SHELL FLAGS INSPECTION CASE STUDY

Similar documents
UNPIGGABLE NO MORE! PRACTICAL SOLUTIONS FOR CHALLENGING PIPELINES

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

THE MISSING LINK - INSPECTING THE FINAL CRITICAL SECTION OF A LARGE CRUDE TRANSMISSION AND EXPORT SYSTEM

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

A NEW APPROACH TO BUCKLING DETECTION IN OFFSHORE PIPELINE LAYING

MULTI-DIAMETER, BI-DIRECTIONAL PIGGING FOR PIPELINE PRE-COMMISSIONING

Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime

INSPECTION OF MULTI-DIAMETER PIPELINES OPERATING AT LOW PRESSURE. Stefan Vages > ROSEN Group

Dynamic Simulation of the Norne Heidrun 10 x 16 Dewatering Pig

Pigging as a Flow Assurance Solution Avoiding Slug Catcher Overflow

OPERATING PROCEDURES

USE OF ISOLATION STOPPLES FOR VALVE REPLACEMENT ON TRANS ALASKA PIPELINE

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

Internal riser inspections on FPSO storage & production facilities

Tutorial. BOSfluids. Relief valve

HOW TO NOT MEASURE GAS - ORIFICE. Dee Hummel. Targa Resources

Best Practice RBI Technology Process by SVT-PP SIMTECH

Hazard Operability Analysis

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project

Paul Ladage 26 September 2017 MOVING THINGS AROUND - LATEST TRENDS IN HONEYWELL FLAGSHIP REGULATORS

The benefits of the extended diagnostics feature. Compact, well-proven, and flexible

Construction. MCP-01: Construction to Decommissioning

CHE Well Testing Package/Service:

Section 4: Sequence valve adjustments

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Mounting and Operating Instructions EB 3007 EN. Self-operated Pressure Regulators. Differential Pressure Regulators (opening) Type Type 42-25

Contents. 1. Non Destructive Testing Requirements. 2. Non Destructive Testing Methods Magnetic Particle Examination

BRINGING A NEW DIMENSION TO PIPELINE PIGGING. By: David Aitken, Aubin Group, UK

WELL SCAVENGER. Versatile wellbore clean-up tool for the most demanding operations

Decommissioning Ageing Infrastructure: Abandoning or Re-Routing Hydrocarbon Pipelines. Dave Vernon - Director of Isolation Services

Slug Catchers Engineered Solutions to Separation Problems

Performance Monitoring Examples Monitor, Analyze, Optimize

A Development of Mechanical Arm for Weight Scale Calibration

Design Enhancements on Dry Gas Seals for Screw Compressor Applications

Survey of Underwater NDT Technologies for Offshore Assets

HIPPS Development Project

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

Heat Pump Connections and Interior Piping

OFFICIAL 2016 A YEAR OF CHANGE IN THE REGULATION OF DECOMMISSIONING?

Emergency Pipeline Repair Isolation System

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

Centre of Excellence for Subsea Safety

GOLFER. The Golf Putting Robot

OPERATING INSTRUCTIONS Sherlock Chamber Testing System

Operations and Requirements A Practical Approach to Managing DP Operations

The Use of Ultrasonic Inspections at Elevated Temperature

Engineered solutions for complex pressure situations

Installation Operation Maintenance. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow IOM.

EMERGENCY PIPELINE REPAIR SYSTEMS DEVELOPED TO FACILITATE PIPELINE REPAIR OF UNPIGGABLE DEFECTS. By: Dale Millward, STATS Group, United Kingdom

Tentec. Instruction Document. Mini Air Driven Pump Unit Model: HTT.627X Series. Part Identifier

Veriforce TG CCT 661OP. Training Guide

PositionMaster EDP300 Extended Diagnostics. Compact, well-proven, and flexible

Air Diving Inspection of ABC Mock-Up Caisson Project 123

Retrievable Bridge Plugs

San Antonio Water System Standard Specifications for Construction ITEM NO. 841 HYDROSTATIC TESTING OPERATIONS

Technology. 38 JUL-SEPT 2010 Visit our websites at /

UNIQUE ADVANTAGES OF PIPENET

H&D Fitzgerald Pressure Pyknometry System Mark 5

AUTOMATIC HOSE TEST UNIT, TYPE SPU

KOMPRESSOREN COMPRESSORS KAESER AIR SERVICE Our Services An Overview

OLGA. The Dynamic Three Phase Flow Simulator. Input. Output. Mass transfer Momentum transfer Energy transfer. 9 Conservation equations

USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT

Spirax Compact FREME Flash Recovery Energy Management Equipment

TSS21 Sealed Thermostatic Steam Tracer Trap

Platelets & Plasma The Management of Unplanned Flow

Model: 720-UL INSTALLATION OPERATION MAINTENANCE. Bermad Pressure Reducing Valve IOM. Model: FP -720-UL Sizes: 2"-12" BERMAD. Application Engineering

VACGEN. Vacuum Components. Product Overview

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

Pulsed Eddy Current (PEC) Inspection through Insulation

Self-operated Pressure Regulators for special applications

COMPARING PLUG & SEAT REGULATORS & CONTROL VALVES. Lamar Jones. Equipment Controls Company 4555 South Berkeley Lake Road Norcross, GA 30071

GAS FUEL VALVE FORM AGV5 OM 8-03

TECHNICAL BENEFITS OF CJS / RAISE HSP. Technical Advantages

Risks Associated with Caissons on Ageing Offshore Facilities

SPE The paper gives a brief description and the experience gained with WRIPS applied to water injection wells. The main

Becker* Products Below Ground Ball Valve Regulators

Design Guide for Generac Industrial SI Generators

CHECK VALVES FOR CRYOGENIC SERVICE

OVERVIEW METCELL SPECIFICATIONS. Lab scale nanofiltration equipment The METcell Range

SV60 Safety valves. for use with steam, gas and liquids

Innovative Pressure Testing Equipment

Consider the design of a central chilled water cooling system for a clubhouse and

A Comparison of the UK Offshore Wind Resource from the Marine Data Exchange. P. Argyle, S. J. Watson CREST, Loughborough University, UK

RESIDENTIAL WATER DISTRIBUTION

LPG DRIVER ATTENDED TRANSPORT LOADING

Flexible Spools Solution at Hybrid Risers Base A. Karnikian, Total and S. Tarbadar, M. Bonnissel, S. Legeay, Technip France

DIAGNOSTICS SYSTEM OF JSC GAZPROM S GAS MAINS

Significant Change to Dairy Heat Treatment Equipment and Systems

Protecting People and the Environment during Stimulation Treatments in Offshore Settings

PRESSURE REDUCING STATION INSTALLATION, OPERATIONS & MAINTENANCE MANUAL

Mounting and Operating Instructions EB 3007 EN. Self-operated Pressure Regulators. Type Type Differential Pressure Regulators (opening)

BACK PRESSURE / SUSTAINING

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Service and Repair Manual

Installations & Equipment

Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant

SEALED-BLOK SELF RETRACTING LIFELINES. Field Proven Technology RSQ Feature Retrieval Capabilities EQUIPPED

BACK PRESSURE / SUSTAINING

TSC developed the practical use of magnetostrictive method for strain measurement and it is embodied in the StressProbe instrument.

Allspeeds Ltd. Royal Works, Atlas St Clayton le Moors Accrington Lancashire England BB5 5LW. Tel +44 (0)

Transcription:

SHELL FLAGS INSPECTION CASE STUDY J. Nonemaker, Solution Engineer, ROSEN T. Steinvoorte, Business Development, ROSEN R. Subramanian, Pipelines & Subsea Technical Support Engineer, Shell U.K. Limited Introduction In-line inspection of offshore pipelines is a challenging task for several reasons, including: Many pipelines that were not designed to be piggable, now require inspection Change in operating conditions resulting in ultra-low flows and pipelines with bore restrictions Presence of in-line components including non-return valves, hot tap tees, etc. Demand for reduced operational impact as a result of pigging operations Offshore pipelines distinguish themselves from onshore lines because external reference measurements and local repairs are often complex and challenging. Furthermore, inspecting offshore pipelines is often more demanding because of logistics, accessibility, and cost. Consequently, tool performance, first run success, risk mitigation and operational impact are key factors to be considered when selecting an inspection solution. Additionally, in order to successfully execute these inspections, expertise from both the operator and inspection contractor, need to be combined in a multidisciplinary team that operates as one team and establishes the confidence and trust in each other to make the correct decisions. This paper will discuss a recent example of such a challenge: the successful inspection of a key Shell U.K. Limited (Shell) pipeline in the North Sea, which required a bespoke solution to overcome the pigging challenges associated with this pipeline. The Challenge The Far North Liquids and Associated Gas System (FLAGS) is an offshore 36 x 450 km pipeline which runs from the Brent B platform to the St. Fergus gas terminal in Scotland. It was commissioned in 1983 and had been in-line inspected on two previous occasions. It was due for the next ILI inspection in 2026. However, due to the decommissioning of the Brent platforms, Shell required an in-line inspection whilst still having topsides launch capability and no subsea pigging operations. This resulted in a step change increase in risk, cost and complexity. The pipeline layout is shown in Figure 1. Figure 1: FLAGS pipeline layout (red dotted line) Copyright 2017 Pigging Products & Services Association

Although the FLAGS pipeline had been in-line inspected before, changes in operating conditions and the addition of a hot tap tee in the system made the inspection task a unique, industry-first challenge. The inspection solution had to overcome: Ultra-low flow of gas at inlet ~ 0.05 m/s Presence of a non-return clapper valve which could not be locked open. Clapper has a weight of 750 kg. High side flow where the gas enters the pipeline with a speed of approximately 15 m/s through the hot tap tee (HTT) High speed and heavy wall thickness downstream of the HTT The pipeline configuration can be found in Figure 2. Figure 2: Pipeline configuration The Solution ROSEN s overall approach to the inspection solution was to provide a ruggedized MFL tool that could perform in the low and high-flow pipeline sections, as well as traverse the check valve and hot tap tee side flow without any damage to any of the elements that would results in sub-optimal tool performance. The main risk associated with low-flow inspections is a stationary tool due to insufficient sealing capacity. Because of the low flow, a small amount of gas bypass over the tool could cause the tool to stop. The engineers therefore designed customized pulling units for the MFL tool and the cleaning/gauging pig that decreased gas bypass to an absolute minimum. The dual-body MFL tool design included protective frames and bumpers to allow the tool to push open the check valve and traverse without becoming damaged or getting caught by the valve clapper. The engineers developed a similar cleaning and gauging pig that would prevent the gauge plate from being damaged by the clapper. The magnetization of the MFL tool was increased to ensure full measurement specifications for the nominal pipe thickness at speeds of up to 3.5 m/s. Because of the challenging nature of the inspection, the tool designs had sufficient contingency. A safety factor of 8 was used to ensure the MFL tool could provide enough drive force to push open the check valve. The tools could perform to speeds as low as 0.01 m/s, lower than the expected minimum in the pipeline (0.05 m/s). Furthermore, the modules of the MFL tool and the cleaning/gauging pig were designed to ensure they would still be functional if the modules separated, i.e. resulting from a joint break at the HTT due to exposure to high side flow. The electronics were placed inside the MFL measurement module so that a joint break between the pull unit and measurement module would still allow the module to record data. For further contingency, in the unlikely event that a tool became lodged, a rescue pig was available on standby. 4-2

A comprehensive testing program was performed to confirm ROSEN s tool design: Differential pressure evaluation tests to determine the friction characteristics and confirm the sealing performance. Pump tests with a large side flow in the test loop simulating the high speed inflow at the hot tap tee (Figure 3). Pull tests through a mock check valve in order to determine the gauge/cleaning and MFL tools could open it without becoming damaged (Figure 4). Tensile test program on the newly developed ultra-strong flexible joint (Figure 5). It was expected that the side flow would cause a force of 60 KN (60 ton) on the joint. During the test it failed at 111 tons. High-speed pull tests as part of the final tool acceptance checks as well as to validate and calibrate the magnet setup. The initial risk assessment revealed a theoretical risk of a reversed flow resulting in the tool moving backwards in the pipeline. This situation would occur in case of a platform shutdown, after which gas would be removed from the pipeline to restart the platform. During the first MFL tool design, solid brushes on the MFL tool were included because they improve the tool s bi-directional capability. However, during testing, excessive wear was observed on these brushes, which forced the engineers to reconsider the design and adjust the inspection schedule. After an in-depth assessment of the issue, a change to lamella brushes was proven suitable and was selected for the final tool design. The risk of tools running backwards was mitigated by establishing operational procedures that prevented removing gas from the pipeline that would result in a reversed flow. Figure 3: Side-flow test setup Figure 4: MFL tool during check valve testing 4-3

Figure 5: Stiff joint tensile test The Field Work After all testing was completed the inspection team mobilized to the platform in November 2016 and launched the cleaning and gauging pig. It was received after 59 hours and 53 minutes. The pig brought out little debris from the pipeline and there was no significant damage to the gauge plate or the tool body. These results led to the conclusion that there were no major risks associated with launching the intelligent tool. The MFL tool was mobilized to site in January 2017 and launched. It arrived at the receiver 60 hours and 6 minutes after launch. Figure 6 shows the MFL tool velocity profile along the full pipeline. The tool was initially in the low-flow pipeline section, as indicated in Figure 7. For the first two kilometers, the tool had an average speed of ~0.1 m/s, but then the velocity rose sharply at the HTT. After passing the tee, the velocity steadily increased as the pressure along the pipeline decreased. Figure 6: Tool velocity across pipeline 4-4

Figure 7: Tool velocity in low-flow section To support the FLAGS activities, Shell built a Compas/USD model. The scope of the model included the main FLAGS pipeline and the Gjoa-Vega and Tampen Link pipelines, and all the associated export flows. The model schematic is shown in Figure 8. During the actual runs, the model was used in the PI connected mode to track the tools from launch at Brent B to receipt at St. Fergus. Filtered real-time PI data was brought into the model by means of a PI Read spreadsheet. Export flows and the pressure at St. Fergus were used directly as inputs at the model boundaries, and the export pressures and St. Fergus flows were plotted against model calculated values to monitor the model performance. Figure 8: Compas/USD model schematic Although it would have been possible to infer the progress of the pig(s) through the system from the flow and pressure conditions, the model provided this information in a simple format. A dashboard was developed to show the pig progress and the estimated arrival times at key points in the system (valve assembly spool piece, HTT, and St. Fergus). Another advantage of the model was the ability to manage unexpected deviations from the operating plans during the pigging runs. Although it was not required, the model could have been used to provide advice to the operations control center to recover from such an event in an efficient way. 4-5

The performance of the model was excellent and the predicted pig arrival times at St Fergus were very much in line with the run in the field (1 hour over prediction for the cleaning pig and 20 minutes under prediction for MFL tool). Result Thanks to the diligent efforts of the project team, the project was executed safely, with a first-time success, on budget, and with minimal impact to normal operations. The engineers were able to qualify the MFL tool for speeds as low as 0.01 m/s and that the chosen polyurethane setup is suitable for the pipeline conditions. Low wear on the discs was observed, meaning that the MFL tool could theoretically have been rerun without exchanging polyurethane. In addition, the engineers demonstrated that reliable testing programs can be developed for low-flow gas conditions and an array of mechanical and operational challenges. The Shell and Rosen personnel operated as one team to identify, embrace, and overcome inspection challenges in a systematic manner. This was achieved by applying success factors such as value driver identification, rigorous planning, onshore testing, risk identification and mitigation, and proactive stakeholder engagement. 4-6