I-10 AT SCENIC LOOP RD Open House
General Information I-10 At Scenic Loop Rd KENDALL COUNTY OPEN HOUSE June 30, 2015 Currey Creek Baptist Church 35 Cascade Cavern 5:00 7:00 Boerne, TX 78015 2
Public Meeting Goals Provide tools to inform the public of the proposed project Presentation Proposed Project Layout Staff available to answer questions 3
Project Need and Purpose Need Significant congestion exists at the Scenic Loop Rd intersections with the east and west frontage roads. Congestion is expected to increase over time. The Existing I-10 Bridge over Scenic Loop Rd has low clearance and potential for bridge strikes. Purpose Improve mobility by adding separate turn lanes and increasing turn lane storage at the intersection approaches Improve Bridge Clearance to reduce the potential for bridge strikes 4
Project Timeline* Project Need Identified Evaluate human and natural environment Prepare environmental study documents Early June - Coordination With City of Boerne Representatives Received approval to proceed to construction June 30 - Public Meeting Fall 2015 Anticipate beginning construction Fall 2017 Anticipate completing construction This timeline is preliminary and subject to change. 5
Existing Conditions Key Challenges Significant Congestion at peak travel times Low Bridge Clearance Limited Sidewalks to accommodate pedestrians Normal Speed Slow Speed N 6
Proposed Improvements Overview Provide Separate Turning Lanes along Frontage Road to reduce congestion Reconstruct I-10 Overpass at Higher Elevation to Improve Clearance Include Right Turn Lane along northbound Scenic Loop Rd. Provide Sidewalks 7
Proposed Improvements 8
2015 Traffic Simulation Morning Peak Existing Conditions Proposed Improvements N N 9
2015 Traffic Simulation Evening Peak Existing Conditions Proposed Improvements N N 10
Intersection Wait Times 11
Intersection Wait Times West Intersection A.M. Wait Time (in seconds) 160 East West 140 120 100 80 60 40 20 85% Reduction 59% Reduction 0 EXISTING PROPOSED EXISTING PROPOSED EXISTING PROPOSED East Approach West Approach North Approach 12
Intersection Wait Times 13
Intersection Wait Times East Intersection A.M. Wait Time (in seconds) 100 90 80 70 60 50 40 30 20 10 0 West East 88% Reduction 85% Reduction EXISTING PROPOSED EXISTING PROPOSED EXISTING PROPOSED West Approach East Approach South Approach 14
Environmental Impacts Environmental Impacts No impact to wetlands of waters of the U.S. No impact to base flood elevation No impacts to threatened or endangered species No displacements or ROW acquisition for proposed improvements No reduction of air quality is anticipated. 15
General Information Construction Anticipated to Begin: Fall 2015 Construction Duration: 19 Months 16
Potential Funding Strategy City of Boerne Funding: Kendall County Funding: Federal Funding: TxDOT Allocated Funding: $0.55 Million $0.55 Million $8.01 Million $0.89 Million $10 Million 17
Next Steps Proposed I-10 Corridor Improvements (From SH 46 to Fair Oaks Pkwy) N Conversion from Two-Way to One- Way Frontage Roads Revise Ramp Configuration to Improve Safety and Local Access Intersection Improvements at Major Cross Streets and Side Streets Integrates Proposed Improvements at Scenic Loop Rd. Possible Public Meeting Fall 2015 Begin Project State Highway 46 End Project Fair Oaks Pkwy 18
Provide Your Comments Options for Commenting 1. Give comment card to TxDOT staff tonight 2. Provide comments to onsite court reporter 3. Fax comments to: (972) 960-4185, Attn: Phillip Hanley 4. Mail comments to: HDR Attn: Phillip Hanley 17111 Preston Rd, Suite 200 Dallas, TX 75248 5. Email comments to: scenicloop@hdrinc.com Deadline for comments: July 08, 2015 19
Thank You for Your Participation! 20