Site Specific Rules at Plants. Individual Unit Function: Safety Procedure No.: SOP-0135 Page: 1 of 8

Size: px
Start display at page:

Download "Site Specific Rules at Plants. Individual Unit Function: Safety Procedure No.: SOP-0135 Page: 1 of 8"

Transcription

1 Procedure No.: SOP-0135 Page: 1 of 8 Preparer: Owner: Approver: Safety Safety Safety 1. PURPOSE To provide BASF site specific rules for the protection of all MIDGA and contract personnel. These rules will provide for the protection of all employees while at specific plant sites. 2. DEFINITIONS 3. SCOPE All MIDGA employees and contractor employees. 4. PROCEDURE Gordon Plant Purpose: This procedure is designed to protect all of MIDGA s shipping personnel and Norfolk Southern from injury associated with the routine rail car switching activities while in the Gordon Plant area. The proper and consistent use of this procedure is mandatory, and its importance is equivalent to our lock-tag-try procedure. Procedure: Whenever Norfolk Southern is conducting switching activities in the Gordon Plant, the following procedures will be in place. GENERAL INFORMATION Some railroad tracks in the Gordon Plant will be grouped into pairs based upon their closeness to one another. Each track in a pair share a common switch where a single track diverges into the two tracks in the pair. Track Pairs: Track 9 & 6 Track 7A & 7B Track 3 & 4 Track 1 & 2 (Tracks in Columbia Plant) Track 1 & 2 (Tracks in Savannah Plant)

2 Procedure No.: SOP-0135 Page: 2 of 8 Tracks 5, 7, and 8 do not require pairing POSITIVE PROTECTION FROM NORFOLK SOUTHERN SWITCHING Protection from Norfolk Southern switching will be provided by permanent lockable derails (with blue flags). The derail between all the Gordon Plant railroad tracks branches and the mainline (Norfolk Southern) track will be activated and locked out when no switching is occurring. When the Norfolk Southern switch engine arrives at the plant to commence switching, which occurs about 6:30a.m. each day, the lock will be removed by a designated BASF employee and the derail deactivated. When switching operations are completed, the Car Leader Man will be responsible for reactivating and locking the derail. This will ensure that at least one person in the Gordon Plant is aware of when switching starts and ends. Permanent derails with blue flags will be placed north of (on the mainline track side) the common (shared) switches for each pair of tracks (9/6, 3/4, 1/2 Columbia Plant, and 1/2 Savannah Plant). A permanent derail with a blue flag will be placed approximately 100 feet north of the shared switch of tracks 7A/7B on track 7. Permanent derails with blue flags will be placed on the non-paired tracks (5, 7 and 8) near where each of these tracks diverge from another track. (See attached layout drawing for a location of derails). 1. For car loading personnel, protection during car switching will be provided by the following: For Tracks Grouped in Pairs/Gordon Location The derail located above each common switch will (already) be activated (in its up position and locked) by the Car Leader Man to protect both tracks (in the pair) before the start of car switching. The loading foreman (or designee) in a particular area will know if work is being performed on any of the tracks. a. If switching cannot be safely performed on either of the tracks (in the pair), the derail will remain activated and locked. b. If switching can be safely performed on both tracks (in the pair), the derail will be unlocked and deactivated by the Car Leader Man. The Car Leader Man in each plant area will be responsible for reactivating and relocking the derail after the Norfolk Southern crew has completed switching for the day. c. If switching can safely occur on only one track in the pair, the derail will be unlocked, deactivated and the common (shared) switch will be locked by the Car

3 Procedure No.: SOP-0135 Page: 3 of 8 Leader Man in one direction to protect the proper track in the pair (but allow the other track to have movement taking place on it). The Car Leade Mman in each plant area will be responsible for unlocking the switch and reactivating and relocking the derail after the Norfolk Southern crew has completed switching for the day. a. For Tracks Not Grouped in Pairs (Tracks 5, 7, and 8) b. The derail located on each of these tracks will (already) be activated (locked into its up position) to protect the track at the start of the car switching process. Area loading foreman (or designee) will monitor the loading areas for work being performed on tracks. c. If switching cannot be safely performed on the track, the derail will remain activated and locked. d. If switching can safely occur on the track, the derail will be unlocked and deactivated by the Car Leader man before switching and the derail will be activated and locked by the Car Leader Man after switching. Loading foreman (or designee) coming to work should verify the status of derails at the start of their shifts. 1. For maintenance, new construction or outside services personnel working on a track. Protection during car movement will be provided by the following: For Tracks Grouped In Pairs a. The construction supervisor will attach his safety lock to the already activated derail (which has a Car Leader Man lock on it) before starting any work on a track. If the derail is not already activated and locked, he should find out why. b. If switching cannot be safely performed on either of the tracks (in the pair), the derail will remain activated and locked. If at all possible, the construction supervisor will stop work on the track and ensure all of his people and equipment are out of harm s way when the switch engine is in the plant. c. If switching can be safely performed on both tracks (in the pair, the construction supervisor will stop work on the track, ensure all of his people and equipment are out of harm s way on the track being worked on (and the other paired track) and will remove his lock from the derail. The Car Leader Man will then remove his lock and deactivate the derail. After switching has been completed on the track pair where the crew is working, he will reinstall his lock onto the derail (Car Leader Man locked and activated).

4 Procedure No.: SOP-0135 Page: 4 of 8 NOTE! d. If switching can safely occur on only one track in the pair, the construction supervisor will stop work on the track and ensure all of his people and equipment are out of harm s way. He will remove his lock from the derail and lock the common (shared) switch in one direction to protect the proper track in the pair (but allow the other track to have car movement take place). If the Car Leader Man has already locked the switch in the opposite direction, the construction supervisor should contact the Car Leader Man and discuss the situation. After switching has been completed on the track pair where his crew was working, he will remove his lock from the switch and reinstall his lock on the activated derail For Tracks Not Grouped In Pairs (Tracks 5, 7, and 8) a. The construction supervisor will attach his safety lock the already activated derail (which has a Car Leader Man's lock on it) before starting any work on a track. If the derail is not already activated and locked, the construction supervisor should find out why. b. If switching cannot be safely performed on the track, the derail will remain activated and locked. If at all possible, the construction supervisor will stop work on the track and ensure all of his people and equipment are out of harm s way when the switch engine is in the plant. c. If switching can safely occur on the track, the construction crew supervisor will stop work on the track and ensure all of his people and equipment are out of harm s way on the track. Then he will remove his lock from the derail. The Car Leader Man will then remove his lock and deactivate the derail. After switching has been completed, he will reinstall his lock onto the (Car Leader Man's locked and activated) derail. One reason for pairing the tracks is if some type of work is being performed on one track in the pair, the Shift Leader, Maintenance supervisor, or construction crew supervisor overseeing the work should consider if car movement on the other track in the pair endangers workers. For example, if loading or maintenance personnel are doing work on track 7A, they may be in such close proximity to track 7B with their working, walking, equipment set-up, etc., that they would be in harm s way in relation to car movement on track 7B. Any time work is being performed on a track during the hours that a plant switch occurs, the Shift Leader, Maintenance Supervisor, or Construction Crew Supervisor should contact the Car Leader Man prior to setting up on the track they are performing work on so the Car Leader Man will know work is being performed in the area.

5 Procedure No.: SOP-0135 Page: 5 of 8 Edgar Plant Purpose: The purpose of this procedure is to establish a Zero Energy State when working in or on moving parts of a calciner. Procedure: The procedure is intended to clarify auxiliary motor lockout on the Edgar Plant Calciners and does not supersede or void any part of the BASF Lock, Tag and Try Procedure. MECHANICAL CLUTCH The Mechanical Clutch is to be locked-out at all times when your work requires you to: 1. Be on the calciner 2. In the calciner 3. Working on or in close proximity to any unguarded moving part of the calciner EQUIPMENT REQUIREMENTS MINERALS 1. Crew Locks 2. Individual Locks 3. Multiple Lock Hasps 1. Crew Locks may be placed by an BASF or contractor crew supervisor to protect his crew while work is being performed on the calciner. This supervisor is directly responsible for the Accountability and Safety of his crew members prior to removing his lock or activating the mechanical clutch. All crew locks must have a Danger tag displaying the owner s identification. 2. Individual Locks require the same identification requirements and are to be used by personnel not protected by a crew lock. Mine Pipeline Lockout Procedure Once the area requiring repair or maintenance has been identified, the appropriate designee(s) for the work crew(s) will contact the site mill operator(s)/helper(s) where the pump and/or other sources of energy need to be locked out.

6 Procedure No.: SOP-0135 Page: 6 of 8 A telephone number that can be used to contact the designee(s) will be left with the mill operator/helper, so they can notify the designee when lockout is complete. Once contacted, the mill operator/helper will lock out the pump by placing the switch lever to the off position, attaching a tag, and placing an Owning/Operating Lock(s) on the switch(s). The tag attached to the Owning/Operating Lock will have the operator s/helper s job title and the name of the crew doing the work printed on it. The key to the lock will be controlled by the operator/helper performing the lock out. Other energy sources that could cause a hazard will be tagged or locked out as necessary. A separate Owning/Operating Lock and tag will be used for each crew working on the pipeline. For example, two crews working on same pipeline will use two separate locks. Each lock will be tagged for each crew. A separate Pipeline Lockout Form should be filled out for each crew working on the line. The mill operator/helper will record on the Pipeline Lockout Form, the information about the work being done. The designee s name must be logged, since the designee is the only individual authorized to have the operator/helper remove their lock(s) and/or tag(s). Washington County operations will notify the Daveyville and Gordon Plants about pipeline work being performed. Gibraltar and Dixie operations will notify the Daveyville Plant about pipeline work being performed. Once all equipment has been properly tagged and locked out, the operator/helper will test the equipment to ensure the pumps will not start-up. When the steps outlined above have been accomplished, a representative of the Owning/Operating department must travel to the intended work site and complete a Safe Work Permit (SWP), with a representative of the Servicing Department. Other appropriate permits such as Line Break, Confined Space and Hotwork will be completed at this time. No work on or above the pipeline will begin until the permits are complete except as follows: It is permissible for the service crew to do the minimal work necessary to prevent or reduce the environmental impact from a leak. The service operator should assess the area from a safety standpoint, and if there are no hazards, they should build appropriate berms, ditches, diversions, etc. as necessary to contain the spill. Once this is complete, no further work would be allowed until all permits are in place. During a shift change the operator/helper will record on the Pipeline Lockout Form, all information on pipeline work being performed. The keys can then be transferred to the new operator/helper. The designee of the work crew will then be contacted to inform them of the change of operators /helpers.

7 Procedure No.: SOP-0135 Page: 7 of 8 If the designee of the work crew needs to be changed, a new Safe Work Permit is required. The original designee will contact the operator/helper that has the pumps locked out. The person s name and phone number that is replacing the original designee will then be logged on the Pipeline Lockout Form and he will then become the designee of the work crew. A representative of the Owning/Operating Department will then terminate the original SWP and complete a new SWP with the new designee. Other permits may be re-issued as appropriate and work can then re-commence. Upon completion of the pipeline work, the designee(s) for each crew will inform the operator/helper the pipeline work has been completed. The operator/helper will remove his/her tag(s) and/or lock(s)...daveyville and Gordon Plant will be contacted to coordinate pump start-up. The pumps will be started and the line inspected for leaks. If no leaks are present, the line can be re-buried (if applicable), and communicated to the operator/helper that all work is now complete. The Operator/Helper will then terminate and file the permit(s). The operator/helper will record in the log book, or on a form, all information about pipeline maintenance or repairs completed. The Daveyville/Toddville Plant to Edgar Plant pipeline, and the Klondyke water line, are not covered under this section. Work on these particular pipelines is covered by our regular Lock, Tag, and Try Procedure. Communication cannot be emphasized enough. This must be maintained and followed up for any procedure to work. If the pipeline to be worked on is located between Daveyville and Gordon, both Daveyville and Washington County must be contacted. The pumps and valves at Daveyville must be locked out and verified before work may begin. 5. RESPONSIBILITIES It is the responsibility of each person working on BASF s property to follow these additional requirements.

8 Procedure No.: SOP-0135 Page: 8 of 8 6. RELATED DOCUMENTS Section Revision Revised Date Revised By Edgar Plant Removed reference to Crew Lock WJK 7/12/10 All SOP Review EM 8/11/13 All SOP Review KMH 07/15/2018

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Introduction 2 Regulatory Requirements 2 Protective Materials

More information

LOCKOUT/TAGOUT POLICY

LOCKOUT/TAGOUT POLICY NAVAJO COUNTY Safety Procedures Reference: PERSONNEL POLICIES & PROCEDURE SECTION: 5.4 Approved: Brett Starns Subject: LOCKOUT/ RM-Safety 09/04/2014 TAGOUT POLICY Revised: 9/16/2014 Initiating Department:

More information

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments)

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments) CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments) PURPOSE This program establishes the general and specific requirements for the control of

More information

LO/TO LOCKOUT/TAGOUT PROGRAM

LO/TO LOCKOUT/TAGOUT PROGRAM LO/TO LOCKOUT/TAGOUT PROGRAM April 2017 CONTENTS Section 1: Introduction...1 Section 2: Purpose... 1 Section 3: Application... 1 Section 4: Definitions... 2 Section 5: Roles and Responsibilities... 4 Section

More information

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout)

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout) Purpose: To provide the minimum requirements for the lockout or tagout of energy isolating devices whenever work is performed or servicing is done on County of DuPage machinery, equipment, vehicles and

More information

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012 PAGE 1 OF 7 LOCK-OUT TAG-OUT (LOTO) THE CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROGRAM PURPOSE: 1. This standard establishes lockout/tagout (LOTO) procedures for the safety of personnel working on

More information

DRAFT LOCKOUT/TAG OUT PROGRAM (CONTROL OF HAZARDOUS ENERGY)

DRAFT LOCKOUT/TAG OUT PROGRAM (CONTROL OF HAZARDOUS ENERGY) DRAFT [name of unit] LOCKOUT/TAG OUT PROGRAM (CONTROL OF HAZARDOUS ENERGY) PURPOSE This program establishes the general and specific requirements for the control of hazardous energy during the servicing

More information

Hazardous Energy Control (Lockout-Tagout)

Hazardous Energy Control (Lockout-Tagout) Hazardous Energy Control (Lockout-Tagout) The purpose of this program is to prevent inadvertent operation or energization of machines, equipment, or processes in order to protect employees and establish

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

Lock Out - Tag Out Safety Program

Lock Out - Tag Out Safety Program Lock Out - Tag Out Safety Program Daniel Schmid 4-22-15 Pam Schmid 4-22-15 Dan Schmid Pam Schmid Safety Director Quality Director Table of Contents DOCUMENT REVISION TABLE... 3 PURPOSE... 4 RESPONSIBILITY...

More information

Lock Out/Tag Out Control of Hazardous Energy

Lock Out/Tag Out Control of Hazardous Energy Lock Out/Tag Out Control of Hazardous Energy University Facilities Internal Procedure: July 1, 2013 Effective date: July 1, 2013 Last Modified: April 2013 Approved by: Bob Wells 1.0 Program Objective UF

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program RIM of the World Unified School District 27315 North Bay Road Blue Jay, CA 92352 (909) 336-4100 July 2016 Safety and Risk Management Department RIM of the World Unified School District

More information

Lockout / Tagout Safety Program

Lockout / Tagout Safety Program Lockout / Tagout Safety Program Prepared by: The Ohio State University Environmental Health and Safety Occupational Safety & Industrial Hygiene 1314 Kinnear Road Columbus, OH 43212-1168 614-292-1284 Phone

More information

PINNACLE OWNING SAFETY: Zero Fires Zero Loss Incidents 100% Employee Engagement

PINNACLE OWNING SAFETY: Zero Fires Zero Loss Incidents 100% Employee Engagement PINNACLE OWNING SAFETY: Zero Fires Zero Loss Incidents 100% Employee Engagement ENERGIZED WORK PERMIT OVERVIEW Effective January, 2016 ENERGIZED WORK DEFINITION Energized work describes work that must

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107

WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107 WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107 Draft Issued 12/97 Revised 11/00 Please direct any questions or comments about the applicability of this document to Luigi Marcone, WCSU

More information

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) 1. PURPOSE The purpose of this program is to establish policy, rules and procedures for the protection of employees against the unexpected energizing, start-up,

More information

LOCKOUT SYSTEM AND POLICIES

LOCKOUT SYSTEM AND POLICIES LOCKOUT SYSTEM AND POLICIES Lockout System Purpose Employees health and safety takes top priority. Isolating hazardous energy to prevent sudden and unexpected energisation of machines, equipment, and processes

More information

Gettysburg College. Energy Control Program

Gettysburg College. Energy Control Program Gettysburg College Energy Control Program Adopted October 2009 Reviewed and Updated February 2015 Reviewed and Updated July 2015 I. Energy Control Procedures Table of Contents A. General Lockout Procedures

More information

Lockout/Tagout Safety Policy

Lockout/Tagout Safety Policy University of North Carolina Wilmington Environmental Health & Safety Workplace Safety Lockout/Tagout Safety Policy GENERAL The UNCW Environmental Health & Safety Department (EH&S) is authorized by UNCW

More information

Lockout - Tagout. Control of Hazardous Energy OSHA Standard

Lockout - Tagout. Control of Hazardous Energy OSHA Standard Lockout/Tagout Lockout - Tagout Control of Hazardous Energy OSHA Standard 1910.147 What Is Lockout/Tagout? Referred to as LOTO Blocks the flow of energy from power source to the equipment Provides means

More information

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Safe Operating Procedure

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Safe Operating Procedure CITY AND COUNTY OF DENVER CR&CF RISK UNIT 65.4.2 Safe Operating Procedure 1.0 Introduction Safe Operating Procedures (SOPs) shall be developed for complex or ongoing activities that present a risk of serious

More information

Facilities Management

Facilities Management Facilities Management Policy Number: 700.6 Title: Lockout/Tag Out Policy Implementation Date: 2004 Last Audited: July 2 nd, 2018 Last Revised: March 25 th, 2015 Introduction This policy contains the necessary

More information

Control of Hazardous Energy (Lockout/Tag-out) 29 CFR

Control of Hazardous Energy (Lockout/Tag-out) 29 CFR Control of Hazardous Energy (Lockout/Tag-out) 29 CFR 1910.147 What Is Lockout/Tag-out? Referred to as LOTO Blocks flow of energy from power source to the equipment Provides means of warning (tag) Regulatory

More information

Safety Manual: Hazardous Energy. January, 2017

Safety Manual: Hazardous Energy. January, 2017 Safety Manual: Hazardous Energy January, 2017 9.0 Hazardous Energy Introduction Energized equipment in the workplace pose a significant risk of injury and death. If the unexpected energization or start-up

More information

LOCKOUT/TAGOUT PLAN August 2015

LOCKOUT/TAGOUT PLAN August 2015 LOCKOUT/TAGOUT PLAN August 2015 Office of Environmental Health and Safety 423-354-5224 TABLE OF CONTENTS Purpose and Intended Use... 2 A. Types of Energy Sources... 2 B. Activities Requiring Lockout/Tagout

More information

Lockout/Tagout Plan Environmental Health & Safety Office July 2017

Lockout/Tagout Plan Environmental Health & Safety Office July 2017 July 2017 Table of Contents Acronyms... iii Foreword... iv Document History... iv 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Scope... 1 1.3 Lockout/Tagout Program... 1 2.0 Roles and Responsibilities...

More information

Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR

Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR Volunteer State Community College Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR 1910.147 The information contained in this maual documents the policies and procedures

More information

H. Control of Hazardous Energy: Lockout/Tag Out

H. Control of Hazardous Energy: Lockout/Tag Out H. Control of Hazardous Energy: Lockout/Tag Out 1. Purpose Control of Hazardous energy is the purpose of the Lockout- Tagout Program. This program establishes the requirements for isolation of both kinetic

More information

Hazardous Energy Control

Hazardous Energy Control Lockout Tagout This program has been prepared to provide assistance in compliance with USA OSHA standards and/or Best Management Practices. It should not be used without consideration of the unique conditions

More information

Control of Hazardous Energy. Environmental Health and Safety

Control of Hazardous Energy. Environmental Health and Safety Control of Hazardous Energy Environmental Health and Safety 11/01/2014 1 CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) OSHA CFR 1910.147 Revised Date: November 2014 STATEMENT OF POLICY Ball State University

More information

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE Office of Environmental Health & Safety CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE LOCK OUT/TAG OUT OSHA 29 CFR 1910.147 rev. 3 2014 Director of Environmental Health & Safety Control of Hazardous Energy

More information

OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM. Environmental Health and Safety. Established:

OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM. Environmental Health and Safety. Established: OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM Environmental Health and Safety Established: Developed in accordance with OSHA Standard 29 CFR 1910.147 1 1.0 SCOPE. Oklahoma City Community

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

Lockout/Tagout Program

Lockout/Tagout Program Purpose Hazardous energy appears in the workplace in the form electrical, mechanical, pneumatic, hydraulic and thermal energy and includes chemical, water, steam and gaseous energy systems. Lockout/Tagout

More information

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT)

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) WAC Page 296-307-320 Control of hazardous energy (lockout-tagout). 1 296-307-32001 What does this section cover? 1 296-307-32003 When does this section

More information

LOCKOUT/TAGOUT: Operating Procedure TABLE OF CONTENTS

LOCKOUT/TAGOUT: Operating Procedure TABLE OF CONTENTS LOCKOUT/TAGOUT: Operating Procedure TABLE OF CONTENTS A. PURPOSE 1 B. FACILITIES STAFF RESPONSIBILITIES 2 C. TRAINING AND RETRAINING of AFFECTED and EUTHORIZED EMPLOYEES 3 NINE POINTS TO REMEMBER 5 LOCKOUT/TAGOUT

More information

MARIPOSA COUNTY LOCKOUT/TAGOUT PROGRAM

MARIPOSA COUNTY LOCKOUT/TAGOUT PROGRAM MARIPOSA COUNTY LOCKOUT/TAGOUT PROGRAM INTRODUCTION Mariposa County ( County ) facilities have equipment and systems that must be deenergized to allow for safe cleaning, repairing, servicing, setting-up,

More information

SOP GEN-007I Energy Isolation

SOP GEN-007I Energy Isolation Page 1 of 6 1.0 Introduction 2.0 Reference 3.0 Scope 4.0 Procedures 5.0 Permit SOP GEN-007I Revision/ Review Log Revision Date Approved by Reviewed by Revision Details/ Proposal Notes 11 January 2010 HSE

More information

University of Arkansas Office of Environmental Health and Safety

University of Arkansas Office of Environmental Health and Safety University of Arkansas Office of Environmental Health and Safety Procedure Name: Lockout / Tagout Procedure Number: 600.26 Effective Date: 12-1-2015 Procedure: Developed in accordance with the OSHA Control

More information

LOCKOUT / TAGOUT PROGRAM

LOCKOUT / TAGOUT PROGRAM LOCKOUT / TAGOUT PROGRAM Developed in accordance with the OSHA Control of Hazardous Energy Standard, 29 CFR 1910.147 DECEMBER 7, 2017 SKIDMORE COLLEGE 815 NORTH BROADWAY, SARATOGA SPRINGS, NY 12866 Table

More information

230-LOCKOUT/TAGOUT PROGRAM

230-LOCKOUT/TAGOUT PROGRAM 230.1 PURPOSE A. To confirm implementation, operation, and recordkeeping of Central New Mexico Community College(CNM) lockout/tagout program in compliance with 29 CFR 1910.147. 230.2 SCOPE A. The requirements

More information

Lockout/Tagout Manual

Lockout/Tagout Manual Manual 2408 Wanda Daley Drive Ames, Iowa 50011-3602 (515) 294-5359 www.ehs.iastate.edu Copyright Environmental Health and Safety 2809 Daley Drive Ames, IA 50011-3660 Ph: (515) 294-5359 www.ehs.iastate.edu

More information

Lockout/Tagout. Page. Introduction. Purpose. 2 Background. 2 Who s Covered?... 3 Responsibilities. 3 Explanation of Key Terms. 4.

Lockout/Tagout. Page. Introduction. Purpose. 2 Background. 2 Who s Covered?... 3 Responsibilities. 3 Explanation of Key Terms. 4. Lockout/Tagout Page Introduction Purpose. 2 Background. 2 Who s Covered?... 3 Responsibilities. 3 Explanation of Key Terms. 4 How It Works General Lockout/Tagout Procedure. 5 General Lock/Tag Removal Procedure.

More information

POLICY & PROCEDURE #502 EFFECTIVE DATE: 6/5/02 LAST REVISED: 7/12/12 LAST REVIEWED: 7/8/15

POLICY & PROCEDURE #502 EFFECTIVE DATE: 6/5/02 LAST REVISED: 7/12/12 LAST REVIEWED: 7/8/15 1.0 PURPOSE PLANT OPERATIONS AND MAINTENANCE, CENTRAL PLANT PERSONNEL ARE RESPONSIBLE FOR USING THE IN ACCOMPLISHING THE VARIOUS JOB TASKS ESTABLISHED IN THEIR JOB DESCRIPTION. THIS POLICY AND PROCEDURE

More information

Lockout/Tagout - Energy Control Program

Lockout/Tagout - Energy Control Program Lockout/Tagout - Energy Control Program Lockout and Tagging of ELECTRICAL Circuits This portion of the K.R. Miller Contractors, Inc. safety program has been created to maintain a written copy of procedures

More information

Lockout/Tagout Program

Lockout/Tagout Program Lockout/Tagout Program Prepared by: Occupational Health and Safety Reviewed by: Joint Health and Safety Committees Approved by: Chief Human Resources Officer November 2014 TABLE OF CONTENTS 1.0 Purpose...3

More information

General Lockout Training Briefing

General Lockout Training Briefing Page 1 of 5 Introduction What is Lockout? Lockout protects your personnel and plant from injury or accident by ensuring that equipment and machinery is properly isolated during scheduled maintenance, shutdown,

More information

University of Vermont Department of Physical Plant Burlington, Vermont

University of Vermont Department of Physical Plant Burlington, Vermont University of Vermont Department of Physical Plant Burlington, Vermont CONTROL OF HAZARDOUS ENERGY SOURCES AND ELECTRICAL HAZARDS LOCKOUT AND TAGOUT PROGRAM in accordance with OSHA 29 CFR 1910.147 REVISED

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM 0 Appendix C OCCUPATIONAL SAFETY AND HEALTH PROGRAM LOCKOUT/TAGOUT PROGRAM Hazardous Energy Control Lockout/Tagout Program TABLE OF CONTENTS Section Page I. Purpose and Scope. 1 II. Definitions 1 III.

More information

Lockout / Tagout Program OSHA 29 CFR

Lockout / Tagout Program OSHA 29 CFR Lockout / Tagout Program OSHA 29 CFR 1910.147 Baylor University utilizes outside contractors to perform set-up, maintenance, service, and repair to equipment utilized on campus. University staff perform

More information

SAFETY DIRECTIVE 2.0 DEPARTMENTS AFFECTED. This Administrative Directive shall apply to all Town of Marana departments and employees.

SAFETY DIRECTIVE 2.0 DEPARTMENTS AFFECTED. This Administrative Directive shall apply to all Town of Marana departments and employees. SAFETY DIRECTIVE Title: Control of Hazardous Energy Lock-out/Tag-out/Try-out Issuing Department: Town Manager s Safety Office Effective Date: July 1, 2014 Approved: Gilbert Davidson, Town Manager Type

More information

TAMPA ELECTRIC COMPANY ENERGY SUPPLY HAZARDOUS ENERGY CONTROL LOCKOUT PROGRAM

TAMPA ELECTRIC COMPANY ENERGY SUPPLY HAZARDOUS ENERGY CONTROL LOCKOUT PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 1-4 EMPLOYEE TRAINING INCLUDING DOCUMENTATION 5-6 HEC APPLICATION AND REMOVAL 7-14 COMMITTEE A HEC DEVICE 15 SPECIAL SITUATIONS 16-23

More information

SAMPLE WRITTEN PROGRAM for Control of Hazardous Energy LOCKOUT TAGOUT

SAMPLE WRITTEN PROGRAM for Control of Hazardous Energy LOCKOUT TAGOUT SAMPLE WRITTEN PROGRAM for Control of Hazardous Energy LOCKOUT TAGOUT SAMPLE WRITTEN PROGRAM The objective of this procedure is to establish a means of positive control to prevent the accidental starting

More information

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0 () 30.0 The purpose of the Energy Control Policy (Lockout/Tagout) is to ensure that before any employee performs any servicing and/or maintenance on machinery or equipment, where the unexpected energizing,

More information

This session covers the safety procedure known as lockout/tagout, which is required by Occupational Safety and Health Administration (OSHA) in its

This session covers the safety procedure known as lockout/tagout, which is required by Occupational Safety and Health Administration (OSHA) in its This session covers the safety procedure known as lockout/tagout, which is required by Occupational Safety and Health Administration (OSHA) in its standard on Control of Hazardous Energy. This is part

More information

Issue: Issued By: Environment, Health & Safety Part: Hazard Identification and Assessment Revision #: 2 Revision

Issue: Issued By: Environment, Health & Safety Part: Hazard Identification and Assessment Revision #: 2 Revision Control of Hazardous Energy Program Section: Occupational Health and Safety Date of 2007.07.24 Management System Issue: Issued By: Environment, Health & Safety Part: Hazard Identification and Assessment

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM Santa Clarita Community College District LOCKOUT/TAGOUT PROGRAM Revised March 2018 TABLE OF CONTENTS PURPOSE... 3 COMPLIANCE...4 DEFINITIONS...5 SECTION I - ENERGY CONTROL PROCEDURES... 7 SECTION II -

More information

Hazardous Energy Control/Lockout

Hazardous Energy Control/Lockout This is a photographic template your photograph should fit precisely within this rectangle. Hazardous Energy Control/Lockout MESH 8.0 - Process Safety Awareness Training 2008 Eaton Corporation. All rights

More information

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018 University Policy Volume E2: Environment, Health, Safety and Security E2.14 Control of Hazardous Energy Responsible Office: Facilities Management Responsible Officer: Safety Officer POLICY STATEMENT All

More information

Central Washington University

Central Washington University Central Washington University Lockout / Tagout (LOTO) Program Plan prepared by: Central Washington University Office of Environmental Health & Safety 400 East University Way Ellensburg, WA 98926 P: 509-963-2252

More information

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.147 BASIS: Approximately three million workers in the United States face risks from uncontrolled energy when servicing machinery

More information

Elements of a Lockout/Tagout Program OSHA

Elements of a Lockout/Tagout Program OSHA September 15, 2015 Elements of a Lockout/Tagout Program OSHA 1910.147 Dayna Noble Industrial Safety Consultant Specialist Ohio BWC 567-204-8917 Dayna.noble@bwc.state.oh.us Top 10 most frequently cited

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM LOCKOUT/TAGOUT PROGRAM HOW CLIMATE ENGINEERS INC. COMPLIES WITH THELO/TO STANDARD It is the intent of Climate Engineers Inc. to comply with OSHA s Control of Hazardous Energy Standard (1910.147). The following

More information

Lockout/Energy Control

Lockout/Energy Control Lockout/Energy Control Presented By: Sotaris, LLP 2000 Auburn Drive, Suite 200 Beachwood, Ohio 44122 P: 216-378-7650 F: 866-794-5756 W: www.sotaris.com E: awj@sotaris.com 1 About Me Andrew W. Johnson,

More information

Hazardous Waste Training Plan. Supersedes: 02/15/16 (Rev.02) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager

Hazardous Waste Training Plan. Supersedes: 02/15/16 (Rev.02) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Procedure No.: PA-033-0006 Page: 1 of 19 Port Arthur, TX. Reviewed: 02/18 Effective: 02/06/18 (Rev.03) Supersedes: 02/15/16 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program 1.0 INTRODUCTION Public Safety Department Environmental, Health and Safety (EHS) Division Standard Operating Procedure (SOP) #18 Purpose To ensure that machinery or equipment is

More information

FCX Department of Occupational Health and Safety. Flagging and Barricading Guideline

FCX Department of Occupational Health and Safety. Flagging and Barricading Guideline FCX Department of Occupational Health and Safety Flagging and Barricading Guideline Approval Date: 11/12/13 Original Date: 03/30/09 SOP # FCX-19 Revision # 1 Supersedes X High Medium Task Risk Low NA Contents

More information

SAINT MARY S COLLEGE OF CALIFORNIA STANDARD HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT. Prepared by

SAINT MARY S COLLEGE OF CALIFORNIA STANDARD HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT. Prepared by SAINT MARY S COLLEGE OF CALIFORNIA STANDARD 1.1.4 HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT Prepared by SAINT MARY S COLLEGE OF CA MORAGA, California KAREN LAURICELLA Original Date: 1 JULY

More information

PROCEDURE NUMBER: PRC-SAF-16 (Preparation of Piping and Equipment for Repair) Page 1 of 10 Rev. 1.4 Date: 10/17/2016 Rev. 2.

PROCEDURE NUMBER: PRC-SAF-16 (Preparation of Piping and Equipment for Repair) Page 1 of 10 Rev. 1.4 Date: 10/17/2016 Rev. 2. ZACHARY SITE PROCEDURE NUMBER: PRC-SAF-16 (Preparation of Piping and Equipment for Repair) Page 1 of 10 Rev. 1.4 Date: 10/17/2016 Rev. 2.0 Date: 11/7/18 PRC-SAF-16 Zachary Site SAFETY POLICIES and PROCEDURES

More information

THE UNIVERSITY OF NORTH CAROLINA

THE UNIVERSITY OF NORTH CAROLINA THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL CHILLED WATER DEPARTMENT ENERGY CONTROL PROCEDURE The purpose of this document is to establish minimum requirements for the manual isolation and securing

More information

LOCK-OUT / TAG-OUT SYSTEM & PROCEDURE

LOCK-OUT / TAG-OUT SYSTEM & PROCEDURE Date Adopted 8/04/2008 Due for Review 8/4/2009 Business Unit HR & Safety Current Policy Date 8/4/2008 LOCK-OUT / TAG-OUT SYSTEM & PROCEDURE 1.0 PURPOSE 2.0 SCOPE To prevent injuries to persons or damage

More information

The Control of Hazardous Energy (Lockout/Tagout) California State University Chico

The Control of Hazardous Energy (Lockout/Tagout) California State University Chico The Control of Hazardous Energy (Lockout/Tagout) California State University Chico Department of Environmental Health and Safety Reviewed July 2008 TABLE OF CONTENTS Section Page 1.0 INTRODUCTION... 1-1

More information

Isolation and Lockout

Isolation and Lockout Work Procedure Facilities Management UBCO-RMS-OHS-WP 16-001 Date Created: July 13, 1999 Date Updated: April 4, 2016 Supersedes: September 18, 2003 1. SCOPE Isolation and Lockout This procedure establishes

More information

CONTROL OF HAZARDOUS ENERGY

CONTROL OF HAZARDOUS ENERGY SECTION 12 CONTROL OF HAZARDOUS ENERGY 12.A GENERAL 12.A.01 This Section shall apply to contractor-managed Hazardous Energy Control Programs (HECP) only, as well as all requirements of 1910.147, ANSI Z244.1,

More information

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) PROGRAM

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) PROGRAM Page: 1 of 15 1.0 Purpose and Applicability 2.0 Scope 1.1 It is the policy of the University of Pennsylvania in coordination with the Office of Environmental Health and Radiation Safety to provide the

More information

Lockout. HealthandSafetyOntario.ca. What is Lockout? How is a Lockout Done? Why is a Lockout Necessary?

Lockout. HealthandSafetyOntario.ca. What is Lockout? How is a Lockout Done? Why is a Lockout Necessary? What is Lockout? Lockout means to physically neutralize all energies in a piece of equipment before beginning any maintenance or repair work. Lockouts generally involve: Stopping all energy flows (for

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program Table of Contents INTRODUCTION... 2 FORWARD... 2 OBJECTIVE... 2 APPLICABILITY... 2 RESPONSIBILITIES... 3 PROGRAM ENFORCEMENT... 4 RECORDKEEPING... 4 LOCKOUT TAGOUT EQUIPMENT... 5

More information

Lock-out Tag-out Program (Zero Energy State)

Lock-out Tag-out Program (Zero Energy State) Lock-out Tag-out Program (Zero Energy State) Department: Environmental Health and Safety 2 TABLE OF CONTENTS Section Title Page 1.0 Scope and Responsibilities. 3 2.0 Examples of Potential Energy and Zero

More information

PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5

PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5 Classroom, Occupational Safety & Health Plan Date: August 5, 2017 PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5 1. Purpose This document establishes the Lockout Program for Tidewater Community

More information

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with?

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with? 1. What is the top priority when working on Canadian Pacific (CP) property? A. Production B. Safety C. Quality D. Project deadline 2. When working on CP property what must all Contractors comply with?

More information

Control of Hazardous Energy Lockout / Tagout Program

Control of Hazardous Energy Lockout / Tagout Program Control of Hazardous Energy Lockout / Tagout Program August 2016 Table of Contents Purpose... 1 Scope and Application... 1 Responsibilities... 1 Environmental Health and Safety Personnel (EH&S)... 1 Directors

More information

CITY OF NEW LONDON LOCKOUT/TAGOUT PROGRAM

CITY OF NEW LONDON LOCKOUT/TAGOUT PROGRAM CITY OF NEW LONDON LOCKOUT/TAGOUT PROGRAM (HAZARDOUS ENERGY CONTROL) May 1, 2003 1 LOCKOUT/TAGOUT PROGRAM (HAZARDOUS ENERGY CONTROL) I. PURPOSE The purpose of this Hazardous Energy Control Program is to

More information

Confined Space Entry Procedure

Confined Space Entry Procedure Purpose The purpose of this chapter is to establish methods to identify confined spaces, classify them according to their risks, and establish guidelines necessary for the safe preparation, entry and rescue

More information

1 Purpose. 2 Responsibilities. 3 Policy Content ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS. TITLE: CONFINED SPACE ENTRY Document Number: *

1 Purpose. 2 Responsibilities. 3 Policy Content ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS. TITLE: CONFINED SPACE ENTRY Document Number: * (Insert Company Logo) CORPORATE SAFETY MANUAL ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS TITLE: CONFINED SPACE ENTRY Document Number: * Issue Date: Revision Date: * 1 Purpose The purpose of this policy

More information

Texas Department of Insurance Division of Workers Compensation. Lockout Tagout HS96-100D (8-06)

Texas Department of Insurance Division of Workers Compensation. Lockout Tagout HS96-100D (8-06) OF OF STATE THE TEXAS TEXAS Texas Department of Insurance Division of Workers Compensation Lockout Tagout HS96-100D (8-06) Contents Purpose 1 Definitions 1-2 Responsibility 2-3 Training 3 Periodic Inspections

More information

ANNUAL IDOL COMPLIANCE TRAINING

ANNUAL IDOL COMPLIANCE TRAINING ANNUAL IDOL COMPLIANCE TRAINING Lock Out / Tag Out Refresher SUGAR GROVE FIRE DEPARTMENT 1 TRAINING DIVISION Instructions To complete this independent study program, view the entire program, advancing

More information

Confined Space Entry

Confined Space Entry Confined Space Entry Purpose The purpose of this chapter is to establish methods to identify confined spaces, classify them according to their risks, and establish guidelines necessary for the safe preparation,

More information

Control of Hazardous Energy Program (LOTO)

Control of Hazardous Energy Program (LOTO) 1.0 PURPOSE The purpose of this program is to establish minimum safety requirements for the lockout and tagout of hazardous energy sources and the verification of energy isolation through the use of isolating

More information

2523-LDG-E. Leader s Guide

2523-LDG-E. Leader s Guide 2523-LDG-E LOCKOUT/TAGOUT TRAINING FOR EMPLOYEES Leader s Guide 2008 ERI Safety Videos LOCKOUT/TAGOUT TRAINING FOR EMPLOYEES This easy-to-use Leader s Guide is provided to assist in conducting a successful

More information

Lockout/Tagout - Control of Hazardous Energy Program

Lockout/Tagout - Control of Hazardous Energy Program Lockout/Tagout - Control of Hazardous Energy Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 6/8/2018

More information

Health, Safety, Security and Environment

Health, Safety, Security and Environment Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change; text clarification-no

More information

MCW s Control of Hazardous Energy Program

MCW s Control of Hazardous Energy Program 2018 MCW s Control of Hazardous Energy Program - Lockout Tagout Program This document is MCW s written program for managing the lockout and tagout of hazardous energy, and identifies roles and responsibilities

More information

Lockout Tagout Policy

Lockout Tagout Policy Office of Environmental Health & Safety www.moreheadstate.edu/ehs 606-783-2584 Lockout Tagout Policy PURPOSE To establish procedures for the de-energization and isolation of energy sources or the lockout

More information

Product Information Report Lockout/Tagout Hazardous Energy Control

Product Information Report Lockout/Tagout Hazardous Energy Control Overview A properly implemented (LOTO) program is designed to protect workers involved in the maintenance and servicing of equipment from the dangerous effects of hazardous energy caused by the unexpected

More information

CONTROL OF HAZARDOUS ENERGY

CONTROL OF HAZARDOUS ENERGY Table of Contents 1.0 Applicability...2 2.0 Scope...2 3.0 Definitions...2 4.0 Core Information and Requirements...3 5.0 Roles and Responsibilities... 12 6.0 Goals, Objectives and Performance Measures...

More information

University of Illinois at Chicago. Control of Hazardous Energy Program (Lockout/Tagout)

University of Illinois at Chicago. Control of Hazardous Energy Program (Lockout/Tagout) University of Illinois at Chicago Control of Hazardous Energy Program (Lockout/Tagout) 10/4/2018 UNIVERSITY OF ILLINOIS AT CHICAGO Control of Hazardous Energy (Lockout/Tagout) Program TABLE OF CONTENTS

More information

Confined Space Entry Program 8 CCR 5157

Confined Space Entry Program 8 CCR 5157 TABLE OF CONTENTS 1. POLICY... 2 2. PURPOSE... 2 3. SCOPE... 2 4. DEFINITIONS... 2 5. CONFINED SPACES IN THE SACRAMENTO STATE... 4 6. PERMIT SPACE ENTRY - PERSONNEL RESPONSIBILITIES... 4 6.1. CONFINED

More information

PRESCOTT SCHOOL DISTRICT NO South A Street Prescott, WA The Control of Hazardous Energy (Lockout/Tagout)

PRESCOTT SCHOOL DISTRICT NO South A Street Prescott, WA The Control of Hazardous Energy (Lockout/Tagout) PRESCOTT SCHOOL DISTRICT NO. 402-37 207 South A Street Prescott, WA 99348 509-849-2217 The Control of Hazardous Energy (Lockout/Tagout) I. Purpose The Control of Hazardous Energy (Lockout/Tagout) This

More information

B&B Gas Well Services, LLC HEALTH, SAFETY AND ENVRONMENTAL MANUAL HAZARD COMMUNICATION PROGRAM

B&B Gas Well Services, LLC HEALTH, SAFETY AND ENVRONMENTAL MANUAL HAZARD COMMUNICATION PROGRAM B&B Gas Well Services, LLC HEALTH, SAFETY AND ENVRONMENTAL MANUAL HAZARD COMMUNICATION PROGRAM 1 HAZARD COMMUNICATION PROGRAM Table of Contents Topic Page 1.0 Objective 3 2.0 Scope 3 3.0 References 3 4.0

More information