CHAPTER 23 HAZARDS AND SAFETY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT

Size: px
Start display at page:

Download "CHAPTER 23 HAZARDS AND SAFETY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT"

Transcription

1 CHAPTER 23 HAZARDS AND SAFETY GULF ALUMINA LTD SKARDON RIVER BAUXITE PROJECT

2 TABLE OF CONTENTS 23.1 Introduction Scope Methodology Overview Risk Analysis Criteria Context Environmental Objectives and Performance Outcomes Environmental Objectives Environmental Outcomes Hazard Identification Site Workers Health and Safety Public Health and Safety Towns and Sensitive Receptors Land and Water Use Use of Marine Environment Air Quality Noise Transport Hazardous Substances Natural Hazards Climate Related Factors Wildlife and Disease Preliminary Hazard Identification Hazard Analysis and Risk Assessment Risk Evaluation - Transportation Risk Evaluation - Bulk Storage Risk Evaluation - Construction and Installation Risk Evaluation - Mining Operations Risk Evaluation - Waste Management Risk Evaluation - Infrastructure Risk Evaluation - Decommissioning Risk Evaluation - Interaction with External Factors Cumulative Risk Risk Management Risk Management Plan Construction Phase Operations Phase Risk Management - Natural Hazards Bushfire Vector-borne disease Wildlife Risk Management - Site Hazards Fire Vehicle, Marine Vessel and Aircraft Accidents Outline of Emergency Management Plan Objective Scope Existing Emergency Services and Medical Resources Page 23-i

3 Proposed Site Emergency Resources Identified Emergency Situations Emergency Response Emergency Plans Fire Management Strategies Fire Management Plan Equipment Operation Fixed Plant and Equipment Flammable Liquids Clearing Operations Welding Operations Fire-fighting Equipment and Protection Training External Resources Vehicle, Vessel or Aircraft Accident or Collision Snake Bite Sabotage Major Health Concerns Flood Spills, Leaks and Release of Contaminants Emergency Shutdown Procedures Evacuation Protocol Communications and Responsibilities Audit and Review Conclusion Tables Table 23-1 Risk Analysis Matrix (Consequence and Likelihood) Table 23-2 Hazard Identification - Site Workers Health and Safety Table 23-3 Indicative List of Hazardous Substances Table 23-4 Hazard Identification Table 23-5 Hazard Analysis for Transportation Table 23-6 Hazard Analysis for Bulk Storage Table 23-7 Hazard Analysis for Construction and Installation Table 23-8 Hazard Analysis for Mining Operations Table 23-9 Hazard Analysis for Waste Management Table Hazard Analysis for Infrastructure Table Hazard Analysis for Decommissioning Table Hazard Analysis for Interaction with External Factors Page 23-ii

4 23. HAZARDS AND SAFETY 23.1 Introduction This chapter describe the potential hazards and risks to people and property that may be associated with the Project in the form of a preliminary risk assessment. An outline of proposed emergency management planning procedures is provided. It should be recognised that the identification and control of hazards and risks to people and property is an integral part of planning for construction and operations and will occur independently of the EIS process Scope The potential hazards and risks to people and property that may be associated with the Project are identified and possible frequencies are predicted. This includes potential hazards, accidents, spillages and abnormal events that may occur during all stages of the Project; identifying all hazardous substances; potential wildlife hazards; potential natural hazards or events and implications related to climate change. A preliminary risk assessment was undertaken in accordance with AS/NZSS ISO 31000:2009 Risk Management Principles and Guidelines, taking into account: external and on site risks, including transport risks potential for mosquito breeding sites construction, operation and decommissioning phases of the project analysis of the identified hazards, examining individual and collective likelihood and consequences of each identified hazard involving injuries and fatalities to workers and to the public quantitative levels of risk. Details of risk control measures are presented. The scope of this chapter does not include assessment of environmental risks or economic risks associated with Project delays. Environmental risks and potential economic impacts are addressed in other sections of the EIS Methodology Overview Assessment of hazards and risk to people and property from Project activities was undertaken via a preliminary risk assessment in accordance with AS/NZS ISO 31000: Risk Management Principles and Guidelines and IEC/ISO Risk Management: Risk Assessment Techniques. The hazard and risk assessment also considers the potential impact on surrounding land use. The study applies to abnormal hazardous events and conditions, rather than conditions considered to be routine. Hazard identification takes into account compliance with regulatory requirements and therefore deliberately licensed release of pollutants such as air emissions and waste disposal is not included in the assessment. The assessment involved the following: Describe values including sensitive receptors. Page 23-1

5 Identify any potential hazards to people and property, documented in a hazard identification word diagram. Assess probability (likelihood) for hazardous events. Evaluate the risks associated with each hazard. Propose mitigation measures. Consider residual risk mitigation Risk Analysis Criteria ISO states that risk analysis consists of determining the causes and sources of risk, their consequences and likelihood taking into account the effectiveness and efficiency of controls. Criteria for likelihood and consequence are detailed in Chapter 1. The likelihood and consequence scales are combined to evaluate the overall level of risk, as outlined in Chapter 1, with the risk analysis matrix presented again in Table Table 23-1 Risk Analysis Matrix (Consequence and Likelihood) Consequence Type of Loss 1 (Insignificant) 2 (Minor) 3 (Moderate) 4 (Major) 5 (Severe) A (Almost Certain) The event has occurred frequently: occurs one or more times per year and is likely to re-occur within 1 year >90% chance Medium (M) High (H) H Extrme (E) E B (Likely) The event has occurred but is not frequent: occurs less than once per year and is likely to re-occur within 5 years 50-90% chance M M H H E Likelihood C (Possible) The event has happened in the business in the past 10 years or could happen within the next 10 years 30-50% chance Low (L) M H H H D (Unlikely) The event has happened in the business in the past 20 years or could happen within the next 20 years 10-30% chance L L M M H E (Rare) The event has never been known to occur in the business and it is highly unlikely that it will occur within less than the next 20 years <10% chance L L M M M Page 23-2

6 23.4 Context The factors influencing the assessment of risk, and the chapters in which they are described are: Project activities Chapter 5 Project location Chapter 4 sensitive receptors Chapter 11 land use within and surrounding the Project area Chapter 11 climate and extremes of climate Chapter Environmental Objectives and Performance Outcomes The environmental objectives and performance outcomes below are based on Schedule 5, Table 2 of the Environmental Protection Regulations 2008 (EP Regulation). The mitigation and management measures presented in this chapter are designed to achieve these environmental objectives and performance outcomes. The environmental management plan (EM Plan) presented in Appendix 13 provides a consolidated description of these mitigation and management measures Environmental Objectives Any waste generated, transported, or received as part of carrying out the activity is managed in a way that protects all environmental values. Identify potential hazards to people and property from abnormal hazardous events and conditions. Determine the residual risk levels (i.e. risks after proposed mitigations measures) and propose new risk treatment measures if risk are not tolerable Environmental Outcomes No contamination of land or waters from waste management beyond the footprint of waste management facilities. If land or groundwater contamination as a result of waste management activities has occurred, an investigation will be undertaken, with management or remediation as required. This may involve engaging a suitably qualified person approved by DEHP as a contaminated land specialist where required, and will fully depend on the nature and extent of contamination. Following risk treatment measures, there are no residual risks which are determined as high or extreme and all other risks are as low as reasonably practicable (ALARP). Prepare a Risk Management Plan and Emergency Management Plan Hazard Identification The focus of the hazard identification is on abnormal hazardous events and conditions, as specified in Hazardous Industry Planning Advisory Paper No. 3: Risk Assessment, NSW Department of Planning. Routine emissions and operations are identified in other technical reports prepared for the Project EIS and are addressed via pollution control mechanisms and legislation. Potential health and safety hazards that may affect s in normal on site day-to day activities during the construction and operation of the Project are listed in Table These hazards are well Page 23-3

7 addressed in workplace health and safety legislation and relevant Australian standards and are not included in the hazard identification process for this EIS. For each hazardous incident (e.g. fire, spill, leak, collision) the potential initiating events have been defined in order to represent the range of possible incidents as recommended in Hazardous Industry Planning Advisory Paper No. 6: Hazard Analysis, NSW Department of Planning. This enables a more accurate assessment of the conceivable scenarios that could lead to the hazard and therefore appropriate risk treatment measures can be recommended. Compliance with regulatory requirements is mandatory and therefore the hazard identification processes has assumed compliance with regulatory requirements and relevant Australian Guidelines and Codes applicable to the management and mitigation of hazards and risks at a Queensland mining operation such as the Project. Hazard identification and recommended risk treatment measures have been identified based on the premise that legislation and relevant, widely accepted, Australian Guidelines and Codes are implemented whilst undertaking the activity. These include: Work Health and Safety Act 2011 and Work Health and Safety Regulation 2011 aims to secure the health and safety of workers and workplaces. Workers and others are to be given the highest level of protection from hazards and risks as is reasonably practicable AS/NZS ISO 31000:2009 Risk Management Principles and Guidelines - provides a framework for managing risk and specifies the elements of the risk management process. AS 1940:2004. The Storage and Handling of Flammable and Combustible Liquids includes the requirements and recommendations for the safe storage handling of flammable liquids and dangerous goods Class 3 (as classified in the United Nations (UN) Recommendations for the Transport of Dangerous Goods). AS1940:2004 also includes requirements and recommendations for the storage and handling of combustible liquids and provides minimum acceptable safety requirements for storage facilities, operating procedures, emergency planning and fire protection. It provides technical guidance that may assist in the storage and handling of flammable and combustible liquids. ADG 7. Australian Goods Code - provides technical requirements for the land transport of dangerous goods across Australia. Queensland Health (2002). Guidelines to minimise mosquito and biting midge problems in development areas. As explosives are not proposed for use in the Project, legislation and codes relevant to explosives have not been considered Site Workers Health and Safety Table 23-2 details the health and safety hazards that are likely to be present in normal on-site day-to-day activities during construction and operation of the Project. These hazards are well addressed in workplace health and safety legislation and relevant standards and will be complied with at all times during the construction, operation and decommissioning of the Project. Table 23-2 Hazard Identification - Site Workers Health and Safety Hazard Description Consequence Risk Treatment Measures Manual Handling Incorrect handling Injury likely to recover from Use approved safe work method, training and competency assessment, provide equipment fit for purpose and suitable allocation of resources. Page 23-4

8 Hazard Description Consequence Risk Treatment Measures Slips and trips Water, oil on ground Interaction with mobile equipment Working heights at Working with electrical equipment Equipment with moving parts Falling objects Worker hit by mobile equipment Injury likely to recover from Use approved safe work method, training and competency assessment. Injury / fatality Training, competency assessment, systems of authorisations, inspections, signage, traffic management plan, no go zones, dedicated pedestrian walkways. Fall Injury / fatality Training, competency, appropriate scaffolding and/or PPE, inspections, safe work methods. Electric shock / Electrocution Failure to isolate correctly Object falls from height Fatigue Operating plant and equipment whilst tired Injury / fatality Qualified electricians, training, competency, approved safe work methods, equipment maintenance, testing and tagging procedures, inspections, separate / barricade work areas, isolation permit system. Injury / fatality Isolation procedures, tag protection system, maintenance of guarding, inspections, training, competency. Injury PPE, barricading, approved safe work methods. Injury / fatality Fit for work program, fatigue management plan, traffic plan. Confined space Suffocation Fatality Confined space permits, training, competency, approved safe work method statement, equipment serviced regularly. Pinch points Crush Fatality Safe work methods, training, competency, guarding, barricading, signage Lightning Struck by lightning Fatality Storm procedures, approved safe work methods, lightning masts. Wildlife hazards Snake bites Fatality PPE e.g. long trousers, high sided safety boots, first aid training, emergency management plan. Disease vectors Mosquito bites Illness PPE e.g. long trousers, long shirts, insect repellent where required. Water bodies, including dams, managed to avoid stagnation hence minimizing potential for mosquito breeding sites. Dust Clearing, excavation, unsealed roads Respiratory issues Watering roads, dust suppression, PPE. Page 23-5

9 Hazard Description Consequence Risk Treatment Measures Noise Excessive noise from plant and equipment Sun burn Working in sun without protection Dehydration /Heat Stress Welding cutting Exposure hazardous substances Fire and to Working in hot conditions without sufficient water Fumes, hot metal, sparks Oils, chemicals Buildings, vehicles, conveyors diesel, Hearing loss Skin damage, no treatment PPE, noise barriers, equipment location. PPE, provision of sunscreen. Hospitalisation PPE, safe work method statement, provide water, training. Poisoning, skin burn, foreign object in eye PPE, safe work method statement, qualifications. Skin, eye irritation PPE, training, MSDS, standards and procedures for transporting, handling, using and disposing of hazardous substances. Smoke inhalation Emergency exits, training, Emergency Management Plan, fire extinguishers, fire alarms Public Health and Safety This section describes the potential health and safety impacts for the public and community associated with the Project. References are provided to other sections of the EIS where these potential health and safety impacts are described in more detail Towns and Sensitive Receptors The nearest population centre to the Project is Mapoon, approximately 15 km south of the most southerly mining lease boundary. The nearest sensitive receptors to the Project live in areas near Mapoon, with the closest receptor approximately 11 km south of the most southerly mining lease boundary Land and Water Use The existing land use within and adjacent to the Project area is described in Chapter 11. There are no permanent residences on or adjacent to the Project area and no regular use of the land. There are no known ongoing uses by the public of fresh surface water or groundwater within or downstream of the Project area. Water management and potential impacts to water are described in Chapter 6, Chapter 12 and Chapter 13. Potential flooding of the site is described in Chapter 14. As there is limited use of waters downstream of the Project and the potential for release of contaminants due to flooding is low, it is very unlikely that any flooding will create additional health and safety impacts arising from the Project activities. Water used by the Project is not predicted to impact on available volumes or quality of water used by people in Mapoon. Page 23-6

10 Use of Marine Environment Skardon River Bauxite Project Use of the estuarine and marine environment in the Skardon River is described in Chapter 22. There is limited use of the Skardon River for recreational and commercial fishing purposes. There are no permanent users of water downstream of the Project, comprising estuarine and marine areas of the Skardon River and Namaleta Creek Air Quality Potential Project and cumulative impacts on air quality are described in Chapter 19. The Project, either in isolation or cumulatively with the nearby Bauxite Hills Project, is not predicted to result in exceedances of air quality objectives in Mapoon. These objectives are designed to protect the health and wellbeing of receptors. Due to the separation distance between the Project and sensitive receptors, it is very unlikely that any odours generated by the Project will affect the health and safety of the community Noise Potential Project and cumulative impacts on noise levels are described in Chapter 20. The Project, either in isolation or cumulatively with the nearby Bauxite Hills Project, is not predicted to result in exceedances of noise and vibration objectives in Mapoon. These objectives are designed to protect the health and wellbeing of receptors Transport Transport of people, equipment and materials to the Project is described in Chapter 22. As described in Chapter 22, road access to the Project for mining is not practical. The potential hazards and risks to the public associated with road, air and marine transport are described below. The beach at the Skardon River mouth is currently accessed by tourists in the dry season using bush tracks that intersect the existing haul road (currently no mining occurs and hence no mining vehicles use the haul road). At any one time approximately 10 vehicles may access the beach area. This is the only practical means of accessing the beach to the west of the mining leases. To allow ongoing use of the land parcel (Lot 11 SP204113), including the beach, Gulf will allow access to the mining lease for crossing of the haul road only. There will be no authorised use of the haul road by tourists. The crossing point will be signed and demarcated with access procedures requiring strict compliance. Management measures have been proposed to reduce transport risks to low or medium Hazardous Substances The Project will use a number of hazardous substances during construction and operations. Table 23-3 provides an indicative list of hazardous substances to be used during the Project and the likely quantities stored on site. Material Safety Data Sheets (MSDS) will be available on site where these substances are to be stored or used. Page 23-7

11 Table 23-3 Indicative List of Hazardous Substances Chemical name Storage location Highest likely total storage quantity Diesel Fuel storage facility comprising interconnected self-bunded bulk diesel storage tanks. Oils Transmission oil Hydraulic oil Diesel Engine oil Final drive oil Waste oil Lubricants coolants Engine coolant Gear oil and Other lubricants Workshop in the infrastructure area Workshop in the infrastructure area Rate usage of Comments 2.2 ML 10 MLpa Diesel will be reticulated to a bunded vehicle refuelling area. The fuel facility is located at a safe operating distance from other infrastructure and facilities. There will be no in-field fuel storage. Fuel trucks may also transfer from the fuel storage tanks to mine vehicles. < 10,000L <250,000 Lpa < 1,000L <25,000 Lpa Petrol MIA Minor Minor Paint MIA Minor Minor Solvents MIA Minor Minor Thinners MIA Minor Minor Self bunded lube and oil storage tanks. Oily water separator for accidental release or contaminated runoff. Self bunded lube and oil storage tanks. Oily water separator for accidental release or contaminated runoff Natural Hazards Climate Related Factors Risks associated with extremes of climate are described in Chapter 9, including temperature extremes, droughts, tropical cyclones, storm surges, erosion prone areas and bushfire risk. The potential for flooding of the Project area for various annual exceedance probability (AEP) rainfall events, is described in Chapter 14. The potential impacts of climate change on the Project area are temperature increases and either declining or increasing rainfall depending on the climate model. It is possible that the frequency and intensity of storms and cyclones may increase in the area of the Project, although these are expected to be within the natural variation of extremes of climate. Page 23-8

12 Wildlife and Disease Skardon River Bauxite Project There are a number of wildlife species that are potentially dangerous to humans in the Project area, including mammals, dingoes, rats, pigs and various snakes. Increasing potential freshwater breeding sites such as receding flood waters and pooling water can result in larger numbers of mosquitoes, which in turn increases the potential for outbreaks of mosquito-borne diseases (Queensland Health 2011). Notifiable diseases reported in Queensland include barmah forest virus, ross river virus, dengue fever and malaria Preliminary Hazard Identification Hazard identification, cause, potential consequences and risk treatment measures are described in Table The hazard identification process identifies the non-routine hazards associated with the construction, operation and decommissioning (abbreviated as C,O,D) of the mine and associated infrastructure taking into account the Project description, natural hazards and estimated hazardous substances being stored and used on site. Transport risks and interaction with external projects are also identified. Potential health and safety hazards to the s for routine operations are not included as these have been previously identified and can be addressed by compliance with relevant standards and regulations. Page 23-9

13 cyclones). Onsite traffic management procedures including speed, fatigue, alcohol and drugs. Page Table 23-4 Hazard Identification Activity / (Phase) Phase (C,O,D) Transport Transporting C,O,D Aircraft accident Pilot error personnel, Aircraft failure equipment and Natural event materials to and from the site and within site Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures Injury to public / Fatality to public / All aircraft movements to comply with regulatory requirements for pilot training, flying duration and equipment standards and maintenance (refer Chapter 22). Flights avoided at times of high risk natural events (e.g. cyclones). C,O,D Supply vessel accident Human error Vessel failure Natural event Injury to public / Fatality to public / All shipping to comply with maritime safety legislation and controls (refer Chapter 22). Vessel movements avoided at times of high risk natural events (e.g. C,O,D Vehicle accident (onsite only) Driver error Fatigue Vehicle collision Injury to Fatality to Project will not be accessed by public roads. The only vehicle movements are on the mining lease. C,O,D Spill, leak of liquid or fumes Supply vessel accident Incorrect loading Tank failure Collision Fire Health impacts from contamination (marine environment, soil, water) Secure loading of materials, procedures, training, spill management, Emergency Management Plan. All shipping to comply with maritime pollution control legislation.

14 Page Activity / (Phase) Phase (C,O,D) Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures C,O,D Excessive dust High winds Vehicle accident / collision Speed limits, paving, watering Unsealed roads roads, wind breaks. Transport of fuel to and within site C,O,D Fire Spill, leak Fuel transfer failure Driver error Vehicle collision Failure of equipment Failure to comply with procedures Injury / fatality Injury / fatality public Health impacts from contamination (marine environment, soil, water, groundwater) Fuel transfer procedures from supply vessel to tank and from tank to barges. Design of fuel transfer equipment safety shut-off valves, steel pipes, catch trays, bunded areas at coupling points. Speed limits, traffic management plan, transport in accordance with relevant standards, training, Emergency Management Plan. Bulk Storage Storage of fuel C,O,D Spill, leak Failure of equipment Failure to comply with procedures Health impacts from contamination (soil, water, groundwater) Fuel storage designed and operated in accordance with AS1940. Bunds, signage, spill procedures, emergency response planning, training, inspection and C,O,D Fire, explosion Ignition source or fire Failure of equipment Failure to comply with procedures Construction and Installation Clearing and C Excessive dust High winds earthworks Unsealed roads Injury to public / Fatality to public / maintenance program. Fuel storage designed and operated in accordance with AS1940. Signage, emergency response planning, training, inspection and maintenance program. Vehicle accident / collision Speed limits, paving, watering roads, wind breaks. C Landslide Heavy rainfall Erosion and sediment control plan including management of water runoff and progressive stabilisation.

15 Road design, signage, speed limits, vehicle maintenance, roll over bars, fitness for work, training, traffic management. Dust control measures and monitoring. Page Activity / (Phase) Phase (C,O,D) Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures C Wildlife (e.g. Disturbance / Injury to snakes) clearance of habitat Injury to public Fatality to / public Construction and C Fire Works such as Injury to installation of welding, grinding in Injury to public infrastructure combination with high winds C Excessive dust High winds Vehicle accident / collision Speed limits, paving, watering Unsealed roads roads, wind breaks. Mining Operations Topsoil and subsoil stripping, transfer and storage C Erosion Heavy rainfall Failure to comply with erosion and sediment control plan Erosion and sediment control plan including management of water runoff and progressive stabilisation. O including management of water runoff and progressive stabilisation. Excessive dust High winds Vehicle accident / collision Speed limits, paving, watering Unsealed roads roads, wind breaks. O Landslide Heavy rainfall Erosion and sediment control plan O Wildlife (e.g. snakes) Disturbance Clearance of habitat Injury to Injury to public Awareness of site personnel regarding hazards, Emergency Response Plan. Hauling Bauxite O Vehicle accident Driver error Vehicle collision Vehicle roll over O Dust High winds Unsealed roads Injury to Fatality to Vehicle accident/collision

16 Page Activity / (Phase) Phase (C,O,D) Bauxite crushing and O Dust High winds stockpiling Failure to comply Bauxite conveying, barging and transhipment Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures with procedures O Fire Ignition source or fire Public amenity Injury to public / Fatality to public / Dust control measures, monitoring. Fire breaks maintained around the infrastructure area including the conveyor, control of ignition sources via procedures and training, Emergency Management Plan, O Dust High winds Failure to comply with procedures O Spill of bauxite Vessel accident Vessel loading procedures Public health Injury to public / Fatality to public / Health impacts from contamination (bauxite is not considered to be toxic) training, exclusion of public. Dust control measures, cover conveyor, spill trays, monitoring. Maritime vessel safety controls (refer Chapter 22). Design of conveyor and loading systems to minimise risk of spills. Transhipment only when wave and wind conditions within designed operating parameters. Operations cease during high risk natural events (e.g. cyclones). Waste Management Waste management storage, transfer and disposal C,O Vermin Failure to comply with procedures Uncontrolled release Failure to comply with procedures Health impacts Appropriate design and distance from ML boundary, procedures, training, inspection and maintenance. Health impacts from contamination (soil, water, groundwater) Refer waste management chapter (Chapter 8) for management measures.

17 waters. Skardon River Bauxite Project extreme rainfall events. All contaminated land will be remediated prior to mine closure and surrender of land (e.g. soil quality investigation and remediation will be undertaken in accordance with EHP Guidelines for Contaminated Land). Security management plan, fencing. Page Activity / (Phase) Phase (C,O,D) Infrastructure Bauxite O Fire, release of Infrastructure area contaminants operations Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures Failure to comply with procedures Design failure Health impacts from contamination Injury to Fatality to Designed in accordance with Relevant standards. Operational procedures implemented. Fire Management Plan. Emergency Management Plan. Bunded areas with hydrocarbons. Situate above potential flood Water management infrastructure Accommodation camp C,O Release of contaminants Failure natural causes or design C,O Fire Failure to comply with procedures Design failure Health impacts from contamination Injury to Fatality to Appropriate design, inspection and maintenance, including after Designed in accordance with Relevant standards. Operational procedures implemented. Fire Management Plan. Emergency Management Plan. Decommissioning Remediation of contaminated land D Release (leaching) Failure to comply with remediation plan Health impacts from contamination (soil, water, groundwater) External Factors External factors C,O,D Sabotage or protest Security breach Injury to public /

18 Page Activity / (Phase) Phase (C,O,D) Hazard Cause / Initiating Event Potential Consequences Risk Treatment Measures C,O,D Disease Epidemic Illness to public / outbreak Fatality to public / Interaction with tourists on the land Interaction with recreational and commercial boats in the Skardon River Interaction with Metro Mining Ltd s Bauxite Hills Project haul roads Interaction with Metro Mining Ltd s Bauxite Hills Project barges Interaction with feral animals, wildlife C,O,D Unauthorised use of Port area and mining lease roads by tourists C,O,D Multiple vessels in Skardon River O Potential for Metro Mining s and Gulf s haul roads to intersect O Metro Mining s and Gulf s barges operating in same navigation channel C,O,D Feral animals, wildlife Vehicle accident Injury to public / Fatality to public / Vessel strike Injury to public / Fatality to public / Vehicle accident Injury to public / Fatality to public / Vessel strike Injury to public / Fatality to public / Vehicle accident Vessel strike Injury to public / Fatality to public / Designated crossing point for haul road with signage. Entry to hail road prohibited except for crossing point. Site access procedures, fencing, gates, security and signage. Maritime vessel safety controls (refer Chapter 22). Traffic control measures. Traffic management plan. Liaison with Metro Mining. Maritime vessel safety controls (refer Chapter 22). Fencing. Equipment barricaded. Maritime operations planning.

19 23.12 Hazard Analysis and Risk Assessment This section outlines the risk analysis undertaken in accordance with the method described in Section 23.3 and using the hazard identification table in Section The risk analysis takes into account the risk treatment measures included in the hazard identification table on the basis that it is expected that all legal requirements, relevant standards, guidelines and codes of practice will be implemented in the design, construction, operation and decommissioning of the Project. The objective of the risk analysis is to determine whether the residual risks (i.e. risks after proposed mitigations measures) are tolerable and if they are not then to propose new risk treatment measures. Where the residual risk is determined as high or extreme, these activities are considered for additional risk mitigation. Tables are prepared for the following hazards and associated risks: Transportation (Table 23-5) Bulk storage (Table 23-6) Construction and Installation (Table 23-7) Mining Operations (Table 23-8) Waste Management (Table 23-9) Infrastructure (Table 23-10) Decommissioning (Table 23-11) Interaction with External Factors (Table 23-12) Risk Evaluation - Transportation The risk levels to people and property associated with the transportation activities are summarised in Table Medium risks were associated with transporting personnel, equipment and materials to and from the site. Although the consequence of transport risks can be severe (e.g. mutiple fatalities), with the appropriate risk treatment measures, the likelihood is rare or unlikely and risk level has been assessed as medium. No high or extreme risks were identified. Table 23-5 Hazard Analysis for Transportation Activity Phase Hazard Potential consequences Transporting personnel, equipment and materials to and from the site and within site C, O, D C, O, D C, O, D Aircraft accident Supply vessel accident Vehicle accident (onsite only) Consequence Likelihood Risk level Injury to public / 3 E Medium Fatality to public 5 E Medium / Property damage 4 E Medium Injury to public / 3 D Medium Fatality to public 5 E Medium / Property damage 4 D Medium Injury to site worker Fatality to site worker 3 D Medium 5 E Medium Page 23-16

20 Activity Phase Hazard Potential consequences Transport of fuel to and within site C, O, D C, O, D O Spill, leak of liquid or fumes Excessive dust Fire Spill, leak Skardon River Bauxite Project Consequence Likelihood Risk level Property damage 3 D Medium Property damage 2 C Medium Fire 2 D Low Health impacts from contamination Vehicle accident / collision Injury to public / 1 C Low 3 D Medium 3 D Medium Fatality public / 5 E Medium Health impacts 2 D Low from contamination Property damage 3 D Medium Risk Evaluation - Bulk Storage The risk levels to people and property associated with the bulk storage activities are summarised in Table Medium risks were associated with storing fuel. It should be noted that the risk ratings are determined as medium when there is a possibility of the consequence resulting in a severe injury or fatality, even though the likelihood of the event is unlikely or rare (rating of D or E). No high or extreme risks were identified. Table 23-6 Hazard Analysis for Bulk Storage Activity Phase Spill, leak Potential consequences Storage of fuel C,O, D C,O, D Consequence Likelihood Risk level Spill, leak Property damage 2 C Medium Fire, explosion Health impacts from contamination Injury to public / site worker 2 D Low 3 D Medium Fatality public / site worker Health impacts from contamination 5 E Medium 2 D Low Page 23-17

21 Risk Evaluation - Construction and Installation Skardon River Bauxite Project The risk levels to people and property associated with the construction and installation activities are summarised in Table No high or extreme risks were identified. Table 23-7 Hazard Analysis for Construction and Installation Activity Phase Spill, leak Potential consequences Clearing and earthworks C Excessive dust Vehicle accident / collision C Landslide Property damage Consequence Likelihood Risk Level 3 D Medium 2 D Low O Wildlife (e.g. snakes) Injury to site worker / public Fatality site worker / public 3 D Medium 5 E Medium Construction and installation of infrastructure C Fire Injury to site 3 D Medium worker Injury to public 3 E Medium Excessive dust Erosion Property damage Vehicle accident / collision Property damage 3 D Medium 3 D Medium 2 E Low Risk Evaluation - Mining Operations The risk levels to people and property associated with mining operations are summarised in Table There were no high or extreme risks identfied. Some risks were rated as medium as there was the possibility of the consequence resulting in a severe injury or fatality. It should be noted that in all cases, the likelihood was assessed as unlikely or rare (D or E). Table 23-8 Hazard Analysis for Mining Operations Activity Phase Hazard Potential consequences Topsoil and subsoil stripping and storage O Excessive dust Vehicle accident / collision Consequence Likelihood Risk level 3 D Medium Landslide Property damage 2 D Low Wildlife (e.g. snakes) Injury to site worker / public Fatality site worker / public 3 D Medium 5 E Medium Page 23-18

22 Activity Phase Hazard Potential consequences Hauling bauxite O Vehicle accident Bauxite crushing and stockpiling Bauxite conveying, barging and transhipment O Fire Excessive dust Injury to site worker Fatality to site worker Skardon River Bauxite Project Consequence Likelihood Risk level 3 D Medium 5 E Medium Property damage 2 C Medium Vehicle accident / collision O Dust Property damage / public amenity O Excessive dust O Fire Injury to public / O Spill of bauxite 3 D Medium Property damage 2 C Medium 1 D Low Property damage 1 D Low Public amenity 1 D Low Fatality to public / 3 E Medium 5 E Medium Property damage 2 C Medium Injury to public / Fatality to public / 3 E Medium 5 E Medium Property damage 2 C Medium Health impacts from contamination 1 E Low Risk Evaluation - Waste Management The risk levels to people and property associated with waste management activities are summarised in Table Waste management is described in Chapter 8. With the implementation of proposed wasste management measures, risks associated with waste management are low or medium. Table 23-9 Hazard Analysis for Waste Management Activity Phase Hazard Potential consequences Consequence Likelihood Risk level C,O Vermin Health impacts 1 E Low Page 23-19

23 Activity Phase Hazard Potential consequences Waste management storage, transfer and disposal Uncontrolled release Health impacts from contamination (soil, water, groundwater) Consequence Likelihood Risk level 2 C Medium Risk Evaluation - Infrastructure The risk levels to people and property associated with the bauxite infrastructure activities, including management of water runoff from the bauxite infrastructure area, and the accommodation camp are summarised in Table No high or extreme risks were identified. Table Hazard Analysis for Infrastructure Activity Phase Hazard Potential consequences Bauxite infrastructure area operations Water management infrastructure Accommodation camp O Fire and / or release of contaminants C,O Release of contaminants Injury to public / Fatality to public / Consequence Likelihood Risk level 3 E Medium 5 E Medium Property damage 2 C Medium Health impacts from contamination 2 D Low Property damage 2 D Low Health impacts from contamination C,O Fire Injury to site worker Fatality to site worker 2 D Low 3 E Medium 5 E Medium Property damage 2 C Medium Risk Evaluation - Decommissioning The risk levels to people and property associated with decommissioning activities are summarised in Table Page 23-20

24 Table Hazard Analysis for Decommissioning Activity Phase Hazard Potential consequences Remediation contaminated land of D Release (leaching) Health impacts from contamination (soil, water, groundwater) Consequence Likelihood Risk level 2 D Low Risk Evaluation - Interaction with External Factors The risk levels to people and property associated with external factors are summarised in Table No high or extreme risks were identfied. Table Hazard Analysis for Interaction with External Factors Activity Phase Hazard Potential consequences External factors C,O,D Sabotage Interaction with tourists on the land Interaction with recreational and commercial boats in the Skardon River Interaction with Metro Mining Ltd s Bauxite Hills Project haul roads C,O,D C,O,D C,O,D O Protest Disease outbreak Vehicle accident Multiple vessels in Skardon River Potential for Metro Mining s and Gulf s haul roads to intersect Injury to public / Consequence Likelihood Risk level 3 E Medium Property damage 3 E Medium Illness to public / Fatality to public / Injury to public / Fatality to public / 3 E Medium 5 E Medium 3 D Medium 5 E Medium Property damage 2 D Low Injury to public / Fatality to public / 3 D Medium 5 E Medium Property damage 3 D Medium Injury to public / Fatality to public / 3 D Medium 5 E Medium Property damage 3 D Medium Interaction with Metro Mining Ltd s O Metro Mining s Injury to public / 3 D Medium Page 23-21

25 Activity Phase Hazard Potential consequences Bauxite Hills Project barges Interaction feral animals, wildlife C,O,D and Gulf s barges operating in same navigation channel Cattle, livestock, wildlife Fatality to public / Skardon River Bauxite Project Consequence Likelihood Risk level 5 E Medium Property damage 3 D Medium Injury to public / Fatality to public / 3 D Medium 5 E Medium Property damage 1 D Low Cumulative Risk Potential interactions with other projects in the region (Metro Mining s Bauxite Hills Project) were identified in Table with associated hazards and risks identified. It is unlikely that there is an increased risk on the hazards identified in Table 23-4 as a result of the Bauxite Hills Project. It is unlikely that the hazards and risks associated with the Project will present additional / increased hazards and risks to other existing or proposed facilities in the vicinity of the Project area Risk Management Risk Management Plan A risk management plan will be developed prior to construction and operations. The purpose of the risk management plan will be to provide a framework for the implementation of the risk treatment and reduction measures proposed in this chapter. It is reiterated that the preliminary risk assessment in this chapter did not consider environmental impacts as they are assessed in other sections of the EIS. Routine operational health and safety risks have been identified and are to be managed in accordance with legislation, standards and codes of practice. The risk assessment process will be undertaken in detail prior to construction and operation and be maintained as operations and conditions may change. In line with standard industry practice, job safety and environmental analyses should take place prior to the commencement of any activity Construction Phase A Construction Environment, Health and Safety plan will be prepared upon completion of the design stage. The Construction EHS plan will focus on hazards related to both site operations and potential off site impacts. HIPAP7: Construction Safety Guidelines (NSW DoP, 2011) recommends the construction study covers the following: Familiarisation with past and proposed operations and a review of construction and commissioning programs Review of construction safety including identification and analysis of hazards and review / revision of construction operational controls Safety assurance including verification that the design intent is maintained throughout the construction period via safety management systems and pre-commissioning checks Page 23-22

26 Change management procedures during construction Operations Phase The proponent will structure health, safety and environmental management systems in accordance with OHSAS 18001: Occupational Health and Safety Management Systems. Requirements and the principles of ISO14001:2004 Environmental Management Systems Requirements with Guidance for Use. Risk management principles in line with ISO 31000:2009. Risk Management Principles and Guidelines will be used to identify hazards, assess risks and identify control at all stages throughout the Project. The outcome of the risk management process will be the development of operational control such as health and safety plans, safe work procedures, job safety analyses, inspections, monitoring and audits. Risks will be managed in accordance with the hierarchy of control, with elimination being the first control method to be used. Hazards and risk will be identified during the Project risk assessment process and documented in a risk register that will be regularly updated. The risk register will be reviewed at any time prior to the introduction of new plant or equipment; change in operations, conditions or plant; after an incident; and at least annually. Should any risks be identified as high or extreme, additional treatment measures will be assessed and implemented as required to ensure that risks are made as low as reasonably practicable (ALARP). Safe work procedures will be developed for routine tasks to address the following hazards: driving vessel loading and unloading manual handling slips and trips interaction with mobile equipment working at heights working with electrical equipment, lightning working with moving parts falling objects fatigue confined spaces pinch points wildlife hazards disease vectors dust noise sunburn, dehydration, heat stress welding and cutting hazardous substances fire. Audits will be conducted on a scheduled and regular basis, dependent on the risk of the activity. Page 23-23

27 Risk Management - Natural Hazards Bushfire A bushfire management plan will be developed to take into account the following: Traditional Owner / landowner bushfire management Maintain safety of people and property by avoiding areas of high or medium bushfire hazard. Design and siting of buildings. Firebreaks, setbacks from vegetation and access to firefighting and emergency vehicles. Adequate road access for firefighting and other emergency vehicles. Providing an adequate and accessible water supply for fire-fighting purposes. Ensure public safety and environment are not adversely affected by the detrimental impacts of bushfire on hazardous materials manufactured or stored in bulk. These items will be addressed in the detailed design of the site and the Emergency Response Plan Vector-borne disease The preliminary hazard and risk assessment identified the potential for the spread of mosquito borne disease as medium. A mosquito management plan will be developed prior to construction and operations. As specified in the Queensland Health (2002) Guidelines to minimise mosquito and biting midge problems in new development areas, the most appropriate way to control mosquitoes is to prevent them from breeding. It is important to address potential mosquito problems before there is a significant increase in the adult population. Where required, mosquito control programs should integrate a variety of control strategies i.e. surveillance, reducing stagnant water and spraying. Any incidence of vector-borne disease will be referred to a doctor, with subsequent notification to Queensland Health. Additional treatment measures may be required if the incidence of disease increases beyond background levels in the general community. It is expected that Queensland Health will provide adequate monitoring of incidence of the known vector-borne diseases and will implement appropriate programs to control any outbreaks. It is unlikely that a significant increase in the incidence of vector-borne disease will occur Wildlife A procedure will be developed prior to clearing to ensure worker safety. This will take into account prevention of snake bites, as well as first aid and medical treatment. Training and awareness will also be considered. Suitable site personnel will be trained in first aid. Procedures will be in place to ensure effective transportation to the nearest medical facility, as required. Further detail will be included in the Emergency Management Plan Risk Management - Site Hazards Fire An on-site fire response capability will be maintained and supported as will be detailed in the Emergency Response Plan. Proposed control measures include: Preventive measures relating to control of ignition sources Page 23-24

Bogo Operations Pollution Incident Response Management Plan

Bogo Operations Pollution Incident Response Management Plan Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au

More information

METHODOLOGY RISK TABLES TABLE 1 - QUALITATIVE MEASURES OF CONSEQUENCE OR IMPACT TABLE 2 - QUALITATIVE MEASURES OF LIKELIHOOD

METHODOLOGY RISK TABLES TABLE 1 - QUALITATIVE MEASURES OF CONSEQUENCE OR IMPACT TABLE 2 - QUALITATIVE MEASURES OF LIKELIHOOD METHODOLOGY This Assessment has been performed as outlined in Australian Standard AS/NZS ISO 31000:2009 with reference to tables 1, 2 and 3 below, for the use of leased land for the purposes of performing

More information

Procedure: Work health and safety hazard management

Procedure: Work health and safety hazard management Procedure: Work health and safety hazard management Purpose This procedure describes how the Australian National University (ANU) manages Work Health Safety hazards for the health, safety, rehabilitation

More information

2.0 Management Systems and Documentation

2.0 Management Systems and Documentation SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This

More information

Faculty/School: Pharmacy Initial Issue Date: Oct 2016

Faculty/School: Pharmacy Initial Issue Date: Oct 2016 Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions

More information

CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

Release: 1. UEPOPL002A Licence to operate a reciprocating steam engine

Release: 1. UEPOPL002A Licence to operate a reciprocating steam engine Release: 1 UEPOPL002A Licence to operate a reciprocating steam engine UEPOPL002A Licence to operate a reciprocating steam engine Modification History Not applicable. Unit Descriptor Unit Descriptor 1)

More information

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT

More information

How severely could the risk hurt someone?

How severely could the risk hurt someone? Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK ConstructSafe Project Team March 2018 Version 1.3 1 Table of Contents 1. Introduction... 3 2. Candidate minimum required knowledge... 3

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)

More information

To comply with the OHS Act, the responsible manager must carry out and document the following:

To comply with the OHS Act, the responsible manager must carry out and document the following: Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act

More information

IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL

IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL CONTENTS 1. INTENT... 3 2. APPLICATION... 3 3. UNDERGROUND VENTILATION... 3 3.2 Underground Ventilation Officer... 3 3.3 Risk

More information

WORK METHOD STATEMENT STRUCTURAL STEEL

WORK METHOD STATEMENT STRUCTURAL STEEL ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Issue date: July 2013 Page 1 of 9 Contents 1. PREVENTATIVE MECHANISMS: 1(a) Hazards to health and the environment Page 3 1(b) Pollutant Inventory Page 4 1(c)

More information

Safe Work Method Statement

Safe Work Method Statement Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees

More information

SAFE WORK METHOD STATEMENT SWMS No Version

SAFE WORK METHOD STATEMENT SWMS No Version SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison

More information

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All

More information

Marine Education Society of Australasia HAZARD MANAGEMENT POLICY

Marine Education Society of Australasia HAZARD MANAGEMENT POLICY Marine Education Society of Australasia HAZARD MANAGEMENT POLICY Purpose of guidelines Commitment to workplace health and safety Scope Legal Framework MESA is committed to ensuring safe and healthy working

More information

Section J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS

Section J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives

More information

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of

More information

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS

More information

SPILL CONTINGENCY AND EMERGENCY RESPONSE PLAN

SPILL CONTINGENCY AND EMERGENCY RESPONSE PLAN SPILL CONTINGENCY AND EMERGENCY RESPONSE PLAN All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, without the written

More information

HAZARDOUS SUBSTANCES / DANGEROUS GOODS

HAZARDOUS SUBSTANCES / DANGEROUS GOODS HAZARDOUS SUBSTANCES / DANGEROUS GOODS Golden Brown is committed to continuously improving the management and standards of Occupational health and Safety. This commitment extends to minimising exposure

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Management of risk. Definition of terms. Managing risks. Risk

Management of risk. Definition of terms. Managing risks. Risk Definition of terms Risk Management of risk Risk is the possibility that harm (death, injury or illness) might occur when exposed to a hazard. A hazard is anything with the potential to cause injury or

More information

Temporary load-bearing support for structural alterations or repairs

Temporary load-bearing support for structural alterations or repairs CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal

More information

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd

More information

Contractor handbook. Purpose

Contractor handbook. Purpose Page no: 1 / 6 Contractor handbook Purpose Mitie aims to ensure that the highest levels of performance are achieved by all persons working for us or on our behalf. We require the same level of performance

More information

CIVIL INFRASTRUCTURE HEALTH, SAFETY, AND ENVIRONMENT Describe protection of health, safety and environment in the civil infrastructure industry

CIVIL INFRASTRUCTURE HEALTH, SAFETY, AND ENVIRONMENT Describe protection of health, safety and environment in the civil infrastructure industry 1 of 8 level: 3 credit: 7 planned review date: October 2006 sub-field: purpose: Civil Works and Services This unit standard is a component of the selfregulation system for operations in the civil infrastructure.

More information

Safety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1

Safety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1 Safety Guidelines for Live Entertainment and Events Part 2. Hazard Identification and Risk Management Contents Disclaimer... 1 1. Principles of Risk Management... 2 2. The Risk Management Process... 2

More information

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE The Risk Information contained in this paper is intended to assist schools in establishing safe procedures for maintaining school grounds. Schools owe a duty of care to employees and students to keep them

More information

Appendix 4C - Sample SWMS Trenching

Appendix 4C - Sample SWMS Trenching Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :

More information

University College Dublin Machinery/Equipment Risk Assessment Template

University College Dublin Machinery/Equipment Risk Assessment Template 1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment

More information

Safe High Pressure Water Washing (HPWW) Requirement

Safe High Pressure Water Washing (HPWW) Requirement Safe High Pressure Water Washing (HPWW) Requirement Index Page Introduction 3 Flow chart of process steps 4-5 Responsibilities 6 Risk assessment process 7-9 Job safety analyses considerations 10-11 Compliance

More information

Work Health and Safety Risk Management Procedures

Work Health and Safety Risk Management Procedures Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard

More information

CIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS

CIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS Title: Circuit Breaker Testing Purpose and Scope: Provide guidelines for testing of Circuit Breakers. Staffing Resources: Staff will have the minimum requirement of an Electrical Fitter/Mechanic Licence

More information

INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT

INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT Information for the public about an establishment subject to the Control of Major Accident Hazards Regulations 2015 (COMAH) The system to provide

More information

Hazard & Risk Management

Hazard & Risk Management Hazard & Risk Management Introduction The Church recognises WHS hazards and risks must be appropriate managed to ensure, so far as reasonably practicable, the health and safety of all workers at Church

More information

CONTRACTOR SAFETY INDUCTION HANDBOOK

CONTRACTOR SAFETY INDUCTION HANDBOOK CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number

More information

SUPPLIER HEALTH AND SAFETY. Supporting a healthy and safe working environment for our people and customers

SUPPLIER HEALTH AND SAFETY. Supporting a healthy and safe working environment for our people and customers SUPPLIER HEALTH AND SAFETY Supporting a healthy and safe working environment for our people and customers Document Template Control Prepared by Georgina East May 2017 Date Approved by May 2017 Mark Beder

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

Faculty/School: Pharmacy Initial Issue Date: Oct 2016

Faculty/School: Pharmacy Initial Issue Date: Oct 2016 Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions

More information

HAZARDOUS SUBSTANCE AND DANGEROUS GOODS

HAZARDOUS SUBSTANCE AND DANGEROUS GOODS The Barro Group is committed to continuously improving the management and standards of Occupational Health and Safety. This commitment extends to minimising exposure of employees, contractors, visitors

More information

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph: PCBU: ALL TRADES ABSEILING ABN: 42 137 576 035 PO Box 774 NEWPORT NSW 2106 LIC: 123517C P: 0412 227 578 Principal Contractor (PC): Date SWMS provided to PC: Work activity: Workplace location: High risk

More information

COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3)

COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3) COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3) The following guidance notes accompany the College Procedure Assessment form (COSHH-related). Please complete all applicable

More information

Specific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).

Specific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable). OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,

More information

Pollution Incident Response Management Plan Austrak Wagga Wagga

Pollution Incident Response Management Plan Austrak Wagga Wagga - 1/16 Workplace Name: Location: Dampier St, Bomen NSW Document Ref. PIRMP Wagga Wagga Effective Date : Nov 2012 Revision Revision Date Description Reviewed Approved 01 Nov. 2012 Development for License

More information

Before you begin. Introduction Implement and monitor work health and safety procedures 1

Before you begin. Introduction Implement and monitor work health and safety procedures 1 Contents Before you begin v Introduction Implement and monitor work health and safety procedures 1 Topic 1 What you need to know about implementing and monitoring WHS procedures 3 1A Emergency and evacuation

More information

(2) but does not include a shaft, trench or tunnel that is a mine or is part of the workings of a mine.

(2) but does not include a shaft, trench or tunnel that is a mine or is part of the workings of a mine. Health and Safety Procedure - Confined Spaces Section 1 - Background and Purpose (1) Confined spaces are, for the purposes of this procedure, defined as the following which is the definition under the

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Accident/Incident Reporting and Investigation Procedures

Accident/Incident Reporting and Investigation Procedures Accident/Incident Reporting and Investigation Procedures Policy reference Workplace Health and Safety Policy Procedure reference Workplace Health and Safety Risk Assessment Procedures Procedure It is imperative

More information

HS329 Risk Management Procedure

HS329 Risk Management Procedure HS329 Risk Management Procedure Work Health and Safety Act 2011 Policy hierarchy link Work Health and Safety Regulation 2011 Work Health and Safety Policy Code of Practice How to Manage Work Health and

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010) (Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:

More information

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George

More information

Hazard Management Making your workplace safer

Hazard Management Making your workplace safer Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,

More information

In an emergency the safety of all personnel and the public is of priority.

In an emergency the safety of all personnel and the public is of priority. P272 : Emergency Planning & Response This DOCUMENT and any linked FORMS have been created to provide specific requirements under the Amalgamated Operating System. For additional information and guidance,

More information

Policy Redesign Project. Plant Safety Policy. Table of Contents

Policy Redesign Project. Plant Safety Policy. Table of Contents Policy Redesign Project All policies and procedures are being reviewed as part of this project. This document is pending review, but remains in effect until the review is carried out. Plant Safety Policy

More information

EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT

EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT OVERVIEW ASSESSING THE RISK RELATIONSHIP BETWEEN FIRES AND EXPLOSIONS CLASSIFYING HAZARDOUS AREAS INTO ZONES

More information

HEAT, COLD, SOLAR ULTRAVIOLET & INCLEMENT WEATHER

HEAT, COLD, SOLAR ULTRAVIOLET & INCLEMENT WEATHER CONTRACTOR WHS HAZARD STANDARD HEAT, COLD, SOLAR ULTRAVIOLET & INCLEMENT WEATHER EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS

More information

SITE INSPECTION PROCEDURE FORM

SITE INSPECTION PROCEDURE FORM SITE INSPECTION PROCEDURE FORM The Oil and Gas Commission, as regulators of British Columbia s oil and gas industry focuses on effectively regulating and managing the Provinces oil and gas sector. The

More information

Potential risk of injury to staff

Potential risk of injury to staff Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to

More information

BHC-P-07.2 Health Hazards in Construction

BHC-P-07.2 Health Hazards in Construction BHC-P-07.2 Health Hazards in Construction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision Register Date Version Description

More information

WHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015

WHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015 5 WHS PROCEDURE P21-01 Page 1 of 7 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons

More information

EVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1

EVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1 EVENT SAFETY RISK ASSESSMENT (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) EVENT SAFETY MANAGEMENT INFORMATION SHEET September 2010 #3 RISK ASSESSMENT IT S A MUST The success of your event is measured in many

More information

SOP. Working in Confined Spaces

SOP. Working in Confined Spaces Purpose This procedure outlines the requirements for the management of entry into confined spaces in all work areas with the intention of minimising risks to health and safety from any potential hazards

More information

Faculty/School: Pharmacy Initial Issue Date: Oct Dr. Alpesh Patel and Padmaja Dhanvate

Faculty/School: Pharmacy Initial Issue Date: Oct Dr. Alpesh Patel and Padmaja Dhanvate Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions

More information

WORK METHOD STATEMENT TERMITE PROTECTION

WORK METHOD STATEMENT TERMITE PROTECTION ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

Codex Seven HACCP Principles. (Hazard Identification, Risk Assessment & Management)

Codex Seven HACCP Principles. (Hazard Identification, Risk Assessment & Management) Codex Seven HACCP Principles (Hazard Identification, Risk Assessment & Management) Logic sequence for application of HACCP Assemble the HACCP team Describe product Identify intended use Construct a flow

More information

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person

More information

Guidance: HSW Risk Assessment Methodology HSW-PR09-WI01. Objective. Implementation

Guidance: HSW Risk Assessment Methodology HSW-PR09-WI01. Objective. Implementation 1.0 Objective This Work Instruction is designed to assist in the assessment of health and safety and wellbeing (HSW) risk and suggested controls associated with hazards identified while working throughout

More information

SCHEDULE 08 Public Safety Plan

SCHEDULE 08 Public Safety Plan SCHEDULE 08 Public Safety AMHERST ISLAND WIND FARM CONTRACT-SPECIFIC PUBLIC SAFETY PLAN 1 Windlectric May 2017 2 TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 Objective... 2 1.2 Responsibility... 2 2.0 RISK

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

Contractor / Exhibitor Handbook

Contractor / Exhibitor Handbook Contractor / Exhibitor Handbook Health and Safety This booklet outlines the basic rules that must be followed by contractors and other visitors working on Live Promotions Events sites. The contractors

More information

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN). Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This

More information

Health & Safety Contractor rules

Health & Safety Contractor rules Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...

More information

CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE

CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE 1. INTRODUCTION The University uses substances hazardous to health in many of its operations, and accepts that it has a duty of care to reduce exposure

More information

Health, Safety and Environment Management System. HSE-PRO-008 HSE Responsibilities Procedure

Health, Safety and Environment Management System. HSE-PRO-008 HSE Responsibilities Procedure Health, Safety and Environment Management System HSE-PRO-008 HSE Responsibilities Procedure 1 Table of Contents 1 Intent... 3 2 Scope... 3 3 Definitions... 3 4 Duty, Obligations and Responsibilities...

More information

Vermin, Insects and Scavenging Birds Management Plan

Vermin, Insects and Scavenging Birds Management Plan VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant Vermin, Insects and Scavenging Birds Management Plan CONTENTS 1 Introduction... 2 2 Sources, Releases and Impacts... 3 3 Vermin, Insects and

More information

SAFE WORK METHOD STATEMENT Part B

SAFE WORK METHOD STATEMENT Part B SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS

More information

Recognition, Evaluation, and Control of Hazards

Recognition, Evaluation, and Control of Hazards Recognition, Evaluation, and Control of Hazards Latest revised date: October 26, 2011 Page 1 of 8 1.0 Introduction Memorial University has established a system for the recognition, evaluation, and control

More information

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS Colin P. Lynas, Elizabeth Campbell and Hendrik J. Koornhof Johnson Matthey Catalysts This paper

More information

How HSE regulates onshore oil and gas

How HSE regulates onshore oil and gas Health and Safety Executive How HSE regulates onshore oil and gas Paul Bradley (Operations Manager Wells and Mines) Craig Norman (Well Engineering and Operations Inspector) Health & Safety Executive Health

More information

HAZARD RECOGNITION EVALUATION and CONTROL

HAZARD RECOGNITION EVALUATION and CONTROL What is a hazard? HAZARD RECOGNITION EVALUATION and CONTROL Hazard - a dangerous object, event, behaviour or condition (in the workplace) which has the potential to cause injury, illness or property damage.

More information

Occupational Health & Safety

Occupational Health & Safety Personal Development Level 3 Occupational Health & Safety Any injury particularly workplace injury is a major cause of concern for all involved in Occupational Health and Safety (OHS). The factors which

More information

PROCESS HAZARD ANALYSIS FOR THE SEPTIC TANKS AND SYSTEMS REMOVALS AT BUILDING 4005, 4009 AND 4100.

PROCESS HAZARD ANALYSIS FOR THE SEPTIC TANKS AND SYSTEMS REMOVALS AT BUILDING 4005, 4009 AND 4100. HDMSP00036449 Page 1 PROCESS HAZARD ANALYSIS FOR THE SEPTIC TANKS AND SYSTEMS REMOVALS AT BUILDING 4005, 4009 AND 4100. Introduction As part of the Area IV Remediation Project, the septic tanks and piping

More information

POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY

POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY Written By: Nursery Manager Date approved by Directors: Signature: Date for Review: November 2018 COSHH (CONTROL OF SUBSTANCES HAZARDOUS

More information

MARINE SAFETY PLAN

MARINE SAFETY PLAN PORT MARINE SAFETY CODE MARINE SAFETY PLAN 2015-2017 Introduction As required at article 3.20 of the Port Marine Safety Code (PMSC), the Port of London Authority (PLA) publishes its Marine Safety Plan

More information

in Australian Workplaces

in Australian Workplaces Copyright 2011 - OnGuard Safety Training Pty Ltd 1 of 7 in Australian Workplaces Introduction Part 2 Part 3 Part 4 Part 5 SafeWork SA Introduction Hazard identification is the process used to identify

More information

Site Safety Brief - F Appleton Dock

Site Safety Brief - F Appleton Dock Site Safety Brief - F Appleton Dock (Melways Ref: Map 42 J8) November 2015 Purpose The purpose of this site brief is to provide you with the necessary information required to conduct your work safely and

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Entanglement Hired From All Master Hire Stores Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Our Approach to Managing Level Crossing Safety Our Policy

Our Approach to Managing Level Crossing Safety Our Policy Our Approach to Managing Level Crossing Safety Our Policy Our policy towards managing level crossing risk is: that we are committed to reducing the risk at level crossings where reasonably practicable

More information

This document provides guidance to conducting health and safety inspections at the University, to ensure Hazards are identified and controlled.

This document provides guidance to conducting health and safety inspections at the University, to ensure Hazards are identified and controlled. Health and Safety Guideline: HSG 10.1 Health and Safety Inspections and Testing 1. Purpose This document provides guidance to conducting health and safety inspections at the University, to ensure Hazards

More information

CHRISTIAN YOUTH CAMPS BURLEIGH HEADS MOUNTAIN BIKING

CHRISTIAN YOUTH CAMPS BURLEIGH HEADS MOUNTAIN BIKING CHRISTIAN YOUTH CAMPS BURLEIGH HEADS MOUNTAIN BIKING Activity Coordinator: Venue(s) Various (Nerang State Forest, The Boarder Track) Ages Attending: Date of Excursion: The Process 1. Breakdown the activity

More information

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date

More information