The Common Project for Completion of Bubbler Condenser Qualification (Bohunice, Mochovce, Dukovany and Paks NPPs)

Size: px
Start display at page:

Download "The Common Project for Completion of Bubbler Condenser Qualification (Bohunice, Mochovce, Dukovany and Paks NPPs)"

Transcription

1 International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, The Common Project for Completion of Bubbler Condenser Qualification (Bohunice, Mochovce, Dukovany and Paks NPPs) Holubec Jaroslav and Baumeister Pavol Slovenské elektrárne a.s. NPP Mochovce Mochovce Slovak Republic 1 ORIGIN OF THE COMMON PROJECT 1.1 Background Intensive discussions within the OECD Support Group on "VVER Bubbler Condenser Containment Research Work" between 1991 and 1994 revealed the need for supplementary research work to achieve sufficient level of basic knowledge about BC behaviour in course of design based accidents (DBAs). In 1994 the European Commission (EC) asked for a complementary "Bubbler Condenser Qualification Feasibility Study". The Phare Project NUC was finished early in 1996 confirming the need for additional research in this field. The Feasibility Study formed the basis for the Bubbler Condenser Experimental Qualification Project (BCEQ) with two separate experimental activities to be executed within the frame of the PHARE/TACIS 2.13/95 project of the European Commission. During the nineties the IAEA has published a series of reports describing the background and characteristic design features of VVER-440/213 NPPs. In this context the mechanical strength of some existing BC containment systems was also reassessed. This work was undertaken to assist operators in the re-evaluation of the BC performance and to identify the need for supplementary experimental studies to better understand the specific problems of the BC. Separate IAEA working group reviewed BC operational indicators and certain possible problems of mechanical strength of BC structure during LB LOCA were identified. However sufficient documentation was not available for the IAEA, confirming that the BC structure is designed in such way that it could withstand pressure differences in the initial phase after an instantaneous rupture of primary circuit with discharge from both sides

2 403.2 In the IAEA document listing generic safety issues for VVER-440/213 reactors five generic containment related issues have been identified and ranked. These issues are : Containment 1 BC strength behaviour at maximum pressure difference possible under LOCA conditions. Containment 2 Bubbler Condenser thermal-dynamic behaviour Containment 3 Containment leak rates (containment tightness) Containment 4 Maximum pressure differences on walls between compartments of hermetic boxes. Containment 5 Peak pressure in containment and activation of sub-atmospheric pressure after coolant blow down. 1.2 PHARE/TACIS PH2.13/95 BCEQ Project Conclusions of PH 2.13/95 project Further analyses of the obtained results is recommended to study the - Non-uniformity in temperature distributions - Non-uniformity in the flow velocity distributions In summary it was stated: The tests and analyses present that the BC systems for Paks, Dukovany, Bohunice and Rovno NPPs are capable to withstand the induced loads and they are capable to keep their functions" (during whole period of the max DBA). The same conclusion was defined at analyses and tests containment Mochovce NPP by Siemens, SVUSS Řež, All-Rusian Thermal Engineering Institute Moscow and VUEZ Levice 1.3 OECD-NEA Bubbler Condenser Steering Group BC-SG Based on the OECD NEA initiative the BC-SG (Bubbler Condenser Steering Group) was established in December Its activities are arranged in form of project with the following main objective: To provide convincing proof that the V-213 type containment acts in compliance with the design in course of design basis accidents. To provide assistance in planning of new tests and in interpretation of their results. To provide qualified experimental results, which will serve as a base for validation by computational tools for the best estimate analyses. The Steering Group under the auspices of OECD NEA has been established in Paris in December 7 th, The Project PR/TS/17 The Project PR/TS/17 with the title "TSO Support to CEEC Nuclear Regulatory Authorities and their TSOs in the safety related evaluation of the VVER 440/213 Bubble Condenser Experimental Qualification" relates to the project TSO Phare SK/HU/CZ/TS/08 and it provides assessment of the Project PH 2.13/95 (BCEQ). It should provide assistance to state regulatory bodies in licensing. Its duration is 18 months and the project started in June 2002 and should be completed in September The main beneficiary in the Slovak Republic is the State Office for Nuclear Safety.

3 THE COMMON PROJEKT FOR COMPLETION OF BUBBLER CONDENSER QUALIFICATION (BOHUNICE, MOCHOVCE, DUKOVANY AND PAKS NPPS) 2.1 Origin of the common project The Atomic Question Group (AEQ) and relevant partners and the state regulatory bodies started discussion on problems concerning completion of Bubbler Condenser Qualification during the meeting of VVER Users Club at the beginning of The managements of four NPPs (Bohunice, Mochovce, Dukovany and Paks) decided on this meeting to perform together additional experiments at the experimental equipment EREC and to invite the national TSOs into supporting work. The Agreement among individual parties was developed for this reason. Meeting on the technical contents of this Agreement was held at Paks Nuclear Power Plant in August There was agreed to perform common additional experiments (in sense of the AQG requirement) as follows: 1. MSLB (Main Steam Line Break simulation) under conditions proposed originally in the PHARE Project (pressure 4.7 MPa, water level 500 mm, duration 1800 sec, simulated break location medium distance from the BC). 2. MBLOCA (Medium Break LOCA simulation) Size of the simulated break was proposed to be 200 mm, in order to prevent total water discharge from tray (pressure MPa, water level 500 mm, duration 1800 sec, simulated location of break as close as possible to BC). 3. SBLOCA (small break LOCA simulation according to the EREC test facility limitation). The necessary time for accident simulation was determined based on the pre-test calculations (pressure MPa, water level 500 mm, duration 3600 sec, simulated break location medium distance from the BC). The specific test conditions were elaborated during consultations with the national research institutes. The necessary administrative and professional issues were negotiated during the common meetings of involved NPP representatives at Paks NPP in August 23 rd, 2001 and in Pieštany in February 8 th, The entire project management was agreed on the following way. 2.2 Provision of project development and its implementation The agreed principles as well as the technical contents of Project provided base for definition of "Agreement on co-operation and implementation of additional tests at the EREC facility Electrogorsk and on development of report on bubbler condenser serviceability". Directors of Dukovany, Bohunice, Mochovce and Paks NPPs signed this agreement in April 25 th 2002.

4 The project management scheme and relation to BC-SG BC-SG (Steering International technical validation of project progress group) OECD-NEA Operating Officer Basic data negotiation in compliance to SG program COMMON PROJECT More detailed progress Leading group (LG) Project manager EDU - 1 vote Paks - 1 vote EBO and EMO - 1 vote Basic data approval Paks NPP contract Work management EREC Experiments according to contract MSLB, MB LOCA, SB LOCA supervision and support TG task definition Basic data processing Technical Group (TG) local contracts EBO, EMO, EDU and Paks Representatives Supporting organizations i Objectives and purpose of the " BC Qualification" National supporting organisations NRI ŘEŽ, SVUSS Praha, VÚJE, VEIKI The intention of the "Agreement on co-operation in preparation on Bubbler Condenser Function Capability" participants were to comply the EU requirements as well as requirements of individual national regulatory bodies in area of BC qualification through the way of mutual co-operation in common experiments, analyses and supporting activities. Participants agreed on that they will reach the above mentioned intention based on the contract between EREC company and with Paks NPP on implementation of tests with scenarios simulating MSLB and MB- and SB LOCA on the test facility built within the framework of the PHARE Project 2.13/95. Subsequently it was agreed to co-operate in development of a common Final Report. The technical support will be provided by the Technical Support organizations, which will compare and provide validation of applied computational codes through exchange of their results. The presentation provides summary of all identified facts about BC behaviour both from the analyses results of common experiments and the PH 2.13/95 Project conclusions. This report is developed with intention to use gathered information to proof the BC function capability for individual national regulatory bodies of participating countries. The conclusions and recommendations are determined also in order to be applied during the OECD NEA SG discussion and as the response to AQG recommendations.

5 DESCRIPTION OF THE BUBBLER CONDENSER SYSTEM 3.1 Brief description of the VVER 440/213 containment design The VVER 440/213 containment presents the 3 rd barrier against the release of radioactive fission products into environment. It consists of the following main parts: Steam Generator Compartment Corridor BC building with accident confinement shaft System of BC with air traps Ventilation systems Spray system The scheme of containment is shown in the Fig.3.1 Air traps R eactor hall Bubble condenser SG boxes reacto r c o rridor cavity door Fig. 3.1: VVER 440/213- Containment building with the Bubble Condenser The containment consists of hermetically sealed compartments, housing reactor equipment and the equipment of air-conditioning systems, spray system and a BC building, which is connected to hermetically sealed compartments by corridor. The BC building contains 12 staggered floors of passive condenser and air traps equipped with check valves. The gas volumes above the water level (beyond the water sealing) are connected to the air traps through dual check valves. There are four air traps to which uncondensed gases from containment are forced to flow - each connected to three floors of BC trays. Between the volume beyond water sealing and the shaft of bubble condenser there are two self-closing check valves on each floor whose function is to prevent a reverse flow of water from trays in case of small LOCA accident. 3.2 Course of maximum design accident in VVER 440/213 containment The BC system is operated only in accident conditions in conjunction with the loss of coolant of either primary or secondary circuit, resulting in pressure and temperature increase in the containment. It is put under operation automatically by the pressure difference arising

6 403.6 between hermetically sealed and retaining areas. Operation of BC is clearly passive. Details of BC building with several floors of trays are given Fig. 3.2 Principle of passive pressure reduction Passive reduction of the quick pressure increase in hermetically sealed areas at design basis accident is enabled by two basic functions of BC: a) steam condensation through the bubbling of steam in 12 floors of trays with water (2 ) b) capture and retention of air and uncondensed gases in four air traps (5) 1 Corridor 2 Bubble condenser shaft 3 Perforated protected wall 4 Gasroom 5 Perforated collectors 6 Lockable check valve DN Tray with water solution (H 3 BO 3 ) 8 Gap for inlet of steam-air mixture 9 Cap forming water seal 10 Check valve inlet protection duct 11 Dual check valve DN Damper device 13 Air trap Fig.3.2 Details of the part of containment bubble condenser system The BC is arranged in such way that the air-steam mixture is passed through the corridor to the BC where the flow is distributed in BC shaft (1) to individual floors and through the volumes between ceilings and bottoms of the floors the mixture enters in 1806

7 403.7 gap-cap water seals (2). After the expulsion of water column in the inlet cap of seals (3) the mixture bubbles through the water layer where steam condenses with transfer of part of its thermal energy and concurrently its volume is reduced significant by way. Air and uncondensed gases are then cumulated above water level and due to arising overpressure this mixture flows through the dual check valve DN 500 (4) to the air traps (5). The time history of the presented process is governed by the pressure difference arising between the BC shaft (1) and air traps (5). In case of design basis accident it means a very quick process (see graph in Fig.3.3.) with significant dynamic impacts of jet flows on all technological devices, as well as on the structure of BC and hermetically sealed area. Dynamic effects of steam-air mixture flow are at the inlet to BC captured by a special reflexive wall anchored to the bearing structure of BC trays and in this way to the reinforced concrete building. In the further course of the accident the pressures above water level (3) and in air traps (5) equalise while check valves DN 500 (4) automatically close retaining compressed air in trap chambers. The flow of hot water and steam from primary circuit continuously decreases and pressure in hermetically sealed area begins to fall due to steam condensation and heat transfer to the walls, also due to operation of an active spray system. Reverse pressure difference, when the pressure above water seal (2) is greater than the pressure in the BC shaft (1), causes a reverse water flow from trays to BC shaft. Water flows through the same path where the steam air mixture flowed up, along the ceiling of the lower floor, flows to the perforated collectors on the front wall of the BC and sprays the volume of shaft. This passive spraying causes a further reduction of pressure in hermetically sealed volumes. Spilled water from trays is collected on the bottom of the BC shaft and spontaneously flows through the corridor to the SG compartments. From this room the water is together with used spray and primary (secondary) leak water transferred to the emergency system pumps. Accidents with small release of coolant are similar but slower in course with lower achieved pressure. In order to prevent an undesirable reflux of water in case of small accident, there are two special check valves DN 250 on each floor (6) which allow pressure equalisation before and behind the water seal. These check valves are fitted with a special blocking system which, depending on pressure in the volume before the hydraulic seal, automatically locks or unlocks the valve. The blocking system is set to the value of 165 ± 5 kpa of absolute pressure. Above this value the valve is automatically locked and does not allow the pressures to equalise. If pressure in the shaft during an accident localisation does not exceed the limit value of 165 kpa the valves remain unlocked and, in case of pressure drop before water seal, the pressures before and behind the seal equalise thus water remains in trays. The presented passive function of BC system causes a spontaneous decrease of pressure in hermetically sealed areas with continuous cumulating of significant amount of released thermal energy. Full localisation of the accident is accomplished by active spraying of SG compartments which gradually reduces pressure in containment to the minimum value of 80 kpa (absolute) when the spray system is automatically switched off. A moderate vacuum in the sealed area will prevent the release of radioactive substances; the vacuum is maintained by controlled actuation of active spray systems.

8 403.8 P [kpa] Break of the MCP Safety margin in the containment pressure Spray system in operation and water back flow from the trays Spray stops Spray starts , P atm [100 kpa] 20 kpa 0 s 10 s 200s 15 min Fig.3.3 Pressure history in VVER 440/213 containment at maximum design accident 4 ASSESSMENT OF BC FUNCTIONALITY 4.1 Test facility and methodology description Short description of the EREC experimental facility BC V-213 The test facility BC V-213 (Fig. 4.1) has been designed and built-up specially for investigating thermal-hydraulic and fluid-structure interactions of the BC system under conditions typically expected during DBAs. It is located in a separate building and consists of the following main systems and components: a simplified room system simulating the hermetic compartment system of the Paks NPP containment upstream of the BC tower; a BC model consisting of 2x9 original sized gap-cap systems, corresponding side walls, bottom and ceiling parts with mechanical properties identical to the Paks Nuclear Power Plant and a corresponding air space above the BC water volume of the trays; an air trap connected to the aforementioned air volume by a check valve; an relief valve to the BC shaft and a spray system providing the simplified room system with spray water; a blow down system consisting of 5 interconnected pressure vessels, pipe systems and blow down nozzles to provide the necessary mass- and energy reservoir to simulate the anticipated DBA blow down rates at three different locations inside the compartments; the necessary auxiliary equipment including instrumentation and the data acquisition system.

9 Dead-end volume (V 0 ) 5 BC module (V 4 ) 2 SG box (break node, V 1 ) 6 Air trap (V 5 ) 3 SG box (V 2 ) 7 High pressure vessel system 4 BC shaft (V 3 ) 8 DN500 check valve Fig. 4.1 General view of the EREC test facility BC V-213 Other items characterising the test facility are: dimensioning of the blow down nozzle derived on the basis of the scale results of ATHLET calculations for the anticipated failure conditions of the reference NPP; preservation of the mechanical properties of the tray and the gap-cap systems, closely linked to the existing configuration of the Paks Nuclear Power Plant; preservation of scale characteristic main volumes and/or flow cross section areas of the prototype plant with limited modelling of the corridors between the steam generator boxes and the BC shaft; scaling factor 1/100 for the design of the test rig volumes and the necessary mass-and energy reservoirs to simulate the variety of DBA conditions Description of methodology followed during the test preparation and execution Scope of the analytical works performed A. Pre-test calculations Plant blow-down and containment calculations for a representative scenario These calculations have been performed to have basis for preparation of the test scenario and for comparison with the EREC pre test blow-down proposal. EREC TF blow-down For the EREC facility the blow down calculations of each specific case have been performed with ATHLET code to define the blow down rates and enthalpy in order to define and agreed initial and boundary conditions of each test to be as compliant as possible with the NPP scenario. The report made by EREC provided good background for these calculation

10 assessing the differences between he measured and calculated values of blow-down rates during the previous experiments. Plant containment calculations These calculations prior to the tests (also with proposed EREC data) have been done to have a basis for comparison and possible requirements to EREC to modify test conditions in order to keep representative ness and/or conservatism of the tests being prepared. Wide discussion was concentrated especially on MSLB test preparation, where several proposals have been treated to reach a technical consensus. EREC TF containment calculations It was appropriate to perform these calculations prior the tests, in order to be ready for the discrepancies caused by the modelling. B. Post-test calculations The goal was to perform additional validation of containment codes and provide both industry and regulators with well-validated codes serving as best estimate calculational tools for any type of LOCAs. 5 OVERALL CONCLUSIONS Bubbler condenser qualification has been performed in the following experimental and analytical projects: LBLOCA tests and post-test calculations performed in the PHARE Project PH 2.13/95, MSLB, MBLOCA and SBLOCA tests and post-test calculations sponsored by VVER utilities, Post-test calculations for the resolution of the open issues of LBLOCA tests, performed by VEIKI in In previous chapters we have reviewed the test results, post-test calculation results and NPP calculation predictions obtained in the projects. We have come to the following conclusions concerning main parameters of NPP containment during accidents (including LBLOCA): peak containment pressures are below the design value (0.25 MPa) with a safety margin, maximum pressure difference on the BC structure is below the limit (30 kpa) with a safety margin, temperature of the BC water is in the anticipated range, far below the saturation level with a safety margin, non-uniform temperature distributions in the BC do not lead to local maximum values that would deteriorate condensation of the steam, pressure oscillations with a capability for impairment of BC function would not occur. On this basis the appropriate operation of BC containment under accident conditions can be positively confirmed. Results of all tests should be used also for validation of codes applicability and for improvement of codes in modelling of phenomena which occur in BC.

11 403.11

Verification and validation of computer codes Exercise

Verification and validation of computer codes Exercise IAEA Safety Assessment Education and Training (SAET) Programme Joint ICTP- IAEA Essential Knowledge Workshop on Deterministic Safety Assessment and Engineering Aspects Important to Safety Verification

More information

Research Article Experimental Studies for the VVER-440/213 Bubble Condenser System for Kola NPP at the Integral Test Facility BC V-213

Research Article Experimental Studies for the VVER-440/213 Bubble Condenser System for Kola NPP at the Integral Test Facility BC V-213 Science and Technology of Nuclear Installations Volume 212, Article ID 275693, 2 pages doi:1.1155/212/275693 Research Article Experimental Studies for the VVER-44/213 Bubble Condenser System for Kola NPP

More information

SENSITIVITY ANALYSIS OF THE FIRST CIRCUIT OF COLD CHANNEL PIPELINE RUPTURE SIZE FOR WWER 440/270 REACTOR

SENSITIVITY ANALYSIS OF THE FIRST CIRCUIT OF COLD CHANNEL PIPELINE RUPTURE SIZE FOR WWER 440/270 REACTOR PROCEEDINGS OF THE YEREVAN STATE UNIVERSITY Physical and Mathematical Sciences 216, 2, p. 57 62 P h y s i c s SENSITIVITY ANALYSIS OF THE FIRST CIRCUIT OF COLD CHANNEL PIPELINE RUPTURE SIZE FOR WWER 44/27

More information

SIMULATION OF CONTAINMENT HYDROGEN CONTROL SYSTEM AT IGNALINA NPP

SIMULATION OF CONTAINMENT HYDROGEN CONTROL SYSTEM AT IGNALINA NPP SIMULATION OF CONTAINMENT HYDROGEN CONTROL SYSTEM AT IGNALINA NPP Egidijus Babilas, Egidijus Urbonavicius, Sigitas Rimkevicius Laboratory of Nuclear Installation Safety, Lithuanian Energy Institute 1.

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS. A high-capacity EBA system [CSVS] [main purge]

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS. A high-capacity EBA system [CSVS] [main purge] PAGE : 1 / 9 5. CONTAINMENT PURGE (EBA [CSVS]) The Reactor Building purge system comprises the following: A high-capacity EBA system [CSVS] [main purge] A low-capacity EBA system [CSVS] [mini-purge] 5.1.

More information

EXPERIMENTAL SUPPORT OF THE BLEED AND FEED ACCIDENT MANAGEMENT MEASURES FOR VVER-440/213 TYPE REACTORS

EXPERIMENTAL SUPPORT OF THE BLEED AND FEED ACCIDENT MANAGEMENT MEASURES FOR VVER-440/213 TYPE REACTORS International Conference Nuclear Energy for New Europe 22 Kranjska Gora, Slovenia, September 9-12, 22 www.drustvo-js.si/gora22 EXPERIMENTAL SUPPORT OF THE BLEED AND FEED ACCIDENT MANAGEMENT MEASURES FOR

More information

Level 2 PSA for the VVER 440/213 Dukovany Nuclear Power Plant

Level 2 PSA for the VVER 440/213 Dukovany Nuclear Power Plant Nuclear Nuclear Research Research Institute Řež plc Institute Řež plc Level 2 PSA for the VVER 440/213 Dukovany Nuclear Power Plant Jiří Dienstbier, Stanislav Husťák OECD International Workshop on Level-2

More information

Experimental Verification of Integrated Pressure Suppression Systems in Fusion Reactors at In-Vessel Loss-of -Coolant Events

Experimental Verification of Integrated Pressure Suppression Systems in Fusion Reactors at In-Vessel Loss-of -Coolant Events Experimental Verification of Integrated Pressure Suppression Systems in Fusion Reactors at In-Vessel Loss-of -Coolant Events K. Takase 1), H. Akimoto 1) 1) Japan Atomic Energy Research Institute (JAERI),

More information

1 SE/P-02. Experimental and Analytical Studies on Thermal-Hydraulic Performance of a Vacuum Vessel Pressure Suppression System in ITER

1 SE/P-02. Experimental and Analytical Studies on Thermal-Hydraulic Performance of a Vacuum Vessel Pressure Suppression System in ITER 1 SE/P-2 Experimental and Analytical Studies on Thermal-Hydraulic Performance of a Vacuum Vessel Pressure Suppression System in ITER K. Takase 1), H. Akimoto 1) 1) Japan Atomic Energy Research Institute,

More information

RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP

RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP Bulatom Conference 2010 Bulgarian Nuclear Energy National, Regional and World Energy Safety 9th -11th June 2010, Riviera complex, Varna Système

More information

HTR Systems and Components

HTR Systems and Components IAEA Course on HTR Technology Beijing, 22-26.October 2012 HTR Systems and Components Dr. Gerd Brinkmann Dieter Vanvor AREVA NP GMBH Henry-Dunant-Strasse 50 91058 Erlangen phone +49 9131 900 96840/95821

More information

Profile LFR-45 LIFUS5 ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy

Profile LFR-45 LIFUS5 ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy Profile LFR-45 LIFUS5 ITALY GENERAL INFORMATION NAME OF THE FACILITY ACRONYM COOLANT(S) OF THE FACILITY LOCATION (address): OPERATOR CONTACT PERSON (name, address, institute, function, telephone, email):

More information

Safety Analysis: Event Classification

Safety Analysis: Event Classification IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Safety Analysis: Event Classification Lecturer Lesson IV 1_2 Workshop Information IAEA Workshop City, Country XX - XX Month,

More information

CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION

CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION PAGE : 1 / 8 CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION SUB-CHAPTER 1.1 INTRODUCTION SUB-CHAPTER 1.2 GENERAL DESCRIPTION OF THE UNIT SUB-CHAPTER 1.3 COMPARISON WITH REACTORS

More information

Containment Structure Performance as Controlled by Penetrations and Extensions

Containment Structure Performance as Controlled by Penetrations and Extensions Containment Structure Performance as Controlled by Penetrations and Extensions Julia Milman 1) and Tarek S. Aziz 1) 1) CANDU Services Civil Engineering, Atomic Energy of Canada Limited, Mississauga, ON,

More information

NUMERICAL INVESTIGATION OF THE FLOW BEHAVIOUR IN A MODERN TRAFFIC TUNNEL IN CASE OF FIRE INCIDENT

NUMERICAL INVESTIGATION OF THE FLOW BEHAVIOUR IN A MODERN TRAFFIC TUNNEL IN CASE OF FIRE INCIDENT - 277 - NUMERICAL INVESTIGATION OF THE FLOW BEHAVIOUR IN A MODERN TRAFFIC TUNNEL IN CASE OF FIRE INCIDENT Iseler J., Heiser W. EAS GmbH, Karlsruhe, Germany ABSTRACT A numerical study of the flow behaviour

More information

Ing. JOZEF BALÁŽ Ph.D. and Ing MILAN CVAN CSc

Ing. JOZEF BALÁŽ Ph.D. and Ing MILAN CVAN CSc PROPOSAL, DESIGN, IMPLEMENTATION AND SAFETY DEMONSTRATION OF SEVERE ACCIDENT MANAGEMENT MEASURES AT VVER440 IN SLOVAKIA Ing. Jozef Baláž, Ph.D. VUJE a.s. Trnava, Slovakia Email: Jozef.Balaz@vuje.sk Ing.

More information

Safety and efficiency go hand in hand at MVM Paks NPP

Safety and efficiency go hand in hand at MVM Paks NPP International Forum Atomexpo 2018 Safety and efficiency go hand in hand at MVM Paks NPP József Elter MVM Paks Nuclear Power Plant Ltd. Hungary Start up Four of the VVER-440/V213 unit Power units up-rate

More information

V.H. Sanchez Espinoza and I. Gómez-García-Toraño

V.H. Sanchez Espinoza and I. Gómez-García-Toraño V.H. Sanchez Espinoza and I. Gómez-García-Toraño ANALYSIS OF PWR SEVERE ACCIDENT SEQUENCES INCLUDING MITIGATIVE MEASURES TO PREVENT OR DELAY THE FAILURE OF SAFETY BARRIERS WITH THE SEVERE ACCIDENT CODE

More information

Simulation of Experiment on Aerosol Behaviour at Severe Accident Conditions in the LACE Experimental Facility with the ASTEC CPA Code

Simulation of Experiment on Aerosol Behaviour at Severe Accident Conditions in the LACE Experimental Facility with the ASTEC CPA Code Simulation of on Aerosol Behaviour at Severe Accident Conditions in the LACE al Facility with the CPA Code Ivo Kljenak, Borut Mavko Jožef Stefan Institute Jamova 39, SI-1000 Ljubljana, Slovenia Ivo.Kljenak@ijs.si,

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS])

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS]) PAGE : 1 / 16 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS]) 7.0. SAFETY REQUIREMENTS 7.0.1. Safety functions The main functions of the EVU system [CHRS] are to limit the pressure inside the containment

More information

Discussion and guidance on the definition and qualification of porous loads

Discussion and guidance on the definition and qualification of porous loads SUMMARY Porous Loads requiring Sterilisation are often a Critical Control Point for the manufacture of Sterile products. Particularly Aseptically filled products. Regulatory guidance in this area is not

More information

DF1 and DF2 Diffusers

DF1 and DF2 Diffusers 1550650/4 IM-P155-07 ST Issue 4 and Diffusers Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning 5. Operation 6. Maintenance

More information

EMERGENCY CORE COOLING SYSTEM SIMPLIFICATION

EMERGENCY CORE COOLING SYSTEM SIMPLIFICATION EMERGENCY CORE COOLING SYSTEM SIMPLIFICATION XA9846601 R.S. HART Sheridan Park Research Community, Atomic Energy of Canada Ltd, Mississauga, Ontario D.B. RHODES Chalk River Laboratories, Atomic Energy

More information

Profile LFR-43 HELENA ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy

Profile LFR-43 HELENA ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy Profile LFR-43 HELENA ITALY GENERAL INFORMATION NAME OF THE FACILITY ACRONYM COOLANT(S) OF THE FACILITY LOCATION (address): OPERATOR CONTACT PERSON (name, address, institute, function, telephone, email):

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS 2. VOLUME AND CHEMICAL CONTROL (RCV [CVCS])

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS 2. VOLUME AND CHEMICAL CONTROL (RCV [CVCS]) PAGE : 1 / 16 2. VOLUME AND CHEMICAL CONTROL (RCV [CVCS]) 2.0. SAFETY REQUIREMENTS 2.0.1. Safety functions 2.0.1.1. Control of reactivity In normal operation, the RCV [CVCS] regulates and adjusts (jointly

More information

ASVAD THE SIMPLE ANSWER TO A SERIOUS PROBLEM. Automatic Safety Valve for Accumulator Depressurization. (p.p.)

ASVAD THE SIMPLE ANSWER TO A SERIOUS PROBLEM. Automatic Safety Valve for Accumulator Depressurization. (p.p.) ASVAD Automatic Safety Valve for Accumulator Depressurization (p.p.) THE SIMPLE ANSWER TO A SERIOUS PROBLEM International Experts Meeting on Strengthening Research and Development Effectiveness in the

More information

Pressure Systems Safety Regulation

Pressure Systems Safety Regulation Pressure Systems Safety Regulation Introduction This document informs Faculty of the key requirements of the UK and Chinese Pressure Systems Safety regulations. The aim of these regulations is to prevent

More information

The Nitrogen Threat. The simple answer to a serious problem. 1. Why nitrogen is a risky threat to our reactors? 2. Current strategies to deal with it.

The Nitrogen Threat. The simple answer to a serious problem. 1. Why nitrogen is a risky threat to our reactors? 2. Current strategies to deal with it. International Conference on Topical Issues in Nuclear Installation Safety: Safety Demonstration of Advanced Water Cooled Nuclear Power Plants. The simple answer to a serious problem Vienna. 6 9 June 2017

More information

Guidance on room integrity testing and its interpretation

Guidance on room integrity testing and its interpretation Guidance Note Guidance on room integrity testing and its interpretation Guidance on room integrity testing and its interpretation 1. SCOPE... 6 2. INTRODUCTION AND BACKGROUND... 6 2.1. DEVELOPMENT OF INTEGRITY

More information

Analysis of Pressure Rise During Internal Arc Faults in Switchgear

Analysis of Pressure Rise During Internal Arc Faults in Switchgear Analysis of Pressure Rise During Internal Arc Faults in Switchgear ASANUMA, Gaku ONCHI, Toshiyuki TOYAMA, Kentaro ABSTRACT Switchgear include devices that play an important role in operations such as electric

More information

SHUTDOWN SYSTEMS: SDS1 AND SDS2

SHUTDOWN SYSTEMS: SDS1 AND SDS2 Chapter 12 SHUTDOWN SYSTEMS: SDS1 AND SDS2 12.1 INTRODUCTION Up to this point we have looked with great details at the reactor regulating system. In order to better understand the overall design of a CANDU

More information

Spirax Compact FREME Flash Recovery Energy Management Equipment

Spirax Compact FREME Flash Recovery Energy Management Equipment IM-UK-cFREME UK Issue 1 Spirax Compact FREME Flash Recovery Energy Management Equipment Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information

This test shall be carried out on all vehicles equipped with open type traction batteries.

This test shall be carried out on all vehicles equipped with open type traction batteries. 5.4. Determination of hydrogen emissions page 1 RESS-6-15 5.4.1. This test shall be carried out on all vehicles equipped with open type traction batteries. 5.4.2. The test shall be conducted following

More information

Loss of Normal Feedwater Analysis by RELAP5/MOD3.3 in Support to Human Reliability Analysis

Loss of Normal Feedwater Analysis by RELAP5/MOD3.3 in Support to Human Reliability Analysis Loss of Normal Feedwater Analysis by RELAP5/MOD3.3 in Support to Human Reliability Analysis ABSTRACT Andrej Prošek, Borut Mavko Jožef Stefan Institute Jamova cesta 39, SI-1 Ljubljana, Slovenia Andrej.Prosek@ijs.si,

More information

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES

More information

TSS21 Sealed Thermostatic Steam Tracer Trap

TSS21 Sealed Thermostatic Steam Tracer Trap 1255050/4 IM-P125-10 ST Issue 4 TSS21 Sealed Thermostatic Steam Tracer Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

Dri-Line Mk3 Monnier Compressed Air Drain Trap

Dri-Line Mk3 Monnier Compressed Air Drain Trap 5044050/2 IM-P504-24 CH Issue 2 Dri-Line Mk3 Monnier Compressed Air Drain Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation and Operation

More information

AIRFLOW GENERATION IN A TUNNEL USING A SACCARDO VENTILATION SYSTEM AGAINST THE BUOYANCY EFFECT PRODUCED BY A FIRE

AIRFLOW GENERATION IN A TUNNEL USING A SACCARDO VENTILATION SYSTEM AGAINST THE BUOYANCY EFFECT PRODUCED BY A FIRE - 247 - AIRFLOW GENERATION IN A TUNNEL USING A SACCARDO VENTILATION SYSTEM AGAINST THE BUOYANCY EFFECT PRODUCED BY A FIRE J D Castro a, C W Pope a and R D Matthews b a Mott MacDonald Ltd, St Anne House,

More information

Helium Loop Karlsruhe (HELOKA) large experimental facility for the in-vessel ITER and DEMO components

Helium Loop Karlsruhe (HELOKA) large experimental facility for the in-vessel ITER and DEMO components 1 /7-12 Helium Loop Karlsruhe (HELOKA) large experimental facility for the in-vessel IER and DEMO components M. Ionescu-Bujor, B.E. Ghidersa, G. Janeschitz, X. Jin orschungszentrum Karlsruhe, Germany e-mail:

More information

CFD SIMULATIONS OF GAS DISPERSION IN VENTILATED ROOMS

CFD SIMULATIONS OF GAS DISPERSION IN VENTILATED ROOMS CFD SIMULATIONS OF GAS DISPERSION IN VENTILATED ROOMS T. Gélain, C. Prévost Institut de Radioprotection et de Sûreté Nucléaire (IRSN), Saclay, France Abstract In order to better understand the risks due

More information

REWIEW OF THE METHODS USED FOR LEAK RATE MEASUREMENTS FOR WWER-440/230 CONFINEMENTS AND WWER-440/213 CONTAINMENTS

REWIEW OF THE METHODS USED FOR LEAK RATE MEASUREMENTS FOR WWER-440/230 CONFINEMENTS AND WWER-440/213 CONTAINMENTS IAEAEBPWWER10 XA9949244 REWIEW OF THE METHODS USED FOR LEAK RATE MEASUREMENTS FOR WWER440/230 CONFINEMENTS AND WWER440/213 CONTAINMENTS A PUBLICATION OF THE EXTRABUDGETARY PROGRAMME ON THE SAFETY OF WWER

More information

ASSIGNMENT 2 CHE 3473

ASSIGNMENT 2 CHE 3473 DUE: May 21 ASSIGNMENT 2 CHE 3473 #Problem 1 Read Chapter 3. ALL OF IT. Time yourself and report the time. #Problem 2: 3.2 #Problem 3: 3.3 #Problem 4: 3.5 #Problem 5: 3.6 #Problem 6: 3.7 #Problem 7: 3.8

More information

Transient Analyses In Relief Systems

Transient Analyses In Relief Systems Transient Analyses In Relief Systems Dirk Deboer, Brady Haneman and Quoc-Khanh Tran Kaiser Engineers Pty Ltd ABSTRACT Analyses of pressure relief systems are concerned with transient process disturbances

More information

Release: 1. UEPOPL002A Licence to operate a reciprocating steam engine

Release: 1. UEPOPL002A Licence to operate a reciprocating steam engine Release: 1 UEPOPL002A Licence to operate a reciprocating steam engine UEPOPL002A Licence to operate a reciprocating steam engine Modification History Not applicable. Unit Descriptor Unit Descriptor 1)

More information

MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap

MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap 1250650/6 IM-P125-07 ST Issue 6 MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation

More information

S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators

S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators 0231150/8 IM-P023-55 ST Issue 8 S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

Spiratec ST14, ST16 and ST17 Sensor Chambers and sensors

Spiratec ST14, ST16 and ST17 Sensor Chambers and sensors 0862050/1 IM-P086-18 MI Issue 1 Spiratec ST14, ST16 and ST17 Sensor Chambers and sensors Installation and Maintenance Instructions 1. Safety Information 2. General product information 3. Installation 4.

More information

IAEA SAFETY STANDARDS for protecting people and the environment

IAEA SAFETY STANDARDS for protecting people and the environment Date: 2016-08-31 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: STEP 8a For Submission to Member States DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS

More information

Preliminary Failure Mode and Effect Analysis for CH HCSB TBM

Preliminary Failure Mode and Effect Analysis for CH HCSB TBM Preliminary Failure Mode and Effect Analysis for CH HCSB TBM Presented by: Chen Zhi Contributors by HCSB TBM Safety Group, in China June 21, 2007 E-mail: chenz@swip.ac.cn Outline Introduction FMEA Main

More information

CAST IRON SAFETY VALVE TYPE 6301

CAST IRON SAFETY VALVE TYPE 6301 CHARACTERISTICS The 6301 safety valve is dedicated to protect the equipment from potential overpressure. This is an automatic device that closes when the pressure conditions are back to normal. It is a

More information

Modelling of the Separated Geothermal Water Flow between Te Mihi flash plants

Modelling of the Separated Geothermal Water Flow between Te Mihi flash plants Proceedings World Geothermal Congress 2015 Melbourne, Australia, 19-25 April 2015 Modelling of the Separated Geothermal Water Flow between Te Mihi flash plants Kevin Koorey, Kim Harwood and Norman Lawgun

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Risk assessment study of the mutual interactive influence of working procedures on terminals handling dangerous goods in port of Koper (Slovenia) L. Battelino Water Management Institute, Maritime Engineering

More information

KBV21i and KBV40i Key Operated Boiler Blowdown Valves Installation and Maintenance Instructions

KBV21i and KBV40i Key Operated Boiler Blowdown Valves Installation and Maintenance Instructions 4059051/3 IM-P405-48 EMM Issue 3 KBV21i and KBV40i Key Operated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information

IAEA SAFETY STANDARDS for protecting people and the environment

IAEA SAFETY STANDARDS for protecting people and the environment IAEA SAFETY STANDARDS for protecting people and the environment DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS DRAFT SAFETY GUIDE DS 482 STATUS: STEP 11 Submission to Review

More information

POP Safety Valve. POP Safety Valve INTRODUCTION DEFINITIONS

POP Safety Valve. POP Safety Valve INTRODUCTION DEFINITIONS POP Safety Valve POP Safety Valve INTRODUCTION The effects of exceeding safe pressure levels in an unprotected pressure vessel or system, can have catastrophic effects on both plant and personnel. Safety

More information

S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators Installation and Maintenance Instructions

S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators Installation and Maintenance Instructions PREVIOUS REFERENCE NO. IMP02355 0231150/13 IMF0501ENISS2 CMGT S1, S2, S3, S5, S6, S7, S8, S12 and S13 Separators Installation and Maintenance Instructions 1. Safety information 2. General product information

More information

ASSIGNMENT 2 CHE 3473

ASSIGNMENT 2 CHE 3473 DUE: May 23 ASSIGNMENT 2 CHE 3473 #Problem 1: 3.3 #Problem 2: 3.4 #Problem 3: 3.5 #Problem 4: 3.6 #Problem 5: 3.7 #Problem 6: 3.8 #Problem 7: 3.11 #Problem 8: 3.15 #Problem 9: 3.22 #Problem 10: 3.32 #Problem

More information

THE WAY THE VENTURI AND ORIFICES WORK

THE WAY THE VENTURI AND ORIFICES WORK Manual M000 rev0 03/00 THE WAY THE VENTURI AND ORIFICES WORK CHAPTER All industrial combustion systems are made up of 3 main parts: ) The mixer which mixes fuel gas with combustion air in the correct ratio

More information

New Findings for the Application of Systems for Explosion- Isolation with Explosion Venting

New Findings for the Application of Systems for Explosion- Isolation with Explosion Venting 529 A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 48, 2016 Guest Editors: Eddy de Rademaeker, Peter Schmelzer Copyright 2016, AIDIC Servizi S.r.l., ISBN 978-88-95608-39-6; ISSN 2283-9216 The

More information

Official Journal of the European Union L 92/3

Official Journal of the European Union L 92/3 3.4.2008 Official Journal of the European Union L 92/3 COMMISSION REGULATION (EC) No 303/2008 of 2 April 2008 establishing, pursuant to Regulation (EC) No 842/2006 of the European Parliament and of the

More information

ZIN Technologies PHi Engineering Support. PHi-RPT CFD Analysis of Large Bubble Mixing. June 26, 2006

ZIN Technologies PHi Engineering Support. PHi-RPT CFD Analysis of Large Bubble Mixing. June 26, 2006 ZIN Technologies PHi Engineering Support PHi-RPT-0002 CFD Analysis of Large Bubble Mixing Proprietary ZIN Technologies, Inc. For nearly five decades, ZIN Technologies has provided integrated products and

More information

European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire

European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire Safety Task Force SC, BE, EN, PH, TE, Staff Ass. [CERN-ATS-2009-002] External Advisory Committee [CERN-ATS-2009-003]

More information

PV4 and PV6 Piston Valves

PV4 and PV6 Piston Valves 1181250/1 IM-P118-05 ST Issue 1 PV4 and PV6 Piston Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning 5. Operation 6.

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER P: REFERENCE OPERATING CONDITION STUDIES (PCC)

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER P: REFERENCE OPERATING CONDITION STUDIES (PCC) PAGE : 1 / 11 1. PASSIVE SINGLE FAILURE ANALYSIS The aim of the accident analysis in Chapter P is to demonstrate that the safety objectives have been fully achieved, despite the most adverse single failure.

More information

LESER Deutschland Standard Functional Tightness Test (Cryo) Content

LESER Deutschland Standard Functional Tightness Test (Cryo) Content Page 1/10 Content 1 Purpose... 1 2 Scope... 1 3 Range of Application... 1 4 Normative Background... 2 5 Terms and Definitions... 2 6 Test Equipment... 3 7 Test Procedure... 5 8 Acceptance Criteria... 8

More information

THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS

THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS J.E. HARBER, M.K. KATTAN Atomic Energy of Canada Limited 2251 Speakman Drive, Mississauga, Ont., L5K 1B2 CA9900006 and M.J. MACBETH Institute for

More information

UKEPR Issue 04

UKEPR Issue 04 Title: PCSR Sub-chapter 6.8 Main steam relief train system - VDA [MSRT] Total number of pages: 16 Page No.: I / III Chapter Pilot: M. LACHAISE Name/Initials Date 25-06-2012 Approved for EDF by: A. PETIT

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

BT6HC Hygienic Sanitary Balanced Pressure Steam Trap for High Capacity and CIP/SIP Applications

BT6HC Hygienic Sanitary Balanced Pressure Steam Trap for High Capacity and CIP/SIP Applications 1800350/6 IM-P180-12 ST Issue 6 BT6HC Hygienic Sanitary Balanced Pressure Steam Trap for High Capacity and CIP/SIP Applications Installation and Maintenance Instructions 1. Safety information 2. General

More information

An Investigation of Liquid Injection in Refrigeration Screw Compressors

An Investigation of Liquid Injection in Refrigeration Screw Compressors An Investigation of Liquid Injection in Refrigeration Screw Compressors Nikola Stosic, Ahmed Kovacevic and Ian K. Smith Centre for Positive Displacement Compressor Technology, City University, London EC1V

More information

Requirements for the Ethylene MACT

Requirements for the Ethylene MACT Requirements for the Ethylene MACT Fugitive Emissions 40 CFR Part 63 Subpart UU 63.1019-63.1039 TX Technology Showcase Houston, Texas March 18, 2003 Bruce C. Davis DuPont Engineering Technology 1 Presentation

More information

SAFETY DEMONSTRATION TESTS ON HTR-10

SAFETY DEMONSTRATION TESTS ON HTR-10 2nd International Topical Meeting on HIGH TEMPERATURE REACTOR TECHNOLOGY Beijing, CHINA,, September 22-24, 24 #Paper H6 SAFETY DEMONSTRATION TESTS ON HTR-1 Shouyin HU, Ruipian WANG, Zuying GAO Institute

More information

1.2 Example 1: A simple hydraulic system

1.2 Example 1: A simple hydraulic system Note: It is possible to use more than one fluid in the Hydraulic library. This is important because you can model combined cooling and lubrication systems of a library. The hydraulic library assumes a

More information

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants the pressure equipment safety authority Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants AB-528 Edition 2, Revision 1 Issued 2016-09-12 Table of

More information

Courses of Instruction: Controlling and Monitoring of Pipelines

Courses of Instruction: Controlling and Monitoring of Pipelines Courses of Instruction: Controlling and Monitoring of Pipelines Date December 2010 Dr. Peter Eschenbacher Partner Angergraben 4 85250 Altomünster Germany Tel. +49-(0)8254 / 99 69 57 Fax +49-(0)8254 / 99

More information

HANDBOOK SAFETY DEVICES. Ed SAFETY DEVICES DS-ED 01/ ENG 1

HANDBOOK SAFETY DEVICES. Ed SAFETY DEVICES DS-ED 01/ ENG 1 HANDBOOK Ed. 2017 DS-ED 01/2017 - ENG 1 2 DS-ED 01/2017 - ENG INDEX CHAPTER 1 Safety valves in series 3030 CHAPTER 2 Safety valves in series 3060 CHAPTER 3 Safety valves in series 3061 CHAPTER 4 Safety

More information

Exercise 4-2. Centrifugal Pumps EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Pumps

Exercise 4-2. Centrifugal Pumps EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Pumps Exercise 4-2 Centrifugal Pumps EXERCISE OBJECTIVE Familiarize yourself with the basics of liquid pumps, specifically with the basics of centrifugal pumps. DISCUSSION OUTLINE The Discussion of this exercise

More information

M-06 Nitrogen Generator (Nitrogen Making Machine)

M-06 Nitrogen Generator (Nitrogen Making Machine) Guideline No.M-06 (201510) M-06 Nitrogen Generator (Nitrogen Making Machine) Issued date: 20 th October, 2015 China Classification Society Foreword This Guideline is a part of CCS Rules, which contains

More information

Effects of Delayed RCP Trip during SBLOCA in PWR

Effects of Delayed RCP Trip during SBLOCA in PWR Effects of Delayed RCP Trip during SBLOCA in PWR Javier Montero Technical University of Madrid, Alenza 4, 28003, Madrid, Spain fj.montero@alumnos.upm.es Cesar Queral, Juan Gonzalez-Cadelo cesar.queral@upm.es,

More information

Pore-Air Entrapment during Infiltration

Pore-Air Entrapment during Infiltration Pore-Air Entrapment during Infiltration GEO-SLOPE International Ltd. www.geo-slope.com 1200, 700-6th Ave SW, Calgary, AB, Canada T2P 0T8 Main: +1 403 269 2002 Fax: +1 888 463 2239 Introduction Infiltration

More information

Leaks from Unit-3 PCV and steam release in a large amount

Leaks from Unit-3 PCV and steam release in a large amount Attachment 3-8 Leaks from Unit-3 PCV and steam release in a large amount 1. Background At Unit-3 the suppression chamber (S/C) vent line configuration was completed at 08:41 on March 13 th and the dry

More information

Enhancing NPP Safety through an Effective Dependability Management

Enhancing NPP Safety through an Effective Dependability Management Prepared and presented by Gheorghe VIERU, PhD Senior Scientific Nuclear Security Research Worker AREN/c.o. Institute for Nuclear Research Pitesti, ROMANIA Safety: Defence in Depth, October 2013 1 OUTLINES

More information

Lockout/Tagout Safety Policy

Lockout/Tagout Safety Policy University of North Carolina Wilmington Environmental Health & Safety Workplace Safety Lockout/Tagout Safety Policy GENERAL The UNCW Environmental Health & Safety Department (EH&S) is authorized by UNCW

More information

44 (0) E:

44 (0) E: FluidFlow Relief Valve Sizing Handbook Flite Software 2016 Flite Software N.I. Ltd, Block E, Balliniska Business Park, Springtown Rd, Derry, BT48 0LY, N. Ireland. T: 44 (0) 2871 279227 E: sales@fluidflowinfo.com

More information

The Discussion of this exercise covers the following points: Pumps Basic operation of a liquid pump Types of liquid pumps The centrifugal pump.

The Discussion of this exercise covers the following points: Pumps Basic operation of a liquid pump Types of liquid pumps The centrifugal pump. Exercise 2-3 Centrifugal Pumps EXERCISE OBJECTIVE In this exercise, you will become familiar with the operation of a centrifugal pump and read its performance chart. You will also observe the effect that

More information

Fig 12, Fig 14HP, Fig 16, Fig 16HP and Fig 16L Strainers

Fig 12, Fig 14HP, Fig 16, Fig 16HP and Fig 16L Strainers 16355/11 IM-S6-17 ST Issue 11 Fig 12, Fig 14HP, Fig 16, Fig 16HP and Fig 16L Strainers Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information

QuickHeat TM Packaged Heat Exchanger Solutions

QuickHeat TM Packaged Heat Exchanger Solutions 4831999/1 IM-P483-03 CH Issue 1 QuickHeat TM Packaged Heat Exchanger Solutions Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

GUIDE YVL 3.7 / 26 Se p t e m b e r 2008

GUIDE YVL 3.7 / 26 Se p t e m b e r 2008 GUIDE YVL 3.7 / 26 Se p t e m b e r 2008 Pressure equipment of nuclear facilities Commissioning inspection 1 Ge n e r a l 3 2 Contents of the commissioning inspection 3 3 First phase of the commissioning

More information

Committee on NFPA 85

Committee on NFPA 85 Committee on NFPA 85 M E M O R A N D U M TO: FROM: NFPA Technical Committee on Heat Recovery Steam Generators Jeanne Moreau DATE: April 23, 2010 SUBJECT: NFPA 85 F10 ROC Letter Ballot The ROC letter ballot

More information

A17W23_MASE_MUS_EN MANUAL

A17W23_MASE_MUS_EN MANUAL A1W2_MASE_MUS_EN MANUAL CONTENTS 1 Identification 1.1 Manufacturer 1.2 Product name 1. Year of manufacture 1. Area of use 2 Technical specification 2.1 Design 2.2 Function 2. Technical data 2. Security

More information

HM and HM34 Inverted Bucket Steam Traps Installation and Maintenance Instructions

HM and HM34 Inverted Bucket Steam Traps Installation and Maintenance Instructions 0670350/4 IM-S03-11 ST Issue 4 HM and HM34 Inverted Bucket Steam Traps Installation and Maintenance Instructions 1. Safety information 2. General product information HM Series 3. Installation 4. Commissioning

More information

The benefits of system solutions for valve users

The benefits of system solutions for valve users 1/16 The benefits of system solutions for valve users 1. Introduction 2. System types 2.1. Pressure control 2.2. Temperature control 3. Technical process design 3.1. Checking of operating data 3.2. Selection

More information

A18W35_MASE 130_F_EN MANUAL

A18W35_MASE 130_F_EN MANUAL A18W_MASE 10_F_EN MANUAL CONTENTS 1 Identification 1.1 Manufacturer 1.2 Product name 1. Year of manufacture 1. Area of use 2 Technical specification 2.1 Design 2.2 Function 2. Technical data 2. Security

More information

A Rationale for Pressure Relief Device(s) Qualification Requirements (LH2)

A Rationale for Pressure Relief Device(s) Qualification Requirements (LH2) UN-GTR PART A INSERTION Stand 09.02.2011, 17:20 Uhr A.3.3 HYDROGEN STORAGE SYSTEM The hydrogen storage system consists of all components that form the primary pressure boundary of the stored hydrogen in

More information

KBV21i and KBV40i Air Actuated Boiler Blowdown Valves

KBV21i and KBV40i Air Actuated Boiler Blowdown Valves 4059051/1 IM-P405-48 AB Issue 1 KBV21i and KBV40i Air Actuated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

ISOLATION ISSUE 2 1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 3 7 SYSTEM & PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

ISOLATION ISSUE 2 1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 3 7 SYSTEM & PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 CONTENTS PAGE 1 AIM 2 2 APPLICATION 2 3 DEFINITIONS 2 4 REASONS FOR INCLUSION 3 5 REQUIREMENTS 3 6 PLANT AND EQUIPMENT REQUIREMENTS 3 7 SYSTEM & PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 APPENDIX

More information

NUBIKI Nuclear Safety Research Institute, Budapest, Hungary

NUBIKI Nuclear Safety Research Institute, Budapest, Hungary System Reliability Analysis and Probabilistic Safety Assessment to Support the Design of a New Containment Cooling System for Severe Accident Management at NPP Paks Tamas Siklossy* a, Attila Bareith a,

More information

Assessment of Internal Hazards

Assessment of Internal Hazards Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste, 12-23 October 2015 Assessment of Internal Hazards Javier Yllera Department

More information

HANDBOOK SAFETY DEVICES. Ed SAFETY DEVICES DS-ED 01/ ENG 1

HANDBOOK SAFETY DEVICES. Ed SAFETY DEVICES DS-ED 01/ ENG 1 HANDBOOK Ed. 2017 DS-ED 01/2017 - ENG 1 CHAPTER 9 BURSTING DISC DEVICES IN SERIES 3070 SCOPE Use: protection against possible overpressure of the apparatuses listed below, with regard to the operating

More information