APEX TM III MASS SPECTROMETER SITE GUIDE AND PRE-INSTALLATION INSTRUCTIONS

Size: px
Start display at page:

Download "APEX TM III MASS SPECTROMETER SITE GUIDE AND PRE-INSTALLATION INSTRUCTIONS"

Transcription

1 APEX TM III MASS SPECTROMETER SITE GUIDE AND PRE-INSTALLATION INSTRUCTIONS NOTE: Important Facilities and Installation Data Within Please Forward to Cognizant Engineering or Using Department All measurements in millimeters Page 1 of 27

2 Page 2 of 27

3 1.0.0 INTRODUCTION It is advantageous for the user to make certain preliminary preparations prior to the arrival of the Bruker field service engineer. These arrangements vary according to the support equipment purchased. However, the basic installation is identical for all units. The basic installation preparations include: a. The selection of the location for the APEX TM III Mass Spectrometer. b. The utility installation necessary for its operation. c. Floor loading determination. d. A method of handling the magnet during installation. e. The purchase of the required cryogens (nitrogen and helium) The following are recommendations for the preparation of your site for the installation of a superconducting magnet FTMS spectrometer system. If any of these recommendations cannot be achieved, please contact your local Bruker service office as soon as possible so that alternate plans can be made prior to the beginning of the installation SELECTION OF THE LOCATION FOR THE MASS SPECTROMETER SAFETY CONSIDERATIONS Superconducting magnets can cause potential safety hazards due to their extended magnetic stray field, their large attractive forces on ferromagnetic objects, and their large content of cryogenic liquids. It is the sole responsibility of our customers to ensure safety in their FTMS laboratory and to comply with local safety regulations. Inc. (BDI) is not responsible for any injuries or damages due to an improper room layout or due to improper operation routines MAGNETIC ATTRACTIVE FORCES Strong attraction of ferromagnetic objects may occur at close distance to the magnet, where the magnetic field is above 50 to 100 Gauss. The attractive force depends on the mass of the object and on the distance from the magnet. It increases rapidly when the distance is reduced (by the 7th power). Hence, it may change from barely noticeable to uncontrollable in a very short distance. It is therefore very important that a safety space is established and marked around the magnet, and that all pathways in the FTMS room stay clear of that area. Massive iron objects such as pressurized gas cylinders used for GCMS, QEA, etc. are extremely dangerous in the vicinity of a superconducting magnet. They should be mounted very close to the door and away from the magnet, or even better, outside the magnet room. In the minimum they should remain outside the 5 gauss line as indicated by the field plots given in the Appendix in this document. Inside the room with the magnet, a wall mounted gas distribution system is recommended. Page 3 of 27

4 2.1.2 MAGNETIC STRAY FIELD It is generally accepted that stray fields are harmless below 3 to 5 Gauss (ten times the earth's magnetic field). Stronger stray fields closer to the magnet may disturb some heart pacemakers, erase magnetic cards and storage devices, and adversely affect watches and micro mechanical devices. It is therefore recommended to mark the 5 Gauss line around the magnet, display warning signs and to limit access to areas with more than 10 to 20 Gauss field to FTMS staff only. A safe location for mechanical watches, wallets, and software disks at the entrance to the FTMS laboratory or in a separate room is recommended for storage of these items by the FTMS staff. Be aware that the magnetic stray field extends in all three dimensions and is not affected by walls, floors, or ceilings. For FTMS magnets the horizontal extension is larger than the vertical one. High fields may also affect the rooms above and below the magnet. Local shielding of sensitive devices such as computer displays is possible in stray fields below 10 Gauss. Global shielding of the entire magnet stray field is usually very costly. However, stray fields can be greatly reduced by using a shielded magnet. Bruker strongly recommends the use of shielded magnets, especially in multi-user installations and facilities where access to the magnet cannot be easily restricted. Stray field plots and warning signs will be included with each magnet. Full stray field plots are also included in this document and extra copies of field plots or warning signs are also available from our customer service representative. A summary of the 5 and 10 gauss field lines for each system follows in table 1 as well as a summary of the effects of magnetic stray fields contained in table 2. Table 1: Stray field lines Magnet z - Axis (Field z Axis (Field Axis) Axis) x, y - Axis x, y - Axis 5 Gauss 10 Gauss 5 Gauss 10 Gauss APEX TM II m 0.8 m ** ** Passively Shielded APEX TM II m 1.4 m 0.7m 0.8m Actively Shielded APEX TM II m 1.7 m 1.1m 0.9m Actively Shielded APEX TM II-94 Actively Shielded 2.2m 2m 1.5m 1.4m ** Does not extend beyond magnet dewar. Page 4 of 27

5 Table 2: Summary of Magnetic Field Effects (level where damage can occur) Effects on electron microscopes 1 Gauss Disturbance of color computer displays* 1-3 Gauss Disturbance of monochrome computer displays 3-5 Gauss Erasing of credit cards and bank cards 10 Gauss Effects on watches and micro mechanical devices 10 Gauss Lowest known field effect on pace makers 1-7 Gauss Erasing of magnetic tapes 20 Gauss Saturation of transformers and amplifiers 50 Gauss Erasing of floppy diskettes or magnetic tape 350 Gauss *Disturbances of computer displays can be effectively reduced by shielding the display, as long as the field is below 10 Gauss RECOMMENDATIONS ON SAFETY These recommendations are adequate for industries and research institutes with limited public access. The general public should not be allowed access to areas with fields above 5 Gauss. No inexperienced persons (such as visitors, cleaning staff, electricians, plumbers, painters, etc.) should have access to the magnet without supervision by the FTMS staff. Table 3: Recommended Area Restrictions Warning signs (safety limit for medical devices) Access limited to FTMS staff only (safety limit for heavy iron objects) Floor markings (safety limit for attraction of iron) Pressurized gas cylinders (wall mounted) 5 Gauss 10 Gauss 5 Gauss 10 Gauss CRYOGENIC LIQUIDS Superconducting magnets use liquid Nitrogen and Helium as cooling agents. These liquids expand their volume by a factor of 700 during evaporation and warm-up. The gases are nontoxic and completely harmless as long as adequate ventilation is provided to avoid suffocation. During normal operation only 100 to 150 cubic feet per day of nitrogen are evaporated, but during a quench 1500 to 3500 cubic feet of helium gas are produced within a short time. Windows and doors are sufficient for ventilation even after a quench, but the magnet should never be in an airtight room. Room layout, room clearance and magnet height should be such that an easy transfer of liquid nitrogen and helium is possible. This will reduce the risks of accidents considerably. Page 5 of 27

6 2.2.0 OPERATIONAL CONSIDERATIONS The ease or difficulty of day-to-day operation depends strongly on the room dimensions and layout. Easy access to the magnet for refilling the cryogenic liquids and adequately located gas and power outlets are important. Room dimensions should be sufficient to allow convenient pathways around the magnet. The addition of auxiliary inlets and equipment such as GC, LC, ethernet connections, etc. should be taken into account at this time also. The minimum room height is given by the space needed for refilling helium. However some extra space makes handling much easier. Special short helium transfer lines are available, but they do have higher helium transfer losses. Large magnets require rooms with oversized doors to enable installation. Magnet dewars are shipped with support fixtures (shipping bungs), which must be removed at the installation site. This requires a suitable hoist with sufficient room height, which is generally more than the minimum required for helium transfer. If this cannot be done in the lab, the magnet system may be moved after assembling, however this will be done at the customers risk. There is no danger of damage to the magnet or dewar, but the very tight tolerances of alignment may be disturbed by moving a dewar after assembly. If so, it only shows up during the cool down or after energization. This requires the warming up and realignment of the dewar with a corresponding waste of much time and helium. The vacuum cart and electronics consoles require sufficient clearance around them to provide for adequate cooling. This space also allows for installation and service of the system which includes convenient changing of the optional sources, changing pump oils and general system maintenance. Please refer to Chapter for system specific recommended room layouts FLOOR LOADING The FTMS magnet system is quite heavy. Depending on field strength, bore diameter and specially the shielding, the weight may be 1,500 to 13,200 kg. The floor of the room must be strong enough to support the weight of the instrument allowing for a certain amount of mild vibration. In general, for field strengths of < 7.0 Tesla, the dead weight floor loading for the magnet is approximately 0.40 kg/cm2 for an unshielded magnet and 1.4 kg/cm2 for a shielded magnet. Please refer to Chapter for the exact footprint of each instrument model ELECTRIC POWER An important consideration when selecting the area for the Mass Spectrometer is availability of adequate power. The magnet system needs electric power only during charging and discharging and for the operation of the optional helium recovery system. Regardless of what accessory equipment is purchased for a particular installation, sufficient power should be brought into the area to provide for future needs. There are recommendations for power distribution located in Chapter 5.1.1, along with the floor layout. A complete APEX TM III Mass Spectrometer requires up to 20 KVA (please refer to Chapter for a explanation of the power consumptions of the various instrument configurations.) Bruker recommends Page 6 of 27

7 that one 3 phase five wire 380 V AC phase to phase, 30 Amp, 50 or 60 Hertz circuit (220 Volt to neutral) be available before the instrument arrives. Power distribution within the mass spectrometer consists of three 220V, 30A circuits-split off from the three phase 220 volt to neutral circuit If the only available power is 208 V AC (common in the United States) then a boost transformer (optionally available) must be installed to raise the output to 380 V AC. If this option is to be used, the transformer should be installed prior to the delivery of the instrument. For additional information on using the boost transformer please contact your sales/service office. If the line voltage fluctuations exceed +10% or -5%, a voltage regulator must be installed. A quick disconnect, in addition to the emergency kill switch on the system, may be required by safety codes in many areas. The customer is responsible for appropriate connection of the instrument to the outlets. The instrument is delivered with a long enough power cable without connector WATER The ultra high vacuum pumps in the mass spectrometer are water-cooled and require a continuous stream of water. Turbo-pumped systems require 150 Liter/hour of filtered, soft water that is not to exceed 20C. Cryopump systems require 200 Liter/hour of filtered, soft water that is not to exceed 20C. If filtered soft "house" water is used, a drain for the water is necessary. A constant pressure regulator on the water line is recommended if the water pressure is likely to change a large amount over a 24-hour period. Many communities prohibit the use of "house" water for cooling and require a closed loop heat exchange system. Bruker, due to environmental considerations, encourages the use of closed loop water chiller systems. Turbo pump systems require water chillers with a 500 W cooling capacity and 40psi supply pressure while cryo pump systems require water chiller with a 3 KW (or better) cooling capacity. Please note that cooling capacity for heat exchangers may depend on the room temperature. These specifications should be examined closely and possibly forwarded to your heat exchanger vendor, for a recommendation based on the proper requirements VENTILATION AND AIR CONDITIONING For most efficient operation, the mass spectrometer must be in an air-conditioned room where both temperature and humidity are controlled. It is important to note, a complete operating mass spectrometer will produce between 15 and 20,000 BTU/hr exclusive of other sources of heat. Room temperature must not exceed 72deg. F and should be maintained within ±10deg F for best performance of the FTMS spectrometer. Relative humidity should remain in the 40 to 60% range. If the air in the lab gets too damp high voltage arcing can be a problem as well as excessive condensation on the cryostats and cooling water lines. If it is too dry there are problems with static electricity. Ventilation should be adequate to avoid depletion of oxygen. Constant air temperature and pressure is very important for high performance operation. Rapid ambient pressure and temperature fluctuations reduce the performance of the FTMS spectrometer. If an air conditioning unit is installed, it should be far away from the magnet. The air in the vicinity of the magnet dewar should not be disturbed by drafts from an inlet or an outlet of the ventilation Page 7 of 27

8 system. If the optional water chiller is used as the source of cooling water for the turbo or cryopumps, the heat load due to these units must be taken into account when calculating the air conditioning capacity GASES Dry, oil and dust free, clean regulated pressurized air at 60 to 100 psi with a dew point of -40deg. F or lower is required for operation of the pneumatic valves on the vacuum system. For refilling the magnet dewar with cryogenic liquids both pressurized nitrogen and helium gas are also required. The electrospray ion source on the APEX TM III requires a source of dry nitrogen psi and 2 scfm and dry oxygen (for negative ions) at psi and 2 scfm. If no fixed gas supplies are available for refilling or the electrospray source, transportable cylinders may be used. However, if ferro-magnetic cylinders are used in the presence of strong magnetic fields, they may present a possible source of serious accidents. Non-magnetic liquid nitrogen cylinders with a pressure build-up system are convenient sources of dry nitrogen gas. Gas requirements for the optional GC inlet depend on the actual experiment planned. MS/MS experiments require a small cylinder of argon or another suitable collision gas LIQUID NITROGEN AND HELIUM A constant and dependable source of the liquid cryogens is essential to maintaining the magnetic field. Therefore, it will be necessary to arrange for the delivery of liquid nitrogen and helium if the facility does not have it readily available. These arrangements may be made through a local supplier of liquefied gases. Typical requirements for installation are: approx. 300 Liters (for 3 Tesla) to 1400 Liters (for the 9.4Tesla) of liquid Helium approx. 500 Liters (for 3 Tesla) to 1500 Liters (for the 9.4Tesla) of liquid Nitrogen Typical requirements for routine fills are: approx. 100 L of liquid He for refills every approx. 90 days approx. 75 L of liquid N2 for refills once per week Please refer to the individual Magnet specifications for exact numbers RADIO FREQUENCY INTERFERENCE RF interference can cause spikes in the spectra at any m/z ratio whose resonance frequency is close to the frequency of the interference. The most common source of RF interference is TV and AM radio stations. They broadcast at frequencies in the range of interest for FTMS (10 MHz to 10 KHz). Other possible sources can be paging systems, ham radio transmitters, arc welders, and other RF spectrometers. Due to the relationship of transmission power and distance radiated and since a common mode rejection of 80- Page 8 of 27

9 100 db is attainable in the receiver chain, these interferents are rarely a major problem RF interferents are often introduced on a poor power grounding coming into the FTMS laboratory TELEPHONE AND ETHERNET It is highly recommended that a telephone and ethernet be installed at the console site. It should be accessible to the operator of the instrument while seated at the console. This would be used for troubleshooting assistance as well as applications support. In addition, APEX TM III spectrometers with the UNIX or Windows NT based acquisition computer use an ethernet connection for remote diagnostics and remote software upgrades or correction of corrupt data, an ethernet line within reach of the computer is required for this function. For facilities where outside ethernet or telephone connection to computers is not permitted for security reasons, an outgoing only telephone line and a voice connection are recommended for remote diagnosis RECOMMENDATIONS FOR ROOM LAYOUT For safety reasons, the magnet should be located away from doors and in a location that the stray field of 10 to 20 Gauss does not extend beyond the room. Refilling of cryogenic liquids is more comfortable if the magnet system is easily accessible for the transport dewars and if adequately located gas outlets are available. The rate of nitrogen boil-off from the system depends on the dewar surface temperature; hence the dewar should not be located close to a heat source or in direct sunlight. The Computer workstation and the electronics console should be placed at sufficient distance from the magnet and oriented so that the display monitor, disk and other magnetic storage devices are on the far end from the magnet. Normally the magnet is located on the right side of the console. If a left hand system is required, this should be specified at the time of order. An installation and access space to the rear of the console and the right side of the vacuum system is recommended with a minimum clearance of 2 feet to the walls. Recommended room layouts are provided at the end of this guide OTHER CONSIDERATIONS In addition to the above, the following should be considered. Dust and corrosive gases or vapors are to be avoided if possible. The same consideration should be given to the mass spectrometer as would be given to any precision electrical equipment containing relays, meters, insulators, etc. The instrument presents no problems in this connection which are not encountered in other electrical and electronic equipment. Most biological samples require refrigeration for long and short-term storage. It is recommended that a freezer be located near the instrument for storage of biological samples and calibration compounds. However, when placing the refrigerator in the same vicinity as the magnet system, remember to maintain a distance from the 5 gauss stray field so the compressor of the refrigerator is not strained. Sufficient space for sample preparation, short-term storage of LC solvents, and storage of optional ion sources and inlets, spare parts and tools is desirable for day-to-day operation. Page 9 of 27

10 Page 10 of 27

11 3.0.0 PERFORMANCE CONSIDERATIONS Almost any site is suitable for routine FTMS operations and good performance may be achieved even with moderate environmental conditions of the FTMS room and its close vicinity. In general, higher performance is possible with FTMS in a given set of environmental conditions than is possible with other high resolution MS systems. Even so, ultra-high performance operation requires a very stable and constant environment. Top performance will only be achieved if you select an adequate magnet location. It is therefore recommended for large FTMS laboratories to plan ahead and influence the building construction in the planning phase. It should be considered that the trend will always be towards larger magnetic fields with inherently higher demands on the conditions of the installation site in order to maintain and optimal operation STATIC IRON DISTRIBUTION Static iron distribution in the vicinity of the magnet will exert a force on the magnet and disturb the field homogeneity in the FTMS cell. The force may disturb the very tight tolerances of alignment, if so, it shows up during the energizing of the magnet. In that case the magnet must be moved away from the iron. An increase in the distance of 25% is usually sufficient. Extended areas of iron with near constant density distributions generate rather harmless field disturbances. Their effects can easily be removed with the superconducting X, Y, and Z shims that are standard on Bruker systems. Concentrated iron objects, however, can produce rather strong local field variations, which are difficult to correct for. Since these may be corrected by shimming during installation, it is recommended that the location of any large iron objects such as gas cylinders be decided before installation so that they may be present at the installation. This aspect becomes more important for high field and wide bore magnets with extended stray fields. If the magnet must be located in the vicinity of iron or steel support beams, a proper alignment is important. Horizontal iron concentrations at heights close to the magnetic center and iron objects terminating near the magnet should be avoided. They lead to very asymmetric field disturbances. Since these are, in most cases, heating or plumbing devices rather than structural support beams, they may need to be removed before installation. Section 3.3 gives some examples of minimum distances, which should be considered for magnet positioning INTERFERENCE FROM VARIABLE MAGNETIC FIELDS Variable field effects are very difficult to eliminate. Therefore they should be considered early in the planning stage. Variations can originate from moving iron objects such as metal chairs, doors, handcarts, elevators, and cars. They also can be caused by electromagnetic equipment, from power lines carrying DC currents or from floor vibrations or oscillations of the entire building. The most disturbing fluctuations are step-like field changes produced by large switching DC currents from subways, trolley cars, etc. or from field ramping mass spectrometers during fly-back of the field. If you have any of these near your site contact Bruker for a magnetic interference survey of the lab as early in the planning stage Page 11 of 27

12 as possible. In general, mass calibration of the FTMS spectrometer is not affected if the variation of a moving iron object occurs outside of the 5 gauss line for the magnet used in the system SUMMARY OF MAGNETIC FIELD DISTURBANCES: Table 4: Stray field or distance from the magnet at which effects may occur Force from large iron objects of over 2000 lbs. Force from iron objects over 400 Lbs. Field from localized static iron of approx. 200 Lbs. Field from moving iron objects of approx. 200 Lbs Metal chairs and doors Hand-carts and heavy metal doors Large moving objects (elevators and cars) Maximum floor vibrations below 1 Hz 20 Gauss 50 Gauss 50 Gauss 3 Gauss 6 to 10 Feet 10 to 15 Feet 20 to 40 Feet Approx. 0.1 mm Table 5: Stray field or distance from the magnet which may lead to noticeable instabilities Minimum field fluctuations (steps) Maximum ac fields (5 to 10 Hz range) Sweeping fields from mass spectrometers (with slow ramping up and no fly-back) Large switching DC currents (subway or trolley) 1 mgauss 5 to 10 mgauss 25 to 30 feet 500 to 1500 feet RECOMMENDATIONS FOR ROOM SELECTION We recommend locating the APEX TM III system at sufficient distance from large moving objects such as cars and elevators. Optimal locations are far away from internal and external traffic areas. For installation sites of high field magnets (7.0 and 9.4T) the rooms above and below the magnet must also be rather quiescent. We do not recommend locations in high rise buildings above the 5th floor because of vibration, sway, and atmospheric pressure fluctuations. The optimum site is in the basement or ground floor directly on the concrete slab. We also advise against locating high field systems in buildings near subway or train lines because of the high magnetic field instabilities caused by the passing of trains and DC currents. Floor support should be rigid in order to avoid vibrations. Windows should be located in such a way that sunlight does not shine directly on the dewar, and constructed such that no sudden pressure fluctuations are produced by winds. For optimal performance the room should be air conditioned with constant temperature control. Page 12 of 27

13 Inc. can provide site information and site inspections for your specific lab. Please contact your sales or service representative for more information and help in preparing the best possible site for your instrument MASS SPECTROMETER INSTALLATION RECEIVING Purchasers are notified at least seven days in advance of the proposed arrival date of the instrument, so that arrangements may be made to move it to the mass spectrometer room. In advance of shipment, contact the local Bruker office with any questions concerning installation of the instrument. It is assumed by Bruker that the instrument can be unloaded on a loading dock and pallet jacks are available at the customer site. If there is no standard height loading dock, Bruker has to be notified prior to shipment to make necessary arrangements. The console, vacuum system, magnet, and accessories will be separately crated allowing the use of a forklift truck to move the system to its final location. The customer has to make sure all hallways and doors from the loading area to the final position of the instrument are wide and high enough to move the magnet and vacuum cart through. The vacuum cart is 110cm (44 ) long and 127cm (50 ) wide, so a minimum door with of 130cm (51 ) is required on all doors. Some passively shielded magnets may require even wider doors; please refer to the magnet guide for dimensions. The minimum door height for most magnets is 7 feet (2.1m). Shipping crate dimensions: Vacuum cart ~1200lbs (140 x 175 x 175cm) Console: ~400lbs (85 x 95 x 140cm for U.S. or 155 x 95 x 160cm for international freight) Accessories: lbs (155 x 95 x 90cm) one or two boxes Magnet: refer to Magnet Guide Upon request, a Bruker representative will visit the customer site for an inspection. Page 13 of 27

14 4.2.0 GENERAL INSTALLATION PROCEDURE It is advisable to wait for arrival of the Bruker representative before any equipment is removed from the shipping crates. However, the crates may be placed near the system s final position. The utilities and cryogens should have been obtained. No attempt should be made to assemble or cool the magnet prior to the arrival of the field service engineer. It is advantageous to have at least one scientist or engineer who can spend most of his/her time working with the Bruker field service engineering during the installation. He/she will acquire valuable experience during this period as well as reduce the time of installation. During the installation, the personnel who are to be responsible for the operation and maintenance of the instrument should also be familiarizing themselves with the data system, circuits, manuals and as much of the instrument as possible LIFTING EQUIPMENT Assembly of the magnet system may be required. In all cases the facility must supply the necessary equipment to remove the magnet and vacuum cart from their shipping crates. The magnet system may require assembly onto a stand requiring lifting equipment, which can raise the magnet to the minimum ceiling height for your magnet. Other magnets (shielded Bruker-Magnex) may require assembly of the shielding. In this case the shields will have to be raised into position alongside the magnet. This usually requires a mobile hoist and the proper slings. For specific requirements for your system, please contact your local service office. Page 14 of 27

15 4.2.2 CRYOGENIC LIQUIDS The customer is responsible for up to the amounts of cryogen in the table in the following table. Total volume used may be less. Bruker offers a liquid helium plan, which provides all of the liquid helium needed for the cool down for a fixed price. Please contact your local sales representative or the magnet department for details and availability. Table 6: Cryogen Requirements Magnet LHe for installation (liters) LHe hold time (days) LHe refill volume (liters) N2 initial cooldown (liters) N2 hold time (days) Bruker/Magnex 3 T 160mm 300 > > N2 refill volume (liters) Bruker/Magnex 4.7T 160mm Actively Shielded Bruker/Magnex 7T 160mm Actively Shielded Bruker/Magnex 9.4 T 160mm Actively shielded 500 > > > > > > Note: All liquid nitrogen must be in low-pressure liquid withdrawal dewars (LX type). Converted gas packs cannot be used COOL DOWN EQUIPMENT The following items are also needed for the cool down of the magnet and must be supplied by the customer: One T cylinder of (industrial grade) nitrogen gas. One T cylinder of (industrial grade) helium gas. One low pressure gas regulator for inert gas (0-25 psi) Twenty feet of 3/8 inch Tygon tubing. Page 15 of 27

16 One Heat gun for de-icing and drying. Page 16 of 27

17 5.0.0 Appendix PRE-INSTALLATION CHECKLIST APEX TM II MASS SPECTROMETERS Space Requirements Installation Clearance around instrument Receiving Auxiliary equipment Handling the magnet Floor loading Personnel Required Ways from loading dock to Instrument location Electrician Utilities Environmental Filtered Soft Water Electrical power (380V 3-phase) Liquid nitrogen and helium Gas and Air Freezer for sample storage Air conditioning Electrical interference Magnetic Interference Vibration Dust and Corrosion Customer Signature / Date Bruker Representative Signature / Date Page 17 of 27

18 5.1.1 RECOMMENDED SITE LAYOUT for the APEX TM III The following figure shows the minimal room requirements for an APEX TM III FTMS system: All dimensions in mm *: Recommended place for all utility outlets (power, water, gases) For dimensions of other magnets please refer to the individual magnet specifications. Power Requirements: Three phase 380/220 V AC to neutral (+10%, -5%), 30 A, with ground (vacuum system and consoles) Single phase 110 or 220 V AC, 30/15A, (optional closed loop water chiller / LC / GC). Single phase 110 or 220 V AC, 20/10 A, quad outlet for computer and accessories Gas Requirements Dry, filtered dust and oil free; dew point below -40deg. F; psi regulated. Drying gas for the ESI source and Air for the pneumatic valves. Connected to a ¼ tubing each. Cooling Water Closed loop water chiller with at least 500W cooling capacity and 40psi pressure or 75 Liter/hour of filtered, soft house water that is not to exceed 20C. Page 18 of 27

19 Environmental Room temperature not to exceed 72deg. F. Total heat output of the system is around 4 kw (15,000-20,000 BTU/hr), depending on options minimum ceiling height: Passively shielded magnets: 3085mm, Actively shielded magnets: 3130mm, 9.4T AS magnet: 3300mm Magnet must be located as to be accessible for filling with cryogens. Page 19 of 27

20 5.1.2 Magnet Stray Fields 3T Passively Shielded Magnet Stray Field Page 20 of 27

21 4.7 T Actively Shielded Magnet Stray Field Page 21 of 27

22 Page 22 of 27

23 Page 23 of 27

24 7 T Actively Shielded Magnet Stray Field Page 24 of 27

25 Page 25 of 27

26 9.4 T Actively Shielded Magnet Stray Field Page 26 of 27

27 Page 27 of 27

DD2 Site Preparation Checklist Hardware Site Preparation Specification

DD2 Site Preparation Checklist Hardware Site Preparation Specification Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities. Important Customer Information. Cary 4000/5000/6000i UV-Vis spectrophotometer Site Preparation Checklist

Customer Responsibilities. Important Customer Information. Cary 4000/5000/6000i UV-Vis spectrophotometer Site Preparation Checklist Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities

Customer Responsibilities Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities

Customer Responsibilities Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities

Customer Responsibilities Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities. Important Customer Information Series Q-TOF LC/MS Systems Site Preparation Checklist

Customer Responsibilities. Important Customer Information Series Q-TOF LC/MS Systems Site Preparation Checklist Thank you for purchasing an Agilent system. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation is

More information

Customer Responsibilities. Important Customer Information. Agilent 6400 Series Triple Quad LC/MS Site Preparation Checklist

Customer Responsibilities. Important Customer Information. Agilent 6400 Series Triple Quad LC/MS Site Preparation Checklist Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Customer Responsibilities

Customer Responsibilities Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Varian 400-MR Magnetic Resonance Spectrometer Pre-installation Instructions

Varian 400-MR Magnetic Resonance Spectrometer Pre-installation Instructions Checklist NOTE: Do not unpack the boxes. Varian 400-MR Magnetic Resonance Spectrometer Pre-installation Instructions Mark the check box after satisfying each requirement as described in the instructions.

More information

Customer Responsibilities. Important Customer Information. Agilent Infinity II Preparative HPLC System Site Preparation Checklist

Customer Responsibilities. Important Customer Information. Agilent Infinity II Preparative HPLC System Site Preparation Checklist Agilent Site Preparation Infinity II Checklist Preparative HPLC System Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer

More information

Customer Responsibilities

Customer Responsibilities Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

Microscopy Cryogenic WORKSTATION. Performance by Design

Microscopy Cryogenic WORKSTATION. Performance by Design CRYO Microscopy Cryogenic WORKSTATION Optical cryostat for use in microscopy and spectroscopy Performance by Design RC102-CFM Microscopy Cryostat offers fast cooldown, high efficiency, excellent temperature

More information

SPECIFICATION FOR AN MRBR 9.4 TESLA/310MM/AS CRYO-COOLED MAGNET SYSTEM

SPECIFICATION FOR AN MRBR 9.4 TESLA/310MM/AS CRYO-COOLED MAGNET SYSTEM SPECIFICATION FOR AN MRBR 9.4 TESLA/310MM/AS CRYO-COOLED MAGNET SYSTEM Prepared by:- Magnex Scientific Limited The Magnet Technology Centre 6 Mead Road Oxford Industrial Park Yarnton, Oxford OX5 1QU, UK

More information

UltraLo 1800 Alpha Particle Counter

UltraLo 1800 Alpha Particle Counter XIA LLC UltraLo 1800 Alpha Particle Counter Site Requirements & Planning Version: 0.4 Friday, February 15, 2013 Table of Contents I. Site Preparation Tasks... 3 A. Instrument Overview... 3 B. Installation

More information

490 Micro GC Site Preparation Checklist

490 Micro GC Site Preparation Checklist Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats

RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats www.cryoindustries.com INDUSTRIES RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats Designed

More information

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS INTRODUCTION The Janis Research Company's Superconducting Magnet/Cryostat System is one of the most versatile tools available to the scientist

More information

Cryostream 800 Series

Cryostream 800 Series Cryostream 800 Series Cryostream 800 Series Nearly 30 years after the invention of the first Cryostream Cooler, Oxford Cryosystems is proud to announce the launch of the new 800 series Cryostream. The

More information

PURPOSE OF THE POLICY

PURPOSE OF THE POLICY Title: Safe Storage, Handling, Use and Disposal Procedures of Compressed Gas Cylinders Effective Date: November 2005 Revision Date: March 1, 2017 Issuing Authority: Responsible Officer: VP, Capital Projects

More information

Proudly serving laboratories worldwide since 1979 CALL for Refurbished & Certified Lab Equipment Varian 310

Proudly serving laboratories worldwide since 1979 CALL for Refurbished & Certified Lab Equipment Varian 310 www.ietltd.com Proudly serving laboratories worldwide since 1979 CALL +847.913.0777 for Refurbished & Certified Lab Equipment Varian 310 310 LC/MS Manual System INCLUDES: 310-MS LC/MS triple quadrople

More information

NGN Series nitrogen generator

NGN Series nitrogen generator NGN Series 8-64 nitrogen generator Applications how it works RK series 5-40 F Blanketing of Chemicals and Pharmaceuticals Gas Assisted Injection Moulding (GAIM) Laser Cutting Food Heat Treament of Ferrous

More information

The HumiSys. RH Generator. Operation. Applications. Designed, built, and supported by InstruQuest Inc.

The HumiSys. RH Generator. Operation. Applications. Designed, built, and supported by InstruQuest Inc. The HumiSys RH Generator Designed, built, and supported by InstruQuest Inc. Versatile Relative Humidity Generation and Multi-Sensor System The new HumiSys with single or dual RH probes capabilities is

More information

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming,

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming, 1 INTRODUCTION Quantum Technology is a leading scientific equipment supplier. For the last thirty years we served our customers by tailoring our products to each customer s unique requirements. Quantum

More information

Best Practice Guide, Servomex 2700

Best Practice Guide, Servomex 2700 For full installations details refer to the. Best Practice Guide, Servomex 2700 Mounting: General Guidelines: Servomex 2700 Control Units and air supplies (utilities units) should, ideally, be mounted

More information

Varian 240-MS GC/MS Ion Trap Mass Spectrometer Pre-installation Instructions

Varian 240-MS GC/MS Ion Trap Mass Spectrometer Pre-installation Instructions Varian 240-MS GC/MS Ion Trap Mass Spectrometer Pre-installation Instructions Checklist NOTE: Do not unpack the boxes. Place a check in the box after satisfying each requirement as described in the instructions.

More information

Detector Carrier Gas Comments Detector anode purge or reference gas. Electron Capture Nitrogen Maximum sensitivity Nitrogen Argon/Methane

Detector Carrier Gas Comments Detector anode purge or reference gas. Electron Capture Nitrogen Maximum sensitivity Nitrogen Argon/Methane Gas requirements Gases for packed columns The carrier gas you use depends upon the type of detector and the performance requirements. Table 520-1 lists gas recommendations for packed column use. In general,

More information

TECHNICAL SPECIFICATION. SPC-1 Stirling Process Cryogenerator

TECHNICAL SPECIFICATION. SPC-1 Stirling Process Cryogenerator TECHNICAL SPECIFICATION SPC-1 Stirling Process Cryogenerator Reference 80 8013 00 Issue Date August 1, 2015 1. INTRODUCTION This document contains detailed technical information and specifications for

More information

Varian 325-MS LC/MS Quadrupole Mass Spectrometer Pre-installation Instructions

Varian 325-MS LC/MS Quadrupole Mass Spectrometer Pre-installation Instructions Varian 325-MS LC/MS Quadrupole Mass Spectrometer Pre-installation Instructions Checklist NOTE: Do not unpack the shipping cartons. Check off each checklist box after satisfying each requirement as described

More information

ATL. Take Control of your Helium Supply. Advanced Technology Liquefier The next generation of helium recycling

ATL. Take Control of your Helium Supply. Advanced Technology Liquefier The next generation of helium recycling ATL Take Control of your Helium Supply Advanced Technology Liquefier The next generation of helium recycling Helium A Limited and Costly Resource Cryogenic researchers and technicians around the world

More information

TECHNICAL SPECIFICATION. SPC-4 Stirling Process Cryogenerator

TECHNICAL SPECIFICATION. SPC-4 Stirling Process Cryogenerator TECHNICAL SPECIFICATION SPC-4 Stirling Process Cryogenerator Reference 80 8043 00 Issue Date August 1, 2015 1. INTRODUCTION This document contains detailed technical information and specifications for

More information

AVANCE. Planning for AVANCE Systems 800 MHz WB with Ascend Aeon (actively refrigerated) Magnets User Manual Version 008. Innovation with Integrity NMR

AVANCE. Planning for AVANCE Systems 800 MHz WB with Ascend Aeon (actively refrigerated) Magnets User Manual Version 008. Innovation with Integrity NMR AVANCE Planning for AVANCE Systems 800 MHz WB Site with Ascend Aeon (actively refrigerated) Magnets User Manual Version 008 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved.

More information

TECHNICAL DATA MAINTENANCE AIR COMPRESSOR MODEL G-1

TECHNICAL DATA MAINTENANCE AIR COMPRESSOR MODEL G-1 Dry 131h 1. DESCRIPTION The Viking Model G-1 Maintenance Air Compressor is an electric motor-driven, aircooled, single-stage, oil-less compressor. The unit is equipped with a check valve and provides a

More information

4-7 kw/ hp. Dual Output Compressors (Air/Nitrogen) Driving Nitrogen Forward

4-7 kw/ hp. Dual Output Compressors (Air/Nitrogen) Driving Nitrogen Forward GN 4-7 kw/5.5-10 hp Dual Output Compressors (Air/Nitrogen) Driving Nitrogen Forward Total capability, total responsibility Right at the heart of your business, Atlas Copco delivers quality compressed air

More information

Oxford Instruments Plasma Technology. PlasmaPro NGP80. Installation Data Sheet. Original Instructions.

Oxford Instruments Plasma Technology. PlasmaPro NGP80. Installation Data Sheet. Original Instructions. Oxford Instruments Plasma Technology www.oxford-instruments.com About this data sheet This data sheet provides basic information about the installation of a tool. Floor and wall loadings Table 1 lists

More information

490 Micro GC Site Preparation Checklist

490 Micro GC Site Preparation Checklist Thank you for purchasing an Agilent instrument. To get you started and to assure a successful and timely installation, please refer to this specification or set of requirements. Correct site preparation

More information

HumiSys HF High Flow RH Generator

HumiSys HF High Flow RH Generator HumiSys HF High Flow RH Generator Designed, built, and supported by InstruQuest Inc. Versatile Relative Humidity Generation and Multi-Sensor System The HumiSys HF is a high flow version of the previously

More information

Distribution Transformer Instruction Manual

Distribution Transformer Instruction Manual Distribution Transformer Instruction Manual TABLE OF CONTENTS SHIPPING.. 3 INSPECTION ON RECEIPT 3 HANDLING.. 4 INTERNAL INSPECTION 5 STORAGE.. 6 LOCATION 6 PREPARING FOR SERVICE 7 PUTTING INTO SERVICE

More information

OPERATION MANUAL NTF-15

OPERATION MANUAL NTF-15 OPERATION MANUAL NTF-15 Nitrogen Tire Filling Valve Stem Caps (Qty=200) Order P/N 436075 RTI Technologies, Inc 10 Innovation Drive York, PA 17402 800-468-2321 www.rtitech.com 035-81235-00 (Rev B) TABLE

More information

Vacuum. Dry Turbo Pumping Stations. Roughing Pumps for 1 K Helium Pots and Lambda Refrigerators. Hermetically Sealed Pumps for He3 Recirculation

Vacuum. Dry Turbo Pumping Stations. Roughing Pumps for 1 K Helium Pots and Lambda Refrigerators. Hermetically Sealed Pumps for He3 Recirculation Cryogenics Vacuum Dry Turbo Pumping Stations Roughing Pumps for 1 K Helium Pots and Lambda Refrigerators Hermetically Sealed Pumps for He3 Recirculation Oils, Filters and Traps Valves, Fittings and Adaptors

More information

PRC CO ² -LASER PRESENTATION

PRC CO ² -LASER PRESENTATION Page 1 of 7 PRC CO ² -LASER PRESENTATION GENERAL CHARACTERISTICS - Embedded PC104 Electronics with exchangeable software allowing very easy integration of customer specified functions: such as eg. specific

More information

Site Planning for AVANCE Systems

Site Planning for AVANCE Systems Site Planning for AVANCE Systems 750-950 MHz User Guide Version 002 The information in this manual may be altered without notice. BRUKER BIOSPIN accepts no responsibility for actions taken as a result

More information

AB SCIEX QTRAP 4500 System

AB SCIEX QTRAP 4500 System MAX cover image size 4.8 inches X 7.8 inches In Body page mode, draw a graphic frame to match this section and then go to the next step. Delete this text from the Front Cover Master page. View>Master Pages,

More information

Major Design Features

Major Design Features Major Design Features 3Flex Features Design Benefits Discussion 316 SS fittings and pneumatically actuated, hard-seal valves Provides virtually leak-free gas management with the lowest outgassing rate

More information

OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE

OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE 1 These instructions generally describe the installation, operation, and maintenance of subject equipment. The manufacturer reserves the right

More information

Ascend DNP. User Manual. Innovation with Integrity. Version NMR

Ascend DNP. User Manual. Innovation with Integrity. Version NMR 300 154 Ascend DNP User Manual Version 01 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,

More information

AVANCE. Site Planning for AVANCE Systems MHz User Manual. Innovation with Integrity. Version 009 NMR

AVANCE. Site Planning for AVANCE Systems MHz User Manual. Innovation with Integrity. Version 009 NMR AVANCE Site Planning for AVANCE Systems 300-800 MHz User Manual Version 009 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced,

More information

Markes Thermal Desorption Systems Site Preparation Page 1 of 8

Markes Thermal Desorption Systems Site Preparation Page 1 of 8 Thermal Desorption Systems Site Preparation Purpose of site preparation Your site must meet this specification to assure a successful and timely installation of your Agilent thermal desorption equipment.

More information

MEDICAL EQUIPMENT CATALOG

MEDICAL EQUIPMENT CATALOG THE MOST TRUSTED MEDICAL EQUIPMENT IN NORTH AMERICA MEDICAL EQUIPMENT CATALOG Total Components Including Bulk Oxygen Supply, Back up and Delivery Equipment Designs for High Pressure, Liquid or Bulk Applications

More information

Current Leads for Cryogenic Systems

Current Leads for Cryogenic Systems Current Leads for Cryogenic Systems American Magnetics Inc. s (AMI) Vapor Cooled Current Leads provide reliable and consistent electrical current transfer from room temperature (300K) to a Liquid Helium

More information

Series Environmental Chambers

Series Environmental Chambers 3119-600 Series Environmental Chambers Challenges in Non-Ambient Testing Testing at non-ambient temperatures adds another layer of challenges to your testing laboratory. Ensuring you get accurate and stable

More information

6000 SERIES OF PNEUMATIC DEADWEIGHT TESTERS

6000 SERIES OF PNEUMATIC DEADWEIGHT TESTERS 6000 SERIES OF PNEUMATIC DEADWEIGHT TESTERS USER MANUAL -1- SI-BARNET DEADWEIGHT TESTER 6000 SERIES Release: S31-0250 Revision: A Date: 05/08/03 MANUFACTURED BY: GE RUSKA RUSKA INSTRUMENT CORPORATION 10311

More information

RDK-408D2 Cold Head. Technical Manual. SHI-APD Cryogenics Inc Vultee Street Allentown, PA U.S.A. Revision A: September 2005

RDK-408D2 Cold Head. Technical Manual. SHI-APD Cryogenics Inc Vultee Street Allentown, PA U.S.A. Revision A: September 2005 RDK-408D2 Cold Head Technical Manual SHI-APD Cryogenics Inc. 1833 Vultee Street Allentown, PA 18103-4783 U.S.A. Revision A: September 2005 (Reference SHI Manual: December 18, 2003 266404A CD32ZZ-160A)

More information

DF-310E PROCESS ANALYSERS APPLICATIONS FEATURES

DF-310E PROCESS ANALYSERS APPLICATIONS FEATURES PROCESS ANALYSERS DF-310E The DF-310E is a Coulometric sensor based oxygen analyzer designed to measure trace and percent level oxygen in pure and multi-gas backgrounds for process and quality control

More information

6890 GC Site Preparation

6890 GC Site Preparation 6890 GC Site Preparation (a16011) This document is believed to be accurate and up-to-date. However, Agilent Technologies, Inc. cannot assume responsibility for the use of this material. The information

More information

AVANCE Systems. General Safety Considerations User Manual. Innovation with Integrity. Version 004 NMR

AVANCE Systems. General Safety Considerations User Manual. Innovation with Integrity. Version 004 NMR AVANCE Systems General Safety Considerations User Manual Version 004 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored

More information

BIMA cryogenics (Dick Plambeck, 18jan2007)

BIMA cryogenics (Dick Plambeck, 18jan2007) BIMA cryogenics (Dick Plambeck, 18jan2007) Normal operation. Monitor from the antennas > 6-meter > receivers multiple> cryo rtd page. Troubleshooting. sensor what is it? normal range stage1 outer dewar

More information

Installation Planning

Installation Planning Installation Planning INOVA NMR Spectrometer Systems Pub. No. 01-999038-00, Rev. B0501 \ Installation Planning INOVA NMR Spectrometer Systems Pub. No. 01-999038-00, Rev. B0501 Revision history: A0398 Changed

More information

NexION 1000/2000 ICP-MS

NexION 1000/2000 ICP-MS PREPARING YOUR LAB NexION 1000/2000 ICP-MS ICP - Mass Spectrometry Preparation Checklist Environmental conditions Electrical requirements Space requirements Exhaust ventilation Coolant requirements Argon

More information

Avio 500 ICP-OES. ICP-Optical Emission Spectroscopy PREPARING YOUR LAB. Preparation Checklist. Suitable Working Area

Avio 500 ICP-OES. ICP-Optical Emission Spectroscopy PREPARING YOUR LAB. Preparation Checklist. Suitable Working Area PREPARING YOUR LAB Avio 500 ICP-OES ICP-Optical Emission Spectroscopy Preparation Checklist Suitable Working Area Exhaust Vent Vent Positions Handling of Gas Cylinders and Other Suggested Safety Practices

More information

Trifecta High-Pressure Systems

Trifecta High-Pressure Systems Trifecta High-Pressure Systems CONSULTING SYSTEM DESIGN INSTALLATION COMMISSIONING TRAINING Trifecta Product Catalog www.chartindustries.com TABLE OF CONTENTS About Chart Inc. 3 Trifecta Applications &

More information

Pneumatic high-pressure controller Model CPC7000

Pneumatic high-pressure controller Model CPC7000 Calibration technology Pneumatic high-pressure controller Model CPC7000 WIKA data sheet CT 27.63 Applications Healthcare and avionics industry Industry (laboratory, workshop and production) Transmitter

More information

Columbus Instruments

Columbus Instruments 0215-003M Portable O 2 /CO 2 /CH 4 Meter User s Manual Columbus Instruments 950 NORTH HAGUE AVENUE TEL:(614) 276-0861 COLUMBUS, OHIO 43204, USA FAX:(614) 276-0529 1 www.colinst.com TOLL FREE 1-800-669-5011

More information

Ascend. User Manual. Innovation with Integrity. Version NMR

Ascend. User Manual. Innovation with Integrity. Version NMR 400 54 Ascend User Manual Version 04 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted,

More information

Laboratory Hardware. Custom Gas Chromatography Solutions WASSON - ECE INSTRUMENTATION. Engineered Solutions, Guaranteed Results.

Laboratory Hardware. Custom Gas Chromatography Solutions WASSON - ECE INSTRUMENTATION. Engineered Solutions, Guaranteed Results. Laboratory Hardware Custom Gas Chromatography Solutions Engineered Solutions, Guaranteed Results. WASSON - ECE INSTRUMENTATION Laboratory Hardware Wasson-ECE Instrumentation offers hardware-only solutions

More information

Aquavar SOLO 2 Frequently Asked Questions

Aquavar SOLO 2 Frequently Asked Questions Aquavar SOLO 2 Frequently Asked Questions How do I size the Aquavar SOLO 2 for the appropriate pump/motor combination? Can I use a 208 Volt motor? Can I run the Aquavar SOLO 2 up to 80HZ? What are the

More information

Trifecta Systems. Cryogenic Equipment for High Performance Gas Supply. Trifecta Product Catalog

Trifecta Systems. Cryogenic Equipment for High Performance Gas Supply. Trifecta Product Catalog Trifecta Systems Cryogenic Equipment for High Performance Gas Supply C O N S U LT I N G S Y S T E M D E S I G N I N S TA L L AT I O N C O M M I S S I O N I N G T R A I N I N G Trifecta Product Catalog

More information

TECHNICAL INFORMATION

TECHNICAL INFORMATION TECHNICAL INFORMATION Installation, Operation, and Maintenance Balston Model 75-77 Nitrogen Generator Figure 1-75-77 Overall Dimensions These instructions must be thoroughly read and understood before

More information

Specifications for the CMI 2409 Magnetocardiograph

Specifications for the CMI 2409 Magnetocardiograph Specifications for the CMI 2409 Magnetocardiograph Revision date April 14, 2006 1 518-381-1000 (tel) The CMI-2409 system consists of a holder (A), a patient bed (B) and a workstation (not shown in the

More information

DPC-30 DPC-100. Reference Manual

DPC-30 DPC-100. Reference Manual DPC-30 DPC-100 Reference Manual 1. Introduction 1.1 Description The Martel DPC Digital Pneumatic Calibrator improves upon traditional dial gauge pneumatic calibrators. The Martel DPC improves accuracy,

More information

Gas density monitor With integrated transmitter Model GDM-100-TI

Gas density monitor With integrated transmitter Model GDM-100-TI SF 6 gas solutions Gas density monitor With integrated transmitter Model GDM-100-TI grid Products WIKA data sheet SP 60.05 for further approvals see page 5 Applications Gas density monitoring of closed

More information

icon i150 / i350 Installation / Operation Manual

icon i150 / i350 Installation / Operation Manual i150 Concentrator i350 Concentrator icon i150 / i350 Installation / Operation Manual www.iconcentrator.com What You Will Need to Install Your icon In order to install your icon you will have to consider

More information

T EK-COR 1100A Coriolis Mass Flowmeter

T EK-COR 1100A Coriolis Mass Flowmeter T EK-COR 1100A Coriolis Mass Flowmeter Instruction Manual Document Number: IM-1100A NOTICE Read this manual before working with the product. For personal and system safety, and for optimum product performance,

More information

Technical Information

Technical Information Technical Information Installation, Operation, Installation, Operation and Maintenance and Maintenance Manual Manual Balston Model 75700-K728 Nitrogen Generator Figure 1-75700-K728 Overall Dimensions These

More information

Requirements For The Construction Of The LCLS Magnetic Measurements Laboratory

Requirements For The Construction Of The LCLS Magnetic Measurements Laboratory LCLS-TN-04-1 Requirements For The Construction Of The LCLS Magnetic Measurements Laboratory Zachary Wolf, Robert Ruland SLAC February 9, 2004 Abstract A magnetic measurements laboratory will be built at

More information

www.ompressedairsystems.com ultra-high purity nitrogen generators nitrogen purity: 95% to 99.999% www.ompressedairsystems.com ultra-high purity nitrogen generators nitrogen purity: 95% to 99.999% Leading

More information

Variable Temperature Storage Dewar Mount Inserts

Variable Temperature Storage Dewar Mount Inserts Variable Temperature Storage Dewar Mount Inserts All inserts are available for either Liquid Helium or Liquid Nitrogen Dewars! DStat - External cryostat with insert leg DStatMag - Super Conducting Magnet

More information

OPERATION MANUAL NTF-60 Plus

OPERATION MANUAL NTF-60 Plus OPERATION MANUAL NTF-60 Plus Nitrogen Tire Filling Valve Stem Caps (Qty=200) Order P/N 436075 RTI Technologies, Inc 10 Innovation Drive York, PA 17402 800-468-2321 www.rtitech.com 035-81264-00 (Rev A)

More information

Information Sheet. About this information sheet. Floor and wall loadings. Attachment of process module to floor. PlasmaPro Estrelas100

Information Sheet. About this information sheet. Floor and wall loadings. Attachment of process module to floor. PlasmaPro Estrelas100 Information Sheet PlasmaPro Estrelas100 About this information sheet This data sheet provides basic information about the installation of a PlasmaPro Estrelas100 tool. Some of the information in this sheet

More information

INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES

INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES Page 1 of 15 INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES Page 2 of 15 1. PURPOSE 2. SCOPE 3. REFERENCES 4. GENERAL INDEX 5. PROCEDURES 5.1 Line survey 5.2 Transport, loading, unloading and storage

More information

Fourier Systems. General Safety Considerations User Manual. Innovation with Integrity NMR

Fourier Systems. General Safety Considerations User Manual. Innovation with Integrity NMR Fourier Systems General Safety Considerations User Manual Version 001 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored

More information

ARCHITECT GUIDELINES 1000 T

ARCHITECT GUIDELINES 1000 T ARCHITECT GUIDELINES 1000 T Architect Guidelines for SwimEx Installation Model 1000T General Layout Call SwimEx at 800-877-7946 to receive AutoCad Drawings of the SwimEx Model that you will be installing.

More information

Multiple Pressure Booster Systems With Variable Speed Controller Type BL

Multiple Pressure Booster Systems With Variable Speed Controller Type BL Multiple Pressure Booster Systems With Variable Speed Controller Type BL General Characteristics - Single or multistage pumps - Horizontal or vertical mounting - Total head 30m ~ 250m - Material construction:

More information

Evaporator (DX) Freon Applications 1 12 Tons MHF

Evaporator (DX) Freon Applications 1 12 Tons MHF Evaporator (DX) Freon Applications 1 12 Tons > > Used For small to medium freon applications The Global Leader In Heat Exchange Technology With seven decades of experience and commitment to total client

More information

Operation manual Level sensor DC-LS-50 Operation Manual Level Sensor DC-LS-50

Operation manual Level sensor DC-LS-50 Operation Manual Level Sensor DC-LS-50 Operation Manual Level Sensor DC-LS-50 Rev.02 (2014.06) OL Page 1 of 8 Table of contents I. STRUCTURE OF THE MANUAL / CLARIFICATION... 3 II. SAFETY AND HEALTH CONCERNS... 4 1 INTRODUCTION... 5 1.1 Use

More information

Ascend Aeon. User Manual. Innovation with Integrity. Version NMR

Ascend Aeon. User Manual. Innovation with Integrity. Version NMR 500 89 Ascend Aeon User Manual Version 00 Innovation with Integrity NMR Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,

More information

ARCHITECTURAL GUIDELINES ONE-PIECE COMMERCIAL

ARCHITECTURAL GUIDELINES ONE-PIECE COMMERCIAL ARCHITECTURAL GUIDELINES ONE-PIECE COMMERCIAL Architect Guidelines for SwimEx Installation of 500OT DW, 500OT, and 400OT General Layout Call SwimEx at 800-877-7946 to receive AutoCad Drawings of the SwimEx

More information

PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT. The present tender is only an unofficial translation provided as a courtesy.

PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT. The present tender is only an unofficial translation provided as a courtesy. ICMCB - CNRS 87 avenue du Docteur Albert Schweitzer 33608 Pessac Cedex France PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT Contenu 1. General context... 1 1.1. Project presentation...

More information

better measurement Simply a question of SCHMIDT Flow Sensor SS The cost-effective alternative in pressurised systems up to 10 bars.

better measurement Simply a question of SCHMIDT Flow Sensor SS The cost-effective alternative in pressurised systems up to 10 bars. Simply a question of better measurement SCHMIDT Flow Sensor SS 20.261 The cost-effective alternative in pressurised systems up to 10 bars. Compressed air technology Industrial processes A cost analysis

More information

BNL. User Manual. Innovation with Integrity. Version. Accessories

BNL. User Manual. Innovation with Integrity. Version. Accessories BNL User Manual Version 04 Innovation with Integrity Accessories Copyright by Bruker Corporation All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted,

More information

Preparing Your Laboratory for the Optima 7300 V and 8300 ICP-OES Spectrometers

Preparing Your Laboratory for the Optima 7300 V and 8300 ICP-OES Spectrometers LABORATORY PREPARATION Preparing Your Laboratory for the Optima 7300 V and 8300 ICP-OES Spectrometers TABLE OF CONTENTS Section Subject 1 Suitable Working Area 2 Exhaust Vent 3 Vent Positions 4 Handling

More information

Spirax Compact FREME Flash Recovery Energy Management Equipment

Spirax Compact FREME Flash Recovery Energy Management Equipment IM-UK-cFREME UK Issue 1 Spirax Compact FREME Flash Recovery Energy Management Equipment Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information

GRUNDFOS DATA BOOKLET. Hydro Solo-E. Complete pressure boosting systems 50/60 Hz

GRUNDFOS DATA BOOKLET. Hydro Solo-E. Complete pressure boosting systems 50/60 Hz GRUNDFOS DATA BOOKLET Complete pressure boosting systems 5/6 z Contents Product data Performance range 3 Operating conditions Inlet pressure Type key Product range 5 Construction 5 Installation 5 Mechanical

More information

Safety instructions and operating manual

Safety instructions and operating manual 5-Master Safety instructions and operating manual TBF-PyroTec GmbH Lichterfelder Str. 5 A 21502 Geesthacht Tel.: + 49 (0)4152 157 9950 Fax: + 49 (0)4152 157 9951 Flame projector 5-Master Safety instructions

More information

Your local gas generation partner. Precision series Modular gas generation solution for GC.

Your local gas generation partner. Precision series Modular gas generation solution for GC. Your local gas generation partner Precision series Modular gas generation solution for GC www.peakscientific.com Perform with Precision Specifically designed and engineered for GC laboratory applications,

More information

ARCHITECTURAL GUIDELINES FOUR-PIECE COMMERCIAL

ARCHITECTURAL GUIDELINES FOUR-PIECE COMMERCIAL ARCHITECTURAL GUIDELINES FOUR-PIECE COMMERCIAL ARCHITECT GUIDELINES FOR SWIMEX FOUR-PIECE COMMERCIAL INSTALLATION GENERAL LAYOUT Call SwimEx at 800-877-7946 to receive AutoCad Drawings of the SwimEx Model

More information

Discovery HP-TGA 75/750. Site Preparation Guide

Discovery HP-TGA 75/750. Site Preparation Guide Discovery HP-TGA 75/750 Site Preparation Guide Revision A Issued August 2018 Table of Contents Table of Contents... 2 Ideal Setup... 3 System Components... 4 Instrument Measurements... 5 Utility Requirements...

More information

Variable Temperature Operation

Variable Temperature Operation Variable Temperature Operation AVIII 400 MHz Spectrometer November 11, 2012 The CBC NMR Laboratory University of Delaware AVIII 400 User Guide: Variable Temperature Operation 1 INTRODUCTION... 5 1.1 SAFETY...

More information

Inert Air (N2) Systems Manual

Inert Air (N2) Systems Manual INSTRUCTION MANUAL Inert Air (N2) Systems Manual N2-MANUAL 2.10 READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT. GENERAL INFORMATION Positive pressure nitrogen gas pressurizing

More information

Optimizing Gas Supply for Industrial Lasers

Optimizing Gas Supply for Industrial Lasers Optimizing Gas Supply for Industrial Lasers Laser cutting of metals and other materials has grown rapidly due to developments in laser power, advancements in CNC automation, and decreasing costs. The industrial

More information

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6 NEUTRAL GROUNDING RESISTORS INSTALLATION, OPERATION & MAINTENANCE MANUAL Contents 1- SAFETY INSTRUCTIONS... 3 1-1- Compliance with Instructions in this Manual. 3 1-2- Guidance Notes Installation.... 3

More information