1 February 26, 2013 Presentation Overview of Proposed Roadway Network and Intersection Improvements Bond Program Excellence - Integrity - Service - Creativity - Communication
2 TRANSPORTATION BOND PROGRAM ADVISORY COMMITTEE LAMAR STREET PECAN STREET and OLIVE STREET Description: With removal of Couplet (March 2012), consider improving roads to provide better traffic circulation, more on-street parking, sidewalks, street lighting and traffic signalization. Install concrete streets in accordance with the Old Town Keller typical street cross section (31-foot wide roadway with 18.5-foot perpendicular parking on both sides) for all streets. Costs include engineering, 6-foot wide sidewalks on both sides of street, street lighting, drainage improvements for all streets, and a traffic signal on US Hwy 377 at Pecan Street. Est. Total Project Cost: $1,484,000 Est. Cost Breakdown: Lamar St (Golden Triangle to Pecan) = $1,006,000; Pecan St (remainder) = $97,000; Olive St (Lamar to US 377) = $156,000; (Traffic Signal on US Hwy 377 at Pecan St = $225,000, included) Eng. Contract Length: 6 months ROW Acquisition: None required Estimated Construction Time: 9 months
3 LAMAR STREET PECAN STREET OLIVE STREET TRAFFIC SIGNAL AT US HWY 377 & PECAN STREET
4 TRANSPORTATION BOND PROGRAM ADVISORY COMMITTEE ELM STREET and PECAN STREET Description: With removal of Couplet (March 2012), consider improving roads to provide better traffic circulation, more on-street parking, sidewalks, and street lighting. Install concrete streets in accordance with the Old Town Keller typical street cross section (31-foot wide roadway with 18.5-foot perpendicular parking on both sides) for both streets. Costs include engineering, 6-foot wide sidewalks on both sides of street, street lighting, and drainage improvements for both streets. Est. Total Project Cost: $1,345,000 Est. Cost Breakdown: Elm St (FM 1709 to Pecan) = $1,006,000; Pecan St (Elm to US 377) = $339,000 Eng. Contract Length: 6 months ROW Acquisition: None required Estimated Construction Time: 9 months Comments: If warranted, intersection improvements may be needed at Elm St. and Pecan St. The design and traffic signals costs may be approximately $225,000, not included in above project costs.
5 ELM STREET PECAN STREET
6 Intersection Improvements for Consideration
7 TRANSPORTATION BOND PROGRAM ADVISORY COMMITTEE BEAR CREEK PARKWAY at ELM STREET / WHITLEY ROAD Description: Proposed traffic signal installation at intersection. Est. Total Traffic Circle Project Cost: $506,250 Est. Cost Breakdown: Design = $75,000; Construction = $431,250 Eng. Contract Length: 6 months Est. ROW Acquisition: 6 months Estimated Construction Time: 10 months 2012 Total Traffic Movements: 32,830 Estimated Total Traffic Circle Project Cost: $932,000 Design = $125,000; ROW = $88,000; Construction = $719,000 Proposed single lane concrete traffic circle in 180 diameter ROW with sidewalks.
8 TRANSPORTATION BOND PROGRAM ADVISORY COMMITTEE BEAR CREEK PARKWAY at ELM STREET / WHITLEY ROAD BEAR CREEK PARKWAY at ELM STREET / WHITLEY ROAD INTERSECTION Proposed traffic signals.
9 Intersection Improvements: Bear Creek Pkwy. at Elm St./Whitley Rd. Intersection City of Keller Intersection Accident Report 11/1/10 11/29/12 Major Accidents Minor Accidents Bear Elm/Whitley 1 3
10 Questions from the Committee
11 How many parking spaces are existing on Elm Street and Pecan Street? How many will be created? How many single family residences front Elm Street? There are 26 existing parking spaces on Elm Street; 265 will be created. There are 10 single family residences that front Elm Street between the intersection of FM 1709 and Pecan Street. There are 74 parking spaces on Pecan Street.
12 How many parking spaces are existing along Lamar St./west of US 377? How many will be created with the proposed improvements? Existing parking spaces in Old Town on the west side of US 377, including all existing parking lots, is 265. Total proposed parking spaces with proposed extension of Lamar Street from Hill Street south to Pecan Street, then on Pecan Street and on Olive Street extension will be 451. This equals 451 total spaces.
13 Response from TXDOT regarding a pedestrian crossing if a traffic signal is installed at Pecan St. TXDOT stated a pedestrian crossings on US 377 is possible at a signalized intersection. They would consider an underpass or overpass pedestrian crossing at the city s cost and city s long term maintenance.
14 QUESTIONS? All meetings of the Transportation Bond Program Advisory Committee are open to the public, who are invited to listen, observe and provide feedback. For more information regarding the Transportation Bond Program Advisory Committee, the projects it is considering and its upcoming meeting times, please visit the following link: Questions regarding the Transportation Bond Program Advisory Committee and/or requests for more information should be directed to: Chris Fuller, Deputy City Manager Steve Polasek, City Manager Phone: Phone: Greg Dickens, Public Works Director Phone:
15 Excellence - Integrity - Service - Creativity - Communication
I-10 AT SCENIC LOOP RD. Open House
I-10 AT SCENIC LOOP RD Open House General Information I-10 At Scenic Loop Rd KENDALL COUNTY OPEN HOUSE June 30, 2015 Currey Creek Baptist Church 35 Cascade Cavern 5:00 7:00 Boerne, TX 78015 2 Public Meeting
More informationFY STIP. Austin District. November Quarterly Revisions HIGHWAY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY Austin District November Quarterly Revisions November 2011 FY 2011-2014 Transportation Improvement Program Amendments October 10,
More informationWELCOME. FM 2818 (Harvey Mitchell Parkway) Open House. Tuesday, Nov. 14, 2017
WELCOME FM 2818 (Harvey Mitchell Parkway) Open House Tuesday, Nov. 14, 2017 Why am I here? Review the planned improvements Provide comments on the proposed project The environmental review, consultation,
More informationDiamond Springs Parkway Project
Diamond Springs Parkway Project Public Information Meeting, Monday, March 18, 2013 330 Fair Lane, Building A, Placerville County Board of Supervisors Meeting Room, 6:30 8:00 p.m. PRESENTED BY: County of
More informationKnox Street Complete Streets Project
Knox Street Complete Streets Project Meeting Purpose Get community feedback on two conceptual street design options Meeting Agenda Presentation (20 minutes) Project background and schedule Summary of preferences
More information2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage
2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage 2 Project Management and Engineering Projects on 40th Ave Extension - Lake Otis Pkwy to Dale St $18,103,000
More informationI-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design
I-20 ODESSA-MIDLAND CORRIDOR STUDY Public Meeting for Schematic Design The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being,
More informationTABLE OF CONTENTS 7.0 THOROUGHFARE PLAN. Analysis of Future Conditions Thoroughfare Plan Proposed Cross-Sections.. 7.
TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN Analysis of Future Conditions.. 7.2 Thoroughfare Plan.. 7.3 Proposed Cross-Sections.. 7.4 Arterials Minor Arterials Collectors Local Streets Thoroughfare Plan Map
More informationLeague City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study. Second Public Meeting February 6, 2018
League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study Second Public Meeting February 6, 2018 City Project Information League City Parkway and Brittany Lakes Dr./ Fennigan
More informationFrequently Asked Questions
Frequently Asked Questions Business US 190 in Copperas Cove From Avenue D to Constitution Drive What is access management? A. Access Management is a growing effort by government agencies to improve how
More informationAGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive
AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington
More information5 REQUEST FOR GRADE-SEPARATED PEDESTRIAN UNDERPASS CROSSINGS OF LESLIE STREET AND ST. JOHN S SIDEROAD TOWN OF AURORA
5 REQUEST FOR GRADE-SEPARATED PEDESTRIAN UNDERPASS CROSSINGS OF LESLIE STREET AND ST. JOHN S SIDEROAD TOWN OF AURORA The Transportation Services Committee recommends the adoption of the recommendations
More informationSIDEWALK ASSESSMENT PHASE TWO
2013 SIDEWALK ASSESSMENT PHASE TWO Table of Contents Lake of the Ozarks Council of Local Governments Sidewalk Assessment Phase TWO Criteria... 1 Communities Included In Sidewalk Assessment Phase TWO...
More informationReadington Road (C.R. 637) Construction
Public Information Meeting Thursday, August 2, 2012 Readington Road (C.R. 637) Construction from Dreahook Road to Harlan School Road Branchburg Township, Somerset County Readington Township, Hunterdon
More informationSD Highway 50 in Yankton (4 TH Street) Reconstruction Project NH 0050(99)381 PCN By Josh Larson McLaury Engineering Inc.
SD Highway 50 in Yankton (4 TH Street) Reconstruction Project NH 0050(99)381 PCN 6926 By Josh Larson McLaury Engineering Inc. Project Limits SD 50 from Broadway to Burleigh and from Marne Creek to Archery
More informationUS 19 PEDESTRIAN AND BICYCLE SAFE ACCESS
US 19 PEDESTRIAN AND BICYCLE SAFE ACCESS TO TRANSIT CORRIDOR STUDY A JOINT EFFORT OF THE FLORIDA DEPARTMENT OF TRANSPORTATION AND FORWARD PINELLAS (F.K.A. PINELLAS COUNTY METROPOLITAN PLANNING ORGANIZATION)
More informationUS 19 Pedestrian and Bicycle Safe Access to Transit Corridor Study
US 19 Pedestrian and Bicycle Safe Access to Transit Corridor Study DRAFT Technical Memorandum #6 Cost and Benefit Evaluation Methodology August 2016 Prepared for: FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT
More informationFifth & Kirkham Traffic-Calming Project. 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018
Fifth & Kirkham Traffic-Calming Project 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018 1 Agenda Welcome and introductions Project history, goals,
More informationFY Candidate Sidewalk Projects. Sidewalk Advisory Committee
FY 17-18 Candidate Sidewalk Projects Sidewalk Advisory Committee Sidewalk Advisory Committee FY 17-18 Candidate Sidewalk Projects January 3, 2017 County Road 540/Clubhouse Road (S. Lakeland) South-Side
More informationCSAH 101 Preliminary Design
CSAH 101 Preliminary Design Public Open House No. 2 January 29, 2013 CSAH 62 to Hutchins Drive Welcome / Introductions Hennepin County Craig Twinem, Transportation Maury Hooper, Transportation Nick Peterson,
More informationCorpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:
Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency
More informationFY 2006 TRANSPORTATION CAPITAL PROGRAM
Airport Circle Elimination, CR 563, 646 S9820 Intersection, operational, and safety improvements at the intersection of Tilton Road (CR 563) and Delilah Road (CR 646) will include elimination of the circle,
More informationLegislative Update Williamsburg Residency
Hampton Roads District Legislative Update Williamsburg Residency Jim Brewer, Resident Administrator 757-253-5140 Projects Under Way Warwick Boulevard Project http://www.warwickboulevard.org/ Contractors:
More informationHenderson Ave. Complete Streets Project
Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to proceeding with preliminary engineering www.dallascompletestreets.wordpress.com MeetingAgenda
More informationSouthcote Road Improvements Class Environmental Assessment Study
1 Southcote Road Improvements Class Environmental Assessment Study Public Information Centre #1 May 24, 2018 Study Area 2 3 Welcome The Ancaster Transportation Master Plan (2011) outlined a long range
More informationPROPOSAL: Review of Alaska DOT&PF project 68471, Glacier Highway reconstruction and pedestrian improvements from
PROPOSAL: Review of Alaska DOT&PF project 68471, Glacier Highway reconstruction and pedestrian improvements from Fritz Cove Rd to Seaview Ave, for consistency with locally adopted plans and ordinances.
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017 Item 9, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan
More informationCTH M Reconstruction
CTH M Reconstruction ID 5992 09 81 City of Madison, South Pleasant View Road (Cross Country Road Prairie Hill Road) CTH M Dane County Public Information Meeting Thursday, May 24, 2012 6 p.m. to 8 p.m.
More informationTraffic Calming Policy
City of Friendswood Traffic Calming Policy May 2012 Community Development Department Table of Contents Title Page Table of contents... 1 Background and History... 2 Purpose and Goals... 2 City Procedure
More information2016 Neighborhood Street Fund Application
2016 Neighborhood Street Fund Application 2016-109 #146 COMPLETE Collector: Web Link 1 (Web Link) Started: Sunday, April 17, 2016 2:29:58 PM Last Modified: Sunday, April 17, 2016 2:36:28 PM Time Spent:
More informationColerain Avenue Roadway Improvements. Sponsored by Hamilton County Engineer
Colerain Avenue Roadway Improvements Sponsored by Hamilton County Engineer Participants Lead Agency: Hamilton County Engineer Review and Approval: Ohio Department of Transportation Design Engineer: Edwards
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationReams Road RCA Study. Board of County Commissioners Public Hearing
Reams Road RCA Study Board of County Commissioners Public Hearing April 24, 2018 Presentation Overview Study Overview Existing Conditions Development of Alternatives Preferred Alternative Public Involvement
More informationa 20 year period. separate phases of development with staggered years)
Proposed: Approximately 2,000 acres located at along SH 130 at FM 973 Mixed Use project consisting of : Residential i Approximately 2,800 single family detached units Approximately 2,000 attached units
More informationORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS
ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS STAFF REPORT OF: January 6, 2019 SUPERVISORIAL DISTRICT: 5 SUBJECT: LOCATION: INVESTIGATOR: O Neill Drive at Roanoke Drive; Ladera Ranch; TB 922-E6 Clever
More informationAttached for your reference please find project updates on ongoing VDOT construction projects in Southampton County.
SOUTHAMPTON COUNTY BOARD OF SUPERVISORS Regular Session i July 25, 2016 6. HIGHWAY MATTERS A. PLAN PROJECT UPDATES Attached for your reference please find project updates on ongoing VDOT construction projects
More informationAtwood Avenue Fair Oaks Avenue Cottage Grove Road
Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House
More informationNEIGHBOURHOOD TRAFFIC COMMITTEE POLICY AND PROCEDURE
The City of Vaughan 2141 Major Mackenzie Drive Vaughan, Ontario Canada L6A 1T1 Tel (905) 832-2281 NEIGHBOURHOOD TRAFFIC COMMITTEE POLICY AND PROCEDURE REVISED JUNE 2010 APPLICABILITY The Neighbourhood
More informationHouma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION
APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP
More information5 Transit & Traffic. Overview
5 Transit & Traffic Overview Montgomery Place s roadways and overall traffic circulation are unique in the city due to the narrow streets and avenues with boulevards; however, no sidewalks or curbs in
More informationVehicular and Pedestrian Access to Herndon Metrorail Station. Robert B. Boxer, Director John Stuart, Clark Nexen October 28, 2015
Vehicular and Pedestrian Access to Herndon Metrorail Station Robert B. Boxer, Director John Stuart, Clark Nexen Project Location The project is located in the Town of Herndon along Herndon Parkway between
More informationTraffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014
Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Project Overview Coordinate roadway improvements with other major projects HUB Flood Control
More informationHouma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION
APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton
More informationSouder, Miller & Associates 401 W. Broadway Farmington, NM
Souder, Miller & Associates 401 W. Broadway Farmington, NM Purpose: To solicit public input before the preparation of construction documents for Foothills Drive from Holmes Drive to 300 north of the intersection
More informationI-35 COMAL COUNTY OPERATIONAL IMPROVEMENTS
I- COMAL COUNTY OPERATIONAL IMPROVEMENTS OPEN HOUSE The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been,
More informationDesigning with the Railroad
Designing with the Railroad 23 CFR 646.214 (b)(2) requires that crossings be evaluated when they are within limits or near terminus of Federally Funded project. Some rough numbers for planning: Active
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationTechnical Advisory Committee Meeting
Technical Advisory Committee Meeting US 181 Harbor Bridge Project July 11, 2013 2:30 pm 4:30 pm Oveal Williams Activity Center, 1414 Martin Luther King Drive, Corpus Christi, TX Display Items Meeting Summary
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17
More informationFM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.
FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association
More informationMASTER BICYCLE AND PEDESTRIAN PLAN
VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.
More informationPublic Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018
Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road
More informationSH-6 Corridor Improvement Study Policy Committee Progress Report M O N D AY, J U N E 1 0, B R A Z O S C E N T E R
SH-6 Corridor Improvement Study Policy Committee Progress Report M O N D AY, J U N E 1 0, 2 0 1 3 B R A Z O S C E N T E R Project Overview Study Goals and Objectives» Improve traffic flow» Reduce delay»
More informationFM 471 PROJECT. OPEN HOUSE FM 471 (Culebra Road) from SH 211 to Old FM 471 Medina and Bexar Counties. FM 471 Project
FM 471 PROJECT OPEN HOUSE FM 471 (Culebra Road) from SH 211 to Old FM 471 Medina and Bexar Counties January 24, 2018 Project Location 2 Proposed Improvements Improvements include: Expansion of FM 471 from
More informationHennepin Avenue Reconstruction Washington Avenue to 12 th Street
CITY OF MINNEAPOLIS Hennepin Avenue Reconstruction Washington Avenue to 12 th Street April 2016 1 Upcoming Opportunities Public Meeting #2 April 25, 2016 Minneapolis Central Library Doty Board Room Repeat
More informationTrans-Canada Highway 1 RW Bruhn Bridge Replacement
Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the
More informationCarmel, Indiana Illinois Street and 126th Street Westfield Boulevard and 96th Street Arts and Design District RAB
Sustainability Benefits Of Network Wide Roundabout Use Case Study of Carmel, Indiana Presented By: Michael McBride PE Carmel City Engineer Carmel, Indiana Carmel, Indiana 1996 Carmel, Indiana Population
More informationHIGHWAY 401 WIDENING SECOND LINE WEST STRUCTURE
HIGHWAY 401 WIDENING SECOND LINE WEST STRUCTURE Public Meeting November 16, 2011 OVERVIEW BACKGROUND DISCUSSION ITEMS TRAFFIC ANALYSIS CYCLIST / PEDESTRIAN CONNECTION BACKGROUND February 1982 Ministry
More informationBicycle and Pedestrian Plans and Improvements
Bicycle and Pedestrian Plans and Improvements Presented to the City Council By Randle Harwood, Planning and Development, and Richard Zavala, Parks and Community Services September 24, 2013 Purpose Review
More informationBikeways Network and Facilities
Findings from the bicycle survey showed a high bicycle use and demand for on and off road bikeway facilities. Currently, the City has 185 miles of bike lanes, 40 miles of signed routes to connect the network
More informationADA Design Overview. Section 2. ADA Design Overview. Pedestrian Access Routes. Pedestrian Access Routes. Overview
ADA Design Overview Section 2 ADA Design Overview Overview Accessible Pedestrian Signals Alternate Fall, 2017 Ann Johnson, PE Services Brady Rutman, SRF Consulting Group 2 Pedestrian Access Route (PAR)
More informationWork Session. Agenda Item # 4. Meeting Date September 8, Daryl Braithwaite Public Works Director. Prepared By. Suzanne R. Ludlow City Manager
Agenda Item # 4 Work Session Meeting Date September 8, 2015 Prepared By Approved By Daryl Braithwaite Public Works Director Suzanne R. Ludlow City Manager Discussion Item Background Temporary Neighborhood
More informationMOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9.
CHAPTER NINE: TRANSPORTATION AND CIRCULATION 9.1 INTRODUCTION 9.1 9.2 ASSUMPTIONS 9.1 9.3 TRANSPORTATION FACILITIES 9.1 9.4 TRANSPORTATION IMPROVEMENTS PHASING 9.3 LIST OF FIGURES LIST OF TABLES Figure
More informationS.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project
Open House Public Meeting S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project Municipality of Bethel Park, Allegheny County Bethel Park Municipal Building 5001 West Library
More informationRM 620 FEASIBILITY STUDY
RM 620 FEASIBILITY STUDY Sections 5 & 6 December 7, 2015 STUDY PROCESS Study Purpose and Goals The RM 620 Feasibility Study was launched by the Texas Department of Transportation (TxDOT) to analyze transportation
More informationDesigning for Pedestrian Safety
Designing for Pedestrian Safety Roundabouts: How They Work for Pedestrians Presented by: Fred Ranck FHWA Resource Center Safety Design Engineer October 5, 2010 Roundabouts: Learning Objectives At the end
More informationWELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015
WELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015 Traffic Improvements Project Goals Widen roadway to construction two-way left turn lanes-greatly decreases congestion Ease access to & from
More informationThis page intentionally left blank.
This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area
More information3.0 Future Conditions
3.0 Future Conditions In order to be able to recommend appropriate improvements to the transportation system of the Town, it is important to first understand the nature and volume of traffic that is expected
More informationCITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE FOR BROAD STREET BICYCLE BOULEVARD PROJECT
City of San Luis Obispo, News Release DATE: August 1, 2017 RELEASE: Immediate CONTACT: Luke Schwartz (805) 781-7190 Transportation Planner-Engineer, Public Works CITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE
More informationFleur Drive Reconstruction
Fleur Drive Reconstruction October 29, 2018 1 Agenda: Fleur Drive Reconstruction Project Scope & Cost Overview Fleur Drive Cross Section Elements - Travel Lane Widths - Sidewalk Widths - Parkway Widths
More informationAPPENDIX D COST SUMMARY TABLES
APPENDIX D COST SUMMARY TABLES Section 1 Between Route 50 and Evergreen Mills Road 3850 linear feet of one 12 foot wide additional lane in southbound direction of Rte 606; from north side of Rte 50 to
More information2016 MOBILITY BOND PROGRAM
February 22, 2017 2016 MOBILITY BOND PROGRAM $720 million bond proposition for transportation and mobility improvements including planning, designing, engineering, constructing, reconstructing, renovating
More informationSaskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening
Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project
More informationFY Candidate Sidewalk Projects. Sidewalk Advisory Committee
FY 16-17 Candidate Sidewalk Projects Sidewalk Advisory Committee Sidewalk Advisory Committee FY 16-17 Candidate Sidewalk Projects While a sidewalk request may be limited to part of a roadway, the initial
More informationBuilding Great Neighbourhoods BELLEVUE AND VIRGINIA PARK
Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting
More informationBradford s Landing. Preliminary Plan Abandonment AB753 & AB754 MONTGOMERY COUNTY PLANNING DEPARTMENT
Bradford s Landing Preliminary Plan 120170060 Abandonment AB753 & AB754 1 Overview Staff recommends Approval of Preliminary Plan 120170060 with revised conditions and Adoption of the Resolution. 244 lots
More informationCity of Fairfax, Virginia City Council Work Session
City of Fairfax, Virginia City Council Work Session Agenda Item # City Council Meeting 12a 9/8/2015 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: FISCAL IMPACT: RECOMMENDATION: ALTERNATIVE COURSE OF ACTION: RESPONSIBLE
More informationCONTENTS EXECUTIVE SUMMARY 1
CONTENTS CHAPTER PAGE EXECUTIVE SUMMARY 1 1 ISSUES AND PURPOSE OF THE ANALYSIS 2 1.1 Background 2 1.2 Analysis Area 2 1.3 Issues and Observations 3 1.4 Project and Public Meetings 3 2 LIST OF PREFERRED
More informationShort and Long Term Needs
Short and Long Term Needs The short- and long-term programs of proposed projects listed below have been designed to address the mobility issues in South Montgomery County. These improvements to the transportation
More informationBonners Ferry US 95 South Hill Report
Bonners Ferry US 95 South Hill Report December 2014 About New Mobility West Project Partners Sonoran Institute LOR Foundation Boundary Economic Development Council (BEDC) Project for Public Spaces Charlier
More informationTransportation Investment Act Gwinnett County. Charlotte J. Nash, Chairman Gwinnett County Board of Commissioners
Transportation Investment Act Gwinnett County Charlotte J. Nash, Chairman Gwinnett County Board of Commissioners April 25, 2012 Transportation Investment Act Gwinnett County Gwinnett County Transportation
More informationWelcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.
BRIDGE REHABILITATION Welcome 53 Avenue Overpass over Whitemud Drive Rehabilitation Public Information Session Wednesday, March 9, 2016 4:30-8:00 p.m. Tonight you can: Learn about the 53 Avenue Overpass
More informationShore Drive Safety Task Force. Report to the SDAC
Shore Drive Safety Task Force Report to the SDAC April 20, 2006 Table of Contents Introduction... 3 Section I Safety Recommendations... 5 Section II Communication/Public Involvement Plan... 14 Section
More informationImprove the livability of our streets by
Pedestrian and Traffic Calming Policy March 2018 2 of 6 Neighborhood Traffic Calming Policy The City of Aspen continually strives to protect multimodal function while maintaining a high standard of safety.
More informationWELCOME TO OPEN HOUSE # 1 June 14, 2017
Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE # 1 June 14, 2017 Please sign in and join our mailing list Purpose of Open House #1 & Study Area York
More informationCASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE
CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE Wednesday, November 15, 2017 AGENDA Project Background and Today s Goals Corridor Constraints and Conflicts Usage Information Public Process Schedule Review
More informationCONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach
CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District
More informationWest LRT Workshop Session Welcome Stony Plain Road from 149 Street to 124 Street May 12, 2010
West LRT Workshop Session Welcome Stony Plain Road from 149 Street to 124 Street May 12, 2010 Tonight's Meeting Purpose To provide more detailed information on West LRT concept engineering To provide specific
More informationSafety Impacts: Presentation Overview
Safety Impacts: Presentation Overview The #1 Theme How Access Management Improves Safety Conflict Points The Science of Access Management By Treatment Studies Themes for Texas Access Management Improve
More informationTABLE OF CONTENTS. Executive Summary
Executive Summary Background... ES-1 Pedestrian Network... ES-2 Bikeway Network... ES-2 Collision History... ES-2 Public Input... ES-4 Conclusions and Recommendations... ES-4 1. Introduction and Setting
More informationCincinnati Dayton Rd Widening
Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge
More informationBICYCLE AND TRAILS ADVISORY COMMISSION Meeting Minutes
Minutes Approved as Submitted Date: 8/10/17 Initials: EC BICYCLE AND TRAILS ADVISORY COMMISSION Meeting Minutes June 8, 2017 The Bicycle and Trails Advisory Commission was called to order at 4:00 p.m.
More informationREPORT OF MEETING DOWNTOWN CROSSING PHASE 2 PUBLIC INFORMATION MEETING. Ives Main Library 133 Elm Street, New Haven, Connecticut September 29, 2014
REPORT OF MEETING DOWNTOWN CROSSING PHASE 2 PUBLIC INFORMATION MEETING Ives Main Library 133 Elm Street, New Haven, Connecticut September 29, 2014 Technical Teams City of New Haven Honorable Toni M. Harp,
More informationCommunity Workshop on the Benefits of a Walkable & Bikeable Community
Community Workshop on the Benefits of a Walkable & Bikeable Community Overview and Summary On March 12, 2012, the Town of Bethlehem hosted a community workshop to collect ideas and recommendations for
More information1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY
1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343
More informationSRTS IMPLEMENTATION COSTS
SRTS IMPLEMENTATION COSTS What Is a Estimate? A cost estimate establishes the anticipated budget required to implement the actions (the improvement projects and programs) identified in your School Travel
More informationBuilding Great Neighbourhoods BONNIE DOON
Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement
More information