Health & Safety Policy Arrangements Temporary Compressed Gas Installation (Inert and Oxidising Gas Only) (HSA 23)
|
|
- Horatio McDonald
- 5 years ago
- Views:
Transcription
1 Health & Safety Policy Arrangements Temporary Compressed Gas Installation (Inert and Oxidising Gas Only) (HSA 23)
2 Version Date Author Changes 1 CB First written arrangements
3 1. Purpose To set a standard for INERT AND OXIDISING GAS temporary gas installations in use in University laboratories. All users of temporary compressed gas supply systems shall adhere to these standards without exception. All current temporary compressed gas supplies shall be updated to meet the necessary standards within two weeks of issue. Warning; Flammable and Toxic gas supply shall only be permanent installations and at no point must a temporary compressed gas supply system be used for these groups of gases. 2. Initial Request i. Prior to a temporary compressed gas supply being installed, the proposing user shall submit an application to the appropriate College H&S co-ordinator, detailing the requirement for a temporary compressed gas supply. ii. The installation may not proceed until confirmation has been received from the H&S coordinator in writing iii. The installation will be inspected against the initial set-up checklist by the assigned H&S coordinator prior to commencement of use. iv. The installation will be issued a reference number for the duration of its use and will be safety tagged by the H&S co-ordinator indicating the system safe for use. Application form (hyperlink) 3. Time Limits For Temporary Installations All temporary compressed gas supply systems shall have a maximum permissible operation period of 3 months, with an option for a maximum 1 month extension, if deemed essential to keep the system in use for a longer period of time. The extension is granted following a successful application process, authorised by the appropriate H&S co-ordinator. Requirements for use beyond the maximum permissible 4 month period shall be considered for a fixed gas supply system and subject to all current legislation, PSSR2000, and require a full Written Scheme of Examination. 4. Mandatory Requirements of ALL Temporary Installations All temporary compressed gas supplies will consist of the following items:- 1) Maximum permissible outlet pressure of 10 barg (145 psi) 2) Cylinder mounted gas regulator designed for use with the specific gas.* 3) Cylinder mounted regulator shall meet the requirements of inlet pressure and outlet pressure with gauges for each. 4) Cylinder mounted regulator must be fitted with a regulator PRV (pressure relief valve).
4 5) Cylinder mounted regulator to be of suitable material of construction to suit the specific gas.* 6) Cylinder mounted regulator shall be the correct orientation to meet the cylinder valve design. 7) Cylinder mounted regulator must not be modified by the user and shall be purchased fit for purpose. 8) Cylinder mounted regulator must be within its 5 year life please check date markings on regulator body. 9) Low pressure flexible hose shall be fit for purpose, gas type and pressure dependant.* 10) It is not permissible to use worn drive hose clips to secure the low pressure hose to the cylinder mounted regulator nor the process equipment. Twin ferrule gas compression fittings or hose barb with flexible hose fitted by means of sized O clips are acceptable. 11) The gas cylinder shall be supported at all times by suitable means, chain, strap or bracket to a suitable fixed point. It must not be fixed to a portable table or bench. The bracket shall be fixed by means suitable to support the weight of the gas cylinder. 12) The restraining device shall be located so it is approximately 2/3rds up the cylinder. The restraining device must never be below the midway point of the gas cylinder. * (check against material safety data sheets for suitability. Alternatively use Air Liquide s encyclopaedia on gases as it defines what is compatible with the gas. 5. Inspection Schedule Once installed, users must undertake a comprehensive inspection regime, with the responsible person being named on the application: 1) Weekly leak test all gas joints with approved leak detection methods. 2) Weekly visual health check by the user, Health Check document to be completed and sent to the appropriate H&S co-ordinator at the start of each week. 3) Monthly Health Check inspection by designated competent person. 6. Operator Duties 1) Only those who have undertaken the University s compressed gases e-learning programme and practical training may be authorised to set up a temporary compressed gas supply. The temporary compressed gas installation must be inspected and passed fit for purpose by the designated competent person prior to use. 2) The temporary compressed gas supply shall be leak tested weekly by the trained operator using approved leak detection methods. 3) The temporary compressed gas supply shall receive a weekly visual inspection by the operator in line with the University s checklist (see section 7). This shall be submitted to the appropriate college H&S advisor at the start of each week. Weekly health check doc (hyperlink)
5 4) All temporary compressed gas supplies shall be turned off at the gas cylinder each night unless this will interfere with the current experiment. 5) Only those who have undertaken the University s compressed gases e-learning programme and practical training may be authorised to; manually handle and/or replace gas cylinders (in accordance with the safe operating procedure for changing a cylinder) and operate the temporary compressed gas supply system.
6 7. Weekly User s Mandatory Check For Temporary Compressed Gas Supply 1) Leak test all joints to include all gas fittings and joints from the gas cylinder to process equipment using an approved gas detection fluid/device. 2) Visual inspection of the cylinder mounted regulator. Confirm the gas type is compatible to that of the gas it is intended for. Check inlet pressure is equal to or greater than the gas cylinder fill pressure. Check the date is current. Never use out of date equipment. Confirm that you are using the correct orientation of the cylinder regulator to meet with that of the gas cylinder valve. Side outlet use a side inlet or top outlet use a bottom inlet. Check the outlet pressure meets requirements. Max 10barg. Check the regulator is marked with manufacturer or suppliers name. Check no PTFE tape in use or present on fittings. Check no damage to the low pressure flexible hose. Check there are no worn drive hose clips in use. Check the gas cylinder is suitably secured. Signed off by operator/user 8. Monthly Mandatory Competent Persons Health Checks for Temporary Compressed Gas Supply 1) Leak test all joints to include all gas fittings and joints from the gas cylinder to process equipment using an approved gas detection fluid/device. 2) Visual inspection of the cylinder mounted regulator. Confirm the gas type is compatible to that of the gas it is intended for. Check inlet pressure is equal to or greater than the gas cylinder fill pressure. Check the date is current. Never use out of date equipment. Check the temporary compressed gas supply system has been weekly inspected. Confirm that you are using the correct orientation of the cylinder regulator to meet with that of the gas cylinder valve. Side outlet use a side inlet or top outlet use a bottom inlet. Check the outlet pressure meets requirements. Max 5barg. Check the regulator is marked with manufacturer or suppliers name. Check no PTFE tape in use or present on fittings. Check the regulator HP inlet fitting for damage to the face seal or if appropriate sealing washer in place and in good serviceable condition. Only replace with gas specific seal. Check the threads on the HP inlet fitting are not damaged. Check the LP outlet fitting is not damaged. Ensure the pressure control knob is captive when fully backed off. Check the regulator has not been tampered with or modified. Check the gauges are not damaged. Confirm the inlet stem is straight and not bent as this could indicate it has been dropped.
7 Check no damage to the low pressure flexible hose. Check there are no worn drive hose clips in use. Check the gas cylinder is suitably secured. NB only remove the regulator if this will not interfere with the experiment. Inspection may have to be earlier or later than set monthly period if this should arise. Signed off by competent person 9. Records All records must be forwarded to the appropriate H&S co-ordinator.
8 Temporary Compressed Gas Installation Section 1 Application: College: Building Location: Room No: Project: Project Investigator: Expected timescale of installation: Reason for temporary installation (rather than permanent fixed): Section 2 - Permission: Temporary Gas Installation Number: Approved By: Section 3 - Initial set-up check by H&S co-ordinator: Standards to be confirmed by the H&S co-ordinator on initial set-up: 1 Confined space risk assessment (oxygen depletion) undertaken 2 Maximum permissible outlet pressure of 10barg (145psi) 3 Maximum permissible outlet pressure of 10barg (145psi) 4 Cylinder mounted regulator shall meet the requirements of inlet pressure and outlet pressure with gauges for each. 5 Cylinder mounted regulator must be fitted with a regulator PRV (pressure relief valve). 6 Cylinder mounted regulator to be of suitable material of construction to suit the specific gas. 7 Cylinder mounted regulator shall be the correct orientation to meet the cylinder valve design. 8 Cylinder mounted regulator must not be modified by the user and shall be purchased fit for purpose. 9 Low pressure flexible hose shall be fit for purpose, gas type and pressure dependant. 10 Worn drive hose clips are not used to secure the low pressure hose to the cylinder mounted regulator nor the process equipment. Twin ferrule gas compression fittings or hose barb with flexible hose fitted by means of sized O clips are acceptable. 11 The gas cylinder shall be supported at all times by suitable means, chain, strap or bracket to a suitable fixed point. It must not be fixed to a portable table or bench. The bracket shall be fixed by means suitable to support the weight of the gas cylinder. 12 The restraining device shall be located so it is approximately 2/3rds up the cylinder. The restraining device must never be below the midway point of the gas cylinder.
9 Section 4 - Weekly checks Competent person to undertake weekly checks: Check 1 Leak test all joints to include all gas fittings and joints from the gas cylinder to process equipment using an approved gas detection fluid/device. 2 Carry out visual inspection of the cylinder mounted regulator: Is the gas type compatible to that of the gas it is intended for. Check that the inlet pressure is equal to or greater than the gas cylinder fill pressure. Is the equipment date current. Never use out of date equipment. Is there correct orientation of the cylinder regulator to meet with that of the gas cylinder valve. Side outlet use a side inlet or top outlet use a bottom inlet. Dies the outlet pressure meet requirements. Max 10 barg. Is the regulator marked with manufacturer or suppliers name. Confirm that no PTFE tape is in use or present on fittings. Check there is no damage to the low pressure flexible hose. Check there are no worn drive hose clips in use. Check the gas cylinder is suitably secured. Pass/ Yes Fail/ No Action taken Checked by/date
10 Section 5 - Monthly checks: Competent person to undertake monthly checks: Training undertaken: Date Check undertaken by Pass/Fail Section 6 Request for extension of 3 month temporary installation Reason for request for extension: Reason why installation may not be fixed: Extension Approved by:
11 Process for Temporary Compressed Gas Installation User requires a temporary gas installation Application to H&S co-ordinator Meets temp installation requirements Doesn t meet temp install requirements Install inspected Permanent installation required Doesn t meet standards Meets standards User must upgrade to meet standards - do not use until tagged ID no given and tagged Weekly user check Monthly check
Installation Operating Instructions for Simple Duplex Manual Manifolds PX-TSD Series
Introduction Powerex manifolds are cleaned, tested and prepared for the indicated gas service and are built in accordance with the Compressed Gas Association guidelines. The manifold consists of a regulator
More informationFILTER REGULATORS MODEL NO: CAT155 & CAT156 FITTING & MAINTENANCE INSTRUCTIONS PART NO: & ORIGINAL INSTRUCTIONS
FILTER REGULATORS MODEL NO: CAT155 & CAT156 PART NO: 3120169 & 3120170 FITTING & MAINTENANCE INSTRUCTIONS ORIGINAL INSTRUCTIONS GC0117 INTRODUCTION Thank you for purchasing this CLARKE Filter/Regulator.
More informationULTRAMAGIC, S.A. MAINTENANCE MANUAL SUPPLEMENT NUMBER 14 INTRODUCTION OF A VAPOUR PILOT VALVE OPTION FOR THE ULTRAMAGIC MK 21 RANGE OF BURNERS
S14.1 INTRODUCTION OF A FOR THE ULTRAMAGIC MK 21 RANGE OF BURNERS Section 1 1.0 Introduction This supplement defines the maintenance and inspection requirements for the range of Ultramagic MK 21 burners
More informationGlasgow City Council EDUCATION SERVICES. Technician Support Service
Glasgow City Council EDUCATION SERVICES Technician Support Service Technician Guidance Sheets TGS/10a Use & Inspection of Gas Cylinders & Associated s Issued by Technician Support Service Date September
More informationCITY AND COUNTY OF DENVER CR&CF RISK UNIT Compressed Gas Safety Standard
CITY AND COUNTY OF DENVER CR&CF RISK UNIT 65.5.11 Compressed Gas Safety Standard 1.0 Introduction 2.0 Scope This standard has been developed to protect all City and County of Denver employees and contractors
More informationSAFETY POLICY AND PROCEDURE MANUAL All Euramax Subsidiaries. Number K-3.0 Welding Safety Procedures
Number K-3.0 Issued: 1/2009 Revised: 3/2016 Page 1 of 3 1.0 PURPOSE: To standardize procedures associated with production and maintenance welding and to minimize the potential risk of accident or injury
More informationnual cylinder change-over unit N) manual Automatic gas cylinder change-over unit Operating manual
nual cylinder change-over unit N) manual Automatic gas cylinder change-over unit Operating manual Copyright 2014 Eppendorf AG, Germany. No part of this publication may be reproduced without the prior permission
More informationBCGA GUIDANCE NOTE 17
BCGA GUIDANCE NOTE 17 BCGA POLICY AND GUIDANCE FOR THE SAFE FILLING OF THIRD-PARTY OWNED AND / OR MAINTAINED TANKS Revision 2: 2013 BCGA GUIDANCE NOTE 17 BCGA POLICY AND GUIDANCE FOR THE SAFE FILLING OF
More informationOperation Manual Piston Sensed Gas Pressure Regulators
687 Technology Way Napa, CA 94558 Phone: (707) 259-0102 FAX: (707) 259-0117 www.aptech-online.com Operation Manual Piston Sensed Gas Pressure Regulators (Models KT9, KT10, Welded KT10, KT12) Table of Contents:
More informationSAFETY FEATURES OF PORTABLE CRYOGENIC LIQUID CONTAINERS FOR INDUSTRIAL AND MEDICAL GASES
SAFETY FEATURES OF PORTABLE CRYOGENIC LIQUID CONTAINERS FOR INDUSTRIAL AND MEDICAL GASES AIGA 016/04 Asia Industrial Gases Association 298 Tiong Bahru Road, #20-01 Central Plaza, Singapore 168730 Tel :
More informationWilkins Safety Group
H & S Guidance - Pressure Systems and Gas Cylinders INTRODUCTION If pressure systems fail, they can seriously injure or kill people. Every year there are about 150 dangerous occurrences (reported to the
More informationBRITISH COMPRESSED GASES ASSOCIATION Registered office: 4a Mallard Way, Pride Park, Derby, UK. DE24 8GX Company Number: 71798, England
BRITISH COMPRESSED GASES ASSOCIATION Registered office: 4a Mallard Way, Pride Park, Derby, UK. DE24 8GX Company Number: 71798, England www.bcga.co.uk TECHNICAL INFORMATION SHEET 29 OXY-FUEL GAS EQUIPMENT
More informationGUIDELINES. Systems. Pressure
GUIDELINES Pressure Systems Guidelines Pressure Systems Safety Regulations SI 2000 No 128 Examination Requirements for LPG Systems on Fork Lift Trucks Document Reference: PSG 12 Issue 2.1 Dated 30/01/12
More informationProcess Name Compressed Gas Cylinders Program
CNM WAY PROCESS CNM Process Name Compressed Gas Cylinders Program (07/11/2018 Revision) Overview of Compressed Gas Cylinders Program Purpose: To prevent injury from failure of compressed gas cylinders
More informationGCE CENTRAL GAS SYSTEMS THE DRINKS DISPENSE INDUSTRY EQUIPMENT FOR GAS SUPPLIER SYSTEMS
THE DRINKS DISPENSE INDUSTRY EQUIPMENT FOR GAS SUPPLIER SYSTEMS THE GCE BUSINESS GCE has almost 100 years of experience in the manufacture and supply of high pressure gas equipment. During this time the
More informationBauman Machine Inc. COMPRESSED GAS CYLINDER SAFETY
Bauman Machine Inc. COMPRESSED GAS CYLINDER SAFETY Many industrial and laboratory operations require the use of compressed gases for a variety of different operations. Compressed gases present a unique
More informationACS.CoNGLP1 SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC NATURAL GAS TO LPG GENERIC
ACS.CoNGLP1 SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC NATURAL GAS TO LPG GENERIC Issue 4.2 ACS. SMB 1 CoNGLP1 INITIAL & RE-ASSESSMENT Range All LPG fittings. Comprises: 2. Gas emergency
More informationINSPECTION of PORTABLE and OXY FUEL GAS SYSTEMS
1.0 PURPOSE This work Instruction describes the procedure for the inspection, testing and identification requirements of portable and mobile oxy-fuel gas systems for welding, cutting, heating to ensure
More informationPremium Series. Economical Price & Reliable Performance. High Quality. Rust-Resistant. Long Life. Tamper-Resistant locking Screw.
Premium Series High Quality Forged Brass Body Rust-Resistant Nickel Plated Finish Long Life Corrosion Resistant Valve Seat Economical Price & Reliable Performance Tamper-Resistant locking Screw Reduces
More informationBCGA GUIDANCE NOTE GN 23
BCGA GUIDANCE NOTE GN 23 Identifying Gas Safety Training Requirements in the Workplace 2012 BCGA GUIDANCE NOTE GN 23 Identifying gas safety training requirements in the workplace Copyright 2012 by British
More informationWorking Environment Safety Assessment
For your own safety and/or safety of your workforce, and to improve the efficiency of your business practices, you should be aware of, and be up to date with, the key safety issues and good practices relevant
More informationPressure Differential Automatic Manifold For LPG. PDH1000 Series. LPG Installation & Operations Instructions
Pressure Differential Automatic Manifold For LPG PDH1000 Series LPG Installation & Operations Instructions Precise Equipment Company 3822 Market St., STE 101 Denton, Texas Phone : 800.795.8388 Precise
More informationDUPLEX PRESSURE REDUCING SET
DUPLEX PRESSURE REDUCING SET Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com
More informationGUIDELINES FOR CONDUCTING HYDROGENATION REACTIONS
Page 1 of 5 GUIDELINES FOR CONDUCTING 1. Definition of Hydrogenation and Hydrogenolysis Reactions Hydrogenation reactions are synthetic transformations involving hydrogen, metallic catalysts (such as nickel,
More informationTEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125
TEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125 Model: VC-40-VYC Table of contents 1. - Installing the test bench 1.1.1- Connecting the compressed air / nitrogen source 1.1.2- Maximum test pressure according
More informationINSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER TRANSPORTABLE CRUDE OIL CONTAINER
INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER TRANSPORTABLE CRUDE OIL CONTAINER MODEL TCC-5 DRAWING NUMBERS AD417CO AD557CO MANUAL NUMBER IOM-197 REVISION Rev. 0, 12/20/2016 TABLE OF CONTENTS
More informationHealth and Safety Inspection Procedure
Template v4 WILTSHIRE POLICE FORCE PROCEDURE Health and Safety Inspection Procedure Effective from: 25.03.2012 Last Review Date: 10.05.2015 Version: 2.0 Next Review Date: 10.05.2018 TABLE OF CONTENTS PROCEDURE
More informationCompressed Gases and Cryogens
Compressed Gases and Cryogens University of Tennessee Safety Guide HM-011 Document Contact: EHS Date effective: January 1, 2009 Revision Date: October 1, 2015 Purpose This guideline adheres to the Occupational
More informationLITTLE MAX MODEL 50G 50,000 BTU PROPANE TORCH
LITTLE MAX MODEL 50G 50,000 BTU PROPANE TORCH INSTRUCTION MANUAL MODEL 50G PROPANE TORCH ASSEMBLY, TESTING, AND OPERATING INSTRUCTIONS PLEASE READ AND RETAIN THIS INFORMATION FOR FUTURE REFERENCE DO NOT
More informationMANUAL GAS MANIFOLDS
MANUAL GAS MANIFOLDS Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com
More information2 CYLINDER MOBILE CART USER S MANUAL / INSTRUCTIONS
Parker Hannifin Corporation Precision Fluidics Division Porter Instrument 245 Township Line Road Hatfield, PA 9440 Office 25-723-4000/Fax 25-723-506 www.porterinstrument.com 2 CYLINDER MOBILE CART USER
More informationCHAPTER 26 WELDING AND CUTTING
CHAPTER 26 WELDING AND CUTTING Revised 7/2010 1 WELDING AND CUTTING Responsibilities 1. The County Safety Officer is responsible for providing appropriate safety instructions for supervisor's use on welding
More informationTHE BP-690 SERIES. Operating and Service Manual. Series includes all variants of BP-LF/MF-690/691
THE BP-690 SERIES Operating and Service Manual Series includes all variants of BP-LF/MF-690/691 Issue B April 2015 1 TABLE OF CONTENTS 1. Description... 3 2. Installation... 3 3. Operation... 4 4. Special
More informationCompressed Gas Cylinder Safety
Session No. 666 Compressed Gas Cylinder Safety David R. Maloney CGS Safety Training, Inc. Farmington Hills, Michigan We take for granted the power a compressed gas cylinder possesses. Think about it, most
More informationINSTRUCTIONS FOR MODELS SG3897 AND SG3898 CROSS PURGE ASSEMBLIES
INSTRUCTIONS FOR MODELS SG3897 AND SG3898 CROSS PURGE ASSEMBLIES THIS BOOKLET CONTAINS PROPRIETARY INFORMATION OF ADVANCED SPECIALTY GAS EQUIPMENT CORP. AND IS PROVIDED TO THE PURCHASER SOLELY FOR USE
More informationCompressed Gas Cylinders - Guideline
Environmental Health and Safety Compressed Gas Cylinders - Guideline Date of Issuance: 1/10/18 Revision Number: Initial Revision Date: Prepared by: EH&S 1. Purpose Carnegie Mellon University has developed
More informationUTAS EH&S INSTRUCTION No. 036 June 2012 Revision No. 3. Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard)
Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard) APPLICABILITY: This EH&S Instruction applies to UTAS sites worldwide, including contractors working at UTAS facilities. The document
More informationProtocol Switchover Station
ADI 3215-B Certified ISO 9001 Protocol Switchover Station INSTALLATION AND OPERATION INSTRUCTIONS Before Installing or Operating, Read and Comply with These Instructions Controls Corporation of America
More information632 Series Gas Distribution System
ADI3223-B Certified ISO 9001:2000 632 Series Gas Distribution System INSTALLATION AND OPERATION INSTRUCTIONS Before Installing or Operating, Read and Comply with These Instructions Controls Corporation
More informationRisk Management Department. Compressed Gas Safety
Risk Management Department Compressed 1 Introduction Many maintenance and vocational education operations require the use of compressed gases. 2 Introduction In this presentation we will discuss: Hazards
More informationCODE OF PRACTICE 47 THE SAFE USE OF INDIVIDUAL PORTABLE OR MOBILE CYLINDER GAS SUPPLY EQUIPMENT
CODE OF PRACTICE 47 THE SAFE USE OF INDIVIDUAL PORTABLE OR MOBILE CYLINDER GAS SUPPLY EQUIPMENT 2018 CODE OF PRACTICE 47 THE SAFE USE OF INDIVIDUAL PORTABLE OR MOBILE CYLINDER GAS SUPPLY EQUIPMENT 2018
More informationOperation Manual. Diaphragm Sensed Gas Pressure Regulators
687 Technology Way Napa, CA 94558 Phone: (707) 259-0102 FAX: (707) 259-0117 www.aptech-online.com Diaphragm Sensed Gas (AP/AZ/AK Models: 20, 100, 500, 1000, 1000T 10PA, 1100, 1200, 12PA, 1300, 1400T, 14PA,
More informationTHE HF-300 SERIES. Operating and Service Manual. Series includes all variants of HF-300/301
THE HF-300 SERIES Operating and Service Manual Series includes all variants of HF-300/301 Issue A July 2015 1 TABLE OF CONTENTS 1. Description... 3 2. Installation... 3 3. Operation... 4 3.1. Spring Loaded...
More informationNetwork Regulator Maintenance Operatives LS (Non-Accredited)
Background Network Regulator Maintenance Operatives LS (Non-Accredited) Network Maintenance Operative (NMO) would be trained to perform work on pressure reducing equipment upstream of the ECV on pressures
More informationCS150 CAP STAPLER OWNER S MANUAL
Operation Revised 6/2013 www.stingerworld.com CS150 CAP STAPLER OWNER S MANUAL! Maintenance Safety Warranty PLEASE READ! This manual contains important information about product safety. WELCOME TO STINGER
More informationTYPICAL TOXIC GAS SYSTEM INSPECTION VIOLATIONS
TYPICAL TOXIC GAS SYSTEM INSPECTION VIOLATIONS The following is a list of typical violations often found by inspectors and a generic solution. You can use this list to improve the safety of your facility,
More informationATD LB PRESSURE BLASTER INSTRUCTION MANUAL
ATD-8402 90LB PRESSURE BLASTER INSTRUCTION MANUAL SAVE THESE INSTRUCTIONS SAFETY INSTRUCTIONS FOR SANDBLASTER 1. Before opening the tank release the air pressure on the sand tank. To do this, turn off
More informationOverview EUSSAM12. Carry out tightness testing and direct purging of gas installations
Overview This standard covers tightness testing and direct purging of low or medium pressure gas, in accordance with approved procedures and practices. It covers the standards required to meet the requirements
More information200 PSI COMPRESSORS - MODEL NUMBERS
200 PSI COMPRESSORS - MODEL NUMBERS 380C AIR COMPRESSOR KIT PART NO. 38033 480C AIR COMPRESSOR KIT PART NO. 48043 380C 480C IMPORTANT: It is essential that you and any other operator of this product read
More informationPURPOSE OF THE POLICY
Title: Safe Storage, Handling, Use and Disposal Procedures of Compressed Gas Cylinders Effective Date: November 2005 Revision Date: March 1, 2017 Issuing Authority: Responsible Officer: VP, Capital Projects
More informationLaboratory Safety Committee
Laboratory Safety Committee Compressed Gas Cylinder Policy Purpose Compressed gas cylinders are an important component of many research laboratories. Wide varieties of gases are packaged in compressed
More informationOperating Manual. R280 Pressure regulator made of brass. 1. Intended Use
Pressure regulator made of brass Operating Manual 1. Intended Use Line or outlet pressure regulators- /reducer for Air, gases and liquids which is designed to effect reduction to a downstream pressure
More informationCompressed Gas Properties. Introduction. Compressed Gas Properties. Definition of a Compressed Gas
1. Properties of gases 2. Cylinders 3. Storage of Gases 4. Regulators 5. Cryogenic Liquids Introduction All compressed gases by definition can be hazardous Know the properties of the gases you are working
More informationTECHNICAL DATA MAINTENANCE AIR COMPRESSOR MODEL G-1
Dry 131h 1. DESCRIPTION The Viking Model G-1 Maintenance Air Compressor is an electric motor-driven, aircooled, single-stage, oil-less compressor. The unit is equipped with a check valve and provides a
More informationIMPORTANT SAFETY INSTRUCTIONS
IMPORTANT SAFETY INSTRUCTIONS CAUTION - To reduce risk of electrical shock: - Do not disassemble. Do not attempt repairs or modifications. Refer to qualified service agencies for all service and repairs.
More informationPressure Regulators. Instructions for Use
Pressure Regulators Instructions for Use 702-0032.11 May 2014 1. Symbols Warning! Caution! Indicates a potentially hazardous situation which, if not avoided, could result in personal injury to the user
More informationDouble Stage Low Pressure Regulator JUMBO KOSAN Type 584
JUMBO KOSAN Type 584 The Type 584 is a double-stage low-pressure regulator, with inlet connection for automatic valves 35 mm in diameter. The Type 584 is a double-stage regulator constructed to control
More informationMANIFLEX System. 52B Series 52C Series 52S Series INSTALLATION AND OPERATION INSTRUCTIONS
ADI 3213C Certified ISO 9001 MANIFLEX System 52B Series 52C Series 52S Series INSTALLATION AND OPERATION INSTRUCTIONS Before Installing or Operating, Read and Comply with These Instructions Controls Corporation
More information420C AIR COMPRESSOR KIT PART NO C AIR COMPRESSOR KIT PART NO
420C AIR COMPRESSOR KIT PART NO. 42042 460C AIR COMPRESSOR KIT PART NO. 46043 420C 460C IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of this
More informationTHE BP-301 SERIES. Operating and Service Manual. Series includes all variants of BP-301 (LF 0.1Cv / MF 0.5Cv)
THE BP-301 SERIES Operating and Service Manual Series includes all variants of BP-301 (LF 0.1Cv / MF 0.5Cv) Issue B October 2015 1 TABLE OF CONTENTS 1. Description... 3 2. Installation... 3 3. Operation...
More informationCalibrated or locked versions available. TREATMENT > Series MD regulators GENERAL DATA. New
> Series MD regulators Series MD pressure regulators New Ports with interchangeable cartridges: threaded (1/8, 1/4, /8) or integrated with super-rapid fitting for tube with Ø 6, 8 and 10 mm Versions: single,
More informationTHE MF-400 SERIES. Operating and Service Manual. Series includes all variants of MF-400/401
THE MF-400 SERIES Operating and Service Manual Series includes all variants of MF-400/401 Issue A October 2013 1 TABLE OF CONTENTS 1. Description... 3 2. Installation... 3 3. Operation... 4 4. Special
More informationACS.CoNGLP1 SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC NATURAL GAS TO LPG GENERIC
ACS.CoNGLP1 SAFETY ASSESSMENT CRITERIA INITIAL & RE-ASSESSMENT DOMESTIC NATURAL GAS TO LPG GENERIC Issue 8.1 ACS. SMB April 2018 1 CoNGLP1 INITIAL & RE-ASSESSMENT Range All LPG fittings. Comprises: 2.
More informationRefrigerant Gases Valves
Refrigerant Gases Valves RUS series Single Outlet Compact Refrigerant Recovery Valves 46 RDU series Diaphragm Packless Multivalves for Refrigerant Gases 47 RBV series Single Outlet Diaphragm Packless Valves
More informationaccidents which arise due to non-observance of these instructions and the safety information herein. SPECIFICATIONS
18 GAUGE 2 INCH BRAD NAILER Model: 7555 CALIFORNIA PROPOSITION 65 WARNING: You can create dust when you cut, sand, drill or grind materials such as wood, paint, metal, concrete, cement, or other masonry.
More information250C-IG COMPRESSOR KIT 12V PART NO C-IG COMPRESSOR KIT 24V PART NO
250C-IG COMPRESSOR KIT 12V PART NO. 25050 250C-IG COMPRESSOR KIT 24V PART NO. 25058 IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of this manual
More informationTECHNICAL BULLETIN. Sigma-Aldrich Pure-Pac II System. Technical Bulletin AL-236
Sigma-Aldrich Pure-Pac II System Technical Bulletin AL-236 TECHNICAL BULLETIN Product The Sigma-Aldrich Pure-Pac II packaging/dispensing system provides a convenient method for storing and dispensing laboratory
More informationaccidents which arise due to non-observance of these instructions and the safety information herein. SPECIFICATIONS
18 GAUGE 1-1/4 INCH BRAD NAILER Model: 7611 CALIFORNIA PROPOSITION 65 WARNING: You can create dust when you cut, sand, drill or grind materials such as wood, paint, metal, concrete, cement, or other masonry.
More informationSERVICE MANUAL MODEL BA200AA-S1 BREATHING AIR PANEL
SERVICE MANUAL MODEL BA200AA-S1 BREATHING AIR PANEL WARNING: Do not attempt to operate this equipment without first reading and understanding the service manual enclosed with this device. 1/00 2 GENERAL
More informationPORTABLE 5 GALLON AIR TANK ASSEMBLY & OPERATING INSTRUCTIONS
PORTABLE 5 GALLON AIR TANK MODEL 472 ASSEMBLY & OPERATING INSTRUCTIONS 349 Mission Oaks Blvd., Camarillo, CA 930 Visit our Web site at http://www.harborfreight.com TO PREVENT SERIOUS INJURY, READ AND UNDERSTAND
More informationAUTOMATIC GAS MANIFOLDS
AUTOMATIC GAS MANIFOLDS Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com
More informationAIR DRIVEN. Gas Boosters & SYSTEMS. Accepting VISA, MasterCard and American Express
AIR DRIVEN Gas Boosters & SYSTEMS Accepting VISA, MasterCard and American Express Gas Boosters AIR DRIVEN FROM 30 PSI TO 21,750 PSI MAXIMATOR Maximator gas boosters are an excellent alternative to high
More informationInstallation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units
Installation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units Models: EPS Single Pump EPT Twin Pump EPS-HP EPT-HP Single Pump High Pressure Twin Pump High Pressure
More informationOXY FUEL SYSTEM SET UP & SHUT DOWN PROCEDURE CHECKLIST ACETYLENE FUEL GAS
OXY FUEL SYSTEM SET UP & SHUT DOWN PROCEDURE CHECKLIST ACETYLENE FUEL GAS Items needed for demonstrations: Fire extinguisher PPE (Personal Protective Equipment): o Lab coats/welding jackets o Leather gloves
More informationCompressed Gases Storage and Handling Safety Policy. Individual Unit Function: Safety Procedure No.: SOP-0103 Page: 1 of 6
Procedure No.: SOP-0103 Page: 1 of 6 MIDGA Reviewed: 07/09/18 Effective: 1/14/98 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety 1. PURPOSE The purpose of this procedure is to establish
More informationSAFETY AND OPERATION MANUAL
SAFETY AND OPERATION MANUAL Congratulations on purchasing the GASPONY 1 Portable Welding/Cutting Outfit! This manual is designed to help you get the most out of your GASPONY 1. CAREFULLY REVIEW ALL SAFETY
More information444C DUAL PERFORMANCE VALUE PACK
(Chrome) PART NO. 44432 IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of this manual before installing and using this product. SAVE THIS MANUAL
More informationU.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL
SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to
More informationInstruction & Parts Manual
Large Capacity Spring Rewind Hose Reel Instruction & Parts Manual Model 88402 3/4 Hose Capacity Model 88402DEF 3/4 Hose Capacity Model 88403 1/2 Hose Capacity Model 88405 1 Hose Capacity P/N 88403-75L
More informationMATHESON s LaserPro Gases and Gas Delivery Equipment
MATHESON s LaserPro Gases and Gas Delivery Equipment MATHESON s LaserPro Support Gases and Services MATHESON delivers the LaserPro line of gases specifically designed to meet the stringent purity requirements
More information200 PSI FAST-FILL AIR SOURCE KIT
200 PSI FAST-FILL AIR SOURCE KIT 55% Duty Compressor on 2.0 Gallon Air Tank PART NO. 20007 IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of
More informationHot Compressed Air Lance Operation Manual. LAB Manufacturing 9483 Reading Road Cincinnati, OH (800)
Hot Compressed Air Lance Operation Manual www.heatlances.com LAB Manufacturing 9483 Reading Road Cincinnati, OH 45215 (800) 776-5830 PARTS CHECK LIST NOTE: Check all fittings & connections prior to operation.
More information200 PSI HIGH-FLOW AIR SOURCE KIT
200 PSI HIGH-FLOW AIR SOURCE KIT 50% Duty Compressor on 2.0 Gallon Air Tank PART NO. 20008 IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of
More informationPeninsula Dental Social Enterprise (PDSE)
Peninsula Dental Social Enterprise (PDSE) Medical Gas Policy Version 3.0 Date approved: August 2018 Approved by: The Board Review due: August 2021 Policy will be updated as required in response to a change
More informationInstallation Operating Instructions for Duplex Manual Manifolds PX-TMD Series
Introduction Powerex manifolds are cleaned, tested and prepared for the indicated gas service and are built in accordance with the Compressed Gas Association guidelines. The manifold consists of a regulator
More informationSERVICE MANUAL MODEL BA200AMST-S1 BREATHING AIR PANEL
1 SERVICE MANUAL MODEL BA200AMST-S1 BREATHING AIR PANEL WARNING: Do not attempt to operate this equipment without first reading and understanding the service manual enclosed with this device. 2 GENERAL
More informationfor the of and the EM55-1
Operating Manua al for the Tapping Points of the EM55-1/EM55-2/EM55-3/ /EM55-4 series and the EE55-1/EE55-2/EE55-3/EE55-4 series EM55-1 Contents Contents... 2 1. Introduction... 3 1.1 General... 3 1.2
More informationPERMA-CYL 230/450/1000/1500/2000. Installation Manual Manual # Revision B
PERMA-CYL 230/450/1000/1500/2000 Installation Manual Manual #11630833 - Revision B TABLE OF CONTENTS SAFETY 3 THE PERMA-CYL FAMILY 4 CONDUCTING A SITE EVALUATION 5 OUTDOOR INSTALLATION EXTERNALLY SITED/GAS
More informationFacilities and Estates. Natural Gas: Standard Operating Procedure. Document Control Summary. Contents
Facilities and Estates Natural Gas: Standard Operating Procedure Document Control Summary Status: Version: Author/Title: Owner/Title: Approved by: Ratified: Related Trust Strategy and/or Strategic Aims
More informationAIRLINE-SERIES HELMET AIR FILTER
OWNER S MANUAL AIRLINE-SERIES HELMET AIR FILTER IMPORTANT WARNING FOR SAFER BLAST CLEANING 1. Use protective equipment: Abrasive-resistant clothing, safety shoes, leather gloves, ear protection, CE-approved
More informationLUBRICATOR ASSEMBLY AND OPERATING INSTRUCTIONS
AIR FILTER, REGULATOR AND LUBRICATOR 4035 ASSEMBLY AND OPERATING INSTRUCTIONS 349 Mission Oaks Blvd., Camarillo, CA 930 Visit our Web site at http://www.harborfreight.com Copyright 004 by Harbor Freight
More information100C Air Compressor Kit
10010 100C Air Compressor (standard mounting bracket, CE Spec) 10014 100C Air Compressor (no leader hose or check valve, CE Spec) 10016 100C Air Compressor (with Omega Bracket, CE Spec) IMPORTANT: It is
More informationNote: You will need a full tank of CO2 for connection and leak testing! Kit Number
Owners Manual Design Engineering Inc. CryO2 Cryogenic Tank Installation Kit To be used with CryO2 components only! Persons experienced in the installation and proper operation of Performance systems like
More informationTHE HF-210 SERIES. Operating and Service Manual. Series includes all variants of HF-210/211. Issue A October 2014 *Section 6.
THE HF-210 SERIES Operating and Service Manual Series includes all variants of HF-210/211 Issue A October 2014 *Section 6.1 in development 1 TABLE OF CONTENTS 1. Description... 3 2. Installation... 3 3.
More information629 Series MicroManifold & Vent Kit System
ADI3221-A Certified ISO 91:2 629 Series MicroManifold & Vent Kit System INSTALLATION AND OPERATION INSTRUCTIONS Before Installing or Operating, Read and Comply with These Instructions Controls Corporation
More informationPRESSURE TEST PUMP OPERATING & MAINTENANCE INSTRUCTIONS. Model No: PTP100. Part No: GC01/09
PRESSURE TEST PUMP Model No: PTP00 Part No: 06020 OPERATING & MAINTENANCE INSTRUCTIONS GC0/09 INTRODUCTION Thank you for purchasing this CLARKE Pressure Testing Pump. Before attempting to use the product,
More informationGAS STRUT SAFETY INFORMATION
VERSION 4.0 - PAGE 1 CONTENTS 1. SAFETY REQUIREMENTS 2. INSTALLATION 3. DO S AND DON TS 4. PERIODIC INSPECTION 5. SERVICE LIFE 6. FUNCTIONAL SAFETY 7. DAMAGED GAS STRUTS VERSION 4.0 - PAGE 2 SAFETY REQUIREMENTS
More informationCS150 CAP STAPLER OWNER S MANUAL Operation Safety Maintenance Warranty! www.stingerworld.com PLEASE READ! This manual contains important information about product safety. REV 06/15 WELCOME TO STINGER Congratula*ons
More informationMEDICAL REGULATOR RANGE (MEDIREG RANGE)
MEDICAL REGULATOR RANGE (MEDIREG RANGE) Medireg Dialreg Flowreg INSPECTION Remove the Medireg from the packaging and inspect for damage. If there is any damage, DO NOT USE, and contact Therapy Equipment
More informationPressure Regulators. Operating Instructions. Instrumentation
Pressure Regulators Operating Instructions FAILURE OR IMPROPER SELECTION OR IMPROPER USE OF THIS PRODUCT CAN CAUSE DEATH, PERSONAL INJURY AND PROPERTY DAMAGE. This document and other information from the
More information