RISK ASSESSMENT / METHOD STATEMENT TUDOR SAILING CLUB VESSEL RECOVERY AND LAUNCH LIFTING OPERATION.
|
|
- Martina Stafford
- 5 years ago
- Views:
Transcription
1 RISK ASSESSMENT / METHOD STATEMENT TUDOR SAILING CLUB VESSEL RECOVERY AND LAUNCH LIFTING OPERATION. Risk assessment Contract No. Generic Tudor Sailing Club lift/launch of Vessels. Appointed person carrying out assessment: G Thomson Site address: Tudor Sailing Club, Eastern Road, Portsmouth, PO3 5LY Office contact: Neil Goodyear Boatswain. Date of Risk assessment: 16/02/09 Time of Assessment: N/A Phone: Phone: Fax: Description of lift: Lift out Launch of pleasure crafts using private slipway and Slipway Hoist. Details of Loads Load position 1 Load position 2 Load position 3 Weight: Max 10 tonnes Dimensions: Max Position of C of G: Variable Height of lift (worst case) 1.5m Max Radius (worst case) N/A Date of lift: Generic all year Time of lift: Daylight hours Value of load ( ): ,000 Details of Hoist 1 st 2 nd 3 rd Make & model: Wise W10 (4472) Capacity: 10 tonnes Minimum width: 3m Max Width: 4m AuxilliaryLift 47.3kN Capacity: Max ground bearing: N/A Tractor weight: Hoist Weight: Counter weight: N/A Ground conditions (Visual assessment) Access/egress for crane & transport: Lifting position: Crossing public Highway & footpath Variable depending On size/keel type. 1
2 Lifting accessories Slings ( Wire rope ): Auxiliary 16mm 6 x 31 IWRC GALV. 5: kN Slings ( Webbing ): SWL 3.25t Slings ( Chains ): Nil used Shackles/Hooks : Other accessories: Identification of hazards Proximity Hazards Present? Other Hazards Present? Overhead power lines: No Other crane operations: No Other overhead/adjacent Yes Excessive noise: No obstacles: Underground services: No Working directly in water: Yes Excavations: No Poor visibility/blind areas Yes Unstable / soft ground: No Restricted access (Site) Yes Hazardous chemicals/ materials: No Pedestrians Yes Confined working areas: Yes Ergonomic constraints Yes Restricted access width: Yes Pedestrians Yes Restricted access height: Yes Manual Lifting & Handling Yes Restricted turning arc: Yes Lifting load with personnel Yes Other vehicles: Yes Portsmouth sailing centre traffic Yes Tudor Members vehicles Yes Council pitch Football traffic Yes Manual Handling Hazards Are any manual handling tasks over the recommended guidelines Are there any other manual handling considerations ( pushing, pulling, use of tag lines etc) Is a complete manual handling assessment required Yes Yes Yes Risk Values for Assessments below: Rate Hazard: A - Death, Major Injury or Major damage/loss to property or equipment. B - Over 3 day injury, damage to property/equipment. C Minor injury or minor damage to property/equipment Rate Risk: 1. extremely likely to occur 2. Frequent/often/likely to occur 3. Slight chance of occurring 2
3 Risk Rating Chart Risk A B C 1 A1 B1 C1 2 A2 B2 C2 3 A3 B3 C3 A1 Unacceptable must receive immediate attention to remove/reduce risk B1 A2 C1 A3 B2 C2 B3 C3 Urgent must receive attention as soon as possible to reduce hazard or risk. Must receive attention to check if hazard or risk can be reduced and those systems In place are satisfactory Should receive attention to check if hazard or risk can be reduced and that Procedures are satisfactory Low priority Assessment of risk Hazard present Risk value Action to avoid or reduce risk B1 Provide trained banks man and Drivers/operators of tractor/hoist. Operate hoist iaw manufacturer s guidelines. Overhead/adjacent obstacles (shrouds/guardrails/vessels) Restricted width/height. Underground services C3 Compound water main. Protect housing with steel plates. Dropping load/damage to load A1 Ensure use of properly trained slinger banks man and hoist operators. Thorough examination of hoist and slings i.a.w LOLER Regs. Inspection of slings and hoist i.a.w Manufactures guidlelines. Operation of hoist i.a.w manufacturer s guidelines. Vessel owners to clearly mark lifting positions. Fresh water wash rig/slings after each use and close all hydraulic rams. Maintain Hoist iaw manufacturers guidelines. 3
4 Confined working areas Restricted turning arcs B2 Ensure restrictions in place to minimise space taken up by dinghies and other associated equipment. (move out of area) Clear car park. Restrict access to pedestrians. And Marshal area. Vehicle access A2 Provide Traffic marshal and warning signs. Stop vehicles in path of hoist whilst underway. Working directly in water B1 Ensure maximum of 4 water, minimum 2 water banks men in water at any one time. Sufficient dive suits (dry bags/wetsuits) available for warmth. Vessel engines to be started/stopped only at the direction of nominated water banks man. Nominated water banks man to direct hoist down slip way and direct hoist operator to hoist/lower arms and auxiliary hoist as required. Safety boat on hand at all times. Buoyancy aid to be at hand. Operation to be stopped in excessive tidal stream. Poor visibility/blind Areas Vehicle marshalling, pedestrian access. A2 Marshal at entrances to and in compound, at point hoist crosses roadway and public footpath to stop traffic/pedestrians when hoist crossing. Unauthorised personnel not to be allowed in compound/on slipway. Boat owners/crews/block movers to remain in cordoned area until called forward by compound supervisor. Letters to be sent to vessel owners prior to launch identifying hazards. Also publish in club magazine and website. Warning signs/cones to be positioned at appropriate locations. Nominated banksman and marshals to wear high visibility clothing. Lifting load with personnel. A1 Ensure equipment maintained iaw manufacturer s guidelines. Ensure all Slinger/banksmen trained iaw with current legislation. Ensure hoist and associated equipment thoroughly examined 6 monthly and inspected prior to and during use. (iaw LOLER/PUWER regs) All crew to remain seated in cockpit whilst hoist underway. 4
5 Ergonomic constraints C2 Regular change of tractor driver to reduce neck/back fatigue. Regular relief for water banks man. Manual Lifting C1 Ensure sufficient numbers available to Move keel blocks, cradles and tenders. Tenders without bungs/ full of water to be emptied before movement. Responsibilities Method Statement Tudor Sailing Club will undertake the responsibilities for the operation of the tractor/hoist to ensuring it is maintained in accordance with the manufacturers guidelines and all statutory examinations are is completed and in date. Note: The appointed person/supervisor will ask to be shown this documentation prior to operations commencing. Personnel Tudor Sailing Club will provide the following personnel, complete with relevant personal protective equipment; the duties of these personnel will be defined in British Standards 7121: Title Name Title Name Appointed Person G Thomson Compound Banksman/Slinger(s) Chris Goodyear Andy Goodyear John Hamblin Richard Clark Andrew Lewis Lin Peek Slip way Supervisor Lin Peek Traffic Marshal Debbie Goodyear Hoist Supervisor G Thomson Frank Sharvil Tractor Driver/Hoist Operator Ian Smith Keith Prior Smith Safety Boat Richard Gunn + 1 Helm/crew Andy Goodyear Ian Silk + 1 Chris Goodyear Kevin Voucher Tony Lewis + 1 Water Taxi Helm/crew Water Banksman/ Neil Goodyear Slingers(s) Mark Brain Boat Crew Coordinator Linda Voucher Bill Jones Compound Supervisor G Thomson Note: The appointed person may decide that one person, can carry out more than one duty. 5
6 Weather conditions The appointed person, or in his absence, the hoist supervisor, will ensure that the lifting operation only takes place if the tidal and weather conditions are within the limits deemed safe to minimise any risk of injury to personnel or damage to a member s vessel or club equipment. Equipment inspection The Tractor driver/hoist operator must carry out visual inspections of the tractor engine and hydraulic oil/water levels. The hydraulic system and brakes should be tested before use. A visual inspection of the boat slings and auxiliary wires/hooks must be carried out by the supervisor in charge. The lifting accessories, as detailed previously, will be provided by Tudor Sailing Club complete with all statutory documentation. Sequence of operations (Launch) 1. Clear all obstructions around vessel to be lifted. 2. Ensure skipper of vessel is briefed and has sufficient crew onboard to allow for tidal and wind conditions. 3. Manoeuvre hoist alongside vessel to be lifted with arms at appropriate height and span to allow for vessel size, paying attention to hazards protruding from adjacent vessels. 4. Position forward sling in appropriate position according to vessel size/keel and hull shape using numbered lifting lugs and adjusting sling length accordingly. 5. Inch up on arms until slack taken up on forward sling. (Banksmen paying attention not To foul underwater fittings with sling, as identified by vessel skipper/owner. 6. Position aft sling ensuring clear of obstructions (shaft/sail drive/logs etc) at lifting point Advised by owner/skipper, or as deemed safe to lift. Hook on to auxiliary hooks with Sling length adjusted accordingly. (See note 3) 7. Raise auxiliary winches until slack taken up on aft sling. 8. Once load deemed safe to lift and all personnel clear, lift both arms on hoist until load At suitable height to allow rudder/keels to clear ground level between compound and water. Use auxiliary winches to level load before moving forwards. 9. Manoeuvre Tractor and hoist out of compound and across public highway to allow hoist to be reversed down slipway to launch position. 10. Reverse hoist and load down slipway into water until depth suitable to lower arms for 6
7 vessel to float. This part of the operation is assisted by banksmen situated in the water at waste height on either side of the slipway. 11. Once vessel is afloat, remove aft sling, ensure sling clear of Underwater obstructions and instruct Skipper to start engine. 12. Once skipper happy to do so, vessel is reversed out of hoist arms and clear. (Under instruction of nominated water banks man. ( See note 1) 13. Aft sling is hooked with both eyes on one auxiliary hook and hoist arms/auxiliary winched hoisted until slings clear of ground level. Proceed to compound for next vessel to be lifted as directed by banks man. Sequence of operations (Lift out) 1. Reverse hoist and load down slipway into water until depth suitable to receive vessel into hoist. (Hoist arms span to be pre set for vessel size/beam to be lifted). This part of the operation is assisted by banks men situated in the water at waste height on either side of the slipway. 2. Ensure skipper of vessel is briefed prior to embarking water taxi to mooring, and has sufficient crew onboard to allow for tidal and wind conditions. 3. The vessel to be lifted will be called using VHF radio or hand signals and instructed to approach the slipway/hoist at a speed suitable for tidal and wind conditions and manoeuvre the vessel into the hoist. The crew of the vessel will pull the vessel on to the forward/bow slings using the ropes attached to the hoist. The water banks man (See note 1) will carry out a visual check to ensure that the stern sling is in the correct position for lifting and this point will advise the owner/skipper to shut down the engine of the vessel. The water nominated banks man will signal the tractor driver/hoist operator to inch up on arms until slack taken up on forward sling. ( Water banks man paying particular attention not to foul underwater fittings with sling, as identified by vessel skipper/owner and vessel lifting marks) (See note 3) Raise auxiliary winches until slack taken up on aft sling. 4 5 Once load deemed safe to lift and all personnel clear, lift both arms on hoist until load At suitable height to allow rudder/keels to clear ground level between compound and water. Use auxiliary winches to level load before moving forwards. 6 Tractor and hoist moves forwards and back up the slipway, across public path and highway into compound where directed by the compound banks man for positioning the vessel to be laid up. The rig/hoist is brought to a standstill to allow the vessel owner/skipper to disembark in order to instruct the compound crew on how the vessel should be landed on blocks or cradle provided. (See note 2) 7 Proceed to slipway for next vessel to be lifted as directed by banks man. Notes: 7
8 1. Use of water banks man is only a requirement to speed up operations during periods of multiple lifts (Tudor launch and lift out weekends) The lifting and launching operation may be conducted without the assistance of water banks man in a slower and controlled method, but paying more attention to tidal and wind conditions. Positioning or removal of the aft sling must be done by vessel owner/skipper and crew in such a manner to avoid fowling under water obstructions (propeller/sail drive/log impellors etc). The tractor/hoist operator will lift on directions given by the vessel owner/skipper. It is the owner/skipper s responsibility to ensure the slings are in the correct position. Normal operations will then commence as per the sequence of operations above. 2. It is the responsibility of the owner/skipper to ensure that his vessel is resting correctly on the blocks/cradle that he/she provides. 3. It is the responsibility of the vessel owner to ensure that sling lifting positions are clearly marked on his/her vessel. 4. Emergency/individual lifts must only be conducted with the use of trained tractor/hoist operators. At least one trained slinger / banks man must be present to supervise the lifting operation. Marshalling of pedestrians and vehicles using the public pathway and highway must still be undertaken. The only exception is the lift may proceed without the use of water banks man as described in note 1 above. 5. During planned lift out and launch weekends a safety boat will be provided to assist vessels that may breakdown and require a tow to or from the hoist. In the event of this happening the slipway supervisor will co-ordinate such requirements on VHF and the water banksman/slingers will assist in positioning/removing the vessel to or from the hoist. 6. A water taxi will be provided on planned launch and recovery weekends to ferry crews to and from vessels to be lifted. The boat crew co-ordinator will liaise closely with the slipway and compound supervisors to ensure vessels have the required crews to meet current weather and tidal conditions. Boat crews are to be directed on and off the slipway/compound as directed by the relevant marshals. Appointed persons acceptance of Responsibilities Signed: I confirm that the lift(s) have been planned and will be carried out in accordance with British Standards 7121 and that I will accept responsibility for the preparation of this risk assessment and method statement. Date: Hoist Supervisors acceptance of Duties Signed: I confirm that I have been fully briefed on the contents of this Risk assessment and Method Statement and that I accept the duty of ensuring that the lift(s) will be carried out in accordance with the method and procedures set out in this document. Date: 8
Appointed person Note: It is recommended that you read the Supporting Information page before you read this factsheet.
Appointed person Note: It is recommended that you read the Supporting Information page before you read this factsheet. Planning and regulatory requirements (Regulatory requirements) The role or duties
More informationCPCS renewal test factsheet
CPCS renewal test factsheet Introduction to the CPCS renewal test The industry-led CPCS Management Committee has determined that key safety-related knowledge must be checked on each category prior to the
More informationFEDERATION OF PILING SPECIALISTS CODE OF INDUSTRY BEST PRACTICE LIFTING OPERATIONS AND LIFTING EQUIPMENT REGULATIONS 1998
FEDERATION OF PILING SPECIALISTS CODE OF INDUSTRY BEST PRACTICE LIFTING OPERATIONS AND LIFTING EQUIPMENT REGULATIONS 1998 CONTENTS 1. Introduction 2. Definitions and Statements 3. LOLER Considerations
More informationOn the Lee Tunnel project, some significant near misses involving cranes have occurred this year.
On the Lee Tunnel project, some significant near misses involving cranes have occurred this year. Experience has shown that lifting operations can be hazardous work activities if not properly planned.
More informationARM 6.4 R/V ARMSTRONG SMALL BOAT OPERATIONS
1. Purpose The purpose of this procedure is to set forth the standards for small boat operations and the qualifications for a small boat operator. These guidelines shall be used while operating the small
More informationBoat Hoist Operations Code of Practice and Guidance COP2
Boat Hoist Operations Code of Practice and Guidance COP2 Edition 2 January 2016 Contents Introduction... 2 Access... 2 Liability... 2 Notification of boat hoisting at La Collette yacht basin... 3 Responsibilities
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationBoat Lifting Operations Code of Practice and Guidance COP3
Boat Lifting Operations Code of Practice and Guidance COP3 Edition 2 January 2016 Contents Introduction... 4 Access... 4 Liability... 4 Responsibilities during boat lifting operations... 5 Preparation...
More informationSUBJECT: LIFTING OPERATIONS AND LIFTING EQUIPMENT (LOLER)
SUBJECT: LIFTING OPERATIONS AND LIFTING EQUIPMENT (LOLER) 1.0 INTRODUCTION The purpose of this procedure is to give direction on the responsibilities and requirements related to UK legislation covering
More informationSEMPEO SQA Unit Code H2CB 04 Preparing and Manoeuvring Armoured Fighting Vehicles (AFVs) for Maintenance and Transportation
Preparing and Manoeuvring Armoured Fighting Vehicles (AFVs) for Maintenance and Transportation Overview This NOS identifies the competencies you need to carry out preparation and manoeuvring activities
More informationStandard Operating Procedure
Standard Operating Procedure BOOMS Offshore RO-BOOM / Lamor HD boom Equipment description SOP intended for the use and deployment of Lamor HD 1300 and Desmi Ro-clean 1500 offshore boom. The boom reel holds
More informationThis guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy.
Guidance on Safe Use of Dalgety Bay Sailing Club Raft This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy. Where any items referred
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationSuitability of Work Equipment
These regulations came into effect on the 5th December 1998 and replace PUWER 1992. They cover almost all equipment used at work, including tool box tools such as hammers, knives etc. They also cover machinery
More informationWork Activity (e.g. Road Work): Work Location:.
Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting
More informationWORK PROGRAMME. Draft amended guidelines for simulated launching of free-fall lifeboats
E MARITIME SAFETY COMMITTEE 97th session Agenda item 19 MSC 97/INF.3 2 August 2016 ENGLISH ONLY WORK PROGRAMME Draft amended guidelines for simulated launching of free-fall lifeboats Submitted by the Marshall
More informationOperation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015
Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039 Name Date Signature Author Jarred Hearle 27/11/2015 Reviewed FMG Site Team 27/11/2015 ---------- Approved Geoff Selfe 27/11/2015
More informationPILOTAGE DIRECTIONS REVIEWED DECEMBER 2016
PILOTAGE DIRECTIONS REVIEWED DECEMBER 2016 REVISION LIST Revision No. Date Details Approved by: Original All sections 12 Dec 2013 First edition of C W Brand v1.0 Pilotage Directions Revision 2 all sections
More informationTravel-Lift Operating Procedure. To that end, we would like to introduce the following procedure for HMPC lifting operations.
Travel-Lift Operating Procedure The Board of Directors for the Holyrood Marina Park Corporation is responsible for the operation and development of the Holyrood Marina complex including the Marine Travel-Lift.
More informationRisk Assessment. Lower Thames Rowing Club. Risk Rating Likelihood = (1-5) Severity = (1-5) Risk Level = (H-M-L) L S RL. Residual Risk L S RL
Assessment Date: 6/06/13 Revision 1 31/05/13 Page 1 of 8 Rating Level = (H-M-L) General Rowing It is the responsibility of the Duty Officer to: Water ingress to craft Sinking Water Spray Drifting Capsizing
More informationPRO Lifting Operations
MS&L Procedure PRO-4.5-0001-1-06 Lifting Operations Document Owner: Bill Kruesi HSSE Manager - Asset Mgmt. Owen Quake ANZ Engineering Authority Approved By: Bill Kruesi HSSE Manager - Asset Mgmt. Control
More informationRISK ASSESSMENT -HEATS-
Honda RYA Youth RIB Championship 2018 RISK ASSESSMENT -HEATS- Issued by Royal Yachting Association October 2017 Page 1 of 12 Risk Assessment Event Summary Event Honda RYA Youth RIB Championship Organising
More informationAppendix 4C - Sample SWMS Trenching
Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :
More informationSOP GEN-007X Crane and Winch Operations
Page 1 of 7 SOP GEN-007X 1.0 Introduction 2.0 Responsibility 3.0 References 4.0 Training and Qualifications 5.0 Operational Inspections 6.0 Maintenance and Load Tests 7.0 Cranes 8.0 Winches 9.0 Mobile
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationReceipt By Jurong Port Representative -To be filled by Jurong Port Representative No Item Yes No Remark 1.
Part 1-General Information -To be filled up by the Applicant (Company Representative) Description of work / Type of Cargo Operation Location Max. Dimension of Cargo Heaviest Cargo Wt. Start Date / Time
More informationPort Sections Guide Section 01
s Guide 01 Cow Bay Marina Date 10/1/2016 Position (lat / lon) Minimum controlled water depth Chart datum Range of water densities Tidal range alongside Bottom type Dredging regime Distance pilot station
More informationEQUIPMENT. (See also: Management of Health & Safety (51); Fork Lift Trucks (32); Warehousing (87); Work Equipment (91))
& (See also: Management of Health & Safety (51); Fork Lift Trucks (32); Warehousing (87); Work Equipment (91)) INTRODUCTION & The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) came
More informationCode Of Practice For Towage Operations In The Port of St Helier (Towage Guidelines)
Code Of Practice For Towage Operations In The Port of St Helier (Towage Guidelines) This Code Covers The Use Of Tugs And Towage In The Port Of St Helier Page number Contents 2 Introduction 3 Communication
More informationStaff Contractors. Public. Staff Contractors
1. Vehicle movements In conjunction with the vehicle driver, venue management and the client, our staff should ensure the safe parking of vehicles for loading and unloading purposes. Depending upon circumstances
More informationWilkins Safety Group
H & S Guidance - Lifting Operations and Equipment Health and Safety Information (See also: Management of Health & Safety ; Fork Lift Trucks ; Warehousing ; Work Equipment ) INTRODUCTION The Lifting Operations
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationForth Ports Limited. Port of Dundee. Rig Move Guidelines
Forth Ports Limited Port of Dundee Contents 1 Introduction... 4 2 Pre-Arrival... 4 2.1 Planning Meetings... 4 2.2 Priority of Movements... 4 2.3 Confirmation/Cancellations... 5 2.4 Weather Parameters...
More informationLEVEL 2 CERTIFICATE OF COMPETENCE IN CHAINSAW AND RELATED OPERATIONS ASSESSMENT SCHEDULE
Registered Charity No. 1096429 STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7685 7300 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE IN CHAINSAW AND RELATED OPERATIONS
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationSKEL RICE 3 PEAKS SAILING INSTRUCTIONS
SKEL RICE 3 PEAKS SAILING INSTRUCTIONS 1. RULES 1.1 The organizing authority shall be the Royal Papua Yacht Club. The event will be governed by the current rules as defined by the International Sailing
More informationSEMAER2_41 Dismantling and removing aircraft access structures
Overview This unit identifies the competences you need to dismantle and remove aircraft access structures, in accordance with approved procedures. You will be required to dismantle and remove the access
More informationSAFETY MANAGEMENT PLAN - All divisions Updated January 2018
SAFETY MANAGEMENT PLAN - All divisions Updated January 2018 1. APPLICATION 1.1 This safety management plan applies only to vessels and crews participating in Cairns Yacht Club (CYC) sanctioned racing events
More informationLifting Operation & Lifting Equipment Procedure
SRSS Lifting Equipment Procedure 1. DOCUMENT CONTROL Management System Element Title SRSS SMS PROCEDURE Lifting Operation & Lifting Equipment Procedure SMS_HS_PR_033_ Version # & V1 10/08/2016 Lifting
More informationStanding Risk Assessment: HARBOUR, DINGHY PARK & SLIPWAYS ANNEX B TO Club HEALTH & SAFETY MANAGEMENT PLAN
Sheet 1 of 5 ANNEX B TO CLUB HEALTH & SAFETY MANAGEMENT PLAN Standing Risk Assessment: HARBOUR, DINGHY PARK & SLIPWAYS ANNEX B TO Club HEALTH & SAFETY MANAGEMENT PLAN L = Likelihood scale: 5 = High 3 =
More informationNOTIFICATION AND STANDARD EVENT PLANNING RISK ASSESSMENT GUIDANCE NOTE
GUIDANCE NOTES ON RISK ASSESSMENT FOR EVENTS IN HARBOUR AUTHORITY AREAS NOTIFICATION AND STANDARD EVENT PLANNING RISK ASSESSMENT GUIDANCE NOTE The DfT (Department for Transport) Port Marine Safety Code
More informationCranes and Hoists. Elevating Work Platforms ASSESSMENT
Cranes and Hoists Elevating Work Platforms ASSESSMENT Part 1 Part 2 Performance Oral/Written June 1995 Contents Page Assessor guidelines general guidelines for Schedule B i Part one Performance Assessment
More informationLIFTING PLAN PERMIT TO WORK RISK ASSESSMENT
Code of Practice on Safe Lifting Operations at Workplaces LIFTING PLAN PERMIT TO WORK RISK ASSESSMENT Yeo Kim Hock 13 th December 2012 Introduction-Objectives of Lifting Plan/ PTW/ RA Fundamental Contents-
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationMEWP - Boom Note: It is recommended that you read the Supporting Information page before you read this factsheet.
MEWP - Boom Note: It is recommended that you read the Supporting Information page before you read this factsheet. Preparation for work (Preparation) Boom-type mobile elevated work platforms, commonly known
More informationLifting Equipment Procedure. Committees / Group Date Consultation: Health and Safety Sub Committee Nov 2016
Title of Standard Operation Procedure: Lifting Equipment Procedure ocedure: Person(s) responsible for the Health and Safety Manager production of report e Reference Number: H&S Procedure 16 Version No:
More informationMethod Statement Author
Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd
More informationIPSWICH. Port Safety Notice
IPSWICH Port Safety Notice 19th October 2018 1 Associated British Ports Ipswich Port Safety Notice to Masters Introduction: This Port Safety Notice has been developed and communicated to provide general
More informationSEMFEW339 - SQA Unit Code H1WC 04 Slinging, lifting and moving materials and components
Slinging, lifting and moving materials and components Overview This unit identifies the competencies you need to move loads by slinging and lifting in accordance with approved procedures. You will be required
More informationA25/A26. MEWP Scissor and Boom
A25/A26 MEWP Scissor and Boom General safety information for CPCS technical test This is for guidance purposes only and does not relate directly to specific CPCS technical test questions. It should only
More informationDalgety Bay Sailing Club; Dinghy Launch Risk Assessment
A. Project Title: Launch /Recovery of Dinghies Prepared by D Adrain Risk Assess. No.: RA 21/11/11 Task/Activity: B. A. Club Member Others (state) C. Launching and recovering dinghies mounted on Launch
More informationRYA MAJOR YOUTH & JUNIOR EVENT SAFETY STANDARD OPERATING POLICY AND PROCEDURES
RYA MAJOR YOUTH & JUNIOR EVENT SAFETY STANDARD OPERATING POLICY AND PROCEDURES Index: 1. Introduction 2. Objectives 3. Overall organisational structure 4. Radio callsigns 5. Radio procedures 6. Safety
More informationProvider of Training for the Management & Supervision of Lifting Operations
Provider of Training for Management & Supervion of Lifting Operations James Baillie Training Ltd an independent training provider specialing in Bespoken training in safe management and planning of lifting
More informationDistrict Risk Assessment: Grass Sledging - Rhydd Covert Campsite
HAZARD OBSERVED RISK BEFORE CONTROL MEASURES PERSONS AT RISK CONTROL MEASURES COMMENTS ACTIONS Lifting weighted objects Muscle strain When lifting and carrying sledges to and from store room Leaders Storage
More informationThe Cruiser Fleet Handbook
The Cruiser Fleet Handbook Rutland Sailing Club Ltd Gibbett Lane Edith Weston Nr Oakham LE15 8HJ 01780 720292 www.rutlandsc.co.uk sailing@rutlandsc.co.uk Welcome To Rutland Sailing Club Cruiser Fleet Rutland
More informationHierarchy of Control. Regard must be had to. Identify all the steps / processes. (a) the severity of the hazard or risk in question;
AUSTRALIAN POWER BOAT ASSOCIATION OFFSHORE COUNCIL INC. OFFSHORE SUPERBOAT CHAMPIONSHIPS HERVEY BAY, 29 30 November 2014 RISK ASSESSMENT FORM General Guidelines Risk Assessment Process Test of Practicability
More informationClass B Accident Report. Tokerau & Kawau Kat Collision
Class B Accident Report Tokerau & Kawau Kat Collision At Auckland on 11 December 2004 REPORT NO: 04 3624 TOKERAU& KAWAU KAT COLLISION Whilst departing from the ferry terminal in Auckland, Tokerau collided
More informationEquipment Operation Procedures
Procedures Purpose It is the policy of this company to permit only trained and authorized personnel to operate construction equipment. These procedures are applicable to both daily operators, and those
More informationDALGETY BAY SAILING CLUB RIB SAFETY BOAT RISK ASSESSMENT
1 INTRODUCTION This safety protocol addresses the assessment of risks associated with use of RIB Safety Botas as part of any dinghy racing event. Some risks are inherent to boating, sailing and racing,
More informationVessel Code of Practice as ratified at the Annual General Meeting held 15 th September 2016 Manx Registered Charity No. 325
The Queens Award for Voluntary Service Vessel Code of Practice as ratified at the Annual General Meeting held 15 th September 2016 Manx Registered Charity No. 325 INDEX 1. Vessel standards 2. Use of the
More informationMarch 1999 Presentation on "Lifting Operations and Lifting Equipment Regulations 1998" by Chris Davies, HM Inspector, HSE Midlands Region.
March 1999 Presentation on "Lifting Operations and Lifting Equipment Regulations 1998" by Chris Davies, HM Inspector, HSE Midlands Region. Chris Davies started his presentation by reflecting on the development
More informationLifting & Hoisting Procedure
AL-Yamama Engineering Company HSSE Department (s) Lifting & Hoisting Contents 1. Objective Error! Bookmark not defined. 2. Scope 1 3. Risk domain and risk 1 4. Activity Responsibility Matrix 1 5. Related
More informationNEWARK ROWING CLUB HEAD December 1st 2018
NEWARK ROWING CLUB HEAD December 1st 2018 Event Safety Plan This safety plan addresses safety issues for the Newark Eights Head Race and separate Small Boats Head to be held on Saturday 1st December 2018.
More informationHealth, Safety and Welfare Policy
Health, Safety and Welfare Policy This Policy is prepared in accordance with section 2(3) the Health and Safety at work etc. Act 1974, with the intention of promoting a safe working environment that will,
More informationLEARNER GUIDE. Transporter Safety (TRO) PO Box 2026 Mountain Gate VIC 3156 p: ABN: RTO: 21396
LEARNER GUIDE Transporter Safety (TRO) PO Box 2026 Mountain Gate VIC 3156 p: 03 9763 5449 ABN: 37 106 951 900 RTO: 21396 ASSESSOR GUIDELINES GENERAL 1. Introduction 1.1 Scope As the Assessment Instruments
More informationOur commitment to safety
2 Our commitment to safety At South East Water, we have an absolute commitment to achieving and maintaining a safe and healthy workplace for our people, including our contractors and stakeholders which
More information05 Boat Handling. Captain
05 Boat Handling Competence (Skills) Knowledge, Understanding and Proficiency Level Required Boat handling theory and techniques Coxswain Crew RQ RQ Describe the forces acting on a vessel while manoeuvering
More informationB S Glass Ltd Safety procedures- outsourced Workplaces
B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission
More informationPROCEDURE. Revision: 1. Operative Date: 10/04/2018 Department: HSEC. Author: D Steel CONTENTS
Title: Lifting Equipment - Inspection and Maintenance PROCEDURE Procedure No: P314.420 Issue: 1 Revision: 1 Operative Date: 10/04/2018 Department: HSEC Sect./Classification: Safety/Gear & Equipment Author:
More informationJob Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)
Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process: Initiators of JSEAs are responsible for consulting the Project Supervisor,
More informationHAYLING ISLAND SAILING CLUB OPEN / CHAMPIONSHIP SAILING RISK ASSESSMENT
HAZARD SAILING RISKS LIKELI HOOD IMPACT RISK FACTOR CONTROL MEASURES Capsize and MOB Capsize resulting in sinking Injury as a result of collision or other accident Gear failure and damage to boat Persons
More informationMadras College Site Traffic Management Plan (South Street) August 2015 Reviewed / Updated August 2016, August 2017 (Next review due August 2018)
Madras College Site Traffic Management Plan (South Street) August 2015 Reviewed / Updated August 2016, August 2017 (Next review due August 2018) South Street, St. Andrews, KY16 9EJ Kilrymont Road, St.
More informationSafety Checklist for Events Held at Hillbrook
Safety Checklist for Events Held at Hillbrook Hazards/ Issues or Tasks 1. EVENT ACCESS AND EGRESS Entry / Exit areas are kept clear and accessible. For an evening event, that you have appropriate Lighting.
More informationUK Contractors Group Mobile Elevating Work Platforms Good Practice Toolkit June June 2015 Page 1 of 16
UK Contractors Group Mobile Elevating Work Platforms Good Practice Toolkit www.ukcg.org Page 1 of 16 Contents Foreword Reference Material Initial Considerations Planning and Preparation for MEWP Activities
More informationSECTION 11 ADVENTUROUS ACTIVITIES BOATING: SAILING
SECTION 11 ADVENTUROUS ACTIVITIES 11.11 BOATING: SAILING 11.11.1. ACTIVITY SCOPE This section relates to the use of small off-the-beach sailing dinghies to conduct sailing activities for members. An off-the-beach
More informationSAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030
SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George
More informationIsis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.
Isis Deployment TMS and Live Boating Inmartech08 Dave Turner Operations Co-ordinator TMS Operations Why Why do do we we have have aa TMS? TMS? ItIt was was deemed deemed an an essential essential part
More informationVessel Code of Practice
The Queens Award for Voluntary Service Vessel Code of Practice Manx Registered Charity No. 325 INDEX 1. Vessel standards 2. Use of the vessel 3. Crewing 4. Training 5. On-board procedure 6. Vessel expenditure
More informationPowerplay Paintball Brighouse Risk Assessment
Chemical Gas bottles Vehicles Physical Electricity Environment Machinery Powerplay Paintball Brighouse Risk Assessment Location Powerplay Paintball Wakefield and Brighouse Venues Carried out by: Steven
More informationWORK METHOD STATEMENT CARPET LAYING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationC Crane. Installation & Operation Manual. SWL 120kg. The Hansa CRANE ID#: Davit ISO/DIS June 2000 Sling AS Sept 2000
The Hansa C Crane CRANE ID#: Installation & Operation Manual Ideal for the safe and dignified transference of sailors with disabilities from a wharf to the boat. The crane is also suited to many other
More informationInstructions for Support Boat Duties
Instructions for Support Boat Duties You must attend the Race day and safety briefing in the committee room (usually at 8.30am) You should bring your own lifejacket with you as the club does not have any
More informationInstructions for Support Boat Duties
Instructions for Support Boat Duties You must attend the Race day and safety briefing in the committee room ( usually at 8.45am) You should bring your own lifejacket with you as the club does not have
More informationGulf Harbour Village Marina Licence of Berth Terms & Conditions
Gulf Harbour Village Marina Licence of Berth Terms & Conditions DEFINITIONS Agreement means the agreement entered into between the Berth Owner and the Berth Renter, to which these Terms and Conditions
More informationRisk Assessment for Shoring & Piling Operations
Reference No. STIG 0403 CPA Safety Guidance Risk Assessment for Shoring & Piling Operations 1. Introduction This safety guidance contains a generic list of possible hazards that may be present when planning
More informationDALGETY BAY SAILING CLUB RYA RTC RISK ASSESSMENT
This Risk Assessment is intended to cover routine training sessions at DBSC, involving the club s fleet of training boats. Responsibility: The overall responsibility for R.Y.A. Training is vested in Dalgety
More informationWater Rescue Boat Operation. Level: 3. Credit value: 6. Assessment criteria. Learning outcomes. The learner can: The learner will:
Title: Water Rescue Boat Operation Level: 3 Credit value: 6 Learning outcomes The learner will: 1 understand the role of the rescue boat operator 2. understand the personal protective, communications and
More informationANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY
E SUB-COMMITTEE ON STANDARDS OF TRAINING AND WATCHKEEPING 42nd session Agenda item 3 STW 42/13/2 25 October 2010 Original: ENGLISH ANY OTHER BUSINESS Guidelines for passenger ship tender operator Submitted
More informationBuggy Policy Document Date: 10 November 2017
Buggy Policy Document Date: 10 November 2017 Cavendish Golf Club recognises that it has a duty of care to the staff, members and guest users of the golf course. The topography and nature of the course
More informationOperate a bridge or gantry crane (remote operation only)
Operate a bridge or gantry crane (remote operation only) Code OHSCER210A Workplace Health and Safety Queensland is moving to a new learning and assessment system for certificates to work in prescribed
More informationEPA Vessel Safety during Response Operations
EPA Vessel Safety during Response Operations EPA Vessel Safety Manual EPA employees who operate Class A vessels under 45 feet in length, shall conform to the minimum qualifications; 1) Approval by the
More informationFATAL AND SEVERE RISK PROGRAM
FATAL AND SEVERE RISK PROGRAM LEADER SESSION FALL FROM HEIGHTS Only do the task if it can be done safely FALL FROM HEIGHTS OUR COMMITMENT LIFE SAVING BEHAVIOUR: I WILL ALWAYS USE ADEQUATE PROTECTION WHERE
More informationPORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL
PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL ABP Marine Operations & Tata Burdening Departments 2017 RESPONSIBILLITIES Tata Steel UK (TSUK) is the operator of the Port Talbot Harbour Bulk Terminal.
More informationTyne LDS and Tyne United SBH. 28 October Safety Plan draft as at (separate versions for LDS and SBH may be produced at next stage)
Tyne LDS and Tyne United SBH 28 October 2017 Safety Plan draft as at 14-07-17 (separate versions for LDS and SBH may be produced at next stage) This document should be read in conjunction with the event
More informationDalgety Bay Sailing Club; Raft Use Risk Assessment
A. Dalgety Bay Sailing Club; Raft Use Risk Assessment Project Title: Mooring Maintenance Prepared by D Adrain Risk Assess. No.: RA 21/03/10 Task/Activity: B. A. Club Member Others (state) C. Lifting, maintenance
More informationWork Permit Help Document For changes introduced in ShIPS Revision 7.1 (Released 11/12/2008)
Introduction Work Permit Help Document For changes introduced in ShIPS Revision 7.1 (Released 11/12/2008) The current ShIPS Revision 7.1 has introduced an automated work permit system which has the benefit
More informationLifting Operations and Lifting Equipment Regulations (LOLER) Policy. Version No. 2. Review: May 2019
Livewell Southwest Lifting Operations and Lifting Equipment Regulations (LOLER) Policy Version No. 2 Review: May 2019 Notice to staff using a paper copy of this guidance The policies and procedures page
More informationHealth & Safety Contractor rules
Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...
More informationWarning CABLE REPLACEMENT INSTRUCTIONS. Questions? - Call Telpro Inc. Customer Service at or
CABLE REPLACEMENT INSTRUCTIONS Warning Read and follow these warnings and the instructions that follow. Failure to do so could result in serious property damage and/or serious bodily injury. BEFORE operating
More informationSafety at Work. Rules for Staying Alive
Safety at Work Rules for Staying Alive Safety at Work Rules for Staying Alive Introduction The purpose of Dana Gas Rules For Staying Alive is to address the key causes of deaths in our industry. These
More information