Traffic and Flood Control Improvements in the Transit Oriented Development District Project Updates Tuesday, November 29, 2016 Meriden Public Library

Similar documents
Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014

New Park Avenue Corridor West Hartford

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

STONY PLAIN ROAD STREETSCAPE

NEWMARKET UPHAM S CORNER

FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Community Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007

San Jose Transportation Policy

GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015

City of Moorhead Committee of the Whole Meeting

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Transportation Corridor Studies: Summary of Recommendations

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

ALLEY 24 TRAFFIC STUDY

ROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS

About the Wilmington Downtown Circulation Study

CITY OF PORTSMOUTH PLANNING DEPARTMENT

FY 2006 TRANSPORTATION CAPITAL PROGRAM

Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013

North Shore Transportation Improvement Strategy

CHAPTER 7.0 IMPLEMENTATION

Lawrence Avenue Streetscape Concepts August 30, 2011

San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project

to the Public Information Centre for the Downtown Traffic Study

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Austell Road Access Management Plan Public Meeting February 17, 2009

2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

Building Great Neighbourhoods BONNIE DOON

Miami Health District

Mineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY

5 CIRCULATION AND STREET DESIGN

Chapter 5 Future Transportation

Paoli Road Improvement Feasibility Study

S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project

FONTAINE AVENUE STUDY Final Report

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

Reams Road RCA Study. Board of County Commissioners Public Hearing

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center

Roosevelt Estates Neighborhood Improvements

Citizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.

Merrick and Memorial Neighborhood Study 5/14/2014 Public Meeting

Ajax: The Road to Complete Streets

City of Atlanta-MARTA Sales Tax Referendum Draft Project List. Atlanta City Council Work Session May 19, 2016

Recommendations. Central Salem Mobility Study

Sacramento Grid 2.0. The Downtown Transportation Study

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input

Austin Avenue Bridges Project. Public Meeting Summary

Enhancing Downtown

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

Road Alterations - Wellington Street East, Church Street, and Front Street Intersection

S T A T I O N A R E A P L A N

Why invest in the 1 Street S.W. Corridor?

VIII. Project Prioritization & Implementation

Memo. Ocean Avenue Corridor Design Project Public Workshop #2 Summary

Tonight is for you. Learn everything you can. Share all your ideas.

City of Wilsonville 5 th Street to Kinsman Road Extension Project

3.16 TRANSPORTATION, CIRCULATION, AND PARKING Regulatory Setting Environmental Setting ROADWAY SYSTEM

Board of Supervisors February 27, 2017

Draft Recommended List of Potential Projects

U.S. HIGHWAY 50 IMPROVEMENT PROJECT

Welcome to the Open House

UPC Design / CN Locally Administered PE Phase VDOT Administered CN Phase

Water Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue &

MCA Member Meeting: Tysons Update. Fairfax County Department of Transportation November 13, 2017

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS)

West Capitol Avenue Road Rehabilitation and Safety Enhancement Project

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Make Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors.

CONTENTS EXECUTIVE SUMMARY 1

122 Avenue: 107 Street to Fort Road

Terwillegar Drive Expressway Draft Concept Plan

Bicycle and Pedestrian Plans and Improvements

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

COMMUNITY WORKSHOP (CW) 3 February 21, 2015

MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY

Harrah s Station Square Casino

Completing the Vision

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

Bellevue Downtown Association Downtown Bike Series

Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session

CENTRAL CITY CAPITAL IMPROVEMENT PLAN RECOMMENDATIONS

Building Great Neighbourhoods QUEEN ALEXANDRA

Crystal City Citizen Review Council Meeting. July 10, 2013

The following is submitted together with the plans and application for the staff and plan commission consideration of approval.

Transportation Planning Division

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Route 29 Solutions Projects

Town of Ashland. Downtown Planning Initiative 2 nd Community Workshop. March 29, Presented by:

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN

Central Avenue Corridor Study FPID Number:

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018

Transcription:

Traffic and Flood Control Improvements in the Transit Oriented Development District Project Updates Tuesday, November 29, 2016 Meriden Public Library

Presentation Format Project Goals and Overview Sidewalk Rehabilitation / Bumpout Removals Two-Way Traffic Conversion Perkins Square Downtown Signals Harbor Brook Flood Control Pratt Street Gateway Semi-Final Design Information Session

Project Overview - Goals Encourage a vibrant downtown for residents and businesses Enhance vehicular and pedestrian safety Mitigate traffic impacts associated with increase rail crossing closures Leverage other projects in Downtown

Project Overview - Objectives Coordinate roadway improvements with other major projects Transit Oriented Development District Zoning Train Station and Hartford rail service Flood Control Brownfield redevelopment Housing (24 Colony St, 177 State St, 11 Crown St)

Project Overview - Strategies Implement two-way traffic on West Main Street / East Main Street, Cook Ave, Hanover Street and Perkins Square Benefit downtown businesses Improve traffic circulation Pedestrian and bicycle networks Create Boulevard on Pratt Street as a gateway Enhance existing streetscape Color banding, decorative features Street trees and landscaping Improved pavement surface

West Main St and Colony St Sidewalk Improvements New sidewalks on West Main St and Colony St Removal of Barrister s Court signal On-Street Loading and Parking Enhancements New trees / tree pits / color banding Spring 2017 DECD grant $300k City Bond funds

Sidewalk Improvements Colony St and Meriden Green State St, Mill St, Pratt St, Colony St Sidewalk and curb replacements (as needed) Spring 2017 State of CT OPM Grant - $869,000 One of 15 communities selected

Two-Way Traffic Conversion / Perkins Square Improve circulation through downtown Improve access to businesses and services Preliminary plans Challenges due to rail crossing Modified two way concept approved by DOT East Main St / West Main St Two Way Currently in preliminary design

Two-Way Traffic Conversion / Perkins Square

Two-Way Traffic Conversion East Main St / Pratt St Reduces future delay Allows full movement Removes two signals Concept Review Improves East - West coordination Increase # of approaches at rail crossing from 4 to 5 Westbound access via Hanover St and East Main St Requires funding for widening East Main Street and realigning Perkins Square

Two-Way Traffic Conversion Concept Review Perkins Square Maintain existing curblines Minimize impacts to Wells Fargo Enhance corner radii Wider sidewalks Safe and efficient access for development Provide two way and one way traffic Enhanced outbound access connection to South Meriden

Downtown Signals Congestion Mitigation and Air Quality (CMAQ) Grant One of thirteen communities 13 Signals $2.9 million Design 35% complete Anticipated Construction 2018

Downtown Signals Signals nearing end of useful life Prepare for increased Hartford Line rail use Two way conversion Replace 4 signals Modify 7 signals Remove 2 signals

Downtown Signals Cook Ave Two-way from Hanover St to Cook Ave Hanover St Corridor Two-way from Cook Ave to South Grove Street East Main Street / West Main St Corridor Two-way from Pratt Street to Cook Ave Church St Two-way from Colony Street to Barristers Ct Perkins Square Two-way from East Main Street to South Colony St

What has been done so far First Mile / Last Mile Transit study Eversource Gas upgrades Mills redevelopment and pending demo 24 Colony St and parking garage Meriden Green Train Station TOD Development under contract / pending 11 Crown St (Record Journal) 177 State St 116 Cook Ave Former Hospital

What has been done so far Harbor Brook Bradley Ave Bridge Coe Ave Bridge Columbus Ave Culvert Rehabilitation Cook Ave Bridge Demolition of 31/33/51 South Colony St Meriden Green Falcon Field Detention Basin Barr Road Mitigation

Harbor Brook Flood Control Cooper St Bridge Funded 50% State / 50% Local Anticipated Construction Date 2017 Amtrak Bridge Locally Funded Anticipated Construction Date 2017 Mill Street Bridge Removal Design Anticipated to begin 2017 Cedar St Bridge Design Anticipated to begin 2017 Center St Bridge Funded Federal and Locally Construction 2018 Cooper St to Bradley Ave Channel Improvements Design 75% complete Anticipated Construction 2017

Question and Answer?????

For More Information Harbor Brook Robert Bass, P.E. Director of Public Works 203-630-4019 Downtown Traffic Howard Weissberg, Associate City Engineer 203-630-4022

Cook Ave two way conversion from Hanover St to Cook Ave Hanover Street at Cook Ave (Route 71 SB) (Southwest limit) NEW West Main Street at Cook Ave (Route 71 SB) (Northwest limit) NEW Hanover St Corridor Hanover Street at Butler Street MODIFY Hanover Street at South Grove Street MODIFY Hanover Street at Senior Center (Pedestrian-activated signal) MODIFY Hanover Street at South Colony Street REMOVE East Main Street / West Main St Corridor East Main Street at Pratt Street (East limit) NEW East Main Street / West Main Street at Colony Street NEW West Main Street at Barristers Court REMOVE (2017) West Main Street at Police / Court Complex (Pedestrian-activated signal) MODIFY West Main Street at Grove Street MODIFY West Main Street at Butler Street MODIFY Church St two way conversion from Colony Street to Barristers Ct Colony Street at Church Street MODIFY Perkins Square Perkins Square at Crown St REMOVE