FISH PROPAGATION 2014 ANNUAL REPORT

Size: px
Start display at page:

Download "FISH PROPAGATION 2014 ANNUAL REPORT"

Transcription

1 SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2014 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2014 DECEMBER 31, 2014 BAKER RIVER HYDROELECTRIC PROJECT FERC No November 2015 PUGET SOUND ENERGY Baker River Hydroelectric Project

2 CONTENTS CONTENTS 1.0 Executive Summary Introduction Principal Management Activities Design and Planning Activities Documents Submitted Accounting Funding Expenditures Adjustments Supporting Documents References PUGET SOUND ENERGY Baker River Hydroelectric Project Page ii

3 List of Tables List of Tables Table 1. Fish Co-Managers preseason sockeye beach loading plan and actual beach loading, Table sockeye salmon beach loading records by data source (WDFW, PSE) and difference Table 3. Salmon production from Baker fish propagation facilities, February 1, 2014 to May 31, Table 4. Sockeye broodstock and fry production from Baker fish propagation facilities, plus subsequent smolts counted for each brood year from 1999 through Table 5. Salmon releases from Baker River fish propagation facilities, Table 6. Salmon rearing inventory at fish propagation facilities as of December 31, Table 7. Funds allocated to nutrient enhancement account, (years one to three) List of Figures Figure 1. Baker fish hatchery site layout Figure 2. Baker fish hatchery constructed facilities Figure 3. Baker Fish Hatchery and improved Spawning Beach 4 during operation Figure 4. Spawning Beach Figure 5. The hatchery A.I. holding facilities contained 4,101 adult sockeye in 2014, and are capable of holding up to 6,000 broodstock Figure 6. Yearly sockeye artificial incubation program Figure 7. Yearly number of sockeye fry released into the reservoirs from Baker fish propagation programs, brood years (release years ) Figure 8. Juvenile fish rearing facilities in use for sockeye and coho salmon and rainbow trout Figure 9. Average fork length for Baker Lake age 1 sockeye smolts ( ) Figure 10. Average condition factor (K) for Baker Lake age 1 sockeye smolts ( ) Figure 11. Five LWD structures were installed in the main channel alignment during July and August 2013 to help maintain pond hydrology Figure 12. Demolition of Spawning Beach 3 (upper). Surface and sub-surface infrastructure removed and hauled offsite for disposal (lower) Figure 13. All site facilities removed Figure LWD modifications to improve function included installing liners on the upstream end and notches Figure LWD modifications included adding a roughen channel between LWD structures 4 and Figure re-vegetation and mulch around the LWD structures Figure re-vegetation and mulch along the former access road and along the floodplain swale Figure 18. Mulch placement along the LWD structures Figure 19. Photos taken at completion in December 2014, following a site walk with the USDA-FS Figure 20. Spawning Beaches 1, 2, and 3 before decommissioning Figure 21. Conditions at completion of decommissioning (April 18, 2013 design), showing infrastructure removed, site regrading, large woody debris structures in the channel alignment, and an overflow swale PUGET SOUND ENERGY Baker River Hydroelectric Project Page iii

4 1.0 Executive Summary This annual report reviews activities undertaken by Puget Sound Energy (PSE) in 2014 to implement settlement agreement article 101, Fish Propagation (SA 101) of the Order on Offer of Settlement, Issuing New License and Dismissing Amendment Application as Moot (the license) issued by the Federal Energy Regulatory Commission (FERC) on October 17, 2008 for the Baker River Hydroelectric Project. The report covers the SA 101 reporting period of January 1 through December 31, 2014, as outlined in the revised aquatics reporting schedule submitted to the FERC on September 11, 2014, and approved by the FERC on January 16, It has been prepared in consistence with SA 102, Aquatics Reporting, and SA 101. SA 101 implementation measures during the reporting period of January 1, 2014 through December 31, 2014 included: Continuing to implement the Fish Propagation Facilities Plan in accordance with the plan s schedule. Completing the decommissioning of the site of Sockeye Spawning Beaches 1, 2, and 3 based on the Channel Creek Site Decommissioning Plan (December 2012); and required modifications outlined in the final USFS construction punch list. Funding and operating fish propagation and enhancement programs for 2014 in the new Baker fish hatchery and Sockeye Spawning Beach 4, including achieving a combined production of 6.59 million fry, the highest in 56 years of production from Baker facilities, and exceeding the goal of 6 million. Approximately 4.76 million sockeye fry were from the fourth brood year operation of the new hatchery, and 1.83 million were from the operation of the improved Spawning Beach 4. Performance of these facilities increased sockeye fry production more than two-fold from levels prior to In June, the hatchery and spawning beach began fifth brood year operation by receiving 2014 adult sockeye. Planning long term surface erosion protection measures at the Sulphur Springs water supply intake (hatchery headworks). Interim surface erosion control measures are currently protecting the hatchery headwork repairs completed in Convening a fry release site technical working group to identify options related to the number of usable release sites. Developing a draft memorandum regarding procedures to be followed in managing the reservoir nutrient enhancement funding requirement per SA 101(f). Continuing a study approach in collaboration with the ARG for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits. PSE provided a summary of results to the ARG from 2014 adult and smolt data collection efforts. 2.0 Introduction This Fish Propagation Report has been prepared for the Baker River Hydroelectric Project (the Project), pursuant to the Order on Offer of Settlement, Issuing New License and Dismissing Amendment Application as Moot dated October 17, 2008 (the license). In the PUGET SOUND ENERGY Baker River Hydroelectric Project Page 1

5 license, settlement agreement article (SA) 101, Fish Propagation (appendix A), sets forth the applicable requirements for the Fish Propagation Facilities Plan (the Plan), which in turn sets forth the requirements of this annual report. This annual report summarizes the activities conducted under SA 101 from January 1, 2014 through December 31, 2014, including management activities, monitoring, design and planning, surveys and data collection activities, consultation, documents prepared, modifications to or deviations from the Plan, issues and resolution, accounting, and purposed changes to the FERC-approved Plan. This report provides the ongoing format for future reports Principal Management Activities Principal activities during the 2014 reporting period (January 1, 2014 through December 31, 2014) included the following (which are described in greater detail in sections through 3.1.5): Continuing to implement the Fish Propagation Facilities Plan (PSE, 2009a) approved by the FERC on May 26, Completing the decommissioning of the site of Sockeye Spawning Beaches 1, 2 and 3 based on a Channel Creek Site Decommissioning Plan (December 2012), after receiving documentation confirming USDA-FS approval ( Notice to Proceed ) of the final design plan dated April 18, 2013 and providing construction updates to the USDA-FS and ARG. The USDA-FS provided a punch list of required construction modifications and concurred with a schedule extension allowing completion of the decommissioning, per the plan and required modifications outlined in the final USFS construction punch list, by December Operating the newly-constructed Baker fish hatchery for the fourth year, releasing 3.78 million sockeye fry to Baker Lake and 1.95 million sockeye fry to Lake Shannon, and retaining 374,000 fry for the 20,000-pound production rearing program. Continuing the existing propagation and enhancement programs. The Fish Comanagers (the Sauk-Suiattle Indian Tribe, Swinomish Indian Tribal Community, Upper Skagit Indian Tribe, and Washington Department of Fish and Wildlife) increased the 20,000-pound production program s rearing goal for sockeye, but left the goals for coho and rainbow trout production unchanged. Allocated to this extended rearing program were approximately 374,000 sockeye, 65,000 coho, and 20,000 rainbow trout fry. Rearing and release objectives were achieved during the reporting period. Planning long-term erosion control measures at the Sulphur springs water supply intake in consultation with the USDA-FS and WDFW. Interim measures installed by PSE to reduce surface erosion in the construction area, has provided protection to the hatchery headwork water supply repairs completed in Consulting with the Washington Department of Fish and Wildlife (WDFW) on fish propagation plans, hatchery operation protocols, and the continuing PSE funding of fish propagation/enhancement programs and an onsite manager. In response to the Fish Co-manager s policy on fry release sites, the Fish Co-managers and PSE PUGET SOUND ENERGY Baker River Hydroelectric Project Page 2

6 convened a Fry Release Site Technical Working Group to identify options and establish a path forward that all can support. The Fish Co-managers and PSE have also exchanged letters to clarify their positions regarding the Fish Co-managers request that PSE purchase and install a water chiller system at the Baker fish hatchery. Developing a draft memorandum regarding procedures to be followed in managing the reservoir nutrient enhancement funding requirement in SA 101(f), including fund requests, fund disbursement, and annual reporting, as well as a mechanism for returning unspent funds to the Habitat Enhancement, Restoration, and Conservation fund. The draft memorandum is being prepared for review by the Fish Co-managers. Continuing a study approach in collaboration with the ARG for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits. PSE provided a summary of results to the ARG in December 2014 from the year s adult and smolt data collection efforts Fish Propagation Facilities Plan Per SA 101, PSE is implementing the Fish Propagation Facilities Plan (FPFP) which FERC approved on May 26, The FPFP directs PSE to include information on a variety of programs and facilities in its annual SA 101 reports. A short update on each such project listed in the FPFP appears below. Sockeye Spawning Beach 4. Construction completion has been documented, as discussed in the 2011 annual report. A Baker Fish Hatchery Renovation Final Project Completion Report dated October 5, 2012, including as-built drawings, was provided to the FERC within 12 months following completion of the Baker fish hatchery renovation. The facility is operating. Section contains a summary. Baker fish hatchery facility. Construction completion has been documented. The Baker Fish Hatchery Renovation Final Project Completion Report mentioned above covers the hatchery facility at Sulphur Springs. The facility is operating. Section contains a summary. Sockeye smolt capacity. This study was completed during the 2010 reporting period. The final study report, including ARG comments and recommendations, was provided to the ARG and included with the 2010 annual report for SA 101. Empirically-derived sockeye production estimate. Following collaboration with the ARG, PSE implemented a study approach in April 2013 for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits. PSE developed the study approach in collaboration with the ARG to identify the number, type, and frequency of adult and smolt data collection efforts. PSE collects juvenile sockeye size information at the juvenile downstream fish passage facilities. PSE presented results of the empirical monitoring data from 2014, both numerical and morphological. Section includes an update. Sockeye Spawning Beach 4 production limits. PSE maintains an enumeration system in Spawning Beach 4. A feasible enumeration system is necessary to evaluate production. As PSE implements the fish propagation program as directed by the Fish Co-managers, and the settlement agreement directs that population enhancement for sockeye will be sequential, production optimization testing will thus PUGET SOUND ENERGY Baker River Hydroelectric Project Page 3

7 commence on a schedule to be determined in consultation with the ARG, and specifically the Fish Co-managers. At the September 2013 ARG meeting, PSE requested that the Fish Co-managers consider approaches to loading one or more spawning beach sections when setting annual broodstock goals, as a means of testing the facility s upper limits. The Fish Co-managers meet annually to establish production goals. Sockeye production has increased gradually at the hatchery, and has remained unchanged at the spawning beach. Spawning Beaches 1 3 (Channel Creek site). The decommissioning project per the plan and required modifications outlined in the final USFS construction punch list was completed by the end of A decommissioning plan, documentation confirming U.S. Forest Service approval of the decommissioning plan, and interim progress updates was provided in the 2013 SA 101 annual report, and progress updates made subsequently until completion of Channel Creek site decommissioning activities. PSE submitted a Channel Creek Site Decommissioning Plan in December The USDA-FS approved the final design plan dated April 18, 2013 (in their Notice to Proceed dated May 29, 2013). Project construction began on July 16, 2013 in accordance to plans. Interim progress updates were provided to the ARG throughout construction. Decommissioning was completed in December 2014, including the required modifications outlined in the final USFS construction punch list. Section provides an update. Confirmation of annual PSE funding of the Fish Propagation and Enhancement Program and the annual fish production plan. The Fish Co- Managers will provide PSE with an annual fish production plan. Following completion of the Baker fish hatchery renovation, PSE requested that the Fish Co- Managers provide the annual fish production plan to PSE annually by September 30 to accommodate the PSE budget, reporting processes, and timeline requirements. PSE funded the fish propagation and enhancement program during the reporting period. The Fish Co-managers are continuing to work on a draft annual plan and progress updates have been provided at the quarterly ARG meetings. Sufficient production planning information in lieu of a plan document was provided throughout the reporting period to successfully implement the fish production programs. The Fish Co-Managers provided PSE with a plan to achieve a production goal of 6 million fry. The Fish Co-managers increased the 20,000-pound production program s sockeye rearing goal from previous years while continuing the status quo for coho and rainbow trout production. Allocated to this extended rearing program were approximately 374,000 sockeye (an increase from 130,000, primarily for fall releases), 65,000 coho, and 20,000 rainbow trout fry. The WDFW informed PSE of sockeye fry distribution plans for the resulting 2014 brood year production of sockeye, directing 4.65 million fry into Baker Lake and 2 million into Lake Shannon and retaining 350,000 for extended rearing and fall parr release into Baker Lake (Baker River Co-Managers, 2014). PSE and the Fish Co-managers convened a technical working group to examine the number of usable sockeye fry release locations, identify options, and establish a and a path forward to resolve the issues that has led to the Fish Co-manager s policy on fry release sites. PSE responded to the Fish Co-managers request that PSE purchase and install a water chiller system at the Baker fish hatchery. Section presents the results of the fish propagation PUGET SOUND ENERGY Baker River Hydroelectric Project Page 4

8 programs and discusses the Fish Co-manager requests, and section 4.2 describes expenditures during the reporting period. Annual confirmation of PSE funding of the Reservoir Nutrient Enhancement Program. Funding, which is not to exceed $60,000 annually, was placed into a PSE account for disbursements available to the Fish Co-managers. The use of funds will be at the discretion of the Fish Co-managers. The process to disburse funds was initiated in PSE met with the Fish Co-managers (the Washington Department of Fisheries, Swinomish Indian Tribal Community, Sauk-Suiattle Indian Tribe, and Upper Skagit Indian Tribe) to discuss a mechanism for distributing the fund. During this reporting period, the Fish Co-managers and PSE have been developing a draft memorandum regarding the procedures to be followed in connection with managing the fund. Section includes an update. Funding is scheduled for license years Funding activity during the reporting period is reported in section 4.1. Fish facility operations manual for the Sulphur Springs site. Operations procedures, including abnormal operation and maintenance procedures in accordance to PSE standards, were developed during completion of the Baker fish hatchery renovation. PSE and the Baker fish hatchery design and construction contractor, McMillen-McDougall, prepared the procedures for inclusion in the updated manual replacing the April 2009 manual completed for the previous fish culture facilities. The new procedures are in use now for the operation and maintenance of Spawning Beach 4 and the new hatchery. Living as an electronic file collection, the operations manual provides access to procedures for operations, maintenance and emergency response from the Baker Plant and hatchery and easy navigation to facility layout, descriptions and drawings, emergency, physical and biological operations, security and maintenance procedures, and makes future updates readily available. Annual contract and budgeting report governing operation of fisheries enhancement programs. This will report the annual budget and actual costs. WDFW is under a PSE contract, whereby PSE funds an onsite manager for operations. Expenditures from the WDFW contract during the reporting period are reported in section 4.2. Fish propagation facilities operations audit. Results of the fish propagation facilities and program are discussed in section and provide an audit of the annual facilities and programs based on a January 1 to December 31 operating year. The audit will address financial accounting, fish handling and disease management operations, hazardous materials handling, and spill prevention, control, and countermeasures (SPCC) compliance. PSE, per the FERC license, developed an SPCC plan for the project. This plan was submitted to the FERC, and compliance is mandatory. At the time of this report, there have been no incidents. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 5

9 3.1.2 SA 101 A & B Sockeye Spawning Beach 4 and Baker Fish Hatchery PSE completed the construction of new fish culture facilities and modification of Spawning Beach 4 at Sulphur Springs by December 31, 2011, based upon the Baker Fish Hatchery Renovation 100% Final Design Documentation Report (McMillen, 2009). Final project completion is documented in the 2011 annual report. A Baker Fish Hatchery Renovation Final Project Completion Report (PSE, 2012a) dated October 5, 2012, including as-built drawings, was provided to the FERC within 12 months following completion of the Baker Fish Hatchery renovation. The facilities are now in their 4 th operating year. Figures 1, 2, and 3 show the Baker fish hatchery site layout and the completed facilities in operation. Figure 1. Baker fish hatchery site layout. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 6

10 Figure 2. Baker fish hatchery constructed facilities. Clockwise from top left: egg incubation, adult holding and fry transfer hoppers, outdoor rearing, early rearing. Figure 3. Baker Fish Hatchery and improved Spawning Beach 4 during operation Fish Propagation /Enhancement Programs This section presents the results of the fish propagation programs during The information and results also represent an audit of the existing propagation and enhancement program. The audit describes the results of biological, operational, and maintenance efforts related to fish propagation and enhancement facilities and programs, and indicates whether the program goals were met for the January 1, 2014 to December 31, 2014 operating year. The audit summarizes the production results of the sockeye spawning beach and artificial propagation facilities, as well as the production results of the coho supplementation and rainbow trout enhancement programs. The information reported includes: PUGET SOUND ENERGY Baker River Hydroelectric Project Page 7

11 Sockeye and coho fry production numbers. A discussion of disease management and results. Remedial responses to protect the water supply headworks from a naturally occurring landslide. Reporting related to adult returns, facility loading, production totals, and release numbers for juvenile sockeye, coho, and the other fish propagation and enhancement programs for rainbow trout. The current fish production program at the Baker River Project is directed by the Fish Co-Managers and is a combination of sockeye, coho, and rainbow trout production. The program continues the previous propagation and enhancement programs established by PSE with the WDFW, the Upper Skagit Indian Tribe, the Sauk-Suiattle Indian Tribe, and the Swinomish Indian Tribal Community, the USFWS, NOAA Fisheries, and the USDA-FS except that these programs are now contained in an improved sockeye spawning beach and the newly-constructed Baker River fish hatchery, and will enable the continued sequential development of population enhancement for sockeye and a 20,000- pound-capacity production program made up of any one or any combination of several species. Program updates, directives, and changes are provided by the Fish Co-Managers and reviewed at scheduled ARG meetings. Fish propagation and enhancement program funding and operations in the new hatchery and improved Spawning Beach 4 during 2014 were based on a production goal of 6 million sockeye fry and a juvenile rearing goal of 330,000 sockeye, 60,000 coho, and 20,000 rainbow trout. In April 2014, the Fish Co-managers initiated a steelhead research program based on a single brood year. The program designates a brood of up to eight Skagit winter steelhead, follows the brood through their release as 2-year-old smolts. The experimental program is an initial exploratory research activity expected to operate for two years; its goal is to inform future consideration regarding restoration of the Baker River steelhead run Sockeye Salmon Spawning Beaches Spawning Beach 4, completed in 1990 to replace the aging, isolated, and vulnerable Beaches 2 and 3, is operated as four isolated compartments (A, B, C, and D) to reduce and contain outbreaks of infectious hematopoietic necrosis (IHN), a viral disease endemic to sockeye populations. The WDFW provides on-site management of Spawning Beach 4, with support from PSE in the form of funds and personnel. The improved Spawning Beach 4 operated for the third year during this reporting period, as the modifications required by SA 101 had been completed. These modifications included an isolated water supply, concrete barriers for compartment isolation, a new pond liner, outlet structure improvements, and cranes and concrete pads for carcass removal and better access. If the IHN virus is detected above the threshold level for any one of the compartments during routine testing, a chlorination treatment system is activated and a protocol to stop collection of fry in that segment is triggered at the direction of the Fish Co-managers. The fry emerging from the infected compartment are terminated, and effluent is diverted PUGET SOUND ENERGY Baker River Hydroelectric Project Page 8

12 to the chlorination treatment system in accordance with the disease management protocol developed by the Fish Co-Managers for the facility. The disease management protocol is a set of agreements on how to determine when to stop taking fry from a beach section. This protocol has been in place for the past 16 years, and is revised annually as more is learned about the disease. During this reporting period, viral sampling of adult fish indicated that IHN virus was present in sockeye that returned to the Baker system in the fall of 2013, and detected IHN virus in adult fish placed in Spawning Beach 4 and in the artificial incubation adult holding ponds. The containment features of the Spawning Beach and hatchery, and operational procedures for disease management and biosecurity procedures worked to contain and limit infection episodes. Winter/spring (2014) viral sampling of fry produced from both these facilities confirmed that IHN was not present in fry produced from Spawning Beach 4. Surplus adult sockeye salmon may be released into Baker Lake for spawning in the upper Baker River and its tributaries. Spawning Beach 3 operated periodically as an unattended production facility until replacement production was provided from the new Baker fish hatchery at Sulphur Springs. When it did operate, Spawning Beach 3 usually required pumping to supplement the gravity water supply. PSE provided support in the form of equipment and personnel at the request of the WDFW. The site of Spawning Beaches 1, 2, and 3 was decommissioned as a requirement of SA 101. The decommissioning project was initiated in June 2013; Spawning Beaches 1, 2, and 3 were dismantled, and the site was returned to a natural condition Sockeye Adult Returns (2014 Brood Year) Each year, the Fish Co-Managers based the spawning beach loading goals and artificial incubation (AI) program goals on the predicted sockeye run size and ideal loading conditions. Spawning density goals help maximize production and manage for disease. It should be noted that the WDFW directs the facility s fish propagation program objectives on behalf of the Fish Co-Managers. In 2014, the plan called for holding up to 2,201 adult sockeye in Spawning Beach 4, and 4,101 sockeye as brood stock for the artificial incubation (AI) program. A total of 14,176 sockeye returned to the Baker River adult trap during The return exceeded the Fish Co-Managers 2014 allocation for the fish propagation facilities, so 7,207 sockeye were placed into Baker Lake, while 622 were allocated to tribal ceremonial and subsistence. A distribution methodology developed by the Fish Co-Managers allocated fish between Spawning Beach 4, the artificial incubation program, lake release, and tribal ceremonial and subsistence fishing based on representative portions of the expected run timing. Beach 4 was seeded with a total of 2,196 fish. Artificial incubation raceways were seeded with a total of 4,101 fish. Combined, the facilities were seeded with a total of 6,297 fish. The loading plan and actual loading count are reported in table 1. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 9

13 Figure 4. Spawning Beach 4. The beach was loaded with 2,196 adult sockeye in 2014, and is capable of holding over 3,400. Figure 5. The hatchery A.I. holding facilities contained 4,101 adult sockeye in 2014, and are capable of holding up to 6,000 broodstock. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 10

14 Table 1. Fish Co-Managers preseason sockeye beach loading plan and actual beach loading, Number of Adults Location/Program Loading Plan based on Pre-season Forecast Actual Loading based on Available Returns Spawning Beach 4, Section A Spawning Beach 4, Section B Spawning Beach 4, Section C Spawning Beach 4, Section D Artificial Incubation Program, Raceway 1 1,025 1,025 Artificial Incubation Program, Raceway 2 1,025 1,025 Artificial Incubation Program, Raceway 3 1,025 1,025 Artificial Incubation Program, Raceway 4 1,026 1,026 Total 6,302 6,297 a See subsequent sections for discussion of sockeye returns, hauling totals, and numbers based on WDFW carcass counts. Table 2 summarizes the WDFW carcass count according to beach and PSE hauling counts. The WDFW reported a lower carcass count (2,036) for the spawning beaches and total stocking density compared to PSE hauling records (table 2). PSE records indicate that 2,196 sockeye were delivered to the spawning beaches. The total difference between the WDFW carcass count and the PSE hauling count for Beach 4 is -160 fish. Discrepancies between WDFW records of total carcass counts and PSE hauling counts can be attributed to human error (recording error, counting other salmonids such as steelhead) and removal by predators/scavengers. The WDFW spawning beach carcass count is summarized in table female and 915 male carcasses were counted. An additional 234 unspawned females were counted, bringing the total carcass count at Beach 4 to 2,036. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 11

15 Table sockeye salmon beach loading records by data source (WDFW, PSE) and difference. WDFW Carcass Count Record PSE Hauling Count Difference (WDFW-PSE) a Beach 4A Females 240 Females n/a Males 231 Males n/a Unspawned Females 48 Unspawned Females n/a Total 519 Total Beach 4B Females 217 Females n/a Males 229 Males n/a Unspawned Females 61 Unspawned Females n/a Total 507 Total Beach 4C Females 227 Females n/a Males 227 Males n/a Unspawned Females 62 Unspawned Females n/a Total 516 Total Beach 4D Females 203 Females n/a Males 228 Males n/a Unspawned Females 63 Unspawned Females n/a Total 494 Total Combined Beach 4 Females 887 Females n/a Males 915 Males n/a Unspawned Females 234 Unspawned Females n/a Total 2,036 Total 2, Sum of Beach 4 2,036 Sum of Beach 4 2, a Carcass counts are considered more reliable data and are therefore utilized for management calculations such as estimation of egg production at the beaches Sockeye Artificial Incubation Program This hatchery program, which as a pilot program had produced 1 million fry annually in temporary incubation facilities, has now expanded to the newly-constructed fish culture facilities as phase 1 in SA 101. The facilities will enable the sequential development of additional population enhancement for sockeye up to the capacity for 7 million fry annually, and will provide added protection in the event of losses from infectious hematopoietic necrosis (IHN). The combined 2014 production (2013 brood year) for the spawning beach and the artificial incubation facility resulted in more than 6 million fry, including 330,000 fry reserved for a delayed-release experiment in the hatchery. The combined 2015 fry PUGET SOUND ENERGY Baker River Hydroelectric Project Page 12

16 production (2014 brood year), which is anticipated to be 7 million, will be totaled in early 2015, and therefore will be reported in the 2015 annual report. PSE will take a sequential approach for scheduling and increasing future sockeye fry production per SA 101 (c), Sequential Development of Sockeye Population, using both the spawning beach program and the artificial incubation (AI) program for enhancement. In this approach, PSE would provide for facility operations as directed by the Fish Co-managers, with sequential increases of approximately 1 million fry per year until either Spawning Beach 4 plus phase 1 of the artificial incubation program reach their maximum capacity, or the Baker River system reaches its maximum capacity Sockeye Egg Production (2013 Brood Year) Spawning Beach 4 (SB4). Based on the carcass counts of spawned females and using an average fecundity of 3,000 eggs, as previously determined for the Baker River stock, it is estimated that approximately 3,039,000 eggs were deposited into the spawning beach gravels. Artificial incubation (AI). According to WDFW records, from 1,664 spawned females, the AI program yielded a total of 4,893,032 eyed-eggs which had developed on vertical stack egg incubation trays supplied by the hatchery. Inclining the egg incubation trays at 5% was a slight operational adjustment this past year to benefit egg survival Sockeye Fry Production (2013 brood year) Spawning Beach 4. According to WDFW records, the spawning beach program produced approximately 1,828,946 fry between February and May 2014 for the 2013 brood year (table 4). These fry after emerging from the beach gravel emigrate to a collection hopper and are transported as unfed fry. Artificial Incubation. According to WDFW records, the AI program produced approximately 4,761,302 fry between February and May 2014, released 3,894,242 fry into the reservoirs, and retained 374,833 for a delayed-release experiment in the hatchery, satisfying the fry production objectives established by the Fish Co-Managers for the artificial incubation program (table 3). In 2014, AI-program-produced fry were held and fed for up to 10 days. Table 3. Salmon production from Baker fish propagation facilities, February 1, 2014 to May 31, Production Year Feb. - May sockeye Feb. - May sockeye Feb. - May sockeye Feb. - May coho Brood Year Species Program Stock Number Artificial Incubation Spawning Beach Extended Rearing Extended Rearing Release Size Baker 3,894,242 a fed fry Release Site Baker Lake, Lake Shannon Baker 1,828,946 b unfed fry Baker Lake Baker 374,833 c fed fry (see table 7) Baker 223,935 d fed fry (see table 7) a Approximately 1,946,111 were released in Baker Lake, 1,948,131 were released in Lake Shannon. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 13

17 b All were counted into Baker Lake, during end of season annual shutdown a residual amount of remaining fry estimated at 10,000 were released into Lake Shannon. c Approximately 374,833 was held in the extended rearing program and will be released in November 2014 (table 6). d Approximately 156,390 will be released as fry in Lake Shannon June 2014, approximately 65,000 will be held in the extended rearing program and will be released in May 2015 (table 6) Sockeye Fry Disposition (2013 Brood Year) Spawning Beach 4. The Fish Co-Managers determine the allocation percentages of fry to Lake Shannon and Baker Lake. According to WDFW records, most (99.5%) of the unfed Spawning Beach 4 fry (1,828,946) were released into Baker Lake. The other 0.5% that went into Lake Shannon consisted of approximately 10,000 residual remaining fry that were released into Lake Shannon when Beach 4 was shut down for the season. Artificial Incubation. The Fish Co-Managers determine the allocation percentage of fry to Lake Shannon and Baker Lake. According to WDFW records, 1,946,111 (45.6%) fed fry from the artificial incubation program were released into Baker Lake, and 1,948,131 (45.6%) fed fry from the artificial incubation program were released into Lake Shannon. Artificial incubation fry were transported to swim-up troughs and fed for one to three weeks before release into Baker Lake and Lake Shannon. The holding was intended to allow the fry to swim up and become active before release, to develop foraging behavior, to time the release to the forage base population and coordinate with operational activities. Of these, 374,833 fed fry (8.8%) from the artificial incubation program are being reared for use in future studies and for continuing fish propagation and enhancement programs (the previous goal was 130,000). 303,434 juvenile sockeye were reserved for the delayed-release experiment at the hatchery: from the 2013 brood year, 295,156 ad-clipped fish at fish per pound (fpp) were released into Baker Lake in November 2014; from the 2012 brood year, 6,281 ad-clipped fish at 20 fpp were inserted with a passive integrated transponder (PIT) and used to study Lower Baker fish passage beginning in March 2014 (table 5); and an additional 1,997 ad-clipped fish at 18 fpp were inserted with a PIT and used to study Upper Baker fish passage beginning in March 2014 (table 5). All fish were raised to appropriate release sizes and released on schedule. Sockeye fry production was only slightly affected by infectious hematopoietic necrosis (IHN), a virulent rhabdoviral disease that occurs in the wild and can typically cause high mortality in juvenile sockeye. During this reporting period, viral sampling indicated that IHN virus was carried in adult sockeye that returned to the Baker system fall 2013, and detected IHN virus in adult fish placed in Spawning Beach 4 and in the artificial incubation adult holding ponds. The containment features of the Spawning Beach and hatchery, operational procedures for disease management, and biosecurity procedures worked to contain and limit infection episodes in subsequent fry production. Winter/spring (2014) viral sampling confirmed that no IHN was present in fry produced from Spawning Beach 4. IHN infection was contained to a single episode in the artificial incubation program: two egg trays from the 2 nd egg take (28,058 sockeye eggs) were euthanized on February 10, PUGET SOUND ENERGY Baker River Hydroelectric Project Page 14

18 Sockeye Fry Production and Distribution (2014 brood year) It is expected that the Spawning Beach 4 segments will produce roughly 2 million sockeye fry, and that the artificial incubation program will produce roughly 5 million fry from the 2014 brood year. The WDFW informed PSE of approximate distributions of those 7 million fry in a sockeye fry distribution plan for the resulting 2014 brood year production of sockeye, directing 4.65 million fry into Baker Lake and 2 million into Lake Shannon and retaining 350,000 (with adiopose mark) for extended rearing for fall par release into Baker Lake of which 5,000 raised to smolt for passage studies (Baker River Co-Managers, 2014) Yearly Sockeye Fry Propagation Sockeye fry recruitment to the reservoirs since 1957 has come from four constructed spawning beaches, hatchery production using artificial incubation, and limited natural spawning. Figure 6 shows the collection of eggs for the sockeye artificial incubation program. Figure 7 shows the trend of fry releases from spawning beaches and hatchery production. Levels have increased significantly since the new Baker Hatchery began operation. Table 4 lists the most recent sockeye fry production from brood years dating back to PSE implemented a study approach April 2013 to monitor the numerical response to increased fry production. The approach to monitoring includes an annual accounting of the empirical data in this table. This includes fry production, plus subsequent smolts counted. During 2014, the total yearly sockeye fry propagation from the Baker Hatchery was 6,590,248, making 2014 the 5 th consecutive year in which fry production exceeded 5 million. The total was a two-fold increase from levels prior to 2008, and the highest in 56 years of production from Baker River facilities. Figure 6. Yearly sockeye artificial incubation program. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 15

19 Brood year Table 4. Sockeye broodstock and fry production from Baker fish propagation facilities, plus subsequent smolts counted for each brood year from 1999 through Spawning beach spawned females Counted fry out of spawning beach #4 Estimated fry from beach #3 AI spawned females Egg take for AI Fry produced from AI Fry to Baker Lake Fry to Lake Shannon Smolts from Baker Lake a ,393 1,856, ,000 2,078, , ,770 3,281, ,000 3,604, ,021 9, ,017 1,316, ,000 1,543,042 70, ,677 1,537, , , ,950 2,259, , ,698 4, ,854 2,089, , , ,944 2,971, , ,767 3, ,662 1,638, , ,212,800 1,188,524 2,801, , ,494 4,810 Smolts from Lake Shannon a ,656, ,157,300 1,134,742 2,791, ,014 41, ,807 1,990, ,246,190 1,224,356 2,914, , , ,892, , ,940 2,814, ,353 7, ,161 1,326, , ,506 2,291, ,297 1, ,713 3,511, ,713,599 1,596,630 5,108, ,550 5, ,637 5,199,858 5,089,860 4,139, , ,612 17, ,158, ,690 5,072,919 4,368,735 3,558,264 2,000, , , ,415 2,100, ,298 3,375,845 3,262,645 3,836,878 1,349, , , ,013 1,828,946 NA 2,124 4,893,032 4,761,302 3,775,057 1,948,131 TBD TBD TBD NA 1,846 5,325,011 TBD TBD TBD TBD TBD a Counts include all sockeye outmigrants (wild produced and Baker propagation facilities) but do not reflect smolt production by brood year because the majority of smolts outmigrate at age 1. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 16

20 Figure 7. Yearly number of sockeye fry released into the reservoirs from Baker fish propagation programs, brood years (release years ) Coho Supplementation program The coho supplementation program continues to produce juvenile coho from the stock of naturally-reproduced wild origin coho adults in the Baker River system for use in studies and for the ongoing fish propagation and enhancement objectives determined by the Fish Co-Managers. Approximately 93,406 fry were allocated for extended rearing and release as smolts in the spring of 2014 to continue migration experiments and contribute to adult returns. These fry, reared in raceways at Upper Baker, resulted in a total of 91,234 yearlings. Of these fish, 3,298 (21 fpp) were released into net pens in Lake Shannon and 1,991 (24 fpp) were released into net pens in Baker Lake to be used for juvenile passage biological studies. The remaining 85,945 yearling fish (22 fpp) were released below both dams into the Baker River stress relief ponds (SRP) in April 2014 to contribute to future fall adult returns. All fish were raised to appropriate sizes and released on schedule (table 5). PUGET SOUND ENERGY Baker River Hydroelectric Project Page 17

21 Release Date Table 5. Salmon releases from Baker River fish propagation facilities, Brood Year Species Stock Number Size (fish/lb.) Pounds Planted Release Site March 13, sockeye Baker 6, Shannon Pens March 13, sockeye Baker 1, Baker Pens March 19, coho Baker 1, Baker Pens March 20, coho Baker 3, Shannon Pens April 30, coho Baker 85, ,997 SRP June 11, coho Baker 156, Lake Shannon Nov 5, sockeye Baker 109, ,448 Baker Lake Nov 6, sockeye Baker 185, ,359 Baker Lake Total Releases 551,058 14, Coho Adult Returns (2014 Brood Year) A total of 2,945 coho adults returned to the Baker River trap in 2014, of which 197 were removed from the trap for the supplementation program. These fish were held at the Baker hatchery until sexually mature and then spawned. The coded wire tags were recovered from their carcasses for stock identification Coho Egg and Fry Production (2013 Brood Year) For the 2013 brood year (2014 fry production), 100 Coho females were spawned and an estimated total of 233,919 eyed eggs were incubated at the hatchery. An inventory of fry based on eyed egg weight samples less ponding loss provided a count of 223,935. Approximately 65,000 fry will be allocated to the extended rearing program (the program goal is 60,000), resulting in a surplus of Coho fry. The 156,390 surplus fry (~200 fpp) were released into Lake Shannon at Sulphur Creek in June The estimated 65,000 fry allocated for extended rearing will be released as yearlings (~20 fpp) in the spring of 2015 to continue migration experiments and contribute to adult returns. An additional 6,500 will be used for juvenile passage biological studies. All of these fish reared at the Baker hatchery will be used for the annual mark-recapture (reservoir migration response) experiments. The remaining 58,500 yearling fish will be released into the Baker River stress relief ponds below both dams to contribute to future fall returns. A salmon rearing inventory is shown in table 6. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 18

22 Table 6. Salmon rearing inventory at fish propagation facilities as of December 31, Planned Release Date Brood Year March Sockeye May Coho Species Program Stock Inventory Extended Rearing Extended Rearing Planned Release (fish/lb.) Baker 9, Baker 63, Planned Release Site Baker/ Shannon Baker/ Shannon/ Baker River Rainbow Trout Production WDFW provided 19,249 rainbow trout fingerlings (2013 brood year) for the rearing program in July These fish will be released in The rearing program contributes catchable-sized rainbow trout for local recreational fishing, and for derbies. PSE supplies labor, rearing facilities, and food until the last release. During 2014, 22,421 catchable fish were released. Approximately 18,103 rainbow trout (from the 2012 brood year) were released into Depression Lake for recreational fishing, and 2,515 rainbow trout were released into Grandy Lake as an expansion of this recreational fishing program. 1,700 trout were allocated to the Upper Skagit Indian Tribe, and 103 for a local community fishing derby. All fish were raised to appropriate target sizes averaging less than 2 fpp, and were released on schedule. Figure 8 shows the Baker fish hatchery in operation for juvenile fish rearing for the 20,000 pound capacity production program directed by the Fish Co-managers annual fish production goals. Figure 8. Juvenile fish rearing facilities in use for sockeye and coho salmon and rainbow trout. Raceways and rectangular and circular tanks are provided for program flexibility and multiple species. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 19

23 Facilities Operations Monitoring Repairs to Water Supply Landslide activity over the years has at times adversely affected the water intake and supply system for the spawning beach and hatchery. Because of the potential for soil slippage at the springs supplying water to the fish production facilities, turbidity events are monitored by alarm systems. Past events have resulted in temporary turbidity excursions in the water supply. PSE has responded to these by switching to an alternate (domestic) water supply until the primary supply could be restored. To address these events, new sand separators were installed as part of the Baker fish hatchery renovation. These sand separators protect the water supply by removing sediment both under normal conditions and following a landslide event. However, landslides in December 2012 resulted in large amounts of sediment infiltrating the water supply and overwhelming the sand separators. PSE mobilized quickly to respond to the December 2012 landslide and temporarily restored water supply by removing rip rap (large boulders), cleaning and removing the sediment buildup, and replacing the riprap back into the spring channel while monitoring for turbidity. Juvenile fish in the hatchery were relocated to offsite locations, including the stress relief ponds at Lower Baker. Only a few adult sockeye broodstock remained and were spawned, and adult coho broodstock were connected to the backup water system. Incubating sockeye and coho eggs already on the domestic water supply remained on the back-up water supply system. PSE began planning for permanent repairs to begin in June 2013 during the normal annual hatchery maintenance shutdown in preparation for the next brood cycle, so that it would have the least effect to fish. June is also part of the drier season, making new landslides unlikely during the repairs. Making these repairs to the hatchery headworks required PSE to review conditions, consult with the USDA-FS and the ARG, and then plan and initiate repairs following USDA-FS approval of planned work. PSE designed a repair method employing a graded filter and geotextile filter fabric at the Sulphur Springs water supply intake to control further sediment infusion. The filter materials were selected to cap the hatchery water intake area, protecting it from sliding materials in the event of a new landslide. The repair method was approved by the USDA-FS on May 28, 2013 (USDA-FS, 2013a) and PSE immediately initiated construction work based on the approved design (PSE, 2013a). Upon exposing the underlying rebar intake pipe structures in the spring flow path, PSE discovered these to be damaged and replaced or refurbished them. Substantial equipment was used throughout construction. In compliance with best management practices, PSE installed straw wattles for erosion control, monitored turbidity, and stopped work when measured turbidities exceeded relevant background criteria, resuming when the condition was no longer present. The repair project was completed on schedule on June 28, Water supply to the hatchery was restored on the same day, ahead of delivery of the earliest returns of fish for spawning. The completed repair work is intended as a permanent solution for protecting the water supply from sliding material. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 20

24 The intake consists of cylindrical pipes constructed with steel bars that are buried in riprap. The riprap is covered with a graded filter consisting of quarry spalls, ballast, gravel, and a woven geotextile. For years, the lack of a graded filter had subjected the intake to sedimentation. The reconstructed intake now collects and conveys spring water to a headworks box free from sediment. PSE is currently working with the USDA-FS and WDFW to implement long-term erosion protection measures that would stabilize the repairs and reduce erosion. Temporary erosion control measures were installed following the unusually large amount of surface runoff that occurred during heavy November 2013 rainstorms. There has not been any additional erosion since these measures were put in place. Even though one rain event produced 3.5 inches; the spawning beach and hatchery water supply remained clear and protected. The objective of the long-term erosion protection measures is to prevent surface erosion in the construction area, thus protecting the repairs to the headworks completed in June 2013 and minimizing sediment transfer to Sulphur Creek. PSE is discussing longer-term erosion control measures with the USDA-FS and WDFW to confirm the design approach and details, and implementation is scheduled for the summer Empirically-Derived Production Limits for Sockeye Salmon PSE implemented a study approach in April 2013 for monitoring adult returns and the size and number of outmigrating smolts to provide feedback on basin sockeye production limits (PSE, 2013). PSE developed the study approach in collaboration with the ARG to establish the number, type, and frequency of adult and smolt data collection efforts (PSE collects juvenile sockeye size information at the juvenile downstream fish passage facilities). PSE submitted a summary to the ARG of empirical data monitored during the 2014 outmigration period, both numerical and morphological, on December 19, Numbers of fry, numbers of outmigrating smolts, and numbers of returning adult sockeye were provided in tables. A record 939,879 sockeye smolts were counted in PSE presented the length and weight of smolts and condition of smolts (k-factor) in graphs. In 2014, the Baker Lake age 1 average size was 107 mm, and the average condition was In Lake Shannon, age 1 average size was 120 mm, and average condition was Figure 9 shows Baker Lake age 1 average size from Figure 10 shows Baker Lake age 1 average condition factor from The complete data summary presentation is attached to this report (see section 5.0, Supporting Documents ). PUGET SOUND ENERGY Baker River Hydroelectric Project Page 21

25 Average Length - "Age 1" (2 Wk May - 2 Wk June) - UPPER BAKER Fork length (mm) mm 109 mm 108 mm 106 mm 107 mm Figure 9. Average fork length for Baker Lake age 1 sockeye smolts ( ). Average Condition factor - "Age 1" (2 Wk May - 2 Wk June) - UPPER BAKER 1.05 Condition factor (K) Figure 10. Average condition factor (K) for Baker Lake age 1 sockeye smolts ( ) Fry Release Site Technical Working Group In a letter dated December 9, 2013, the Fish Co-managers responded to PSE s fry release information and identification of alternate release sites that was presented at the June 13, 2013 ARG meeting (Baker River Co-managers, 2013). The Fish Co-managers letter clarified their technical evaluation of current fry release locations that has led to their objectives and policy for effective fry planting. The Fish Co-managers and PSE convened a technical working group to identify options and establish a path forward to resolving the issues related to the number of usable release sites. The technical working PUGET SOUND ENERGY Baker River Hydroelectric Project Page 22

26 group met three times during 2014 (April 3, 2014, June 30, 2014 and September 24, 2014) and had important discussions, including brainstorming options, identifying areas to research, and considering potential funding mechanisms. The group is in the midst of working through various issues specific to the options, including potential funding sources, permitting options, and contingency plans. The meetings have produced important discussions and a good understanding of each stakeholder s interests. These meetings will continue during Request to Install Chillers In a letter dated October 8, 2013, the Fish Co-managers made a request to PSE to purchase and install a water chiller system at the Baker fish hatchery, which was completed in 2011 (WDFW, 2013). The request was made for two main reasons: (1) slow egg development during incubation for some early portions of the hatchery production, and (2) to enable the application of otolith marks to fish stocks in order to assist the Fish Co-managers in making ongoing management decisions for fish propagation. After reviewing the history of the hatchery renovation, the license obligations, and ultimately the need for chilled water at the hatchery for fish propagation, PSE responded to the request in a letter dated April 4, 2014, indicating that PSE had fulfilled its obligation under SA 101(b) to construct additional fish culture facilities, and is not obligated to fund a chilled water system for management activities. The Fish Comanagers provided a follow-up response April 15, 2014, calling attention to their interpretation of PSE s much broader commitment under the full context of SA 101. PSE reviewed the first response to the Fish Co-managers, and in a July 28, 2014 letter outlined the company s basis for declining the request to fund a chilled water system at the Baker fish hatchery. PSE suggested the use of adaptive management funds already in the license as one potential funding mechanism for the chilled water system. The issue remains an area of disagreement between the Fish Co-managers and PSE Nutrient Enhancement Fund SA 101(f) The license requires PSE to make funding available for the implementation of a reservoir nutrient enhancement program. Annual funding prescribed by SA 101(f) for nutrient enhancement was made available in 2012 (the first year of deposit), and will accrue at $60,000 per year (escalated from 2006 dollars; see section 4.1) each year from the date of license issuance. On June 12, 2013, PSE met with the Fish Co-managers to discuss a mechanism for distributing the fund. During 2014, the Fish Co-managers and PSE have been developing a draft memorandum regarding the procedures to be followed in managing the fund, including fund requests, fund disbursement, and annual reporting, as well as a mechanism for returning unspent funds to the Habitat Enhancement, Restoration, and Conservation (HERC) fund. Completion of the memorandum is expected in SA 101 d Maintain, Then Restore Natural Conditions at Spawning Beaches 1, 2, and 3 Before the renovation and construction of the Baker fish hatchery was complete, PSE initiated discussion with the USDA-FS to develop a decommissioning plan that outlines decommissioning procedures for the site of Sockeye Spawning Beaches 1, 2, and 3. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 23

27 Actual decommissioning of the Channel Creek site will occur after the USDA-FS (the land owner) authorizes decommissioning. PSE consulted with the USDA-FS towards an understanding of the decommissioning procedures. PSE and the USDA-FS sought input from the ARG and the Cultural Resources Advisory Group (CRAG) at meetings. The consultation process resulted in a USDA-FS scope-of-work document (USDA-FS, 2011), an agreement on a general approach that considered the input of the ARG and CRAG, and the development of conceptual design options presented to the ARG in June 2012, followed by the ARG s selection of restoration Alternative 5, in July The following restoration goals for the decommissioning of the site were determined during a workshop with PSE, and the ARG, held on June 26, 2012 (PSE, 2012). Salmon Spawning Habitat: Provide spawning habitat for adult salmon throughout the existing natural channel in the project area (to the most practicable extent). Maintain Pond Hydrology: Maintain the open water component of the upstream pond by implementing some type of downstream grade control structure (or similar) to help maintain pond water elevations. Overflow Swale: Provide an overflow swale to direct overflows from the upstream pond to the downstream pond and channel. This will prevent water from flowing overland to the south away from the channel and pond network. The following site decommissioning goals were identified by the USDA-FS. Remove Infrastructure: All surface and subsurface infrastructure constructed and installed as part of the spawning beaches will be removed and hauled off-site for appropriate disposal or recycle. Decommission Gravel Surfacing: The gravel surfacing within the site will be decommissioned to USFS standards (roadway decommissioning may involve removal of the gravel surface and the sub-base scarified to a depth of approximately 1 foot). Re-grade Site: Upon removal of the site facilities (surface and subsurface), the site will be re-graded to emulate natural, pre-facility grades and contours. Cut and Fill Volume: Decommissioning will generate cut and fill. To the extent practicable, cuts and fills will be balanced on-site to minimize or eliminate the need for the import and export of fill materials. Alternative 5, which meets these goals, includes enhancement along the existing Channel Creek alignment with grade control (large woody debris structures) placed in the channel to help maintain the water surface elevations in the upstream pond. In addition, an overflow swale will connect the upstream pond to the downstream pond to help keep water in the existing channel and pond complex. The overflow swale will provide a flow pathway during higher-flow drainage events, and if beaver activity in the main channel creates backwater conditions (with the potential for overflow) in the pond. PSE provided an alternatives assessment report to the ARG in August 2012 as documentation for moving forward with the Alternative 5 design. PSE developed a Channel Creek Site Decommissioning Plan that outlines the progress that PSE has made in planning for decommissioning and the procedures for decommissioning based on the Alternative 5 design. Following ARG review, PSE provided the ARG with an updated plan including ARG comments and PSE responses (December 2012). PSE finalized the PUGET SOUND ENERGY Baker River Hydroelectric Project Page 24

28 design with a plan set dated April 18, 2013 (Anchor QEA, 2013). PSE received documentation ( Notice to Proceed ) confirming that the USDA-FS had completed its review and approved the decommissioning (USDA-FS, 2013). Construction began on July 16, 2013 and all in-water work was completed on August 9, All five LWD structures were set and man-made objects were removed from the upper pond and creek. Demolition of Beach 1 commence first out the three beaches. Asbestos abatement in Beach 2 began August 26 th and was completed in about 1 week. Final grading of the site was completed by the end of December Interim progress updates were provided to the ARG at meetings in June and September 2013, and in January Re-vegetation was completed on approximately 50% of the site. Efforts were suspended until 2014 due to issues with frozen ground. The site was stabilized for the winter, and modifications to the LWD structures that were requested by the USDA- FS were scheduled for mid-july The remaining re-vegetation work was scheduled for the fall of 2014, along with the completion of other remaining punch list items. The USDA-FS provided a punch list of construction modifications it would require for completion, which included modifications to correct intended functions of several of the LWD structures during the next allowable in-water work window (July-August 2014), and hence concurred with a schedule extension to complete the decommissioning in the fall of The decommissioning project per the plan and required modifications outlined in the final USFS construction punch list was completed by the end of Modifications to the LWD installations to improve their function included notching the LWD structures to assist fish passage, lining the upstream end to prevent undermining, and installing a roughened channel between LWD structures 3 and 4. That work was completed in August 2014 and those structures are functioning very well. Re-vegetation on the site resumed in October and was completed in November A walk through of the site to review all finished work with the USDA-FS was conducted, final punch list items were identified and then completed in December Figures show the construction, LWD modifications, re-vegetation, final completion and original plans. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 25

29 Figure 11. Five LWD structures were installed in the main channel alignment during July and August 2013 to help maintain pond hydrology. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 26

30 Figure 12. Demolition of Spawning Beach 3 (upper). Surface and sub-surface infrastructure removed and hauled offsite for disposal (lower). PUGET SOUND ENERGY Baker River Hydroelectric Project Page 27

31 Figure 13. All site facilities removed. Cut, fill and re-graded areas once occupied by the beaches (upper). Re-vegetation work on the graded site (lower) PUGET SOUND ENERGY Baker River Hydroelectric Project Page 28

32 Figure LWD modifications to improve function included installing liners on the upstream end (upper) and notches (lower) PUGET SOUND ENERGY Baker River Hydroelectric Project Page 29

33 Figure LWD modifications included adding a roughen channel between LWD structures 4 and 3. PUGET SOUND ENERGY Baker River Hydroelectric Project Page 30

34 Fish Propagation 2014 Annual Report Figure re-vegetation and mulch around the LWD structures. BAK SA 101 Annual Report 2014.Docx PUGET SOUND ENERGY Baker River Hydroelectric Project 17 November 2015 Page 31

35 Fish Propagation 2014 Annual Report Figure re-vegetation and mulch along the former access road (upper) and along the floodplain swale (lower) BAK SA 101 Annual Report 2014.Docx PUGET SOUND ENERGY Baker River Hydroelectric Project 17 November 2015 Page 32

36 Fish Propagation 2014 Annual Report Figure 18. Mulch placement along the LWD structures. BAK SA 101 Annual Report 2014.Docx PUGET SOUND ENERGY Baker River Hydroelectric Project 17 November 2015 Page 33

37 Fish Propagation 2014 Annual Report Figure 19. Photos taken at completion in December 2014, following a site walk with the USDA-FS. BAK SA 101 Annual Report 2014.Docx PUGET SOUND ENERGY Baker River Hydroelectric Project 17 November 2015 Page 34

38 Figure 20. Spawning Beaches 1, 2, and 3 before decommissioning. (PSE, 2013) PUGET SOUND ENERGY Baker River Hydroelectric Project Page 35

39 Figure 21. Conditions at completion of decommissioning (April 18, 2013 design), showing infrastructure removed, site regrading, large woody debris structures in the channel alignment, and an overflow swale. (PSE, 2013) PUGET SOUND ENERGY Baker River Hydroelectric Project Page 36

FISH PROPAGATION 2015 ANNUAL REPORT

FISH PROPAGATION 2015 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2015 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2015 DECEMBER 31, 2015 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 November 2016 PUGET SOUND ENERGY

More information

FISH PROPAGATION 2012 ANNUAL REPORT

FISH PROPAGATION 2012 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2012 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2012 MAY 31, 2013 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 December 2013 BAK SA 101 Annual Report 2012.Doc

More information

FISH PROPAGATION 2010 ANNUAL REPORT

FISH PROPAGATION 2010 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 101 FISH PROPAGATION 2010 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2010 MAY 31, 2011 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 April 2012 BAK SA 101 Annual Report 2010.Doc

More information

UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT

UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 103 UPSTREAM FISH PASSAGE 2015 ANNUAL REPORT REPORTING PERIOD JANUARY 1, 2015 DECEMBER 31, 2015 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 November 2016 PUGET SOUND ENERGY

More information

P U B L I C U T I L I T Y D I S T R I C T N O.

P U B L I C U T I L I T Y D I S T R I C T N O. P U B L I C U T I L I T Y D I S T R I C T N O. 1 o f C H E L A N C O U N T Y P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org

More information

THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT

THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT LICENSE ARTICLE 410 THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT REPORTING PERIOD JANUARY 1 DECEMBER 31, 2010 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 Puget Sound Energy Bellevue,

More information

Yakima/Klickitat Fisheries Project

Yakima/Klickitat Fisheries Project Yakima/Klickitat Fisheries Project Lower Yakima River Supplementation and Research Project Operations and Maintenance Annual Report 2002-2003 March 2004 DOE/BP-00006677-1 This Document should be cited

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, September 4, 27 9: a.m. : a.m. Place: CONFERENCE CALL ONLY Contacts: Frank

More information

Baker River Project License Implementation. Aquatics Resource Group Meeting Final Conference Call Notes. March 9, 2010 ~ 9:00-11:00 am

Baker River Project License Implementation. Aquatics Resource Group Meeting Final Conference Call Notes. March 9, 2010 ~ 9:00-11:00 am Baker River Project License Implementation Aquatics Resource Group Meeting Final Conference Call Notes March 9, 2010 ~ 9:00-11:00 am Team Leader: Arnie Aspelund, PSE (arnie.aspelund@pse.com) PRESENT: Arnie

More information

FISH CONNECTIVITY IMPLEMENTATION PLAN

FISH CONNECTIVITY IMPLEMENTATION PLAN FISH CONNECTIVITY IMPLEMENTATION PLAN SETTLEMENT AGREEMENT ARTICLE 104 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 October 2011 BAK SA 104 Fishconnectivityimplan.Doc PUGET SOUND ENERGY Baker River

More information

145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Public Utility District No. 1 of Douglas County, Washington Project No. 2149-163 ORDER APPROVING BULL TROUT STRANDING, ENTRAPMENT,

More information

Cushman Hydro Project Public Meeting. Cushman Fire Hall Dec. 6, 2018

Cushman Hydro Project Public Meeting. Cushman Fire Hall Dec. 6, 2018 Cushman Hydro Project Public Meeting Cushman Fire Hall Dec. 6, 2018 Reservoir Operations Florian Leischner Fish and Habitat Biologist Cushman Reservoirs Cushman dams were built in 1924-30 New Cushman license

More information

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT FEDERAL AID JOB PROGRESS REPORTS F-20-52 2016 Lake Tahoe Rainbow Trout Study WESTERN REGION NEVADA DEPARTMENT OF WILDLIFE, FISHERIES DIVISION

More information

APPENDIX D: LEWIS RIVER HATCHERY REVIEW

APPENDIX D: LEWIS RIVER HATCHERY REVIEW APPENDIX D: LEWIS RIVER HATCHERY REVIEW JANUARY 14, 2004 Prepared for PacifiCorp and Cowlitz PUD Prepared by S.P. Cramer & Associates, Inc. 600 NW Fariss Gresham, Oregon 97030 www.spcramer.com D-1 TABLE

More information

Hatchery Scientific Review Group Review and Recommendations

Hatchery Scientific Review Group Review and Recommendations Hatchery Scientific Review Group Review and Recommendations Lochsa River Spring Chinook Population and Related Hatchery Programs January 31, 2009 Lochsa River Spring Chinook Population Report Page - 1

More information

Attachment 1. Agenda Item Summary BACKGROUND

Attachment 1. Agenda Item Summary BACKGROUND Attachment 1 Agenda Item Summary BACKGROUND Spring Chinook Salmon: Prior to the late 1970s, non-treaty spring Chinook fisheries in the mainstem Columbia River occurred from February through May and harvested

More information

OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP

OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP Hatchery 13 Article 07 OXBOW FISH HATCHERY AND HELLS CANYON FISH TRAP 1 9 8 8 A n n u a l R e p o r t b y Brent R. Snider, Fish Hatchery Superintendent I March 1993 TABLE OF CONTENTS Page ABSTRACT... 1

More information

FINAL Caples Lake Fisheries Management Plan. Version 4.0

FINAL Caples Lake Fisheries Management Plan. Version 4.0 FINAL Caples Lake Fisheries Management Plan Version 4.0 August 15, 2008 Purpose The Caples Lake Fisheries Management Plan (Plan) outlines the stocking plan to reestablish a sport fishery in Caples Lake

More information

Don Pedro Project Relicensing

Don Pedro Project Relicensing Don Pedro Project Relicensing M ODESTO I RRIGATION D ISTRICT TURLOCK I RRIGATION D ISTRICT FERC PROJECT N O. 2299 Resident Fish in Don Pedro Reservoir Don Pedro Reservoir Fish Stocking (1971-Present) CDFG

More information

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell:

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell: From: To: Cc: Subject: Date: Attachments: Hemstrom, Steven "Lewis, Stephen" Sokolowski, Rosana 2014 Rocky Reach Bull Trout Report Wednesday, June 18, 2014 3:01:07 PM Final 2014 Rocky Reach Bull Trout Observations

More information

SALMON RIVER HATCHERY

SALMON RIVER HATCHERY SALMON RIVER HATCHERY PROGRAM MANAGEMENT PLAN 2018 Salmon River Hatchery INTRODUCTION Salmon River Hatchery is located seven miles north of Lincoln City off Highway 18 near Otis. Site is at an elevation

More information

Yakima River Basin Coho Reintroduction Feasibility Study

Yakima River Basin Coho Reintroduction Feasibility Study Yakima River Basin Coho Reintroduction Feasibility Study Yakima Klickitat Fisheries Project Goals and Mission The purposes of the YKFP are to: enhance existing stocks of anadromous fish in the Yakima and

More information

Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities

Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities Platte River State Fish Hatchery Summary of 2012 Production and Operational Activities Antibiotic Use The antibiotic use at the Platte River State Fish Hatchery (Hatchery) in 2012 only focused on disease

More information

Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery

Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery Perspectives of a State Director Selective fisheries as a tool in fisheries management and salmon recovery Jeffrey P. Koenings, PhD. Washington Department of Fish and Wildlife American Fisheries Society

More information

Ned Currence, Nooksack Indian Tribe

Ned Currence, Nooksack Indian Tribe Ned Currence, Nooksack Indian Tribe Problem Status Distribution Habitat Hatcheries Harvest 25000 20000 Natural-Origin Spawners 15000 10000 22500 5000 0 Historic catch Spawners (2011-2015) Problem Status

More information

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. Public Utility District No. 1 of

More information

***Please Note*** April 3, Dear advisory committee members:

***Please Note*** April 3, Dear advisory committee members: April 3, 29 Dear advisory committee members: The fifth meeting of the CHF advisory committee will be held April 13 in Grants Pass from 6:-8:3 PM, and the purpose of this document is to help committee members

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

NORTH NEHALEM HATCHERY

NORTH NEHALEM HATCHERY NORTH NEHALEM HATCHERY PROGRAM MANAGEMENT PLAN 2018 Nehalem Hatchery Plan Page 1 North Nehalem Hatchery INTRODUCTION The North Nehalem Hatchery is located on the North Fork Nehalem River 12 miles East

More information

The Blue Heron Slough Conservation Bank

The Blue Heron Slough Conservation Bank 1 The Blue Heron Slough Conservation Bank CONSERVATION BANKING July 19-23, 2010 CASE STUDY SERIES The Blue Heron Slough Conservation Bank (Washington) I. OVERVIEW & BACKGROUND: Location: Snohomish River

More information

ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017

ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017 ROCK CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2017 Rock Creek Hatchery INTRODUCTION Rock Creek Hatchery is located on the North Umpqua River, 23 miles east of Roseburg, just off Highway 138. The site is

More information

Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation

Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program: F 1 Generation Tim Hoffnagle, Rich Carmichael, Joseph Feldhaus, Deb Eddy, Nick Albrecht and Sally Gee Oregon Department of Fish and

More information

LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report

LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report LOWER SNAKE RIVER COMPENSATION PLAN: Oregon Spring Chinook Salmon Evaluation Studies 2006 Annual Progress Report Oregon Department of Fish and Wildlife Fish Research and Development, NE Region Fred R.

More information

THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON

THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON THE CONFEDERATED TRIBES OF THE WARM SPRINGS RESERVATION OF OREGON To: Branch of Natural Resources P.0. Box C, Warm Springs, Oregon 97761 Phone (541) 553-2002/2003 Fax (541) 553-1994 The Independent Science

More information

CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018

CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 CEDAR CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 Cedar Creek Hatchery INTRODUCTION Cedar Creek Hatchery is located 1.5 miles east of Hebo off Highway 22, adjacent to Three Rivers, a Nestucca River tributary.

More information

SALMON RIVER HATCHERY

SALMON RIVER HATCHERY SALMON RIVER HATCHERY OPERATIONS PLAN 2006 Salmon River Hatchery Plan Page 1 Salmon River Hatchery INTRODUCTION Salmon River Hatchery is located four miles north of Lincoln City off Highway 18 near Otis.

More information

UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT

UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT SETTLEMENT AGREEMENT ARTICLE 103 UPSTREAM FISH PASSAGE 2013 ANNUAL REPORT REPORTING PERIOD JUNE 1, 2013 MAY 31, 2014 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 January 2015 PUGET SOUND ENERGY Baker

More information

Kootenay Lake Kokanee and other Fish 2017 Status

Kootenay Lake Kokanee and other Fish 2017 Status Kootenay Lake Kokanee and other Fish 2017 Status Friends of Kootenay Lake 5th Annual Kootenay Lake Summit November 2017 Matt Neufeld and Jeff Burrows BC Fish and Wildlife Nelson Outline Kootenay Lake Fish

More information

Hatcheries: Role in Restoration and Enhancement of Salmon Populations

Hatcheries: Role in Restoration and Enhancement of Salmon Populations Hatcheries: Role in Restoration and Enhancement of Salmon Populations Hatcheries play a large role in the management, ecology, and evolution of Pacific salmon. Why were/are they built? What are the assumptions

More information

OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018

OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018 OXBOW HATCHERY PROGRAM MANAGEMENT PLAN 2018 Oxbow Hatchery and Satellites (Upper and Lower Herman Creek Ponds) INTRODUCTION Oxbow Hatchery is located approximately 1 mile east of Cascade Locks, Oregon,

More information

FISH PASSAGE IMPROVEMENT in California s Watersheds. Assessments & Recommendations by the Fish Passage Forum

FISH PASSAGE IMPROVEMENT in California s Watersheds. Assessments & Recommendations by the Fish Passage Forum FISH PASSAGE IMPROVEMENT in California s Watersheds Assessments & Recommendations by the Fish Passage Forum FISH PASSAGE IMPROVEMENT in California s Watersheds The mission of the Fish Passage Forum is

More information

BOGUS CREEK SALMON STUDIES 2002

BOGUS CREEK SALMON STUDIES 2002 BOGUS CREEK SALMON STUDIES 2002 BY: JEANNINE RICHEY California Department of Fish and Game KLAMATH RIVER PROJECT 303 SOUTH STREET YREKA, CALIFORNIA 96097 (530) 842-3109 California Department of Fish and

More information

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1 COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Cole Rivers Hatchery Plan Page 1 Cole Rivers Hatchery INTRODUCTION Cole Rivers Hatchery is located on the Rogue River, 30 miles northeast of Medford, Oregon,

More information

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1

COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN Cole Rivers Hatchery Plan Page 1 COLE RIVERS HATCHERY PROGRAM MANAGEMENT PLAN 2019 Plan Page 1 INTRODUCTION is located on the Rogue River, 30 miles northeast of Medford, Oregon, on Highway 62, about ½ mile downstream of Lost Creek Dam.

More information

OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO.

OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO. OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT SUMMER FACT SHEET NO. 1 Columbia River Compact/Joint State Hearing June 28, 2018 Fisheries under consideration: Treaty commercial

More information

Subject: Wells Hydroelectric Project FERC Project No Bull Trout Management Plan and Incidental Take Annual Report

Subject: Wells Hydroelectric Project FERC Project No Bull Trout Management Plan and Incidental Take Annual Report Ms. Jessica Gonzales April 15, 2015 Wenatchee Office Lead Central Washington Field Office U. S. Fish and Wildlife Service 215 Melody Lane, Suite 119 Wenatchee, WA 98801-5933 Subject: Wells Hydroelectric

More information

Conditions affecting the 2011 and 2012 Fall Chinook Adult Returns to Spring Creek National Fish Hatchery.

Conditions affecting the 2011 and 2012 Fall Chinook Adult Returns to Spring Creek National Fish Hatchery. FISH PASSAGE CENTER 1827 NE 44 th Ave., Suite 240, Portland, OR 97213 Phone: (503) 230-4099 Fax: (503) 230-7559 http://www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: Liz Hamilton, NSIA FROM:

More information

Harvest Mgmt. & Fishery Regulations 2017 KATHRYN KONOSKI, FISHERIES BIOLOGIST STILLAGUAMISH TRIBE OF INDIANS

Harvest Mgmt. & Fishery Regulations 2017 KATHRYN KONOSKI, FISHERIES BIOLOGIST STILLAGUAMISH TRIBE OF INDIANS Harvest Mgmt. & Fishery Regulations 2017 KATHRYN KONOSKI, FISHERIES BIOLOGIST STILLAGUAMISH TRIBE OF INDIANS Harvest Management Annual Cycle Egg Alevin Post Season Pre-Season Spawn Adult In-Season Fishery

More information

Reproductive success of hatchery chinook salmon in the Deschutes River, Washington

Reproductive success of hatchery chinook salmon in the Deschutes River, Washington Reproductive success of hatchery chinook salmon in the Deschutes River, Washington Howard Fuss Hatchery Wild Interactions Team Washington Department of Fish and Wildlife Acknowledgments HSRG for providing

More information

2016 Annual Work Plan

2016 Annual Work Plan Rocky Reach Hydroelectric Project FERC No. 2145 2016 Annual Work Plan 2015 Progress Report d per Rocky Reach Settlement Agreement, Sections 15.1.1 & 15.6.5 Reports provided by Chelan PUD Leads: Ray Heit

More information

Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist

Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist Jamie Laatsch, Conservation & Outreach Coordinator Christina Morrisett, Research Assistant Dr. Rob Van Kirk, Senior Scientist 1 1. Chester Fish Ladder Project history Monitoring progress 2. Buffalo River

More information

TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING

TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING TAY DISTRICT SALMON FISHERIES BOARD POLICY ON SALMON STOCKING August 2011 1 INTRODUCTION This document describes the policy adopted by the Tay District Salmon Fisheries Board for the artificial stocking

More information

Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012

Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012 Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012 Bureau of Reclamation, 2800 Cottage Way, Sacramento, CA 95825 Cafeteria Conference Room C1003 FINAL: 2013.1.14

More information

MARION FORKS HATCHERY

MARION FORKS HATCHERY MARION FORKS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Marion Forks Hatchery INTRODUCTION Marion Forks Hatchery is located along Marion and Horn Creeks (Santiam River tributaries in the Willamette Basin) about

More information

Shasta Dam Fish Passage Evaluation. Public Stakeholder Webinar

Shasta Dam Fish Passage Evaluation. Public Stakeholder Webinar Shasta Dam Fish Passage Evaluation Public Stakeholder Webinar 9-24-2015 Today s Topics 1. Introduction Craig Moyle (MWH) 2. Project Overview John Hannon (Reclamation) 3. Sacramento River Conditions and

More information

Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River. Kris Homel

Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River. Kris Homel Addressing Critical Uncertainties in the Reintroduction of Chum Salmon to Oregon Tributaries of the Columbia River Kris Homel NW Fish Culture Concepts Wilsonville, OR 2015 Historic distribution and abundance

More information

Managing for IHNV in Rainbow Trout at Leaburg Hatchery. Erik Withalm

Managing for IHNV in Rainbow Trout at Leaburg Hatchery. Erik Withalm Managing for IHNV in Rainbow Trout at Leaburg Hatchery Erik Withalm erik.j.withalm@state.or.us Background Mitigate for lost recreational fishing opportunities due to the construction of Blue River and

More information

ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN Round Butte Hatchery Plan Page 1

ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN Round Butte Hatchery Plan Page 1 ROUND BUTTE HATCHERY PROGRAM MANAGEMENT PLAN 2018 Round Butte Hatchery Plan Page 1 Round Butte Hatchery and Satellite (Pelton Ladder) INTRODUCTION Round Butte Hatchery is located on the Deschutes River

More information

SANDY HATCHERY OPERATIONS PLAN Sandy Hatchery Plan Page 1

SANDY HATCHERY OPERATIONS PLAN Sandy Hatchery Plan Page 1 SANDY HATCHERY OPERATIONS PLAN 2014 Sandy Hatchery Plan Page 1 Sandy Hatchery INTRODUCTION Sandy Hatchery is located along Cedar Creek (a Sandy River tributary) 1.5 miles north of Sandy, Oregon, off Highway

More information

COA-F17-F-1343 YEAR END REPORT

COA-F17-F-1343 YEAR END REPORT DAVE MARSHALL SALMON RESERVE RESTORATION, MAINTENANCE, AND UPGRADES YEAR END REPORT Prepared for: Fish and Wildlife Compensation Program Prepared by: Edith Tobe, RPBio, Executive Director Box 1791, Squamish,

More information

NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT

NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT Attachment 4 NATIVE FISH CONSERVATION PLAN FOR THE SPRING CHINOOK SALMON ROGUE SPECIES MANAGEMENT UNIT Figures in Draft Plan of February 28, 27 Figure 1. Map of the Rogue River Basin. PASSAGE ESTIMATES

More information

BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018

BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 BIG CREEK HATCHERY PROGRAM MANAGEMENT PLAN 2018 Big Creek Hatchery INTRODUCTION Big Creek Hatchery is located 16 miles east of Astoria, Oregon, 2 miles south of Knappa off Highway 30, and is approximately

More information

IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018

IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018 IRRIGON HATCHERY PROGRAM MANAGEMENT PLAN 2018 Irrigon Hatchery INTRODUCTION Irrigon Hatchery is located along the Columbia River above John Day Dam 3 miles west of Irrigon, Oregon. The facility is at an

More information

LOOKINGGLASS HATCHERY

LOOKINGGLASS HATCHERY LOOKINGGLASS HATCHERY PROGRAM MANAGEMENT PLAN 2018 Lookingglass Hatchery And Imnaha Satellite Facility INTRODUCTION Lookingglass Hatchery is located along Lookingglass Creek, a tributary to the Grande

More information

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington for Energy Northwest's Packwood Lake Hydroelectric Project FERC No. 2244 Lewis County, Washington Submitted to P.O. Box 968 Richland, Washington 99352-0968 Submitted by EES Consulting 1155 North State

More information

Blue Creek Chinook Outmigration Monitoring Technical Memorandum

Blue Creek Chinook Outmigration Monitoring Technical Memorandum Blue Creek Chinook Outmigration Monitoring 2012 Technical Memorandum Prepared by: Andrew Antonetti and Erika Partee Yurok Tribe Fisheries Program PO Box 1027 Klamath, California 95548 In Partnership with:

More information

Informational Report 1 USFWS Mass Marking Update April 2005 Update on USFWS 2005 Mass Marking Initiative Background Under Section 138 of FY 2003 Omnibus Appropriations Act (PL 108-7), Congress directed

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, August, 27 9: a.m. :45 a.m. Place: CONFERENCE CALL ONLY Contacts: Frank

More information

Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin

Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin ACC Participants Present (13) Meeting Notes Lewis River License Implementation Aquatic Coordination Committee (ACC) Meeting March 8, 2012 Meeting at Merwin Eli Asher, Lower Columbia River Fish Recovery

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, February 14, 219 9: a.m. 1:3 a.m. Place: CONFERENCE CALL ONLY Contacts:

More information

Eric Jones Fish Hatchery Manager II Ca. Dept. of Fish & Wildlife

Eric Jones Fish Hatchery Manager II Ca. Dept. of Fish & Wildlife Mount Shasta Hatchery 2014 Photo courtesy of M. Dege Eric Jones Fish Hatchery Manager II Ca. Dept. of Fish & Wildlife McCloud River Redband trout reared at Mt. Shasta Hatchery About MSH Why were the redbands

More information

R & E Grant Application Biennium

R & E Grant Application Biennium R & E Grant Application 15-17 Biennium Project #: 15-053 Elk River Hatchery Maintenance Project Information R&E Project Request: Total Project: Start Date: End Date: Organization: $116,262 $139,300 8/8/2016

More information

Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director

Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director Oregon Hatchery Research Center January 2014 David L. G. Noakes, Professor & Director Research Proposal Homing Homing behavior is a striking feature of the biology of Pacific salmon, and is the basis for

More information

Study Update Fish Distribution and Species Composition

Study Update Fish Distribution and Species Composition Study Update Fish Distribution and Species Composition Goals and Study Area Gain a better understanding of fish species composition and abundance in waters associated with the Packwood Lake Hydroelectric

More information

Kirt Hughes Washington Department of Fish and Wildlife Region 6 - Fish Program Manager

Kirt Hughes Washington Department of Fish and Wildlife Region 6 - Fish Program Manager Kirt Hughes Region 6 - Fish Program Manager Habitat Hatcheries Harvest Clean Water Act Shorelines Harvest Hydro Habitat Forest Practices Non-regulatory Programs Water Supply & Conservation Growth Management

More information

Appendix B. Data on Aquatic Focal Species: Adult returns to TMFD, Disposition, Escapement, Artificial Production, and Harvest

Appendix B. Data on Aquatic Focal Species: Adult returns to TMFD, Disposition, Escapement, Artificial Production, and Harvest Draft /Willow Subbasin Plan May 28, 2004 Appendix B. Data on Aquatic Focal Species: Adult returns to TMFD, Disposition, Escapement, Artificial Production, and Harvest Table 1. Summer steelhead adult returns,

More information

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017 Final for the Wallowa Falls Hydroelectric Project (FERC No. P-308) June 2017 Prepared by: Jeremiah Doyle PacifiCorp 825 NE Multnomah Street Portland, OR 97232 June, 2017 Page 1 of 8 Table of Contents 1.0

More information

Lakelse Sockeye Recovery Program

Lakelse Sockeye Recovery Program Lakelse Sockeye Recovery Program The Ninth Annual BC Interior Stewardship Workshop May 7 th and 8 th, 2013 DFO North Coast Resource Restoration Unit Presentation Overview History/background Stock and habitat

More information

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016

Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 Yale Reservoir Kokanee (Oncorhynchus nerka) Escapement Report 2016 North Fork Lewis River Hydroelectric Project Yale FERC No. 2071 Prepared by: Jeremiah Doyle, PacifiCorp April 4, 2017 1.0 INTRODUCTION

More information

Management Strategies for Columbia River Recreational and Commercial Fisheries: 2013 and Beyond

Management Strategies for Columbia River Recreational and Commercial Fisheries: 2013 and Beyond Management Strategies for Columbia River Recreational and Commercial Fisheries: 2013 and Beyond Recommendation of the Columbia River Fishery Management Workgroup to the Fish and Wildlife Commissions of

More information

18 March 2016 Oregon Department of Fish and Wildlife

18 March 2016 Oregon Department of Fish and Wildlife 18 March 2016 Oregon Department of Fish and Wildlife Background Joint OR/WA policy adoption 2012 OR re-adoption of rules 6/13 Transition period (2013-2016) Phased allocation shift Mainstem gillnets allowed

More information

Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006

Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006 Wild Steelhead Coalition Richard Burge Conservation VP September 11, 2006 The following are talking points for the WDFW SEPA Scoping Meetings regarding the preparation of the State-wide and the Puget Sound

More information

!Skagit River Basin. Overview FISHERIES 16

!Skagit River Basin. Overview FISHERIES 16 !Skagit River Basin Overview This region includes the watersheds contained by the Skagit River Basin. For the purposes of this review, the Scientific Group reviewed the hatchery programs involving each

More information

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda Date & Time: Thursday, December 14, 2017 9:00 a.m. 11:15 a.m. Place: Merwin Hydro Control Center

More information

STEELHEAD SURVEYS IN OMAK CREEK

STEELHEAD SURVEYS IN OMAK CREEK STEELHEAD SURVEYS IN OMAK CREEK 2002 Annual Report Prepared by Chris Fisher John Arterburn Colville Confederated Tribes Fish and Wildlife Department P.O. Box 150 Nespelem, WA 99155 Prepared for Project

More information

Okanagan Sockeye Reintroduction

Okanagan Sockeye Reintroduction Okanagan Sockeye Reintroduction Backgrounder Elders accounts, and other forms of Traditional Ecological Knowledge (TEK) tell us that many species of salmon once came into the Okanagan Valley and tell us

More information

ROUND BUTTE HATCHERY OPERATIONS PLAN Round Butte Hatchery Plan Page 1

ROUND BUTTE HATCHERY OPERATIONS PLAN Round Butte Hatchery Plan Page 1 ROUND BUTTE HATCHERY OPERATIONS PLAN 2012 Round Butte Hatchery Plan Page 1 Round Butte Hatchery and Satellite (Pelton Ladder) INTRODUCTION Round Butte Hatchery is located on the Deschutes River at the

More information

FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP)

FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP) FINAL HATCHERY AND GENETIC MANAGEMENT PLAN (HGMP) Hatchery Program: Sandy Hatchery Spring Chinook Species or Hatchery Stock: Sandy River Spring Chinook (Stock 11) Agency/Operator: Oregon Department of

More information

April 14, Subject: Rocky Reach Hydroelectric Project, FERC No Rock Island Hydroelectric Project, FERC No

April 14, Subject: Rocky Reach Hydroelectric Project, FERC No Rock Island Hydroelectric Project, FERC No P U B L I C U T I L I T Y D I S T R I C T N O. 1 o f C H E L A N C O U N T Y P.O. Box 1231, Wenatchee, WA 98807-1231 327 N. Wenatchee Ave., Wenatchee, WA 98801 (509) 663-8121 Toll free 1-888-663-8121 www.chelanpud.org

More information

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT FEDERAL AID JOB PROGRESS REPORTS F-20-49 2013 LAKE TAHOE WESTERN REGION NEVADA DEPARTMENT OF WILDLIFE, FISHERIES DIVISION ANNUAL PROGRESS REPORT

More information

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ

OKANAGAN RIVER RESTORATION INITIATIVE - FAQ OKANAGAN RIVER RESTORATION INITIATIVE - FAQ Initiative background: The health of the q awsitk w (Okanagan River) has been severely impacted by the channelization works that occurred in the mid-1950 s.

More information

Hood Canal Steelhead Project A conservation hatchery experiment. Joy Lee Waltermire

Hood Canal Steelhead Project A conservation hatchery experiment. Joy Lee Waltermire Hood Canal Steelhead Project A conservation hatchery experiment Joy Lee Waltermire Cooperating Project Partners: NOAA: NWFSC Behavioral Ecology Team Long Live the Kings WA Department of Fish and Wildlife

More information

Cheakamus River IR 11 Floodplain Restoration Final Report Project Number 13.CMS.01

Cheakamus River IR 11 Floodplain Restoration Final Report Project Number 13.CMS.01 Cheakamus River IR 11 Floodplain Restoration Final Report Project Number 13.CMS.01 Prepared by: Squamish River Watershed Society Box 1791 Squamish, B.C. V08B 0B3 With financial support of: BC Hydro Fish

More information

Survival Testing at Rocky Reach and Rock Island Dams

Survival Testing at Rocky Reach and Rock Island Dams FISH PASSAGE CENTER 1827 NE 44 th Ave., Suite 240, Portland, OR 97213 Phone: (503) 230-4099 Fax: (503) 230-7559 http://www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: FROM: Michele DeHart Erin

More information

MEMORANDUM. Joan Dukes, NPCC. Michele DeHart. DATE: August 5, Data Request

MEMORANDUM. Joan Dukes, NPCC. Michele DeHart. DATE: August 5, Data Request FISH PASSAGE CENTER 1827 NE 44 th Ave., Suite 240, Portland, OR 97213 Phone: (503) 230-4099 Fax: (503) 230-7559 http://www.fpc.org/ e-mail us at fpcstaff@fpc.org MEMORANDUM TO: Joan Dukes, NPCC FROM: Michele

More information

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A.

Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon February 8, By Greg A. Monitoring of Downstream Fish Passage at Cougar Dam in the South Fork McKenzie River, Oregon 1998- February 8, 2 By Greg A. Taylor Oregon Dept. of Fish & Wildlife 315 E. Main Street Springfield, OR 97478

More information

Project Award Presentation

Project Award Presentation University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys

Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys FEDERAL AID IN FISH RESTORATION Job Performance Report, Project F-73-R-9 Subproject II: SALMON AND STEELHEAD INVESTIGATIONS Study I: Salmon Spawning Ground Surveys By Judy Hall-Griswold, Fishery Technician

More information

McKENZIE RIVER HATCHERY

McKENZIE RIVER HATCHERY McKENZIE RIVER HATCHERY PROGRAM MANAGEMENT PLAN 2017 McKenzie River Hatchery INTRODUCTION McKenzie River Hatchery is located along the McKenzie River approximately 22 miles east of Springfield, Oregon.

More information

Lewis River Upstream Transport Plan Interim Final. Prepared by Frank Shrier Principal Fish Biologist PacifiCorp Energy.

Lewis River Upstream Transport Plan Interim Final. Prepared by Frank Shrier Principal Fish Biologist PacifiCorp Energy. Lewis River Interim Final Upstream Transport Plan Lewis River Upstream Transport Plan Interim Final Prepared by Frank Shrier Principal Fish Biologist PacifiCorp Energy December 18, 2009 Page 1 of 31 Table

More information