canada) Location: Unit: Foreman: Task: Supervisors Ensure: Workers must review and sign this fall protection work plan prior to starting work in an
More informationTelco Antennas SWMS Working At Height Above 2m
Telco Antennas SWMS Working At Height Above 2m A SWMS shall be developed for a task where the risk has been assessed as Medium or Higher Division: Date: SWMS No: (e.g. Installation, Engineering Workshop)
More informationSWMS No 007 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS Manual SWMS No 007 Samark North Qld Pty Ltd ABN : 99 082 958 487 Electrical Contractors License C37121 Page 2 of 6 Safe Work Method Statement Title: SWMS:007 WORKING ON ENERGISED
More informationWorking at Heights PROCEDURE
Working at Heights PROCEDURE Contents 1.0 Purpose 2.0 Objective 3.0 Scope and limitation 4.0 References and sources of information 5.0 Responsibilities 5.1 University Managers 5.2 University Staff Overseeing
More information2018 INSPECTION REPORT
2018 INSPECTION REPORT Compiled For Queensland University of Technology KELVIN GROVE CAMPUS INTRODUCTION Height Dynamics is an innovative height safety company that provides a diverse range of products
More informationWork At Height Health & Safety Management Standard Issue 3 (April 2011)
Work At Height Health & Safety Management Standard Issue 3 (April 2011) Introduction This document contains corporate standards and guidance on the management of risks arising from work at height. It is
More informationTraining Manual RIIWHS204D Work Safely at Heights
Training Manual RIIWHS204D Work Safely at Heights START TIME: 7.45AM SHARP Participants must read this manual prior to attending the training program and are required to bring the manual to the training
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More informationWork At Heights Toolkit. for Supervisors
Work At Heights Toolkit for Supervisors For Supervisors How to use this toolkit? The toolkit aims to provide information for supervisor to communicate one topic a day to workers. Pictures are for illustration
More informationGARDENS POINT CAMPUS
08 INSPECTION REPORT Compiled For Queensland University of Technology GARDENS POINT CAMPUS INTRODUCTION Height Dynamics is an innovative height safety company that provides a diverse range of products
More informationROOFING FALL PROTECTION 27.I
ROOFING FALL PROTECTION 27.I Prior to the start of work, a structural analysis of the roof shall be conducted by a Qualified Person to assure that the load capacity of the roof deck will not be exceed.
More informationFALL PROTECTION LADDERS ACCESSWAYS
FALL PROTECTION LADDERS ACCESSWAYS PORTABLE LADDERS Max. Height 20 Step Ladder For small hand tool use only Must have non-slip feet Top step is not to be stood on Wood ladders not to be painted See COE
More informationSWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional
More informationROOF ANCHOR TO GO INSTALLATION & OPERATING INSTRUCTIONS. AZ-200 Portable Roof Anchor for Metal Roofs. zero4heightsafety.com
ROOF ANCHOR TO GO AZ-200 Portable Roof Anchor for Metal Roofs INSTALLATION & OPERATING INSTRUCTIONS WARNING: This product is part of a fall protection system. Users must read and follow instructions in
More informationRisk Control at United Fire Group
In the United States, falls are the leading cause of fatalities on a construction site. Employers and employees need to do the following: Where protection is required, select fall protection systems appropriate
More informationSOP. Working in Confined Spaces
Purpose This procedure outlines the requirements for the management of entry into confined spaces in all work areas with the intention of minimising risks to health and safety from any potential hazards
More informationCONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition WHS
More informationWorking at Height. Contents
Working at Height Contents Disclaimer... 2 1. Overview... 3 2. Key Considerations Working at Height... 4 2.1 All work at height... 4 2.2. Ladders NOTE ladders are the last option that should be considered
More informationSAFE WORK METHOD STATEMENT Part B
SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS
More informationCHAPTER 10 FALL PROTECTION
CHAPTER 10 FALL PROTECTION A. INTRODUCTION... 1 B. CHAPTER-SPECIFIC ROLES and RESPONSIBILITIES... 2 C. HAZARD IDENTIFICATION... 3 1. Job Hazard Analysis (Jha).... 3 2. Fall Hazards... 3 D. HAZARD CONTROL...
More informationSAFETY 101: FALL PROTECTION: REDUCING FALLS DURING RESIDENTIAL CONSTRUCTION: RE-ROOFING FACT SHEET
SAFETY 101: FALL PROTECTION: REDUCING FALLS DURING RESIDENTIAL CONSTRUCTION: RE-ROOFING FACT SHEET Re-roofing exposes workers to the hazards of demolition work at heights. With the proper fall protection,
More informationEZ SERIES FIXED ACCESS LADDERS
EZ SERIES FIXED ACCESS LADDERS Engineered from the ground up for OSHA 1910.3 COMPLIANCE Installs in three easy steps 1 ATTACH MOUNTING BRACKETS PLACE RUNG IN BRACKET 3 SECURE WITH BOLTON CAPTURE PLATE
More informationFALL PREVENTION PROCEDURE
TABLE OF CONTENTS 1. OBJECTIVE... 3 2. SCOPE... 3 3. DEFINITIONS... 3 4. RESPONSIBILITIES... 4 5. HAZARD AND RISK ASSESSMENT... 4 5.1 WORKING AT HEIGHT PERMIT... 4 5.1.1 Permit Currency... 5 5.1.2 Working
More information1. Objective of the initiative To ensure that all employees and subcontractors are aware of the risks associated with working at height.
Safety Initiative 02 Working at Height May 2011 CONTENTS 1. Objective of the initiative 2. Overview. 3. Implementation 4. Duties 5. Hierarchy of Controls 6. Workplace Inspections 7. Fragile Surfaces 8.
More informationDREW UNIVERSITY FALL PROTECTION PROCEDURE (DRAFT 12/11)
PURPOSE The objective of this policy & guideline is to eliminate the potential for injuries and fatalities to employees and contractors resulting from falls from elevated work areas at Drew University
More informationWORKING AT HEIGHTS CS-PTW-HAZ-02
CS ENERGY PROCEDURE FOR WORKING AT HEIGHTS CS-PTW-HAZ-02 Responsible Officer: Corporate PTW Administrator Responsible Executive: Chief Executive Officer (CEO) DOCUMENT HISTORY Key Changes Prepared By Checked
More informationOverview. Identify fall hazardous areas Describing potential fall hazards How appropriate portable and extension ladders are used
FALL PROTECTION Overview Identify fall hazardous areas Describing potential fall hazards How appropriate portable and extension ladders are used Fall Protection All situations that expose personnel to
More informationSECTION FACILITY FALL PROTECTION PART I - GENERAL
SECTION 11 24 29 - FACILITY FALL PROTECTION PART I - GENERAL 1.1 The Illinois Department of Labor (IDOL) regulates fall protection for general industry and construction in the public sector under the Illinois
More informationSubparts D and I Walking-Working Surfaces & Personal Protective Equipment Final Rule
Subparts D and I Walking-Working Surfaces & Personal Protective Equipment Final Rule OSHA s Mission To Assure So Far as Possible Every Working Man and Woman in the Nation Safe and Healthful Working Conditions...
More informationJ&S Cooper Utilities
Working at Heights Inspection conducted for J&S Cooper Utilities Conducted on 17 Apr 2018 08:35 AM Location 11953 Tyler Rd, Red Bluff, CA 96080, USA Prepared by SafetyCulture Staff Completed on 17 Apr
More informationSWMS No 009 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 4
Samark North Qld Pty Ltd SWMS Manual SWMS No 009 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C72 Page 2 of Safe Work Method Statement Title: SWMS:009 Confined Space Work
More informationThe following items represent the bulk of the exposure to falls on a construction site.
Falls Page 60 Wily Coyote always seems to fall into a deep canyon and not be injured at all. People can t. Then why do we seem to have trouble getting workers to pay attention to the fall hazards around
More informationApplication Showcase LIFE MATTERS TM
Application Showcase LIFE MATTERS TM Diversified Fall Protection specializes in the design, development, and manufacture of engineered fall protection systems designed to keep workers safe while working
More informationFALL PROTECTION PLAN July 2012
FALL PROTECTION PLAN July 2012 Office of Police and Safety (423)323.0255 Introduction In the construction industry in the United States, falls are the leading cause of worker fatalities. Each year, on
More informationKG Training and Assessing. IMPORTANT! You must read this letter!
IMPORTANT! You must read this letter! ABN: 421 334 328 63 National Provider Number (RTO ID): 52112 Location: Unit 1/8 Day Road, Rockingham WA 6168 Postal Address: PO Box 2111Rockingham DC WA 6967 Ph: 08
More informationWorking at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.
Working at Height Policy and Procedures Author: Beth Webster Assistant Safety Advisor Authorised by: Issued by: John Stephenson Safety Office On behalf of School Safety Committee Review Date: NO LATER
More informationSurface exploration drilling
Checklist Surface exploration drilling This checklist is intended to assist employers to identify common hazards and manage risks associated with surface exploration drilling. June 2017 Background In surface
More informationFALL PROTECTION PROGRAM (OHS-0010)
() For Issued: December 17, 2007 Revised: 1 st Issue PAGE 1 OF 17 Table of Contents 1.0 Purpose...2 2.0 Document Control...2 2.1 Approvals...2 2.2 Responsibility...2 3.0 Definitions...3 4.0 Objective...7
More informationWorking at Heights Training Checklist (Ontario Version)
Working at Heights Training Checklist (Ontario Version) The new working at heights training is different from the fall protection training required by Sec. 26.2(1) of the Ontario Construction Projects
More informationSAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units
Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person
More informationOnce the job has been planned and the site has been inspected according to WHS and site requirements it is important to follow work procedure and
Once the job has been planned and the site has been inspected according to WHS and site requirements it is important to follow work procedure and instructions in the implementation of safe work at heights.
More informationFCX Department of Occupational Health and Safety. Flagging and Barricading Guideline
FCX Department of Occupational Health and Safety Flagging and Barricading Guideline Approval Date: 11/12/13 Original Date: 03/30/09 SOP # FCX-19 Revision # 1 Supersedes X High Medium Task Risk Low NA Contents
More informationFALL PROTECTION PLAN INSTRUCTIONS
Sonic Drilling Ltd. FALL PROTECTION PLAN INSTRUCTIONS Each employer must ensure that a fall protection system is used when work is done at a place from which a fall of 3 m (10 ft) or more may occur, or
More informationThis information has been developed by an OSHA Compliance Assistance Specialist and is intended to assist employers, workers, and others as they
New Walking-Working Surfaces and PPE (Fall Protection) Rule Disclaimer This information has been developed by an OSHA Compliance Assistance Specialist and is intended to assist employers, workers, and
More informationReviewed: New Effective: 5/18/12 Supersedes: New Preparer: Owner: Approver: Team Member, Occupational Safety Industrial Hygiene
Procedure No.: BC032.027 Page: 1 of 15 Preparer: Owner: Approver: Team Member, Occupational Safety Industrial Hygiene Manager, Occupational Safety Industrial Hygiene Vice President, Ecology & Safety (Signature
More informationTUDOR PARK EDUCATION TRUST. Working at Heights and Risk Assessment
TUDOR PARK EDUCATION TRUST Working at Heights and Risk Assessment Person(s) responsible for updating the policy: Chief Executive Officer Date Approved: Board of Directors on 7 July 2016 Period of Review:
More informationDepartment of Facilities Management. Occupational Health and Safety. Fall Protection Program
Department of Facilities Management Occupational Health and Safety Fall Protection Program October 2016 1 1.0 INTRODUCTION This program has been developed to provide guidance to those managers and supervisors
More informationSafety Checklist for Events Held at Hillbrook
Safety Checklist for Events Held at Hillbrook Hazards/ Issues or Tasks 1. EVENT ACCESS AND EGRESS Entry / Exit areas are kept clear and accessible. For an evening event, that you have appropriate Lighting.
More informationSafe Work Procedure for installation of external cladding
Safe Work Procedure for installation of external cladding This procedure has been formulated to cover safe systems of work for the installation of external cladding. This instruction will be used to reduce
More informationTraining and Assessment Strategy
TAS Work Safely at Heights RIIWHS204D Training and Assessment Strategy Version 5.00 Introduction This Training and Assessment Strategy (TAS) provides a guide to Trainers/Assessors as to how to deliver
More informationFALL PROTECTION CODE OF PRACTICE
FALL PROTECTION CODE OF PRACTICE This guide can help you comply with Section 50.2 of the General Regulation 91-191. NOTE: Not for use when a safety monitor is part of the fall protection system on a work
More information2.2. Anchorage Point A secure point of attachment for Lifelines, lanyards or deceleration devices.
Title: Elevated Walking/Working Surfaces (Fall Protection) Site Function: Safety Procedure No.: MC032.122 Page: 1 of 16 McIntosh Site Reviewed: 02/2013 Effective: 03/2013 Supersedes: 08/2012 Preparer:
More informationFall Protection Program
Fall Protection Program 135 College Street, Suite 100, New Haven, CT 06510 Telephone: 203-785-3550 / Fax: 203-785-7588 ehs.yale.edu 6/26/2018 CONTENTS: 1. Introduction... 3 2. Responsibilities... 3 A.
More informationFALL DATA COLLECTION INSTRUMENT
FALL DATA COLLECTION INSTRUMENT Case ID: MI Date of Investigation / / Respondent Victim Information 1. Was the victim performing a task that was not a part of their normal work duties/tasks? 2. Was anyone
More informationType: Policy. Working at Heights Policy. Register No: Status: Public. Developed in response to: Work at Height Regs 2007
Working at Heights Policy Type: Policy Register No: 09085 Status: Public Developed in response to: Work at Height Regs 2007 Contributes to CQC Outcome: Regulation 15 - Premises and equipment Consulted
More informationWorking at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use.
A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: WORKING AT HEIGHT CSBP-GM-11-031-02 Version Number: 24.0.0 Date Revised: 10 September
More informationFall Protection on Low Sloped Roofs for General Industry. Presented by: Brian Stickler
Fall Protection on Low Sloped Roofs for General Industry Presented by: Brian Stickler Learning Objectives: Learn how to identify hazard areas on the roof Determine what OSHA considers to be a hole on the
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationThe content of this resource has been generously provided by the AGC Houston, the Associated General Contractors of America.
Construction & Utilities Division Planning Tools The content of this resource has been generously provided by the AGC Houston, the Associated General Contractors of America. Guidelines for Creation of
More informationPRO Working at Height
MS&L Procedure PRO-4.5-0001-1-05 Working at Height Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21/11/2017 This document has been approved for release and changed as per the associated
More informationFall Protection ABC s
Fall Protection ABC s Chris Caron American Safety & Supply, Inc. Fall Protection ABC Itinerary Review types of fall arrest systems Review and discuss ladder safety Discuss the various components of fall
More informationFALL PROTECTION GUIDELINE
FALL PROTECTION GUIDELINE July 2001 Table of Contents INTRODUCTION...3 CONTROL MEASURES...4 SURFACE PROTECTION...4 FIXED BARRIERS...5 EXAMPLES OF GUARDRAIL...6 WARNING BARRIERS...7 HANDRAILS...8 SURFACE
More informationConfined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).
Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This
More informationTesting and Inspection. eurosafesolutions.com
Testing and Inspection Eurosafe Solutions, Testing and Inspection Working at height requires reliable and effective fall protection systems to safeguard the people who work there, but also in order to
More informationWork at Height Procedure Rooftop, Climbing & Equipment
Work at Height Procedure Rooftop, Climbing & Equipment Purpose The information within this procedure demonstrates how Cornerstone Telecommunications Infrastructure Ltd (CTIL) fulfill statutory obligations.
More informationWalking-Working Surfaces
Walking-Working Surfaces 29 CFR 1910, Subpart D Presented by: Chesapeake Region Safety Council Rod Markley, CSP, CHST, CET Subpart D - Walking-Working Surface Topics we will cover: Background of rule Overview
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES