THE LOVIISA NUCLEAR POWER PLANT DECOMMISSIONING PLAN UPDATE Matti Kaisanlahti NKS-R Decommissioning Seminar, Halden, Norway, November 2013
|
|
- Bertram Smith
- 5 years ago
- Views:
Transcription
1 THE LOVIISA NUCLEAR POWER PLANT DECOMMISSIONING PLAN UPDATE 2012 Matti Kaisanlahti NKS-R Decommissioning Seminar, Halden, Norway, November 2013
2 Agenda Background Licensing Decommissioning schedule Decommissioning work plan Decontamination of primary circuit Needs for personal protective equipment Final disposal Risks of decommissioning work Decommissioning costs Conclusions 2
3 Background Revised every 6th year Studies for the decommissioning plan 2012: - Licensing - The influence of primary circuit decontamination - The needs for personal protective equipment - Risks of decommissioning Immediate dismantlement Disposal at the plant site 3
4 Licensing 4
5 Decommissioning schedule 5
6 Decommissioning work plan 1/2 The dismantling and treatment of the plant s radioactive components can be carried out with currently available technology and methods Large components, such as the reactor pressure vessels and steam generators, as whole components Other decommissioning waste will be mainly packed into concrete and wooden containers The total volume of the decommissioning waste will be m 3, when packed 6
7 Decommissioning work plan 2/2 7
8 Decontamination of primary circuit Decontamination of the primary circuit will be carried out during the preparatory phase First time simulated by MCNP 5-modeling program (Monte Carlo N-Particle) 8
9 Needs for personal protective equipment The dismantling of the activated material will mostly be done by remote-control A lot of different kind of cutting work, so the migration of the dust must be prevented by isolating the working object The personal protective equipment for dismantling will be finally selected according to the work object In the decommissioning work plan the effects of protective equipment on work has been taken into account when estimating the time needed for different works 9
10 Final disposal 10
11 Risks of decommissioning Availability of experienced people Loviisa 2 power plant unit will still be in power generation while the decommissioning of the power plant unit 1 starts The consequences of potential accidents are that the contamination could spread to the environment, or personnel dismantling the power plant could be exposed to high levels of radiation. The risk study showed that there is no need for evacuation or any other restrictions for people living near the power plant The decommissioning of the power plant needs a preparedness plan, which is based on the accident and risk analyses Scope and schedule 11
12 Decommissioning costs Cost item Costs, euros Preparatory phase Main equipment, constructions and materials Dismantling works (contracts) Handling of wastes and final disposal Surveillance, guarding, maintenance and utilities at the site Project administration and design Other costs (personnel and insurances) Costs in all Reserve to cover unspecified costs, 10% Total costs Round total costs 359 M 12
13 Conclusions The decommissioning of the Loviisa power plant units is designed to start in So the licensing of decommissioning should start early 2020's Decontamination of the primary circuit will be carried out during the preparatory phase. The calculations show that decontamination will significantly reduce the collective doses caused by handling of the contaminated material The dismantling and treatment of the plant s radioactive components can be carried out with currently available technology and methods. Still an important part of planning the decommissioning is to follow various technological improvements and decommissioning projects around the world The decommissioning waste will be disposed of in the extension of the existing repository for operating waste. The licensing of the extension of the L/ILW repository should start early 2020s Next decommissioning plan update will be at
14 Thank you for your attention! 14
Safety Standards for Decommissioning Activities
Safety Standards for Decommissioning Activities Koji OKAMOTO The University of Tokyo (Chair of AESJ Decommissioning Standard Committee) Status of decommissioning in Japan Nuclear Power Plant (NPP) under
More informationCONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION
PAGE : 1 / 8 CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION SUB-CHAPTER 1.1 INTRODUCTION SUB-CHAPTER 1.2 GENERAL DESCRIPTION OF THE UNIT SUB-CHAPTER 1.3 COMPARISON WITH REACTORS
More informationR2D2P. Working group report
R2D2P Working group report Working group members: Clédola Cassia Oliveira de Tello (Brazil), Farouk Abdel-Rahman (Egypt), Ibrahim Muhamad (Malaysia), Milan Vujovic (Serbia), Quang Huy Pham (Vietnam) Team
More informationManagement of Reactor Decommissioning
Management of Reactor Decommissioning Tom McCool Project Manager Sellafield Ltd 9/24/2008 1 Introduction/ Background Managed the decommissioning of two research reactors in the UK Scottish Universities
More informationTransportation Emergency Preparedness Program (TEPP) Model First Responder Procedure for Transportation Accidents Involving Radiological Materials
Transportation Emergency Preparedness Program (TEPP) Model First Responder Procedure for Transportation Accidents Involving Radiological Materials This Transportation Emergency Preparedness Program (TEPP)
More informationThe Regulatory Framework Improvement for Safe Decommissioning of Nuclear Power Plants in Korea
The Regulatory Framework Improvement for Safe Decommissioning of Nuclear Power Plants in Korea Sangmyeon Ahn 17th February 2016 Title ~ February 2016 ~ 1 Major Nuclear Facilities Nuclear Power Plants (NPP)
More informationIAEA Regional Workshop Legal and Regulatory Aspects of Decommissioning of Research Reactors June Manila, Philippines
IAEA Regional Workshop Legal and Regulatory Aspects of Decommissioning of Research Reactors 26 30 June 2006 Manila, Philippines Monday, 26 June 2006 09:00 09:45 Opening (A. Dela Rosa, B. Batandjieva) Welcoming
More informationEvaluation and Demonstration of Safety of Decommissioning of
Evaluation and Demonstration of Safety of Decommissioning of Research Reactors Borislava Batandjieva, IAEA Research Reactor Decommissioning Demonstration Project (R2D2P) 26-30 June 2006, Manila, Philippines
More informationEach year, the United States produces many tons of nuclear
36 Storing Waste TA L K I N G I T O V E R Each year, the United States produces many tons of nuclear waste. For more than forty years, scientists have been considering different ways to store this waste.
More informationOBJECTIVE 22: EMERGENCY WORKERS, EQUIPMENT, AND VEHICLES - MONITORING AND DECONTAMINATION
OBJECTIVE Demonstrate the adequacy of procedures for the monitoring and decontamination of emergency workers, equipment, and vehicles. INTENT This objective is derived from NUREG-0654 which provides that
More informationDismantling of Fuel Flask Group B
Dismantling of Fuel Flask Group B Evangelos Maragkos; Gabor Toth; John Marquez; Lucian Leonido Biro; Mitica Dragusin; Yuri Lobach; Phuong Hoai Pham Bruce Watson List of hazards when using A) mechanical
More informationUniversità di Pisa Facoltà di Ingegneria Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione. Emergency Planning.
Università di Pisa Facoltà di Ingegneria Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione Emergency Planning Marino Mazzini Professore Ordinario nel s.s.d. Impianti Nucleari DOCUMENTAZIONE
More informationWHS record keeping - general (Local areas responsible for keeping these records)
WHS record keeping - general (Local areas responsible for keeping these records) Records Examples Retention period Records relating to risk assessment and management of hazards (except particular requirements
More informationRegulatory Review of Safety Assessment for Decommissioning of Facilities Using Radioactive Material
SAFETY ASSESSMENT FOR DECOMMISSIONING Annex III Regulatory Review of Safety Assessment for Decommissioning of Facilities Using Radioactive Material INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1.
More informationContractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.
Working Together Contractor Control Procedures November 2014 Borders College 24/11/2014 1 Working Together 1. Introduction This procedure aims to control the health and safety of contractors working on
More informationNaturally Occurring Radioactive Material (NORM) Supersedes: 05/30/08 (Rev.01) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager
Procedure No.: PA-020-0021 Page: 1 of 8 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document Revision Change Table Revision Number Revision Description Revised By Revision Date
More informationCompetency type. positions. All workers (including contractors), higher degree students and volunteers
Appendix A Training Required for Work Health & Safety Training WHS general and/or site/work specific induction of the emergency procedures and assembly areas Local first aid provisions. of hazards and
More informationMSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for NORM Contaminated Tanks, Vessels & Separators
MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for NORM Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE/32 Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered
More informationIonising Radiations Code of Practice & Guidance Contingency Arrangements
Ionising Radiations Code of Practice & Guidance Contingency Arrangements Where any radiation user uses a source of ionising radiations, which may for example include working with sealed (closed) sources,
More information4.1 The Vice-Chancellor and University Executive Committee
UON Key Risk Area: KRA 1.4 Plant and Equipment 1. Purpose This procedure describes how the University meets its obligation to ensure the health and safety of people, through the processes of selection,
More informationApproved for public release; distribution is unlimited.
EMERGENCY RESPONSE TO HAZARDOUS SUBSTANCE SPILLS AND RELEASES IN ARMY MILITARY TREATMENT FACILITIES TECHNICAL INFORMATION PAPER NO. 59-040-0915 PURPOSE. To provide compliance strategies for responding
More informationYucca Mountain. Los Alamos National Laboratory. Presented to: DOE-EM Performance Assessment Community of Practice Technical Exchange Meeting
Status of the Repository at Yucca Mountain Presented to: DOE-EM Performance Assessment Community of Practice Technical Exchange Meeting Presented by: Dr. Paul R. Dixon Nuclear Waste Program Manager Los
More informationComplementarity between Safety and Physical Protection in the Protection against Acts of Sabotage of Nuclear Facilities
Complementarity between Safety and Physical Protection in the Protection against Acts of Sabotage of Nuclear Facilities Robert Venot Institut de Radioprotection et de Sûreté Nucléaire 77-83, avenue du
More informationQUALITY ASSURANCE SPECIFICATION NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7
QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements
More informationOCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE
OCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE Date: 04-22-2009 Revision: 02 Page: 1 of 6 SUMMARY: SCOPE: REFERENCE REGULATIONS: Employees using laboratory fume hoods shall observe all applicable
More informationEnergiewerke Nord GmbH
Energiewerke Nord GmbH CEG-Meeting Speaker Venue : Workshop JAEA : Holger Schmidt : Oxford, England Date : 05 th -07 th March 2008 1 Visualisation 2 Regional centre at Sayda Bay for conditioning and long-term
More informationTEPP Planning Products Model Procedure
TEPP Planning Products Model Procedure for First Responder Initial Response to Radiological Transportation Accidents 02B00215-13.p65 Prepared for the Department of Energy Office of Transportation and Emergency
More information! Subpart D - Contingency Plans and Emergency Procedures (40 CFR to ) (EPA regulations adopted by NJDEP); and
APPENDIX D EMERGENCY PROCEDURES IN PUBLIC SECONDARY SCHOOLS IN THE EVENT OF A CHEMICAL SPILL There are five major sources of regulations that are potentially applicable to emergencies involving a chemical
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Treatment of G1 Baskets at the CEA Marcoule Site 12027
Treatment of G1 Baskets at the CEA Marcoule Site 12027 Line Fourquet, Didier Boya CEA Marcoule, France ABSTRACT In the dismantling program for the first-generation French reactors in accordance with the
More informationNew Licensed Asbestos Manager Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Manager Training This unit has twenty-three learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationIEM on Severe Accident Management in the light of the accident at the Fukushima Daïchi NPP
IEM on Severe Accident Management in the light of the accident at the Fukushima Daïchi NPP Progress, challenges and perspectives in the field of design features, as regards SAMG IAEA, March 2014 Introduction
More informationSafety Procedures on Vacating Premises
Safety Procedures on Vacating Premises Policy From time to time Departments, Units and Centres of HKU vacate accommodation as a result of relocation or major refurbishment. When any accommodation is vacated,
More informationHAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE (HAZWOPER)
SECTION 28 HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE (HAZWOPER) 28.A. GENERAL. 28.A.01 This Section applies to: a. Hazardous waste site cleanup operations performed under the Comprehensive Environmental
More informationEquipment Decommissioning and Removal
Hard copy of this document, if not marked CONTROLLED in red, is by definition uncontrolled and may be out of date. Doc. No. & Rev. Procedure for Equipment Decommissioning and Removal Rev No. REVISION DCN
More informationSPECIALIZED ONLINE TRAINING COURSE LIST
SPECIALIZED ONLINE TRAINING COURSE LIST Grainger Online Safety Manager provides you with access to online training courses covering today's most relevant safety topics. The training content is designed
More informationCBRN Academy. Assistance and Protection Training Course PROGRAMME PLAN
CBRN Academy Assistance and Protection Training Course PROGRAMME PLAN TRAINING PROGRAMME CONTENTS PAGE ASSISTANCE AND PROTECTION TRAINING COURSE 3 PREVIOUS KNOWLEDGE 3 PREREQUISITES 3 TIME ALLOCATION 4
More informationSafety of Decommissioning: International Cooperation under the IAEA Coordination
Safety of Decommissioning: International Cooperation under the IAEA Coordination Vladan Ljubenov WM 09, Session 68 - Panel discussion IAEA Mission The IAEA serves as an intergovernmental forum for scientific
More informationNuclear safety Lecture 4. The accident of the TMI-2 (1979)
Nuclear safety Lecture 4. The accident of the TMI-2 (1979) Ildikó Boros BME NTI 27 February 2017 The China Syndrome Opening: 16 March 1979 Story: the operator of the Ventana NPP tries to hide the safety
More informationPOLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY
POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY Written By: Nursery Manager Date approved by Directors: Signature: Date for Review: November 2018 COSHH (CONTROL OF SUBSTANCES HAZARDOUS
More informationHazardous Materials Spill Response
Hazardous Materials Spill Response The University of Iowa Rev. 02/10 Department Lab/Room Number PI/Lab Coordinator After Hours Contact Number University Public Safety (Phone 911) Fire, Police, Ambulance
More informationWhat are the benefits of the best practice: New PAAA Enforcement Coordinators will have a better understanding of the associated CFR.
Facility: Hanford Tank Farm/Hanford Best Practice Title: for Point of Contact: Barry Thom 509-376-1814 charles_thom@rl.gov Brief Description of Best Practice: The Price Anderson Amendment Act (PAAA) involves
More informationRefresher Licensed Asbestos Supervisor Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS Refresher Licensed Asbestos Supervisor Training This unit has nineteen learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationIC67 - Pre-Instructional Survey
IC67 - Pre-Instructional Survey 1. What does the term code refer to in the installation of power plant piping? a. National welders code b. Fire protection code c. ASME Boiler and Pressure Vessel Code Section
More informationTechnical Specification Bases Update to the NRC for Period Dated
...~Entergy Entergy Operations, Inc. 7003 Bald Hill Road PO. Box 756 Port Gibson, MS 39150 Tel 601 437 6299 Christina L. Perino Manager Licensing GNRO-2009/00017 March 4, 2009 U.S. Nudear Regulatory Commission
More informationHazardous Materials Spill Response
Hazardous Materials Spill Response The University of Iowa Rev. 01/2019 Department: Lab/Room Number: PI/Lab Coordinator: After-hours Contact Number: University Public Safety - 911 Fire, Police, Ambulance
More informationProcedure: Pressure equipment safety
Procedure: Pressure equipment safety Purpose The purpose of this procedure is to define the method for safe operation and inspection of pressure equipment and the collection and recording of associated
More informationComprehensive dismantlement of the Lepse technical floating base
Comprehensive dismantlement of the Lepse technical floating base M. Kashka, Deputy Technical Director of the Nuclear Icebreaker Fleet, Murmansk Shipping Company, Russia 1. General specifications of the
More informationHunters Point Naval Shipyard
Hunters Point Naval Shipyard Radiological Data Retesting Update HPS CAC Environmental & Reuse Subcommittee Meeting November 7, 2018 Derek J. Robinson, P.E. Navy Base Realignment and Closure (BRAC) BRAC
More informationPage 1 of 5 UC Santa Barbara Policy 5400 Policies Issuing Unit: Administrative Services Date: June 1, 1989 ENVIRONMENTAL HEALTH AND SAFETY I. REFERENCES (Available at the Environmental Health and Safety
More informationReview and Assessment of Engineering Factors
Review and Assessment of Engineering Factors 2013 Learning Objectives After going through this presentation the participants are expected to be familiar with: Engineering factors as follows; Defense in
More informationEmergency Response Code CODE BROWN HAZARDOUS SPILLS. Purpose & Authority. Definitions
CODE BROWN HAZARDOUS SPILLS Purpose & Authority This plan addresses the procedures to be followed in the event of a spill involving a hazardous substance. All hazardous substance spills shall be reported
More informationIAEA SAFETY STANDARDS for protecting people and the environment
IAEA SAFETY STANDARDS for protecting people and the environment DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS DRAFT SAFETY GUIDE DS 482 STATUS: STEP 11 Submission to Review
More informationIntroduction to Emergency Response & Contingency Planning
& Contingency Planning Rationale Why is it important for you to learn this material? Designed for those who may witness a release, this is an introductory course designed to help ensure those who are likely
More informationThe «practical elimination» approach for pressurized water reactors
The «practical elimination» approach for pressurized water reactors V. TIBERI K.HERVIOU International Conference on Topical Issues in Nuclear Installation Safety: Safety Demonstration of Advanced Water
More informationYucca Mountain Update and Transportation Impacts Robert J. Halstead Office of the Governor Nevada Agency for Nuclear U.S. Conference of Mayors Winter
Yucca Mountain Update and Transportation Impacts Robert J. Halstead Office of the Governor Nevada Agency for Nuclear U.S. Conference of Mayors Winter Meeting Washington, DC January 24, 2018 Visit our website:
More informationPlanned reference and intervention levels in Finland
Radioprotection 2013 Vol. 48, n o 5, pages S85 à S92 DOI: 10.1051/radiopro/20139913 Case studies in national experiences Planned reference and intervention levels in Finland Abstract In Finland, Radiation
More informationHAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN
HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN November 2014 UNIVERSITY OF NORTHERN COLORADO HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN TABLE OF CONTENTS I. INTRODUCTION... 3 II. HAZARDOUS
More informationIAEA SAFETY STANDARDS for protecting people and the environment
Date: 2016-08-31 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: STEP 8a For Submission to Member States DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationPolicy Redesign Project. Plant Safety Policy. Table of Contents
Policy Redesign Project All policies and procedures are being reviewed as part of this project. This document is pending review, but remains in effect until the review is carried out. Plant Safety Policy
More information/16/05 11:24 PM Page 1 DECON IN A BAG. Printed on waterproof paper.
46003 9/16/05 11:24 PM Page 1 DECON IN A BAG Printed on waterproof paper. 46003 9/16/05 11:24 PM Page 2 1 Contents of Decon-In-A-Bag Decon-In-A-Bag is designed for emergency response personnel such as
More informationDEPARTMENT SCHOOLS OF HEALTH
PATIENT LIFTING: Work with patients/human subjects may involve lifting and moving of patients. Exposure to physical injury from lifting and moving of patients/human subjects. Avoid unnecessary exposures.
More informationDevelopment of a technology to investigate inside the Reactor Primary Containment Vessel (PCV)
Development of a technology to investigate inside the Reactor Primary Containment Vessel (PCV) - Results of follow up check after the site test - [For April 18 and 19, 2015] April 20, 2015
More informationThe Role of Modeling and Simulation in Extreme Engineering Projects. Jon Berkoe Bechtel National, Inc. San Francisco, California
The Role of Modeling and Simulation in Extreme Engineering Projects Jon Berkoe Bechtel National, Inc. San Francisco, California Introduction Extreme environments add Design Complexity and Risk to Engineering
More informationSevere Accident Management Programmes for Nuclear Power Plants
DS 483: Mode 2 27 March 2017 IAEA SAFETY STANDARDS for protecting people and the environment STEP 11: Approval by the relevant review Committees Reviewed in NSOC (Asfaw) Severe Accident Management Programmes
More informationERIC LAFFORGUE. The Atomic surfers from Fukushima
ERIC LAFFORGUE The Atomic surfers from Fukushima On 11 March 2011, at 2.46 pm, Japan was hit by a magnitude 9.0 earthquake which generated a tsunami on the coast. Here, on Futaba beach, the giant wave
More informationNew Licensed Asbestos Operative Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Operative Training This unit has twenty-two learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationin84061.txt at Page 1 of 6 2/25/00
in84061.txt at www.nrc.gov Page 1 of 6 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C. 20555 SSINS No.: 6835 IE INFORMATION NOTICE NO. 84-61: OVEREXPOSURE
More informationInstructions in the Use of Radiation Protection. Equipment and Radiation Measuring Instruments by. Disaster Response Personnel in a Nuclear Emergency
Instructions in the Use of Radiation Protection Equipment and Radiation Measuring Instruments by Disaster Response Personnel in a Nuclear Emergency April 1,2018 (First edition:april 1,2017) (Second edition:april
More informationDecommissioning International Network
Potential demands & contributions of Enresa to the Decommissioning International Network SOMETHING ABOUT ENRESA State-owned company Responsible, by law, of a) The management of all the radioactive waste
More informationRISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP
RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP Bulatom Conference 2010 Bulgarian Nuclear Energy National, Regional and World Energy Safety 9th -11th June 2010, Riviera complex, Varna Système
More informationTEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY
Page 1 of 9 ISSUED: 5/00 REVISED: 08/06 Introduction Purpose: In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to Ethylene Oxide. Applicability
More informationInstructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.
APPENDIX F - RISK CONTROL PLAN FORMAT FOR CONTRACTORS OF THE PANAMA CANAL Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply,
More informationStandard Test Procedures Manual
STP 204-6 Standard Test Procedures Manual Section: 1. SCOPE This procedure determines the density of asphalt concrete in place by using the backscatter position (the gamma radiation source remains on the
More informationOBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING
OBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING OBJECTIVE Demonstrate the appropriate use of equipment and procedures for determining field radiation measurements. INTENT This
More informationAUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011
AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level
More informationSH&E Training Matrix (Americas, all Business Groups)
SH&E Training Matrix (Americas, all Business Groups) Employee Name: Location: Employee Number: Date: Table 1: All Employees 10 Hour Outreach Course (OSHA General Industry or Construction) 30 Hour Outreach
More informationDecommissioning Regulatory Process
Decommissioning Regulatory Process Deanna Toy June 27, 2018 Diablo Canyon Decommissioning Engagement Panel 1055 Monterey St. San Luis Obispo County Government Building June 27, 2018 Safety Moment AED CPR
More informationThe Energy Seminar The Discussion: Nuclear Energy
The Energy Seminar The Discussion: Nuclear Energy Amory B. Lovins Chief Executive Officer and Chairman of the Board Rocky Mountain Institute MAP/Ming Professor, Stanford University, Spring Qtr. Burton
More informationGEOS 5311 Lecture Notes: Numerical Modeling Example, Yucca Mountain, Nevada
GEOS 5311 Lecture Notes: Numerical Modeling Example, Yucca Mountain, Nevada Dr. T. Brikowski Spring 2010 file:yuccamtn.tex,v (1.11, January 26, 2010), printed March 30, 2011 Introduction 1 Introduction:
More informationDESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS
SAFETY STANDARDS SERIES No. NS-G-1.10 DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS SAFETY GUIDE DS 482 2016-04-20 INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA, C-41 (May 13)
More informationNorthern Kentucky University Issue Date: 11/02/2018 Revised Date: Title: PERSONAL PROTECTIVE EQUIPMENT PROCEDURE OBJECTIVE AND PURPOSE
Northern Kentucky University Issue Date: 11/02/2018 Revised Date: Policy Link: Occupational Safety Policy Title: PERSONAL PROTECTIVE EQUIPMENT PROCEDURE OBJECTIVE AND PURPOSE The objective of this procedure
More informationLevel 4 Certificate in Asbestos Removal for Contract Managers
Level 4 Certificate in Asbestos Removal for Contract Managers January 2012 This qualification has a Credit Value of SEVENTEEN Guided Learning Hours: 94 Ofqual Qualification Number: 600/4478/0 Description
More information24 Hour HAZWOPER 29 CFR (e) The Official Site of Environmental Health & Safety Training. Course Description
NATIONAL ENVIRONMENTAL TRAINERS, INC. 3812 SHOAL CREEK COURT MARTINEZ, GEORGIA 30907 1.888.877.7130 WWW.NATIONALENVIRONMENTALTRAINERS.COM The Official Site of Environmental Health & Safety Training 24
More informationOverview. OPIPOH10 - SQA Unit Code HG Operate an Oil and Gas Process ( Gas Treatment)
OPIPOH10 - SQA Unit Code HG21 04 Overview This process involves the removal of impurities from the gas stream to reach the specified quality. The process boundary is from the inlet such as separator, compressor
More informationLOCKOUT SYSTEM AND POLICIES
LOCKOUT SYSTEM AND POLICIES Lockout System Purpose Employees health and safety takes top priority. Isolating hazardous energy to prevent sudden and unexpected energisation of machines, equipment, and processes
More informationSection 33 TABLE OF CONTENTS Hazardous Waste Operations and Emergency Response (HAZWOPER) 33.A General
Section 33 TABLE OF CONTENTS Hazardous Waste Operations and Emergency Response (HAZWOPER) Section: Page 33.A General... 33-1 33.B Site Safety and Health Plan (SSHP)... 33-1 33.C Responsibilities... 33-4
More informationEMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE
Name Department Initial Orientation Date Supervisor Review Instructions: Check off each section once you have read and discussed it with your Supervisor. EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE
More informationClearing a recent building a chance to get as much material out as indistinguishable from background
Clearing a recent building a chance to get as much material out as indistinguishable from background A rare opportunity Pete Burgess 3/4/2014 Winfrith EAST building Built to treat 300 m 3 of sludge from
More informationCouncil CNL(16)31. Annual Progress Report on Actions Taken Under the Implementation Plan for the Calendar Year EU - Finland
Agenda item 6.1 For information Council CNL(16)31 Annual Progress Report on Actions Taken Under the Implementation Plan for the Calendar Year 2015 EU - Finland CNL(16)31 Annual Progress Report on Actions
More informationMSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for Dismantling Equipment
MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for Dismantling Equipment Document No: Supersedes Revision no: 1 1/10/2004 Custodian: MSE/32 Revision no: 1 1/10/2006 Filename: NORMMGT. DOC Administered
More informationLaboratory Preparedness Checklists for Advanced Planning, Preparing to Close & Safe Re-Entry
Laboratory Preparedness Checklists for Advanced Planning, Preparing to Close & Safe Re-Entry Disruptions, utility outages, and severe weather events may require a laboratory closure. These events have
More informationPART P CONTINGENCY PLANNING FOR RESPONSE TO RADIOACTIVE MATERIAL EMERGENCIES
Sec. P.1 - P.3 SSRCR Volume I - August 2001 PART P CONTINGENCY PLANNING FOR RESPONSE TO RADIOACTIVE MATERIAL EMERGENCIES Sec. P.1 - Purpose. This Part provides for preparedness and response to events involving
More informationHazardous Materials Management. Presented by. James E. Roughton, MS, CSP, CRSP, CHMM.
Hazardous Materials Management Presented by. James E. Roughton, MS, CSP, CRSP, CHMM. Hazardous Waste Operations And Emergency Response (HAZWOPER) 29 CFR 1910.120 Scope Clean-up Operations At Uncontrolled
More informationTemporary Increase in the Emergency Exposure Dose Limit in Response to the TEPCO Fukushima Daiichi NPP Accident December 3, 2014
ひと くらし みらいのために 厚生労働省 Temporary Increase in the Emergency Exposure Dose Limit in Response to the TEPCO Fukushima Daiichi NPP Accident December 3, 2014 Shojiro Yasui,, PhD Office for Radiation Protection
More informationPROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES
NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES
More informationSafety and efficiency go hand in hand at MVM Paks NPP
International Forum Atomexpo 2018 Safety and efficiency go hand in hand at MVM Paks NPP József Elter MVM Paks Nuclear Power Plant Ltd. Hungary Start up Four of the VVER-440/V213 unit Power units up-rate
More informationFUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS])
PAGE : 1 / 16 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS]) 7.0. SAFETY REQUIREMENTS 7.0.1. Safety functions The main functions of the EVU system [CHRS] are to limit the pressure inside the containment
More informationTA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions
3500032/2 IM-P350-02 CH Issue 2 TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.
More information