1 FACILITY MARKING ASSESSMENT & AUDIT SAMPLE ONLY PREPARED FOR: ABC CORPORATION ABCTOWN, TX JULY 23 RD JULY 24 TH, 2003

2 Introduction Brady Corporation, Identification Services Group is pleased to provide this Facility Marking Evaluation and On-site Product Audit to support your interest in making your facility more visually instructive. Since 1914, Brady has been providing high quality OEM, MRO and safety identification materials, resources and solutions. In addition, for over 17 years Brady s Corporation has been providing plant marking and identification support to the industrial community as a value added service. We are a recognized leader in facility and process marking and labeling and have been involved in over 250 labeling projects. We have provided services for a wide range of customers including 3M, Solutia, Monsanto, Dupont, Proctor & Gamble, Hoechst Celanese, Sherwin Williams, Moltech Power Systems, PPG Industries, Motorola, Exxon Mobil, Georgia Pacific, International Paper, Weyerhaeuser, Phillip Morris, Shell Offshore, and others. We have gained extensive experience in data collection, engineering, installation and maintenance of plant marking and labeling solutions. This experience makes us uniquely qualified to provide you with this evaluation of your facility marking and labeling. This report may be used as a foundation in understanding what can be done to improve the pipe, tank, vessel identification, safety and general information signs throughout your facility, and as a first step toward improvement. The evaluation is based on regulatory requirements, industry standards, and good practices. As you review the suggested corrective actions and implement the recommendations in this report we are confident that the improved facility marking will serve to ensure a safer, more efficient, and more productive work place. The report provides you with documentation of the specific issues noted with photographs (when permissible) supporting the comments. The photographs may also serve as a record of the before corrective action status and you may wish to take after photos to emphasize the changes made. Suggestions on how and where to begin to upgrade your plant marking are also included. This report provides an understanding of your current marking status, a list of materials to order to get started, and a vision for future improvement. With the data provided in this report you should be able to proceed with a logical, step-by-step approach to reaching the goal of creating a more visually instructive work environment. The enclosed report provides a comprehensive review of pipe marking, safety signs, and tank and vessel signs. The review of safety signs includes general safety concerns, personal protective equipment marking, confined space marking, safety shower and eyewash station identification, plant egress route identification, and fire protection equipment identification. Additional comments may be included, which identifies potential safety or compliance concerns noted during the facility walk through. Your facility assessment includes - 1) evaluation and documentation of your existing plant marking with photographs to illustrate the walk down notes comments, 2) evaluation of the strengths and weaknesses of your existing labeling and marking program, 3) recommended corrective actions to improve your facility marking and become more visually instructive, 4) suggested priorities for the corrective action steps, 5) identification of the Brady contacts for further support, and 6) a comprehensive list of sign and markers needed to upgrade plant marking

3 TABLE OF CONTENTS SECTION PAGE I. STANDARDS AND REGULATORY REFERENCES 4 II. ASSESSMENT GUIDELINES 6 III. EVALUATION AND RECOMMENDATIONS 10 Assessment Overview 10 Existing Pipe Marking Strengths and Weaknesses 12 Existing Safety Sign Strengths and Weaknesses 13 Existing Tank & Vessel Marking Strengths and Weaknesses 29 Conclusions 31 Corrective Actions and Priorities 31 Brady Corporation Contacts 33 IV. ADDITIONAL SUPPORT SERVICES AVAILABLE 33 V. ON-SITE PRODUCT AUDIT SPREADSHEET

4 Standards and Regulatory References I. PIPE MARKING A. ASME 13.1 (ANSI 13.1) - Scheme For The Identification of Piping Systems B. IIAR Bulletin Identification of Ammonia Refrigeration Piping and System Components C. 29 CFR Incorporation by reference. (ANSI 13.1) D. 29 CFR Process safety management of highly hazardous chemicals E. 29 CFR Appendix C - Compliance Guidelines and Recommendations for Process Safety Management (Non-mandatory). F. 29 CFR Pulp, paper, and paperboard mills. G. 29 CFR Textiles. II. SAFETY SIGNS General Safety Concerns A. ANSI Z535 B. 29 CFR Acetylene C. 29 CFR Hydrogen D. 29 CFR Oxygen E. 29 CFR Nitrous oxide F. 29 CFR General requirements (Personal, protective equipment) G. 29 CFR Eye and face protection H. 29 CFR Respiratory protection I. 29 CFR Head protection J. 29 CFR Occupational foot protection K. 29 CFR Hand protection L. 29 CFR Safety color code for marking physical hazards M. 29 CFR Specifications for accident prevention signs and tags N. 29 CFR (f), Appendix A - Recommended color coding O. 29 CFR Handling materials - general P. 29 CFR Powered industrial trucks Q. 29 CFR Overhead and gantry cranes R. 29 CFR General requirements S. 29 CFR Oxygen-fuel gas welding and cutting T. 29 CFR Pulp, paper, and paperboard mills U. 29 CFR Wiring methods, components, and equipment for general use V. 29 CFR Asbestos W. 29 CFR Carcinogens (4-Nitrobiphenyl, etc.) X. 29 CFR Lead Y. 29 CFR , Appendix B - Employee standard summary Z. 29 CFR Blood borne pathogens Confined Space Marking A. 29 CFR Permit required confined spaces - 4 -

5 Standards and Regulatory References II. SAFETY SIGNS (continued) Safety Shower/Eye Wash Station Marking A. 29 CFR (c) - Medical Services and First Aid Egress Marking A. 29 CFR 1910 Subpart E Appendix - Means of Egress B. 29 CFR Means of egress, general C. 29 CFR Employee emergency plans and fire prevention plans D. 29 CFR Process safety management of highly hazardous chemicals E. NFPA Key Provisions" Fire Protection Marking A. 29 CFR Portable Fire Extinguishers B. 29 CFR Standpipe and hose systems C. 29 CFR "Fixed extinguishing systems, general D. 29 CFR Powered industrial trucks Electrical Panel Marking A. NFPA 70E - Standard For Electrical Safety Requirements For Employee Workplaces B. NEC National Electric Code C. 29 CFR 1910 Subpart S - Electrical General III. TANK & VESSEL SIGNS A. ANSI Z129 - Precautionary labeling hazardous industrial chemicals B. NFPA 49 - Hazardous Chemical Data C. NFPA Guide to fire hazard properties of flammable liquids, gases, and volatile solids D. NFPA Standard system for the identification of the hazards of materials for emergency response E. 29 CFR Hazard Communication F. 29 CFR Occupational exposure to hazardous chemicals in laboratories - 5 -

6 Assessment Guidelines GUIDELINES AND KEY POINTS: I. Pipe Marking 1. Pipes are marked in accordance with standards. 2. Labels are sized appropriately - for pipe diameter, for viewing distance. 3. Labels are installed in a neat, consistent, professional manner. 4. Labels materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 5. Labels are installed so they may be seen from the point of normal approach. 6. Pipe labels are installed: a. adjacent to changes in direction. b. adjacent to valves and flanges. c. on both sides of wall and floor penetrations. d. at any other point of entry into the line. e. at 50-foot (max.) intervals on straight runs. 7. Label text / descriptions are matched to the correct process lines. 8. Label descriptions are adequate for the application. ( To - From information may be more useful than content descriptions, in some facilities.) 9. Labels are color coded in a clear, distinctive manner. (ASME 13.1) 10. Labels are color coded to distinguish between hazardous and non-hazardous contents. 11. Pipe markers are consistently sized, color-coded, printed (text), and installed in the various plant areas. All one program! 12. Flow direction arrows (or tape) are included on, or are adjacent to, each pipe marker. II. SAFETY SIGNS General Safety Concerns 1. Signs are sized appropriately for hazard identification. 2. Signs are installed in a neat, consistent, professional manner. 3. Signs materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 4. Signs are installed so they are highly visible (positioned to clearly warn against potential accident or injury). 5. Sign text is appropriate to the application. 7. Pictograms and symbols are used consistently and appropriately. 8. Signs are color coded in accordance with ANSI Z Safety Color Code 9. Safety Signs are consistently sized, color-coded, printed (text), and installed in the various plant areas. All one program! - 6 -

7 Assessment Guidelines II. SAFETY SIGNS (continued) General Safety Concerns 10. All safety concerns are properly identified -- visually, clearly. Note: Color Codes Danger - red Warning - orange Caution - yellow General Safety - green Notice blue Confined Space Marking 1. Danger Signs are used to mark confined space entry points. 2. Signs are sized appropriately for hazard identification viewing distance. 2. Signs are installed in a neat, consistent, professional manner. 3. Signs materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 4. Signs are installed so they are highly visible even when the access port is open (positioned to clearly warn against potential accident or injury). 5. Sign text is - "Danger: Permit Required Confined Space, Do Not Enter" or similar language appropriate to this application. 7. Pictograms and symbols, if used, are used consistently and appropriately. 8. Signs are color coded per ANSI Z Safety Color Code 9. Confined Space Signs are consistently sized, color-coded, printed (text), and installed. All one program! Safety Showers/Eye Wash Station Marking 1. Signs are installed so they are highly visible and the stations are painted consistently (either yellow or green) with clear area floor marking (positioned to clearly identify locations for quick access in case of emergency and to remind personnel to keep the area clear of any obstructions). 2. Signs are sized appropriately for viewing distances (i.e., must be seen clearly from some distance, should "stand out"). 3. Signs are installed in a neat, consistent, and professional manner. 4. Signs materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 5. Pictograms and symbols, if used, are used consistently and appropriately. 6. Signs are color coded in accordance with ANSI Z Safety Color Code 9. Signs for each application are consistently sized, color coded, printed (text), and installed. All one program! 10. All showers and eye wash stations are marked! Egress Marking 1. Exit signs are sized appropriately to comply with regulations. 2. Signs are installed in a neat, consistent, professional manner. 3. Signs materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears

8 Assessment Guidelines II. SAFETY SIGNS (continued) Egress Marking 4. Pictograms and symbols, if used, are applied consistently and appropriately. 5. Emergency escape route signs are used as part of the Emergency Action Plan. 6. Emergency escape route signs use floor plans or workplace maps to clearly show emergency escape routes. 7. Color coding is used on the emergency escape route signs to aid employees in determining their route assignments. 8. All exits are marked by "readily visible signs" which are "distinctive in color"... "provide contrast with decorations, interior finish, and other signs. 9. Access to exits are marked by readily visible signs and directional arrows in all cases where the exit or way to reach it is not immediately visible to the occupants. 10. Doors that are not exits, but could be confused as exits are marked as "Not An Exit", or identify specific room or area on other side of door. 11. Exit signs are not covered or view blocked by "decorations, furnishings, or equipment" nor are there brightly illuminated signs, displays, or objects that distract from the exit sign so that it may not be noticed. 12. Internally illuminated exit signs are provided where reduction of normal illumination is permitted. 13. Exit signs have 6" letters with a minimum 3/4" stroke width. Fire Protection Marking 1. Signs are installed so they are highly visible and at in-plant mounting locations there are red painted backgrounds and floor clear areas (positioned to clearly identify locations for quick access in case of emergency and to remind personnel to keep the area clear of any obstruction). 2. Signs are sized appropriately for viewing distances (i.e., must be seen clearly from some distance, should "stand out"). 3. Signs are installed in a neat, consistent, and professional manner. 4. Signs materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 5. Pictograms and symbols, if used, are used consistently and appropriately. 6. Signs are color coded in accordance with ANSI Z Safety Color Code. 7. Signs are installed to readily identify all fire protection equipment for emergency response, and preventive maintenance purposes. (Fire hoses, extinguishers, alarms, standpipes, valves, detectors, panels, etc.) 8. Signs for each application are consistently sized, color coded, printed (text), and installed. All one program! 9. Warning or caution signs are posted inside, and at all outside entry ways into areas protected by fixed extinguishing systems that use agents in concentrations known to be hazardous to employee health and safety. (CO2, Halon, etc.) - 8 -

9 Assessment Guidelines Electrical Panel Marking 1. Electrical panels are marked with voltage levels preferably with an orange label. 2. All electrical panels or transformers with 600 volts or greater nominal voltage rating are marked with Danger High Voltage or similar signs. 3. Disconnect switches are marked with the load that they disconnect especially if remotely mounted. 4. Requirements for special protective clothing are posted on entry doors to MCC/Switchgear rooms or on the MCC/Switchgear in accordance with NFPA 70E. 5. MCC/Switchgear breakers are labeled to identify the load they isolate or supply. 6. MCC/Switchgear panels are marked with Arc Flash warning labels. 7. Lighting and electrical distribution panels are identified and the individual breakers are marked with the load supplied. 8. Electrical panels and distribution equipment are marked in a clear, consistent manner throughout the facility. 9. Safety related electrical marking is color coded in accordance with 29 CFR III. TANK & VESSEL SIGNS 1. All containers containing hazardous materials are labeled. 2. Tank & Vessel signs contain the following information: Identification Number Name or description Content hazards, including the 1) chemical name, 2) target organs, and 3) chronic and acute health and physical hazards 3. Signs are installed in a neat, consistent, professional manner. 4. Sign materials are appropriate for the application. No temperature, UV, or chemical damage. No physical damage to labels - rips, tears. 5. Signs can be viewed from all approach points. (For large tanks spanning more than one level - mark at each level and in multiple locations as needed.) 6. Labels are installed on all hazardous chemical containers, except those portable containers only for the immediate use of the employee making the transfer. 7. Tank & Vessel Signs are consistently sized, color-coded, printed (text), and installed. All one program! - 9 -

10 I. ASSESSMENT OVERVIEW: A. On-site Meetings, Interviews, and Walk Through On July 23 rd and July 24 th, 2003, Brady Corporation Identification Services Department personnel evaluated your facility with specific regard to safety and general information signs and markings, pipe marking and tank and vessel marking. Two workdays were required for the on-site audit and interviews. Additional time, equaling approximately three workdays, was required to compile the information and generate the formal report. Day one on-site began with a short pre-audit briefing and agenda discussion. The purpose of the briefing was to receive instruction on the ABC Corp. safety rules and to provide a concise overview of the Brady evaluation methods and on-site requirements for the assessment. After the briefing an ABC Corp. employee served as escort and tour guide providing an initial plant orientation tour. The detailed assessment walk down and evaluation of the areas of concern began at approximately nine AM. Safety sign and tank data was collected for all outside areas, south addition and main building south to north plant areas. Day one on-site ended at approximately four PM. Day two on-site resumed the assessment walk down at eight-ten AM. Completed safety sign and tank data collection for the remaining plant areas at about ten AM. Evaluation of plant pipe marking was completed for all plant areas at approximately three PM. Held an exit briefing with the Plant Manager at about three fifteen PM and discussed safety issues and provided an overview of assessment report topics. The day two portion of the on-site assessment was completed at approximately three thirtyfive PM. Contacts List: John Doe Manager Facility/Manufacturing Engineering

11 I. ASSESSMENT OVERVIEW: B. General Notes There were several specific safety issues that should be corrected. Some of those issues are listed below: 1. Portable fire extinguishers are required to be located, mounted and identified and many were neither located mounted or identified. Ensure that all fire extinguishers have a specifically designated location, that they are mounted and not sitting on the floor or nearby equipment and that each has an identification sign. In addition, recommend painting red backgrounds and floor clear areas for each mounting location to make them stand out from the surrounding environment. 2. Recommend adding large signs on the outside of the buildings and structures to ensure that off-site emergency response teams can quickly and easily get to the proper location in the case that offsite emergency response is required. 3. Identification and marking of confined spaces are incomplete! 4. Safety shower and eye wash stations should have identification signs added and should be painted to stand out from their surroundings. The floor should be painted to identify a clear area to help keep parts and materials clear of safety showers. 5. Switchgear and MCC s need arc flash markings in accordance with NEC and NFPA 70E. 6. The housekeeping program is good overall. However, there are some areas where reminder signs could support the existing program especially in the warehouse, electrical compartments, water treatment, gas compressor building and other peripheral buildings, etc. 7. Pipe marking is a compliance issue only for the piping carrying hazardous substances and that piping should be marked to satisfy the process safety management guidelines. Recommend complete pipe identification and marking for efficiency and error reduction purposes. 8. Found compressed gas bottles tied off with electrical wire or in other cases not tied off at all. Recommend chain or heavy-duty wire for tying off gas bottles to prevent a possible missile hazard; or round up and remove the old construction gas bottles. 9. Exits were generally well marked. However, some backlit EXIT signs were replaced with non-backlit signs and the new sign installations appear to be temporary in some cases. 10. Emergency lights are on in the upper elevations of the stairwells. The general area lighting is on also. Recommend trouble shooting and testing the emergency light circuits to ensure that they will work properly in case of a loss of all AC

12 I. ASSESSMENT OVERVIEW: C. Facility Labeling (Scale) - (5) (4) (3) (2) (1) Excellent Good Fair Poor Very Poor. Assessment Category Rating Value* Pipe Markers 3 Safety Signs General Safety Concerns 4 Confined Space Marking 1 Safety Shower / Eye Wash Stations 3 Egress 4 Fire Protection Marking 4 Electrical Panel Marking 3 Tank & Vessel Signs 1 Average Overall Rating 2.88 Rating = "Poor" *Quantifying Assessment Ratings Definitions: Rating Value Very Poor - little or no marking done, or misleading marking 1 Poor - Some marking done, not complete/haphazard, not maintained 2 Fair - evident effort put forth to some degree, need for marking recognized and acted on 3 Good - well marked, but needing fine tuning or minor revisions or additions 4 Excellent - well marked, no significant changes or additions required

13 I. PIPE MARKING Program Strengths: Plant management and personnel at the ABC Corporation facility have recognized the need for pipe identification and marking and the utility piping has been marked to varying degrees depending on the plant area. Program Weaknesses: The facility pipe-marking program was evaluated for conformance to the ASME A standards and utility piping identification, in most cases, does not meet the standard (i.e., wrong or inconsistent color coding, sized too small for pipe diameter, various types stick-on, wrap around, missing in some locations, etc.) a. Using the attached spreadsheet order or fabricate utility pipe markers that comply with the design requirements of the ASME standard. b. Install pipe markers that are of a consistent style, are properly sized, correctly color-coded and are installed at regular intervals in accordance with the ASME standard

14 II. SAFETY SIGNS Program Strengths: General Safety Concerns 1. Good safety signs and markings have been installed to identify many potentially hazardous situations. Examples include: Eye Protection Required signs, Hazardous Waste Accumulation Site signs, Danger No Smoking signs, Dock Bridge Plate signs, Trash Compactor Warning signs, etc. 2. Compressed gas cylinders were generally well marked and taken care of from a safety perspective: As a rule, cylinders are legibly marked to identify the gas contained and are located or stored in areas where they will not be damaged by passing or falling objects or subject to tampering by unauthorized persons. 29 CFR (f)(5);.101(b);.103(b)(1)(i)(c);.110(c)(2)(i);.103(c)(2)(iii)(f) Generally, compressed gas cylinders were located or stored in a manner to prevent them from creating a hazard by tipping, falling, or rolling. 29 CFR (b);.102(a) Valve protectors (caps) were in place when cylinders were not in use. 29 CFR (b);.110(c)(6)(iii) & (iv):.111(e)(5)

15 II. SAFETY SIGNS Program Strengths: (continued) Safety Shower/Eye Wash Station Marking 1. Some of the eye wash stations were readily identifiable in case of emergency. 2. Eye wash stations were readily accessible in many cases. 29 CFR (c) Confined Space Marking N/A Egress Marking 1. Exits are well marked at the doorways with backlit EXIT signs. Signs are visible and unobstructed and the letter sizes are 6 or greater with a character width of ¾ per OSHA regulations. 29 CFR (q) 2. For the most part exit doors were not blocked and egress routes were generally unobstructed allowing personnel a safe exit route in case of emergency. 29 CFR (d)(1); 37(q) 3. Main production and central warehouse floors are somewhat marked to identify aisles. 29 CFR (b)(2);.176(a)

16 II. SAFETY SIGNS Program Strengths: (continued) Fire Protection Marking Fire extinguisher mounting locations are established and extinguishers are permanently mounted in most cases. 29 CFR (c)(1) Electrical Distribution Panel Marking N/A Other Safety Marking 1. Original Equipment Manufacturer (OEM) safety markings are good on many of the utilities and production machines. Safety instructions, identification of Pinch Points, and other safety concerns on the individual machines are well marked in many cases. Examples: Air Compressors, Fab Machines F01 F09, Air Handling Units on the roof, Expedite Area Equipment A01 A09 Program Weaknesses: General Safety Concerns 1. Compressed gas cylinders should be well marked and taken care of from a safety perspective: Cylinders should be legibly marked to identify the gas contained and should be located or stored in areas where they will not be damaged by passing or falling objects or subject to tampering by unauthorized persons

17 II. SAFETY SIGNS Program Weaknesses: (continued) 29 CFR (f)(5);.101(b);.103(b)(1)(i)(c);.110(c)(2)(i);.103(c)(2)(iii)(f) Compressed gas cylinders must be located or stored in a manner to prevent them from creating a hazard by tipping, falling, or rolling. 29 CFR (b);.102(a) Valve protectors (caps) must be kept in place when cylinders are not in use or connected for use. 29 CFR (b);.110(c)(6)(iii) & (iv);.111(e)(5) 2. Caution - Safety Glasses Required signs are installed on several of the entry doors into the production area. These signs are missing on some doors but are needed to identify the appropriate protective equipment required for entry to the production floor and various operating areas. Signs should be posted at the personnel entry doors and at the entry to areas requiring special PPE. Example: safety glasses required signs at entries to the main production floor, hearing protection signs at the air compressor room entries, etc. a. Order or fabricate PPE signs per attached audit list. b. Install consistent safety signs as required to support personnel and equipment protection. c. Document safety signs installed in such a way that replacements may be purchased or fabricated again, if needed in the future

18 II. SAFETY SIGNS Program Weaknesses: (continued) 3. Hand-written, magic marker, and computer printout paper signs are used in many locations. Generally, handmade or computer printout signs are worded poorly, are not easy to read, are black text on white background (or are Xerox copies) causing them to recede and not stand out, and are mounted in poor locations or by inadequate means. 29 CFR ; ANSI Z a. Provide the site with a means to print custom signs on the spot. *{The Brady Globalmark or Powermark System should be used for this purpose. Custom safety signs from 4 to 10 wide can be created on-site at your facility and paper signs become unnecessary.} b. Require that facility and contractor personnel not use hand made, home made, computer printout, or copied safety signs. 4. The battery charging area needs additional safety signs, to provide clear direction regarding safe work practices in this potentially hazardous work area, and must be kept clear of clutter or debris. 29 CFR (g)(1) - Battery charging installations shall be located in areas designated for that purpose. 29 CFR (g)(10) - Smoking shall be prohibited in the charging area. 29 CFR (g)(11) - Precautions shall be taken to prevent open flames, sparks, or electric arcs in battery charging areas

19 II. SAFETY SIGNS Program Weaknesses: (continued) 29 CFR (a)(1) - The employer shall ensure that each affected employee uses appropriate eye or face protection when exposed to eye or face hazards from flying particles, molten metal, liquid chemicals, acids or caustic liquids, chemical gases or vapors, or potentially injurious light radiation. a. Fabricate and install Battery Charging Area, Caution - Eye Protection Required, Danger No Smoking, etc. signs at each charger location per attached audit lists. b. Clear storage and clutter out of battery charging areas. c. Paint a defined area for battery charging operations and maintain areas clear. 5. Housekeeping is a problem in some areas of the ABC Corporation facility. Proper housekeeping practices are vital to safe and productive plant operations. The OSHA Labor Regulations reference proper housekeeping as a safety requirement in over twenty chapters. For Example: 29 CFR (a)(1) - All places of employment, passageways, storerooms, and service rooms shall be kept clean and orderly and in a sanitary condition. 29 CFR (a)(2);.141(a)(3) - The floor of every workroom shall be maintained in a clean and, so far as possible, a dry condition. Where wet processes are used, drainage shall be maintained, and false floors, platforms, mats, or other dry standing places should be provided where practicable. 29 CFR (b)(3) - "Housekeeping." The employer shall control accumulations of flammable and combustible waste materials and residues so that they do not contribute to a fire emergency. The housekeeping procedures shall be included in the written fire prevention plan

20 II. SAFETY SIGNS Program Weaknesses: (continued) a. Establish a daily routine of cleaning and organizing all work and storage areas

21 II. SAFETY SIGNS Program Weaknesses: (continued) b. Ensure that all potential fire hazards are removed or stored properly (e.g., aerosol cans at column N-12 should be in nearby Flammable Storage Cabinet). c. Using 5S principles visually identify locations for production equipment, carts, tools, etc. Then store items in their designated locations. d. Post housekeeping reminder signs at or near work areas and in problem areas to encourage a culture of routine housekeeping maintenance. e. Post signs assigning housekeeping responsibility / ownership of individual areas to specific plant personnel. 6. Currently outside buildings are not identified. It is a good practice to clearly identifying major buildings and areas with large highly visible signs to be seen from the roadway. This should be done to support and aid emergency response personnel in case of a site emergency where outside help is required. a. Order large durable signs (fiberglass for best durability). b. Install signs for easy location of buildings by fire department personnel. 7. Storage or potential storage areas above office and restroom areas should either be identified as No Storage or floor load limit signs should be installed indicating the maximum safe loading for the storage area. 29 CFR (d)

22 II. SAFETY SIGNS Program Weaknesses: (continued) a. Order or fabricate signs. b. Install signs as needed to identify No Storage areas or load limit posting. 8. Safety signs are inconsistent on the entry doors to the various booths throughout the facility. Color-coding and sign headers should be appropriate for the level of warning required for the application. 29 CFR a. Use signs with a header or signal word to capture immediate attention to identify potential consequences if proper PPE is not used

23 II. SAFETY SIGNS Program Weaknesses: (continued) b. Order or fabricate consistent signage for all entry doors for any given booth. c. Replace inconsistent signs or missing signs. 9. Bench grinders and other power equipment should have safety reminder signs at the machines to remind production and maintenance personnel to wear the proper PPE and to observe the safety precautions appropriate to the specific machine. In addition bench grinders are required to be set a specific tolerances for safe operation and most of the grinders observed were out of specification. 29 CFR (a)(4) Work rests. On offhand grinding machines, work rests shall be used to support the work. They shall be of rigid construction and designed to be adjustable to compensate for wheel wear. Work rests shall be kept adjusted closely to the wheel with a maximum opening of one-eighth inch to prevent the work from being jammed between the wheel and the rest, which may cause wheel breakage. The work rest shall be securely clamped after each adjustment. The adjustment shall not be made with the wheel in motion. 29 CFR (b)(9) the distance between the wheel periphery and the adjustable tongue or the end of the peripheral member at the top shall never exceed one-fourth inch

24 II. SAFETY SIGNS Program Weaknesses: (continued) a. Order or fabricate consistent signs with correct color-coding and a header or signal word to capture attention and remind personnel to wear proper PPE and to take appropriate safety precautions for the equipment in use. b. For bench grinders it is a good practice to install signs reminding machine operators to check and set adjustments prior to each use. c. Install signage in conspicuous locations at or near the machinery. Confined Space Marking 1. Tanks and vessels, and all other spaces with limited access and presenting a potential safety hazard to personnel entering the space, should be marked with a Danger - Confined Space warning sign at each entry to the confined space. The CFR does allow for other equally effective means of informing employees of the existence, location and danger posed by permit - required confined spaces. However, information at the point of need should be the preferred method of keeping employees informed and reminded of confined space entry dangers and permit requirements. 29 CFR (b), (c)(2) Examples: Cooling Tower, Diesel Fuel and Motor Oil Storage Tanks, Compressed Air Receiver, etc. a. Identify all confined spaces in the facility. b. Install danger signs at access points to warn and remind employees of the hazards. Safety Shower/Eye Wash Station Marking 1. Some plant locations do not have eye wash stations within easy reach in case of emergency. In other locations the eye wash stations are blocked and not readily accessible in case of emergency. Safety showers and eye wash stations are required within the work area for immediate emergency use where employees are exposed to injurious corrosive materials. 29 CFR (c);.1048(i)(3) Examples: No Eye Wash At - 1) Pre-Treat Booth Chem. Add Station, 2) Pool 18 Battery Charging Station, 3) Receiving Area Battery Charging Station, 4) Chiller Chem. Add Station

25 II. SAFETY SIGNS Program Weaknesses: (continued) a. Add safety showers and eye wash facilities as required for employee protection and safety. b. Install locator signs. c. It is a good practice to paint backgrounds behind each of the eye wash stations to ensure that they stand out from the general plant environment and are easily identifiable. d. It is a good practice to paint 36 clear areas in front of the eye wash stations to remind plant personnel not to block access to the station and to ensure that the station is easily reachable in case of emergency

26 II. SAFETY SIGNS Program Weaknesses: (continued) Egress Marking 1. Egress paths are blocked, at some Exits, by material or equipment storage and clutter. In some cases aisles and walkways have materials stored in them partially blocking the paths. Exit doors must not be blocked and egress routes must not be obstructed to ensure that personnel always have a safe exit route in case of emergency. 29 CFR (d)(1); 37(q) a. Clearly mark aisles and walk ways preferably with durable paint to accommodate the traffic demands on the surface. b. Install signs to remind plant personnel, including forklift drivers, to keep aisles clear at all times. 2. Emergency Action Plan assembly areas (outside the building) are not marked. Clearly identify the assembly locations for plant personnel in case a fire or other emergency situation requires evacuation of the building. Fire Protection Marking Employers are required to mount, locate, and identify portable fire extinguishers so that they are readily accessible to employees without subjecting the employees to possible injury. For human factors reasons it is best to identify all portable fire extinguisher locations in a consistent manner. 29 CFR (c)(1)

27 II. SAFETY SIGNS Program Weaknesses: (continued) a. Fire extinguishers must be mounted and not sitting on the ground. b. All fire extinguishers must be kept in their mounting location

28 II. SAFETY SIGNS Program Weaknesses: (continued) c. It is good practice to identify fire extinguisher mounting locations with a red painted background for immediate recognition/high visibility to stand out from their surroundings. For marking columns the red background should be painted all the way around the column to be seen from all directions. d. Another good practice is to provide a visual reminder to plant personnel not to block the fire extinguishers. To accomplish the visual marking the fire extinguisher mounting locations should have a clear area painted or marked off in front of them (36 clear space recommended). e. Fire extinguishers must be mounted so that they are readily accessible and not blocked in by other equipment or storage. Electrical Distribution Panel Marking 1. Certain electrical panels are required to have Arc Flash warning labels or signs. NEC Electrical switchboards, panel-boards, industrial control panels, and motor control centers that are likely to require examination, adjustment, servicing, or maintenance while energized, shall be field marked to warn qualified persons of potential electric arc flash hazards. The marking shall be located so as to be clearly visible to qualified persons before examination, adjustment, servicing, or maintenance of the equipment. Install Arc Flash warning labels on MCC/Swgr per attached audit list. 2. Electrical panels are blocked or access is partially limited by storage and clutter in some cases. NEC , , 384-2; 29 CFR (g) Sufficient access and working space shall be provided and maintained about all electrical equipment (especially panel-boards, safety switches, distribution boards, and motor control centers) to permit ready and safe operation and maintenance

29 II. SAFETY SIGNS Program Weaknesses: (continued) For Example: a. Install signs on electrical panels to remind plant personnel to keep areas clear near panels. b. Mark a floor clear area of at least 36 around each electrical panel (Swgr., MCC, distribution panel, equipment disconnects, etc.), to provide a visual reminder to facility personnel to keep electrical panels clear of all obstructions. c. Instruct facility personnel to keep all electrical panel areas clear. 3. Bus duct disconnect switches are not identified with the load they supply, and that load is generally not immediately apparent. 29 CFR (f) Identification of disconnecting means and circuits. Each disconnecting means required by this subpart for motors and appliances shall be legibly marked to indicate its purpose, unless located and arranged so the purpose is evident. Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, shall be legibly marked to indicate its purpose, unless located and arranged so the purpose is evident. These markings shall be of sufficient durability to withstand the environment involved. Identify bus duct disconnects with their respective loads to support safe, efficient maintenance and operations

30 II. SAFETY SIGNS Program Weaknesses: (continued) 4. Approximately ten (10) electrical boxes/receptacles are improperly supported in the Alignment, Expedite, and Door Buildup Cabinet Prep areas. Electrical wiring methods must meet National Electrical Code specifications. NEC states that all boxes and enclosures must be securely fastened. Maximum support intervals for non-metallic sheathed cable are 4 ½ ft. and 12 in. from box or fitting per NEC ; and for non-metallic extensions the maximum support intervals are 8 in. per NEC 342-7(a)(2). Reinstall receptacles using properly support rigid conduit. III. TANK & VESSEL SIGNS Program Strengths: N/A Program Weaknesses: The Diesel Fuel and Mobile Motor Oil storage tanks are not identified. At a minimum the tank should have signs that identify the hazardous chemical contents and the appropriate warnings of the physical and health hazards - for employees Right-To- Know. 29 CFR (f)(5), Appendix E - 4.A Note: The NFPA color code and number may be used to indicate the hazard warnings. However, many employees will not know or remember what the hazard levels or categories are if asked by an auditor. A more user friendly sign works hand-in-hand with safety training and acts as a constant visual reminder about existing chemical hazards

31 III. TANK & VESSEL SIGNS Program Weaknesses: (continued) a. Define an acceptable layout for tank and vessel hazard information / right-toknow signs. b. Order / fabricate signs that will stand up to the environment in which they are used. Sample Tank Signs:

32 : IV. CONCLUSIONS: An overall rating of poor was given to the current labeling and marking of the ABC Corporation facility. This rating was assigned using the method as noted in the Assessment Overview section above. The poor rating was assigned as a result of the current status of plant marking. Upgrades to the current sign program are recommended and consistency should be emphasized when marking safety issues from one plant area to the next. The corrective actions should be reviewed thoroughly and a consistent, conservative facility-marking upgrade program should be implemented. As a first step toward creating a visually instructive plant, management should perform a thorough, methodical review and evaluation of each of the suggestions included in this report. The evaluation should include a decision making process with recommended steps as follows: 1) Determine whether or not to take action on each suggestion provided, 2) Review recommended action steps and decide if the recommended actions or other options are best for the facility, 3) Create a plan of action to implement the recommendations, 4) Evaluate the cost to implement the recommendations, 5) Budget for the action steps, and 6) Set up a tentative schedule of implementation. Some actions may be as simple as 1) ordering consistent designs of the appropriate premade signs and labels, or 2) purchasing do-it-yourself labeling machines that will produce the required signs, tags, and labels, and 3) notifying personnel, through safety training and other appropriate communications, that they are expected to use the standardized signs. In other cases it may take a more involved approach to correct certain noncompliance or safety problems. Each weakness or problem area should be evaluated carefully to determine the specific actions best suited for your facility. V. CORRECTIVE ACTIONS AND PRIORITIES: A. 1. For individual action steps see the Recommended Actions immediately following each item identified in the section above. 2. The following action steps and support service options are recommended steps to bring the facility up to Visually Instructive Plant standards for safety signs, pipes and tanks: Order prefabricated signs, tags and labels based on the attached On-site Product Audit Spreadsheet. - Or - Using the make-it-yourself method, fabricate signs, tags and labels on-site utilizing the Brady Labeling Systems - Power Mark, Globalmark, and Handimark

33 : V. CORRECTIVE ACTIONS AND PRIORITIES: (continued) B. Priorities: From an overall labeling program view, priorities should be determined first, by the most urgent actions to be taken to ensure personnel and equipment safety needs are met. Then, the weak or problem areas that are not in compliance with regulations should be corrected. Finally, consistency and productivity issues should determine the next general level of priorities. With this basic logic in mind, the plant labeling and marking areas are listed in the suggested order of upgrade and correction: Priority Category 1 Safety Signs Confined Space Marking General Safety Concerns Safety Shower/Eye Wash Station Marking Exit & Evacuation Marking Fire Protection Marking Electrical Panel Marking 2 Pipe Markers 3 Tank & Vessel Signs Right-To-Know Information Tank & Vessel Identification Since safety marking and identification relates directly to personnel and equipment safety, all safety sign marking should be a priority. All facets of facility marking for safety are high priority and markers should be purchased or fabricated and installed as soon as practical. The utilities and process systems pipe marking in the various areas of the ABC Corporation facility should be upgraded to conform to the ASME A standards. The Diesel Fuel Oil and Mobile Engine Oil Storage Tanks should be clearly marked with signs that provide employees with easy to read right-to-know information about all hazardous chemicals and personnel hazards. In addition, production and maintenance tasks may be made more efficient by clearly identifying the storage tanks with the tank number and name as identified on design drawings

34 : VI.BRADY CORPORATION CONTACTS Services Project Manager Territory Manager James T. Gables (Jim) Ms. Jane Doe 3816 Snow Creek Drive 210 Appletree Drive Aledo, TX Houston, TX Phone/Fax: (817) Phone: (123) Voice Mail: (800) , ext Voice Mail: (800) , ext. xxxx Additional Support Services Available: Graphical Lockout Procedure Services With Graphical, machine specific Lockout Procedures, you can eliminate wasted time and maximize your maintenance and operations teams productivity. The most time-consuming and difficult requirement of the LOTO standard is the documentation of the procedures/steps necessary to lockout every piece of equipment in your facility. Brady s engineering group has developed a suite of tools that coupled with the experience of writing over 15,000 procedures, allow us to create the procedures faster. These visually instructive procedures have been reviewed by OSHA and meet and exceed their expectations as defined in CFR The visually instructive procedures will allow authorized employees to quickly, confidently and safely establish a state of zero energy within a piece of equipment that is completely under control. The Graphical Lockout Procedure Service includes written procedures, machine analysis, graphics/placards creation, placard and isolation point tag fabrication, installation and zero energy state verification as needed to support your individual requirements. Contact Brady's Identification Services Team to learn more about how our Graphical Lockout Procedure Services can enhance your required plant Lockout/Tagout program. Brady s Identification Services Team (800)

35 AUDIT DETAILS

CONTRACTOR SAFETY RULES

CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES AND REGULATIONS This manual sets forth policy with regards to contractor safety. Each Quinn facility consists of one or several diverse operations under

More information

Savard Labor & Marine Staffing, Inc. Compressed Gas Safety Program Rev3/14

Savard Labor & Marine Staffing, Inc. Compressed Gas Safety Program Rev3/14 Compressed Gas Safety Program Purpose: The purpose of this safety policy and procedure is to establish guidelines for the protection and safety of this company s employees who handle and use compressed

More information

SAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE

SAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE The following questionnaire is designed to aid us in the creation of your policy and procedure manual. Please place a checkmark in the boxes that correspond to the sections that you would like to be included

More information

(g)(1) Space about electric equipment.

(g)(1) Space about electric equipment. s af et yandheal t h. uf cw. org Blocked Electrical Panels 1910.303(g)(1) Space about electric equipment. Sufficient access and working space shall be provided and maintained about all electric equipment

More information

Risk Management Resources

Risk Management Resources Risk Management Resources Machine Guarding Name: Notes: Electrical Systems: Fire Prevention Are circuit breakers accessible to personnel, protected from physical damage, and located away from ignitable

More information

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS... REVISION 0 PAGE 1 OF 8 TABLE OF CONTENTS SECTION PAGE INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...2 PROCEDURE...3 Responsibilities...3 Work Area Safety

More information

Lockout/Tagout Safety Policy

Lockout/Tagout Safety Policy University of North Carolina Wilmington Environmental Health & Safety Workplace Safety Lockout/Tagout Safety Policy GENERAL The UNCW Environmental Health & Safety Department (EH&S) is authorized by UNCW

More information

TOP 5 ITEMS TO CONSIDER WHEN CHOOSING SAFETY SIGNS

TOP 5 ITEMS TO CONSIDER WHEN CHOOSING SAFETY SIGNS TOP 5 ITEMS TO CONSIDER WHEN CHOOSING SAFETY SIGNS By: Thomas Smith, Product Manager, Brady Worldwide Inc. Last updated: January, 2012 Safety signs are a necessary component for warning and communicating

More information

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0 () 30.0 The purpose of the Energy Control Policy (Lockout/Tagout) is to ensure that before any employee performs any servicing and/or maintenance on machinery or equipment, where the unexpected energizing,

More information

FLAMMABLE & COMBUSTIBLE LIQUIDS PROGRAM

FLAMMABLE & COMBUSTIBLE LIQUIDS PROGRAM FLAMMABLE & COMBUSTIBLE LIQUIDS PROGRAM 1.0 PURPOSE This program applies to employees, visitors and contractors (persons) for the purpose of articulating safe work practices when working with and around

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

Leader s Guide ERI Safety Videos

Leader s Guide ERI Safety Videos 1717 SAFE ELECTRICAL WORK PRACTICES & THE 2018 NFPA 70E Leader s Guide ERI Safety Videos SAFE ELECTRICAL WORK PRACTICES & THE 2018 NFPA 70E This easy-to-use Leader s Guide is provided to assist in conducting

More information

TABLE OF CONTENTS PART 2 - CONFINED SPACES

TABLE OF CONTENTS PART 2 - CONFINED SPACES May 11, 2006 TABLE OF CONTENTS PART 2 - CONFINED SPACES Page DEFINITIONS... 2-1 GENERAL... 2-2 RESPONSIBILITIES... 2-2 HAZARD ASSESSMENT AND WORK PROCEDURES... 2-3 IDENTIFICATION AND ENTRY PERMITS... 2-3

More information

Management Plan for Electrical Safety ISD #535

Management Plan for Electrical Safety ISD #535 Management Plan for Electrical Safety ISD #535 Health & Safety Office Maintenance Service Building 10 SE 9 ½ Street Rochester, MN 55904 507-328-4507 MANAGEMENT PLAN FOR ELECTRICAL SAFETY Table of Contents

More information

I. Subject: Compressed gas cylinders, regulators, and portable liquid systems.

I. Subject: Compressed gas cylinders, regulators, and portable liquid systems. I. Subject: Compressed gas cylinders, regulators, and portable liquid systems. II. Objective: To provide safe and effective use, storage, and transport of therapeutic gases. II. Procedure: A. Compressed

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica

More information

HEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS

HEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS Page 1 of 15 1.0 PURPOSE 1.1. Axiall, Plaquemine Complex, has developed this Hot Tap Permit Program to eliminate potential accidents, injuries, and to enhance employee protection. 1.2. To provide for the

More information

Written Programs Listing

Written Programs Listing Written Programs Listing Bloodborne Pathogens (BBP) (29CFR1910.1030) This standard requires that precautions be taken to prevent the transmission of bloodborne pathogens. Viruses and bacteria can be found

More information

Elements of a Lockout/Tagout Program OSHA

Elements of a Lockout/Tagout Program OSHA September 15, 2015 Elements of a Lockout/Tagout Program OSHA 1910.147 Dayna Noble Industrial Safety Consultant Specialist Ohio BWC 567-204-8917 Dayna.noble@bwc.state.oh.us Top 10 most frequently cited

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM LOCKOUT/TAGOUT PROGRAM HOW CLIMATE ENGINEERS INC. COMPLIES WITH THELO/TO STANDARD It is the intent of Climate Engineers Inc. to comply with OSHA s Control of Hazardous Energy Standard (1910.147). The following

More information

SAFETY DIRECTIVE. 2.0 DEPARTMENTS AFFECTED This directive applies to all departments and employees of the Town of Marana.

SAFETY DIRECTIVE. 2.0 DEPARTMENTS AFFECTED This directive applies to all departments and employees of the Town of Marana. SAFETY DIRECTIVE Title: Safety Signs and Accident Prevention Tags Issuing Department: Town Manager s Safety Office Effective Date: September 1, 2014 Approved: Gilbert Davidson, Town Manager Type of Action:

More information

This written Compressed Gas Plan is kept at the corporate office and in the written Safety & Health Program.

This written Compressed Gas Plan is kept at the corporate office and in the written Safety & Health Program. Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Compressed Gas Plan Purpose It is the policy of EMA to permit only trained and authorized

More information

New Employee Safety Indoctrination Checklist

New Employee Safety Indoctrination Checklist New Employee Safety Indoctrination Checklist Emergency Response Training Read and understand the Facility s Emergency Response Action Plan Complete Emergency Response Training Locate the Facility s Evacuation

More information

Effective Date: 26, October 2016 TITLE: COLOR CODING AND ACCIDENT PREVENTION SIGNS AND TAGS GUIDELINES

Effective Date: 26, October 2016 TITLE: COLOR CODING AND ACCIDENT PREVENTION SIGNS AND TAGS GUIDELINES Version: 2 Page: 1 of 5 1.0 Introduction 1.1 Purpose The purpose of this guideline is to communicate information and to establish a method for marking physical hazards. 1.2 Scope This guideline is intended

More information

OSU - COLLEGE OF FOOD, AGRICULTURAL AND ENVIRONMENTAL SCIENCES OSHA COMPLIANCE SELF-INSPECTION CHECKLIST

OSU - COLLEGE OF FOOD, AGRICULTURAL AND ENVIRONMENTAL SCIENCES OSHA COMPLIANCE SELF-INSPECTION CHECKLIST OSU - COLLEGE OF FOOD, AGRICULTURAL AND ENVIRONMENTAL SCIENCES OSHA COMPLIANCE SELF-INSPECTION CHECKLIST INSPECTED BY: BUILDING: ROOM: DATE: YES NA NO COMMENTS Recordkeeping / Safety Training Are all occupational

More information

Hot Work Program. University of Wisconsin-Platteville Reviewed 4/2016

Hot Work Program. University of Wisconsin-Platteville Reviewed 4/2016 Hot Work Program University of Wisconsin-Platteville Reviewed 4/2016 The purpose of the Hot Work Program is to establish safety procedures for employees, contractors, and subcontractors engaging in any

More information

SECTION 7 HAZARD COMMUNICATION PROGRAM

SECTION 7 HAZARD COMMUNICATION PROGRAM SECTION 7 HAZARD COMMUNICATION PROGRAM 7.1 Hazard Communication 7.2 Hazard Communication Standards (HCS) Pictograms and Hazards 7.3 Safety Data Sheets (SDS) Revised: June 2013 Reviewed: October 2008 Date

More information

Management Plan for Compressed Gas

Management Plan for Compressed Gas IEA, INC. N E W P R A G U E A R E A S C H O O L S I S D # 7 2 1 A Service-Disabled Veteran-Owned Small Business Contact Us: BROOKLYN PARK OFFICE 9201 W. BROADWAY, #600 BROOKLYN PARK, MN 55445 763-315-7900

More information

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT)

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) WAC Page 296-307-320 Control of hazardous energy (lockout-tagout). 1 296-307-32001 What does this section cover? 1 296-307-32003 When does this section

More information

General Precautions for handling compressed gases

General Precautions for handling compressed gases General Precautions for handling compressed gases Introduction Compressed gas cylinders can be extremely hazardous when misused or abused. Compressed gas cylinders can present a variety of hazards due

More information

SAFETY AND HEALTH INDUSTRIAL HYGIENE Hazard Communication Program Effective Date: 08/07/14 Standard: 10.1 Document Number: KUSHIH0008 Rev: 01

SAFETY AND HEALTH INDUSTRIAL HYGIENE Hazard Communication Program Effective Date: 08/07/14 Standard: 10.1 Document Number: KUSHIH0008 Rev: 01 Introduction: This Hazard Communication (HazCom) Program manual was designed to meet the requirements of OSHA 29 CFR 1910.1200, MSHA 30 CFR Part 47, and all Rio Tinto Kennecott Copper (RTKC) standards.

More information

PERSONAL PROTECTIVE EQUIPMENT

PERSONAL PROTECTIVE EQUIPMENT C H A P T E R 9 PERSONAL PROTECTIVE EQUIPMENT 9.1. General Personal protective equipment (PPE) when properly used and maintained saves lives and reduces injury and illness. PPE includes equipment for eyes,

More information

University of Vermont Department of Physical Plant Burlington, Vermont

University of Vermont Department of Physical Plant Burlington, Vermont University of Vermont Department of Physical Plant Burlington, Vermont CONTROL OF HAZARDOUS ENERGY SOURCES AND ELECTRICAL HAZARDS LOCKOUT AND TAGOUT PROGRAM in accordance with OSHA 29 CFR 1910.147 REVISED

More information

Safety Sign Assessment for Frequently Endangered Employees

Safety Sign Assessment for Frequently Endangered Employees SAFE Safety Sign Assessment for Frequently Endangered Employees Guidelines: This checklist covers the regulations issued by the U.S. Department of Labor - OSHA under the General Industry standards 29 CFR

More information

THE OSHA LOCK-OUT/TAG-OUT STANDARD

THE OSHA LOCK-OUT/TAG-OUT STANDARD PRESENTER'S GUIDE "LOCK-OUT/TAG-OUT" Training for THE OSHA LOCK-OUT/TAG-OUT STANDARD Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS OUTLINE OF MAJOR PROGRAM

More information

CUSTODIAL Safety Inspection Checklist

CUSTODIAL Safety Inspection Checklist CUSTODIAL Safety Inspection Checklist Priority 1 Any condition which is life-threatening, or may cause injury, or permanent disability Priority 2 Any condition which may cause serious, but non-disabling

More information

OSHA Federal Standards October 1, 2016 September 30, 2017

OSHA Federal Standards October 1, 2016 September 30, 2017 OSHA Federal Standards October 1, 2016 September 30, 2017 29 CFR 1926 SUBPARTS 29 CFR 1926. C M L L E M M E X M MOST FREQUENTLY CITED SERIOUS VIOLATIONS IN CONSTRUCTION 2017.501(b)(13) FALL PROTECTION

More information

Lockout/Tagout - Energy Control Program

Lockout/Tagout - Energy Control Program Lockout/Tagout - Energy Control Program Lockout and Tagging of ELECTRICAL Circuits This portion of the K.R. Miller Contractors, Inc. safety program has been created to maintain a written copy of procedures

More information

2. The purpose of this program is to achieve the following objectives:

2. The purpose of this program is to achieve the following objectives: Section 16A. Lockout and Tagout Program 1. In the course of their duties, personnel at the TFREC may need to secure controls, switches, and equipment in order to prevent injury caused by the sudden, unexpected

More information

Electrical Safety Program

Electrical Safety Program Electrical Safety Program For Adopted LC-1005 Rev. 06/16 Page 1 I. Introduction As part of Organization s overall safety and health program, an

More information

Product Information Report Lockout/Tagout Hazardous Energy Control

Product Information Report Lockout/Tagout Hazardous Energy Control Overview A properly implemented (LOTO) program is designed to protect workers involved in the maintenance and servicing of equipment from the dangerous effects of hazardous energy caused by the unexpected

More information

Doc No: WELDHOT Midland Engineering Co., Inc. Initial Issue Date 12/14/15 Safety Management System

Doc No: WELDHOT Midland Engineering Co., Inc. Initial Issue Date 12/14/15 Safety Management System Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 PURPOSE To provide guidelines for the safe operation of welding, cutting and hot work of equipment, and to itemize

More information

Ways to Meet OSHA Requirements for Safety Signage

Ways to Meet OSHA Requirements for Safety Signage Safety Sign Training Ways to Meet OSHA Requirements for Safety Signage References: 29 CFR 1910.145 and ANSI Z535 Standard This material was developed by MCLBA, Risk Management. It does not necessarily

More information

The Best Use of Lockout/Tagout and Control Reliable Circuits

The Best Use of Lockout/Tagout and Control Reliable Circuits Session No. 565 The Best Use of Lockout/Tagout and Control Reliable Circuits Introduction L. Tyson Ross, P.E., C.S.P. Principal LJB Inc. Dayton, Ohio Anyone involved in the design, installation, operation,

More information

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY 1. CONTROL OF HAZARDOUS ENERGY POLICY AND PROCEDURES A. OSHA References: 29 CFR 1910.147, 29 CFR 1910.332, 29 CFR 1910.333, 29 CFR 1926.417 B.

More information

THE TLC COMPANIES. Self Inspection Program. Self Inspection. Program. Revised 12/13/2002 DC00026

THE TLC COMPANIES. Self Inspection Program. Self Inspection. Program. Revised 12/13/2002 DC00026 THE TLC COMPANIES Self Inspection Program Self Inspection Program Table of Contents SECTION 1 INSPECTION REQUIREMENTS 1 Informal Inspection 1 General Inspection 1 SECTION 3 CONDUCTING INSPECTIONS 5 Preparation

More information

The Basics of Signage

The Basics of Signage 2009 The Basics of Signage The nature of signage is, at the most basic level, designed to let these employees know the nature of the danger and what they need to do to avoid injury Rob Vajko 1/12/2009

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

Self Inspection Checklist

Self Inspection Checklist Self Inspection Checklist Name: Date: Job Name: Title: Time: Job Number: Instructions: Review each lettered subpart under each section that you are responsible for completing. If you have inspected all

More information

Confined Space Policy

Confined Space Policy Confined Space Policy Introduction Employees of Lawrence University may at times be required to enter into and perform work inside tanks, chests, sewers, vessels and other confined spaces. Due to the potentially

More information

Electrical Safety Work Practices

Electrical Safety Work Practices Work Practices I. SCOPE This program covers any SOUTHWESTERN COMMUNITY COLLEGE employee that may work or be exposed to exposed electrical systems: To assure that employees are not exposed to potentially

More information

OFFICE OF STATE HUMAN RESOURCES

OFFICE OF STATE HUMAN RESOURCES OFFICE OF STATE HUMAN RESOURCES NUMBER: PPE-1 TOTAL PAGES: 8 SUBJECT: Personal Protective Equipment Program Effective Date: Revision Date: Revision #: RELATED LEGISLATION: The purpose of this program is

More information

OFFICE SAFETY. Environmental Health and Safety. Greg Hogan Oklahoma State University Environmental Health and Safety

OFFICE SAFETY. Environmental Health and Safety. Greg Hogan Oklahoma State University Environmental Health and Safety Current as of September 2017 OFFICE SAFETY Greg Hogan Oklahoma State University Environmental Health and Safety 405-744-7241 OBJECTIVE Recognize potential hazards in office environments and learn to eliminate

More information

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER EL PASO

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER EL PASO TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER EL PASO Operating Policy and Procedure HSCEP OP: 75.35, Confined Space Entry Program PURPOSE: The purpose of this Texas Tech University Health Sciences Center

More information

LO/TO LOCKOUT/TAGOUT PROGRAM

LO/TO LOCKOUT/TAGOUT PROGRAM LO/TO LOCKOUT/TAGOUT PROGRAM April 2017 CONTENTS Section 1: Introduction...1 Section 2: Purpose... 1 Section 3: Application... 1 Section 4: Definitions... 2 Section 5: Roles and Responsibilities... 4 Section

More information

Contractors' Code of Safe Practice

Contractors' Code of Safe Practice Contractors' Code of Safe Practice Introduction As the controller of premises, The University of Hong Kong has a duty to ensure, so far as is reasonably practicable, the health and safety of all its employees,

More information

Risk Management Resources

Risk Management Resources Risk Management Resources Hazardous Waste Storage Area Safety Checklist Company Name: Notes: Hazardous Waste: Accumulation 1. If you have containers that you use to store waste temporarily (accumulate)

More information

SAFETY TRAINING LEAFLET 02 BASIC RULES FOR SAFETY AND GOOD HOUSEKEEPING

SAFETY TRAINING LEAFLET 02 BASIC RULES FOR SAFETY AND GOOD HOUSEKEEPING SAFETY TRAINING LEAFLET 02 BASIC RULES FOR SAFETY AND GOOD HOUSEKEEPING Doc 23.02/18 EUROPEAN INDUSTRIAL GASES ASSOCIATION AISBL AVENUE DES ARTS 3-5 B 1210 BRUSSELS Tel: +32 2 217 70 98 Fax: +32 2 219

More information

H. Control of Hazardous Energy: Lockout/Tag Out

H. Control of Hazardous Energy: Lockout/Tag Out H. Control of Hazardous Energy: Lockout/Tag Out 1. Purpose Control of Hazardous energy is the purpose of the Lockout- Tagout Program. This program establishes the requirements for isolation of both kinetic

More information

Fiat - Argentina - Wheel Aligner / Headlamp Aimer #16435

Fiat - Argentina - Wheel Aligner / Headlamp Aimer #16435 2017 Wheel Aligner / Headlamp Aimer Operation & Maintenance Manual Safety Fori Automation Version 1.2 4/21/2017 SECTION 1.0 SAFETY These Safety Requirements Must Be Read And Understood By All Machine Operators,

More information

General Requirements of the NEC Advanced Course. Building Officials and Inspectors Educational Association

General Requirements of the NEC Advanced Course. Building Officials and Inspectors Educational Association General Requirements of the NEC Advanced Course Building Officials and Inspectors Educational Association General Requirements -NEC Course Outcome Explain general requirements found in Article 110 of the

More information

SAFETY AND OSHA GUIDELINE CURRICULUM

SAFETY AND OSHA GUIDELINE CURRICULUM SAFETY AND OSHA GUIDELINE CURRICULUM CertiLearn - Non-Industrial OSHA Safety Guidelines These courses are ideal for any small business or non-industrial environment Safety Basics In this course you will

More information

WELDING AND OTHER HOT WORK

WELDING AND OTHER HOT WORK CHAPTER 26 WELDING AND OTHER HOT WORK SECTION 2601 GENERAL 2601.1 Scope. Welding, cutting, open torches and other hot work operations and equipment shall comply with this chapter. Exception: Hot work on

More information

SAFETY POLICY AND PROCEDURE MANUAL All Euramax Subsidiaries. Number K-3.0 Welding Safety Procedures

SAFETY POLICY AND PROCEDURE MANUAL All Euramax Subsidiaries. Number K-3.0 Welding Safety Procedures Number K-3.0 Issued: 1/2009 Revised: 3/2016 Page 1 of 3 1.0 PURPOSE: To standardize procedures associated with production and maintenance welding and to minimize the potential risk of accident or injury

More information

Material Handling and Storage of compressed gases and Air equipment

Material Handling and Storage of compressed gases and Air equipment Material Handling and Storage of compressed gases and Air equipment Compressed gases can be toxic, flammable, oxidizing, corrosive, inert, or some combination of these hazards. Compressed gas cylinders

More information

Accident Prevention Signs and Tags Safety Training Course

Accident Prevention Signs and Tags Safety Training Course Accident Prevention Signs and Tags Safety Training Course Copyright protected. All rights reserved. ATTENTION! This PowerPoint training presentation provides safety education and information to our employees

More information

Hazard Communication Program

Hazard Communication Program The University of Memphis Hazard Communication Program November 2016 Table of Contents University of Memphis Hazard Communication Program Contents Purpose... 1 Scope and Application... 1 Responsibilities...

More information

WHAT IS GAS TANK/CYLINDER?

WHAT IS GAS TANK/CYLINDER? Introduction To use compressed gas cylinders safely, it is important that they are stored properly, handled correctly, used with the correct equipment, and that the properties of the gases they contain

More information

Electrical Safety. Introduction

Electrical Safety. Introduction Electrical Safety 1 Introduction There are four main types of electrical injuries: Electrocution (death due to electrical shock) Electrical shock Burns Falls Around 300 workers were electrocuted in 2008

More information

Welding, Cutting, and Brazing

Welding, Cutting, and Brazing Welding, Cutting, and Brazing Hazards of Welding Operations Fire hazards Metal splatter Electric shock Explosion hazards Released gases Radiant energy Where would these hazards be found on oil and gas

More information

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Compressed Gas Safety Standard

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Compressed Gas Safety Standard CITY AND COUNTY OF DENVER CR&CF RISK UNIT 65.5.11 Compressed Gas Safety Standard 1.0 Introduction 2.0 Scope This standard has been developed to protect all City and County of Denver employees and contractors

More information

Compressed Gasses Safety

Compressed Gasses Safety COMPRESSED GASES SAFETY Last Modified: APR 2015 1 of 6 Compressed Gasses Safety 1 PURPOSE To provide guidelines for transport, storage, handling, and use of cylinders containing compressed gas. 2 SCOPE

More information

SPECIALIZED ONLINE TRAINING COURSE LIST

SPECIALIZED ONLINE TRAINING COURSE LIST SPECIALIZED ONLINE TRAINING COURSE LIST Grainger Online Safety Manager provides you with access to online training courses covering today's most relevant safety topics. The training content is designed

More information

MISSOURI UNIVERSITY OF SCIENCE & TECHNOLOGY Procedure: 3.6

MISSOURI UNIVERSITY OF SCIENCE & TECHNOLOGY Procedure: 3.6 Procedure This electrical safety procedure structures safety procedures to meet the requirements of the NFPA-70E Standard. The program is designed for qualified employees who occasionally must perform

More information

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , , ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.331 335-29 CFR 1926.302, 1926.416, 1926.417 BASIS: The National Safety Council estimates that there are at least 300 deaths

More information

Leader s Guide ERI Safety Videos

Leader s Guide ERI Safety Videos 1419 SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E Leader s Guide ERI Safety Videos SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E This easy-to-use Leader s Guide is provided to assist in conducting a

More information

SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE CAT A-2 SOP #33

SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE CAT A-2 SOP #33 SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE Date Issued:

More information

SHOP SAFETY INSPECTIONS

SHOP SAFETY INSPECTIONS SHOP SAFETY INSPECTIONS SOP No 1.014 1 PURPOSE 1.01 This document details the procedures and forms to be used when performing safety inspections for shops. 2 EXPECTATIONS 2.01 Shops and storage closets

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM March 2017 CONTENTS Section 1: Introduction... 1 Section 2: Purpose... 1 Section 3: Definitions... 2 Section 4: Roles and Responsibilities... 4 Section 5: Testing and Monitoring...

More information

There is one Fact Sheet for each module presented in the course. They are easily printed either singly or collectively.

There is one Fact Sheet for each module presented in the course. They are easily printed either singly or collectively. OSHA 10 GENERAL INDUSTRY FACT SHEETS The following Fact Sheets are provided to assist the student in identifying content and learning objectives for each module presented in the training course. There

More information

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.147 BASIS: Approximately three million workers in the United States face risks from uncontrolled energy when servicing machinery

More information

PURPOSE OF THE POLICY

PURPOSE OF THE POLICY Title: Safe Storage, Handling, Use and Disposal Procedures of Compressed Gas Cylinders Effective Date: November 2005 Revision Date: March 1, 2017 Issuing Authority: Responsible Officer: VP, Capital Projects

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program Table of Contents INTRODUCTION... 2 FORWARD... 2 OBJECTIVE... 2 APPLICABILITY... 2 RESPONSIBILITIES... 3 PROGRAM ENFORCEMENT... 4 RECORDKEEPING... 4 LOCKOUT TAGOUT EQUIPMENT... 5

More information

14. Personal Protection Chapter , WAC

14. Personal Protection Chapter , WAC 14. Personal Protection Chapter 296-800-160, WAC 1.0 Introduction PLU will provide most required personal protective equipment (PPE). The employee may be required to provide PPE that is of a personal nature

More information

SOUTHEAST REGIONAL MAINTENANCE CENTER LOCAL STANDARD ITEM CFR Part , Operator Qualification and Certification

SOUTHEAST REGIONAL MAINTENANCE CENTER LOCAL STANDARD ITEM CFR Part , Operator Qualification and Certification SOUTHEAST REGIONAL MAINTENANCE CENTER LOCAL STANDARD ITEM ITEM NO: 099-74SE DATE: 18 FEB 2014 CATEGORY: I 1. SCOPE: 1.1 Title: General Safety Requirements; accomplish 2. REFERENCES: 2.1 Standard Items

More information

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018 University Policy Volume E2: Environment, Health, Safety and Security E2.14 Control of Hazardous Energy Responsible Office: Facilities Management Responsible Officer: Safety Officer POLICY STATEMENT All

More information

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Introduction 2 Regulatory Requirements 2 Protective Materials

More information

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012 PAGE 1 OF 7 LOCK-OUT TAG-OUT (LOTO) THE CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROGRAM PURPOSE: 1. This standard establishes lockout/tagout (LOTO) procedures for the safety of personnel working on

More information

5.0 Store. safely IN THIS SECTION: 5.1 Decanting or transferring

5.0 Store. safely IN THIS SECTION: 5.1 Decanting or transferring 5.0 Store hazardous substances safely IN THIS SECTION: 5.1 Decanting or transferring hazardous substances 5.2 Incompatibles 5.3 Store only what you need, store it safely 5.4 Gas cylinders 5.5 Oxy-acetylene

More information

Gettysburg College. Energy Control Program

Gettysburg College. Energy Control Program Gettysburg College Energy Control Program Adopted October 2009 Reviewed and Updated February 2015 Reviewed and Updated July 2015 I. Energy Control Procedures Table of Contents A. General Lockout Procedures

More information

General Safety and Health Provisions for Construction Self Inspection Checklist

General Safety and Health Provisions for Construction Self Inspection Checklist Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: General Safety and Health Provisions for Construction Self Inspection Checklist Instructions:

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

James J Arendas Ph.D.

James J Arendas Ph.D. James J Arendas Ph.D. Safety Program Elements Management Commitment Hazard Identification Hazard Correction Training Hazard Identification Qualified and Competent Persons Identify Hazards in the Workplace

More information

Hazardous Energy Control (Lockout-Tagout)

Hazardous Energy Control (Lockout-Tagout) Hazardous Energy Control (Lockout-Tagout) The purpose of this program is to prevent inadvertent operation or energization of machines, equipment, or processes in order to protect employees and establish

More information

Escondido Union High School District. Hazard Communication Plan

Escondido Union High School District. Hazard Communication Plan Escondido Union High School District Hazard Communication Plan Updated June 2017 Table of Contents Introduction. 2 Globally Harmonized System (GHS). 2 Hazardous Substance Inventory. 3 Safety Data Sheets

More information

SAFETY DIRECTIVE 3.0 REFERENCES. 3.1 See Appendix B

SAFETY DIRECTIVE 3.0 REFERENCES. 3.1 See Appendix B SAFETY DIRECTIVE Title: Hot Work Issuing Department: Town Manager s Safety Office Effective Date: September 1, 2014 Approved: Gilbert Davidson, Town Manager Type of Action: New 1.0 PURPOSE To provide proper

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM A confined space, as defined in 29 CFR 1910.146: Is large enough and so configured that an employee can bodily enter and perform assigned work AND Has limited or restricted means

More information

Environmental: Hazardous Waste: Satellite Accumulation Areas (SAA)

Environmental: Hazardous Waste: Satellite Accumulation Areas (SAA) https://ehs.mit.edu/site/content/inspections-level-i-level-ii Level I Guidance Documentation Environmental: Hazardous Waste: Satellite Accumulation Areas (SAA) 1. Is all hazardous waste stored in the satellite

More information

11/2/2017. Course Objectives. Overview

11/2/2017. Course Objectives. Overview Course Objectives The objective of this CBT module is to insure that personnel receive basic training in electrical safety. Every employee's work involves electricity. This may vary from typical electrical

More information